ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT. February 29, NO CHANGE: March 8, 2012 / NOT LATER THAN 2:00 PM

Size: px
Start display at page:

Download "ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT. February 29, NO CHANGE: March 8, 2012 / NOT LATER THAN 2:00 PM"

Transcription

1 ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT February 29, 2012 RFP NO: 17 PROJECT: Josephine County Justice Center HVAC Upgrades BID CLOSING DATE: NO CHANGE: March 8, 2012 / NOT LATER THAN 2:00 PM This Solicitation Addendum is issued to the above referenced bid and forms a part of the contract documents and modifies the original scope of work, specifications and drawings, requirements and deadlines. Except as changed by this Addendum, all terms, conditions, scope of work, plans, specification, requirements and deadlines in the original ITB and previous addenda remain unchanged. This Solicitation Addendum must be acknowledged by inserting its number on the appropriate blank lines in the Invitation to Bid. Failure to do so may result in rejection of Bid. ================================================================================ 1 Modification to Submission Requirements This item is included as a reminder. Addendum #2 It originally appeared in Prequalification Applications Insurance Certification Requirement. For those contractors who submitted prequalification applications to work with Josephine County, the insurance certificate indicating the required coverage will be due as a part of the bid submission due on March 8, 2012 no later than 2:00 PM. 2 Change Addendum 3 Attachment #1. One (1) page titled Section 1; Bid Form. To replace in its entirety page 2 of 13 from the ITB/Bid Response section. This revision adds three Alternates (F, G, and H) for DDC system. This is the second revision to this form. Ensure you submit the correct Bid Form with your Bid. 3 Change Addendum 3 Attachment #2. Three (3) pages labeled Attachment #2 provides additions and revisions to the Specifications including sections: Air Distribution, and DDC Controls; responses to Substitution Requests; and list of attached sketches. 4 Change Addendum 3 Attachment #3. Four (4) 8 ½ x 11 pages labeled Attachment #3 provides revisions to drawings M0.0, M5.1, M5.2. End of Addendum 3

2 Addendum 3 Attachment #1 SECTION 1: BID FORM Justice Center HVAC Upgrades The undersigned agrees, if this Bid is accepted, to enter into a contract with County to provide all labor, materials, transportation, equipment, services, and testing required to make a complete and finished Project as shown in the Project Drawings and Specifications and in accordance with the Project Schedule. ENERGY EFFICIENCY MEASURE #1 (DDC system): ENERGY EFFICIENCY MEASURE #2 (Replace existing mixing box to VAV s): ENERGY EFFICIENCY MEASURE #3 (Replace electric heating coils to hot water coils/new boilers): Base Bid: Base Bid: Base Bid: ADD ALTERNATES: TOTAL BASE BID: $ Energy Efficiency Measure #1 Alternates. Respond with a -0- for the vendor used in the Base Bid. Alternate A Alerton Technologies Alternate B Andover Controls Alternate C Delta Controls Alternate D Reliable Controls Corp. Alternate F Siemens Corp. Alternate G Johnson Controls Corp. Alternate H Honeywell Controls Corp. Other Alternates Alternate E Modifications to air handler serving the basement including $9,800 allowance for controls: Bidder s Signature: Print Name of Bidder: Date: BID RESPONSE Josephine County Page 2 of 13 Justice Center HVAC Upgrades

3 Addendum 3 Attachment #2 ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT February 29, 2012 PROJECT: Josephine County Justice Center HVAC Upgrades BID CLOSING DATE: March 8, 2012 / NOT LATER THAN 2:00 PM SPECIFICATIONS Note: Additions are shown in bold, deletions have a strikethrough Air Distribution Line 17 Variable Air Volume Terminal Box: Construct unit casings of 22 gauge galvanized steel fully lined with 1/2", 2 lb. density, neoprene coated fiberglass complying with the UL Standard 181 for erosion, and NFPA 90A for fire resistivity. Unit Inlets: Double round, oval, or rectangular with double thickness gasketed damper blade mounted in selflubricating bearings unless otherwise noted. Provide with attenuator or mixer to allow operation of heating & cooling duct damper in mixing range with heating and mixing airflow rate equal to 50% cooling air flow rate, and with cooling and heating duct inlet sizes the same. See schedule for size. VAV-1-13 shall be single duct without reheat section. ARI Certified: Test in accordance with ARI Standard DDC Controls Line 25 Heating Section Control: The heating system shall modulate based on percent heating load. During occupied mode, the BAS will modulate the heating valve to maintain discharge temperature setpoint (at hot deck temperature sensor) according to discharge temperature reset schedule. Heating system shall remain off during cool-down, night high limit, as well as during night purge mode. The heating system shall be off when outside air temperature is above 60 F (adjustable). Provide operator screen switch to enable operation of electric heating coil. Operation of electric heating coil is only for back-up heat on failure of boiler system serving this air handler. When energized electric heating system shall stage elements (2 stages) to maintain discharge temperature per sequence above Line 21 SEQUENCE OF OPERATION SINGLE ZONE CONSTANT VOLUME AIR HANDLING SYSTEMS (HV-1) (HV-2) Fan Enable / Optimal Start Control (Heating Mode) or Warm-Up Mode: Page 1 of 3

