1 Preliminary Construction & Traffic Planning Intro to Shop Local/Shop Eglinton Initiative June 27, 2012
2 Agenda Introductions Project Update Preliminary Crosstown Construction & Traffic Planning Overview Tunnelling Process Stations Allen Road Shop Eglinton, Shop Local Initiative Q&A, Discussion and Next Steps 7/3/2012 ning
3 The Crosstown Final number and location of stations subject to Provincial review 60% faster than current bus routes 7 minutes from Eglinton West Station (Allen Road) to Yonge Street
4 Update The first Tunnel Contract (Keele St to Yonge St) will be awarded this summer Detailed traffic plans will be developed after the contract is awarded Additional public meetings in Fall 2012 to discuss detailed construction plans for the first tunnelling contract The earliest utility work could begin on Eglinton in the vicinity of Allen Road is late 2012 Allen southbound & Keele Street)
5 Tunnel Construction Principles Package contracts to coordinate all work under same umbrella (utilities, city, transit) Maintain a minimum of one lane eastbound and westbound on Eglinton in construction zones Access to buildings from Eglinton remains open Only propose road closures if required for safety reasons or to provide exceptional time savings and reduction to long term disruption
6 Eglinton Bus Ridership Eglinton 32 & 34 buses carry 68,500 riders every weekday Transfers required at Eglinton West and Eglinton Stations (Allen & Yonge) Eglinton has amongst the highest ridership of all bus routes 6
7 Eglinton at Bathurst (looking west) 7
8 Eglinton West Station 8
9 Looking east from Oakwood 9
10 Crosstown Construction Update Tunnel preparation work at Black Creek and Eglinton in Keelesdale Park Piling rigs are building concrete support walls for the future west tunnel launch shaft The west launch shaft will enable tunnelling works in late 2012 towards Allen Road
11 West Launch Shaft Keelesdale Park near Black Creek Drive Launch Shaft 60m long 20m wide 16m deep
12 Tunnel Construction Overview Relocate utilities at major intersections to maintain services (gas, water, cable) Construct headwalls (support walls formed by a series of concrete columns) at east and west ends of each future station location months per station location - Process called Jet Grouting when soil conditions allow 3-4 months Concurrently, construct Tunnel launch and extraction shafts The tunnel machines are launched from Keelesdale Park (just west of Keele Street) and tunnel eastward through the station headwalls
13 Jet Grouting - Headwalls Typical Rig Jet Grouting Process 2 3m Diameter Jet Grout Formed Soilcrete Columns
14 Tunnel Construction Overview Continued To maintain Subway Service throughout construction, tunnelling machines are extracted at the west side of Allen Road on Eglinton and re-launched from a new pit on the east side of Allen Road on Eglinton Tunnelling proceeds to Yonge Street, and a second extraction pit is built to remove and re-furbish the machines before they reach Eglinton Station Following this tunnelling work, the Crosstown Stations between Keele and Yonge will be constructed Stations will each take approximately 4 years to construct
15 Utility Relocation
16 Utilities - Bathurst Intersection STACKED SANITARY SEWERS 600mm WATERMAIN 1125mm STORM SEWER BELL/ROGERS CONDUITS (2) 225mm SANITARY SEWER EGLINTON AVENUE WEST PEVERIL HILL NORTH T.H.E.S. DUCT BANK (12) TELUS/GT DUCT BANK (18) 150mm GASMAIN (ABANDONED) 300mm COMBINED SEWER BATHURST STREET 300mm GASMAIN (TO BE ABANDONED) BELL/ROGERS CONDUITS (20) STACKED SANITARY SEWERS EXISTING STORM SEWER EXISTING SANITARY SEWER EXISTING WATERMAIN EXISTING COMBINED SEWER EXISTING GASMAIN EXISTING BELL/ROGER CONDUIT EXISTING TELUS/GT CONDUIT EXISTING T.H.E.S./COGECO DUCT BANK 7/3/2012
17 Challenge of Underground Utilities
18 Tunnel Drive Sequence Launch Shaft
19 Tunnel Drive Sequence Extraction Shaft
20 Tunnel Drive Sequence Leading Tunnel Trailing Tunnel
21 Tunnel Drive Sequence Station Headwalls
22 Tunnel Drive Sequence Mine-Through Headwalls
23 Extraction Shaft Example Spadina Subway Extension - Keele and Finch
24 Extraction Shaft Example Spadina Subway Extension - Keele south of Finch
25 Eglinton and Allen - Existing
26 Utility Relocation Work Exact Lane Setup TBD Minimum one through lane in each direction on Eglinton Aiming to provide 3 rd lane when safe to do so
27 Extraction & Launch Shaft Preparation Exact Lane Setup TBD
28 Extract TBM & Re-Launch (Ensure Subway Service is Maintained)
29 Soil removal for Tunnelling cubic metres of soil to be removed during tunnelling Enough to fill the ACC rink higher than the CN Tower
30 West Tunnelling Keele Street to Yonge Street Preliminary Traffic Management Overview
31 Existing Conditions on Eglinton Rush Hours : 7am to 9am & 4pm to 6pm Most sections from Keele to Allen have one lane in each direction for general traffic in rush hours Most sections from Allen to Yonge have two lanes in each direction available for general traffic in rush hours In most sections during rush hours, the curb lane is for buses/taxis only Outside of rush hours, the curb lanes are used for on-street parking, generally leaving one lane per direction for moving traffic
32 Traffic Origin Eglinton Avenue Dufferin to Chaplin External traffic represents 45% of the auto trips (AM peak) 45% of traffic has an origin and destination outside the area & use Eglinton as a traffic corridor in AM peak PM peak period is similar, 42% external, 58% local
33 During Tunnel Construction One lane of traffic available on Eglinton both EB and WB all-day in active construction zones. Buses and general traffic will share this lane. Advance warning signs will be placed in the vicinity of the corridor. Changeable Message Signs and Static Signs.
