1 Renovation Program GENERAL This program provides guidance and protocols for renovation projects in occupied, operational acute hospitals. Team building is essential to quality control and HFD Services personnel have extensive experience building relationships with healthcare facility Administrative, Engineering, and Staff groups. The program takes into consideration the type of project, location, level of construction activity, and a risk group classification for the types of patients under care. This program outline defines an example of an interior renovation involving high levels of dust from construction activity in an environment caring for high risk patients. HFD Services will serve as coordinator and manager of the various entities that will be contracted to the Client as well as liaison between contractors and hospital personnel Roswell Rd., Building 100, Atlanta, GA Office Fax com gbruton@hfdservices. com

2 PROGRAM Project Evaluation Project plan review to determine the extent and scope of work to be performed Location study to determine the use of all spaces impacted by the construction activity Development of an Infection Control Plan appropriate to the level of construction activity Evaluation of project impact on Life Safety and emergency egress routes Develop a project Contact List and determine individual responsibilities Establish and coordinate all local and internal Permit requirements Evaluate the Project Schedule duration and phasing opportunities Implementation HFDS will represent the Owner to coordinate a formal Preconstruction Meeting between the healthcare facility s Safety, Quality, Infection Control and Administrative representatives and the Contractor s Project Manager, Superintendent, Safety, and Subcontractor representatives. At a minimum, the following tasks and responsibilities will be covered: Facility access, orientation, and security requirements for all contractor personnel Facility policies for parking, smoking, and designated bathroom facilities for contractor personnel Review of permits and permit requirements from the Local Authority Having Jurisdiction (LAHJ) Review of the Project Schedule Coordinate the requirements of the Infection Control Permit with hospital personnel Determine requirements for other internal permitting including Above Ceiling Permits and Hot Work Permits Propose a plan for implementing Infection Control precautions that will satisfy the requirements of the facility s Quality Manager and those outlined in the Infection Control Permit Plan locations for temporary dust control barriers

3 Establish the methods and equipment required to place the work spaces under negative pressure to prevent dust and fumes from escaping through temporary barriers Establish safe demolition and debris removal methods, routes and dumpster location Discuss in detail the requirements of the Interim Life Safety Measures and when they will be placed in effect Provide Flame Spread data sheets and Material Safety data sheets for all construction materials that will be used on the project Coordinate a plan for relocating staff and patients as needed to complete the work, develop a phasing plan if required Prepare a schedule for receiving and incorporating Owner supplied materials and equipment if applicable Discuss the importance of a clean job site. Coordinate routine construction cleaning, final cleaning, and terminal cleaning responsibilities Set a date for Mobilization Infection Control HFDS will provide guidance to the facility s Quality Control Manager by developing an Infection Control Permit with recommendations for Infection Control methods and materials: Provide a detailed description of the location and level of Construction Activity Identify one of four levels of Construction Activity Identify one of four levels of the Infection Control Risk Group based on the location of the work and the types of patients under care Cross reference the level of Construction Activity with the Infection Control Risk Group to establish specific Infection Control Precautions required for the project Discuss the proposed Infection Control Precaution methods, barrier locations, and all materials & equipment that will be used Review the Infection Control Permit form for completeness and accuracy

4 Interim Life Safety Measures HFDS will provide recommendations for instituting specific Interim Life Safety Measures for the duration of the project, working closely with the facility s Safety Manager and Engineering Manager. Here are some key aspects to Interim Life Safety: Ensuring free and unobstructed exits, egress routes, and access for emergency services Ensuring fire alarm, detection, and suppression systems remain in good working order throughout the project Ensuring that temporary barriers are smoke tight and built of materials that will not contribute to the development or spread of fire Providing additional fire fighting equipment and ensuring that staff and contractors are trained in its use Prohibiting smoking throughout the facility and in or near construction areas Developing and enforcing storage, housekeeping, and debris removal practices that reduce the facility s flammable and combustible fire load to the lowest feasible level Establishing an increased minimum number of fire drills required per shift and per quarter throughout the duration of the project Increasing hazard surveillance of buildings, grounds, and equipment with special attention to construction areas Training staff to compensate for impaired structural or compartmentalization features of fire safety Conducting hospital wide safety education programs to promote awareness of life safety building deficiencies, construction hazards, and Interim life Safety measures Pre-construction Inspection HFDS personnel can coordinate and document a thorough Pre-construction inspection prior to commencing work. This is performed in conjunction with the contractor s Project Manager and the facility s Engineering, Safety, and Quality Control representatives. Here are several essential inspection points: Evaluate the work spaces for the presence of hazardous materials, chemicals, asbestos, confined spaces, etc. Document the status of all utilities, mechanical systems, fire safety & detection systems, and other operational life safety systems Review the Infection Control Plan and any other procedures that will reduce the risk of injury and illness

5 Review and document the erection and location of temporary barriers and methods of dust and fume control Assess the efficiency of dust barriers and negative pressure exhaust fans Review the plan for debris removal with the facility Provide documentation of the Preconstruction inspection to all responsible parties and Safety Committees Daily Monitoring Daily monitoring of safety measures and infection control is a vital part of the successful completion of healthcare facility renovation projects. HFDS will provide guidance and documentation recommendations to establish a chain of accountability for the daily monitoring of the project. A daily checklist would include: Clear unobstructed exits and egress routes Appropriate posting of signage indicating construction areas and Interim Life Safety Measures that are in effect Ensure life safety equipment and fire safety systems are in proper operating condition or a temporary equivalent system approved by the facility and the LAHJ is operational Fire Safety and employee training has been maintained and current status is established for hot work, fire watches, smoking policy, etc. Status of general safety including hand & safety rails, clean work sites, construction material storage practices, and proper documentation for all required agencies (OSHA forms, MSDS, etc.) A thorough check of all Infection Control barriers and exhaust systems

