Evaluation of How O&M Costs Vary for Alternative Flood Control Strategies
|
|
- Adam Sutton
- 5 years ago
- Views:
Transcription
1 Evaluation of How O&M Costs Vary for Alternative Flood Control Strategies Fargo-Moorhead Diversion Channel ASFPM Conference June 13, 2013 Matt Redington, PE Jeremy Cook HDR Engineering
2 Red River of the North Watershed Insert map showing Red River Watershed and various states Get this map from Ted Shannon HMS project
3 Flood Fighting Flood Stage = 18 feet (19 of the past 20 years) 29 of 90 previous years reached flood stage 1997, 2009, 2011, 2013
4 Fargo and Moorhead Red River Fargo, North Dakota Moorhead, Minnesota
5 Red River Valley Flooding
6 Regular Flood Fighting
7 The Fargo Arena
8 Diversion Project Features Channel In-Town Improvements Buyouts Levees Interior drainage Pump stations Storage
9 Fargo-Moorhead Diversion Channel Is a Monumental Effort Total Cost: $2 Billion USACE O&M Estimate: $3,559,000
10 Fargo-Moorhead Diversion Channel O&M Considered in Design Two Ways O&M Costs Entered Planning: What are the O&M cost impacts of varying flood control strategies? What are the cost savings for Alternate Flood Protection Measures?
11 Operations Defined Inventory Administration Inspections and Monitoring Public Communications Heavy Equipment and Generators Supply and HR Management Temporary Levees Sandbagging
12 Operations Defined Revenue Losses Campgrounds Admission Golf Courses Greens Fees Athletic Facility Fees
13 Maintenance Defined Clean up: Streets Open spaces Repair: Levee Embankments Roadway Embankments Topsoil and Turf Repair Ditch cleanout Debris Removal
14 Maintenance Clean up Paved Surfaces Linear Feet of Street RS Means
15 Maintenance Clean up Open Space Assumed crew Estimated wages Assumed acres/hr
16 Maintenance Roadway Embankment Repair Ditch Cleanout and Debris Removal
17 Calculating Operations Costs Existing Conditions Proposed Alternatives FEMA Cost Data Economist Cost Curves
18 Constructing Cost Curves Insert Figures 2 and 3
19 Calculating New O&M Costs Calculated Expected Annual O&M Costs Similar approach that HEC-FDA uses to estimate flood damages How its calculated: Variable O&M is estimated for each exceedance O&M Costs are weighted by the exceedance probability Sum the probability weighted O&M Costs
20 Exceedance and O&M Cost Curve Expected Annual O&M is the sum of the O&M Costs weighted by the exceedance probability across the curve $ s O&M Exceedance
21 Baseline Costs to Compare The Flood Control Strategy of the System $4,800,000 Pre Mitigation - Total O&M $95,000,000 $4,600,000 $4,400,000 $90,000,000 Expected Annual $4,200,000 $4,000,000 $85,000,000 $80,000,000 Present Value $3,800,000 $3,600,000 $75,000,000 $3,400, Year Operational Stage $70,000,000 EA PV
22 Determining Costs Savings for Alternate Flood Protection Measures
23 Determining Costs Savings for Alternate Flood Protection Measures
24 Determining Costs Savings for Alternate Flood Protection Measures Stage Before Mitigation With Mitigation Option 1 PV O&M Cost PV O&M Cost ($ Millions) ($ Millions) % Reduction % % % % % % % %
25 Summary O&M costs should be a design consideration Alternate flood control strategies can result in varying O&M costs Historical flood fighting data can be a useful tool for proposed conditions