34 Transit Services during Tunnel Construction Pedestrian and bus access to Eglinton West and Eglinton Stations will remain open Some local bus route detours may be required for key tunnelling activities (e.g. tunnel extraction shaft near Duplex Avenue) Eglinton buses will be monitored and additional buses added as needed to respond to changes in traffic conditions
35 Parking Currently, 3 hour paid parking is available on Eglinton Avenue West outside of weekday rush hours. In order to provide space for construction work, some of these spaces will be unavailable One-hour parking on some local roads will be extended to 3 hours, only while construction is impacting parking availability on Eglinton Avenue Parking on local roads will be enforced to discourage long-term parking and will be closely monitored by Toronto Police Services Parking Enforcement
36 Pedestrians/ Cyclists Front door access to Eglinton Avenue buildings maintained Minimum 1.5 metre sidewalk widths Some temporary closures of sections of sidewalk required. Where necessary, crossings will be available at traffic signals. One side open at all times. Bike lanes not currently provided on Eglinton During construction, cyclists will continue to share general traffic lanes Where space is available, wider lanes provided to accommodate all users
37 Allen Road Area Detailed Traffic management plans will be developed upon award of tunnel contract and presented at Fall 2012 follow-up meeting 2013 Potential for occasional, off peak (overnight) Southbound Right Turn prohibitions from Allen to Eglinton for utility relocations at Extraction Shaft Potential short duration Eastbound to Northbound left turn prohibitions from Eglinton onto Allen Road for decking installation at ramp
38 Allen Road Proposed Closure to Northbound Access at Eglinton in 2014 Potential closure of northbound access to Allen Road at Eglinton to expedite tunnelling Closure projected to reduce construction by approximately one year Northbound Allen access would remain open at Lawrence Closure would give contractor enough space for construction staging and movement of 150 trucks per day directly onto Allen Road All prohibitions at Allen Road require City Council approval Anticipated report timing is FALL 2012 Public Works Committee/City Council
39 Tunnel Launch Shaft Sheppard Subway Example at Leslie
40 13 Division Working with Police Temporary Property Requirements 5 metre area between sidewalk and 13 Division building Utility construction area Temporary sidewalk Tree removals are unavoidable Sign removal/ relocation Tiebacks
41 Cross Passages Cross passages are used for emergency evacuation of the tunnels and for access between the tunnels for maintenance Constructed by hand mining between the two tunnels Area needed on road for pumping equipment to dewater the area where the mining is conducted Bathurst to Yonge: Jet grouting is required. Street occupation similar to station headwalls Impact = 2-3 months per location 1 lane per direction
42 Temporary Local Road Closures at Eglinton Avenue Temporary closures at Eglinton intersections with some local streets will unfortunately be required during different phases of tunnel construction to safely complete work: Yarrow Road ( weeks) Kane Avenue ( weeks) Little Boulevard ( days) Strathearn Road ( Weeks) Flanders Road ( Weeks) Peveril Hill North Road ( Weeks) Chaplin Crescent Southbound Thru & Left ( Weeks) Latimer Avenue ( Weeks) Highbourne Road ( Weeks) Maxwell Avenue ( Weeks)
43 Station Construction Overview Projected Start 2015 After tunneling is completed, station construction begins
44 Eglinton Pre-Construction - Existing Right of Way Use Watermain
45 Station Construction Stage 1A Piling - Divert Traffic & Construct Support of Excavation (Exact Construction Set-Up TBD by Location for all stages) Watermain
46 Station Construction Stage 1B Construct Centre Piles Watermain
47 Station Construction Stage 2A - Construct Roadway Decking on one Side Watermain
48 Station Construction Stage 2B Construct opposite side Decking & Support of Excavation Watermain
49 Station Construction Stage 3: Construct Station Box under the Roadway Decking Watermain
50 Station Construction Station Complete Restore Roadway, Utilities & Traffic Watermain
51 Monitoring Construction Noise & Vibration Noise levels monitored and must comply with City of Toronto Noise by-law Noise by-law allows: Civil construction 7 am to 11 pm, 7 days per week Continuous underground tunnelling work Sound barrier to be installed in TTC East Commuter Parking Lot Vibration levels monitored and must comply with Municipal Code section If limits exceeded, contractor required to take action to reduce noise and vibration to within specified limits ning
52 Future Shop Eglinton Program to Support Local Businesses Grassroots program to be developed for 2013 to support local businesses through construction Local business & community involvement for brainstorming Sign-up tonight to become involved & Support your Business Improvement Areas 7/3/2012 ning
53 Next Steps a) Fall Meetings in advance of construction (Review and input on traffic and construction staging plans) b) Construction Liaison Groups Smaller groups (10 local representatives per station with local councillor) give input, questions & concerns directly to construction team c) Contact Community Liaisons with specific local issues & recommendations for investigation as well as for meetings
54 The Crosstown Team Please Get in Touch with Us! Devin Horne, Franca Di Giovanni, Denise Jayawardene Online: Tel: Fax: TTY: Visit our West Community Office at 1848 Eglinton Avenue West (at Dufferin) Community Office Hours 2012 Monday, Wednesday, Friday: 9:00 a.m. 5:00 p.m. Tuesday & Thursday: by appointment