6 Renovation Program Project Closeout HFDS continues coordination all the way to final occupancy of the spaces: Observe functional testing of all newly installed systems and equipment Ensure spaces are ready for terminal cleaning by the facility s housekeeping services Coordinate a Notice of Substantial Completion with the Architect Coordinate certifications of all critical systems including but not limited to emergency power systems and transfer equipment, fire alarm systems, smoke & fire damper systems, fire sprinkler systems, nurse call systems etc. Coordination of final project documentation including facility Maintenance & Operations Manuals and As-Builts Monitor closeout of all local and internal permits, final inspections, and Certificate of Occupancy inspection(s) by the LAHJ Provide a formal turnover to the facility s Engineering representative Final turn over of the completed project to the Owner and assist with Certificate of Occupancy 8215 Roswell Rd., Building 100, Atlanta, GA Office Fax com gbruton@hfdservices. com

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY Revision No.: 11 Page 1 of 12 I. PURPOSE This procedure establishes a tool to help maintain a safe environment for all patients, visitors and staff by evaluating the loss of a life safety feature during

More information

This policy may also be used for routine work orders that are Life Safety in nature and cannot be completed within 45-days.

This policy may also be used for routine work orders that are Life Safety in nature and cannot be completed within 45-days. Policy: It is the policy of the St. Joseph Mercy Health System (SJMHS- Ann Arbor, Oakland, Livingston, Brighton, Chelsea and St. Mary Mercy Hospital- Livonia) and associated satellite facilities to assure

More information

Procedure DESCRIPTION/OVERVIEW

Procedure DESCRIPTION/OVERVIEW Applies To: UNMH Responsible Department: Life Safety Revised: 07.08.16 Procedure Patient Age Group: (X ) N/A ( ) All Ages ( ) Newborns ( ) Pediatric ( ) Adult DESCRIPTION/OVERVIEW To assure the safety

More information

UNIVERSITY OF TOLEDO

UNIVERSITY OF TOLEDO UNIVERSITY OF TOLEDO SUBJECT: INTERIM LIFE SAFETY MEASURES AND INFECTION Procedure No: LS-08-008 CONTROL PROCEDURE STATEMENT Interim life safety and infection control measures will be implemented to protect

More information

Interim Life Safety Measures. Healthcare Construction Certificate - Level 1

Interim Life Safety Measures. Healthcare Construction Certificate - Level 1 Interim Life Safety Measures Purpose of Interim Life Safety Management BASIC SAFETY: During renovations projects in healthcare occupancies, the basic level of protection for the occupants must be maintained

More information

Measures (ILSM) Process

Measures (ILSM) Process Managing the Interim Life Safety Measures (ILSM) Process 1 A Program for The Texas Association of Healthcare Facility Management Monday, April 30, 2012 Robert H. Bartels, CHFM CHSP CHEP SASHE President,

More information

LIFE SAFETY & FIRE PREVENTION MANAGEMENT PLAN

LIFE SAFETY & FIRE PREVENTION MANAGEMENT PLAN Title/Description: Life Safety & Fire Prevention Management Department: Facilities Management Personnel: All Effective Date: 5/97 Revised: 7/00, 7/01, 7/02, 7/03, 7/04, 7/05, 7/08 LIFE SAFETY & FIRE PREVENTION

More information

Interim Life Safety Assessments and Infection Prevention Assessments

Interim Life Safety Assessments and Infection Prevention Assessments Interim Life Safety Assessments and Infection Prevention Assessments 1 Healthcare Construction ILSM and ICRAs PRESENTED BY Bob Dubiel, CHFM, CHC -Mayo Clinic Health System NWWI -Projects and Construction

More information

Lancaster General Health. Contractor Safety Management Orientation Manual

Lancaster General Health. Contractor Safety Management Orientation Manual Lancaster General Health Contractor Safety Management Orientation Manual Instructions for using the Lancaster General Health Contractor Orientation Manual: 1. Provide this orientation manual to all contractors

More information

Safety Policy Manual Policy No. 145

Safety Policy Manual Policy No. 145 Policy: Interim Life Safety (ILS) Program Page 1 of 9 APPLICATION NYU Langone PURPOSE To ensure adequate life safety protection: When a standpipe, sprinkler, or fire alarm system is out-of-service. When

More information

Onsite Fire Risk Reduction Methods

Onsite Fire Risk Reduction Methods Onsite Fire Risk Reduction Methods Outline Construction Fire Background Site Safety Code Requirements Construction Fire Safety Practices Additional Resources Construction Fire Statistics According to NFPA,

More information

Risk Management Services

Risk Management Services Risk Management Services FIRE PROTECTION IMPAIRMENT PROGRAM Introduction Fire protection systems represent a significant capital investment for organizations. Companies want to make sure that they are