4 Addendum 3 Attachment # Line 50 Fan speed is reset to 0 (zero) Hz when the AHU is off. Coordinate signal from fire alarm panel to duct mounted smoke detector. One signal to detector disables fan (Hz = 0), waits 15 seconds (adjustable), and starts smoke damper closing. During morning warm-up, NNL, NHL, or purge operation fan static set point shall be at upper limit. Return Fan Control: Return fan will start (upon proof of operation) and stop with supply fan. Return fan speed shall modulate to maintain area served by air handler at 0.02 WC positive (Adj.) Line 40 Zone Control: Individual zone temperature conditions during occupancy will be maintained within a heating/cooling range (initial setpoints, adjustable, 70 F heating and 75 F cooling, unless otherwise instructed by Engineer and Owner). Zone temperature heating/cooling setpoints will incorporate a throttling range of 2 F degrees (adjustable). Setpoints will be easily adjustable at both the operator s terminal and at the Maintenance Building remote operator s station. For zones that are cooling only operation (VAV-1-13) operate damper between full cooling mode and minimum to maintain space between 55º F and 85º F. Delete these zones from reset schedule calculation. During morning warm-up or night low limit,hot duct damper shall operate at full heating airflow position until space is at setpoint then modulate to maintain space temperature until occupied mode. During night purge high limit or morning cool down, operate cold duct damper at full cooling airflow position until space is at setpoint. Otherwise, modulate cooling or heating duct damper between heating and cooling ducts to maintain space temperature setpoint as follows: In cooling mode, as temperature approaches setpoint, cold air modulates from maximum to a minimum mix flow rate. Minimum flow rate equals heating flow rate. As temperature continues to drop, hot airflow modulates open as cold airflow closes, maintaining a minimum total flow rate. Lower heating flow rates require unequal inlet sizes to maintain control. A mixer/attenuator section is required. SUBSTITUTION REQUESTS Alternates Line 5: Add following Alternates. Alternate F (EEM #1F): Provide direct digital controls system manufactured by Siemens Corp. and installed by an Siemens Corp. area representative only. Alternate G (EEM #1G): Provide direct digital controls system manufactured by Johnson Controls Corp. and installed by an Johnson Controls Corp. area representative only. Alternate H (EEM #1H): Provide direct digital controls system WEBs AX manufactured by Honeywell Controls Corp. and installed by an Honeywell Controls Corp. area representative only. Page 2 of 3

5 Addendum 3 Attachment # Basic Mechanical Materials and Methods Line 5 Variable Speed Motor Controllers Add Yakzawa as an approved manufacturer Heating Boilers Line 42 Condensing Boilers Add Laars as an approved manufacturer Line 42 Copper Finned Boilers Add Laars as an approved manufacturer Air Distribution Line IAQ Damper - Add Greenheck IAQ - 42 damper with optional aluminum frame as approved product DDC Controls Line 12: Add following Alternates. Alternate F (EEM #1F): Provide direct digital controls system manufactured by Siemens Corp. and installed by an Siemens Corp. area representative only. Alternate G (EEM #1G): Provide direct digital controls system manufactured by Johnson Controls Corp. and installed by an Johnson Controls Corp. area representative only. Alternate H (EEM #1H): Provide direct digital controls system WEBs AX manufactured by Honeywell Controls Corp. and installed by an Honeywell Controls Corp. area representative only. DRAWINGS 1. ADD#3 M1-REF:M0.0 (8.5x11 revision sheet) Add Alternate F-H descriptions. 2. ADD#3-M2-REF:M5.1 (8.5x11 revision sheet) Revise chiller control schematic and points list as shown. 3. ADD#2-M3-REF:M5.2 (8.5x11 revision sheet) Revise VAV and HV-2 control schematics as shown. 4. ADD#3-M4-REF:M5.2 (8.5x11 revision sheet) Revise emergency generator, VAV and HV-2 points lists as shown. MFIA, Inc. Page 3 of 3

6 Addendum 3 / Attachment #3

7 Addendum 3 / Attachment #3

8 Addendum 3 / Attachment #3

9 Addendum 3 / Attachment #3

A. Base Bid: 1. Heating Contractor provide: a. Control sequences for HVAC systems, subsystems, and equipment.

A. Base Bid: 1. Heating Contractor provide: a. Control sequences for HVAC systems, subsystems, and equipment. SECTION 23 09 93 - SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL 1 WORK INCLUDES A. Base Bid: Heating Contractor provide: Control sequences for HVAC systems, subsystems, and equipment. B. Alternate

More information

SEQUENCE OF OPERATION GUIDELINE. AIR TERMINAL UNITS SINGLE DUCT VARIABLE AIR VOLUME with HOT WATER REHEAT or ELECTRIC HEAT

SEQUENCE OF OPERATION GUIDELINE. AIR TERMINAL UNITS SINGLE DUCT VARIABLE AIR VOLUME with HOT WATER REHEAT or ELECTRIC HEAT SEQUENCE OF OPERATION GUIDELINE AIR TERMINAL UNITS SINGLE DUCT VARIABLE AIR VOLUME with HOT WATER REHEAT or ELECTRIC HEAT Document: VAV-HTG rev1 Revision: 1.0 Rev. Date: July 22, 2011 NOTES: 1. THIS SEQUENCE

More information

Guide Spec Summary. Option List. Date: 05/21/2001. EarthWise VAV Terminal Units Full Spec. Prepared by: Phone Number: Prepared for:

Guide Spec Summary. Option List. Date: 05/21/2001. EarthWise VAV Terminal Units Full Spec. Prepared by: Phone Number: Prepared for: Date: 05/21/2001 Time: 02:57:44 PM Job Name: EarthWise VAV Terminal Units Full Spec Location: AnyTown, Earth Prepared by: Phone Number: Prepared for: Guide Spec Summary Option List SINGLE & DUAL DUCT UNIT

More information

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS SECTION 23 09 93 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes control sequences for HVAC systems, subsystems, and equipment. B. See Division 23 Section

