1 Projects Completed FY14, FY15 and FY16 (arranged alphabetically) Abrams Planetarium Install automatic door opener on main doors of the Planetarium. Completed: Summer 2016 Cost: $13,000 Akers Hall Renovations to the food service areas and installation of new life safety equipment throughout the building. Project will improve accessibility within the hall, public restrooms, and will provide a new elevators to enable accessibility to the dining hall. All new food service operation will greatly enhance accessibility in dining operations. Completed: January 2015 (Food Service Areas) August 2014 (Residential Areas) Cost: $20.6 million (total Akers Hall project cost) Bessey Hall Bike Shop Site improvements including widening and re-sloping concrete ramp to accommodate pedestrian/wheelchair traffic as well as display of bikes and tire pump area. Install new railing system at the stairs and elevated concrete slabs. Replace existing doors with larger doors swinging opposite the ramp, and install automatic door opener. Install light kits in the doors for improved visibility. Completed: December 2015 Cost: $80,000 Bessey Hall 3 rd Floor Classroom Wing Renovated classrooms and corridor on the 3 rd floor of Bessey Hall. Variety of accessible seating provided in classrooms and corridors. Accessible drinking fountain and bottle filling station installed on the floor as well. Completed: Fall 2014 Cost: $1.5 Million (Total project cost) Business College Complex Install automatic door opener to vestibule doors outside of room N130. Completed: Fall 2016 Cost: $12,000 Office of Planning and Budgets Facilities Planning and Space Management 1

2 Butterfield Hall Renovations to the building to enhance and update infrastructure, improve accessible entrances and accessibility within the hall, public and community restrooms, way finding and upgrades to life safety systems. Modify site to include grade level entry at all main entrances, provide heated sidewalk to accessible parking. Completed: August 2014 Cost: $16 Million (total Butterfield Hall project cost) Chittenden Hall Modify site to provide outdoor terrace with ramped/grade level entry to the building, automated entry door from ramp, snow melt system to accessible parking, install elevator for access to all levels, provide barrier-free toilet rooms, ADA signage. Completed: October 2014 Cost: $6.2 Million (total Chittenden Hall project cost) Demonstration Hall: Renovate and expand restrooms in the Arena for barrier-free access. Install automatic door opener. Completed: August 2016 Cost: $200,000 Giltner Hall Install automatic door opener to doors on the North Side of Giltner Hall. Completed: Fall 2016 Cost: $16,000 Holmes Hall Renovated two accessible student room restroom suites, providing new finishes, fixtures and lighting. Completed: Summer 2014 Cost: $80,000 Kresge Courtyard Project Site renovation of Kresge Courtyard into an accessible venue for Summer Circle Theater and other events. Stage and two out of three seating tiers are accessible. Grade level ramps provided. Contrasting material colors were used throughout the design. Completed: Fall 2014 Cost: $1.2 Million Office of Planning and Budgets Facilities Planning and Space Management 2

3 Landon Hall Renovations to the building to enhance and update infrastructure, improve accessible entrances and accessibility within the hall, public restrooms, two new elevators to enable lower level accessibility, new ramp at NE entrance to increase accessibility of building. All new food service operation will greatly enhance accessibility in dining operations. Completed: August 2014 Cost: $18.7 Million (total Landon Hall project cost) MSU River Trail Construction of dedicated bicycle and pedestrian pathway extending along the south side of the Red Cedar River from Kalamazoo Street at the Spartan statue to Farm Lane. Completed: Summer 2014 Cost: $670,000 Munn Ice Arena Improvements include replacement of all bench seating with a combination of chair/bench seats; addition of six ADA platforms; install railings in all aisle ways. Completed: September 2015 Cost: $900,000 (Total Munn Ice Arena project cost) Music Practice Building Install automatic door opener and changed double doors to a single entry door. Completed: Winter 2016 Cost: $ 35,000 Spartan Stadium North End Zone Addition to the north end of the stadium includes new home and visiting team locker rooms; equipment areas; training rooms and coaches locker rooms; media center; restroom facilities on concourse level, including family restrooms; new Engagement Center; expanded entry plazas. All areas listed are fully accessible. Completed: August 2014 Cost: $24.5 Million (Total Spartan Stadium project cost) Office of Planning and Budgets Facilities Planning and Space Management 3

4 Spartan Stadium Student Seating Section SE Corner of Bowl Construction of an accessible seating platform integral to the student seating section in the SE Corner of Stadium Bowl with 20 wheelchair locations and additional companion seating. Additionally, entrances to the student sections have been updated to meet accessibility standards. Completed: August 2015 Cost: $850,000 (Total Spartan Stadium project cost) Trout Food Science Building Install automatic door opener to the exterior door at the rear of the building. Install magnet hold-opens on three interior doors. Completed: Summer 2016 Cost: $15,000 Various Buildings Auto Door Sensors Modify location, height and/or orientation of the automatic door sensors at entrances to various buildings on campus. Current installations comply with ADAG code, however do not meet MSU Construction Standards for installation and thereby limit accessibility. Completed: January 2013 / October 2014 Cost: $26,000 Veterinary Medical Center Install automatic door opener to the entrance of the G-Wing (closest to classroom G150). Completed: Summer 2016 Cost: $15,000 Wilson Hall Renovated two accessible student room restroom suites, providing new finishes, fixtures and lighting. Completed: Summer 2014 Cost: $80,000 New Construction All new construction adheres to ADA standards Place Phase I Aug 2016, Phase II Fall 2017 FRIB Office Addition III Fall 2016 Golf Facility Jan 2016 Interdisciplinary Science & Tech. Fall 2019 Bio Engineering Building Fall 2016 Office of Planning and Budgets Facilities Planning and Space Management 4