More information

2010 FIRE CODE OF NEW YORK STATE

2010 FIRE CODE OF NEW YORK STATE 2010 FIRE CODE OF NEW YORK STATE CHAPTER 14 FIRE SAFETY DURING CONSTRUCTION AND DEMOLITION SECTION 1401 GENERAL 1401.1 Scope. This chapter shall apply to structures in the course of construction, alteration,

More information

POLICY NUMBER ISSUE DATE REVISED DATE REVIEW DATE

POLICY NUMBER ISSUE DATE REVISED DATE REVIEW DATE POLICY NAME: IMPLEMENTATION OF INTERIM LIFE SAFETY MEASURES, FIRE SYSTEM IMPAIRMENTS, AND FIRE WATCH (formerly Implementation of Interim Life Safety Measures) POLICY NUMBER: S06-10 ISSUE DATE: FEBRUARY

More information

Department Of Public Works: Internal Operations

Department Of Public Works: Internal Operations Department Of Public Works: Internal Operations A Checklist There are over 800 municipalities in the Michigan Municipal League s Pool and Fund Programs. Most perform public works functions of one type

More information

Hot Work Policy. Department of Risk Management. 1. Purpose. 2. Authority. 3. Scope

Hot Work Policy. Department of Risk Management. 1. Purpose. 2. Authority. 3. Scope 1. Purpose The purpose of the University of Denver Hot Work policy is to protect personnel and property from a fire caused by hot work. The DU Hot Work policy defines the responsibilities and requirements

More information

Other EC and LS documents may be requested by surveyors, as needed, throughout the survey.

Other EC and LS documents may be requested by surveyors, as needed, throughout the survey. Documentation required by the Hospital Accreditation program Life Safety (LS) and selected Environment of Care (EC) standards is presented in the following pages. These documents will be reviewed by the

More information

FIRE SAFETY PLAN FOR CONSTRUCTION, RENOVATION AND DEMOLITION SITES

FIRE SAFETY PLAN FOR CONSTRUCTION, RENOVATION AND DEMOLITION SITES BACKGROUND INFORMATION Alberta Fire Code 2014: FIRE SAFETY PLAN FOR CONSTRUCTION, RENOVATION AND DEMOLITION SITES Alberta Fire Code (AFC) 2014, Division B, Section 5.6. requires a Fire Safety Plan for

More information

First Aspen Federal Regulation Set: K LSC 2000 Health Existing

First Aspen Federal Regulation Set: K LSC 2000 Health Existing First Aspen Federal Regulation Set: K 01.01 LSC 2000 Health Existing K 0000 Title CFR Type INITIAL COMMENTS Memo K 0011 If the building has a common wall with a nonconforming building, the common wall

More information

Xavier Field Office Fire Prevention Plan. for. Xavier Field Office Dana Avenue

Xavier Field Office Fire Prevention Plan. for. Xavier Field Office Dana Avenue Xavier Field Office for Xavier Field Office 1601 Dana Avenue Xavier University January 30, 2012 Ken Grossman Page 1 10/29/2013 Table of Contents Introduction... 3 Responsibilities... 3 Major Workplace

More information

The University of Chicago Medical Center

The University of Chicago Medical Center POLICY NAME: INTERIM LIFE SAFETY MEASURES, FIRE SYSTEM IMPAIRMENTS, AND FIRE WATCH POLICY NUMBER: S06-10 ISSUE DATE: FEBRUARY 10, 2004 REVISED DATE: MAY 10, 2017 REVIEW DATE: MAY 10, 2017 PURPOSE: The

More information

EC 5.10 FIRE PREVENTION MANAGEMENT

EC 5.10 FIRE PREVENTION MANAGEMENT EC 5.10 FIRE PREVENTION MANAGEMENT The organization manages fire safety risks. 1 The organization develops and maintains a written management plan describing the processes it implements to effectively

More information

IIPP. Injury & Illness Prevention Program Hartog Drive San Jose CA Responsibilities. Workplace Hazards. Training. Incident Investigations

IIPP. Injury & Illness Prevention Program Hartog Drive San Jose CA Responsibilities. Workplace Hazards. Training. Incident Investigations Injury & Illness Prevention Program Responsibilities Training Workplace Hazards IIPP Recordkeeping Incident Investigations Employee Communications 1876 Hartog Drive San Jose CA 95131 Page 1 of 23 IIPP

More information

Contractor Safety. Workplace Safety & Environmental Division

Contractor Safety. Workplace Safety & Environmental Division Contractor Safety Workplace Safety & Environmental Division Click to edit Master title style This information is designed for tradespersons and persons supervising tradespersons who are performing work

More information

Beth Israel Deaconess Medical Center BIDMC Manual

Beth Israel Deaconess Medical Center BIDMC Manual Beth Israel Deaconess Medical Center BIDMC Manual Title: Life Safety/Fire Safety Management Plan Policy #: EOC-04 Purpose: The BIDMC Life Safety Management Plan defines the program to minimize the probability

More information

DUKE CLINIC SITE-SPECIFIC FIRE PLAN Part II General Statement. Fire Procedures

DUKE CLINIC SITE-SPECIFIC FIRE PLAN Part II General Statement. Fire Procedures OCCUPATIONAL AND ENVIRONMENTAL SAFETY OFFICE DUKE CLINIC SITE-SPECIFIC FIRE PLAN Part II General Statement This Department also adheres to the Duke University Safety Manual located at http://www.safety.duke.edu.

