Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15)
|
|
- Hope Gibbs
- 6 years ago
- Views:
Transcription
1 Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) School/Department FY 16 FY 17 FY18 FY19 FY20 Chariho Regional High School FY 16 FY 17 FY18 FY19 FY20 *Repair Bleachers (inside) 4,000 *Replace Football Bleachers (outside) 32,500 *Modify Existing Classroom Courtyard Doors 50,000 **Replace Furniture/Cafeteria Tables 4,000 4,000 4,000 4,000 4,000 **Maintenance of Track (MS/HS Split) 27,500 **Maintenance of Tennis Court (MS/HS Split) 2,000 2,000 2,000 2,000 2,000 ****Replace AC Rooftop Unit and extend to teacher's room 10,000 ****Install two fixed roof ladders & install roof access to water tank room 3,500 *****Install Swipe Key System 15,000 ******Install Door in HS Trainer's Room 7,000 ******Install HS Door Handles 4,500 4,500 4,500 4,500 4,500 TOTAL 46,500 38,000 14,000 43,000 60,500 Chariho Regional Middle School FY 16 FY 17 FY18 FY19 FY20 *Upgrade Dishwasher Exhaust 25,000 *Upgrade Kitchen Exhaust 40,000 *Resurface Boy's Locker Room Floor 8,000. **Replace Office Carpet 18,000 **Replace Furniture/Cafeteria Tables 4,000 4,000 4,000 4,000 4,000 **Refinish Gymnasium Floor 5,000 5,000 5,000 **Replace Lockers 50,000 50,000 **Remediate Oil Spill 17,000 10,000 10,000 **Replace Classroom Doors 8,000 8,000 **Maintenance of Tennis Court (MS/HS Split) 2,000 2,000 2,000 2,000 2,000 **Maintenance of Track (MS/HS Split) 27,500 ****Replace Lower Bowl Auditorium Seating 50,000 *****Replace Bathroom Petitions 20,000 ******Install AC rooftop unit for Self- Contained Classrooms 20,000 ******Resurface Girls' Locker Room Floor and Replace Lockers 15,000 ******Replace 4 Exterior Solid Steel Doors in Gym Hallway/Boys' Locker Room 8,000 ******Replace Double Wooden Doors from Hallway to Stage 2,000 ******Install New Security Cameras 4,525 TOTAL 135,525 63,500 97,000 56,000 84,000 2/11/2015 1
2 Chariho Career and Technical Center FY 16 FY 17 FY18 FY19 FY20 **Replace Septic System 60,000 60,000 ******Upgrade Culinary Kitchen 195,000 TOTAL 195,000 60,000 60, Hope Valley Elementary School FY 16 FY 17 FY18 FY19 FY20 *Provide Accessible Path to Courts and Fields 10,000 *Replace Wood Fiber Tile Ceilings 15,000 *Provide Elevator in 1935 Building 175, ,000 *Repair 1955 Building Exterior Masonry 10,000 *Replace VAT and Carpet 50,000 *Replace Window Treatments 16,000 *Replace Roof on 1955 Addition 135, ,250 *Upgrade Master Clock 16,000 *Upgrade Intercom 90,000 *Upgrade Fire Alarm System 34,000 *Add Grease Interceptor for Pot Sink 5,000 *Replace Galvanized Water Pipe 12,000 *Upgrade Corridor Ventilation 35,000 *Upgrade Kitchen Exhaust Fan 6,500 *Replace Display Cases 4,500 **Replace Furniture 2,000 2,000 2,000 2,000 *****Install Auto Door Closures 7,200 ******Refinish HV Gym Floor 15,000 ******Playground Fence 3,336 ******Interior Doors of the Old Section 30,000 TOTAL 73, , , , ,000 Richmond Elementary School FY 16 FY 17 FY18 FY19 FY20 Replace Remaining Concrete Curb 18,000 *Create, Sign and Stripe Passenger Drop-Off Area 5,000 *Correct Approaches to Accessible Entrances 9,000 *Provide Curb Cut and Accessiblility to Flag 1,000 *Redesign Traffic Areas 25,000 75,000 *Upgrade Intercom, ****Including Cafeteria 40,000 *Provide New or Repaired Chain Link Fence 3,000 *Repave Play Area Behind School 30,000 *Provide Accessible Paths to Play Structures 3,000 2/11/2015 2
