1 Public Works Department 104 W. Magnolia Street, Suite 109 Bellingham, WA (360) STORMWATER PERMIT SUBMITTAL REQUIREMENTS Most development within the City of Bellingham that involves disruption of soils, or construction of buildings, streets, parking lots, etc. requires the issuance of a Stormwater Permit. This packet contains material that will aid you in providing a complete application for this permit. Stormwater Permit requirements are based on either the amount of soil to be disrupted (grading, vegetation removal), or the amount of impervious surface that is created or replaced on a site (building footprint, concrete, asphalt or gravel parking, sidewalk, etc.). A Stormwater Site Plan consists of plan sheets showing all proposed Stormwater systems and facilities, Stormwater Pollution Prevention Plan (SWPPP), and if applicable, a Stormwater report by a licensed civil engineer. Please follow the steps on the worksheets to determine the level of stormwater management required for your project. Many applications will not need to use all information provided in this packet. If you need assistance in your determination, contact the Development section of the Public Works Dept. located at 104 W. Magnolia St., Suite 109 or call (360) STORMWATER MANAGEMENT REQUIREMENT CHECKLIST Provide the following information as part of your submittal: Impervious surface calculation (see next page) Stormwater management requirement determination Stormwater site plan and/or erosion control plan as stated on the applicable Requirements List I, II, or III Attach a copy of a General Construction Stormwater Pollution Prevention Plan (SWPPP) to Site Plan (see Page 7 of this packet) and erosion control details (see Page 8)

2 IMPERVIOUS SURFACE CALCULATION Per Bellingham Municipal Code Stormwater Management ( Impervious surface means a hard surface area that either prevents or retards the entry of water into the soil mantle as under natural conditions prior to development. A hard surface area which causes water to run off the surface in greater quantities or at an increased rate of flow from the flow present under natural conditions prior to development. Common impervious surfaces include, but are not limited to, roof tops, walkways, patios, driveways, parking lots or storage areas, concrete or asphalt paving, packed gravel surfaces, packed earthen materials, or other surfaces which similarly impede the natural infiltration of stormwater. The total square footage of impervious surface on your project site will determine the storm water management requirements and the storm water utility fees. Impervious surface calculations must include all of the impervious areas on your project site. "New impervious surface means impervious surfaces that replace or supplant existing pervious surfaces. For example, resurfacing by upgrading from dirt to gravel, asphalt, or concrete. "Replaced impervious surface" means, for structures, the removal and replacement of any exterior impervious surfaces or foundation. For other impervious surfaces, the removal down to bare soil or base course and replacement is considered "replaced". Provide detailed information about your project in the following table. Enter 0 in the sections that are not applicable to your project. Impervious Surface Area (square feet) Existing Removed Proposed New Proposed Replaced Totals LAND DISTURBANCE Land Disturbance* (square feet) *Greater than 500 square feet of land disturbance requires a Stormwater Permit. 2 P age

3 STORMWATER MANAGEMENT REQUIREMENT DETERMINATION Follow the diagram using information from your impervious surface calculation. Your answers will determine the stormwater management requirements list you will use. Is your project less than 120 S.F. new, replaced or new plus replaced imperious surface AND less than 500 S.F. land disturbance? YES NO STORMWATER PERMIT REQUIRED NO Is the total new or replaced impervious surface greater than 5,000 S.F.? OR Does the project disturb more than 1 acre of land? YES Address the requirements of STORMWATER MANAGEMENT REQUIREMENTS LIST III NO Is your project inside the Lake Whatcom watershed? YES NO Is your project a new single family residence or duplex? NO YES Address the requirements of STORMWATER MANAGEMENT REQUIREMENTS LIST II Does the project contain more than 2,000 S.F. of new, replaced or new plus replaced impervious area? YES NO Address the requirements of STORMWATER MANAGEMENT REQUIREMENTS LIST I 3 P age

4 STORMWATER MANAGEMENT REQUIREMENTS LIST I If the project includes less than 2,000 square feet of new, replaced or new plus replaced impervious surface (and is not a new single family residence or duplex) or land disturbance greater than 500 square feet, provide a simplified site plan which shows: Clearing limits and indicate how limits will be marked on property. Construction entrance location and silt fence location (show location on site plan and attach standard plan sheet, see page 8). Attach General Construction Stormwater Pollution Prevention Plan (SWPPP) to site plan (see page 8). If project is a new single family residence or duplex residence see Stormwater Management Requirements List II on page 5 In addition, consider the following elements for your project: Stormwater management (tight lined to City storm system or On-Site Stormwater Management, see Appendix B). Stabilize soils Protect slopes Protect drain inlets Stabilize channels and outlets Control pollutants Control de-watering Maintain "Best Management Practices" (BMPs) Manage the project 4 P age

5 STORMWATER MANAGEMENT REQUIREMENTS LIST II If your project is a new single family home or duplex or between 2,000 and 5,000 square feet of new, replaced or new plus replaced impervious surface or 5,000 square feet or more of land disturbance, the project requires compliance with the following listed minimum requirements. For specific information, please refer to the current edition of the Washington State Department of Ecology's Stormwater Management Manual for Western Washington (click on link: 1. Preparation of Site Plans The following elements must be considered during the development of the site plan: Existing public and private development, including utility infrastructure on and adjacent to the site. Minor hydrologic features, including seeps, springs, closed depression areas, drainage swales. Major hydrologic features such as streams, wetlands and waterbodies. Flood hazard areas on or adjacent to the site, if present. Geologic Hazard areas as defined by the local jurisdiction. Topographic features that may act as natural stormwater storage, infiltration or conveyance. Underlying soils on the site utilizing soil surveys, soil test pits, soil borings, or soil grain analyses (see for soil survey information). Plat conditions or other restrictions on the allowed impervious surface coverage. Easements and/or other restrictions associated with the project area. 2. Construction Stormwater Pollution Prevention Plan (SWPPP) See the attached requirements for "General Construction Stormwater Pollution Prevention Plan" on page 8 3. Source Control of Pollutants See Appendix A for information about available source control BMPs 4. Preservation of Natural Drainage Systems and Outfalls Natural drainage patterns shall be maintained, and discharges for the project site shall occur at the natural location, to the maximum extent practicable. The manner by which runoff is discharged from the project site must not cause a significant adverse impact to downstream receiving waters and downgradient properties. All outfalls require energy dissipation. Where no conveyance system exists at the adjacent downgradient property line and the discharge was previously unconcentrated flow or significantly lower concentrated flow, you may need to obtain an easement or consider an engineered storm system to prevent impacts to downstream property. 5 P age

6 5. On-Site Stormwater Management Projects shall employ on-site stormwater management BMPs to infiltrate, disperse, and retain stormwater runoff on-site to the maximum extent feasible without causing flooding or erosion impacts. Roof downspout control BMPs (see Appendix B), and Dispersion and Soil Quality BMPs shall be required to reduce the hydrologic disruption of developed sites. 6 P age

