1 Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) School/Department FY 16 FY 17 FY18 FY19 FY20 Chariho Regional High School FY 16 FY 17 FY18 FY19 FY20 *Repair Bleachers (inside) 4,000 *Replace Football Bleachers (outside) 32,500 *Modify Existing Classroom Courtyard Doors 50,000 **Replace Furniture/Cafeteria Tables 4,000 4,000 4,000 4,000 4,000 **Maintenance of Track (MS/HS Split) 27,500 **Maintenance of Tennis Court (MS/HS Split) 2,000 2,000 2,000 2,000 2,000 ****Replace AC Rooftop Unit and extend to teacher's room 10,000 ****Install two fixed roof ladders & install roof access to water tank room 3,500 *****Install Swipe Key System 15,000 ******Install Door in HS Trainer's Room 7,000 ******Install HS Door Handles 4,500 4,500 4,500 4,500 4,500 TOTAL 46,500 38,000 14,000 43,000 60,500 Chariho Regional Middle School FY 16 FY 17 FY18 FY19 FY20 *Upgrade Dishwasher Exhaust 25,000 *Upgrade Kitchen Exhaust 40,000 *Resurface Boy's Locker Room Floor 8,000. **Replace Office Carpet 18,000 **Replace Furniture/Cafeteria Tables 4,000 4,000 4,000 4,000 4,000 **Refinish Gymnasium Floor 5,000 5,000 5,000 **Replace Lockers 50,000 50,000 **Remediate Oil Spill 17,000 10,000 10,000 **Replace Classroom Doors 8,000 8,000 **Maintenance of Tennis Court (MS/HS Split) 2,000 2,000 2,000 2,000 2,000 **Maintenance of Track (MS/HS Split) 27,500 ****Replace Lower Bowl Auditorium Seating 50,000 *****Replace Bathroom Petitions 20,000 ******Install AC rooftop unit for Self- Contained Classrooms 20,000 ******Resurface Girls' Locker Room Floor and Replace Lockers 15,000 ******Replace 4 Exterior Solid Steel Doors in Gym Hallway/Boys' Locker Room 8,000 ******Replace Double Wooden Doors from Hallway to Stage 2,000 ******Install New Security Cameras 4,525 TOTAL 135,525 63,500 97,000 56,000 84,000 2/11/2015 1

2 Chariho Career and Technical Center FY 16 FY 17 FY18 FY19 FY20 **Replace Septic System 60,000 60,000 ******Upgrade Culinary Kitchen 195,000 TOTAL 195,000 60,000 60, Hope Valley Elementary School FY 16 FY 17 FY18 FY19 FY20 *Provide Accessible Path to Courts and Fields 10,000 *Replace Wood Fiber Tile Ceilings 15,000 *Provide Elevator in 1935 Building 175, ,000 *Repair 1955 Building Exterior Masonry 10,000 *Replace VAT and Carpet 50,000 *Replace Window Treatments 16,000 *Replace Roof on 1955 Addition 135, ,250 *Upgrade Master Clock 16,000 *Upgrade Intercom 90,000 *Upgrade Fire Alarm System 34,000 *Add Grease Interceptor for Pot Sink 5,000 *Replace Galvanized Water Pipe 12,000 *Upgrade Corridor Ventilation 35,000 *Upgrade Kitchen Exhaust Fan 6,500 *Replace Display Cases 4,500 **Replace Furniture 2,000 2,000 2,000 2,000 *****Install Auto Door Closures 7,200 ******Refinish HV Gym Floor 15,000 ******Playground Fence 3,336 ******Interior Doors of the Old Section 30,000 TOTAL 73, , , , ,000 Richmond Elementary School FY 16 FY 17 FY18 FY19 FY20 Replace Remaining Concrete Curb 18,000 *Create, Sign and Stripe Passenger Drop-Off Area 5,000 *Correct Approaches to Accessible Entrances 9,000 *Provide Curb Cut and Accessiblility to Flag 1,000 *Redesign Traffic Areas 25,000 75,000 *Upgrade Intercom, ****Including Cafeteria 40,000 *Provide New or Repaired Chain Link Fence 3,000 *Repave Play Area Behind School 30,000 *Provide Accessible Paths to Play Structures 3,000 2/11/2015 2