3 Richmond Elementary School FY 16 FY 17 FY18 FY19 FY20 *Replace Weather Stripping at Windows; Replace Screens 6,000 *Replace Window Treatments 20,000 *Replace Asphalt Shingle Roof 182, ,500 *Repair Exterior East Foundation 18,000 *Repair Damaged Masonry 10,000 *Replace Plumbing Fixtures in Newer Portions of Building 50,000 *Kitchen Hood Suppression System 7,500 *Upgrade Toilet Exhaust System 60,000 *Upgrade Kitchen/Café Exhaust System 77,000 ** Upgrade Alarm System 10,000 **Remove Asbestos Floor Tiles 30,000 30,000 **Sheetrock Ceilings 10,000 **Replace Furniture 2,000 2,000 2,000 2,000 **Replace Gutters 20,000 **Replace Kitchen Landing 10,000 **Install AC in Library 8,000 **Waterline Payments 32,500 32,500 32,500 32,500 32,500 **Replace Septic System 100,000 ****Install Kindergarten Playground Fence 5,000 ******Repair Sheds 7,500 ******Replace Interior Doors 51,000 TOTAL 202, , , , ,000 Charlestown Elementary School FY 16 FY 17 FY18 FY19 FY20 *Construct Islands to Define Parking/Entrance 70,000 *Provide Accessibility to Entrances 7,500 *Clean and Re-Set Catch Basins; Replace Pipes 80,000 *Correct Accessibility to Fields and Playgrounds 14,000 *Provide Signage and Islands to Segregate Buses from Parking 5,000 *Pulverize and Re-Pave Parking Lot and Drive; Provide Curbing 25,000 55,000 *Replace Concrete Walks and Curbs 56,000 *Replace Damaged Interior Doors 20,000 *Replace Corridor Ceiling Tiles/Grid 16,500 *Upgrade Dishwasher Exhaust System 25,000 *Upgrade Gymnasium Return Register 5,000 *Upgrade Gymnasium Storage/Office HVAC 25,000 **Remove Asbestos Floor Tiles 30,000 **Replace Furniture/Cafeteria Tables 2,000 2,000 2,000 2,000 ****Install Shades re: SmartBoards 2,000 2/11/2015 3
4 Charlestown Elementary School FY 16 FY 17 FY18 FY19 FY20 ******Install Security Cameras 5,600 ******Ceiling Fan Replacements in Cafeteria 3,000 ******Hot Water Line Replacement 10,000 TOTAL 42,700 27, ,500 32,000 75,000 Ashaway Elementary School FY 16 FY 17 FY18 FY19 FY20 *Provide/Repair Chain Link Fence 3,000 *Clean Catch Basins and Drainage Manholes 5,000 *Repair Rear Stairs 20,000 *Make Nature Trail ADA Compliant 3,000 *Pulverize and Repave Parking Lot and Drive 25,000 45,000 *Provide Accessible Pathways to Play Structures 3,000 *Create Separation from Parent Drop-Off Loop and Play Areas with Curbs/Planters 20,000 *Add Concrete Pad for Dumpster and Screen 10,000 *Provide Dedicated Bus Drop-Off Area 25,000 *Replace Interior Doors 50,000 *Provide Smoke Vents for Stage 15,000 *Replace Windows 175, ,000 *Upgrade Electrical Service 81,000 *Upgrade Intercom 50,000 50,000 *Replace Plumbing Fixtures 65,000 65,000. *Upgrade Make-up Air for Generator 10,000 *Upgrade Corridor Ventilation 35,000 *Upgrade Gymnasium Distribution System 77,000 **Install Elevator 300,000 **Replace Furniture/Cafeteria Tables 3,500 2,000 2,000 2,000 2,000 **Replace Gymnasium Floor 55,000 **Refinish Stage 5,000 **Replace Underground Septic Piping 75,000 **Upgrade Gymnasium/Restroom Ventilation 9,500 ****** Install 4 Security Cameras 3,676 ******Install New Floor for Portable Building 5,534 TOTAL 96, , , , ,000 The RYSE School FY 16 FY 17 FY18 FY19 FY20 TOTAL /11/2015 4
5 Administration Building FY 16 FY 17 FY18 FY19 FY20 ******Install new Buzzer System 3,000 TOTAL 3, Maintenance and Technology Building FY 16 FY 17 FY18 FY19 FY20 TOTAL District FY 16 FY 17 FY18 FY19 FY20 **Replace Maintenance Vehicles 25,000 25,000 ******Facility Study Update 25,000 TOTAL 50,000-25, GRAND TOTALS 844, ,750 1,341, ,000 1,191,500 Housing Aid (386,336) CTC Categorical Aid (195,000) Out-of-Scope Wiring Reimbursement (42,000) 221,235 *Existing Facilities Evaluation, Kaestle Boos Associates, Inc., February 16, 2011 **FY12-FY16 Capital Plan (Duplicate Entries Have Been Eliminated) *** Added ****Added *****Added ******Added /11/2015 5
Briar Crest Elementary
Promises Kept This document includes partial lists of major projects completed at Pattonville Schools since 1986 as part of past bond issues approved by the Pattonville community. Briar Crest Elementary
More informationCAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14
2014-2015 CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 School Item Amount a. Classroom A/R (Increase CR capacity to 804, add l Resource and tutoring spaces needed. Teacher
More informationVOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED
Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological
More information2014 Bond Project Guide
2014 Bond Project Guide Bush Elementary School Page 1 Instructional Technology Computers, Projectors, Mobile Carts, Document Cameras and Printers Wireless Connectivity New Construction New Tech Center
More informationSchool District of Milton 5- Year Capital Maintenance and Improvement Plan
Updated - 02/21/17 School District of Milton 5- Year Capital Maintenance and Improvement Plan 101 East Elementary 1 Parking Lot/Traffic Flow Project 615,175 Includes Construction and Engineering 2 Bathroom
More informationNYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS
NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS DECEMBER 3, 2013 KEY QUESTIONS 1. What is the time sequence for available funding? (In what years will the funding be available?) 2. What is the
More informationMaster Facility Planning Update School Board Meeting May 26, 2016
Master Facility Planning Update School Board Meeting May 26, 2016 Master Facilities Committee Overview Reflection of Committee Work Review of District Wide Facility Issues Identified District Wide Facility
More informationTillamook High School Bond Projects
Tillamook High School Bond Projects School Project Description All Buildings Upgrade fire alarm H&S All Buildings Add door lock capability from inside rooms Security All Buildings Install card lock entry
More information3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000
1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades Allowance $300,000 C. Tilden Entrance Upgrades D. Door and Glass Improvements Allowance $500,000 E. Alert
More informationTIFT COUNTY SCHOOLS E-SPLOST HISTORY
TIFT COUNTY SCHOOLS E-SPLOST HISTORY July 1, 1997 June 30, 2002 $28,766,187.16 collected July 1, 2002 June 30, 2007 $39,025,830.10 collected July 1, 2007 June 30, 2012 $41,886,155.46 collected July 1,
More informationREPORT CARD TO THE COMMUNITY MAY 15, 2018
REPORT CARD TO THE COMMUNITY MAY 15, 2018 O On May 10, 2014 voters in Greenville ISD approved a $72,275,000 bond election. BOND PROPOSAL PROJECT BOND AMOUNT CONSTRUCT A NEW BOWIE ELEMENTARY SCHOOL $17,600,000
More informationOxford Hills School District Capital Renewal Plan Updated March 2017
Color Coding Guide Recently Completed In Progress FY 2017 Budget in FY 2018 Future Budgets/Projects 3/20/17 Capital Renewal Plan Updated March 2017 Capital Renewal Plan - Harrison Elementary Harrison add
More informationForest Hills Facilities Plan
Forest Hills Facilities Plan Extensive updates to 8 of our 9 schools Replace Wilson Elementary Enhance learning environments across the district Build additional classrooms to accommodate gradual implementation
More informationFORT ERIE SECONDARY SCHOOL FACILITY INFORMATION. Lake Erie Corridor Secondary Schools Accommodation Review
FORT ERIE SECONDARY SCHOOL FACILITY INFORMATION Lake Erie Corridor Secondary Schools Accommodation Review November 2012 LAKE ERIE CORRIDOR SECONDARY SCHOOLS ACCOMMODATION REVIEW Fort Erie Secondary School
More informationAllisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767
Allisonville Elementary School Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 ADA improvements are Fire alarms need to be updated Playground equipment needs to be
More informationSITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL)
SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL) Basketball Courts 15 25 Built Improvements Playgrounds, Site Furniture, etc. 20 20 Catch Basin 40 40 Cold Water Lines 40 40 Compactors DHW Supply
More informationNew High School Concept
Approved Bond Projects for Alamance-Burlington Schools In November 2018, Alamance County citizens approved a $150 million bond project proposal. Bond funds will pay to construct a new high school and provide
More informationDEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students
DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students FACILITY NEEDS THE CHALLENGE Deerfield Middle School/High School building has served the community for
More informationCampus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111
Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111 Year Opened 1971 Current Square Footage 175,743 Site Acreage (included in CCHS) 87.22 campus.cherrycreekschools.org $2,441,170
More informationHVAC / Boilers / Hot Water. Expected Life Span. very rough estimates Condition/Issue Age. Athletics / Gyms
$4,013,500.00 $4,013,500.00 $ 1,155,000.00 $ 1,000,000.00 $ 205,000.00 $ 275,000.00 $ 300,000.00 $ 360,000.00 $ 438,500.00 $ 280,000.00 School Status Item HS Boilers boiler controls replaced 2017 2002
More informationMUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY
MUKWONAGO SCHOOL DISTRICT ARCHITECTURE PARK VIEW MIDDLE SCHOOL The original school building was dedicated in 1954 as the High School, with an addition in 1959, a library addition in 1970, and an addition/renovation
More information2014 Bond District-wide Facility Repairs
Elementary Schools Aloha-Huber Park Fire Detector upgrade Replace electric backboard winches in gym Heating/cooling system controls upgrade Barnes Replace exterior windows Heating/cooling system and controls
More informationMUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY
ARCHITECTURE ROLLING HILLS ELEMENTARY SCHOOL Rolling Hills Elementary was built in 1999 and is the newest addition to the Mukwonago Area School District. The building contains approximately 64,900 gross
More informationFlorence High School / Middle School Page 1 of 3 Florence, WI
Florence High School / Middle School Page 1 of 3 Florence, WI Plumbing Systems Review: The following report is the result of a site visit by Tim Kehoe of Muermann Engineering, LLC that occurred on October
More information2014 Bond District-wide Facility Repairs
Elementary Schools Aloha-Huber Park Fire Detector upgrade Replace electric backboard winches in gym Heating/cooling system controls upgrade Barnes Replace exterior windows Heating/cooling system and controls
More informationJosefa Ortiz De Dominguez Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationEdward Jenner Elementary Academy of the Arts
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationGreenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111
Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Year Opened 1958 Current Square Footage 50,504 Site Acreage 8.53 greenwood.cherrycreekschools.org $220,720 Electrical
More informationGenevieve Melody Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationALLISON ELEMENTARY SCHOOL 4315 Don Julio Blvd., North Highlands, CA 95660
ALLISON ELEMENTARY SCHOOL 4315 Don Julio Blvd., North Highlands, CA 95660 Year Built 1960 // Age 58 years Building Area 31,688 Square Feet Student Capacity 389 Current Enrollment (2017-2018) 466 Priority
More informationIchabod Crane Central School District 2018 Capital Project Preliminary Estimate
Health & Safety 1,399,000 Academics & Program 17,140,800 Physical Education & Athletics 5,922,000 Building Infrastructure 3,103,800 Site Infrastructure 1,049,600 TOTAL SCOPE OF WORK 28,615,200 PROPOSED
More informationJoseph Brennemann Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationMOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School
MOUNT PLEASANT MIDDLE SCHOOL HVAC M-01 Heating Plant: The existing boilers have recently been upgraded. (3) steam boilers (8660 mbh each) manufactured by Weil- McLain have been installed. Newer hot water
More informationSagebrush Elementary School East Temple Place Aurora, Colorado 80015