26 Questions?
27 Extra photos for incorporation into presentation
28 Base Condition Results 100 Year Event Operational Stage Total Operations and Maintenance Cost of 100 Year Event Expected Annual Cost Present Value* 30 4,194,000 3,893,000 78,525, ,660,000 4,174,000 84,191, ,802,000 4,259,000 85,906, ,010,000 4,306,000 86,854, ,417,000 4,406,000 88,871, ,159,000 4,524,000 91,252, ,858,000 4,545,000 91,677, ,497,000 4,554,000 91,857,000
29 Costs Not Included Lost Business Revenue Road Closures Private Property In-Town Cleanup Golf Courses Farmland
30 Operations Defined
31 Calculating Operations Costs Costs removed for stages<30 feet Daily average cost per foot of inundation Estimated that 80% of costs were for temporary measures and 20% for permanent measures Divided costs by linear feet of protection impacted by flooding
32 Discount Factor for Smaller Events In Town Flood 100-year Flood Protection Level River Stage
33 Valuing Change in O&M Costs Expected Annual O&M is the sum of the O&M Costs weighted by the exceedance probability across the curve
34 Exceedance Relationships Exceedance 100 Year Event Operational Stage
35 Flood Protection
PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM
PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM Project ID Number: 25-5 Problem: Stormwater collected from the neighborhood upstream is released at 9 Muirfield Lane and flows west toward
More informationCity of Norfolk Coastal Flood Mitigation Program. March 13, 2013
City of Norfolk Coastal Flood Mitigation Program March 13, 2013 Topics Brief overview of Norfolk s Coastal Flood Program Data-driven analysis and decision making City-wide vulnerability, project concepts,
More information7th Avenue Creek Master Plan Development Project. City of St. Charles, IL. IAFSM CONFERENCE March 14, 2018 MARKET
7th Avenue Creek Master Plan Development Project MARKET City of St. Charles, IL IAFSM CONFERENCE March 14, 2018 7 TH AVENUE CREEK PROJECT AREA 2 2008 RAIN EVENT 3 RESIDENTIAL STRUCTURE FLOODING COMMERCIAL
More informationADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET ARROYO PROJECTS
ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET ARROYO PROJECTS HAHAMONGNA FY 212-216 Capital Improvement Program Priority Description Total Estimated Costs Appropriated Through FY 211 Adopted FY 212 FY 213
More informationCity of Elmhurst. City of Elmhurst. Storm Sewer System Workshop November 22, 2010
City of Elmhurst City of Elmhurst Storm Sewer System Workshop November 22, 2010 1 City of Elmhurst Watershed divide (green dashed line) through Elmhurst Area east of divide drains to Addison Creek Area
More informationPROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM
PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM Project Name: 362 Featherstone Dr Project ID Number: 27-3 Problem: Anecdotal evidence suggests a natural spring exists in the backyard
More informationTown of Lyons Parks Flood Recovery Planning Process. Photograph courtesy of Ed Bruder
Town of Lyons Parks Flood Recovery Planning Process Photograph courtesy of Ed Bruder Lyons Parks and Recreation Flood Recovery Update 1. Meadow Park Phase II - Project PW20B1 Estimated Completion: Summer
More informationThe Economic Value of Protected Open Space in Southeastern Pennsylvania
The Economic Value of Protected Open Space in Southeastern Pennsylvania SUMMARY REPORT Looking at the landscape. 200,000+ Acres Protected in Southeastern Pennsylvania. 30% Privately Owned or Eased Lands
More informationAppendix E Preliminary Location Hydraulic Study
Appendix E Prepared for: State of Alaska Department of Transportation and Public Facilities Prepared by: HDR Alaska, Inc. 2525 C Street, Suite 305 Anchorage, Alaska 99503 February 2014 This page intentionally
More informationBlake C. Kronkosky, PE, Ph.D.
Blake C. Kronkosky, PE, Ph.D. Blake.Kronkosky@statetecheng.com, CELL (512) 663-1954 Education Ph.D., Civil Engineering, Texas Tech University, May 2018: An Engineer's Guide for Estimating 1-Day, 100-Year
More informationC. WATER. 1. Surface Water Runoff. See Section C.3, Flood Hazard/Mudflow Hazard, page Ground Water
C. WATER 1. Surface Water Runoff See Section C.3, Flood Hazard/Mudflow Hazard, page 67. 2. Ground Water Determined not significant by the October 1984 and January 1999 Initial Studies conducted by the
More informationStormwater Management at The University of New Orleans
University of New Orleans ScholarWorks@UNO DRU Workshop 2013 Presentations Disaster Resistant University Workshop: Linking Mitigation and Resilience Conferences and Workshops 3-1-2013 Stormwater Management
More information3/7/2013. Compliance & Sustainability
Overview www.kieser associates.com Celebrating 20 Years of Excellence in Environmental Science & Engineering WMU Arcadia Creek Stormwater Treatment and Floodplain Enhancement Project DEQ #2008 0018 and
More informationRESILIENCY, ADAPTATION, & SUSTAINABILITY AT THE CITY OF ST. AUGUSTINE
RESILIENCY, ADAPTATION, & SUSTAINABILITY AT THE CITY OF ST. AUGUSTINE PROGRAM UPDATE JANUARY 14, 2019 MICHAEL G. CULLUM, P.E. DIRECTOR, PUBLIC WORKS PROGRESSION OF PLANNING FOR RESILIENCY / ADAPTATION
More informationSimulating the Effects of Ridge Elevation and Geometry on Ridge Slough Landscape Hydrology
Simulating the Effects of Ridge Elevation and Geometry on Ridge Slough Landscape Hydrology Subodh Acharya 1, David A. Kaplan 2, Matthew J. Cohen 1, James W. Jawitz 3, 1 University of Florida, School of
More informationCanyon Lake Master Plan Revision Public Information Meeting March 18, 2016
Canyon Lake Master Plan Revision Public Information Meeting March 18, 2016 Marcus Schimank Canyon Lake Manager Capital Regional Office U.S. Army Corps of Engineers Fort Worth District US Army Corps of
More information13 Maintenance and Operations Plan 223
222 13 Operations Maintenance and Plan 223 Chapter 13 MAINTENANCE AND OPERATIONS PLAN 13.1 Stewardship The Minneapolis Park and Recreation Board (MPRB) is the steward of a nationally-acclaimed park system.