5 Accessibility Projects Funded and In Process (arranged alphabetically) ADA Route Site Improvements Phase 1 of a multiphase improvement plan to improve accessibility of all persons, and in particular, people with disabilities. Status: In progress Estimated Cost: $360,000 Breslin Center Barrier-free stalls and fixtures added to existing north and south restrooms. New single occupancy toilet rooms added. Barrier free entry and exit corridors to and from all public restrooms. New Concession stands designed to be accessible. New barrier-free ramp created at the north end of the site. Power assisted doors added. Upgrades to current lighting meet standards for ADA visibility requirements. Status: In progress (scheduled to be complete Oct 2017) Cost: $50 Million (total project cost) Jenison Install automatic door opener to women s locker room. Status: In progress Cost: $11,000 Accessibility Projects In-Planning/Under Review (arranged alphabetically) Cook Hall Building: evaluate the need for snowmelt system, check availability of barrier-free parking, install elevator, provide toilet room modifications, ADA signage and fire alarm modifications as required. Status: Will be completed as part of a comprehensive building renovation. Library Modify north main entry to provide ramped/grade level entry to the building, automate entry doors as necessary and evaluate the need for snowmelt system. Status: Scope & Estimate TBD Office of Planning and Budgets Facilities Planning and Space Management 5

6 Old Botany Building evaluate need for snow melt system, check availability of barrier-free parking, install elevator, provide toilet room modifications, ADA signage and fire alarm modifications as required. Status: Will be completed as part of a comprehensive building renovation. Packaging Building evaluate need for snow melt system, check availability of barrier-free parking, provide toilet room modifications and ADA signage. Status: Scope & Estimate TBD Urban Planning and Landscape Architecture Building evaluate need for snow melt system, check availability of barrier-free parking, provide toilet room modifications, ADA signage and fire alarm modifications as required. Status: Awaiting identification of funding Estimated Cost: $1.2 Million Wharton Center: Path of travel and companion seating modifications associated with the seat replacement project at the Great Hall and Pasant Theater. Status: Scope is under review Estimated Cost: $1.4M - $1.6M (total project cost) Wills House: evaluate the need for snowmelt system, check availability of barrier-free parking, install elevator, provide toilet room modifications, ADA signage and fire alarm modifications as required. Status: Scope & Estimate TBD Office of Planning and Budgets Facilities Planning and Space Management 6

7 ADA Route Site Improvements Various Locations Modify site in various pedestrian routes/areas on campus that require site improvements. These site related projects across campus impact accessibility of all persons, and in particular, people with disabilities. Multiphase plan in development. Phase 1 funded and in process, reference page 5 of report. Status: Awaiting identification of funding (phased) Estimated Cost: $2.1 Million (remaining total project cost) Office of Planning and Budgets Facilities Planning and Space Management 7

Facilities Procedure for Accessibility or Compliance Related Requests:

Facilities Procedure for Accessibility or Compliance Related Requests: Facilities Procedure for Accessibility or Compliance Related Requests: All doorways, entry ways, equipment height, etc. will be checked to ensure compliance with the Americans with Disabilities Act (ADA)

More information

Binghamton University Construction SUMMER 2012 HIGHLIGHTS

Binghamton University Construction SUMMER 2012 HIGHLIGHTS Binghamton University Construction SUMMER 2012 HIGHLIGHTS Binghamton University Construction Summer 2012 Large and small construction projects were completed during the summer 2012 construction season.

More information

City of Plattsburgh DRI: Downtown Streetscapes & Riverfront Access. Downtown Streetscape and Riverfront Access Design

City of Plattsburgh DRI: Downtown Streetscapes & Riverfront Access. Downtown Streetscape and Riverfront Access Design City of Plattsburgh DRI: Downtown Streetscapes & Riverfront Access Welcome Thank you for coming this evening. Agenda PART I - Project Context The Downtown Revitalization Program Our DRI Projects Other

More information

Johnson Street Bridge Public Realm Update

Johnson Street Bridge Public Realm Update Johnson Street Bridge Public Realm Update August 20, 2015 Background Johnson Street Bridge Replacement Project impacts a diverse range of stakeholders In addition to a new bridge, the project also includes

More information

Forest Hills Facilities Plan

Forest Hills Facilities Plan Forest Hills Facilities Plan Extensive updates to 8 of our 9 schools Replace Wilson Elementary Enhance learning environments across the district Build additional classrooms to accommodate gradual implementation

More information

New High School Concept

New High School Concept Approved Bond Projects for Alamance-Burlington Schools In November 2018, Alamance County citizens approved a $150 million bond project proposal. Bond funds will pay to construct a new high school and provide

More information

Virginia Department of Planning and Budget Project Request Justification

Virginia Department of Planning and Budget Project Request Justification DPB Form CNJ June 2005 Virginia Department of Planning and Budget Project Request Justification 2006-2008 Biennium Date: July 22, 2005 A. General Information 1. Agency name: Virginia Tech 2. Agency code:

More information

CAMPUS PLANNING COMMITTEE STAFF REPORT SAMARITAN SPORTS MEDICINE INSTITUTE AT OSU 10/21/2013

CAMPUS PLANNING COMMITTEE STAFF REPORT SAMARITAN SPORTS MEDICINE INSTITUTE AT OSU 10/21/2013 Office of Capital Planning and Development; 130 Oak Creek Building; Corvallis, Oregon 97331-2001 CPC STAFF REPORT: SAMARITAN SPORTS MEDICINE INSTITUTE AT OSU CAMPUS PLANNING COMMITTEE STAFF REPORT SAMARITAN

More information

Emerson Park Master Plan Update. Public Meeting III August 27, 2014

Emerson Park Master Plan Update. Public Meeting III August 27, 2014 Emerson Park Master Plan Update Public Meeting III August 27, 2014 Meeting Agenda: Project Update Presentation of Master Plan Components Discussion and Feedback The Path Forward: Building on the Concept