More information

CAMPUS COMMUNITY FIRE AND LIFE SAFETY POLICY

CAMPUS COMMUNITY FIRE AND LIFE SAFETY POLICY CAMPUS COMMUNITY FIRE AND LIFE SAFETY POLICY Origination Date: July 1 st 2009 1. PURPOSE The purpose of this policy is to create a safe environment for faculty, staff, students and visitors by applying

More information

SURREY FIRE SERVICE. Construction Fire Safety Plan Bulletin

SURREY FIRE SERVICE. Construction Fire Safety Plan Bulletin SURREY FIRE SERVICE Construction Fire Safety Plan Bulletin The B.C. Fire Code requires building owners/contractors to comply with the requirements of the BC Fire Code 5.6 Construction and Demolition Sites

More information

Code Red Consultants- Fire Door Inspection, Testing, and Maintenance 1/5/2018. Learning Objectives. NFPA 241 Implementation

Code Red Consultants- Fire Door Inspection, Testing, and Maintenance 1/5/2018. Learning Objectives. NFPA 241 Implementation NFPA 241 Implementation Presented by: Peter Harrod, P.E. Chad Farrell, P.E. Learning Objectives Scoping and Purpose At what project milestones is the property owner s involvement necessary? Who is responsible

More information

Fire Safety Plan Information. For Construction and Demolition Sites

Fire Safety Plan Information. For Construction and Demolition Sites Fire Safety Plan Information For Construction and Demolition Sites FIRE CODE INTERPRETATION November 2009 FCI-09-03 Page 1 of 8 ISSUE: FIRE SAFETY PLAN Construction and Demolition Sites Safety provisions

More information

SCALES NW EMERGENCY ACTION PLAN

SCALES NW EMERGENCY ACTION PLAN Purpose Each SCALES NW, INC location shall have a written Emergency Action Plan, appropriate to the hazards of the workplace, in order to respond to an emergency that may require rescue or evacuation.

More information

WELDING, CUTTING, AND BRAZING SAFETY PROGRAM

WELDING, CUTTING, AND BRAZING SAFETY PROGRAM WELDING, CUTTING, AND BRAZING SAFETY PROGRAM HOT WORK TABLE OF CONTENTS 1.0 Introduction 1.1 Purpose 1.2 Scope 2.0 Responsibilities 2.1 Building Office 2.2 Building Personnel 2.3 Individuals Performing

More information

The Social Accountability International (SAI) Fire Safety Checklist

The Social Accountability International (SAI) Fire Safety Checklist The Social Accountability International (SAI) Fire Safety Checklist Introduction The Social Accountability International (SAI) Fire Safety Checklist is a guidance tool prepared for SA8000 & BSCI Auditors

More information

Fire Prevention Plan for

Fire Prevention Plan for Kuhlman Hall for Kuhlman Hall 3824 Ledgewood Avenue Xavier University November 9, 2006 Steve Owen Page 1 10/29/2013 Table of Contents Introduction... 3 Responsibilities... 3 Major Workplace Fire Hazards...

More information

FIRE SAFETY AND PREVENTION POLICY

FIRE SAFETY AND PREVENTION POLICY Effective Date: July 26, 2011 Supersedes /Amends: VRS-49/April 2006 Originating Office: Office of the Vice-President, Services Policy Number: VPS-49 PREAMBLE Concordia University (the University ) has

More information

General Safety Training

General Safety Training General Safety Training May 20, 2015 Outline Purpose Chancellor s Policy Statement Safety Responsibilities General Safety Rules Hazard Communication Reducing Hazard Exposure Fires and Fire Extinguishers

More information

FIRE SAFETY PRACTICES AND PROCEDURES

FIRE SAFETY PRACTICES AND PROCEDURES FIRE SAFETY PRACTICES AND PROCEDURES One of the most costly and destructive causes for loss of life and property that the City could experience would be from a major fire. Reporting Fires All employees

More information

Camden County Fire Rescue Office of the Fire Marshal 125 N. Gross Road, Kingsland, GA

Camden County Fire Rescue Office of the Fire Marshal 125 N. Gross Road, Kingsland, GA Camden County Fire Rescue Office of the Fire Marshal 125 N. Gross Road, Kingsland, GA 31548 912-510-4302 February 9, 2011 Greetings Camden County Businesses, As always, our department is working vigilantly

More information

Written Fire Safety Plans

Written Fire Safety Plans Written Fire Safety Plans 2012 LSC KATHARINE ACHOR SEPTEMBER 2016 NFPA Standard: 2012 NFPA 101, 19.1.1.3.1 All health care facilities shall be designed, constructed, maintained, and operated to minimize

More information

John Jay College of Criminal Justice HOT WORK PERMIT STANDARD OPERATING PROCEDURES

John Jay College of Criminal Justice HOT WORK PERMIT STANDARD OPERATING PROCEDURES John Jay College of Criminal Justice HOT WORK PERMIT STANDARD OPERATING PROCEDURES Last Updated: July 18, 2013 1 TABLE OF CONTENTS A. PURPOSE 3 B. SCOPE 3 C. POLICIES AND PROCEDURES 3 1. Facility Hot Work

More information

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY Revision No.: 5 Page 1 of 6 I. PURPOSE This policy outlines the guidelines for posting a fire watch if the fire alarm and/or fire suppression system in any University building becomes inoperable and the

