Piles, inverters, trenching, cabling, assembly.

Size: px
Start display at page:

Download "Piles, inverters, trenching, cabling, assembly."

Transcription

1 Agricultural Inspection Report General Information Project Name Montrose Date of Inspection 11/9/2016 Start/End Time 7:00 am Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Piles, inverters, trenching, cabling, assembly. Weather Information Weather at time of this inspection? Clear, temperature in the upper 20s to low 30s. General Inspection Notes: Additional personnel accompanying me on the site inspections included Ryan Molsee (Enel), Karl Everett (Biosar), and Jacob Thompson (Barr). Site conditions have improved since last inspection due to warm, dry weather and completion of trenching and assembly activities in the most saturated portion of the site. Additional mats were placed in the laydown yard to provide adequate protection for the areas where fabric was compromised. Efforts to correct the other compliance items noted during the previous inspection continue as site conditions allow. A new deep rut was observed crossing the location of a new drain tile installation in the northwest corner of the site. The area will continue to be monitored for evidence of impact to the underlying tile. No new compliance items noted. Issues Noted During Inspection: No previously reported compliance items were identified. Corrective Actions: Corrective actions discussed onsite included: Continue efforts to correct previously identified compliance items. Agricultural Inspection Report Montrose

2 Photos: Photo 1: Additional mats added to laydown area. Agricultural Inspection Report Montrose

3 Agricultural Inspection Report General Information Project Name West Waconia Date of Inspection Start/End Time 9:30 am Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Piles, inverters, setting SCADA house, cabling, trenching, assembly. Weather Information Weather at time of this inspection? Clear, temperature in the low 40s. General Inspection Notes: Additional personnel accompanying me on the site inspection today included Jacob Thompson (Barr), Karl Everett (Biosar), and Ryan Molsee (Enel). A significant amount of subsoil remained on the surface on the west end of a motor trench in the southwest portion of the site. The area was pointed out to Mark and Chris (Biosar site personnel). This is another instance of a compliance item pointed out during the previous inspection; a complete list of areas requiring further scraping of subsoils or the addition of topsoil to facilitate restoration should be identified prior to completion of construction to help guide restoration activities. Imported materials such as sand and aggregate will require additional scraping on the north end of the access road where the SCADA house was being set. Crews are not finished working in the area and the material was pointed out to a Faith worker to confirm they were aware of the need to remove more of the material prior to finishing. Severe ruts noted at the previous inspection had been filled and smoothed in some areas. Work on other compliance items is ongoing. The area in the far northern portion of the site remains very saturated and additional restoration measures may be necessary in this area to ensure successful restoration. No new compliance items were noted. Agricultural Inspection Report West Waconia

4 Issues Noted During Inspection: No new compliance items were noted. Corrective Actions: Corrective actions discussed onsite included: Corrective actions are continuing on this site to address items identified during the previous inspection. Photos: Photo 1: Topsoil remaining at surface after backfilling motor trench. Agricultural Inspection Report West Waconia

5 Agricultural Inspection Report General Information Project Name Lake Emily Date of Inspection Start/End Time 1:00 pm Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Piles, inverters, SCADA excavations, trenching and cabling. Weather Information Weather at time of this inspection? Mostly clear, temperature in the low to mid 50s. General Inspection Notes: Additional personnel accompanying me on the site inspection today included Jacob Thompson (Barr), Karl Everett (Biosar) and Ryan Molsee (Enel). Acting site manager Mark Smiley advised us that Blattner will be blading and re-rocking access roads on the site this week. Excavation of the MV trench had good separation and segregation of soil horizons. Drain tile that was hit in three locations in the trench was appropriately repaired. Torque tubes were being distributed through the site with a lull that was causing some rutting, approximately six inches in some areas, though no soil horizon mixing was observed. Evidence of improper de-watering was observed along the MV trench. Crews had procured large sediment bags, but they were the felt-like bags that are rated for oil and larger sediment separation and do not sufficiently filter small particles. Pumps were not running at the time of the inspection. Jacob and Karl discussed the issue with the Blattner field coordinator. No further compliance items noted. Issues Noted During Inspection: No significant compliance items were noted at this time. Corrective Actions: Agricultural Inspection Report Lake Emily

6 Corrective actions discussed onsite included: Proper sediment filtration bags were discussed but this is not considered a significant issue at this time. Photos: Photo 1: Repaired drain tile. Agricultural Inspection Report Lake Emily