3 Richmond Elementary School FY 16 FY 17 FY18 FY19 FY20 *Replace Weather Stripping at Windows; Replace Screens 6,000 *Replace Window Treatments 20,000 *Replace Asphalt Shingle Roof 182, ,500 *Repair Exterior East Foundation 18,000 *Repair Damaged Masonry 10,000 *Replace Plumbing Fixtures in Newer Portions of Building 50,000 *Kitchen Hood Suppression System 7,500 *Upgrade Toilet Exhaust System 60,000 *Upgrade Kitchen/Café Exhaust System 77,000 ** Upgrade Alarm System 10,000 **Remove Asbestos Floor Tiles 30,000 30,000 **Sheetrock Ceilings 10,000 **Replace Furniture 2,000 2,000 2,000 2,000 **Replace Gutters 20,000 **Replace Kitchen Landing 10,000 **Install AC in Library 8,000 **Waterline Payments 32,500 32,500 32,500 32,500 32,500 **Replace Septic System 100,000 ****Install Kindergarten Playground Fence 5,000 ******Repair Sheds 7,500 ******Replace Interior Doors 51,000 TOTAL 202, , , , ,000 Charlestown Elementary School FY 16 FY 17 FY18 FY19 FY20 *Construct Islands to Define Parking/Entrance 70,000 *Provide Accessibility to Entrances 7,500 *Clean and Re-Set Catch Basins; Replace Pipes 80,000 *Correct Accessibility to Fields and Playgrounds 14,000 *Provide Signage and Islands to Segregate Buses from Parking 5,000 *Pulverize and Re-Pave Parking Lot and Drive; Provide Curbing 25,000 55,000 *Replace Concrete Walks and Curbs 56,000 *Replace Damaged Interior Doors 20,000 *Replace Corridor Ceiling Tiles/Grid 16,500 *Upgrade Dishwasher Exhaust System 25,000 *Upgrade Gymnasium Return Register 5,000 *Upgrade Gymnasium Storage/Office HVAC 25,000 **Remove Asbestos Floor Tiles 30,000 **Replace Furniture/Cafeteria Tables 2,000 2,000 2,000 2,000 ****Install Shades re: SmartBoards 2,000 2/11/2015 3

4 Charlestown Elementary School FY 16 FY 17 FY18 FY19 FY20 ******Install Security Cameras 5,600 ******Ceiling Fan Replacements in Cafeteria 3,000 ******Hot Water Line Replacement 10,000 TOTAL 42,700 27, ,500 32,000 75,000 Ashaway Elementary School FY 16 FY 17 FY18 FY19 FY20 *Provide/Repair Chain Link Fence 3,000 *Clean Catch Basins and Drainage Manholes 5,000 *Repair Rear Stairs 20,000 *Make Nature Trail ADA Compliant 3,000 *Pulverize and Repave Parking Lot and Drive 25,000 45,000 *Provide Accessible Pathways to Play Structures 3,000 *Create Separation from Parent Drop-Off Loop and Play Areas with Curbs/Planters 20,000 *Add Concrete Pad for Dumpster and Screen 10,000 *Provide Dedicated Bus Drop-Off Area 25,000 *Replace Interior Doors 50,000 *Provide Smoke Vents for Stage 15,000 *Replace Windows 175, ,000 *Upgrade Electrical Service 81,000 *Upgrade Intercom 50,000 50,000 *Replace Plumbing Fixtures 65,000 65,000. *Upgrade Make-up Air for Generator 10,000 *Upgrade Corridor Ventilation 35,000 *Upgrade Gymnasium Distribution System 77,000 **Install Elevator 300,000 **Replace Furniture/Cafeteria Tables 3,500 2,000 2,000 2,000 2,000 **Replace Gymnasium Floor 55,000 **Refinish Stage 5,000 **Replace Underground Septic Piping 75,000 **Upgrade Gymnasium/Restroom Ventilation 9,500 ****** Install 4 Security Cameras 3,676 ******Install New Floor for Portable Building 5,534 TOTAL 96, , , , ,000 The RYSE School FY 16 FY 17 FY18 FY19 FY20 TOTAL /11/2015 4

5 Administration Building FY 16 FY 17 FY18 FY19 FY20 ******Install new Buzzer System 3,000 TOTAL 3, Maintenance and Technology Building FY 16 FY 17 FY18 FY19 FY20 TOTAL District FY 16 FY 17 FY18 FY19 FY20 **Replace Maintenance Vehicles 25,000 25,000 ******Facility Study Update 25,000 TOTAL 50,000-25, GRAND TOTALS 844, ,750 1,341, ,000 1,191,500 Housing Aid (386,336) CTC Categorical Aid (195,000) Out-of-Scope Wiring Reimbursement (42,000) 221,235 *Existing Facilities Evaluation, Kaestle Boos Associates, Inc., February 16, 2011 **FY12-FY16 Capital Plan (Duplicate Entries Have Been Eliminated) *** Added ****Added *****Added ******Added /11/2015 5