More informationPrado Ranch North Common Open Space Tentative Map. Washoe County Planning Commission July 3, 2018
Prado Ranch North Common Open Space Tentative Map Washoe County Planning Commission July 3, 2018 Site Characteristics Intersection of Chickadee and Lemmon Drive ~1 mile north of Deodar/Lemmon Drive intersection
More informationTowards a Resilient Stormwater Future: Building Back from Hurricane Irene and Tropical Storm Lee. October 15, 2015 VUSP Symposium
Towards a Resilient Stormwater Future: Building Back from Hurricane Irene and Tropical Storm Lee October 15, 2015 VUSP Symposium Russ Dudley, P.E., LEED AP Environmental Engineer Presentation Outline Impacts
More informationARROYO PROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET
A RROYO P ROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET FISCAL YEARS 214-218 HAHAMONGNA Priority Description 1 Hahamongna Watershed Park - Implement Master Plan 211,6 211,6 (77565) 2 Hahamongna -
More informationCity of Waco Stormwater Management Regulations
1.0 Applicability: City of Waco Stormwater Management Regulations These regulations apply to all development within the limits of the City of Waco as well as to any subdivisions within the extra territorial
More informationSTORM WATER UTILITY FREQUENTLY ASKED QUESTIONS
STORM WATER UTILITY FREQUENTLY ASKED QUESTIONS In 2007, the City Council adopted Ordinance No. 1155 establishing a storm water utility in the City. No fee structure was adopted at that time. The idea of
More informationPublic Information Centre # 2 Coronation Park Drainage Improvements Town of Oakville Municipal Class Environmental Assessment
November 26, 2014 Public Information Centre # 2 Coronation Park Drainage Improvements Town of Oakville Municipal Class Environmental Assessment Study Area & Drainage System Legend Coronation Project Park
More informationFARGO-MOORHEAD METRO AREA FLOOD RISK MANAGEMENT PROJECT CEMETERY MITIGATION PLAN. U.S. Army Corps of Engineers, St Paul District
FARGO-MOORHEAD METRO AREA U.S. Army Corps of Engineers St. Paul District FLOOD RISK MANAGEMENT PROJECT CEMETERY MITIGATION PLAN U.S. Army Corps of Engineers, St Paul District Draft Report June 2015 Page
More informationImproving an Urban Watershed The Past, Present and Future of Addison Creek
Improving an Urban Watershed The Past, Present and Future of Addison Creek IAFSM Conference March 14, 2018 Stormwater Management 1 Stormwater Management 2 PAST Reservoirs and Channel Improvements Stormwater
More informationACTION PLAN FOR RETROFITTING THE EXISTING MS4 WITH STRUCTURAL BMPS
ACTION PLAN FOR RETROFITTING THE EXISTING MS4 WITH STRUCTURAL BMPS FEBRUARY 16, 2017 For the City and County of Honolulu MS4 NPDES Permit No. HI S000002 STORMWATER RETROFIT BMP OPPORTUNITIES Permit Requirements
More informationPollutant Removal Benefits
Bioswales Bioswales Similar to biocells, but have a slight, but positive grade toward an outlet Designed to convey the WQv event at very low velocities Promote filtration through native vegetation, infiltration
More informationFisher Slough Tidal Marsh Restoration Project Scaling Down the Restoration Planning & Analysis Framework to Evaluate Project Alternatives
Fisher Slough Tidal Marsh Restoration Project Scaling Down the Restoration Planning & Analysis Framework to Evaluate Project Alternatives Project Sponsor/Partners The Nature Conservancy Dike District #3
More informationNorthern Branch Corridor SDEIS March 2017
Northern Branch Corridor SDEIS March 2017 15. 15.1. Chapter Overview 15.1.1. Introduction This chapter discusses changes to the Preferred Alternative resulting in the potential for project improvements
More information2011 ASLA Design Awards. Westside Creeks Restoration Plan Merit Award AECOM, Fort Collins. Planning & Urban Design
2011 ASLA Design Awards Westside Creeks Restoration Plan Merit Award AECOM, Fort Collins Planning & Urban Design Project Fact Sheet Category of Entry: Rotating Specialty Award: 2011 2011 ASLA Colorado
More informationSTREAM BUFFERS
88-415 STREAM BUFFERS 88-415-01 PURPOSE In the Kansas City region and throughout the nation, vegetated stream buffers have been clearly shown to protect stream stability and related infrastructure, improve
More informationSnail Lake Overflow/Grass Lake Optimization Studies. May 2, Ramsey-Washington Metro Watershed District.