More information

Abbreviated Accessibility Checklist (Reception, Telephones, and Emergency Procedures) Reception Telephones

Abbreviated Accessibility Checklist (Reception, Telephones, and Emergency Procedures) Reception Telephones Abbreviated Accessibility Checklist (Reception, Telephones, and Emergency Procedures) Reception Can patients request needed accommodations (alternate formats, sign language interpreters, etc.) through

More information

Garfield Elementary School Feasibility Study for New Library Building Project Number A C

Garfield Elementary School Feasibility Study for New Library Building Project Number A C Larry Teixeira Selma Unified School District 3036 Thompson Avenue Selma, CA 93662 Subject: Feasibility Study for New Library Building Project Number A 12-8581.00 C Dear Mr. Teixeira: At your request, we

More information

Chapter 6: Plumbing Elements and Facilities. 603 Toilet and Bathing Rooms Wheelchair Accessible Compartment

Chapter 6: Plumbing Elements and Facilities. 603 Toilet and Bathing Rooms Wheelchair Accessible Compartment Practical Applications of the 2010 Standards for New Construction -- Part 1I James A. Bostrom Deputy Chief Disability Rights Section U. S. Department of Justice 1 Chapter 6: Plumbing Elements and Facilities

More information

LINCOLN HIGH SCHOOL MODERNIZATION BEX IV COMMUNITY MEETING JUNE 23, 2016

LINCOLN HIGH SCHOOL MODERNIZATION BEX IV COMMUNITY MEETING JUNE 23, 2016 LINCOLN HIGH SCHOOL MODERNIZATION BEX IV COMMUNITY MEETING JUNE 23, 2016 PROJECT OVERVIEW PROJECT OVERVIEW + PRE-DESIGN BEGAN IN FALL OF 2015 + EXISTING CONDITIONS ANALYSIS + PROJECTED GROWTH IN HIGH SCHOOL

More information

ROSLINDALE BRANCH, BPL COMMUNITY PRESENTATION #2 MARTIN J. WALSH, MAYOR CITY OF BOSTON PUBLIC FACILITIES DEPARTMENT 02/07/2018

ROSLINDALE BRANCH, BPL COMMUNITY PRESENTATION #2 MARTIN J. WALSH, MAYOR CITY OF BOSTON PUBLIC FACILITIES DEPARTMENT 02/07/2018 ROSLINDALE BRANCH, BPL COMMUNITY PRESENTATION #2 MARTIN J. WALSH, MAYOR CITY OF BOSTON PUBLIC FACILITIES DEPARTMENT 02/07/2018 MEETING AGENDA TEAM & GOALS ENTRY DESIGN PROGRESS INTERIOR PLAN DESIGN PROGRESS

More information

Number of persons with a disability that live with a disability in your community?

Number of persons with a disability that live with a disability in your community? Building name: re Dame Location: Owen Sound Assessment by: Cathy Smart Date: August 25, 2003 Total number of students: 378 Number of students living with a disability? Deaf/Hard of hearing Blind/Low vision

More information

UAA School of Engineering Parking Garage Master Plan Amendment. 1. Purpose

UAA School of Engineering Parking Garage Master Plan Amendment. 1. Purpose UAA School of Engineering Parking Garage Master Plan Amendment 1. Purpose Since the UAA campus master plan was drafted in 2003, adopted in 2004, and amended in 2009 a number of significant changes regarding

More information

EXISTING CONDITIONS SUMMARY

EXISTING CONDITIONS SUMMARY SITE Fire alarm system does meet current requirements Accessible path of travel lacking throughout campus Announcer s booth at Football Field booth not ADA compliant Covered and non covered outdoor eating

More information

Interior signs are an extension of the exterior sign system and their content and design should take this into consideration.

Interior signs are an extension of the exterior sign system and their content and design should take this into consideration. General Guideline The Interior Sign standard is developed to address the need for a cost effective, functional, flexible and serviceable sign system. The intent is to assure code compliance, consistency

More information

Fall 2017 Construction Update

Fall 2017 Construction Update Fall 2017 Construction Update Ward 4 Southeast Engineering Department Riverwalk Red Multi-Use Trail Bridge Rehabilitation The Riverwalk Red Multi Use Trail Bridge was awarded to Cramer and Associates,

More information

Speedway Mall Project Frequently Asked Questions

Speedway Mall Project Frequently Asked Questions Speedway Mall Project Frequently Asked Questions These FAQs will continue to be updated as new questions arise. Purpose of the Project and Uses of the Mall Q: Why is this project being done? A: The 1999

More information

School District of Milton 5- Year Capital Maintenance and Improvement Plan

School District of Milton 5- Year Capital Maintenance and Improvement Plan Updated - 02/21/17 School District of Milton 5- Year Capital Maintenance and Improvement Plan 101 East Elementary 1 Parking Lot/Traffic Flow Project 615,175 Includes Construction and Engineering 2 Bathroom

More information

Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS

Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS DATE: July 10, 2007 TO: FROM: SUBJECT: ORIGINATOR: RESOURCE PERSON(S): BOARD OF EDUCATION Dr. Joe A. Hairston, Superintendent ABBREVIATED FACILITY STATUS REPORT

More information

Purpose of the Act. Learning Objectives. Latest with DOJ. Latest with DOJ. Texas Registered Accessibility Specialists Association

Purpose of the Act. Learning Objectives. Latest with DOJ. Latest with DOJ. Texas Registered Accessibility Specialists Association Texas Registered Accessibility Specialists Association Mission Statement To enhance accessibility in the built environment throughout Texas To raise the level of service provided by our members by presenting