7 Agricultural Inspection Report General Information Project Name Eastwood Date of Inspection Start/End Time 3:10 pm Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Piles, deliveries, inverters, trenching, cabling, SCADA, assembly. Weather Information Weather at time of this inspection? Clear, temperature near 60 degrees. General Inspection Notes: Additional personnel accompanying me on the site inspection today included Karl Everett (Biosar), Ryan Molsee (Enel), and Jacob Thompson (Barr). Site has experienced several areas of significant rutting; due to deep topsoil covering this site little mixing of soil horizons has been observed. Workers are continuing to stockpile residual subsoils left over from backfilling the motor trenches. Subsoil stockpile in the southwest corner of the site will be capped with topsoil once all subsoils have been removed from the arrays. Some subsoils were found to have been added to the topsoil pile. Joe (Biosar site manager) will have the material removed. Work to correct items noted during last week s inspections has continued. The site continues to experience significant levels of rutting and compaction, though these issues are expected to improve with continued warm, dry weather. Improper dewatering setups were identified and addressed with the site manager and other subcontractor personnel. Issues Noted During Inspection: Subsoils added to topsoil stockpile. Improper dewatering setups. Corrective Actions: Corrective actions discussed onsite included: Agricultural Inspection Report Eastwood

8 Remove subsoils from topsoil stockpile. Use proper filter bags during dewatering. Continue corrective actions identified during last week s inspection. Photos: Photo 1: Topsoil deposited on access road; large rock being exposed due to Class 5 material migrating off road on tires. Agricultural Inspection Report Eastwood

9 Agricultural Inspection Report General Information Project Name Hastings Date of Inspection Start/End Time 7:00 am Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Assembly, pile driving, pile drilling, material deliveries, inverters, trenching and cabling Weather Information Weather at time of this inspection? Cloudy, temperature in the low 40s. General Inspection Notes: Additional personnel accompanying me on the site inspection today included Ryan Molsee (Enel) and Jacob Thompson (Barr). Site was in good condition. Trenches have very good separation of soil horizons. Crews are doing a good job of utilizing a limited number of designated access routes through the site. Additional work to correct pile reveal heights will involve the addition of topsoil to some areas and grading of others. No compliance items were noted. Issues Noted During Inspection: None. Corrective Actions: Corrective actions discussed onsite included: None. Agricultural Inspection Report Hastings

10 Agricultural Inspection Report General Information Project Name Pine Island Date of Inspection 11/10/2016 Start/End Time 10:00 am Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Piles driven, inverter and SCADA housing set, trenching, assembly. Weather Information Weather at time of this inspection? Partly cloudy, temperature in the low 50s. General Inspection Notes: Additional personnel accompanying me on the site inspection included Jacob Thompson (Barr) and Ryan Molsee (Enel). Available construction mats have been placed in the field on access roads. A new, corrected sediment bag was installed last Thursday for dewatering efforts. A limited amount of sediment was observed outside of the bag and a significant amount of material could be felt inside the bag. The water filtering through the bag was deemed to be adequately filtered when pumping at the slow speeds observed during the site inspection. The MV trench in the center of the site was found to have trenched through the turnaround near PCU-2. There was no segregation of soil horizons or road material. Topsoil may need to be added to the backfilled trench to ensure vegetation establishment. Issues Noted During Inspection: No separation of material and soil horizons occurred in the MV trench by PCU-2. Corrective Actions: Corrective actions discussed onsite included: Agricultural Inspection Report Pine Island

11 Ensure adequate topsoil is placed over the trench when backfilled to facilitate vegetation establishment. Photos: Photo 1: Excavation with no separation of soils and road material. Agricultural Inspection Report Pine Island

12 Agricultural Inspection Report General Information Project Name Dodge Center Date of Inspection Start/End Time 12:00 pm Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Assembly complete, CCTV cabling and trenching. Weather Information Weather at time of this inspection? Partly cloudy, temperature in the low to mid-50 s General Inspection Notes: Additional personnel accompanying me on the site inspection today included Paula Fitzgerald (Biosar), Ryan Molsee (Enel) and Jacob Thompson (Barr). Additional work has been done at the south end of the site to scrape and dry sediment that was accumulated by the vacuum trucks. More work will be needed to remove sediment in vegetation prior to final restoration. Additional excavation by the CCTV crew at the southwest corner of the laydown yard was performed without adequately separating laydown yard material from soils. Issues Noted During Inspection: Gravel and fabric were incorporated into spoils pile from the CCTV trench. Corrective Actions: Corrective actions discussed onsite included: Remove imported material from spoils prior to backfilling; keep topsoil at surface. Agricultural Inspection Report Dodge Center