7 STORMWATER MANAGEMENT REQUIREMENTS LIST III If your project is greater than 5,000 square feet of new, replaced or new plus replaced impervious surface. The project requires compliance with the following minimum requirements. The plan must be designed by a licensed civil engineer. For specific information, please refer to the most current edition of the Washington State Department of Ecology Stormwater Management Manual for Western Washington ( 1. Preparation of Stormwater Site Plans 2. Construction Stormwater Pollution Prevention Plan (SWPPP) 3. Source Control of Pollution 4. Preservation of Natural Drainage Systems and Outfalls 5. On-site Stormwater Management 6. Runoff Treatment 7. Flow Control 8. Wetland Protection 9. Basin/Watershed Planning 10. Operation and Maintenance 7 P age

8 GENERAL CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN SWPPP Purpose To prevent the discharge of sediment and other pollutants to the maximum extent practicable from small construction projects. Design and Installation Plan and implement proper clearing and grading of the site. It is most important only to clear the areas needed, keeping exposed areas to a minimum. Phase clearing so that only those areas that are actively being worked are uncovered. Note: Clearing limits shall be flagged on the lot or project area prior to initiating clearing. From October 1 through April 30, no soils shall remain exposed and unworked for more than two days. From May 1 to September 30, no soils shall remain exposed and unworked for more than seven days. Soil shall be managed in a manner that does not permanently compact or deteriorate the final soil and landscape system. If disturbance and/or compaction occur the impact must be corrected at the end of the construction activity. This shall include restoration of soil depth, soil quality, permeability, and percent organic matter. Construction practices must not cause damage to or compromise the depth of permanent landscape or infiltration areas. Locate any soil piles away from drainage systems. Soil piles should be tarped or mulched until the soil is either used or removed. Piles should be situated so that sediment does not run into the street or adjoining yards. Backfill foundation walls as soon as possible after backfilling. This will eliminate any sediment loss from surplus fill. The construction entrance shall be stabilized where traffic will be leaving the construction site and traveling on paved roads or other paved surfaces. Provide for periodic street cleaning to remove any sediment that may have been tracked out. Sediment should be removed by shoveling or sweeping and carefully removed to a suitable disposal area where it will not be re eroded. Street washing is prohibited without special permission from the SSW utility, call (360) P age

9 SEDIMENT BARRIER (STRAW WATTLE) 9 P age

10 10 P age

11 FEES What are the fees? Part One Permit Fees: Charged when a permit is needed for construction activity. The fee amount is based on either the amount of impervious surface added and/or replaced or the amount of land disturbance. Stormwater Permit Fees Effective 08/01/05 per ordinance Permit Type Amount of Amount of Clearing Fee Impervious & Grading Level One Permit (fee per site) 300 to 1000 SF 500 to 5000 SF $ Level Two Permit (fee per site) 1000 to 5000 SF 5,000 to 30,000 SF $ Level Three Permit (fee per site) 5000 SF to 1 acre More than 30,000 SF $ Level Four Permit (fee per site) More than 1 acre N/A $ Part Two Development Charges: Charged on each parcel of property that is developed or redeveloped within the City of Bellingham. Stormwater Type of Use Single Family Residence (SFR) & Duplexes All other types of new impervious surface greater than or equal to 3,000 square feet Amount $ per SFR $0.226 per square foot of impervious What are the standards for stormwater design? Stormwater designs must be done in accordance with Bellingham Municipal Code 15.42, the most current Stormwater Management Manual for Western Washington, and the Low Impact Technical Guidance Manual for Western Washington. These documents are subject to change. 11 P age

12 APPENDIX A SOURCE CONTROL BMPS. There are two categories of Source Control BMPs: operational and structural. Here is a link to Volume IV - Source Control of the Department of Ecology's Stormwater Management Manual: Operational Source Control BMPs are non-structural practices that prevent or reduce pollutants from entering stormwater. Examples include formation of a pollution prevention team, good housekeeping practices, preventive maintenance procedures, spill prevention and cleanup, employee training, inspections of pollutant sources, and record keeping. They can also include process changes, raw material/product changes, and recycling wastes. Operational Source Control BMPs are considered the most cost-effective pollutant minimization practices. The following operational source control BMPs must be implemented at the commercial and industrial establishments listed in Appendix IV-A, where required by Ecology's Industrial General Permit or by local government ordinances. Assign one or more individuals to be responsible for stormwater pollution control. Hold regular meetings to review the overall operation of the BMPs. Establish responsibilities for inspections, operation and maintenance, and availability for emergency situations. Train all team members in the operation, maintenance and inspections of BMPs, and reporting procedures. Promptly contain and clean up solid and liquid pollutant leaks and spills including oils, solvents, fuels, and dust from manufacturing operations on any exposed soil, vegetation, or paved area. Sweep paved material handling and storage areas regularly as needed, for the collection and disposal of dust and debris that could contaminate stormwater. Do not hose down pollutants from any area to the ground, storm drain, conveyance ditch, or receiving water unless necessary for dust control purposes to meet air quality regulations and unless the pollutants are conveyed to a treatment system approved by the local jurisdiction. Clean oils, debris, sludge, etc. from all BMP systems regularly, including catch basins, settling/detention basins, oil/water separators, boomed areas, and conveyance systems, to prevent the contamination of stormwater. Refer to Appendix IV-D R.3 for references to assist in determining if a waste must be handled as hazardous waste. Promptly repair or replace all substantially cracked or otherwise damaged paved secondary containment, high-intensity parking and any other drainage areas, which are subjected to pollutant material leaks or spills. Promptly repair or replace all leaking connections, pipes, hoses, valves, etc. which can contaminate stormwater. Operational and structural BMPs that are designed to address specific types of pollutant sources are presented in Stormwater Management Manual for Western Washington (DOE Stormwater Manual), Volume IV, Chapter 2, section 2 12 P age

13 APPENDIX B ON-SITE WATER MANAGEMENT Roof Downspout Controls Roof downspout controls are simple pre-engineered designs for infiltrating and/or dispersing runoff from roof areas for the purposes of limiting development impacts. Here is a link to Volume V - Runoff Treatment BMPs, Department of Ecology Stormwater Management Manual for Western Washington Selection of Roof Downspout Controls Where roof downspout controls are planned, the following three types must be considered in the order of preference show below. 1. Downspout infiltration systems 2. Downspout dispersion systems 3. Downspout perforated stub-out connections 1. Downspout Infiltration Systems Downspout infiltration systems are trench or drywell designs intended only for use in infiltrating runoff from roof downspout drains. They are not designed to directly infiltrate runoff from pollutant-generating impervious surfaces. Please check the soils map (Potential Infiltration Areas). If your project site is in a shaded area, you may be able to use infiltration. Contact the Public Works Development Section at (360) to confirm applicability. Infiltration System Setbacks All infiltration systems should be at least 10 feet from any structure, property line, or sensitive area (except slopes over 40%). All infiltration systems must be at least 50 feet from the top of any slope over 40%. The setback may be reduced based on a geotechnical evaluation, but in no instances may it be less than the buffer width. Infiltration Trench should be designed according to the following specifications: The minimum lengths (linear feet) per 1,000 square feet of roof area based on soil type may be use for sizing downspout infiltration trenches. Coarse sands Medium sand Fine or Loamy sand Sandy Loam cobbles loam 20 LF 30 LF 75 LF 125 LF 190 LF Maximum length of trench must not exceed 100 feet from the inlet sump. Minimum spacing between trench centerlines must be 6 feet. Filter fabric must be placed over the drain rock as shown on Figure 1. Infiltration trenches may be located in fill material if the fill is placed and compacted under the direct supervision of a geotechnical engineer of professional civil engineer with geotechnical expertise, and if the measured infiltration rate is at least 8 inches per hour. Trench length in fill must be 60 L.F. per 1000 S.F. of roof area. Infiltration trench should not be built on slopes steeper than 25%. Infiltration Drywell should be designed according to the following specifications: Drywell bottoms must be a minimum of 1 foot above seasonal high groundwater level or impermeable soil layers. If using drywells, each drywell may serve up to 1000 S.F. of imperious surface for either medium sand or coarse sands. Typically drywells are 48 inches in diameter (mini.) and have a depth of 5 feet (4 feet of gravel and 1 foot of suitable cover material). 13 P age