Snail Lake Overflow/Grass Lake Optimization Studies May 2, 2018 Ramsey-Washington Metro Watershed District. Purpose Purpose: 1. Summarize what s been done 2. Update board on cost vs. benefits of various
More informationLower Don River West Remedial Flood Protection Project TABLE OF CONTENTS. Page. Executive Summary
TABLE OF CONTENTS Page Executive Summary 1.0 INTRODUCTION...1-1 1.1 Purpose of the Undertaking...1-1 1.2 Study Area Description...1-1 1.3 Description of the Undertaking...1-1 1.4 Rationale for the Undertaking...1-2
More informationHAZARD MITIGATION GOALS AND OBJECTIVES
SEWRPC Community Assistance Planning Report No. 282, 2nd Edition CITY OF MILWAUKEE ALL HAZARDS MITIGATION PLAN UPDATE Chapter IV HAZARD MITIGATION GOALS AND OBJECTIVES [NOTE: Throughout this plan update
More informationI. INTRODUCTION. identify long-term capital improvements and rehabilitation measures for the existing drainage system;
I. INTRODUCTION The Town of Windsor, Colorado is presently experiencing rapid growth and development within the boundaries of several of its major drainage basins. As growth continues within these basins,
More informationDayton Transportation Plan 2016 Update
WENCK File #3164-30 February 9, 2016 Dayton Transportation Plan 2016 Update Prepared for: City of Dayton, MN 12260 S. Diamond Lake Road Dayton, MN 55327 Prepared by: WENCK Associates, Inc. 1800 Pioneer
More informationTown of Vershire Road Erosion Inventory Report
Town of Vershire Road Erosion Inventory Report Taylor Valley Road. Photo taken by TRORC staff. Prepared by: 128 King Farm Road Woodstock, VT 05091 Inventory and report funded by the Vermont Agency of Transportation
More informationEMERGENCY ACTION PLAN
EMERGENCY ACTION PLAN Lake Sunapee Dam Sunapee, NH Dam #229.04 (Class B Dam) Water Division Lake Sunapee Dam - Sunapee, NH TABLE OF CONTENTS Section 1 Section 2 Section 3 Section 4 Notification Flowchart
More informationKankakee River Bridge & Track Improvements Supplemental Environmental Assessment. May 5, 2016
Kankakee River Bridge & Track Improvements Supplemental Environmental Assessment May 5, 2016 1 History: Chicago-St. Louis Corridor Since 1980 s IDOT has been looking at this corridor for high-speed service
More informationSanta Cruz River Master Plan. Presented to the Arizona Floodplain Management Association Spring Conference June 8-10, 2011
Santa Cruz River Master Plan Presented to the Arizona Floodplain Management Association Spring Conference June 8-10, 2011 Introduction Who is FICO? 2 Project Team Kimley-Horn and Associates, Inc. River
More informationQUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project
QUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project Project Overview... 2 Thalia Creek (Windsor Woods) Tide Gate... 6 Club House Road Drainage Project... 9 Updated
More informationVISUALIZATION TOOLS FOR COMMUNICATION & DECISION MAKING REAL MINNESOTA EXAMPLES
REAL MINNESOTA EXAMPLES 23rd Annual CTS Transportation Research Conference Leif Garnass, P.E., PTOE Senior Engineer lgarnass@srfconsulting.com Sean Jergens, ASLA, LEED AP Senior Landscape Architect sjergens@srfconsulting.com
More informationFloodplain Discipline Report
Floodplain Discipline Report Duportail Street Bridge Project Benton County, Washington Prepared for: Federal Highway Administration 711 South Capitol Way, Suite 501 Olympia, WA 98501 Washington State Department
More informationTracking spatiotemporal patterns of building vulnerabilities and evacuations during flood hazards
Tracking spatiotemporal patterns of building vulnerabilities and evacuations during flood hazards Shane Hubbard Junchuan Fan Kathleen Stewart Emily White The University of Wisconsin Madison, SSEC/CIMSS
More informationLower Meramec Multi-Jurisdictional Floodplain Management Plan Public Involvement (Results of Early Public Engagement) 27 June 2018