More information

Agency for Health Care Administration

Agency for Health Care Administration Page 1 of 130 ST - K0000 - Initial Comments Title Initial Comments Statute or Rule Type Memo Tag These guidelines are meant solely to provide guidance to surveyors in the survey process. Based on the LSC

More information

Fire Safety, Risks, & Response at Jackson Health System JHS Annual Mandatory Education

Fire Safety, Risks, & Response at Jackson Health System JHS Annual Mandatory Education Fire Safety, Risks, & Response at Jackson Health System 2016 JHS Annual Mandatory Education Objectives of this module Become familiar with applicable administrative policies related to Fire Safety, Risks,

More information

Emergency Planning for Institutional Facilities

Emergency Planning for Institutional Facilities Emergency Planning for Institutional Facilities Pacific ADA Emergency Preparedness Webinars Presented by: Kimberly Paarlberg, ICC Based on the 2015 edition of the International Building Code (IBC) and

More information

Fire Prevention Plan for Cintas Center 1624 Musketeer Drive

Fire Prevention Plan for Cintas Center 1624 Musketeer Drive Athletics Xavier Dining Cintas Center Operations Xavier Leadership Center for Cintas Center 1624 Musketeer Drive Xavier University November 1, 2006 Ken Grossman Page 1 10/29/2013 Table of Contents Introduction...

More information

DUQUESNE UNIVERSITY. Fire Protection System Impairment Program (Red etag Permit)

DUQUESNE UNIVERSITY. Fire Protection System Impairment Program (Red etag Permit) DUQUESNE UNIVERSITY Fire Protection System Impairment Program (Red etag Permit) Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Purpose 1 Scope 1 Exceptions 2 Definitions

More information

Standards Revisions Related to Life Safety Code Update

Standards Revisions Related to Life Safety Code Update Prepublication Issued Requirements The Joint Commission has approved the following revisions for prepublication. While revised requirements are published in the semiannual updates to the print manuals

More information

CHAPTER 7 ALTERATIONS LEVEL

CHAPTER 7 ALTERATIONS LEVEL CHAPTER 7 ALTERATIONS LEVEL 2 SECTION 701 GENERAL 701.1 Scope. Level 2 alterations as described in Section 404 shall comply with the requirements of this chapter. Exception: Buildings in which the reconfiguration

More information

General Safety Training

General Safety Training Environmental Health and Safety General Safety Training Revised February 3, 2017 Outline Purpose Chancellor's Policy Statement Safety Responsibilities General Safety Rules Hazard Communication Reducing

More information

LOS ANGELES UNIFIED SCHOOL DISTRICT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY PROCEDURE

LOS ANGELES UNIFIED SCHOOL DISTRICT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY PROCEDURE TITLE: ISSUER: Occupancy Inspections for New Schools and Modernization Projects John Sterritt, Director Office of Environmental Health and Safety ROUTING Office of Environmental Health & Safety Staff DATE:

More information

INFORMATION BULLETIN

INFORMATION BULLETIN INFORMATION BULLETIN Revised: April 9, 2013 Ministry of Justice Emergency Management BC Fire Safety Planning for Construction and Demolition Sites The purpose of this Information Bulletin is to provide

More information

PRINTED: 06/09/2017 FORM APPROVED CENTERS FOR MEDICARE & MEDICAID SERVICES OMB NO (X2) MULTIPLE CONSTRUCTION A. BUILDING 03 - A BUILDING

PRINTED: 06/09/2017 FORM APPROVED CENTERS FOR MEDICARE & MEDICAID SERVICES OMB NO (X2) MULTIPLE CONSTRUCTION A. BUILDING 03 - A BUILDING SUMMARY PROVER'S PLAN OF CORRECTION K 000 INITIAL COMMENTS K 000 A Life Safety Code Survey was conducted by the State Fire Marshal beginning on May 9th, 2017 and ending on May 10th, 2017. Adair Acute Care

More information

Savard Labor & Marine Staffing, Inc. Fire Prevention Program Rev3/14

Savard Labor & Marine Staffing, Inc. Fire Prevention Program Rev3/14 Fire Prevention Program Purpose The Company Fire Safety Plan has been developed to work in conjunction with company emergency plans and other safety programs. This includes reviewing all new building construction

More information

OXNARD FIRE DEPARTMENT Fire Watch Guidelines

OXNARD FIRE DEPARTMENT Fire Watch Guidelines OXNARD FIRE DEPARTMENT Fire Watch Guidelines What is a Fire Watch? A Fire Watch is a temporary measure intended to ensure continuous and systematic surveillance of an activity, building or portion thereof

More information

Fire Safety Plan (FSP) Review Checklist 1

Fire Safety Plan (FSP) Review Checklist 1 Fire Safety Plan (FSP) Review Checklist 1 (Component of a BC Fire Code (BCFC) compliance inspection) COMPANY INFORMATION Company name: Building Name: Address: Street # and name City/Province Postal Code

More information

Building Self-Inspection Program

Building Self-Inspection Program Building Self-Inspection Program www.tridentinsurance.net Lines of Business: Property, General Liability, Worker s Compensation, Public Official Liability Risk Control Strategy/Key Issues: Reduce physical