More information

Florida Department of Transportation

Florida Department of Transportation Page 1 of 7 RICK SCOTT GOVERNOR Florida Department of Transportation 1109 S. Marion Avenue Lake City, Florida 32025 ANANTH PRASAD SECRETARY September 27, 2011 To: Proposal Holders Addendum No: 1, E2Q23,

More information

RE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana

RE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana ADDENDUM NO. 2 RE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana TO: All Bidders Gentlemen: This Addendum

More information

SECTION SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL

SECTION SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL SECTION 15910 SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION SECTION 237433, PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to

More information

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL SECTION 23 09 93 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS 1.1 SUMMARY A. This Section includes control sequences for HVAC systems, subsystems, and other equipment. B. See Division 23 Section

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-23 09 93 (November 2015) ----------------------------- Preparing Activity: USACE Superseding UFGS-23 09 23 (May 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS References

More information

DIGI-VAV APPLICATIONS

DIGI-VAV APPLICATIONS DIGI-VAV DIGI-VAV APPLICATIONS Digi-VAV: An optimization kit for Variable Air Volume Air Handling Units (VAV AHU) that ensures individual zone indoor air quality (IAQ), and minimizes system energy consumption.

More information

Chilled Water DOAS Fan Powered Terminal Units

Chilled Water DOAS Fan Powered Terminal Units Chilled Water DOAS Fan Powered Terminal Units CHILLED WATER DOAS FAN POWERED TERMINAL UNITS DOAS TERMINAL UNITS FEATURES AND BENEFITS MINIMUM VENTILATION CONTROL The DOAS unit provides the Designer, Owner

More information

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 11/11/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 11/11/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma Objectives and Requirements For the Creative and Performing Arts High School (CAPA), the main objective of the mechanical design is to provide an energy efficient system that is easily maintainable and

More information

Job Name Control Systems Description Date

Job Name Control Systems Description Date Job Name Control Systems Description Date Project Overview The project is a describe the building and its major HVAC systems (e.g. three-story office building, served by a rooftop unit VAV system ). In

More information

AIR DISTRIBUTION. C. Section Building Automation and Control System Guidelines. D. Section Fire Alarm System & Detection Systems

AIR DISTRIBUTION. C. Section Building Automation and Control System Guidelines. D. Section Fire Alarm System & Detection Systems 233100 AIR DISTRIBUTION PART 1: GENERAL 1.01 RELATED SECTIONS A. Section 230700 HVAC Insulation B. Section 237300 Air Handling C. Section 230900 Building Automation and Control System Guidelines D. Section

More information

Air Handler Unit (AHU) Equipment Purchase and Delivery Invitation to Bid

Air Handler Unit (AHU) Equipment Purchase and Delivery Invitation to Bid DATE: February 1, 2018 SUBJECT: Letter of Clarification #2 RE: TO: Air Handler Unit (AHU) Equipment Purchase and Delivery Invitation to Bid All Prospective Bidders Houston First Corporation ( HFC ) issues

More information

terminal unit accessories

terminal unit accessories CNTRL SEQUENCES SINGLE DUCT VAV (Variable Volume) Cooling the minimum to the maximum Models: PESV, PECV, PQCV VAV Cooling, Reheat thermostat modulates the hot water coil valve toward the closed position.

More information

November 11, City of Sparks 215 S. 21 st St. Sparks, NV

November 11, City of Sparks 215 S. 21 st St. Sparks, NV November 11, 2014 City of Sparks 215 S. 21 st St. Sparks, NV 89432-0857 Attn: Brian Cason Re: Sparks City Hall HVAC Upgrade Project-Alerton Direct Digital HVAC Control System to Match Existing City of

More information

HVAC Controls Upgrades: Requirement Details ( )

HVAC Controls Upgrades: Requirement Details ( ) REQUIRED CONTROLS/FEATURES To qualify the upgrade must add or substantially modify 3 or more sequences/system capabilities. Also, all sequences and items listed under the required section are needed in

More information

SECTION AIR DUCT ACCESSORIES

SECTION AIR DUCT ACCESSORIES SECTION 23 33 00 AIR DUCT ACCESSORIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes back-draft dampers, combination fire-and-smoke dampers, duct access doors, fire dampers, smoke dampers, volume control

More information

DIVISION 15 MECHANICAL

DIVISION 15 MECHANICAL DIVISION 15 MECHANICAL A. GENERAL DESIGN CONDITIONS 1. Design occupied spaces to maintain 72 F and a space dew point temperature not to exceed 55 F. 2. Design classroom and office space buildings with

More information

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT Taylor Engineering 1080 Marina Village Parkway, Suite 501 Alameda, CA 94501-1142 (510) 749-9135 Fax (510) 749-9136 LLC HVAC DESIGN INTENT PART 1 - GENERAL 1.1 Overview A. The project consists of a 3-story

More information

B. Use UT Austin specifications and equipment schedule format for HVAC equipment where available.

B. Use UT Austin specifications and equipment schedule format for HVAC equipment where available. PART 1: GENERAL 1.01 General Requirements A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the

More information

SINGLE DUCT TERMINAL UNITS

SINGLE DUCT TERMINAL UNITS Performance Data AHRI Certification and Performance Notes Model Series 3000 asic Unit AHRI Certification Rating Points VAV: Fiberglass Inlet Size Airflow cfm l/s Min. Inlet Ps w.g. Pa Discharge Sound Power

More information

HVAC Controls Upgrades: Requirement Details ( )

HVAC Controls Upgrades: Requirement Details ( ) REQUIRED CONTROLS/FEATURES HVAC non CENTRAL PLANT 1) Zone Level Scheduling & Override for all air handlers (supply and exhaust) to match occupied hours by zone DDC or occupancy sensors (OS) allowed. (403.2.4.3,

More information

SECTION SPECIFICATION FOR HI-VELOCITY FAN COIL SYSTEMS

SECTION SPECIFICATION FOR HI-VELOCITY FAN COIL SYSTEMS 1.0 GENERAL SECTION 15740 SPECIFICATION FOR HI-VELOCITY FAN COIL SYSTEMS 1.01 DESCRIPTION Item A. Scope This section specifies four sizes of fan coil units designed for hydronic heating and air conditioning.