More information

Enhance the High Line Canal Projects

Enhance the High Line Canal Projects Enhance the High Line Canal Projects Joint Project Proposal for Arapahoe County Open Spaces Funding Partner Sponsors: South Suburban Park and Recreation District City of Centennial City of Littleton October

More information

Ohlone College Measure G Project Scope Revisions

Ohlone College Measure G Project Scope Revisions Scope Revisions Current Title Revised Title Current Scope Revised Scope 6101 Relocated Baseball Field Athletic Fields Create new sustainable baseball field with synthetic turf, bleacher seating and batting

More information

ADDENDUM NO. 1 BID-CONTRACT DOCUMENTS FOR. RFP No Professional Design Services for CCC Le-Jao Student Resource Center

ADDENDUM NO. 1 BID-CONTRACT DOCUMENTS FOR. RFP No Professional Design Services for CCC Le-Jao Student Resource Center ADDENDUM NO. 1 BID-CONTRACT DOCUMENTS FOR RFP No. 2030 Professional Design Services for CCC Le-Jao Student Resource Center COAST COMMUNITY COLLEGE DISTRICT COSTA MESA, CALIFORNIA COUNTY OF ORANGE COAST

More information

Design Review of Facility Improvement Projects

Design Review of Facility Improvement Projects Design Review of Facility Improvement Projects Agenda Board Meeting Schedule Scope of Work Summary Overall Building Plans and Scope Summary Update on Areas of Design Development Programming and Space planning

More information

Design Presentation. Chief Operations Officer Willie Burroughs

Design Presentation. Chief Operations Officer Willie Burroughs Design Presentation Chief Operations Officer Willie Burroughs Agenda Introduction Community Feedback Project updates 2 Feedback Citizens Advisory Committee meetings Growth and Development meetings Community

More information

TOWN COUNCIL / PLANNING COMMISSION

TOWN COUNCIL / PLANNING COMMISSION Workshop #3 TOWN COUNCIL / PLANNING COMMISSION January 20, 2011 Consultant Team In Attendance Tonight BMS Design Group Nevada City and San Francisco Michael Smiley, AICP, ASLA Partner-in-Charge Nancy L.

More information

ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET ARROYO PROJECTS

ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET ARROYO PROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET ARROYO PROJECTS HAHAMONGNA FY 212-216 Capital Improvement Program Priority Description Total Estimated Costs Appropriated Through FY 211 Adopted FY 212 FY 213

More information

PRINCE GEORGE LIBRARY NEW ENTRANCE REPORT Patricia Boulevard Prince George, BC V2L 3V9

PRINCE GEORGE LIBRARY NEW ENTRANCE REPORT Patricia Boulevard Prince George, BC V2L 3V9 #230 177 Victoria Street P rince George, BC V2L 5R8 Tel. (250) 564-7285 F ax. (250) 564-7286 1100 Patricia Boulevard Prince George, BC V2L 3V9 PRINCE GEORGE LIBRARY NEW ENTRANCE REPORT CITY OF PRINCE GEORGE

More information

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological

More information

Recreation Unlimited Foundation

Recreation Unlimited Foundation Recreation Unlimited Foundation Building Campaign New Construction, Renovation & Expansion Summary Presentation Unlimited Dreams For Individuals With Disabilities & Health Concerns Year-Round April 2015

More information

Philip A. Ginsburg, General Manager Toks Ajike, Acting Planning and Capital Program Director

Philip A. Ginsburg, General Manager Toks Ajike, Acting Planning and Capital Program Director Date: March 7, 2018 To: Through: From: Subject: Recreation and Park Commission Capital Committee Philip A. Ginsburg, General Manager Toks Ajike, Acting Planning and Capital Program Director Dan Mauer,

More information

Planning Guide for the Refurbishment, Renovation, or Construction of Instructional Space Environments

Planning Guide for the Refurbishment, Renovation, or Construction of Instructional Space Environments Planning Guide for the Refurbishment, Renovation, or Construction of Instructional Space Environments April 7, 2014 Introduction This Planning Guide was developed to assist Cornell faculty and staff as

More information

Community Assistantship Program. Milaca Downtown Revitalization

Community Assistantship Program. Milaca Downtown Revitalization Community Assistantship Program Milaca Downtown Revitalization Prepared in partnership with City of Milaca Prepared by Zachary Jorgensen Research Assistant University of Minnesota December, 2009 CAP Report

More information

Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018

Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018 Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018 WHAT IS A BOND ELECTION? Provide communities an opportunity to vote to give the Board of Trustees authority

More information

1. Parks & Recreation Neighborhood Parks Community Parks Special Use Sites 2. Open Space 3. Trails

1. Parks & Recreation Neighborhood Parks Community Parks Special Use Sites 2. Open Space 3. Trails Appendix A: Park Classifications The intent of parks and recreation classifications is to aid in making acquisition and design decisions for park sites, facilities and the organization of recreation space

More information

Illustrative Campus Plan with Proposed Development

Illustrative Campus Plan with Proposed Development Illustrative Campus Plan with Proposed Development Approved Compiled Plan January 2003 Figure IV-52 89 The supportive relationship and interaction between the campus and the surrounding community is an

More information

Briar Crest Elementary

Briar Crest Elementary Promises Kept This document includes partial lists of major projects completed at Pattonville Schools since 1986 as part of past bond issues approved by the Pattonville community. Briar Crest Elementary

More information

ADA Checklist AIRPORTS

ADA Checklist AIRPORTS ADA Checklist AIRPORTS 205 North 400 West Salt Lake City, Utah 84103 (800) 662 9080 (800) 550 4182 TTY www.disabilitylawcenter.org Access Airport Name New Construction (ADAAG 10.4, 10.4.1) Yes No Are ramps,