More information

Fire Safety Plan (FSP) Review Checklist 1

Fire Safety Plan (FSP) Review Checklist 1 Fire Inspection & Prevention Initiative Fire Safety Plan (FSP) Review Checklist 1 (Component of a BC Fire Code (BCFC) compliance inspection) Date: COMPANY INFORMATION Company Name: Building Name: Address:

More information

a) Establishment of emergency procedures to be followed at the time of an emergency;

a) Establishment of emergency procedures to be followed at the time of an emergency; 5.10 Fire Safety 5.10.1 Introduction The Corporation is responsible for carrying out the provisions of the Ontario Fire Code. This section outlines our responsibilities as well as inspections and testing

More information

New School Construction: Safe School Opening. OAR and IOR Joint Training February 17, 2005

New School Construction: Safe School Opening. OAR and IOR Joint Training February 17, 2005 New School Construction: Safe School Opening OAR and IOR Joint Training February 17, 2005 1 Purpose Provide information on process moving from construction to occupancy and opening schools 2 School Opening

More information

Fire Prevention Plan for Alter Hall 3743 Ledgewood Drive

Fire Prevention Plan for Alter Hall 3743 Ledgewood Drive Administrative Office and Classroom Building for Alter Hall 3743 Ledgewood Drive Xavier University October 2, 2006 Page 1 3/3/2016 Table of Contents Introduction... 3 Responsibilities... 3 Major Workplace

More information

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 6

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 6 BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 6 1. Purpose This policy sets forth requirements for preventing and detecting fires, sounding an alarm, and suppressing fires. Fire protection

More information

Fire Prevention Plan for Alumni Center 1507 Dana Avenue

Fire Prevention Plan for Alumni Center 1507 Dana Avenue University Relations Division Department of Physical Plant Human Resources Community Building Institute Office of University Communications and Administrative Office Building Fire Prevention Plan for Alumni

More information

Fire Prevention Plan for Campus Services Building 1630 Musketeer Drive

Fire Prevention Plan for Campus Services Building 1630 Musketeer Drive Application Services and Technology Support Mailing Services for Campus Services Building 1630 Musketeer Drive Xavier University October 31, 2006 Ken Grossman Page 1 10/29/2013 Table of Contents Introduction...

More information

NFPA 101 Life Safety Code Culture change 2012

NFPA 101 Life Safety Code Culture change 2012 NFPA 101 Life Safety Code Culture change 2012 Produced by Kansas Fire Marshal April, 2012 On March 9, 2012 Centers for Medicare & Medicaid Services implements a policy where they have formally adopted

More information

Agency for Health Care Administration

Agency for Health Care Administration Page 1 of 51 FED - K0000 - INITIAL COMMENTS Title INITIAL COMMENTS CFR Type Memo Tag FED - K0130 - MISCELLANEOUS Title MISCELLANEOUS OTHER LSC DEFICIENCY NOT ON 2786 FED - K9999 - FINAL OBSERVATIONS Title

More information

Agency for Health Care Administration

Agency for Health Care Administration Page 1 of 100 FED - K0000 - INITIAL COMMENTS Title INITIAL COMMENTS CFR Type Memo Tag FED - K9999 - FINAL OBSERVATIONS Title FINAL OBSERVATIONS CFR Type Memo Tag FED - KA100 - General Requirements - Other

More information

Builders Risk - Fire Prevention Inspection Checklist

Builders Risk - Fire Prevention Inspection Checklist Builders Risk - Fire Prevention Inspection Checklist Use our inspection checklist tool to help you identify and monitor risk related to builders risk of fire on the job site. Inspection Details: Inspector

More information

Emergency Action Fire Prevention Plan

Emergency Action Fire Prevention Plan Emergency Action Fire Prevention Plan Table of Contents Section Title Page 1.0 Purpose 2 2.0 Scope and Application 2 3.0 Responsibilities 2-3 University Safety Coordinator 2-3 Department Heads, Supervisors

More information

Minimum Standards for Engineers Practicing Fire Protection Engineering in the State of Oklahoma September 14, 2016

Minimum Standards for Engineers Practicing Fire Protection Engineering in the State of Oklahoma September 14, 2016 1. Introduction The intent of this document is to establish minimum standards for the practice of fire protection engineering within the State of Oklahoma as conducted by licensed professional engineers.

More information

AFEC FIRE ENGINEERING TEMPLATE FOR CLIENTS INTERNALLY COMPLETED RISK ASSESMENT

AFEC FIRE ENGINEERING TEMPLATE FOR CLIENTS INTERNALLY COMPLETED RISK ASSESMENT AFEC FIRE & RISK ENGINEERING SPECIALISTS would like to share an in house Risk Assessment Template we have developed for in house use to assist Facilities Managers and Environmental Health and Safety Staff

More information

Fire Prevention Plan for Residence Life 1625 Musketeer Drive

Fire Prevention Plan for Residence Life 1625 Musketeer Drive Residence Life for Residence Life 1625 Musketeer Drive Xavier University November 14, 2006 Ken Grossman Page 1 10/29/2013 Table of Contents Introduction... 3 Responsibilities... 3 Major Workplace Fire

More information

EXAMPLE FIRE PREVENTION AND PROTECTION PLAN WORKSHEET

EXAMPLE FIRE PREVENTION AND PROTECTION PLAN WORKSHEET EXAMPLE FIRE PREVENTION AND PROTECTION PLAN WORKSHEET Directions: This worksheet is intended to guide General Contractors through development of a site-specific fire prevention and protection plan meeting