More information

CALL FOR TENDER - MUNICIPALITY OF THE DISTRICT OF CLARE LITTLE BROOK, N.S.

CALL FOR TENDER - MUNICIPALITY OF THE DISTRICT OF CLARE LITTLE BROOK, N.S. CALL FOR TENDER - MUNICIPALITY OF THE DISTRICT OF CLARE LITTLE BROOK, N.S. NAME OF TENDER: CONSTRUCT, DELIVER AND COMMISSION 3 (THREE) LIFT STATION ELECTRICAL LOCATION OF WORK: 3 Separate work sites in

More information

A. American National Standards Institute (ANSI) : Establishes requirements applicable to certifying direct gas-fired heaters.

A. American National Standards Institute (ANSI) : Establishes requirements applicable to certifying direct gas-fired heaters. Section 15 _ Energy Recovery Air Handling System Part 1: GENERAL 1.1 Section Includes: A. Energy Recovery Air Handler B. Controls (most by Others) C. Equipment Schedule 1.2 Related Sections: A. Section

More information

AIR-CONDITIONING SYSTEMS AND APPLICATIONS. Abdullah Nuhait Ph D. King Saud University

AIR-CONDITIONING SYSTEMS AND APPLICATIONS. Abdullah Nuhait Ph D. King Saud University AIR-CONDITIONING SYSTEMS AND APPLICATIONS Abdullah Nuhait Ph D. King Saud University AIR-CONDITIONING SYSTEMS Earliest air conditioning system used only for heating (winter) Provided heated air for comfort

More information

Design Standard. Thermal Systems (Chilled Water and Hot Water Systems) Detailed specifications follow. CHW AND HHW SUPPLY TEMPERATURE RESET

Design Standard. Thermal Systems (Chilled Water and Hot Water Systems) Detailed specifications follow. CHW AND HHW SUPPLY TEMPERATURE RESET Design Standard Detailed specifications follow. PART 1 CHW AND HHW SUPPLY TEMPERATURE RESET 1.1 The Utilities & Energy Services Department (UES) at Texas A&M University is actively identifying and implementing

More information

1. Delete BID FORM in its entirety and replace with the BID FORM attached to this Addendum.

1. Delete BID FORM in its entirety and replace with the BID FORM attached to this Addendum. ADDENDUM NO. 2 TO THE BIDDING DOCUMENTS Solicitation Number 2016-13 Fire Alarm, Sprinkler & BFP Inspections and Repairs Saint Clair County MidAmerica Saint Louis Airport DATE: November 30, 2016 BIDS CLOSE:

More information

Technical Assignment 3 11/15/04. Executive Summary

Technical Assignment 3 11/15/04. Executive Summary Executive Summary This report is an analysis of the existing systems within the Outreach Innovation Building in University Park, PA. One significant design criteria was a lower than average noise criteria

More information

AIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS

AIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS AIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS 1 AIR HANDLING UNIT TRENDS 2 1. The trending charts provided on the following pages prepared as part of a retro-commissioning investigation. The

More information

Modular Heating & Ventilating Unit Model IGX-HV

Modular Heating & Ventilating Unit Model IGX-HV Modular Heating & Ventilating Unit Model IGX-HV Indirect Gas-Fired Heating Evaporative Chilled Water DX Cooling October 2008 Product Features Model IGX-HV Indirect Gas-Fired Heating and Ventilating Unit

More information

Retrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems

Retrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

Selected Laboratory Energy Efficiency Measures

Selected Laboratory Energy Efficiency Measures Selected Laboratory Energy Efficiency Measures These are some of the most effective energy efficiency measures for laboratories 1. Reduce (optimize) air changes per hour in lab space 2. Design to the proper

More information

SECTION HVAC TABLE OF CONTENTS PART 1 - SYSTEM DESCRIPTION / OUTLINE SPECIFICATIONS FILED SUB BID PROJECT OVERVIEW...

SECTION HVAC TABLE OF CONTENTS PART 1 - SYSTEM DESCRIPTION / OUTLINE SPECIFICATIONS FILED SUB BID PROJECT OVERVIEW... SECTION 230001 TABLE OF CONTENTS SECTION 230001 PART 1 - SYSTEM DESCRIPTION / OUTLINE SPECIFICATIONS... 1 1.00 FILED SUB BID... 1 1.01 PROJECT OVERVIEW... 2 1.02 DESIGN CRITERIA... 4 1.03 CODE ISSUES...