More information

ADA Checklist Transient Lodging, Hotels, Motels, Inns, Boarding Houses, Dormitories and similar facilities

ADA Checklist Transient Lodging, Hotels, Motels, Inns, Boarding Houses, Dormitories and similar facilities ADA Checklist Transient Lodging,, Motels, Inns, Boarding Houses, Dormitories and similar facilities 205 North 400 West Salt Lake City, Utah 84103 (800) 662 9080 (800) 550 4182 TTY www.disabilitylawcenter.org

More information

Doing Business with Bartlett Cocke General Contractors

Doing Business with Bartlett Cocke General Contractors Doing Business with Bartlett Cocke General Contractors FACTS 59 5 580 $ 700 YEARS OFFICES STATEWIDE EMPLOYEES MILLION IN REVENUE Established in 1959 by Bartlett Cocke, Jr. San Antonio (headquarters) Austin

More information

FY Capital Improvement Program Arroyo Projects

FY Capital Improvement Program Arroyo Projects FY 219-223 Capital Improvement Program FY 218 FY 219 FY 22 FY 221 FY 222 FY 223 1 2 3 4 5 6 7 8 9 1 Hahamongna - Implement Master Plan - Oak Grove Area Improvements (7756) Hahamongna - Implement Master

More information

ARROYO PROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET

ARROYO PROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET A RROYO P ROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET FISCAL YEARS 214-218 HAHAMONGNA Priority Description 1 Hahamongna Watershed Park - Implement Master Plan 211,6 211,6 (77565) 2 Hahamongna -

More information

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000 1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades Allowance $300,000 C. Tilden Entrance Upgrades D. Door and Glass Improvements Allowance $500,000 E. Alert

More information

VISION PLAN PRESENTATION - SEPTEMBER 28, 2013

VISION PLAN PRESENTATION - SEPTEMBER 28, 2013 AREAS OF IMPROVEMENT E A POOL HOUSE POOL DECK B B MAIN BUILDING UPPER PLAZAS A D F G C MAJOR BLEACHERS DUGOUTS FIELD MAIN COURTYARD D REGGIE PARK C E SPORT COURT ADA RAMP H F G H TENNIS COURTS KITCHENETTE

More information

Overview and Update of the Rutgers-New Brunswick Physical Master Plan. January 2015

Overview and Update of the Rutgers-New Brunswick Physical Master Plan. January 2015 Overview and Update of the Rutgers-New Brunswick Physical Master Plan January 2015 Failure To Plan, is Planning For Failure Winston Churchill 2 Good Planning; The Key to Success 3 The university physical

More information

Today Land & People. Northeast Nampa Gateway District. Employment. Land Use Characteristics. Demographics. Current Zoning

Today Land & People. Northeast Nampa Gateway District. Employment. Land Use Characteristics. Demographics. Current Zoning Today Land & People Employment Major employers include Saint Alphonsus, the College of Western Idaho, the Auto Mall, Sorrento Lactalis and Walmart. 3,004 jobs in 2010 (COMPASS-CIM 2040 TAZ data) 4,345

More information

4.1 Build Alternative 1 Construction Phasing

4.1 Build Alternative 1 Construction Phasing SECTION 4 Implementation Plan This section discusses potential segmentation of the build alternatives into multiple projects for implementation of improvements to the NSH from Rabbit Creek Road to 36th

More information

COMMUNICATION URBAN DESIGN REVIEW BOARD CITY OF DES MOINES, IOWA MAY 16, 2017 MEETING

COMMUNICATION URBAN DESIGN REVIEW BOARD CITY OF DES MOINES, IOWA MAY 16, 2017 MEETING COMMUNICATION URBAN DESIGN REVIEW BOARD CITY OF DES MOINES, IOWA MAY 16, 2017 MEETING Subject: Recommendation Prepared by: PRELIMINARY DESIGN REVIEW OF LOCUST STREET BRIDGE CONSTRUCTION & COURT AVENUE,

More information

DUNCAN STUDENT CENTER. Emergency Action Plan

DUNCAN STUDENT CENTER. Emergency Action Plan DUNCAN STUDENT CENTER Emergency Action Plan August 21, 2017 DUNCAN STUDENT CENTER - EMERGENCY ACTION PLAN An emergency action plan describes the actions employees should take in case of fire or other emergency

More information

Facility Improvements

Facility Improvements AP-SI-03 BICYCLE RACK ADDITION AP-SI-05 EXTERIOR BENCH ADDITIONS Installation of bike rack will allow for designated and secure storage of bicycles. Installation of exterior benches will provide an outdoor

More information

NASSAU COMMUNITY COLLEGE. Garden City, New York Capital Committee Meeting January 12, :00 PM

NASSAU COMMUNITY COLLEGE. Garden City, New York Capital Committee Meeting January 12, :00 PM NASSAU COMMUNITY COLLEGE Garden City, New York 11530 Capital Committee Meeting January 12, 2016 5:00 PM 1. Review and Approval of December 8, 2015 minutes: Chair: Do I have a motion to approve the minutes

More information

2010 Campus Master Plan Update - USF TAMPA Campus Master Plan Update USF TAMPA

2010 Campus Master Plan Update - USF TAMPA Campus Master Plan Update USF TAMPA 2010 Campus Master Plan Update USF TAMPA Purpose of the Update: Required by the Board of Governors Provides a framework for planned growth in a context of sustainability Master Plan Update Approval Process

More information

Master Facility Planning Update School Board Meeting May 26, 2016

Master Facility Planning Update School Board Meeting May 26, 2016 Master Facility Planning Update School Board Meeting May 26, 2016 Master Facilities Committee Overview Reflection of Committee Work Review of District Wide Facility Issues Identified District Wide Facility