55 THANK YOU
56 Additional Information
57 Extract TBM & Re-Launch (Future LRT concept under Subway)
58 Additional Background Information
59 Approach to Traffic Management Existing Conditions as Baseline vs. Construction Conditions Pedestrians, vehicles, & transit (allocation of space) Level of service at signalized intersections Levels of through traffic vs. local traffic On-street Parking Strategy Strategies Adjustments to signal timing Monitoring and preventing local infiltration through residential streets Signage program across City and nearby 400 series Highways
60 Traffic Study Methodology City of Toronto Planning Department participates in Transportation Tomorrow Survey of travel patterns in Toronto and the GTA (5% sampling of GTA households approximately 150,000 interviews) Data reflects trip origin and destination information Intersection turning movement counts from City of Toronto Reviewed City of Toronto Transportation Model Undertook counts at un-signalized intersections where counts were not available Analysis with specialized transportation software using established methodology
61 Existing Conditions Dufferin to Chaplin & Chaplin to Yonge Existing capacity constraints Dufferin to Chaplin Westbound Eglinton to southbound Oakwood (PM peak) Allen Road southbound off-ramp during AM peak Northbound left at Spadina Road and Eglinton during PM peak
62 Pedestrians & Transit Pedestrian Activity Ensure safe crossing spaces Re-routings when necessary with effective signage Between Allen and Chaplin increased pedestrian activity is found at key points such as Allen Road and Bathurst street Allen Road SB 5027 pedestrian crossing during peak 8 hours Bathurst has 3788 pedestrian crossings during peak 8 hours Transit Service & Bus ridership Maintain efficient service throughout construction for daily Eglinton bus riders Bus ridership on the 7 Bathurst 3000 daily commuters through the intersection
63 Ministry of Transportation (MTO) Highway 401 /Allen Road Ramp Improvements MTO is rehabilitating 8 structures in the Highway 401 and Allen Road Interchange Bridge improvements have been broken into 2 contracts Contract 1 (Bridges 4 and 24) Contract 2 (Bridges 5, 6, 12, ) Construction for Contract 1 commenced in Spring 2012 Completion for Contract 1: late Fall 2012 Construction schedule for Contract 2 TBD
64 Ministry of Transportation (MTO) Highway 401 /Allen Road Ramp Improvements
65 MTO - Highway 401 /Allen Road Ramp Construction Details Lane reductions on the 401 to Allen Road ramps and bridges Periodic overnight ramp/bridge closures Advance traffic warning signs will be posted in the area to advise the public of traffic restriction and lane closures Construction is planned to take place during daytime hours from Monday to Friday Extended working hours (periodic night time work) & weekend work required to complete construction on schedule. Project information: Mr. Sam Molai, P.Eng., Senior Structural Engineer Ministry of Transportation, Central Region tel: Sam.Molai@ontario.ca Mr. Larry NG, Project Manager Design SNC Lavalin tel: Ext 2711
66 City of Toronto Long Term Planning Allen Road Environmental Assessment The City of Toronto is studying ways to improve Allen Road The study will follow a provincially mandated Environmental Assessment process. Study investigating current challenges and opportunities in the Allen Road corridor from Eglinton to just south of Transit Road Currently, a Terms of Reference (Study Framework/Work Plan) is being developed to guide future work
67 Allen Road Environmental Assessment For more information, please contact: Jason Diceman Tel: Web Site:
68 Diamond Lane Offpeak - East to Bathurst
Eglinton West/Allen Road Station Potential South Side Entrance Options. Online Consultation April 2 nd to April 16 th
Eglinton West/Allen Road Station Potential South Side Entrance Options Online Consultation April 2 nd to April 16 th Eglinton West/Allen Road Station Consultation #1 Most common comment: south side entrance
More informationTRANSPORTATION COMMITTEE
TRANSPORTATION COMMITTEE CITY OF OTTAWA Ministry of Transportation Detailed Design Assignment G.W.P.# 4058-01-00 Highway 417 (Ottawa Queensway) Widening & Rehabilitation from Maitland Avenue to Island
More information1 Metrolinx overview. Mission We connect our communities. Vision Getting you there better, faster and easier
Mission We connect our communities Vision Getting you there better, faster and easier Values Play as a team Think forward Serve with passion 1 Metrolinx overview go transit, up express, presto Serve a
More information2
CROSSTOWN LRT 2 3 4 5 6 Construction of the Eglinton Crosstown LRT Line Background In September 2008, Metrolinx launched a regional transportation plan a 25-year, $50 billion plan -- to coordinate and
More informationSt. Clair Avenue West Area Transportation Master Plan
1 (Between Keele Street and Old Weston Road) Public Information Centre 1 December 2, 2015 2 Welcome Welcome to the first Public Information Centre for the St. Clair Avenue West Area. The panels will present
More informationCoordinated Transit Planning in Toronto SmartTrack GO RER Scarborough Relief Line Waterfront Transit
Coordinated Transit Planning in Toronto SmartTrack GO RER Scarborough Relief Line Waterfront Transit Public Information Centres February 2016 Transportation Planning Section City Planning Division Toronto
More information2
CROSSTOWN LRT 2 3 4 5 6 Construction of the Eglinton Crosstown LRT Line Background In September 2008, Metrolinx launched a regional transportation plan a 25-year, $50 billion plan -- to coordinate and
More informationMavis Road Class Environmental Assessment