Sagebrush Elementary School 14700 East Temple Place Aurora, Colorado 80015 Year Opened 1977 Current Square Footage 57,100 Site Acreage 7.66 sagebrush.cherrycreekschools.org Asphalt and concrete work; electrical
More information5 Year Capital Improvement Plan Update
5 Year Capital Improvement Plan Update Board Approved May 10, 2016 Collierville Schools Board of Education Wanda Chism Wright Cox Mark Hansen, Chairman Cathy Messerly Kevin Vaughan Superintendent John
More informationDesign Presentation. Chief Operations Officer Willie Burroughs
Design Presentation Chief Operations Officer Willie Burroughs Agenda Introduction Community Feedback Project updates 2 Feedback Citizens Advisory Committee meetings Growth and Development meetings Community
More informationRichard Henry Lee Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationCustodial Guide
Custodial Guide 2018-2019 Table of Contents Page Number 1 General Items to Note 2-3 Maintenance for Office Areas 4-5 Maintenance for Classrooms and Hallways 6 Maintenance for Lounge Areas 7 Maintenance
More informationHOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District
HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the
More informationFacilities Management Services
Facilities Management Services Operating Budget Facilities Management (FM) receives an Operating Budget each year predicated on funding the routine, predictable costs of cleaning, maintaining,, and repairing,
More informationJanuary 11, New benches installed. Paving of parking lot adjacent to piers and the canoe put-in. Near complete with clean up remaining.
Project Updates January 11, 2018 CENTERVILLE CHESAPEAKE ARBORETUM BELLS MILL CITY CREEKWOOD SOUTH DEEP CREEK LOCK WORK TO BE PERFORMED/UPDATES Improvements to the parking lot include installation of a
More informationPLATTEVILLE MIDDLE SCHOOL
Architectural The building has aluminum clad wood awning windows in combination with aluminum fixed glass units. They appear to be exterior glazed with insulated glazing. See photo 2. Platteville Middle
More informationSPLOST I, II, III,IV
ACWORTH ES (OLD) ACWORTH INTERMEDIATE Construction projects not done due to school replacement Land Acquisition, 61 IU Replacement Elementary School Access Controls, Temperature monitors for walk in coolers
More informationWashington Irving Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationState College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT
State College Area School District High School South Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the
More informationKenmore Town of Tonawanda Union Free School District : Capital Improvement Project Phase 2
Kenmore Town of Tonawanda Union Free School District : Capital Improvement Project Phase 2 Adams Field Kenmore East High School Kenmore West High School Crosby Field Charles Lindbergh Elementary Thomas
More informationMeadow Point Elementary School East Grand Avenue Aurora, Colorado 80015
Meadow Point Elementary School 17901 East Grand Avenue Aurora, Colorado 80015 Year Opened 1982 Current Square Footage 53,100 Site Acreage 7.48 meadowpoint.cherrycreekschools.org $2,081,600 Electrical system,
More informationNYC Department of Education
Asset: COLUMBUS AF - BRONX, 925 ASTOR AVENUE, New York, 10469 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2017-10-31 9:21 AM 2017-11-29 8:45 AM AA : Architectural - Associate
More informationCharles W Earle Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationAgustin Lara Elementary Academy
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationFrancis M McKay Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationVISION PLAN PRESENTATION - SEPTEMBER 28, 2013
AREAS OF IMPROVEMENT E A POOL HOUSE POOL DECK B B MAIN BUILDING UPPER PLAZAS A D F G C MAJOR BLEACHERS DUGOUTS FIELD MAIN COURTYARD D REGGIE PARK C E SPORT COURT ADA RAMP H F G H TENNIS COURTS KITCHENETTE