Briar Crest Elementary

Briar Crest Elementary Promises Kept This document includes partial lists of major projects completed at Pattonville Schools since 1986 as part of past bond issues approved by the Pattonville community. Briar Crest Elementary

More information

CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14

CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 2014-2015 CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 School Item Amount a. Classroom A/R (Increase CR capacity to 804, add l Resource and tutoring spaces needed. Teacher

More information

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological

More information

2014 Bond Project Guide

2014 Bond Project Guide 2014 Bond Project Guide Bush Elementary School Page 1 Instructional Technology Computers, Projectors, Mobile Carts, Document Cameras and Printers Wireless Connectivity New Construction New Tech Center

More information

School District of Milton 5- Year Capital Maintenance and Improvement Plan

School District of Milton 5- Year Capital Maintenance and Improvement Plan Updated - 02/21/17 School District of Milton 5- Year Capital Maintenance and Improvement Plan 101 East Elementary 1 Parking Lot/Traffic Flow Project 615,175 Includes Construction and Engineering 2 Bathroom

More information

NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS

NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS DECEMBER 3, 2013 KEY QUESTIONS 1. What is the time sequence for available funding? (In what years will the funding be available?) 2. What is the

More information

Master Facility Planning Update School Board Meeting May 26, 2016

Master Facility Planning Update School Board Meeting May 26, 2016 Master Facility Planning Update School Board Meeting May 26, 2016 Master Facilities Committee Overview Reflection of Committee Work Review of District Wide Facility Issues Identified District Wide Facility

More information

Tillamook High School Bond Projects

Tillamook High School Bond Projects Tillamook High School Bond Projects School Project Description All Buildings Upgrade fire alarm H&S All Buildings Add door lock capability from inside rooms Security All Buildings Install card lock entry

More information

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000 1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades Allowance $300,000 C. Tilden Entrance Upgrades D. Door and Glass Improvements Allowance $500,000 E. Alert

More information

TIFT COUNTY SCHOOLS E-SPLOST HISTORY

TIFT COUNTY SCHOOLS E-SPLOST HISTORY TIFT COUNTY SCHOOLS E-SPLOST HISTORY July 1, 1997 June 30, 2002 $28,766,187.16 collected July 1, 2002 June 30, 2007 $39,025,830.10 collected July 1, 2007 June 30, 2012 $41,886,155.46 collected July 1,

More information

REPORT CARD TO THE COMMUNITY MAY 15, 2018

REPORT CARD TO THE COMMUNITY MAY 15, 2018 REPORT CARD TO THE COMMUNITY MAY 15, 2018 O On May 10, 2014 voters in Greenville ISD approved a $72,275,000 bond election. BOND PROPOSAL PROJECT BOND AMOUNT CONSTRUCT A NEW BOWIE ELEMENTARY SCHOOL $17,600,000

More information

Oxford Hills School District Capital Renewal Plan Updated March 2017

Oxford Hills School District Capital Renewal Plan Updated March 2017 Color Coding Guide Recently Completed In Progress FY 2017 Budget in FY 2018 Future Budgets/Projects 3/20/17 Capital Renewal Plan Updated March 2017 Capital Renewal Plan - Harrison Elementary Harrison add

More information

Forest Hills Facilities Plan

Forest Hills Facilities Plan Forest Hills Facilities Plan Extensive updates to 8 of our 9 schools Replace Wilson Elementary Enhance learning environments across the district Build additional classrooms to accommodate gradual implementation

More information

FORT ERIE SECONDARY SCHOOL FACILITY INFORMATION. Lake Erie Corridor Secondary Schools Accommodation Review

FORT ERIE SECONDARY SCHOOL FACILITY INFORMATION. Lake Erie Corridor Secondary Schools Accommodation Review FORT ERIE SECONDARY SCHOOL FACILITY INFORMATION Lake Erie Corridor Secondary Schools Accommodation Review November 2012 LAKE ERIE CORRIDOR SECONDARY SCHOOLS ACCOMMODATION REVIEW Fort Erie Secondary School

More information

Allisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767

Allisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 Allisonville Elementary School Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 ADA improvements are Fire alarms need to be updated Playground equipment needs to be