More information

FAN TERMINAL UNITS Constant Volume (Series Flow), Standard Design

FAN TERMINAL UNITS Constant Volume (Series Flow), Standard Design FAN TERMINAL UNITS Constant Volume (Series Flow), Standard Design Fan motor (PSC or ECM). UL Listed 1 insulation conforms to UL Test 181 and NFPA 90A. Plenum air filter rack. (Filter Optional) Casing has

More information

1.1 This section applies to air handling units for HVAC Systems.

1.1 This section applies to air handling units for HVAC Systems. AIR HANDLING UNITS GENERAL INFORMATION 1.1 This section applies to air handling units for HVAC Systems. DESIGN REQUIREMENTS 2.1 Design Criteria a. The decision to use modular central station air handling

More information

Power and Energy Management Solutions

Power and Energy Management Solutions Selection Guide Power and Energy Management Solutions Heating, Ventilating and Air Conditioning (Bulletin 1414) Selection Guide 2 HVAC Selection Guide Instrumentation Selection Checklist Use the following

More information

COMcheck Software Version Review Mechanical Compliance Certificate

COMcheck Software Version Review Mechanical Compliance Certificate COMcheck Software Version 4.0.7.2 Review Mechanical Compliance Certificate Section 1: Project Information Energy Code: 2014 Oregon Energy Efficiency Specialty Code Project Title: Benton County Health Project

More information

Digital Precise Air Control - DPAC

Digital Precise Air Control - DPAC Digital Precise Air Control - DPAC Mode Enable Sensor Options The temperature of this sensor will determine if the unit is in heating, cooling or vent mode during Occupied operation. The following options

More information

OSU Alumni Center Phase I Implementation Review. Oregon State University 130 Oak Creek Bldg. Corvallis, Oregon

OSU Alumni Center Phase I Implementation Review. Oregon State University 130 Oak Creek Bldg. Corvallis, Oregon OSU Alumni Center Phase I Implementation Review Prepared for Oregon State University 130 Oak Creek Bldg. Corvallis, Oregon 97331 October 31, 2011 Job No. 02.11.00113 Introduction: Glumac was engaged by

More information

DACC Health Sciences Building Air Handler Assessment/Study

DACC Health Sciences Building Air Handler Assessment/Study DACC Health Sciences Building Air Handler Assessment/Study NMSU Facilities and Services Department P.O. Box 30001 Las Cruces, NM 88003-8001 June 14, 2016 Final Submittal 1065 S. Main St., Bldg. D, Ste.

More information

IAQ: Re-tuning Commercial Buildings

IAQ: Re-tuning Commercial Buildings IAQ: Re-tuning Commercial Buildings A low-cost path to improved air quality and energy efficiency. B y S c o t t G o r d o n, C M All images courtesy of Johnson Controls Service. 10 RSES Journal FEBRUARY

More information

THIS ADDENDUM MUST BE ACKNOWLEDGED.

THIS ADDENDUM MUST BE ACKNOWLEDGED. Denver Public Schools Purchasing Department 1350 East 33 rd Avenue Denver, Colorado 80205 INVITATION TO BID 13-MC-Fire Extinguisher ADDENDUM NUMBER ONE December 14, 2012 THIS ADDENDUM MUST BE ACKNOWLEDGED.

More information

SUWANNEE RIVER WATER MANAGEMENT DISTRICT REQUEST FOR BID NO. 15/16-003AO FIRE ALARM SYSTEM INSTALLATION AND MONITORING.

SUWANNEE RIVER WATER MANAGEMENT DISTRICT REQUEST FOR BID NO. 15/16-003AO FIRE ALARM SYSTEM INSTALLATION AND MONITORING. SUWANNEE RIVER WATER MANAGEMENT DISTRICT REQUEST FOR BID NO. 15/16-003AO FIRE ALARM SYSTEM INSTALLATION AND MONITORING Table of Contents Section Title Page 1 Introduction 2 2 Proposed Schedule 2 3 Instructions

More information

10+ HVAC Troubleshooting Tips for Healthcare Facilities Jerry Hirsch JCI Facility O&M Performance Development Manager.

10+ HVAC Troubleshooting Tips for Healthcare Facilities Jerry Hirsch JCI Facility O&M Performance Development Manager. 10+ HVAC Troubleshooting Tips for Healthcare Facilities Jerry Hirsch JCI Facility O&M Performance Development Manager 2019 WHEA Webinar Johnson Controls Institute Overview Operation & Maintenance (O&M)

More information

UNIVERSITY OF ALASKA FAIRBANKS DIVISION 25- INTEGRATED AUTOMATION DESIGN STANDARDS SECTION INTEGRATED CONTROL OF FACILITY LAB FUME HOODS

UNIVERSITY OF ALASKA FAIRBANKS DIVISION 25- INTEGRATED AUTOMATION DESIGN STANDARDS SECTION INTEGRATED CONTROL OF FACILITY LAB FUME HOODS PART 1 - GENERAL 1.01 General: A. Laboratory ventilation system will ensure the health and safety of laboratory occupants. B. Room pressurization control will utilize airflow tracking to vary the volume

More information

Your Home. Jacco & Assoc.

Your Home. Jacco & Assoc. Your Home Fan on with call for heating or cooling Heating on with call from space thermostat Stage as required to maintain The 75F Basics adj. - First stage of heating shall be heat pump Cooling on with

More information

BULLETIN. Temperature Controls (Chilled / Hot Water)

BULLETIN. Temperature Controls (Chilled / Hot Water) BULLETIN Temperature Controls (Chilled / Hot Water) (05-07-2013) This bulletin is to advise you of the fees and responsibilities associated with the tenant s temperature controls. Tenant Responsibility:

More information

Madeira City Schools Madeira, Ohio. HVAC Assessment. December 2011 (Revised February 2012)

Madeira City Schools Madeira, Ohio. HVAC Assessment. December 2011 (Revised February 2012) Madeira City Schools Madeira, Ohio HVAC Assessment December 2011 (Revised February 2012) Prepared by: CMTA Engineering Consultants, Inc. 10411 Meeting Street Prospect, KY 40059 www.cmtaegrs.com (502) 326-3085

More information

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner ESL-TR-99/12-09 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University at Commerce (TAMU-Commerce) Commerce, Texas Submitted to Texas

More information

DX-9100 Applications from Engineering Services

DX-9100 Applications from Engineering Services System 9100 Technical Manual 636.4 Application Examples Section Technical Bulletin Issue Date 0896 DX-9100 Applications from Engineering Services Introduction Page 3 Overview 3 Air Handling Unit Applications