13 Photos: Photo 1: No segregation of soil horizons or laydown gravel in CCTV trench. Agricultural Inspection Report Dodge Center

14 Agricultural Inspection Report General Information Project Name Albany Date of Inspection Start/End Time 7:00 am Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Piles, Trenching, Inverters, SCADA, Cables, Racking, Assembly Weather Information Weather at time of this inspection? Mostly cloudy, temperature in the low 30s. General Inspection Notes: Additional personnel accompanying me on the site inspection today included Paula Fitzgerald (Biosar), Kevin Bolling (Enel) and Mandy Bohnenblust (Barr). Site was in overall good condition. Some areas were muddy with minor rutting but no severe conditions were noted. Trash and packaging materials were found scattered throughout the site, mainly within the arrays. Clayton (Biosar site assistant manager) noted that trash will be picked up. Trash has typically been well-controlled on this site. Several incorrect sediment bags (felt-type) were observed on the site but only one was used recently. Sediment was observed on the ground and vegetation adjacent to the bag. The large POI trench in the southeast corner of the site is planned to be dewatered next week. Faith and the Biosar site personnel will coordinate with Karl Everett for dewatering. Issues Noted During Inspection: No new, significant issues. Corrective Actions: Corrective actions discussed onsite included: Trash containment. Agricultural Inspection Report Albany

15 Correct de-watering set up and subsoil sediment removal from topsoil. Agricultural Inspection Report Albany

16 Agricultural Inspection Report General Information Project Name Paynesville Date of Inspection Start/End Time 9:20 am Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Piles installed, trenching, cabling, inverters, SCADA work, assembly, deliveries. Weather Information Weather at time of this inspection? Partly sunny, temperature in the upper 30 s to low 40s. General Inspection Notes: Additional personnel accompanying me on the site inspection today included Paula Fitzgerald (Biosar), Mandy Bohnenblust (Barr) and Ryan Molsee (Enel). Several areas of deep lull ruts were observed across the southern half of the western portion of the site. Some ruts reached the subsoil layer; due to the nature of the soils, topsoil was pulled up off of the underlying subsoil but little actual mixing was observed. Proper separation of road materials, topsoil and subsoil was observed at the PCU excavation on the east side of the site. A deficient dewatering set up was observed in on the east side of the site. The hose discharging from the pump was placed into a sediment bag but nothing was used to secure the bag to the hose. Sediment had accumulated on the ground outside of the sediment bag. When the pumped water began accumulating near the work area, a worker scraped a trough into the topsoil to funnel the pumped water away from the work area. The trough led through topsoil and vegetation to the nearest perimeter silt fence that is adjacent to the wetland. Issues Noted During Inspection: Deep rutting and compaction. Improper dewatering. Agricultural Inspection Report Albany

17 Corrective Actions: Corrective actions discussed onsite included: Minimize unnecessary lull travel and consolidate travel routes. Implement proper dewatering procedures. Photos: Photo 1: Ruts reaching subsoil. Agricultural Inspection Report Albany

18 Photo 2: Lull traveling in previously undisturbed area; no designated travel routes. Photo 3: Unsecured sediment bag. Agricultural Inspection Report Albany

19 Photo 4: Trough scraped to divert water to site perimeter. Photo 5: Trough scraped to divert water to site perimeter. Agricultural Inspection Report Albany

20 Photo 6: Sediment accumulated in bottom of trough. Agricultural Inspection Report Albany

21 Agricultural Inspection Report General Information Project Name Atwater Date of Inspection Start/End Time 12:45 pm Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Piles, Inverters, Material Deliveries and Staging, Trenching, Assembly, SCADA house. Weather Information Weather at time of this inspection? Clear, temperatures in the mid 40s. General Inspection Notes: Additional personnel accompanying me on the site inspection today included Mandy Bohnenblust (Barr), Ryan Molsee (Enel), and Paula Fitzgerald (Biosar). Site is in good condition. The eastern third has been mulched with straw and disk-anchored. Weed-free forage tags were observed on bales still on trailer, and tags for bales spread onsite are kept in the construction trailer. A dewatering set up was observed to have been started with the proper sediment bag, but no zip tie or other method of securely attaching the bag to the hose. The Faith foreman had already shut the pump down prior to our arrival. Water was observed bubbling to the surface outside of the perimeter fence where the telecommunications contractor, Frontier Communications, had knifed in a cable for the SCADA house. Ed (Biosar site manager) stated that a drain tile exits the main site in the approximate location and the water is likely from this tile. Additional investigation is needed to determine if tile was damaged. Issues Noted During Inspection: Potential/Likely drain tile damage outside of perimeter fence. Corrective Actions: Corrective actions discussed onsite included: Further investigate drain tile for potential damage. Agricultural Inspection Report Atwater