More information

SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL)

SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL) SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL) Basketball Courts 15 25 Built Improvements Playgrounds, Site Furniture, etc. 20 20 Catch Basin 40 40 Cold Water Lines 40 40 Compactors DHW Supply

More information

New High School Concept

New High School Concept Approved Bond Projects for Alamance-Burlington Schools In November 2018, Alamance County citizens approved a $150 million bond project proposal. Bond funds will pay to construct a new high school and provide

More information

DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students

DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students FACILITY NEEDS THE CHALLENGE Deerfield Middle School/High School building has served the community for

More information

Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111

Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111 Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111 Year Opened 1971 Current Square Footage 175,743 Site Acreage (included in CCHS) 87.22 campus.cherrycreekschools.org $2,441,170

More information

HVAC / Boilers / Hot Water. Expected Life Span. very rough estimates Condition/Issue Age. Athletics / Gyms

HVAC / Boilers / Hot Water. Expected Life Span. very rough estimates Condition/Issue Age. Athletics / Gyms $4,013,500.00 $4,013,500.00 $ 1,155,000.00 $ 1,000,000.00 $ 205,000.00 $ 275,000.00 $ 300,000.00 $ 360,000.00 $ 438,500.00 $ 280,000.00 School Status Item HS Boilers boiler controls replaced 2017 2002

More information

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY MUKWONAGO SCHOOL DISTRICT ARCHITECTURE PARK VIEW MIDDLE SCHOOL The original school building was dedicated in 1954 as the High School, with an addition in 1959, a library addition in 1970, and an addition/renovation

More information

2014 Bond District-wide Facility Repairs

2014 Bond District-wide Facility Repairs Elementary Schools Aloha-Huber Park Fire Detector upgrade Replace electric backboard winches in gym Heating/cooling system controls upgrade Barnes Replace exterior windows Heating/cooling system and controls

More information

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY ARCHITECTURE ROLLING HILLS ELEMENTARY SCHOOL Rolling Hills Elementary was built in 1999 and is the newest addition to the Mukwonago Area School District. The building contains approximately 64,900 gross

More information

Florence High School / Middle School Page 1 of 3 Florence, WI

Florence High School / Middle School Page 1 of 3 Florence, WI Florence High School / Middle School Page 1 of 3 Florence, WI Plumbing Systems Review: The following report is the result of a site visit by Tim Kehoe of Muermann Engineering, LLC that occurred on October

More information

2014 Bond District-wide Facility Repairs

2014 Bond District-wide Facility Repairs Elementary Schools Aloha-Huber Park Fire Detector upgrade Replace electric backboard winches in gym Heating/cooling system controls upgrade Barnes Replace exterior windows Heating/cooling system and controls

More information

Josefa Ortiz De Dominguez Elementary School

Josefa Ortiz De Dominguez Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Edward Jenner Elementary Academy of the Arts

Edward Jenner Elementary Academy of the Arts Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111

Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Year Opened 1958 Current Square Footage 50,504 Site Acreage 8.53 greenwood.cherrycreekschools.org $220,720 Electrical

More information

Genevieve Melody Elementary School

Genevieve Melody Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

ALLISON ELEMENTARY SCHOOL 4315 Don Julio Blvd., North Highlands, CA 95660

ALLISON ELEMENTARY SCHOOL 4315 Don Julio Blvd., North Highlands, CA 95660 ALLISON ELEMENTARY SCHOOL 4315 Don Julio Blvd., North Highlands, CA 95660 Year Built 1960 // Age 58 years Building Area 31,688 Square Feet Student Capacity 389 Current Enrollment (2017-2018) 466 Priority

More information

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate Health & Safety 1,399,000 Academics & Program 17,140,800 Physical Education & Athletics 5,922,000 Building Infrastructure 3,103,800 Site Infrastructure 1,049,600 TOTAL SCOPE OF WORK 28,615,200 PROPOSED

More information

Joseph Brennemann Elementary School

Joseph Brennemann Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

MOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School

MOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School MOUNT PLEASANT MIDDLE SCHOOL HVAC M-01 Heating Plant: The existing boilers have recently been upgraded. (3) steam boilers (8660 mbh each) manufactured by Weil- McLain have been installed. Newer hot water

More information

Sagebrush Elementary School East Temple Place Aurora, Colorado 80015

Sagebrush Elementary School East Temple Place Aurora, Colorado 80015 Sagebrush Elementary School 14700 East Temple Place Aurora, Colorado 80015 Year Opened 1977 Current Square Footage 57,100 Site Acreage 7.66 sagebrush.cherrycreekschools.org Asphalt and concrete work; electrical