14 Filter fabric (geotextile) must be placed on the top of the drain rock and on trench or drywell sides prior to backfilling. Spacing between drywells must be a minimum of 4 feet. Downspout infiltration drywells must not built on slopes greater than 25 %(4:1). Drywells may not be placed on or above a landslide hazard area or slopes greater than 15% with evaluation by a professional engineer with geotechnical expertise or qualified geologist and jurisdiction approval. Figure 1 - Typical Downspout Infiltration Trench 14 P age

15 l Figure 2 Alternative Downspout Infiltration Trench System for Course Sand and Gravel Figure 3 Typical Downspout Infiltration Drywell 15 P age

16 2. Downspout Dispersion Systems Downspout dispersion systems are splash blocks or gravel-filled trenches, which serve to spread roof runoff over vegetated pervious areas. Dispersion attenuates peak flows by slowing entry of the runoff into the conveyance system, allows for some infiltration, and provides some water quality benefits. Dispersion Trenches should be designed according to the following specifications: 1. A vegetated flowpath of at least 25 feet in length must be maintained between the outlet of the dispersion trench and any property line, structure, stream, wetland, lake or impervious surface. A vegetated flowpath of at least 50 feet in length must be maintained between the outlet of the trench and any steep slope. Sensitive area buffers may count towards flowpath lengths. 2. Maintain a setback of at least 5 feet between trench and structures or property line. 3. Splashblocks require a vegetated flow path of at least 50 feet in length between any property line, structure, stream, wetland, lake or impervious surface. 4. A maximum of 700 square feet of roof area may drain to each splashblock or standard dispersion trench. 5. A trench with a notched grade board may be used for larger areas. 6. No erosion or flooding of downstream properties may result. 7. Runoff discharged towards landslide hazard areas must be evaluated by a professional engineer with geotechnical expertise or a qualified geologist. Downspout dispersion systems may not be placed on or above slopes greater than 20% or above erosion hazard areas without evaluation by a professional engineer with geotechnical expertise or a qualified geologist and jurisdiction approval. Figure 4. Typical Downspout Dispersion Trench 16 P age

17 Figure 5 Standard Dispersion Trench with Notched Grade Board 17 P age

18 Figure 6 Typical Downspout Splashblock Dispersion house Roof downspout serves up to 700 sf. Of roof 50 min. Vegetated flow path Splash block Downspout extension Splash block 18 P age

19 3. Perforated Stub-Out Connections A perforated stub-out connection is a length of perforated pipe within a gravel-filled trench that is placed between roof downspouts and a stub-out to the local drainage system. Figure 7 below illustrates a perforated stub-out connection. These systems are intended to provide some infiltration during drier months. During the wet winter months, they may provide little or no flow control. Perforated stub-outs are not appropriate when the seasonal water table is < 1 foot below trench bottom. In single-family subdivision projects subject to Minimum Requirement #7 for flow control (see Volume I), perforated stub-out connections may be used only when downspout infiltration or dispersion is not feasible. Location of the connection should be selected to allow a maximum amount of runoff to infiltrate into the ground (ideally a dry location on the site that is relatively well drained). To facilitate maintenance, the perforated pipe portion of the system should not be located under impervious or heavily compacted (e.g., driveways and parking areas) surfaces. Perforated stub-out connections should consist of at least 10 feet of perforated pipe per 5,000 square feet of roof area laid in a level, 2-foot wide trench backfilled with washed drain rock. The drain rock should extend to a depth of at least 8 inches below the bottom of the pipe and should cover the pipe. The pipe should be laid level and the rock trench covered with filter fabric and 6 inches of fill (see Figure 7). Setbacks are the same as for infiltration trenches; at least 10 feet from any structure, property line, or sensitive area. Potential runoff discharge towards a landslide hazard area must be evaluated by a professional engineer with geotechnical expertise or a qualified geologist. The perforated portion of the pipe may not be placed on or above slopes greater than 20% or above erosion hazard areas without evaluation by a professional engineer with geotechnical expertise or qualified geologist and jurisdiction approval. For sites with septic systems, the perforated portion of the pipe must be downgradient of the drain field primary and reserve areas. This requirement can be waived if site topography will clearly prohibit flows from intersecting the drain field or where site conditions (soil permeability, distance between systems, etc.) indicate that this is unnecessary. 19 P age

20 Figure 7 Perforated Stub-Out Connection 20 P age

21 Purpose and Definition BMP T5.13: Post Construction Soil Quality and Depth Naturally occurring (undisturbed) soil and vegetation provide important stormwater functions including: water infiltration; nutrient, sediment, and pollutant adsorption; sediment and pollutant biofiltration; water interflow storage and transmission; and pollutant decomposition. These functions are largely lost when development strips away native soil and vegetation and replaces it with minimal topsoil and sod. Applications and Limitations Establishing a minimum soil quality and depth is not the same as preservation of naturally occurring soil and vegetation. However, establishing a minimum soil quality and depth will provide improved on-site management of stormwater flow and water quality. Soil organic matter can be attained through numerous materials such as compost, composted woody material, biosolids, and forest product residuals. It is important that the materials used to meet the soil quality and depth BMP be appropriate and beneficial to the plant cover to be established. Likewise, it is important that imported topsoils improve soil conditions and do not have an excessive percent of clay fines. This BMP can be considered infeasible on till soil slopes greater than 33 percent. Design Guidelines Soil retention. Retain, in an undisturbed state, the duff layer and native topsoil to the maximum extent practicable. In any areas requiring grading remove and stockpile the duff layer and topsoil on site in a designated, controlled area, not adjacent to public resources and critical areas, to be reapplied to other portions of the site where feasible. Soil quality. All areas subject to clearing and grading that have not been covered by impervious surface, incorporated into a drainage facility or engineered as structural fill or slope shall, at project completion, demonstrate the following: 1. A topsoil layer with a minimum organic matter content of 10% dry weight in planting beds, and 5% organic matter content in turf areas, and a ph from 6.0 to 8.0 or matching the ph of the undisturbed soil. The topsoil layer shall have a minimum depth of eight inches except where tree roots limit the depth of incorporation of amendments needed to meet the criteria. Subsoils below the topsoil layer should be scarified at least 4 inches with some incorporation of the upper material to avoid stratified layers, where feasible. 2. Mulch planting beds with 2 inches of organic material 3. Use compost and other materials that meet these organic content requirements: a. The organic content for pre-approved amendment rates can be met only using compost meeting the compost specification for Bioretention (BMP T7.30), with the exception that the compost may have up to 35% biosolids or manure. 21 P age