More information

FIRE PREVENTION PLAN EMERGENCY ACTION

FIRE PREVENTION PLAN EMERGENCY ACTION FIRE PREVENTION PLAN EMERGENCY ACTION 1.0 PURPOSE This Plan is presented for University employees to be informed so that they react safely and effectively during an emergency situation. The Plan also reinforces

More information

Agency for Health Care Administration

Agency for Health Care Administration Page 1 of 21 ST - K0000 - INITIAL COMMENTS Title INITIAL COMMENTS Statute or Rule Type Memo Tag These guidelines are meant solely to provide guidance to surveyors in the survey process. ST - K0300 - Other

More information

ALARM SYSTEMS AND EVACUATION PLANS SELF INSPECTION CHECKLIST

ALARM SYSTEMS AND EVACUATION PLANS SELF INSPECTION CHECKLIST OPTIONAL INFORMATION Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: ALARM SYSTEMS AND EVACUATION PLANS Guidelines: This checklist covers regulations issued

More information

Health, Safety and Wellbeing Management Arrangements. Core I Consider I Complex. Fire Safety. Health, Safety and Wellbeing Service

Health, Safety and Wellbeing Management Arrangements. Core I Consider I Complex. Fire Safety. Health, Safety and Wellbeing Service Health, Safety and Wellbeing Management Arrangements Core I Consider I Complex Fire Safety Health, Safety and Wellbeing Service 1. Success Indicators The following indicators will demonstrate success in

More information

CONSTRUCTION ENVIRONMENTAL HEALTH & SAFETY EXHIBIT FIRE PREVENTION AND PROTECTION

CONSTRUCTION ENVIRONMENTAL HEALTH & SAFETY EXHIBIT FIRE PREVENTION AND PROTECTION I. Definitions CONSTRUCTION ENVIRONMENTAL HEALTH & SAFETY EXHIBIT A. Heating Device. Any device, whether electric, fuel, or gas-fired used to provide heat to an area within the construction project. B.

More information

Impairments to Fire Protection Equipment

Impairments to Fire Protection Equipment Impairments to Fire Protection Equipment INTRODUCTION Buildings and equipment are provided with fire protection and/or detection systems to reduce property damage and interruption to business in the event

More information

FIRE RISK ASSESSMENT Self Assessment

FIRE RISK ASSESSMENT Self Assessment FIRE RISK ASSESSMENT Self Assessment Important! This fire risk assessment form is to be filled in by the responsible person within a business or organisation. As this is a free download for the use of

More information

FIRE SAFETY LOG BOOK. (Record of Fire Safety Equipment Testing)

FIRE SAFETY LOG BOOK. (Record of Fire Safety Equipment Testing) FIRE SAFETY LOG BOOK (Record of Fire Safety Equipment Testing) Fire safety log book MARCH 2013 CONTENTS 1.0 PREMISES SPECIFIC INFORMATION 2.0 FIRE SAFETY EQUIPMENT TESTING 2.1 Escape Routes 2.2 Fire Warning

More information

Fire Risk Assessment Safety Checklist

Fire Risk Assessment Safety Checklist Fire Risk Assessment Safety Checklist This checklist has been prepared to help you comply with The Regulatory Reform Fire Safety Order 2005 What is the Regulatory Reform (Fire Safety) Order 2005? The Regulatory

More information

Fire Safety Audit: Part B - Questionnaire (Questionnaire Devised By Mr.R.R.Nair) Yes No x

Fire Safety Audit: Part B - Questionnaire (Questionnaire Devised By Mr.R.R.Nair) Yes No x Fire Safety Audit: Part B - Questionnaire (Questionnaire Devised By Mr.R.R.Nair) Yes No x Name & Address of the Society IDENTIFY PEOPLE AT RISK 01 Have you identified who is at risk? 02 Have you identified

More information

Fire Prevention Plan for McGrath Health and Wellness Center 1714 Cleneay Avenue

Fire Prevention Plan for McGrath Health and Wellness Center 1714 Cleneay Avenue Health and Wellness Fire Prevention Plan for McGrath Health and Wellness Center 1714 Cleneay Avenue Xavier University November 10, 2006 Ken Grossman Page 1 10/29/2013 Table of Contents Fire Prevention

More information

Steven Craft, PhD, P.Eng. FIRE SAFETY DURING THE COURSE OF CONSTRUCTION

Steven Craft, PhD, P.Eng. FIRE SAFETY DURING THE COURSE OF CONSTRUCTION Steven Craft, PhD, P.Eng. FIRE SAFETY DURING THE COURSE OF CONSTRUCTION Mid-Rise Workshop, Coast Plaza Inn, Calgary, Feb. 4 th, 2016 Outline Overview of risks Regulations Changes to 2015 NFC for mid-rise

More information

Accreditation Program: Hospital

Accreditation Program: Hospital ccreditation Program: Hospital Life Safety 2008 The Joint ommission on ccreditation of Healthcare Organizations ccreditation Program: Hospital hapter: Life Safety Standard LS.0001 The [organization] designs

More information

HOT WORK SAFETY PROGRAM:

HOT WORK SAFETY PROGRAM: HOT WORK SAFETY PROGRAM: 1.0 Purpose. To establish safe procedure for open flame or hot work process at Oklahoma City Community College (OCCC) to avoid loss of property and injury to personnel. 2.0 Scope.