More information

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate Health & Safety 1,399,000 Academics & Program 17,140,800 Physical Education & Athletics 5,922,000 Building Infrastructure 3,103,800 Site Infrastructure 1,049,600 TOTAL SCOPE OF WORK 28,615,200 PROPOSED

More information

Lowe Park Master Plan Update Marion, IA August 25 th, 2011

Lowe Park Master Plan Update Marion, IA August 25 th, 2011 Lowe Park Master Plan Update Marion, IA August 25 th, 2011 Lowe Park Master Plan Update Concept Plan - June 1 st, 2011 Agenda 1 - INTRODUCTION Vision Statement Aerial of Existing Condition 2 MASTER PLAN

More information

BUSINESS DISTRICT DESIGN GUIDELINES

BUSINESS DISTRICT DESIGN GUIDELINES Des Plaines, Illinois Prepared for the City of Des Plaines by: The Lakota Group Laurie Marston, AICP March 2005 Section 5: Streetscape Elements Business District Design Guidelines STREETSCAPE ELEMENTS

More information

CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY

CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY NEW MEXICO HIGHLANDS UNIVERSITY CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY 27 2010 MASTER PLANNING GOALS TO BALANCE THE STRATEGIC GOALS OF THE UNIVERSITY WITH THE PHYSICAL CAMPUS through the assessment

More information

REPORT CARD TO THE COMMUNITY MAY 15, 2018

REPORT CARD TO THE COMMUNITY MAY 15, 2018 REPORT CARD TO THE COMMUNITY MAY 15, 2018 O On May 10, 2014 voters in Greenville ISD approved a $72,275,000 bond election. BOND PROPOSAL PROJECT BOND AMOUNT CONSTRUCT A NEW BOWIE ELEMENTARY SCHOOL $17,600,000

More information

South Davis County COMMUNITY SPOTLIGHT

South Davis County COMMUNITY SPOTLIGHT South Davis County COMMUNITY SPOTLIGHT Davis/SLC Community Connector Bus Rapid Transit line connecting SLC & Davis County RTP Phase 1 Project Generate 3,100 average weekday riders Relieve congestion on

More information

Wold Architects and Engineers. 332 Minnesota Street Suite W2000 Saint Paul, MN

Wold Architects and Engineers. 332 Minnesota Street Suite W2000 Saint Paul, MN Wold Architects and Engineers 332 Minnesota Street Suite W2000 Saint Paul, MN 55101 651 227 7773 PLANNERS ARCHITECTS ENGINEERS ISD #15 St. Francis Area Schools East Bethel Elementary School Additions and

More information

Welcome to the. Open House

Welcome to the. Open House Welcome to the 5th Street to Kinsman Road Open House November 14 5:30 7:00 p.m. Please sign in Project Overview In December 2016, City Council adopted SW 5th Street as the preferred alignment to connect

More information

4 Semi-Private & Private Open Spaces

4 Semi-Private & Private Open Spaces 4 Semi-Private & Private Open Spaces 4.1 Semi-private Open Space 4.1.1 Common Courtyards The common courtyards for each complex will be designed and programmed for the typical owners living there. They

More information

Foothill College Site Improvements Foothill De Anza Community College District Board of Trustees Presentation May 7, 2012

Foothill College Site Improvements Foothill De Anza Community College District Board of Trustees Presentation May 7, 2012 Foothill College Site Improvements Foothill De Anza Community College District Board of Trustees Presentation May 7, 2012 1 of 17 PRESENTATION OVERVIEW - Campus Outreach Efforts - Project Timeline & Construction

More information

SF REC & PARK STANYAN STREET IMPROVEMENT. Supervisor London Breed District 5. Project Manager Dan Mauer Recreation and Parks Department

SF REC & PARK STANYAN STREET IMPROVEMENT. Supervisor London Breed District 5. Project Manager Dan Mauer Recreation and Parks Department SF REC & PARK STANYAN STREET IMPROVEMENT PLANNING PRESENTATION WEDNESDAY, OCTOBER 19, 2016 Supervisor London Breed District 5 Project Manager Dan Mauer Recreation and Parks Department Design Team William

More information

Subcampus Recommendations

Subcampus Recommendations T he campus is is comprised of three major areas. These subcampus areas are known as WestCampus, South Campus, Campus Oakland and Drive East Campus. and Future East growth Campus. requires a Future careful

More information

Pomegranate Center and Tully s Coffee Gathering Grounds program partnership Butterfly Park Gathering Place Project Preliminary Design I.

Pomegranate Center and Tully s Coffee Gathering Grounds program partnership Butterfly Park Gathering Place Project Preliminary Design I. Pomegranate Center and Tully s Coffee Gathering Grounds program partnership Pomegranate Center, ARTS /A Reason To Survive, Olivewood Gardens, San Diego Foundation, and City of National City Butterfly Park

More information

2014 Bond Project Guide

2014 Bond Project Guide 2014 Bond Project Guide Bush Elementary School Page 1 Instructional Technology Computers, Projectors, Mobile Carts, Document Cameras and Printers Wireless Connectivity New Construction New Tech Center

More information

The McCoppin Hub. Boor Bridges Architecture

The McCoppin Hub. Boor Bridges Architecture The McCoppin Hub Boor Bridges Architecture Comments on the Original Concept: - Unify - explore means of making the layout feel less broken up and compartmentalized. Suggestions include: remove one level

More information

CRA Five Year Capital Improvement Plan. September 2, 2015

CRA Five Year Capital Improvement Plan. September 2, 2015 CRA Five Year Capital Improvement Plan September 2, 2015 Downtown CRA Recap Introduction Downtown Capital Improvement Projects: $2.6M available for FY 2016. Includes the recent loan of $2.0M. DOWNTOWN