22 The compost must also have an organic matter content of 40% to 65%, and a carbon to nitrogen ratio below 25:1. The carbon to nitrogen ratio may be as high as 35:1 for plantings composed entirely of plants native to the Puget Sound Lowlands region. b. Calculated amendment rates may be met through use of composted material meeting (a.) above; or other organic materials amended to meet the carbon to nitrogen ratio requirements, and not exceeding the contaminant limits identified in Table 220-B, Testing Parameters, in WAC The resulting soil should be conducive to the type of vegetation to be established. Implementation Options: The soil quality design guidelines listed above can be met by using one of the methods listed below: 1. Leave undisturbed native vegetation and soil, and protect from compaction during construction. 2. Amend existing site topsoil or subsoil either at default pre-approved rates, or at custom calculated rates based on tests of the soil and amendment. 3. Stockpile existing topsoil during grading, and replace it prior to planting. Stockpiled topsoil must also be amended if needed to meet the organic matter or depth requirements, either at a default pre-approved rate or at a custom calculated rate. 4. Import topsoil mix of sufficient organic content and depth to meet the requirements. More than one method may be used on different portions of the same site. Soil that already meets the depth and organic matter quality standards, and is not compacted, does not need to be amended. Maintenance Establish soil quality and depth toward the end of construction and once established, protect from compaction, such as from large machinery use, and from erosion. Plant vegetation and mulch the amended soil area after installation. Leave plant debris or its equivalent on the soil surface to replenish organic matter. Reduce and adjust, where possible, the use of irrigation, fertilizers, herbicides and pesticides, rather than continuing to implement formerly established practices. 22 P age

STORMWATER PERMIT SUBMITTAL REQUIREMENTS

STORMWATER PERMIT SUBMITTAL REQUIREMENTS STORMWATER PERMIT SUBMITTAL REQUIREMENTS Most development within the City of Bellingham that involves disruption of soils, or construction of buildings, streets, parking lots, etc. requires a Stormwater

More information

Chapter 2 Roof Downspout Controls

Chapter 2 Roof Downspout Controls Chapter 2 Roof Downspout Controls 2.1 Description This section presents the criteria for design and implementation of roof downspout controls. Roof downspout controls are simple pre-engineered designs

More information

2.1.4 Roof Downspout Rain Gardens

2.1.4 Roof Downspout Rain Gardens 2008 SWMM, 2010 Revision City of Tacoma 2.1.4 Roof Downspout Rain Gardens Purpose and Definition Bioretention areas are shallow stormwater retention facilities designed to mimic forested systems by controlling

More information

Chapter 5 - On-Site Storm Water Management

Chapter 5 - On-Site Storm Water Management Chapter 5 - On-Site Storm Water Management Note: Figures 5.1 through 5.5 are courtesy of King County, Figures 5.6 and 5.7 are from Ecology s 1992 Manual, and Figures 5.8 through 5.14 are courtesy of Washington

More information

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE Please complete this narrative form and submit with your SWPPP drawings. Refer to Kitsap County Stormwater Design Manual Vol.

More information

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) (360) (FAX)

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) (360) (FAX) CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA 98501 (360) 754-4180 (360) 754-4126 (FAX) Email: cdd@ci.tumwater.wa.us APPENDIX II-C SHORT FORM CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN (SWPPP)

More information

SUPPORTING DOCUMENT POST-CONSTRUCTION SOIL QUALITY AND DEPTH WORKSHEET

SUPPORTING DOCUMENT POST-CONSTRUCTION SOIL QUALITY AND DEPTH WORKSHEET SUPPTING DOCUMENT POST-CONSTRUCTION SOIL QUALITY AND DEPTH WKSHEET For Department of Ecology Stormwater BMP T5.13 This submittal worksheet will help determine what soil amendments are needed to meet the

More information

SECTION 1 CLEARING /GRADING PERMIT APPLICATION:

SECTION 1 CLEARING /GRADING PERMIT APPLICATION: PLEASE REFER TO THE CLEARING & GRADING PERMIT CHECKLIST BELOW FOR SUBMITTAL REQUIREMENTS. SECTION 1 CLEARING /GRADING PERMIT APPLICATION: PROJECT ADDRESS (Street, Suite #): Parcel(s) #: Total Site Area

More information

CHAPTER 9 STORM DRAINAGE. Minimum Requirements for New Development and Redevelopment

CHAPTER 9 STORM DRAINAGE. Minimum Requirements for New Development and Redevelopment CHAPTER 9 STORM DRAINAGE 9.01 General The standards established by this chapter are intended to represent the minimum standards for the design and construction of storm drainage facilities. 9.02 Design

More information

PLANNING & DEVELOPMENT SERVICES 1800 Continental Place Mount Vernon, WA Inspections Office Fax

PLANNING & DEVELOPMENT SERVICES 1800 Continental Place Mount Vernon, WA Inspections Office Fax PLANNING & DEVELOPMENT SERVICES 1800 Continental Place Mount Vernon, WA 98273 Inspections 360.336.9306 Office 360.336.9410 Fax 360.336.9416 Application will expire 6 mo from this date: Floodplain Development

More information

Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM

Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM I. PROJECT DATA Project Name Bay Meadows Development Phase II Project Address 2600

More information

Clallam County Small Project Drainage Requirements And Technical Guidance Manual DRAFT

Clallam County Small Project Drainage Requirements And Technical Guidance Manual DRAFT Clallam County Small Project Drainage Requirements And Technical Guidance Manual DRAFT 2 Small Project Drainage Requirements and Technical Guidance Manual Table of Contents Section I. Section II. Section

More information

2008 SWMM, 2010 Revision City of Tacoma

2008 SWMM, 2010 Revision City of Tacoma 2008 SWMM, 2010 Revision City of Tacoma 2.2.3.1 BMP L630 Rain Gardens Purpose and Definition Bioretention areas are shallow stormwater retention facilities designed to mimic forested systems by controlling

More information

Directors Rules for Seattle Municipal Code, Chapters Stormwater Code

Directors Rules for Seattle Municipal Code, Chapters Stormwater Code Directors Rules for Seattle Municipal Code, Chapters 22.800 22.808 Stormwater Code Requirements for Green Stormwater Infrastructure to the Maximum Extent Feasible for Single-Family Residential and Parcel-Based

More information

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS 5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS Low Impact Development (LID) requires a shift in stormwater management away from conveying runoff to a small number of downstream points through hydraulically

More information

New Development Stormwater Guidelines

New Development Stormwater Guidelines New Development Stormwater Guidelines CITY OF MOUNTLAKE TERRACE Table of Contents Introduction... 2 Ecology s Minimum Requirements for stormwater management... 2 Description of the 9 Minimum Requirements...