More information

5 Year Capital Improvement Plan Update

5 Year Capital Improvement Plan Update 5 Year Capital Improvement Plan Update Board Approved May 10, 2016 Collierville Schools Board of Education Wanda Chism Wright Cox Mark Hansen, Chairman Cathy Messerly Kevin Vaughan Superintendent John

More information

Design Presentation. Chief Operations Officer Willie Burroughs

Design Presentation. Chief Operations Officer Willie Burroughs Design Presentation Chief Operations Officer Willie Burroughs Agenda Introduction Community Feedback Project updates 2 Feedback Citizens Advisory Committee meetings Growth and Development meetings Community

More information

Richard Henry Lee Elementary School

Richard Henry Lee Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Custodial Guide

Custodial Guide Custodial Guide 2018-2019 Table of Contents Page Number 1 General Items to Note 2-3 Maintenance for Office Areas 4-5 Maintenance for Classrooms and Hallways 6 Maintenance for Lounge Areas 7 Maintenance

More information

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the

More information

Facilities Management Services

Facilities Management Services Facilities Management Services Operating Budget Facilities Management (FM) receives an Operating Budget each year predicated on funding the routine, predictable costs of cleaning, maintaining,, and repairing,

More information

January 11, New benches installed. Paving of parking lot adjacent to piers and the canoe put-in. Near complete with clean up remaining.

January 11, New benches installed. Paving of parking lot adjacent to piers and the canoe put-in. Near complete with clean up remaining. Project Updates January 11, 2018 CENTERVILLE CHESAPEAKE ARBORETUM BELLS MILL CITY CREEKWOOD SOUTH DEEP CREEK LOCK WORK TO BE PERFORMED/UPDATES Improvements to the parking lot include installation of a

More information

PLATTEVILLE MIDDLE SCHOOL

PLATTEVILLE MIDDLE SCHOOL Architectural The building has aluminum clad wood awning windows in combination with aluminum fixed glass units. They appear to be exterior glazed with insulated glazing. See photo 2. Platteville Middle

More information

SPLOST I, II, III,IV

SPLOST I, II, III,IV ACWORTH ES (OLD) ACWORTH INTERMEDIATE Construction projects not done due to school replacement Land Acquisition, 61 IU Replacement Elementary School Access Controls, Temperature monitors for walk in coolers

More information

Washington Irving Elementary School

Washington Irving Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

State College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT

State College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT State College Area School District High School South Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the

More information

Kenmore Town of Tonawanda Union Free School District : Capital Improvement Project Phase 2

Kenmore Town of Tonawanda Union Free School District : Capital Improvement Project Phase 2 Kenmore Town of Tonawanda Union Free School District : Capital Improvement Project Phase 2 Adams Field Kenmore East High School Kenmore West High School Crosby Field Charles Lindbergh Elementary Thomas

More information

Meadow Point Elementary School East Grand Avenue Aurora, Colorado 80015

Meadow Point Elementary School East Grand Avenue Aurora, Colorado 80015 Meadow Point Elementary School 17901 East Grand Avenue Aurora, Colorado 80015 Year Opened 1982 Current Square Footage 53,100 Site Acreage 7.48 meadowpoint.cherrycreekschools.org $2,081,600 Electrical system,

More information

NYC Department of Education

NYC Department of Education Asset: COLUMBUS AF - BRONX, 925 ASTOR AVENUE, New York, 10469 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2017-10-31 9:21 AM 2017-11-29 8:45 AM AA : Architectural - Associate

More information

Charles W Earle Elementary School

Charles W Earle Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Agustin Lara Elementary Academy

Agustin Lara Elementary Academy Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Francis M McKay Elementary School

Francis M McKay Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

VISION PLAN PRESENTATION - SEPTEMBER 28, 2013

VISION PLAN PRESENTATION - SEPTEMBER 28, 2013 AREAS OF IMPROVEMENT E A POOL HOUSE POOL DECK B B MAIN BUILDING UPPER PLAZAS A D F G C MAJOR BLEACHERS DUGOUTS FIELD MAIN COURTYARD D REGGIE PARK C E SPORT COURT ADA RAMP H F G H TENNIS COURTS KITCHENETTE

More information

Calmeca Academy of Fine Arts and Dual Language

Calmeca Academy of Fine Arts and Dual Language Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Oscar DePriest Elementary School