Mavis Road Class Environmental Assessment Public Information Centre #2 Wednesday November 9, 2016 6:00 to 8:00 p.m. Please sign in and complete a comment sheet Review the displays on your own or join in
More informationExpo Line Transit Project. Project Status Update Meeting West End Corridor Segment C
Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center November 18, 2010 Phase 1 Project Description Phase 1 from Downtown Los Angeles
More information3.5.7 Black Creek to Don Mills
Toronto Transit Commission/City of Toronto 3.5.7.2 Keele Station Keele Station will be located at the intersection of Eglinton Avenue and Trethewey Drive/Keele Street. It will be the western-most station
More informationWELCOME TO OPEN HOUSE TWO November 28, 2018
Langstaff Road Weston Road to Highway 7 Class Environmental Assessment Study WELCOME TO OPEN HOUSE TWO November 28, 2018 Please sign in and join our mailing list Study Overview York Region is conducting
More informationCOUNCIL ATTACHMENT 2 HIGHWAY 7 CORRIDOR AND VAUGHAN NORTH-SOUTH LINK
COUNCIL ATTACHMENT 2 HIGHWAY 7 CORRIDOR AND VAUGHAN NORTH-SOUTH LINK Welcome! The purpose today is to: Present the Study Background; Describe Alignment Alternatives Analyzed; Present the Evaluation of
More informationWELCOME TO OPEN HOUSE # 3
Bayview Avenue Class Environmental Assessment Study Steeles Avenue to Elgin Mills Road WELCOME TO OPEN HOUSE # 3 Please sign in and join our mailing list Why Are We Here Tonight? Study Process and Purpose
More informationWELCOME NEIGHBORS! April 11, 2019
District of Columbia Water and Sewer Authority David L. Gadis, CEO and General Manager Clean Rivers Project Northeast Boundary Tunnel Tunnel Forum Meeting WELCOME NEIGHBORS! April 11, 2019 0 Welcome! 1
More informationDowntown Brampton Capital Project
Downtown Brampton Capital Project BIA Update November 1 st, 2017 Anthony Parente, Director, Wastewater Region of Peel Public Works 1 Agenda Why Now? Design Update Construction Sequencing Traffic Management
More informationCanal Road City Limits (East of Van Dyke Ave) to Saal Road
Canal Road City Limits (East of Van Dyke Ave) to Saal Road Construction Update 9/14/2018 The ashalt paving on the southside of Canal Road is expected to start Saturday, September 15 (weather permitting)
More informationStrachan Ave. Overpass Community Design Update. October 26, 2010 Stephen Lipkus Executive Director Georgetown South Project GO Transit
Strachan Ave. Overpass Community Design Update October 26, 2010 Stephen Lipkus Executive Director Georgetown South Project GO Transit Welcome Program Overview 6:30 8:30 p.m.: Storyboard Review Project
More informationMonroe Street Reconstruction. Public Preconstruction Meeting February 21, 2018
Monroe Street Reconstruction Public Preconstruction Meeting February 21, 2018 Thank you to Edgewood College! Tonight s Agenda 1. Project Overview 2. Initial project schedule and phasing 3. Expectations
More informationOpen House Wellesley Station Second Exit Construction Update and Public Art Concept
Open House Wellesley Station Second Exit Construction Update and Public Art Concept YMCA 20 Grosvenor Street 1 Improvements coming to Wellesley Station Second Exit and Automatic Entrance Conceptual drawings
More informationAdelaide Street / Canadian Pacific Railway (CPR) Grade Separation. Public Information Centre #1
1 Adelaide Street / Canadian Pacific Railway (CPR) Why Are We Here? 2 The purpose of Public Information Centre (PIC) #1 is to: Introduce the study Provide the study background and context Identify the
More informationI-25 / Rio Bravo Interchange. I-25 / Rio Bravo Interchange. Presenters 11/30/2016 THIRD PUBLIC MEETING DECEMBER 1, 2016 NMDOT CN A300280
I-25 / Rio Bravo Interchange TONIGHT S MEETING SCHEDULE OPEN HOUSE 6:00 PM TO 6:30 PM PRESENTATION BEGINS AT 6:30 PM Q & A FOLLOWING PRESENTATION CN A300280 / PNA300280 I-25 / Rio Bravo Interchange THIRD
More informationCROSSTOWN LRT Central Open House March 21, 2018
CROSSTOWN LRT Central Open House March 21, 2018 Metrolinx was created in 2006 by the Province of Ontario to improve the coordination and integration of all modes of transportation in the Greater Toronto
More informationAshbridges Bay TTC Maintenance and Storage Facility
Ashbridges Bay TTC Maintenance and Storage Facility September 8, 2010 Presented to Government Review Team 1 Presentation Overview Overview of the Project Status of Transit Project Assessment Process Potential
More informationCommissioners Road West Realignment Environmental Assessment
City of London Commissioners Road West Realignment Environmental Assessment Public Information Centre No. 1 March 30, 2017 Welcome to the Public Information Centre This first Public Information Centre
More informationGLEN ROAD PEDESTRIAN BRIDGE ENVIRONMENTAL ASSESSMENT STUDY PUBLIC INFORMATION CENTRE #2 OCTOBER 24, 2017
GLEN ROAD PEDESTRIAN BRIDGE ENVIRONMENTAL ASSESSMENT STUDY PUBLIC INFORMATION CENTRE #2 OCTOBER 24, 2017 Glen Road Pedestrian Bridge Class Environmental Assessment 1 WELCOME! Welcome to the second Public
More information3 MARKHAM NORTH-SOUTH LINK CORRIDOR PUBLIC TRANSIT IMPROVEMENTS ENVIRONMENTAL ASSESSMENT UPDATE
3 MARKHAM NORTH-SOUTH LINK CORRIDOR PUBLIC TRANSIT IMPROVEMENTS ENVIRONMENTAL ASSESSMENT UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the adoption of the recommendations
More informationDRAFT DRAFT DRAFT DRAFT
# 19 EXPAND GREEN AND OPEN SPACES AND COMMUNITY FACILITIES IN TANDEM WITH NEW DEVELOPMENT The role of Eglinton will change in the coming years, along with the intensity of activity and land uses. As more
More informationWelcome. Date: Thursday March 2, 2017 Time: 6:30 p.m. 9:00 p.m. Location: Woodview School Gym, 69 Flatt Road, Burlington Presentation Time: 7:00 p.m.