More informationCalmeca Academy of Fine Arts and Dual Language
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationOscar DePriest Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More information2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16
1. General: This summary is offered as a supplement to the 2015 Building Condition Survey being filed with SED on behalf of the District. All cost estimates are preliminary, and should be re-evaluated
More informationAshland School District Facility & Capacity Assessment Report 2005
Ashland School District Facility & Capacity Assessment Report 2005 Briscoe Elementary School (Closed Facility) Address: 265 N Main Street Area: 33,980 square feet Buildings: Original Building 1948 Music
More informationGreater Albany Public Schools May 2017 Ballot Measure for School Repairs, Crowding and Job Training
PUBLIC SCHOOLS Greater Albany Public s for Repairs, Crowding and Job Training CRITICAL FACILITY UPGRADES ADA Improvements: Architectural Improvements: Envelope Improvements Including Roofs: Exterior Improvements:
More informationMARY CRAPO CENTER Miller Road, Swartz Creek, Michigan
MARY CRAPO CENTER 8197 Miller Road, Swartz Creek, Michigan MARY CRAPO CENTER 8197 Miller Road, Swartz Creek General Information: - Instructional, Child Care Development Center (West Wing) o (2) Infant/Toddler
More informationJohn Palmer Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationColumns REF, RESPONSIBLE and COMPL TD are provided for your numbering, assignments and control. REF ISSUE RESPONSIBLE COMPL TD
PREPARING FOR THE DESIGN OF YOUR SCHOOL CAPITAL PROJECT A Checklist of Issues March 2014, v.1 This document can be used in preparing the stakeholder team for decision-making and for documenting the input
More informationCherry Hill Public Schools BUILDING A SOLID FUTURE
Cherry Hill Public Schools BUILDING A SOLID FUTURE Who We Are The Cherry Hill School District is the 12 th largest in the state, serving 11,500 students 19 Locations 2 High Schools, 3 Middle Schools, 12
More informationWarren County Schools Plant and Operations
Warren County Schools Plant and Operations Buildings/Facilities/Energy Strategic Plan September 28, 2017 (Updated January 18, 2018) Donnie Caldwell; Facilities Director One Team, One Goal, High Levels
More informationNYC Department of Education
Asset: NEW UTRECHT AF - BROOKLYN, 1601 80 STREET, New York, 11214 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2017-10-31 4:06 PM 2018-06-13 10:51 AM AA : Architectural
More informationMaster Project List Report
Blue Hills Elementary School 01-8215 Site Utilities Replacement $52,835 01-8502 Modernization $3,135,933 01-8525 Exterior Painting $181,478 01-8552 Kindergarden Fencing $13,180 Install new backflow preventer.
More informationMajor Public Facilities. Section 4
Major Public Facilities Section 4 Significant Public Facilities Section Index Facility Page Alphabetical by Title (sort) Broadmeadow Elementary School 419 Center at the Heights (Senior Center) 447 Chestnut
More informationKerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018
Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018 WHAT IS A BOND ELECTION? Provide communities an opportunity to vote to give the Board of Trustees authority
More informationSCHOOLS + COMMUNITY rehabs, renovations, new construction
OCV HAS A WEALTH OF EXPERIENCE HELPING S AND COMMU- NITY CENTERS BUILD, MODERNIZE + EXPAND THEIR FACILITIES, PROVIDING THE RIGHT ENVIRONMENT FOR GROWTH 2015 SMILOW CLUBHOUSE, MADISON SQUARE BOYS & GIRLS
More informationPh: (907) Quality Homes
Standard Specifications BUILDING your dream home www.destinyhomesak.com Ph: (907) 232-9751 Email: destiny4paul@aol.com Quality Homes 2016 1 HOME PRICE Prices of the homes are based on the $40,000 lot allowance.