Oscar DePriest Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16

2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16 1. General: This summary is offered as a supplement to the 2015 Building Condition Survey being filed with SED on behalf of the District. All cost estimates are preliminary, and should be re-evaluated

More information

Ashland School District Facility & Capacity Assessment Report 2005

Ashland School District Facility & Capacity Assessment Report 2005 Ashland School District Facility & Capacity Assessment Report 2005 Briscoe Elementary School (Closed Facility) Address: 265 N Main Street Area: 33,980 square feet Buildings: Original Building 1948 Music

More information

Greater Albany Public Schools May 2017 Ballot Measure for School Repairs, Crowding and Job Training

Greater Albany Public Schools May 2017 Ballot Measure for School Repairs, Crowding and Job Training PUBLIC SCHOOLS Greater Albany Public s for Repairs, Crowding and Job Training CRITICAL FACILITY UPGRADES ADA Improvements: Architectural Improvements: Envelope Improvements Including Roofs: Exterior Improvements:

More information

MARY CRAPO CENTER Miller Road, Swartz Creek, Michigan

MARY CRAPO CENTER Miller Road, Swartz Creek, Michigan MARY CRAPO CENTER 8197 Miller Road, Swartz Creek, Michigan MARY CRAPO CENTER 8197 Miller Road, Swartz Creek General Information: - Instructional, Child Care Development Center (West Wing) o (2) Infant/Toddler

More information

John Palmer Elementary School

John Palmer Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Columns REF, RESPONSIBLE and COMPL TD are provided for your numbering, assignments and control. REF ISSUE RESPONSIBLE COMPL TD

Columns REF, RESPONSIBLE and COMPL TD are provided for your numbering, assignments and control. REF ISSUE RESPONSIBLE COMPL TD PREPARING FOR THE DESIGN OF YOUR SCHOOL CAPITAL PROJECT A Checklist of Issues March 2014, v.1 This document can be used in preparing the stakeholder team for decision-making and for documenting the input

More information

Cherry Hill Public Schools BUILDING A SOLID FUTURE

Cherry Hill Public Schools BUILDING A SOLID FUTURE Cherry Hill Public Schools BUILDING A SOLID FUTURE Who We Are The Cherry Hill School District is the 12 th largest in the state, serving 11,500 students 19 Locations 2 High Schools, 3 Middle Schools, 12

More information

Warren County Schools Plant and Operations

Warren County Schools Plant and Operations Warren County Schools Plant and Operations Buildings/Facilities/Energy Strategic Plan September 28, 2017 (Updated January 18, 2018) Donnie Caldwell; Facilities Director One Team, One Goal, High Levels

More information

NYC Department of Education

NYC Department of Education Asset: NEW UTRECHT AF - BROOKLYN, 1601 80 STREET, New York, 11214 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2017-10-31 4:06 PM 2018-06-13 10:51 AM AA : Architectural

More information

Master Project List Report

Master Project List Report Blue Hills Elementary School 01-8215 Site Utilities Replacement $52,835 01-8502 Modernization $3,135,933 01-8525 Exterior Painting $181,478 01-8552 Kindergarden Fencing $13,180 Install new backflow preventer.

More information

Major Public Facilities. Section 4

Major Public Facilities. Section 4 Major Public Facilities Section 4 Significant Public Facilities Section Index Facility Page Alphabetical by Title (sort) Broadmeadow Elementary School 419 Center at the Heights (Senior Center) 447 Chestnut

More information

Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018

Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018 Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018 WHAT IS A BOND ELECTION? Provide communities an opportunity to vote to give the Board of Trustees authority

More information

SCHOOLS + COMMUNITY rehabs, renovations, new construction

SCHOOLS + COMMUNITY rehabs, renovations, new construction OCV HAS A WEALTH OF EXPERIENCE HELPING S AND COMMU- NITY CENTERS BUILD, MODERNIZE + EXPAND THEIR FACILITIES, PROVIDING THE RIGHT ENVIRONMENT FOR GROWTH 2015 SMILOW CLUBHOUSE, MADISON SQUARE BOYS & GIRLS

More information

Ph: (907) Quality Homes

Ph: (907) Quality Homes Standard Specifications BUILDING your dream home www.destinyhomesak.com Ph: (907) 232-9751 Email: destiny4paul@aol.com Quality Homes 2016 1 HOME PRICE Prices of the homes are based on the $40,000 lot allowance.