Lower Meramec Multi-Jurisdictional Floodplain Management Plan Public Involvement (Results of Early Public Engagement) 27 June 2018 Public Involvement Summary: The planning process includes opportunities
More informationCity of East Point Comprehensive Floodplain Management Program
City of East Point Comprehensive Floodplain Management GAFM 2012, 7 th Annual Technical Conference Reza Aral, CFM, CPESC (City of East Point, GA) Shayne Wood, P.E. (CDM Smith) March, 28, 2012 Agenda Overview
More informationSEWRPC. Joint Meeting of the Advisory Committees on Regional Land Use Planning and Regional Transportation Planning APRIL 26, 2018
SEWRPC Joint Meeting of the Advisory Committees on Regional Land Use Planning and Regional Transportation Planning APRIL 26, 2018 WISCONSIN DEPARTMENT OF TRANSPORTATION BRETT WALLACE, FOXCONN PROJECT DIRECTOR
More informationDraft Rhode Island Stormwater Design and Installation Standards Manual
Draft Rhode Island Stormwater Design and Installation Standards Manual Summary The May 2009 Public Review Draft version of the RI Stormwater Design and Installation Standards Manual consists of approximately
More informationProblem Understanding
Introduction...2-1 Previous Data and Mapping...2-2 Known Problem Areas...2-3 Resident Survey.2-3 Introduction The Village of Downers Grove stormwater system includes storm sewers, streams, wetlands, roadway
More informationMunicipal Class EA Study Public Information Centre No. 1 December 13, :00 pm 7:00 pm. Please sign in so we can keep you updated on this study
Reconstruction of Regional Road 45 (Creek Road) Between Regional Road 27 (River Road) and Regional Road 63 (Canborough Road) in the Township of Wainfleet Municipal Class EA Study Public Information Centre
More informationCatherine Bray John Buss Manager City of Tallahassee/Stormwater Management
Florida Stormwater Association EXCELLENCE AWARD for STORMWATER PROGRAMS and PROJECTS NOMINATION FORM I. Nomination Information Nomination Category (please check only one box): Program (Department/Division)
More informationCITY OF HOLLY SPRINGS STORMWATER UTILITY FREQUENTLY ASKED QUESTIONS
CITY OF HOLLY SPRINGS STORMWATER UTILITY FREQUENTLY ASKED QUESTIONS GENERAL What is a Stormwater Utility and why is it needed in Holly Springs? A Stormwater Utility is an entity responsible for the daily
More informationGeosynthetics for Erosion Control and Reinforcement
Geosynthetics for Erosion Control and Reinforcement Stan Boyle, Ph.D., P.E. Shannon & Wilson, Inc. What are Geosynthetics? Geosynthetics are (generally) polymeric products used in civil engineering applications.
More informationSTORMWATER UTILITY PRESENTATION November 18, 2014
STORMWATER UTILITY PRESENTATION November 18, 2014 AGENDA 1. Introduction 2. What is Stormwater 3. What is the problem with polluted runoff? 4. Local Environmental Initiatives 5. Current status to fund,
More informationPasco County Watershed Meeting for Flood Impacted Areas Port Richey Watershed
Pasco County Watershed Meeting for Flood Impacted Areas March 15, 2017 Regency Park Library, 9701 Little Road, New Port Richey, Pasco County The following is a summary of the meeting held on March 15,
More informationI-494 Rehabilitation Project SP (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination
I-494 Rehabilitation Project SP 2785-330 (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination State Project Number 2785-330 Federal Project No. NHPP-I494 (002) Trunk Highway:
More informationCity of Stoughton Erosion Control Permit Application (effective 2/6/2018)
City of Stoughton Erosion Control Permit Application (effective 2/6/2018) Incomplete applications will not be accepted Project Name: Address of subject property: Landowner Name(s): Applicant Name: Landowner
More informationManitoba Association of Native Firefighters, Inc.