More information

APPENDIX A SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS. In West Sadsbury Township, Chester County, Pennsylvania

APPENDIX A SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS. In West Sadsbury Township, Chester County, Pennsylvania APPENDIX A SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS In West Sadsbury Township, Chester County, Pennsylvania TABLE OF CONTENTS I. Introduction 3 II. Importance of Stormwater Management

More information

COMMUNITY DEVELOPMENT DEPARTMENT POLICY DRAINAGE FOR RESIDENTIAL PROJECTS WITH ONE OR TWO UNITS REVISED JANUARY 4, 2018

COMMUNITY DEVELOPMENT DEPARTMENT POLICY DRAINAGE FOR RESIDENTIAL PROJECTS WITH ONE OR TWO UNITS REVISED JANUARY 4, 2018 COMMUNITY DEVELOPMENT DEPARTMENT POLICY DRAINAGE FOR RESIDENTIAL PROJECTS WITH ONE OR TWO UNITS REVISED JANUARY 4, 2018 A. California Residential Code Requirement - Construction plans shall indicate how

More information

TO BE FILLED OUT BY APPLICANT

TO BE FILLED OUT BY APPLICANT CITY OF BAINBRIDGE ISLAND CLEARING PERMIT APPLICATION FORM MUST BE COMPLETED IN INK, PREFERABLY BLUE. PENCIL WILL NOT BE ACCEPTED. DATE STAMP FOR CITY USE ONLY PROJECT NAME: TAX ASSESSOR S NUMBER(S): TO

More information

Appendix D - Technical Design Criteria for BMPs

Appendix D - Technical Design Criteria for BMPs Appendix D - Technical Design Criteria for BMPs City of Wayzata Page 3 On-site infiltration features Definitions and Scope: Infiltration facilities are constructed basins or depressions located in permeable

More information

MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS

MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS May 2007 SECTION 1 Responsibility of Applicant TABLE OF CONTENTS A. Stormwater Management Plan Required Information

More information

Stormwater Management Techniques WMPF LAND USE TRAINING INSTITUTE MARCH 14, 2018

Stormwater Management Techniques WMPF LAND USE TRAINING INSTITUTE MARCH 14, 2018 Stormwater Management Techniques WMPF LAND USE TRAINING INSTITUTE MARCH 14, 2018 Potential Impacts of New Development Urban development can significantly increase stormwater runoff Water quality considerations

More information

STORMWATER SITE PLAN INSTRUCTIONS AND SUBMITTAL TEMPLATE Medium and Large Projects

STORMWATER SITE PLAN INSTRUCTIONS AND SUBMITTAL TEMPLATE Medium and Large Projects DEPARTMENT OF COMMUNITY DEVELOPMENT 621 Sheridan Street, Port Townsend, WA 98368 Tel: 360.379.4450 Fax: 360.379.4451 Web: www.co.jefferson.wa.us/communitydevelopment E-mail: dcd@co.jefferson.wa.us STORMWATER

More information

Chapter 4 - Preparation of Stormwater Site Plans

Chapter 4 - Preparation of Stormwater Site Plans Chapter 4 - Preparation of Stormwater Site Plans The Stormwater Site Plan is the comprehensive report containing all of the technical information and analysis necessary for the City to evaluate a proposed

More information

PAVING PARKING AREAS AND ROADS DESCRIPTION. Alternate Names: Pavement Practices, Impervious Paving

PAVING PARKING AREAS AND ROADS DESCRIPTION. Alternate Names: Pavement Practices, Impervious Paving 4.2-i PAVING PARKING AREAS AND ROADS Alternate Names: Pavement Practices, Impervious Paving DESCRIPTION All roads, driveways, and parking lots proposed for year-round use shall be paved with a hard plowable

More information

STORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE

STORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE STORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE Codes analyses for each subcommittee were completed to assist participants of the Richland County Site Planning Roundtable.

More information

4. CONCEPT PLAN DEVELOPMENT

4. CONCEPT PLAN DEVELOPMENT 4. CONCEPT PLAN DEVELOPMENT Concept Plan Step 1: Identify Site Constraints and Opportunities Review the existing site to identify constraints and opportunities for GI Practices to meet the RRv. Constraints

More information

Insert Community Name. Homeowner Guide for On-Site Stormwater BMP Maintenance and Care

Insert Community Name. Homeowner Guide for On-Site Stormwater BMP Maintenance and Care Insert Community Name Homeowner Guide for On-Site Stormwater BMP Maintenance and Care Insert Community Name Homeowner Guide for On-Site Stormwater BMP Maintenance and Care Hello! Welcome to the neighborhood.

More information

General Information. Site Conditions. 9b 9b. 9a 1b. Best Management Practices Illustration

General Information. Site Conditions. 9b 9b. 9a 1b. Best Management Practices Illustration Model Construction SWPPP Planning & Development Services 1800 Continental Place Mount Vernon WA 98273 voice 360-416-1320 inspections 360-416-1330 www.skagitcounty.net/stormwaterpermitting Permit #: General

More information

Appendices: Glossary. General Terms. Specific Terms. Low Impact Development Approaches Handbook

Appendices: Glossary. General Terms. Specific Terms. Low Impact Development Approaches Handbook 67 67 General Terms Specific Terms 66 Low Impact Development Approaches Handbook The vocabulary of low impact development is evolving, and many terms are used interchangeably and to describe the same or

More information

Slow it, Spread it, Sink it using Green Stormwater Infrastructure

Slow it, Spread it, Sink it using Green Stormwater Infrastructure Milly Archer Water Resources Coordinator Becky Tharp Green Infrastructure Collaborative Slow it, Spread it, Sink it using Green Stormwater Infrastructure Overview Defining LID and GSI Hydrology and impacts

More information

City of Stoughton Erosion Control Permit Application (effective 2/6/2018)

City of Stoughton Erosion Control Permit Application (effective 2/6/2018) City of Stoughton Erosion Control Permit Application (effective 2/6/2018) Incomplete applications will not be accepted Project Name: Address of subject property: Landowner Name(s): Applicant Name: Landowner

More information

Draft Rhode Island Stormwater Design and Installation Standards Manual

Draft Rhode Island Stormwater Design and Installation Standards Manual Draft Rhode Island Stormwater Design and Installation Standards Manual Summary The May 2009 Public Review Draft version of the RI Stormwater Design and Installation Standards Manual consists of approximately

More information

4.6. Low Impact and Retentive Grading

4.6. Low Impact and Retentive Grading 4.6. Low Impact and Retentive Grading Low Impact Grading techniques focus on utilizing existing topography during Site layout to minimize cost. Proposing structures, roads, and other impervious surfaces

More information

6.1 Bioretention Areas

6.1 Bioretention Areas SAN MATEO COUNTYWIDE WATER POLLUTION PREVENTION PROGRAM 6.1 Bioretention Areas Figure 6-1. Bioretention Area. Source: City of Brisbane Bioretention areas 1, or rain gardens, are concave landscaped areas

More information

Key elements : Filter Strips must be designed within parameters required by the Fort Wayne s Development Standards/Criteria Manual.

Key elements : Filter Strips must be designed within parameters required by the Fort Wayne s Development Standards/Criteria Manual. 4.4. Filter Strips Filter Strips are densely vegetated lands that treat sheet flow storm water from adjacent pervious and impervious areas. They function by slowing runoff, trapping sediment and pollutants,

More information

WHATCOM COUNTY LID CODE INTEGRATION PROJECT WCC (DEFINITIONS)

WHATCOM COUNTY LID CODE INTEGRATION PROJECT WCC (DEFINITIONS) Chapter 20.97 DEFINITIONS Sections: 20.97.029 Best management practice (BMP). 20.97.171.1 Hard surface. 20.97.171.1 2 Hazard tree. 20.97.187 Impervious surface. 20.97.194.1 Land disturbing activity. 20.97.220.1

More information

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT NOT WELL 800 - Urban Stormwater Wetlands A constructed system of shallow pools that create growing conditions for wetland plants to lessen the impacts of stormwater quality and quantity in urban areas.