More information

California Environmental Quality Act (CEQA) Environmental Review Process

California Environmental Quality Act (CEQA) Environmental Review Process California Environmental Quality Act (CEQA) Environmental Review Process Los Angeles Union Station Forecourt and Esplanade Improvements constitute a Project Los Angeles County Metropolitan Transportation

More information

BENJAMIN BANNEKER PARK FRAMEWORK PLAN (PLAN ADOPTION)

BENJAMIN BANNEKER PARK FRAMEWORK PLAN (PLAN ADOPTION) BENJAMIN BANNEKER PARK FRAMEWORK PLAN (PLAN ADOPTION) COUNTY BOARD MEETING DECEMBER 16, 2017 County Board Consideration: Adopt the Benjamin Banneker Park Framework Plan and Design Guidelines Framework

More information

SF REC & PARK STANYAN STREET IMPROVEMENT. Supervisor London Breed District 5. Project Manager Dan Mauer Recreation and Parks Department

SF REC & PARK STANYAN STREET IMPROVEMENT. Supervisor London Breed District 5. Project Manager Dan Mauer Recreation and Parks Department SF REC & PARK STANYAN STREET IMPROVEMENT COMMUNITY MEETING #3 THURSDAY, JANUARY 25 TH, 2018 Supervisor London Breed District 5 Project Manager Dan Mauer Recreation and Parks Department Design Team William

More information

The University District envisions, in its neighborhood

The University District envisions, in its neighborhood Envisioning the University District Link Light Rail in Seattle s neighborhoods CIY OF SEALE CONCEP-LEVEL SAION AREA PLANNING RECOMMENDAION RESOLUION # 30165 EXHIBI L Vision 08.2000 he University District

More information

Master Project List Report

Master Project List Report Blue Hills Elementary School 01-8215 Site Utilities Replacement $52,835 01-8502 Modernization $3,135,933 01-8525 Exterior Painting $181,478 01-8552 Kindergarden Fencing $13,180 Install new backflow preventer.

More information

Introduction. Community Outreach Approach. Sacramento Valley Station Master Plan. Online Questionnaire Summary of Feedback.

Introduction. Community Outreach Approach. Sacramento Valley Station Master Plan. Online Questionnaire Summary of Feedback. Introduction Located in the northwest sector of downtown Sacramento, the Sacramento Valley Station (SVS) is the primary rail station in northern California and the seventh busiest station in the country.

More information

29 Bella Fontaine Park

29 Bella Fontaine Park 29 Bella Fontaine Park 9565 Bellefontaine Road St. Louis County Parks Master Plan Planning Zone 2 Visit Date: July 2016 Page 1 129 Bella Fontaine Park 9565 Bellefontaine Road St. Louis County Parks Master

More information

UNCW CAMPUS MASTER PLAN

UNCW CAMPUS MASTER PLAN UNCW CAMPUS MASTER PLAN JULY 27, 2017 MASTER PLAN FRAMEWORK RECOMMENDATIONS BOARD OF TRUSTEES PRESENTATION UNCW Campus Master Plan Update Board of Trustees Presentation July 27, 2017 The attached Campus

More information

AvalonBay Communities + BRIDGE Housing. Mission Housing Habitat for Humanity Pacific Union Development Corporation

AvalonBay Communities + BRIDGE Housing. Mission Housing Habitat for Humanity Pacific Union Development Corporation AvalonBay Communities + BRIDGE Housing Mission Housing Habitat for Humanity Pacific Union Development Corporation Tonight s Agenda Recap of discussion from last CAC meeting Updates on meetings with Stakeholders

More information

Richard Henry Lee Elementary School

Richard Henry Lee Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Planning Stage. Mosaic Park. Long Term Project. Restoration of 4 Mile Run. Planning Stage. Herndon and 13 th. Project Underway. Clarendon Central Park

Planning Stage. Mosaic Park. Long Term Project. Restoration of 4 Mile Run. Planning Stage. Herndon and 13 th. Project Underway. Clarendon Central Park Planning Stage Long Term Project Planning Stage Project Underway Mosaic Park Restoration of 4 Mile Run Herndon and 13 th Clarendon Central Park Arlington County Parks, Recreation and Cultural Resources

More information

Welcome to Greenwood Village Corporate Capital of Colorado

Welcome to Greenwood Village Corporate Capital of Colorado Welcome to Greenwood Village Corporate Capital of Colorado Greenwood Village Setting Incorporated: 1950 Land Area: 8.4 sq. miles + / - Budget $35M Debt $0 Reserve $20M Population Daytime: 50,000 Residents:

More information

Neighborhood Districts

Neighborhood Districts NEIGHBORHOOD DISTRICTS SEVEN MAIN DISTRICTS Neighborhood Districts While the Development Plan provides a broad-scale overview of the neighborhood, this section focuses on uses and relationships at the

More information

PROJECTS UNDER CONSTRUCTION

PROJECTS UNDER CONSTRUCTION Project Name Project Status Project Funding Project Manager PJ 2144 Clayton Rd-Treat Blvd Intersection Improvements Widen the Clayton Road/Treat Blvd intersection and upgrade the traffic signal. Construction

More information

Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15)

Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) School/Department FY 16 FY 17 FY18 FY19 FY20 Chariho Regional High School FY 16 FY 17 FY18 FY19 FY20 *Repair Bleachers

More information

Encumbered Balance (E-D) Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765, $635, $635, $130, $0.