More information

West Hartford Public School District

West Hartford Public School District West Hartford Public School District Agenda Item: Adoption of Capital Improvement Plan for 2018-19 Meeting Date: February 6, 2018 From: Through: Andy Morrow, Assistant Superintendent for Administration

More information

Sidney Sawyer Elementary School

Sidney Sawyer Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Emergency Management Resource Guide. Appendix A: Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky Public Schools

Emergency Management Resource Guide. Appendix A: Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky Public Schools Appendix A: Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky Public Schools 143 Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky

More information

If there are emergency situations they should be reported to Maintenance Department immediately.

If there are emergency situations they should be reported to Maintenance Department immediately. To: From: Re: Mercer County Schools Principals Mercer County Schools Safety Committee Required Safety Reports Date: October 30, 2010 In order to work toward safer schools, two reports are required to be

More information

DeWitt Clinton Elementary School

DeWitt Clinton Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Updated: 8/16/ Facilities Profile

Updated: 8/16/ Facilities Profile Updated: 8/16/17 2017-2018 Facilities Profile Purpose This package is put together to provide general information to District Administration, the School board and the public. The information contained

More information

EXISTING CONDITIONS SUMMARY

EXISTING CONDITIONS SUMMARY SITE Fire alarm system does meet current requirements Accessible path of travel lacking throughout campus Announcer s booth at Football Field booth not ADA compliant Covered and non covered outdoor eating

More information

Custom Report // Priorities 1+2

Custom Report // Priorities 1+2 Custom Report // Priorities + All costs are shown in 08 dollars. The cost of all work items after this date should be adjusted accordingly. Print Date: 4/3/08 Foothill High School DESCRIPTION Building

More information

NYC Department of Education

NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: LEHMAN AF - BRONX, 3000 EAST TREMONT AVENUE, New York, 10461 Inspection Id Inspection Type Time In Last Edited SA : Architectural -

More information

Smith Douglas Homes Presents HAYNESCREST TOWNHOMES

Smith Douglas Homes Presents HAYNESCREST TOWNHOMES The Oxford You ll be amazed to find that the Oxford, our newest townhome design, offers an unbelievable combination of comforts and amenities you re not likely to find in a townhome. An open kitchen with

More information

Vendor Application Form

Vendor Application Form Vendor Application Form DIRECTIONS: Fill out this form as completely as possible. Forms that are incomplete will be discarded without notification. If you encounter an error, use the "Back" function in

More information

Major Public Facilities. Section 7

Major Public Facilities. Section 7 Major Public Facilities Section 7 Significant Public Facilities Section Index Title Page Alphabetical by Title (sort) Broadmeadow Elementary School 7-14 Chestnut Street Annex 7-37 Daley Building 7-30 Department

More information

State College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT

State College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT State College Area School District High School North Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the

More information

Ohlone College Measure G Project Scope Revisions

Ohlone College Measure G Project Scope Revisions Scope Revisions Current Title Revised Title Current Scope Revised Scope 6101 Relocated Baseball Field Athletic Fields Create new sustainable baseball field with synthetic turf, bleacher seating and batting

More information

Springpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp.

Springpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp. Volume 1 Bidding Requirements, Contract Forms, Conditions of the Contract, Division 1, Architectural and Site Specifications 000107 Certification Page 000110 Table of Contents DIV00 PROCUREMENT AND CONTRACTING

More information

LKA Partners. A Professional Corporation for Architecture/Planning. 430 North Tejon Street Colorado Springs, CO /

LKA Partners. A Professional Corporation for Architecture/Planning. 430 North Tejon Street Colorado Springs, CO / LKA Partners A Professional Corporation for Architecture/Planning 430 North Tejon Street Colorado Springs, CO 80903 719/473-8446 C O N F E R E N C E R E C O R D PROJECT: BOULDER VALLEY SCHOOL DISTRICT

More information

FOOD SERVICE May 6, 2016

FOOD SERVICE May 6, 2016 FOOD SERVICE May 6, 2016 I. PROGRAM REQUIREMENTS Refer to the project-specific Schedule of Spaces for student stations, square footage, and for any requirements that may differ from the prototype requirements

More information

Service Description Service Shop Customer Charge Comments. Electronic Shop. Electric Shop Yes additional circuits for equipment

Service Description Service Shop Customer Charge Comments. Electronic Shop. Electric Shop Yes additional circuits for equipment Fire alarm repairs Electronic Shop Fire alarm sound level testing Electronic Shop Fire system inspections Electronic Shop Installation of additional fire detection/alarm/supression devices Electronic Shop