Welcome Public Information Centre No.2 City of Burlington, City of Hamilton, Region of Halton Waterdown Road Widening Detailed Design Craven Avenue to Mountain Brow Road Date: Thursday March 2, 2017 Time:
More informationCITY OF VAUGHAN D R A F T YONGE STREET STUDY. June 2008 YOUNG + WRIGHT /IBI GROUP ARCHITECTS DILLON CONSULTING LTD.
CITY OF VAUGHAN June 2008 YOUNG + WRIGHT /IBI GROUP ARCHITECTS GHK SUSTAINABILITY INTERNATIONAL + LIVABILITY (CANADA) LTD. = COMMUNITY VALUE DILLON CONSULTING LTD. Public Open House Tonight s Meeting WELCOME
More informationCity of Cornwall Municipal Class Environmental Assessment. Proposed Improvement and Extension of Lemay Street
Welcome City of Cornwall Municipal Class Environmental Assessment Proposed Improvement and Extension of Lemay Street Redevelopment and Design of the Municipal Works Yard Public Information Centre #1 Thursday,
More informationRt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016
Rt. 29 Solutions Project Delivery Advisory Panel January 7, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Dec
More informationplanningalliance City of Toronto Lawrence Allen Revitalization Project Transportation Master Plan
planningalliance City of Toronto Lawrence Allen Revitalization Project Transportation Master Plan September 2011 This report takes into account the particular instructions and requirements of our client.
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: NOVEMBER 17, 2009 SUBJECT: REQUEST FOR APPROVAL OF THE EGLINTON CROSSTOWN LRT TRANSIT PROJECT ASSESSMENT STUDY ACTION ITEM
More informationEglinton West LRT Update
Eglinton West LRT Update Community Consultation Update May 16, 2016 Background Rapid transit along Eglinton Ave between Kennedy Station and Pearson Airport was included in the Metrolinx Regional Transportation
More informationReconfiguration of The Six Points Interchange. Community Update #2 June 18, 2014
Reconfiguration of The Six Points Interchange Community Update #2 June 18, 2014 Outline 1. Project overview 2. How did we get here? 3. Etobicoke Centre 4. Existing and future road network 5. Design Update
More informationVictoria Bridge Municipal Class EA Civic Works Committee
Municipal Class EA John Pucchio, P. Eng., Project Manager June 19 2018 Introduction Existing Conditions Municipal Class EA Proposed Bridge Proposed Road Reconstruction Proposed Improvements Construction
More informationVAUGHAN METROPOLITAN CENTRE STATION
VAUGH VAUGH METROPOLIT STATION Located South West of 407 ETR and Jane Street intersection Five Level intermodal line station 600 Bay Commuter Parking Lot Passenger Pick-Up and Drop-Off (PPUDO) 18 bay Bus
More informationNEWSLETTER #03 BEAUDESERT ROAD LOGAN MOTORWAY
NEWSLETTER #03 MT. LINDESAY HIGHWAY Feedback shapes design changes Thank you to the more than 600 stakeholders and community members that provided feedback on the Logan Enhancement Project initial concept
More informationProject Overview. Fairfax County Parkway Widening Fairfax County. Get Involved. Public Information Meeting. Contact Information
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationProject Overview. Get Involved. Public Information Meeting. Contact Information
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationThis Review Is Divided Into Two Phases:
Semiahmoo Town Centre Review The purpose of this review: To review the Semiahmoo Town Centre Concept Plan, originally approved in 1993, to ensure that this centre will continue to serve the needs of South
More informationRelief Line Project Assessment
Relief Line Project Assessment Public Information Centre April 5, 2017 Tonight s Meeting PURPOSE To review the preferred alignment for the Local Segment. AGENDA 6:30 Open House 7:00 Presentation / Discussion
More informationDon Mills Crossing Study and Celestica Lands Development Application Community Meeting, Open House, and Breakout Discussions
Consultation Summary Don Mills Crossing Study and Celestica Lands Development Application Community Meeting, Open House, and Breakout Discussions This report is not intended to provide a verbatim transcript
More informationStreetcar Noise Reduction King & Sumach Intersection. Community Meeting Toronto Transit Commission. Tuesday, June 27, 2017
Streetcar Noise Reduction King & Sumach Intersection Community Meeting Toronto Transit Commission Tuesday, June 27, 2017 STREETCAR NOISE REDUCTION KING & SUMACH INTERSECTION AGENDA 1) Welcome and Introductions
More informationHighway 417 Expansion East
Highway 417 Expansion East Nicholas Street to Ottawa Road 174 GWP 4091-07-00 & GWP 4320-06-00 Outline Project Overview Highway 417 Widening Bridge Rapid Replacements Traffic & Incident Management Project
More informationTOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,
TOWN OF PALM BEACH DATE: October 19, 2017 FOR IMMEDIATE RELEASE MEDIA CONTACT: Patricia Strayer, P.E., Town Engineer Phone: 561-838-5440, Email: pstrayer@townofpalmbeach.com Construction and Traffic Highlights
More informationTOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,
TOWN OF PALM BEACH DATE: October 18, 2018 FOR IMMEDIATE RELEASE MEDIA CONTACT: Patricia Strayer, P.E., Town Engineer Phone: 561-838-5440, Email: pstrayer@townofpalmbeach.com Construction and Traffic Highlights
More informationFANSHAWE PARK ROAD/RICHMOND STREET INTERSECTION IMPROVEMENTS. PUBLIC INFORMATION CENTRE 2 June 16, 2016
FANSHAWE PARK ROAD/RICHMOND STREET INTERSECTION IMPROVEMENTS Municipal Class Environmental Assessment PUBLIC INFORMATION CENTRE 2 June 16, 2016 ACCESSIBILITY Under the Accessibility Standards 2015 for
More informationI-66 EASTBOUND WIDENING INSIDE THE BELTWAY PARDON OUR DUST MEETING
I-66 EASTBOUND WIDENING INSIDE THE BELTWAY From the Dulles Connector Road (Route 267) to Fairfax Drive (Route 237) PARDON OUR DUST MEETING Bill Cuttler, PE (VDOT District Construction Engineer, Northern
More informationBurloak Drive Grade Separation
Burloak Drive Grade Separation Transit Project Assessment Process Public Meeting #1 March 30, 2017 GO Lakeshore West Service Plan Weekday Rush Hour 15-minute, two-way service between Aldershot* and Union
More informationGlen Road Pedestrian Bridge Environmental Assessment
Glen Road Pedestrian Bridge Environmental Assessment Presentation to Design Review Panel July 18, 2017 Glen Road Pedestrian Bridge Class Environmental Assessment STUDY AREA Bloor Street East Streetscape
More informationAdelaide Street / Canadian Pacific Railway (CPR) Grade Separation Class Environmental Assessment. Public Information Centre 3
1 Adelaide Street / Canadian Pacific Railway (CPR) Grade Separation Study Process and Purpose of PIC 3 2 Study Commencement February 2016 Phase 1: Problem and Opportunity Identify problems and opportunities
More informationMount Dennis Mobility Hub Study Public Meeting December 12 th, :30pm 9:30pm York Memorial Collegiate, Cafeteria 2690 Eglinton Avenue West
Mount Dennis Mobility Hub Study Public Meeting December 12 th, 2012 6:30pm 9:30pm York Memorial Collegiate, Cafeteria 2690 Eglinton Avenue West MEETING SUMMARY On December 12 th, 2012, over 89 people participated
More informationSCARBOROUGH RAPID TRANSIT ENVIRONMENTAL PROJECT REPORT CHAPTER 2 PROJECT DESCRIPTION. Table 2-4: North Segment Alignment Analysis 2-21
Table 2-4: North Segment Alignment Analysis 2-21 SCARBOROUGH RAPID TRANSIT Based on the above analysis (detailed analysis is contained in Appendix A-4), North Alignment 3 is preferred because it: Has the
More informationWelcome. Walk Around. Talk to Us. Write Down Your Comments
Welcome This is an information meeting introducing the applications for proposed redevelopment of the Yorkdale Shopping Centre site at 3401 Dufferin Street and 1 Yorkdale Road over the next 20+ years,
More informationPROPOSED IMPROVEMENTS
IV. PROPOSED IMPROVEMENTS The proposed improvements for each alternative carried forward are discussed below. A. FUNCTIONAL CLASSIFICATION AND ROADWAY CROSS-SECTIONS The classifications of the roadways
More informationWelcome. Community Consultation Meeting November 28, Review and discuss the Bathurst Quay Neighbourhood Plan Framework
Welcome Community Consultation Meeting November 28, 2016 Why Are We Here Today? Review and discuss the Bathurst Quay Neighbourhood Plan Framework Review and discuss an Action Plan for Implementation Next
More informationWHAT IS THE PURPOSE OF THE OPEN HOUSE?
WHAT IS THE PURPOSE OF THE OPEN HOUSE? OPEN HOUSE PURPOSE The purpose of the open house is to provide an update on the study process and introduce the preliminary concept alternatives. The open house provides
More informationNEWTONBROOK PLAZA. Aerial of Site SILVERCORE PROPERTIES INC. Wallman Architects
Aerial of Site Precedents Legacy at Heron s Hill Don Valley Parkway / Sheppard Avenue West ARC Condominiums Bayview Avenue / Sheppard Avenue West Rhythm Condominium Brampton Yonge / Avondale Community
More informationThe Commissioner of Engineering and Public Works recommends that this report be received for information purposes.
COMMITTEE OF THE WHOLE FEBRUARY 1, 2011 407 TRANSITWAY - ENVIRONMENTAL PROJECT REPORT MINISTRY OF TRANSPORTATION CITY WIDE Recommendation The Commissioner of Engineering and Public Works recommends that
More informationProject Status. Construction is underway for Phase 3. Overall Project Area and Schedule. Schedule of Current Construction Phases.