22 Photos: Photo 1: Water bubbling to the surface at location of newly installed telecommunications cable. Agricultural Inspection Report Atwater

23 Agricultural Inspection Report General Information Project Name Annandale Date of Inspection Start/End Time 2:30 pm Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Piles and inverters installed, access roads complete, SWPPP updates/maintenance, material delivery, trenching, cabling, assembly Weather Information Weather at time of this inspection? Partly Cloudy, temperature in the upper 40s. General Inspection Notes: Additional personnel accompanying me on the site inspection today included Mandy Bohnenblust (Barr), and Ryan Molsee (Enel). Site is in overall good condition. Trash is being well-controlled. Minnesota Native Landscapes was onsite working on tree-planting activities around the site perimeter. The CCTV cabling crew worked through the wetland on the southern perimeter of the site. The trench was not closed and compacted in the wetland area. The area was pointed out to Kimber (Biosar assistant site manager). Issues Noted During Inspection: CCTV trench in southern wetland perimeter needs to be closed/compacted. Corrective Actions: Corrective actions discussed onsite included: Close and compact CCTV trench. Agricultural Inspection Report Annandale

24 Photos: Photo 1: CCTV cable trench remains open. Agricultural Inspection Report Annandale

25 Agricultural Inspection Report General Information Project Name Lake Pulaski Date of Inspection Start/End Time 4:00 pm Inspector s Name(s) Inspector s Title(s) Describe present phase of construction Shannon Kulseth Agricultural Monitor Grading, piles, inverters, access roads, assembly, material deliveries, laydown yard Weather Information Weather at time of this inspection? Partly cloudy, temperature in the mid 40s. General Inspection Notes: Additional personnel accompanying me on the site inspection today Ryan Molsee (Enel) and Mandy Bohnenblust (Barr). Site conditions have improved due to warm, dry weather. Improper dewatering bags were observed near a storage connex. Dane (Biosar site manager) and Luke (Blattner site manager) were informed that the correct silt bags need to be rated for fine material; the felt bags are for oil and sediment. They will obtain proper bags prior to dewatering activities. A box blade has been used to smooth some area that had been rutted previously. Significant soil disturbance was still present across the site. Due to the difficulty in differentiating soil horizons in portions of the site, the lack of topsoil in some areas prior to beginning work activities, and the widespread rutting that occurred due to working in wet conditions, it is likely that topsoil or soil amendments will be needed as part of final restoration to ensure establishment of vegetation. Issues Noted During Inspection: No significant new issues were noted. Corrective Actions: Corrective actions discussed onsite included: None. Agricultural Inspection Report Lake Pulaski

Additional personnel accompanying me on the site inspection today included Paula Fitzgerald (Biosar) and Ryan Molsee (Enel).

Additional personnel accompanying me on the site inspection today included Paula Fitzgerald (Biosar) and Ryan Molsee (Enel). Dodge Center Date of Inspection 20161114 Start/End Time 12:00 pm Assembly complete, CCTV cabling and trenching, Decompaction equipment testing Partly cloudy, temperature in the low to mid-40 s Additional

More information

Piles, Trenching, Inverters, Cables, Material Deliveries

Piles, Trenching, Inverters, Cables, Material Deliveries Agricultural Inspection Report General Information Project Name Albany Date of Inspection 20161012 Start/End Time 7:50 am Inspector s Name(s) Inspector s Title(s) Describe present phase of construction

More information

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT FIELD INSPECTION REPORT Date September 19, 2018 Project Northern Natural Gas Company (Northern) Cedar Station Upgrade Project Dakota County, Minnesota Authority: Section 7(c) Personnel FERC Staff: Company

More information

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline Agricultural Impact Minimization Plan Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline operation. PennEast

More information

Information for File # JTF

Information for File # JTF Information for File # 2013-04665-JTF Applicant Corps Contact Enbridge Energy, Limited Partnership Josh Fitzpatrick Address 1554 Highway 2, Suite 2, Two Harbors, MN 55616 E-Mail joshua.t.fitzpatrick@usace.army.mil