More information

George B Swift Elementary Specialty School

George B Swift Elementary Specialty School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

SCHEMATIC DESIGN PRESENTATION

SCHEMATIC DESIGN PRESENTATION August 5, 2014 SCHEMATIC DESIGN PRESENTATION ADDITIONS & RENOVATIONS Greenville Independent School District Acknowledgments 2 Narrative 3-6 Crockett Elementary School 7-12 L.P. Waters Early Childhood Center

More information

DOCUMENT TABLE OF CONTENTS

DOCUMENT TABLE OF CONTENTS DOCUMENT 00003 June 16, 2005 TABLE OF CONTENTS DOCUMENT NO. INTRODUCTORY INFORMATION DOCUMENT 00003 TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS SECTION 01011 SECTION 01025 SSP21.1-1 SECTION 01026

More information

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA 18064 610-759-1367 FAX 610-759-7028 TO: FROM: Dr. Riker, Superintendent of Schools Board of School Directors Lewis F.

More information

Encumbered Balance (E-D) Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765, $635, $635, $130, $0.

Encumbered Balance (E-D) Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765, $635, $635, $130, $0. Branham High School Budget Remaining 1 906030 Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765,473.00 $635,342.00 $635,342.00 $130,131.00 $0.00 2 970205 Branham Interim Housing - 12 Portable

More information

ALLEGHANY COUNTY PUBLIC SCHOOLS Maintenance Work Request Completion Analysis

ALLEGHANY COUNTY PUBLIC SCHOOLS Maintenance Work Request Completion Analysis ALLEGHANY COUNTY PUBLIC SCHOOLS Maintenance Work Request Completion Analysis 204-205 YEAR-TO-DATE Custodial Supplies 88.00 9.50 $,643. $26,39.60 $27,782.7 Preventive Maintenance 67.00,74.00 $20,372.68

More information

Arena Elementary School 314 Willow St. Arena, WI 53503

Arena Elementary School 314 Willow St. Arena, WI 53503 FACILITIES PLANNING STUDY RIVER VALLEY SCHOOL DISTRICT Arena Elementary School 314 Willow St. Arena, WI 53503 7 South Dewey Street Eau Claire, Wisconsin 54701 715.83.1605 sdsarch.com ARENA General Overview

More information

Alessandro Volta Elementary School

Alessandro Volta Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

OPERATING. Salaries, wages, and benefits personnel costs for repairs and maintenance functions, including living or accommodation allowances.

OPERATING. Salaries, wages, and benefits personnel costs for repairs and maintenance functions, including living or accommodation allowances. Page 1 of 6 Maintenance Labour Salaries, wages, and benefits personnel costs for repairs and maintenance functions, including living or accommodation allowances. Maintenance Materials & Services Building

More information

1354 CHECKLIST for Project Closeout

1354 CHECKLIST for Project Closeout 1354 CHECKLIST for Project Closeout PROJECT NUMBER: BUILDING NUMBER: DESCRIPTION OF PROJECT: Describe description of work; i.e., New Construction, Addition, Modification, Renovation, etc DRAWING NUMBER

More information

E-SPLOST V. Facts and Information. August 2018

E-SPLOST V. Facts and Information. August 2018 E-SPLOST V Facts and Information August 2018 Education Special Purpose Local Option Sales Tax What is E-SPLOST? It is a one penny sales tax that allows for shared contribution to education, including visitors

More information

Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS

Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS DATE: July 10, 2007 TO: FROM: SUBJECT: ORIGINATOR: RESOURCE PERSON(S): BOARD OF EDUCATION Dr. Joe A. Hairston, Superintendent ABBREVIATED FACILITY STATUS REPORT

More information

LONG-TERM OPERATIONS AND MAINTENANCE PLAN

LONG-TERM OPERATIONS AND MAINTENANCE PLAN LONG-TERM OPERATIONS AND MAINTENANCE PLAN May, 2017 BOARD OF EDUCATION Cathe Russe President Jackie Lutz Vice President Sam Ach Member John Heggie Member Natalie Jachtorowycz Member John J. Murphy Member

More information

Binghamton University Construction SUMMER 2012 HIGHLIGHTS

Binghamton University Construction SUMMER 2012 HIGHLIGHTS Binghamton University Construction SUMMER 2012 HIGHLIGHTS Binghamton University Construction Summer 2012 Large and small construction projects were completed during the summer 2012 construction season.

More information