I-95 Avenue Interchange Project Status Construction is underway for Phase 3. Overall Project Area and Schedule Phase 0: Completed 2010 Section GR0: Completed in Fallin 2010 Phase 2: Completed Section GR2:
More informationIOWA HIGHWAY 57 / WEST 1 ST STREET STUDY PUBLIC INFORMATIONAL MEETING APRIL 22, 2014
IOWA HIGHWAY 57 / WEST 1 ST STREET STUDY PUBLIC INFORMATIONAL MEETING APRIL 22, 2014 INTRODUCTION The City of Cedar Falls and the Iowa Department of Transportation are conducting a Public Informational
More informationPROJECT SHOWING MINUTES
PROJECT SHOWING MINUTES North Lynn Street Esplanade Improvements Project No. 0029-000-859, C501, B605 UPC No. 109813 November 1, 2017 10:00 a.m. 1911 North Ft. Myer Drive, LL-10, Arlington, VA Overview
More informationThe purpose of tonight s PIC is to:
The purpose of tonight s PIC is to: Provide an overview of the work completed to date and a summary of the Class EA process being followed; Provide a summary of public input received so far, including
More informationNew. Stations. Smart Track I tlo MTDRONIO. Public Information Centre
Public Information Centre New Smart Track I tlo - - -E>- - Stations Public Information Centre. King-Liberty SmartTrack Station. St. Clair-Old Weston SmartTrack Station. Spadina-Front GO Station. Bloor-Lansdowne
More information2002 TAC Sustainable Transportation Award
2002 TAC Sustainable Transportation Award Nomination: Dismantling the F.G. Gardiner Expressway East REMOVING TORONTO S ELEVATED EXPRESSWAY ONE PIECE AT A TIME Nominated by: Kathleen Llewellyn-Thomas, P.
More informationBexar County Public Works Department Flood Control Program
Bexar County Public Works Department Flood Control Program Bulverde Rd. at Mud Creek Trib. A (SC-27) February 23 rd, 2016 Agenda Introductions Bexar County Flood Control (Engineering and PR) Office of
More informationWhat s Up Next In The Seattle Squeeze. PSRC Transportation Policy Board April 11
What s Up Next In The Seattle Squeeze PSRC Transportation Policy Board April 11 1 Current construction Alaskan Way Viaduct removal Removes the viaduct (including foundations and ramps) and restores the
More informationMETRO Gold Line BRT CMC Meeting
METRO Gold Line BRT CMC Meeting April 26, 2018 Today s Topics Welcome and Introductions Project Overview CMC Roles and Responsibilities Current Project Baseline: Scope and Cost Estimate Overview Municipal
More informationHighway 15 Project - Hutchinson
Highway 15 Project - Hutchinson Agenda What are we going to talk about today? Goals and benefits of the project Details about the proposed work Project schedule and costs Any questions you may have about
More informationFall 2017 Construction Update
Fall 2017 Construction Update Ward 4 Southeast Engineering Department Riverwalk Red Multi-Use Trail Bridge Rehabilitation The Riverwalk Red Multi Use Trail Bridge was awarded to Cramer and Associates,
More informationFairfax County Parkway (Route 286) Widening Project
Fairfax County Parkway (Route 286) Widening Project Route 29 (Lee Highway) to Route 123 (Ox Road) State Project No. 0286-029-259, P101; UPC 107937 Fairfax Station HOA Meeting January 30, 2018 7:00 to 9:00
More informationSouth Yonge Street Corridor
South Yonge Street Corridor Streetscape Master Plan Study Draft Final Executive Summary Prepared by: January 2012 In Partnership with: Introduction The Future... Yonge Street is at the forefront of York
More informationMeeting Purpose: Date and Time: Location: Attendance: Handouts:
Meeting Purpose: Date and Time: Location: Attendance: Handouts: PA Turnpike / I-95 Interchange Project Design Advisory Committee (DAC)/Public Officials Meeting #8 April 12, 2012 at 1:30 p.m. Project Office,
More informationLaird in Focus Community Information Session
Laird in Focus Community Information Session Tuesday, December 5, 2017 St. Anslem Catholic School, 182 Bessborough Drive Session 1: 5:30 pm - Presentation and Question and Answer Period 6:15 pm - Breakout
More informationCity of Plattsburgh DRI: Downtown Streetscapes & Riverfront Access. Downtown Streetscape and Riverfront Access Design
City of Plattsburgh DRI: Downtown Streetscapes & Riverfront Access Welcome Thank you for coming this evening. Agenda PART I - Project Context The Downtown Revitalization Program Our DRI Projects Other
More information7 HIGHWAY 7 CORRIDOR AND VAUGHAN N-S LINK ENVIRONMENTAL ASSESSMENT RECOMMENDED ALIGNMENT
7 HIGHWAY 7 CORRIDOR AND VAUGHAN N-S LINK ENVIRONMENTAL ASSESSMENT RECOMMENDED ALIGNMENT The Rapid Transit Public/Private Partnership Steering Committee recommends the adoption of the recommendations contained
More informationROAD CONSTRUCTION. 36 June 2014 ROADS&BRIDGES
ROAD CONSTRUCTION 36 June 2014 ROADS&BRIDGES Young is full of life Recent expansion completes continuous, multilane arterial By Donald Hammack, P.E. Contributing Author The Florida Department of Transportation
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: AUGUST 26, 2009 SUBJECT: REQUEST FOR APPROVAL OF THE SCARBOROUGH-MALVERN LRT ENVIRONMENTAL ASSESSMENT STUDY ACTION ITEM RECOMMENDATION
More informationPrince William Street Project (Grant Avenue to Wellington Road)
Prince William Street Project (Grant Avenue to Wellington Road) 1 Goals Improve pedestrian and bike traffic safety Improve street drainage with curb & gutter Upsize water mains Enhance overall street appearance
More informationOn behalf of Metrolinx, in coordination with the City of Mississauga. and Presentation Materials (draft)
On behalf of Metrolinx, in coordination with the City of Mississauga Port Credit GO Station Area Master Plan Study Advisory Panel Meeting #3 Handouts and Presentation Materials (draft) June 10, 2015 Agenda
More informationMARINA BAY NEIGHBORHOOD PRESENTATION. City of Richmond Officer Bradley A. Moody Memorial Underpass. April 11, 2012
MARINA BAY NEIGHBORHOOD PRESENTATION City of Richmond Officer Bradley A. Moody Memorial Underpass April 11, 2012 TEAM INTRODUCTIONS Project Oversight and Approval City of Richmond Formally Richmond Community
More informationBetter Cycling. The City will update the cycling master plan (London ON Bikes) based on the approved BRT network.