Manitoba Association of Native Firefighters, Inc. History of MANFF The Manitoba Association of Native Firefighters, Inc. (MANFF) was formed in 1991. Our membership is composed of, and directed by, Manitoba
More informationCITY OF FORT LUPTON STORM DRAINAGE DESIGN AND TECHNICAL CRITERIA SECTION 10 STREETS
SECTION 10 STREETS CITY OF FORT LUPTON STORM DRAINAGE DESIGN AND TECHNICAL CRITERIA SECTION 10 STREETS 10.1 INTRODUCTION The criteria presented in this section shall be used in the evaluation of the allowable
More informationCity of Greater Sudbury Subwatershed Study Program. Public Open House Tom Davis Square, C-13 A and B March 9, 2016
City of Greater Sudbury Subwatershed Study Program Public Open House Tom Davis Square, C-13 A and B March 9, 2016 Welcome to the City of Greater Sudbury Subwatershed Study Program Public Open House Tom
More informationTable of Contents G.1.a Water Resources - Surface Water - Drainage
Table of Contents G.1.a Water Resources - Surface Water - Drainage 1. INTRODUCTION... 1335 2. ENVIRONMENTAL SETTING... 1335 a. Regional Hydrology... 1335 b. Local Hydrology... 1337 c. On-site Hydrology...
More informationExisting Conditions and Environmental Consequences Floodplains
3.9 Environmental Consequences 3.8 3.8.1 WHAT ARE FLOODPLAINS? are low-lying areas adjacent to rivers, streams, and other waterbodies that are susceptible to inundation (flooding) during rain events. These
More informationWATERS EDGE AT DOBBS FERRY DRAFT ENVIRONMENTAL IMPACT STATEMENT VOLUME I
WATERS EDGE AT DOBBS FERRY DRAFT ENVIRONMENTAL IMPACT STATEMENT VOLUME I Atilda, Fairlawn and Constance Avenues Village of Dobbs Ferry Town of Greenburgh Westchester County, New York Tax Lot Numbers Section
More informationelm creek Watershed Management Commission
elm creek Watershed Management Commission ADMINISTRATIVE OFFICE 3235 Fernbrook Lane Plymouth, MN 55447 PH: 763.553.1144 FAX: 763.553.9326 Email: judie@jass.biz Hickory Drive Utility & Street Improvements
More informationEvaluation of Using Alternative First Floor Elevation Sources for Flood Risk Mitigation
Evaluation of Using Alternative First Floor Elevation Sources for Flood Risk Mitigation Jerry W. Sparks, P.E., CFM Michael K. Buckley, P.E. ASFPM Conference June 23, 2016 A Look Back Crowds panic as floods
More informationStormwater Management Plan Narrative Quality Fleet Services, Inc. SITE RE-DEVELOPMENT 548 New Ludlow Road South Hadley, MA The project proposed by Quality Fleet Services, Inc. consists of the site improvements
More informationQUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project
QUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project PROJECT OVERVIEW Windsor Woods, Princess Anne Plaza and The Lakes are neighborhoods located in what was once
More informationGaining Consensus for Green Infrastructure Rain to Recreation
Gaining Consensus for Green Infrastructure Rain to Recreation May 2nd, 2017 Tom Jacobs, PE, CFM Stormwater Engineer City of Lenexa Ronald L Norris, PE, PWLF Affiliated with Shockey Consulting Rain to Recreation:
More informationAlternatives Analysis Summary Memorandum
F 16253 Swingley Ridge Rd, Suite 100, St. Louis, MO 63017 636-777-3000 P 314.432.5812 F Alternatives Analysis Summary Memorandum To: City of Creve Coeur, Missouri By: Mark Meyer, PE Date: 09-25-2013 Re:
More information17.1 INTRODUCTION CONTEXT CONCLUSIONS
CHAPTER 17. FLOODPLAIN 17.1 INTRODUCTION 17.1.1 CONTEXT A floodplain is part of an extensive drainage and filtration system and water cycle that serves to contain flood waters from storms. Floodplain areas
More information2008 Combined Clean Water Legacy Grant Application Id#: Use TAB key to move from field to field
cwl funds - CWL_FY08Application.doc Page 1 2008 Combined Clean Water Legacy Grant Application Id#: Use TAB key to move from field to field 1. Applicant Organization Applicant Organization:THREE RIVERS
More informationTENNESSEE GAS PIPELINE COMPANY, L.L.C.