More information

Building Automation System (BAS) Design Criteria

Building Automation System (BAS) Design Criteria 25 0520 Building Automation System (BAS) Design Criteria 1. Design Statement a. During the various design phases of this project, the Engineer will develop options and strategies for selection of the appropriate

More information

Submitted to. Texas A&M University-Corpus Christi The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

Submitted to. Texas A&M University-Corpus Christi The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge ESL-TR-99/12-04 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University-Corpus Christi (TAMU-CC) Corpus Christi, Texas Submitted to Texas

More information

Verasys System Operation Overview Technical Bulletin

Verasys System Operation Overview Technical Bulletin Contents subject to change. Verasys System Operation Overview Technical Bulletin Code No. LIT-12012370 Issued January 2016 Refer to the QuickLIT Web site for the most up-to-date version of this document.

More information

Tualatin Valley Fire & Rescue Finance Department SW 70 th Ave., Tigard, OR Phone: , Fax:

Tualatin Valley Fire & Rescue Finance Department SW 70 th Ave., Tigard, OR Phone: , Fax: Tualatin Valley Fire & Rescue Finance Department 11945 SW 70 th Ave., Tigard, OR 97223 Phone: 503-259-1157, Fax: 503-649-5347 SOLICITATION NO: ITB 13-0002 AMENDMENT NO. 2 General Contractor Construction

More information

A. American National Standards Institute (ANSI): Establishes requirements applicable to certifying direct gas-fired heaters.

A. American National Standards Institute (ANSI): Establishes requirements applicable to certifying direct gas-fired heaters. SECTION 15622 DIRECT GAS-FIRED BURNER & MANIFOLD SYSTEM PART 1: GENERAL 1.1 Section includes: A. Direct gas-fired heater modules B. Controls C. Equipment schedule 1.2 Related Sections A. Section 01655:

More information

York 25-Ton VAV Rooftop Unit

York 25-Ton VAV Rooftop Unit HVAC PRO for Windows User s Manual 637.5 OEM Section Technical Bulletin Issue Date 0996 York 25-Ton VAV Rooftop Unit Introduction Page 3 Overview *3 Configuration 5 Sequence of Operation 7 Modes of Operation

More information

ADDENDUM #1: MODIFICATIONS AND ADDITIONS TO CONTRACT DOCUMENTS

ADDENDUM #1: MODIFICATIONS AND ADDITIONS TO CONTRACT DOCUMENTS Annex Laundry and Shower Alterations ADDENDUM #1 March 7, 2019 ADDENDUM #1: MODIFICATIONS AND ADDITIONS TO CONTRACT DOCUMENTS A. Invitation to Bid - Call for Bids has been modified as follows: 1. Notice

More information

C. ASME Compliance: Fabricate and label water chiller heat exchangers to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

C. ASME Compliance: Fabricate and label water chiller heat exchangers to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1. SECTION 236426 - ROTARY-SCREW WATER CHILLERS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes packaged, water cooled or air cooled as scheduled, electric-motor-driven, rotary-screw water chillers

More information

15900 HVAC INSTRUMENTATION AND CONTROLS

15900 HVAC INSTRUMENTATION AND CONTROLS 15900 HVAC INSTRUMENTATION AND CONTROLS PART 1 GENERAL - Andover Controls BAS system is the standard for the University, and may be specified as a proprietary item. 1.0 RELATED DOCUMENTS A. Drawings and

More information

Submitted to. Texas A&M University at Galveston The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

Submitted to. Texas A&M University at Galveston The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge ESL-TR-99/12-05 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University at Galveston (TAMU-G) Galveston, Texas Submitted to Texas A&M University

More information

ISERIES VERTICAL AHU ENGINEERING SPECIFICATIONS

ISERIES VERTICAL AHU ENGINEERING SPECIFICATIONS ISERIES VERTICAL AHU ENGINEERING SPECIFICATIONS BULLETIN 20-131.001 Page 1 Copyright 2017 Unico Inc. TABLE OF CONTENTS APPLICATIONS... 3 CABINET CONSTRUCTION... 3 FEATURES AND CONTROLS... 3 DIMENSIONAL

More information

Modular Supply Make-Up Air Unit

Modular Supply Make-Up Air Unit Modular Supply Make-Up Air Unit Model MSX Flexible Design Factory Assembled Heating Options Hot Water Steam Electric Cooling Options Evaporative Direct Expansion Chilled Water November 2009 Product Features

More information

SECTION AIR COOLED WATER CHILLERS

SECTION AIR COOLED WATER CHILLERS PART 1 GENERAL 1.1 SECTION INCLUDES A. Chiller package B. Charge of refrigerant and oil C. Controls and control connections D. Chilled water connections E. Starters F. Electrical power connections 1.2

More information

BOOK 1 OVERVIEW RD2XRT INSTALLATION AND OPERATION MANUAL. Table of Contents ABOUT BOOK 1:

BOOK 1 OVERVIEW RD2XRT INSTALLATION AND OPERATION MANUAL. Table of Contents ABOUT BOOK 1: 4510 Helgesen Drive, Madison, WI, 53718 608.221.4499, 800.627.4499, Fax: 608.221.2824 support@renewaire.com www.renewaire.com RD2XRT INSTALLATION AND OPERATION MANUAL BOOK 1 OVERVIEW ABOUT BOOK 1: This

More information

Industrial Space Heating Direct Gas-Fired Heating. Greenheat 50/50 Recirculation

Industrial Space Heating Direct Gas-Fired Heating. Greenheat 50/50 Recirculation Industrial Space Heating Direct Gas-Fired Heating Greenheat 00% Outdoor Air Greenheat 50/50 Recirculation 80/0 Recirculation March 008 Product Overview Industrial Space Heating Greenheck s space heating