More informationWest Hartford Public School District
West Hartford Public School District Agenda Item: Adoption of Capital Improvement Plan for 2018-19 Meeting Date: February 6, 2018 From: Through: Andy Morrow, Assistant Superintendent for Administration
More informationSidney Sawyer Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationEmergency Management Resource Guide. Appendix A: Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky Public Schools
Appendix A: Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky Public Schools 143 Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky
More informationIf there are emergency situations they should be reported to Maintenance Department immediately.
To: From: Re: Mercer County Schools Principals Mercer County Schools Safety Committee Required Safety Reports Date: October 30, 2010 In order to work toward safer schools, two reports are required to be
More informationDeWitt Clinton Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationUpdated: 8/16/ Facilities Profile
Updated: 8/16/17 2017-2018 Facilities Profile Purpose This package is put together to provide general information to District Administration, the School board and the public. The information contained
More informationEXISTING CONDITIONS SUMMARY
SITE Fire alarm system does meet current requirements Accessible path of travel lacking throughout campus Announcer s booth at Football Field booth not ADA compliant Covered and non covered outdoor eating
More informationCustom Report // Priorities 1+2
Custom Report // Priorities + All costs are shown in 08 dollars. The cost of all work items after this date should be adjusted accordingly. Print Date: 4/3/08 Foothill High School DESCRIPTION Building
More informationNYC Department of Education
Architectural Inspection Building Assessment Survey 2017-2018 Asset: LEHMAN AF - BRONX, 3000 EAST TREMONT AVENUE, New York, 10461 Inspection Id Inspection Type Time In Last Edited SA : Architectural -
More informationSmith Douglas Homes Presents HAYNESCREST TOWNHOMES
The Oxford You ll be amazed to find that the Oxford, our newest townhome design, offers an unbelievable combination of comforts and amenities you re not likely to find in a townhome. An open kitchen with
More informationVendor Application Form
Vendor Application Form DIRECTIONS: Fill out this form as completely as possible. Forms that are incomplete will be discarded without notification. If you encounter an error, use the "Back" function in
More informationMajor Public Facilities. Section 7
Major Public Facilities Section 7 Significant Public Facilities Section Index Title Page Alphabetical by Title (sort) Broadmeadow Elementary School 7-14 Chestnut Street Annex 7-37 Daley Building 7-30 Department
More informationState College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT
State College Area School District High School North Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the
More informationOhlone College Measure G Project Scope Revisions
Scope Revisions Current Title Revised Title Current Scope Revised Scope 6101 Relocated Baseball Field Athletic Fields Create new sustainable baseball field with synthetic turf, bleacher seating and batting
More informationSpringpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp.