TENNESSEE GAS PIPELINE COMPANY, L.L.C. HYDROLOGIC AND HYDRAULIC CALCULATIONS FOR ACCESS ROADS ALONG THE CONNECTICUT PIPELINE EXPANSION PROJECT CONNECTICUT LOOP Submitted by: Tennessee Gas Pipeline Company,
More informationMetropolitan Water Reclamation District of Greater Chicago. Supervising Civil Engineer
Metropolitan Water Reclamation District of Greater Chicago Green and Gray Infrastructure John P. Murray, P.E., CFM Supervising Civil Engineer STORMWATER MANAGEMENT District conveyed authority in November
More informationPreparing Hudson River Waterfronts for an Era of Rapid Sea Level Rise
Preparing Hudson River Waterfronts for an Era of Rapid Sea Level Rise CITY OF KINGSTON TIDAL WATERFRONT FLOODING TASK FORCE Gregg Swanzey Director, Office of Economic Development & Strategic Partnerships,
More information15. Wetlands Chapter Overview Introduction
15. Wetlands 15.1. Chapter Overview 15.1.1. Introduction Pursuant to Presidential Executive Order 11990 entitled Protection of Wetlands, the United States Department of Transportation (USDOT) developed
More informationPROPOSED DRAINAGE PATTERNS
1121 1118.50 Basin Floor 1120 1119 0 N 100 200 PROPOSED DRAINAGE PATTERNS Deroiser Drive Riverwood Drive County 260 0 100 200 Project Name: Riverwood Drive LITTLE FALLS TOWNHOMES Project Location: LITTLE
More informationSouth Bismarck Watershed Model Update and Stormwater Improvement Project
Preliminary Engineering Report Bismarck Tribune South Bismarck Watershed Model Update and Stormwater Improvement Project City of Bismarck, ND January 2017 14.105.0046 1.0 Executive Summary The focus of
More informationChapter 1 GENERAL SOUTH DAKOTA DRAINAGE MANUAL
Chapter 1 GENERAL SOUTH DAKOTA DRAINAGE MANUAL October 2011 Table of Contents Section Page 1.1 INTRODUCTION...1-1 1.2 BASIC APPROACH...1-2 1.3 FUNCTIONAL RESPONSIBILITIES...1-3 1.3.1 Office of Road Design...1-3
More informationProject Description WOO/LUC-SR /0.00. Waterville Bridge Replacement
Ohio Department of Transportation District 2 317 East Poe Rd. Bowling Green, Ohio 43402 (419) 353-8131 John R. Kasich, Governor Jerry Wray, Director Todd Audet, P.E., District Deputy Director Project Description
More informationMaintenance Plan for Vegetated Portions of the MS4
Maintenance Plan for Vegetated Portions of the MS4 Hawaii State Department of Transportation Highways Division, Oahu District Storm Water Management Program NPDES Permit No. HI S000001 April 2015 This
More informationSustainable Storm Water Management
Incorporating Water Management into the Community Planning Process August 16, 2012 Sustainable Storm Water Management Samantha Brown Environmental Engineer SD1 SD1 s Service Area CVG Airport SD1 Service
More informationAlternate Green Stream Bank Stabilization Methods
U.S. Army Corps of Engineers Philadelphia/Baltimore Districts Alternate Green Stream Bank Stabilization Methods Wissahickon Creek, Tannery Run and Rose Valley Creek Bo-Rit Asbestos Site Ambler, Pennsylvania
More informationFinger Lakes National Forest. Backbone Horse Camp Water Hydrant Project
United States Department of Agriculture Forest Service February 2014 Backbone Horse Camp Water Hydrant Project Scoping Information Hector Ranger District Town of Lodi, Seneca County, New York For Information
More information7.0 SOCIAL, ECONOMIC, AND ENVIRONMENTAL ISSUES
7.0 SOCIAL, ECONOMIC, AND ENVIRONMENTAL ISSUES The following list of social, economic, and environmental issues have been identified based on a preliminary inventory of resources in the project area, an
More informationSeptember 7, Mr. Brant Gary Director of Public Works City of Bellaire 7008 S. Rice Avenue Bellaire, Texas 77401
September 7, 2016 Mr. Brant Gary Director of Public Works City of Bellaire 7008 S. Rice Avenue Bellaire, Texas 77401 Re: City of Bellaire, Texas FY 2016 Drainage Study Dear Mr. Gary: ARKK Engineers, LLC
More informationCity of West Palm Beach. Floodplain Management Plan Draft Action Plan August 3, 2016
City of West Palm Beach Floodplain Management Plan Draft Action Plan August 3, 2016 The projects in this draft Action Plan are in order by the six categories of floodplain management activities identified
More informationJoe Pool Lake Master Plan Revision Public Information Meeting May 23, 2017
Joe Pool Lake Master Plan Revision Public Information Meeting May 23, 2017 Presented By Jason Owen Lake Manager U.S. Army Corps of Engineers Fort Worth District US Army Corps of Engineers Purpose of this
More informationFigure 1 Cypress Street Study Area Location Map
July 20, 2016 TO: FROM: Jim Massarelli Director of Engineering Jeff Julkowski, PE Michael Burke, PE SUBJECT: Cypress Street Study Area Stormwater Analysis (CBBEL Project No. 16-0058) At the request of
More informationProject: Developer/Designer: Reviewer: I. Narrative: 1. Project Description: Describes the nature and purpose of the land disturbing activity.