More information

MARBLE RIVER WIND POWER PROJECT Agricultural Protection Measures

MARBLE RIVER WIND POWER PROJECT Agricultural Protection Measures MARBLE RIVER WIND POWER PROJECT Siting Considerations 1. Locate access roads and, to the extent allowed by local laws, wetlands and topography, individual wind turbines and other structures along field

More information

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline Agricultural Impact Minimization Plan Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline operation. PennEast

More information

Information for File # ARC

Information for File # ARC Information for File # 2015-02781-ARC Applicant Corps Contact Enbridge Energy, Limited Partnership Andrew R Chambers Address 600 South Lake Avenue, Suite 211, Duluth, MN 55802 E-Mail Andrew.R.Chambers@usace.army.mil

More information

UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN

UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN 01/17/2003 VERSION UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN TABLE OF CONTENTS I. APPLICABILITY... 1 II. SUPERVISION AND INSPECTION...

More information

Preventing Storm Water Pollution: What We Can Do

Preventing Storm Water Pollution: What We Can Do Preventing Storm Water Pollution: What We Can Do ~Employee Training Series~ Land Disturbances PREPARED IN COOPERATION WITH THE Texas Commission on Environmental Quality AND U.S. ENVIRONMENTAL PROTECTION

More information

3" TO 4" OF TOPSOIL 2:1 MIRAFI HP 565 GEO FABRIC OR EQUIVALENT 9' SPILLWAY EL=7147 2:1 SPILLWAY SECTION N.T.S. TOP OF POND EL=7149' RIP-RAP D 50 8" WRAPPED IN FILTER FABRIC 45 MIL HDPE POND LINER OR EQUIVALENT

More information

Wisconsin Contractors Institute Continuing Education

Wisconsin Contractors Institute Continuing Education Wisconsin Contractors Institute Continuing Education Erosion & Sediment Control Course # 12775 2 hours Wisconsin Contractors Institute N27 W23953 Paul Road, Suite 203 Pewaukee, WI 53072 Website: www.wicontractorsinstitute.com

More information

Low Flow Rates Low Filtration Sandy Soils Medium Flow Rates Medium Filtration Clayey Soils [1] High Flow Rates High Filtration Polluted Soils

Low Flow Rates Low Filtration Sandy Soils Medium Flow Rates Medium Filtration Clayey Soils [1] High Flow Rates High Filtration Polluted Soils Filter Ponds DE-WATERING SEDIMENT CONTROL TECHNIQUE Low Flow Rates Low Filtration Sandy Soils Medium Flow Rates Medium Filtration Clayey Soils [1] High Flow Rates High Filtration Polluted Soils [1] Capture

More information

December 13, 2005 Meeting Status of NPDES Post Fire BMPs

December 13, 2005 Meeting Status of NPDES Post Fire BMPs December 13, 2005 Meeting Status of NPDES Post Fire BMPs Agenda Overview of Current Operations At SSFL Impacts of Fire At SSFL Rebuilding & Improvement of BMPs Future Activities Site Tour Close-out 1 Santa

More information

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance. The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language

More information

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE Please complete this narrative form and submit with your SWPPP drawings. Refer to Kitsap County Stormwater Design Manual Vol.

More information

SITE TOPSOIL & FINISH GRADING

SITE TOPSOIL & FINISH GRADING CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 02911-1 PART 1 GENERAL 1.1 Related Work.1 Section 02311 Site Grading.2 Section 02315 Excavating, Trenching, & Backfilling.3 Section 02906 Planting of Trees,

More information

Town of Essex Small Site Erosion Control Guide

Town of Essex Small Site Erosion Control Guide Town of Essex Small Site Erosion Control Guide Why do we need to protect against erosion? Water Quality: Erosion and the transport of sediment and pollutants impacts the water quality of nearby streams

More information

Site Formation Excavation - 6' depth square yard $8.00 $0.00 Grading square yard $1.50 $0.00 Hauling off-site - 6' depth square yard $10.00 $0.