Volume 1 Bidding Requirements, Contract Forms, Conditions of the Contract, Division 1, Architectural and Site Specifications 000107 Certification Page 000110 Table of Contents DIV00 PROCUREMENT AND CONTRACTING
More informationLKA Partners. A Professional Corporation for Architecture/Planning. 430 North Tejon Street Colorado Springs, CO /
LKA Partners A Professional Corporation for Architecture/Planning 430 North Tejon Street Colorado Springs, CO 80903 719/473-8446 C O N F E R E N C E R E C O R D PROJECT: BOULDER VALLEY SCHOOL DISTRICT
More informationFOOD SERVICE May 6, 2016
FOOD SERVICE May 6, 2016 I. PROGRAM REQUIREMENTS Refer to the project-specific Schedule of Spaces for student stations, square footage, and for any requirements that may differ from the prototype requirements
More informationService Description Service Shop Customer Charge Comments. Electronic Shop. Electric Shop Yes additional circuits for equipment
Fire alarm repairs Electronic Shop Fire alarm sound level testing Electronic Shop Fire system inspections Electronic Shop Installation of additional fire detection/alarm/supression devices Electronic Shop
More informationGeorge B Swift Elementary Specialty School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationSCHEMATIC DESIGN PRESENTATION
August 5, 2014 SCHEMATIC DESIGN PRESENTATION ADDITIONS & RENOVATIONS Greenville Independent School District Acknowledgments 2 Narrative 3-6 Crockett Elementary School 7-12 L.P. Waters Early Childhood Center
More informationDOCUMENT TABLE OF CONTENTS
DOCUMENT 00003 June 16, 2005 TABLE OF CONTENTS DOCUMENT NO. INTRODUCTORY INFORMATION DOCUMENT 00003 TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS SECTION 01011 SECTION 01025 SSP21.1-1 SECTION 01026
More informationNAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX
NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA 18064 610-759-1367 FAX 610-759-7028 TO: FROM: Dr. Riker, Superintendent of Schools Board of School Directors Lewis F.
More informationEncumbered Balance (E-D) Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765, $635, $635, $130, $0.
Branham High School Budget Remaining 1 906030 Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765,473.00 $635,342.00 $635,342.00 $130,131.00 $0.00 2 970205 Branham Interim Housing - 12 Portable
More informationALLEGHANY COUNTY PUBLIC SCHOOLS Maintenance Work Request Completion Analysis
ALLEGHANY COUNTY PUBLIC SCHOOLS Maintenance Work Request Completion Analysis 204-205 YEAR-TO-DATE Custodial Supplies 88.00 9.50 $,643. $26,39.60 $27,782.7 Preventive Maintenance 67.00,74.00 $20,372.68
More informationArena Elementary School 314 Willow St. Arena, WI 53503
FACILITIES PLANNING STUDY RIVER VALLEY SCHOOL DISTRICT Arena Elementary School 314 Willow St. Arena, WI 53503 7 South Dewey Street Eau Claire, Wisconsin 54701 715.83.1605 sdsarch.com ARENA General Overview
More informationAlessandro Volta Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationOPERATING. Salaries, wages, and benefits personnel costs for repairs and maintenance functions, including living or accommodation allowances.
Page 1 of 6 Maintenance Labour Salaries, wages, and benefits personnel costs for repairs and maintenance functions, including living or accommodation allowances. Maintenance Materials & Services Building
More information1354 CHECKLIST for Project Closeout
1354 CHECKLIST for Project Closeout PROJECT NUMBER: BUILDING NUMBER: DESCRIPTION OF PROJECT: Describe description of work; i.e., New Construction, Addition, Modification, Renovation, etc DRAWING NUMBER
More informationE-SPLOST V. Facts and Information. August 2018
E-SPLOST V Facts and Information August 2018 Education Special Purpose Local Option Sales Tax What is E-SPLOST? It is a one penny sales tax that allows for shared contribution to education, including visitors
More informationExhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS
Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS DATE: July 10, 2007 TO: FROM: SUBJECT: ORIGINATOR: RESOURCE PERSON(S): BOARD OF EDUCATION Dr. Joe A. Hairston, Superintendent ABBREVIATED FACILITY STATUS REPORT
More informationLONG-TERM OPERATIONS AND MAINTENANCE PLAN
LONG-TERM OPERATIONS AND MAINTENANCE PLAN May, 2017 BOARD OF EDUCATION Cathe Russe President Jackie Lutz Vice President Sam Ach Member John Heggie Member Natalie Jachtorowycz Member John J. Murphy Member
More informationBinghamton University Construction SUMMER 2012 HIGHLIGHTS
Binghamton University Construction SUMMER 2012 HIGHLIGHTS Binghamton University Construction Summer 2012 Large and small construction projects were completed during the summer 2012 construction season.
More information