Encumbered Balance (E-D) Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765, $635, $635, $130, $0. Branham High School Budget Remaining 1 906030 Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765,473.00 $635,342.00 $635,342.00 $130,131.00 $0.00 2 970205 Branham Interim Housing - 12 Portable

More information

NECC Strategic Plan Goal Team 1: Develop a Comprehensive Campus in Downtown Lawrence

NECC Strategic Plan Goal Team 1: Develop a Comprehensive Campus in Downtown Lawrence NECC Strategic Plan Goal Team 1: Develop a Comprehensive Campus in Downtown Lawrence Meeting Minutes April 9, 2014 Lawrence Campus Backfill Subcommittee Updates Martha Leavitt/Dick Goulet Revised goal

More information

Wilson County Projects

Wilson County Projects Wilson Projects SR-109 Reconstruction & Widening TIP # 2009-72-036 Road Widening TDOT Wilson Length 3.50 Regional Plan ID 1072-348-2 Air Quality Status Non-Exempt TDOT PIN 100281.03 $34,000,000.00 SR-109

More information

PALO ALTO HIGH SCHOOL Palo Alto Unified School District MEETING NOTES. DATE: 21 September Palo Alto HS Update

PALO ALTO HIGH SCHOOL Palo Alto Unified School District MEETING NOTES. DATE: 21 September Palo Alto HS Update PALO ALTO HIGH SCHOOL Palo Alto Unified School District MEETING NOTES DATE: 21 September 2010 SUBJECT: Landscape Subcommittee Meeting Palo Alto HS Update The purpose of the meeting was to update the Landscape

More information

Comprehensive Roadside Management Project (CRMP)

Comprehensive Roadside Management Project (CRMP) Caroline County Comprehensive Roadside Management Project (CRMP) DEPARTMENT OF PUBLIC WORKS/UTILITIES 12613 Mill Creek Rd Ruther Glen, Virginia 22427 CARMEL CHURCH CRMP MASTER PLAN Table of Contents Introduction

More information

UNIVERSITY OF OREGON OREGON BACH FESTIVAL CPC Presentation February 11, 2016

UNIVERSITY OF OREGON OREGON BACH FESTIVAL CPC Presentation February 11, 2016 UNIVERSITY OF OREGON OREGON BACH FESTIVAL CPC Presentation February 11, 2016 LARGE SCALE CAMPUS TRANSPORTATION SITE ARRANGEMENT BUILDING DESIGN Campus Trees Good Neighbor Main Gateways Open-Space Framework

More information

MEMORANDUM. This memo deals with proposed amendments to previously issued Development Permit No for Park Royal North.

MEMORANDUM. This memo deals with proposed amendments to previously issued Development Permit No for Park Royal North. MEMORANDUM Date: August 28, 2015 Our File: 1010-20-15-062 To: Design Review Committee From: Lisa Berg, Senior Community Planner Re: Amendment to Development Permit for Park Royal North This memo deals

More information

LINCOLN COUNTY COMMONS - REVISED MASTER PLAN. Lincoln County Public Meetings June 26-27, 2018, 6pm

LINCOLN COUNTY COMMONS - REVISED MASTER PLAN. Lincoln County Public Meetings June 26-27, 2018, 6pm LINCOLN COUNTY COMMONS - REVISED MASTER PLAN Lincoln County Public Meetings June 26-27, 2018, 6pm PROJECT OVERVIEW Lincoln County is preparing a Refined Master Plan for facilities at the Lincoln County

More information

Access Statement. Royal Botanic Garden Edinburgh Access Statement January 1, 2014

Access Statement. Royal Botanic Garden Edinburgh Access Statement January 1, 2014 Access Statement The Royal Botanic Garden Edinburgh Arboretum Place/Inverleith Row Edinburgh EH3 5LR +44 (0) 131 248 2909 www.rbge.org.uk 1 Contents 1.0 Our Accessibility Promise to You 3 2.0 A Map of

More information

12 th Pacific Science Inter Congress HEALTH AND SAFETY INFORMATION BOOKLET FOR PARTICIPANTS

12 th Pacific Science Inter Congress HEALTH AND SAFETY INFORMATION BOOKLET FOR PARTICIPANTS 12 th Pacific Science Inter Congress HEALTH AND SAFETY INFORMATION BOOKLET FOR PARTICIPANTS 1 Occupational Health and Safety Each delegate has a duty of care to fellow delegates by ensuring that they shall,

More information

City of San Juan Capistrano PROJECT PRESENTATION NORTHWEST OPEN SPACE COMMUNITY PARK (CIP 09209) March 22, 2016 FOR THE PROJECT PRESENTATION

City of San Juan Capistrano PROJECT PRESENTATION NORTHWEST OPEN SPACE COMMUNITY PARK (CIP 09209) March 22, 2016 FOR THE PROJECT PRESENTATION City of San Juan Capistrano PROJECT PRESENTATION PROJECT PRESENTATION FOR THE NORTHWEST OPEN SPACE COMMUNITY PARK (CIP 09209) PLANNING COMMISSION 1 PROCESS & OBJECTIVES A. Develop a new Concept Plan for

More information

CAMPUS MASTER PLAN UPDATE Transportation Element Focus Group Meeting #3

CAMPUS MASTER PLAN UPDATE Transportation Element Focus Group Meeting #3 CAMPUS MASTER PLAN UPDATE 2010-2020 Transportation Element Focus Group Meeting #3 December 2012 5 03 December 2012 1 Campus Master Plan 2010-2020 : Transportation Agenda 1. MMC 2. EC a. Inventory & Analysis

More information

TIFT COUNTY SCHOOLS E-SPLOST HISTORY

TIFT COUNTY SCHOOLS E-SPLOST HISTORY TIFT COUNTY SCHOOLS E-SPLOST HISTORY July 1, 1997 June 30, 2002 $28,766,187.16 collected July 1, 2002 June 30, 2007 $39,025,830.10 collected July 1, 2007 June 30, 2012 $41,886,155.46 collected July 1,

More information