More information

High Point Community: Site Drainage Technical Standards. High Point Community Site Drainage Technical Standards

High Point Community: Site Drainage Technical Standards. High Point Community Site Drainage Technical Standards High Point Community Site Drainage Technical Standards Prepared by SvR Design Company for High Point Community Seattle, Washington 5/2004 Revised 12/2006 101 Acknowledgements: for innovative development

More information

Beyond Rain Gardens Advancing the Use of Compost for Green Infrastructure, Low Impact Development, & Stormwater Management

Beyond Rain Gardens Advancing the Use of Compost for Green Infrastructure, Low Impact Development, & Stormwater Management Beyond Rain Gardens Advancing the Use of Compost for Green Infrastructure, Low Impact Development, & Stormwater Management VORS 2018 Stormwater Management Session 2 Stormwater Management, Green Infrastructure,

More information

State of Rhode Island Stormwater Management Guidance for Individual Single-Family Residential Lot Development

State of Rhode Island Stormwater Management Guidance for Individual Single-Family Residential Lot Development State of Rhode Island Stormwater Management Guidance for Individual Single-Family Residential Lot Development Section 300.6 of the RI Coastal Resources Management Program (RICRMP) and Rule 7.12 of the

More information

SMALL PROJECTS SIMPLIFIED APPROACH

SMALL PROJECTS SIMPLIFIED APPROACH SMALL PROJECT APPLICATION AND STORMWATER MANAGEMENT DESIGN ASSISTANCE MANUAL FOR SMALL PROJECTS IN FULTON TOWNSHIP LANCASTER COUNTY, PENNSYLVANIA SMALL PROJECTS SIMPLIFIED APPROACH Prepared By: Light-Heigel

More information

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion Topics Erosion, TESC and Construction sequencing Procedures and timing Remedies for failing sites Curtis Hinman WSU Extension and Bio Systems Eng. Faculty Low Impact Development Specialist chinman@wsu.edu

More information

Structural Stormwater Best Management Practices

Structural Stormwater Best Management Practices Structural Stormwater Best Management Practices for Small Commercial and Residential Applications Timothy Bruno Watershed Manager PA Department of Environmental Protection What are STRUCTURAL BMPs? Physical

More information

Homeowners Guide to Stormwater BMP Maintenance

Homeowners Guide to Stormwater BMP Maintenance Homeowners Guide to Stormwater BMP Maintenance What You Need to Know to Take Care of Your Property Rain Barrel Dry Well Rain Garden Pervious Asphalt Porous Pavers City of El Monte Stormwater BMP Management

More information

Worksheet #14 Water Runoff Management

Worksheet #14 Water Runoff Management Water Runoff Management Use this worksheet to assess how well your property minimizes the potential for water runoff and property damage.. Why should you be concerned? What can you do? Rural runoff, also

More information

Title 11 Streets and Sidewalks

Title 11 Streets and Sidewalks Chapter 11.01 - Definitions Title 11 Streets and Sidewalks Low Impact Development (LID) - A stormwater and land use management strategy that strives to mimic predisturbance hydrologic processes of infiltration,

More information

Vegetated Filter Strips and Buffers

Vegetated Filter Strips and Buffers 3.15 Sediment Control Description: Buffer strips (existing vegetation) and filter strips (planted vegetation) are sections of vegetated land adjacent to disturbed areas. They are designed with low slopes

More information

SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL

SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL Standard Operating Procedures Central Massachusetts Regional Stormwater Coalition SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL Erosion and sedimentation from land-disturbing

More information

BMP Suitability Matrix

BMP Suitability Matrix Green Infrastructure Across the Urban to Rural Spectrum Guidance document for how to use the BMP Suitability Matrix. BMP Suitability Matrix A User s Guide to Green Infrastructure Best Management Practices

More information

DECLARATION OF COVENANT FOR IMPERVIOUS SURFACE LIMIT

DECLARATION OF COVENANT FOR IMPERVIOUS SURFACE LIMIT RECORDING REQUESTED BY AND WHEN RECORDED MAIL TO: DECLARATION OF COVENANT FOR IMPERVIOUS SURFACE LIMIT Grantor: _ Grantee: King County Legal Description: Additional Legal(s) on: Assessor's Tax Parcel ID#:

More information

Vegetated Filter Strips and Buffers

Vegetated Filter Strips and Buffers 3.15 Sediment Control Description: Buffer strips (existing vegetation) and filter strips (planted vegetation) are sections of vegetated land adjacent to disturbed areas. They are designed with low slopes

More information

Stormwater Control Plan: Small (Tier 1) Land Development Project

Stormwater Control Plan: Small (Tier 1) Land Development Project Stormwater Control Plan: Small (Tier 1) Land Development Project Project ID for Tracking (for City Staff only): The California Regional Water Quality Control Board for the Central Coast Region (Water Board)

More information

CHAPTER 11 SITE DESIGN AND LOW IMPACT DEVELOPMENT

CHAPTER 11 SITE DESIGN AND LOW IMPACT DEVELOPMENT CHAPTER 11 SITE DESIGN AND LOW IMPACT DEVELOPMENT Source: City of Bend Chapter Organization 11.1 Purpose... 11-1 11.2 Applicability... 11-1 11.3 Low Impact Development Overview... 11-2 11.3.1 Key Strategies...

More information

Appendix I. Checklists

Appendix I. Checklists Appendix I Checklists Town of Greenwich Drainage Manual Department of Public Works - Engineering Division Town Hall - 101 Field Point Road, Greenwich, CT 06836-2540 Phone 203-622-7767 - Fax 203-622-7747

More information

ST. MARY S SOIL CONSERVATION DISTRICT (SMSCD) AND DPW&T CONCEPT EROSION AND SEDIMENT CONTROL AND STORMWATER MANAGEMENT GUIDELINES AND CHECKLIST

ST. MARY S SOIL CONSERVATION DISTRICT (SMSCD) AND DPW&T CONCEPT EROSION AND SEDIMENT CONTROL AND STORMWATER MANAGEMENT GUIDELINES AND CHECKLIST St. Mary s Soil Conservation District 26737 Radio Station Way, Suite B Leonardtown, MD 20650 Phone: 301-475-8402 ext. 3 Fax: 301-475-8391 www.stmarysscd.com St. Mary s County Government Department of Public

More information

6.2 Flow-Through Planter

6.2 Flow-Through Planter SAN MATEO COUNTYWIDE WATER POLLUTION PREVENTION PROGRAM 6.2 Flow-Through Planter Figure 6-8: At-grade flow-through planter. Source: City of Emeryville Best uses Treating roof runoff Next to buildings Dense

More information

ABBREVIATIONS: TABLE OF CONTENTS: REFERENCE MATERIALS: CITY OF SEATTLE COMBINED SEWER OVERFLOW GALLONS PER MINUTE POLYVINYL CHLORIDE SQUARE FEET