More information

HVAC DISTRIBUTION and DELIVERY SYSTEMS

HVAC DISTRIBUTION and DELIVERY SYSTEMS HVAC DISTRIBUTION and DELIVERY SYSTEMS (Part 1) Ball State Architecture ENVIRONMENTAL SYSTEMS 2 Grondzik 1 REMINDER HVAC = Heating, Ventilating, Air-Conditioning The AC part of HVAC implies a system that

More information

Brown University Revised August 3, 2012 Facilities Design & Construction Standards SECTION AIR HANDLING UNITS

Brown University Revised August 3, 2012 Facilities Design & Construction Standards SECTION AIR HANDLING UNITS SECTION 23 70 00 AIR HANDLING UNITS PART 1. GENERAL 1.1 Section includes air-handling units to 15,000 cfm and accessories. 1.2 Related Sections 1 : A. Division 01 - Brown University Standard for Narragansett

More information

SECTION AIR COILS

SECTION AIR COILS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 23 82 16 AIR COILS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also delete any other item or paragraph not applicable in the section

More information

THE FOLLOWING CHANGES/ADDITIONS TO THE ABOVE CITED SOLICITATION ARE ANNOUNCED:

THE FOLLOWING CHANGES/ADDITIONS TO THE ABOVE CITED SOLICITATION ARE ANNOUNCED: Business Services Procurement and Contracting 16550 SW Merlo Road Beaverton, OR 97003 (503) 356-4324 February 20, 2018 SOLICITATION ADDENDUM NO. 2 ITB 18-0003 Kinnaman-Hiteon Chiller Replacement THE FOLLOWING

More information

Computing Services Center

Computing Services Center Continuous Commissioning Report for the Computing Services Center Building #516 Submitted to: Utilities Energy Office Physical Plant Department Texas A&M University Prepared by: Energy Systems Laboratory

More information

PURCHASING DEPARTMENT LOUISVILLE, KENTUCKY

PURCHASING DEPARTMENT LOUISVILLE, KENTUCKY PURCHASING DEPARTMENT LOUISVILLE, KENTUCKY Date: June 14, 2017 Invitation No: IB-096-17 Title: Student Activity Center Renovation and Addition, Bid Package V Addendum No. Three (3) The following shall

More information

Zoning System Design Manual

Zoning System Design Manual Zoning Made Effortless 70-2321-03 Introduction The Concept of Zoning The basic principle of forced air zoning is to allow one HVAC system to be controlled by multiple thermostats, heating and cooling a

More information

BULLETIN. Temperature Controls (Chilled Water) Phase III only (3/11/2010)

BULLETIN. Temperature Controls (Chilled Water) Phase III only (3/11/2010) BULLETIN Temperature Controls (Chilled Water) Phase III only (3/11/2010) This bulletin is to advise you of the fees and responsibilities associated with the tenant s temperature controls. Tenant Responsibility:

More information

Problems Air and Water Distribution Systems

Problems Air and Water Distribution Systems Problems Air and Water Distribution Systems ME419 D. Abata 1. Cooled air at 1 atm, 50 F, and 10% relative humidity is transported in a 600 ft long circular sheet metal duct at a rate of 800 cfm. If the

More information

American University Design Standards

American University Design Standards 25 95 00 CONTROL SEQUENCES FOR HVAC PART 1. GENERAL 1.01 SECTION INCLUDES A. Description of Work B. Control Sequences General Requirements C. System Specific Control Sequences 1.02 RELATED DOCUMENTS A.

More information

"This is only the scope of work for the project. For more information, interested parties should contact Procurement at

This is only the scope of work for the project. For more information, interested parties should contact Procurement at "This is only the scope of work for the project. For more information, interested parties should contact Procurement at purchasing@stpgov.org to ensure receipt of a full bid package, to be listed as a

More information

Virginia Tech Standards for Building Automation System

Virginia Tech Standards for Building Automation System March 1, 2016 Virginia Tech Standards for Building Automation System A. Existing Conditions: The Campus Building Automation System is Siemens Apogee and controls all significant campus facilties. Virginia

More information

SECTION SEQUENCE OF OPERATIONS FOR BUILDING CONTROLS

SECTION SEQUENCE OF OPERATIONS FOR BUILDING CONTROLS PART 1 GENERAL 1.01 SECTION INCLUDES SECTION 23 0993 SEQUENCE OF OPERATIONS FOR BUILDING CONTROLS A. This section defines the manner and method by which controls function. Requirements for each type of

More information

Plenum Fans. Model HPA. Direct Drive

Plenum Fans. Model HPA. Direct Drive Plenum Fans Model HPA Direct Drive October 2012 Quiet & Efficient HPA Plenum Fans Greenheck s modular plenum fan, model HPA, is designed and engineered to provide superior performance and reliability in

More information

THERMA FUSER SIDEWALL LINEAR VAV DIFFUSER

THERMA FUSER SIDEWALL LINEAR VAV DIFFUSER THE ELW INTEROPERABLE THERMA FUSER SIDEWALL LINEAR VAV DIFFUSER FORM 56.1 REV 0707 SPECIFICALLY DESIGNED FOR INTEROPERABILITY The ELW provides more information about what s happening in the space than

More information

Tenant Heat Pump Bulletin Temperature Controls Buildings A1, C1, and H1

Tenant Heat Pump Bulletin Temperature Controls Buildings A1, C1, and H1 12/4/2017 Tenant Heat Pump Bulletin Temperature Controls Buildings A1, C1, and H1 This bulletin is to advise you of the fees and responsibilities associated with the tenant s temperature controls. Tenant