More information

Safe Operating Procedure

Safe Operating Procedure Safe Operating Procedure (Revised 10/17) HOT WORK PERMIT OPERATIONS Authority In recognition of the inherent hazards posed by certain hot work processes, the National Fire Protection Agency adopted Standard

More information

This policy applies to all Hot Work jobs performed on the Calhoun mill property by AbitibiAbitibiBowater employees.

This policy applies to all Hot Work jobs performed on the Calhoun mill property by AbitibiAbitibiBowater employees. Reviewed: July 30, 2009 Revised: July 30, 2009 Effective: October 1, 2007 I. PURPOSE The purpose of this policy is to protect employees and prevent property loss due to fire and/or explosion during welding

More information

-SAMPLE- Safety Inspection Checklist: Manufacturing

-SAMPLE- Safety Inspection Checklist: Manufacturing -SAMPLE- Safety Inspection Checklist: Manufacturing Prepared by: Midwest Builders Casualty The following procedures are not intended to be an exhaustive treatment of the subject, and should not be interpreted

More information

I. Scope: II. Environmental Health and Safety Fire Alarm System Impairment Program - Guideline Revision Date: April, 2018

I. Scope: II. Environmental Health and Safety Fire Alarm System Impairment Program - Guideline Revision Date: April, 2018 Environmental Health and Safety Fire Alarm System Impairment Program - Guideline Revision Date: April, 2018 Prepared by: EH&S The probability of casualties and major structural damage increases when fire

More information

FIRE SAFETY POLICY LEEDS METHODIST MISSION. Oxford Place Centre

FIRE SAFETY POLICY LEEDS METHODIST MISSION. Oxford Place Centre FIRE SAFETY POLICY LEEDS METHODIST MISSION Oxford Place Centre P a g e 2 8 Version Draft 1 Name of responsible (ratifying) committee Leeds Methodist Mission Council Date ratified Document Manager (job

More information

Safety Best Practices Manual

Safety Best Practices Manual CHAPTER 24 OSHA Compliance Checklist te: This is not a comprehensive checklist. It is designed for a typical corporate aviation maintenance department. You must consult the OSHA 1910 Regulations for specific

More information

NOT PROTECTIVELY MARKED. Fire Legislation

NOT PROTECTIVELY MARKED. Fire Legislation Fire Legislation Contents Policy Statement... 2 Legislation... 2 Fire Extinguisher Usage... 2 Fire Evacuation Procedure... 3... 4 Line Managers/Supervisors... 4 Business Support Officer... 5 Driver/Handy

More information

Slight Harm Moderate Harm Extreme Harm Low Trivial Risk Tolerable Risk Moderate Risk Medium Tolerable Risk Moderate Risk Substantial Risk

Slight Harm Moderate Harm Extreme Harm Low Trivial Risk Tolerable Risk Moderate Risk Medium Tolerable Risk Moderate Risk Substantial Risk Fire Risk Assessment: ABC Sample House Sample Road SA1 3M2 C J Sparks Ltd 13 Alexandra Gardens Carshalton SM5 4LJ T: 02077577457 W: www.cjsparks.com E: sales@cjsparks.com Ref: 3077 Action Plan Number Action

More information

- CONSTRUCTION FIRE SAFETY STANDARDS

- CONSTRUCTION FIRE SAFETY STANDARDS SGG15 - CONSTRUCTION FIRE SAFETY STANDARDS 1) Construction Planning All construction sites shall plan and sequence their construction activities to ensure the early installation and operation of permanent

More information

1303 Trans Canada Way SE Medicine Hat, AB T1B 3Z9 Phone

1303 Trans Canada Way SE Medicine Hat, AB T1B 3Z9 Phone Medicine Hat Fire Service Construction Site Fire Safety Plan ABC Part 9 Buildings 1303 Trans Canada Way SE Medicine Hat, AB T1B 3Z9 Phone 403-529-8282 Email fireprevention@medicinehat.ca Small Buildings

More information

Fire Risk Assessment Case Study

Fire Risk Assessment Case Study Appendix B Fire Risk Assessment Case Study The purpose of this case study is to illustrate one practical approach to conducting a fire risk assessment. The checklist and proformas used in this case study

More information

WORKPLACE EVALUATION CHECKLIST & REPORT

WORKPLACE EVALUATION CHECKLIST & REPORT Work Center: Supervisor: Telephone Number: Building & Room Number: Date of Last Evaluation: Date: WORKPLACE EVALUATION CHECKLIST & REPORT ITEM YES NO N/A COMMENTS Has this area been surveyed in the last

More information

OUTLINE FOR FIRE PREVENTION ACTIVITY

OUTLINE FOR FIRE PREVENTION ACTIVITY OUTLINE FOR FIRE PREVENTION ACTIVITY Background Buildings under construction present unique fire exposures that require special attention. Fires can result in major losses and long delays in the completion

More information

Guidelines for Fire Safety Plans at Construction or Demolition Sites

Guidelines for Fire Safety Plans at Construction or Demolition Sites Guidelines for Fire Safety Plans at Construction or Demolition Sites Sun Peaks Fire Rescue P.O. Box 1000, Sun Peaks, V0E 5N0 Phone 250-578-8985 Fax 250-578-8905 Guidelines for Fire Safety Plans at Construction

More information