City of Charlottesville, Virginia Erosion and Sediment Control Plan Review Checklist 610 East Market Street, Charlottesville, VA 22902 Telephone 434-970-3182; Fax 434-970-3359 Project: Developer/Designer:
More informationGetting the Locals to Go Along. Keys to Tulsa s Successful Floodplain Management
Getting the Locals to Go Along Keys to Tulsa s Successful Floodplain Management Presented by: Ronald D. Flanagan, CFM Principal Planner Flanagan & Associates, LLC Land-Use & Natural Hazards Planning Consultants
More informationSTORMWATER UTILITY FREQUENTLY ASKED QUESTIONS
STORMWATER UTILITY FREQUENTLY ASKED QUESTIONS What is Stormwater? Stormwater is water that falls to the ground during a precipitation event. When land is undeveloped or covered with vegetative surface,
More informationSTREAM BANK STABILIZATION THORPS MORTIMER RECREATION AREA Grandfather Ranger District SITE LOCATION & DRAINAGE AREA
STREAM BANK STABILIZATION THORPS CREEK @ MORTIMER RECREATION AREA SITE LOCATION & DRAINAGE AREA SITE LOCATION Drainage Area = 1.14 sq. miles STREAM BANK STABILIZATION THORPS CREEK @ MORTIMER RECREATION
More informationWELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A
WELCOME! 168 TH STREET IMPROVEMENTS 6:30 Open House 7 8 Presentation & Q&A 8 8:30 Open House WELCOME Todd Pfitzer City of Omaha Engineer Bob Stubbe City of Omaha Public Works Director Jon Meyer Project
More informationFarmers Investment Co. (FICO) Continental Farms
Farmers Investment Co. (FICO) Continental Farms Planning & Zoning Commission Study Session (River Master Plan) January 25, 2012 FICO Property 7,000 acres total area 6,000 acres in Town of Sahuarita 1,000
More informationSTORM WATER MANAGEMENT SYSTEMS
STORM WATER MANAGEMENT SYSTEMS MichiganReportCard.com 38 GRADE D+ STORM WATER MANAGEMENT SYSTEMS OVERVIEW Michigan s storm water management system provides flood protection, makes development possible,
More informationCity of Elmhurst. Comprehensive Flood Plan. City of Elmhurst. City Council Meeting September 15, 2014
City of Elmhurst City of Elmhurst Comprehensive Flood Plan City Council Meeting September 15, 2014 City of Elmhurst Presentation Overview Study Background Study Methodology Analysis of Three Additional
More informationStormwater Regulations & Considerations Morse Study Area. Pam Fortun, P.E. CFM Senior Stormwater Treatment Engineer Engineering Services Division
Stormwater Regulations & Considerations Morse Study Area Pam Fortun, P.E. CFM Senior Stormwater Treatment Engineer Engineering Services Division Stormwater Regulations Development Considerations Floodplain
More informationWEATHER IT TOGETHER Building Resilience. The Annapolis Model for Cultural Resource Hazard Mitigation Planning
WEATHER IT TOGETHER Building Resilience The Annapolis Model for Cultural Resource Hazard Mitigation Planning Weather It Together A Public / Private Partnership Weather It Together is the Annapolis model
More informationLewisville Lake Master Plan Revision Public Information Meeting May 2 & 4, 2017
Lewisville Lake Master Plan Revision Public Information Meeting May 2 & 4, 2017 Presented By Rob Jordan Lake Manager U.S. Army Corps of Engineers Fort Worth District US Army Corps of Engineers Purpose
More information6.5 Lakewood Gulch. Basin Snapshot
6.5 Lakewood Gulch The Lakewood Gulch Map Unit is comprised of both Lakewood Gulch and Dry Gulch (4800-01 and 4801-01) from the Denver Storm Drainage Master Plan (SDMP) and has a total drainage area of
More information