More information

control sequences model QST / EST Series Table 47: QST / EST Analog Electronic Control Strategies Fan Powered Air Terminals

control sequences model QST / EST Series Table 47: QST / EST Analog Electronic Control Strategies Fan Powered Air Terminals control sequences Table 47: QST / EST Analog Electronic Control Strategies Control Package Number QST EST FS-A-5000 FSE-A-5000 FS-A-5001 FSE-A-5001 FS-A-5002 FSE-A-5002 FS-A-5003 FSE-A-5003 FS-A-5004 FSE-A-5004

More information

Civil Engineering Building

Civil Engineering Building Continuous Commissioning Report For the Civil Engineering Building Building 492 Submitted to: Utilities Energy Office Physical Plant Department Texas A&M University Prepared by: Energy Systems Laboratory

More information

SECTION PACKAGED, OUTDOOR, CENTRAL-STATION AIR-HANDLING UNITS

SECTION PACKAGED, OUTDOOR, CENTRAL-STATION AIR-HANDLING UNITS SECTION 237413 - PACKAGED, OUTDOOR, CENTRAL-STATION AIR-HANDLING UNITS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes packaged, outdoor, central-station air-handling units (rooftop units) with the

More information

SECTION AIR COILS

SECTION AIR COILS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:

More information

Sequence of Operations (excerpt)

Sequence of Operations (excerpt) Sequence of Operations (excerpt) Chilled Water System Consists of one (1) 600 cooling ton Trane CVHE 3 stage centrifugal chiller, with associated chilled water pumps, condenser water pumps and one (1)

More information

4. OVERVIEW OF MECHANICAL SYSTEM

4. OVERVIEW OF MECHANICAL SYSTEM 4. OVERVIEW OF MECHANICAL SYSTEM The 87,000 SF SLCC is served by six (6) Trane M-Series Climate Changer Air Handing Units (AHUs). Each unit serves a distinct zone within the facility that is unique in

More information

BOOK 1 OVERVIEW RD2XIN INSTALLATION AND OPERATION MANUAL. Table of Contents ABOUT BOOK 1:

BOOK 1 OVERVIEW RD2XIN INSTALLATION AND OPERATION MANUAL. Table of Contents ABOUT BOOK 1: 4510 Helgesen Drive, Madison, WI, 53718 608.221.4499, 800.627.4499, Fax: 608.221.2824 support@renewaire.com www.renewaire.com RD2XIN INSTALLATION AND OPERATION MANUAL BOOK 1 OVERVIEW ABOUT BOOK 1: This

More information

SUBJECT: ADDENDUM NO. 1 RFP# , FIRE ALARM SYSTEM SERVICE (DISTRICTWIDE) REPOST

SUBJECT: ADDENDUM NO. 1 RFP# , FIRE ALARM SYSTEM SERVICE (DISTRICTWIDE) REPOST Larry Hammel Chief Financial Officer Veronica Jackson Office of Purchasing & Contracts DATE: March 15, 2018 TO: FROM: All Prospective Proposers Veronica Jackson, Purchasing and Contracts Coordinator SUBJECT:

More information

CITY OF MILTON INVITATION TO BID (THIS IS NOT AN ORDER)

CITY OF MILTON INVITATION TO BID (THIS IS NOT AN ORDER) CITY OF MILTON INVITATION TO BID (THIS IS NOT AN ORDER) Bid Number: 13-CM01 Due Date and Time: March 12th, 2013 Local Time: 2:00pm Project Name: City of Milton Outdoor Warning Siren System ISSUING DEPARTMENT

More information

VariCool VAV Engineering Guide

VariCool VAV Engineering Guide Engineering Guide Effective September 2017 Water-Cooled and Chilled Water, Variable Air Volume Contents Product Features... 3 UNIT FEATURES... 3 Product Features... 4 Marvel Plus Microprocessor Control

More information

ATTACHMENT D #1 - HVAC (OIL) - SINGLE FAMILY DWELLINGS Category C: OIL

ATTACHMENT D #1 - HVAC (OIL) - SINGLE FAMILY DWELLINGS Category C: OIL LINE ITEM # ATTACHMENT D #1 - HVAC (OIL) - SINGLE FAMILY DWELLINGS Category C: OIL LINE ITEM DETAIL Labor Material FURNACE COMPONENTS 1 Furnish & Install Sight-Impaired Thermostat For Heating and Cooling

More information

THE ULTIMATE ROOFTOP SOLUTION

THE ULTIMATE ROOFTOP SOLUTION Configured Packaged Rooftop Solutions Specializing in Dedicated Outdoor Air Systems (DOAS) Capacities from 6 to 90 Tons Available in 208, 230, 460 and 575 Volts THE ULTIMATE ROOFTOP SOLUTION Service Friendly

More information

Yes, any other system must be clean agent, and the Fire Alarm Control Panel must be a single addressable Fire Alarm Control Panel.

Yes, any other system must be clean agent, and the Fire Alarm Control Panel must be a single addressable Fire Alarm Control Panel. Please respond to: SB-8 Mayo Building Tallahassee, Florida 32399 TO: FROM: RE: Vendors Christie Hutchinson, Purchasing Director INVITATION TO BID NUMBER ITB/PI-12/13-53 INSTALLATION OF A FIRE SUPPRESSION

More information

TESTING, ADJUSTING AND BALANCING

TESTING, ADJUSTING AND BALANCING PART 1 GENERAL 1.01 DESCRIPTION A. Work Included: After completion of the work of installation, owner is responsible for procuring an air balancing and testing agency to test and regulate all components