ABBREVIATIONS: TABLE OF CONTENTS: REFERENCE MATERIALS: CITY OF SEATTLE COMBINED SEWER OVERFLOW GALLONS PER MINUTE POLYVINYL CHLORIDE SQUARE FEET TABLE OF CONTENTS: ABBREVIATIONS: SHEET NO. A SHEET DESCRIPTION REFERENCE SHEETS TITLE SHEET COS CSO GPM PVC SF CITY OF SEATTLE COMBINED SEWER OVERFLOW GALLONS PER MINUTE POLYVINYL CHLORIDE SQUARE FEET

More information

Post Construction BMPs

Post Construction BMPs Post Construction BMPs Why are Post Construction BMPs important? With increased development brings the increase of impervious cover Parking lots, rooftops, driveways Storm water runoff volume increases

More information

Volume 6 - Low Impact Development. Table of Contents

Volume 6 - Low Impact Development. Table of Contents City of Tacoma Volume 6 - Low Impact Development Table of Contents Purpose of this Volume............................................................6-1 Content and Organization of this Volume..............................................6-1

More information

County of Prince Edward. Stormwater Management Plan. Agreement in lieu of a Stormwater Management Plan

County of Prince Edward. Stormwater Management Plan. Agreement in lieu of a Stormwater Management Plan County of Prince Edward Stormwater Management Program Date: E-Permitting Number: This stormwater management plan (Agreement) is hereby submitted by the Owner to specify the methods that will be implemented

More information

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance. The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language

More information

Infiltration. Keep Water Where it Falls. Frank Franciosi Novozymes

Infiltration. Keep Water Where it Falls. Frank Franciosi Novozymes Keep Water Where it Falls Frank Franciosi Novozymes Defined refers to the movement of water into the soil layer. The rate of this movement is called the infiltration rate. If rainfall intensity is greater

More information

Post - Construction Hydromodification Development Requirements

Post - Construction Hydromodification Development Requirements Condensed Version - Interim Low Impact Development / Hydromodification Guidelines, City of Lompoc 1 Post - Construction Hydromodification Development Requirements I. PURPOSE A. The purpose of these requirements

More information

Urban Water Management (ESRM 311 & SEFS 507) Cougar Mtn Regional Wildland Park & Lakemont Blvd, Bellevue WA

Urban Water Management (ESRM 311 & SEFS 507) Cougar Mtn Regional Wildland Park & Lakemont Blvd, Bellevue WA Urban Water Management (ESRM 311 & SEFS 507) Cougar Mtn Regional Wildland Park & Lakemont Blvd, Bellevue WA Lecture Today Urban Water management terms Examples of water management in urban areas Field

More information

4.5 City of Indianapolis Stormwater Green Infrastructure Guidance: Bioretention (rain gardens) Bioretention Fact Sheet Bioretention Technical Design

4.5 City of Indianapolis Stormwater Green Infrastructure Guidance: Bioretention (rain gardens) Bioretention Fact Sheet Bioretention Technical Design 4.5 City of Indianapolis Stormwater Green Infrastructure Guidance: Bioretention (rain gardens) Bioretention Fact Sheet Bioretention Technical Design Specification Bioretention O & M Manual Draft Green

More information

Project: Developer/Designer: Reviewer: I. Narrative: 1. Project Description: Describes the nature and purpose of the land disturbing activity.

Project: Developer/Designer: Reviewer: I. Narrative: 1. Project Description: Describes the nature and purpose of the land disturbing activity. City of Charlottesville, Virginia Erosion and Sediment Control Plan Review Checklist 610 East Market Street, Charlottesville, VA 22902 Telephone 434-970-3182; Fax 434-970-3359 Project: Developer/Designer:

More information

Background on LID in Western WA

Background on LID in Western WA Low Impact Development Process (MR #5) Douglas C. Howie, P.E. Department of Ecology Background on LID in Western WA PCHB Requirements from 2007 Permits Two LID Advisory Committees Expanded MR #5 LID Performance

More information

SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS

SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS Introduction As required by federal and state law, the Borough of Swarthmore has adopted regulations that affect stormwater runoff and surface

More information

STORM WATER MANAGEMENT PLAN APPLICATION Manheim Borough

STORM WATER MANAGEMENT PLAN APPLICATION Manheim Borough STORM WATER MANAGEMENT PLAN APPLICATION Manheim Borough DATE Application is hereby made to Manheim Borough for the issuance of a Storm Water Management Plan approval pursuant to the Manheim Borough Storm

More information

Urban Water Management and Soils (ESRM 311 & SEFS 507)

Urban Water Management and Soils (ESRM 311 & SEFS 507) Urban Water Management and Soils (ESRM 311 & SEFS 507) Cougar Mtn Regional Wildland Park & Lakemont Blvd, Bellevue WA Lecture Today Some Urban Water management terms Examples of water management in urban

More information

Chapter 14. Stormwater Quality Introduction

Chapter 14. Stormwater Quality Introduction 14.0 Introduction This chapter addresses requirements and design criteria related to post-construction stormwater best management practices (requirements for construction erosion and sediment control are

More information

HIGHLAND LAKES WATERSHED ORDINANCE WATER QUALITY MANAGEMENT TECHNICAL MANUAL

HIGHLAND LAKES WATERSHED ORDINANCE WATER QUALITY MANAGEMENT TECHNICAL MANUAL Effective July 1, 2007 HIGHLAND LAKES WATERSHED ORDINANCE WATER QUALITY MANAGEMENT TECHNICAL MANUAL EFFECTIVE JULY 1, 2007 FIFTH EDITION Lower Colorado River Authority TABLE OF CONTENTS DESIGN SPREADHEET

More information

Drainage Control Plans

Drainage Control Plans 2016 Drainage Design and Erosion Control Manual - Guide Sheet 1C Drainage Control Plans A Drainage Control Plan is the comprehensive submittal package containing all of the technical information, analysis,

More information

Table of Contents. Preface... xv

Table of Contents. Preface... xv Table of Contents Preface... xv Objective... xv Organization of this Manual...xvi How to Use this Manual...xvii Development of Best Management Practices (BMPs) for Stormwater Management...xviii Best Management

More information

DRAFT DESIGN CRITERIA STORMWATER TREATMENT STANDARDS CITY OF OVERLAND PARK

DRAFT DESIGN CRITERIA STORMWATER TREATMENT STANDARDS CITY OF OVERLAND PARK DRAFT DESIGN CRITERIA STORMWATER TREATMENT STANDARDS CITY OF OVERLAND PARK A. Authority As set forth in the Overland Park Municipal Code (OPMC), Chapter 16.210, the Director of Planning and Development

More information

A P P E N D I X D. Project Stormwater Plan Worksheets

A P P E N D I X D. Project Stormwater Plan Worksheets A P P E N D I X D Worksheets for Section 1: Basic Project Information This worksheet must be filled out for all projects required to implement the 2015 Post- Construction Stormwater Standards Manual. A

More information

Erosion & Sediment Control Plan Application Form & Checklist

Erosion & Sediment Control Plan Application Form & Checklist Erosion & Sediment Control Plan Application Form & Checklist GENERAL INFORMATION Application Date: Project Address: Tax Map / Parcel Number(s): PROPERTY OWNER / DEVELOPER Firm Name: Contact Person: Title:

More information

Zoning Regulation Amendments Adopted December 19, 2018 effective date January 7, 2019

Zoning Regulation Amendments Adopted December 19, 2018 effective date January 7, 2019 Zoning Regulation Amendments Adopted December 19, 2018 effective date January 7, 2019 Article 2 General Provisions Section 2.2 Definitions Definitions- FIRE LANE The aisle immediately adjacent to a building

More information

RAIN GARDEN ILLINOIS URBAN MANUAL PRACTICE STANDARD. (feet) CODE 897 DEFINITION

RAIN GARDEN ILLINOIS URBAN MANUAL PRACTICE STANDARD. (feet) CODE 897 DEFINITION ILLINOIS URBAN MANUAL PRACTICE STANDARD RAIN GARDEN (feet) CODE 897 Source: Kendall County Soil and Water Conservation District DEFINITION Rain gardens are small, shallow, flat bottomed depressions constructed

More information

J. Paul Guyer, P.E., R.A.

J. Paul Guyer, P.E., R.A. J. Paul Guyer, P.E., R.A. Paul Guyer is a registered civil engineer, mechanical engineer, fire protection engineer, and architect with over 35 years experience in the design of buildings and related infrastructure.

More information

Huntington Stormwater Utility

Huntington Stormwater Utility Huntington Stormwater Utility Stormwater Management & Sediment and Erosion Control Requirements for Construction Sites Authorized by Huntington City Code Articles: 971, 970, 930, 935, 955, Revised April

More information

Stormwater Drainage Assessment For Single Family Residence

Stormwater Drainage Assessment For Single Family Residence Stormwater Drainage Assessment For Single Family Residence Project Name: SEADER SFD Project Address: 2301 NE Perkins Way, Lake Forest Park, King County WA. Parcel Number(s): Tax Parcel No. 86659-00181

More information

Preventing Storm Water Pollution

Preventing Storm Water Pollution Storm Water Runoff occurs during rainfall events or snow melt, causing 1000s of gallons of storm water to enter the City of Belpre s storm drain system. The storm drain system is made up of catch basins,

More information

Small Project Guidance Document

Small Project Guidance Document Small Project Guidance Document Introduction If you are considering a relatively small construction project on your property that creates new impervious area and you need to manage the stormwater that

More information

STORMWATER GREEN INFRASTRUCTURE AND PLANNING/ZONING BOARDS

STORMWATER GREEN INFRASTRUCTURE AND PLANNING/ZONING BOARDS STORMWATER GREEN INFRASTRUCTURE AND PLANNING/ZONING BOARDS Source: Center for Watershed Protection, 2007 Southern Tier Central Regional Planning & Development Board Chemung County Stormwater Team OUTLINE

More information

Erosion Control for Home Builders in the. City of Jacksonville

Erosion Control for Home Builders in the. City of Jacksonville Erosion Control for Home Builders in the City of Jacksonville Eroding construction sites are a leading cause of water quality problems in Jacksonville. For every acre under construction, about a dump truck

More information

WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES

WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES Greenville County Technical Specification for: WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES 1.0 Mountainous and Steep Slope Sites 1.1 Description The geographic locations of portions of Greenville County are

More information

Example Stormwater Control Plan For a Residential Subdivision Project. Whispering Pines Lane Anytown, USA. February 21, 2018

Example Stormwater Control Plan For a Residential Subdivision Project. Whispering Pines Lane Anytown, USA. February 21, 2018 Example Stormwater Control Plan For a Residential Subdivision Project Whispering Pines Lane Anytown, USA February 21, 2018 XYZ Corporation Jane Jones, 925-555-1212 This example prepared by Dan Cloak Environmental

More information

Preventing Storm Water Pollution

Preventing Storm Water Pollution Storm Water Runoff occurs during rainfall events or snow melt, causing 1000s of gallons of storm water to enter the City of Belpre s storm drain system. The storm drain system is made up of catch basins,

More information

SOIL EROSION AND SEDIMENT CONTROL

SOIL EROSION AND SEDIMENT CONTROL SOIL EROSION AND SEDIMENT CONTROL SECTION 1: AUTHORITY, TITLE AND PURPOSE 11. STATUTORY AUTHORIZATION This ordinance is adopted pursuant to the provisions of the Federal Water Pollution Control Act 86

More information

WATER QUALITY IMPACT ASSESSMENT (WQIA) FORM

WATER QUALITY IMPACT ASSESSMENT (WQIA) FORM WATER QUALITY IMPACT ASSESSMENT (WQIA) FORM Name: CCW Development Associates, L.L.C. Street Address: Telephone Number(s): 1209 Laskin Road, Virginia Beach, VA 23451 (757) 491-1996 Email: chris@vbhomesliving.com

More information

NON-PRIORITY PROJECT WATER QUALITY PLAN (NPP)

NON-PRIORITY PROJECT WATER QUALITY PLAN (NPP) NON-PRIORITY PROJECT WATER QUALITY PLAN (NPP) For: (Insert Project Name) (Site Address or Tract/Lot Number) Prepared for: (Insert Owner/Developer Name) (Insert Address) (Insert City, State, ZIP) (Insert

More information

Community LID Workgroup Issue Paper #6

Community LID Workgroup Issue Paper #6 Community LID Workgroup Issue Paper #6 Topic: Hard and Impervious Surface Coverage Limits Objective: Minimize the amount of hard and impervious surfaces in developments to allow more stormwater to infiltrate

More information

West Norriton Township

West Norriton Township West Norriton Township Earth Disturbance and Drainage Permit Application 1630 W. Marshall Street Norristown, PA 19403 Phone: (610) 631-0450 Fax: (610) 630-0304 www.westnorritontwp.org A stormwater permit

More information

Low Impact Development Guidance Manual

Low Impact Development Guidance Manual May 2009 TABLE OF CONTENTS Section 1 Introduction 1 Overview 2 Definitions 4 2 Conservation Design Practices 5 Cluster Development 6 Minimize Pavement Widths 8 Minimize Setbacks & Frontages 10 Open Space

More information

SEATTLE PUBLIC UTILITIES Drainage Design Options for street right of ways.

SEATTLE PUBLIC UTILITIES Drainage Design Options for street right of ways. SEATTLE PUBLIC UTILITIES Drainage Design Options for street right of ways. Numerous ecosystem-based functional stormwater quantity and quality design alternatives are possible within the street ROW. Several

More information

Introduction Post Construction Stormwater Management Performance Requirements

Introduction Post Construction Stormwater Management Performance Requirements Introduction Post Construction Stormwater Management Performance Requirements The primary objective of these Post Construction Stormwater Management Performance Requirements is to minimize the downstream

More information

City of Waco Stormwater Management Regulations

City of Waco Stormwater Management Regulations 1.0 Applicability: City of Waco Stormwater Management Regulations These regulations apply to all development within the limits of the City of Waco as well as to any subdivisions within the extra territorial

More information

SECTION PLANTING SOIL for SOIL CELLS. This specification defines material and performance requirements for soils which are to be used

SECTION PLANTING SOIL for SOIL CELLS. This specification defines material and performance requirements for soils which are to be used This specification defines material and performance requirements for soils which are to be used within the Silva Cell system. The SPECIFICATION EDITOR must select the type of soil appropriate to each particular

More information