Better Cycling Dedicated bike facilities will be constructed along BRT corridors where space is available. Nearby bike routes will also be upgraded to ensure a complete network is available for cyclists.
More informationSTATION AND STOP NAMES Eglinton Line. September 2015
STATION AND STOP NAMES Eglinton Line September 2015 Naming Conventions. Why? There are ten transit agencies operating in the GTHA The planned construction of hundreds of kilometers of new rapid transit
More informationONLINE PUBLIC INFORMATION CENTRE
ONLINE PUBLIC INFORMATION CENTRE County Road 17 Bridge Replacements Detail Design and Environmental Assessment GWP 4203-15-00 The Ministry of Transportation Ontario (MTO) has retained CH2M Hill and Dillon
More informationTOWN OF WHITBY REPORT RECOMMENDATION REPORT
TOWN OF WHITBY REPORT RECOMMENDATION REPORT REPORT TO: Council REPORT NO: PL 95-09 DATE OF MEETING: October 13, 2009 PREPARED BY: Planning/Public Works Joint Report FILE NO(S): N/A LOCATION: N/A REPORT
More informationPUBLIC MEETING April, 20161
PUBLIC MEETING April, 20161 The Study Area Study Area Focus Area Corridor Neighbourhoods 2 Today s Presentation This material is aimed at providing viewers with enough background to be able to think about
More informationMoving The Metro. A special construction update for the metro Omaha area.
Moving The Metro A special construction update for the metro Omaha area. ebraska Department of Roads Spring/Summer 2017 I-80 / I-480 / US-75 Interchange The improvements on this project consist of bridge
More informationAllen Road-Eglinton West Station Public Consultation Report Open House & Online Consultation #1
Allen Road-Eglinton West Station Public Consultation Report Open House & Online Consultation #1 March 2, 2012 2 Allen Road Eglinton West Station Consultation Table of Contents 1. Executive Summary... 4
More informationALTERNATIVES. NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives).
III. ALTERNATIVES A. CONSTRUCTION METHOD ALTERNATIVES NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives). One of the
More informationHighlan. March Submitted by: Fax
Gate Golf Course ReDevelopment Highlan d Gate Developments Inc. Town of Aurora Construction Impact Mitigation Plan Submitted by: SCS Consulting Group Ltd 30 Centurian Drive, Suite 100 Markham, ON, L3R
More informationProposed Staging Plan For:
701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 1 Proposed Staging Plan For: St aging Plan Includes: 1.0 Construction Site 2.0 MOT Traffic Circulation Plan 2.1.P1 MOT Road Closures (Alhambra)
More informationWelcome! MILLENNIUM LINE BROADWAY EXTENSION. Over the next 30 years, Metro Vancouver will welcome 1 million new residents and 600,000 new jobs.
WELCOME Welcome! MILLENNIUM LINE BROADWAY EXTENSION Over the next 30 years, Metro Vancouver will welcome 1 million new residents and 600,000 new jobs. The Broadway Corridor is home to the second largest
More informationRt. 29 Solutions Project Delivery Advisory Panel. December 3, 2015
Rt. 29 Solutions Project Delivery Advisory Panel December 3, 2015 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Nov
More informationCity of Toronto. Emery Village Transportation Master Plan
City of Toronto Emery Village Transportation Master Plan May 2009 Emery Village Transportation Master Plan Toronto, ON May 2009 Consulting Inc. 100 York Blvd., Suite 300 Richmond Hill, ON L4B 1J8 Tel:
More informationII PREVIOUS REPORTS PERTINENT TO THIS MATTER II
~ ~~ ~~~ ~ ~~ ~ ~~~~ ~ ~~ ~~ ~~~~ ~ Agenda Item # Page # TO: FROM: -..-.-I- 3UBJCL I CHAIR AND MEMBERS ENVIRONMENT AND TRANSPORTATION COMMITTEE MEETING ON OCTOBER 17,2005 DAVID A. LECKIE, P. ENG DIRECTOR
More informationEastside Transit Corridor Phase 2 Technical Study Update Community Outreach Meeting February 2017
Eastside Transit Corridor Phase 2 Technical Study Update Community Outreach Meeting February 2017 Purpose of Tonight s Meeting Recap of Board motion (2014) and technical study process Provide update on
More informationStation Expansion Project
Streetsville Reservoir and Pumping Station Expansion Project Public Information Centre Paul Dagenais, P.Eng. AECOM September 23, 2010 Erin Meadows Community Centre Purpose of Tonight s Meeting Update residents
More informationCROSSTOWN LRT Central-West Open House April 18, 2018
CROSSTOWN LRT Central-West Open House April 18, 2018 Metrolinx was created in 2006 by the Province of Ontario to improve the coordination and integration of all modes of transportation in the Greater Toronto
More informationI-75/I-475 Interchange Upgrade Project Informational Meeting Tuesday, July 27, 2010
I-75/I-475 Interchange Upgrade Project Informational Meeting Tuesday, July 27, 2010 I-75/I-475 Interchange Upgrade Project David R. Dysard, AICP District Two Deputy Director Theresa Pollick Public Information
More information