Site Formation Excavation - 6' depth square yard $8.00 $0.00 Grading square yard $1.50 $0.00 Hauling off-site - 6' depth square yard $10.00 $0. SURFACE SAND FILTER COST ESTIMATE WORKSHEET 2005 Prices Project Title Owner Location Project Number Date Description Units Quantity Unit Cost Total Estimated Price Site Preparation Tree removal - up to

More information

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance. The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language

More information

SUPPORTING DOCUMENT POST-CONSTRUCTION SOIL QUALITY AND DEPTH WORKSHEET

SUPPORTING DOCUMENT POST-CONSTRUCTION SOIL QUALITY AND DEPTH WORKSHEET SUPPTING DOCUMENT POST-CONSTRUCTION SOIL QUALITY AND DEPTH WKSHEET For Department of Ecology Stormwater BMP T5.13 This submittal worksheet will help determine what soil amendments are needed to meet the

More information

Shelbyville, KY Stormwater Best Management Practices. Section 2 EROSION PREVENTION AND SEDIMENT CONTROL PLAN

Shelbyville, KY Stormwater Best Management Practices. Section 2 EROSION PREVENTION AND SEDIMENT CONTROL PLAN Section 2 EROSION PREVENTION AND SEDIMENT CONTROL PLAN 2.1 Requirements The City of Shelbyville, KY will require an Erosion Prevention and Sediment Control (EPSC) Plan for most types of development construction.

More information

SECTION PLANTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION PLANTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 329000 PLANTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Special Conditions and Division 01 Specification Sections, apply

More information

A. Contractor shall provide product data for each type of product indicated.

A. Contractor shall provide product data for each type of product indicated. 31 13 00 SELECTIVE TREE AND SHRUB REMOVAL AND TRIMMING SECTION 1 GENERAL 1.1 SUMMARY A. This section includes general protection and pruning of existing trees and plants that are affected by execution

More information

Guidelines to Minimize Phytophthora Contamination in Restoration Projects

Guidelines to Minimize Phytophthora Contamination in Restoration Projects Guidelines to Minimize Phytophthora Contamination in Restoration Projects These guidelines aim to avoid contamination of restoration sites with exotic pathogenic Phytophthora species or other plant pathogens

More information

Plan of Development Mountain Valley Pipeline Project. APPENDIX M Winter Construction Plan

Plan of Development Mountain Valley Pipeline Project. APPENDIX M Winter Construction Plan APPENDIX M October 20, 2017 Appendix M Prepared by: October 20, 2017 TABLE OF CONTENTS 1.0 INTRODUCTION... M-1 2.0 STABILIZATION/WINTERIZATION... M-2 3.0 EROSION AND SEDIMENT CONTROL MEASURES... M-3 4.0

More information

Pavement Removal Fact Sheet

Pavement Removal Fact Sheet Rushern L. Baker, III County Executive Pavement Removal Fact Sheet What is pavement removal? Pavement removal is the replacement of impervious surfaces, such as asphalt and concrete, with grass or native

More information

field note Culvert foundation improvement design concepts The challenge of low-cost culvert foundations

field note Culvert foundation improvement design concepts The challenge of low-cost culvert foundations field note Culvert improvement design concepts Mark Partington, R.P.F., M.Sc., EP 1 Papa Masseck Thiam, Ing. Jr., M.Sc. 2 Introduction Canada s northern forested landscapes feature numerous wetlands, such

More information

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT NOT WELL 800 - Urban Stormwater Wetlands A constructed system of shallow pools that create growing conditions for wetland plants to lessen the impacts of stormwater quality and quantity in urban areas.

More information

SILT FENCE MACHINE SLICED ERO-1A STEEL FENCE POST (T-POST), MINIMUM 5' LONG, 6' MAXIMUM SPACING.

SILT FENCE MACHINE SLICED ERO-1A STEEL FENCE POST (T-POST), MINIMUM 5' LONG, 6' MAXIMUM SPACING. STEEL FENCE POST (T-POST), MINIMUM 5' LONG, 6' MAXIMUM SPACING. ATTACH FABRIC TO POSTS WITH MINIMUM 3 ZIP TIES (50 LB. TENSILE) PER POST IN TOP 8" OF FABRIC. MONOFILAMENT GEOTEXTILE FABRIC PER MNDOT TABLE

More information

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT Date June 20, 2018 Project Northern Natural Gas Company Northern Lights 2017 Expansion Project Rice, Sherburne, and Isanti Counties, Minnesota

More information

SECTION AMENDED TOPSOIL

SECTION AMENDED TOPSOIL SECTION 02486 AMENDED TOPSOIL PART 1 - GENERAL 1.01 SUMMARY A. Work described in this section includes requirements for soil amendments, soil preparation, preparation and finish grading of turf restoration

More information

EROSION & SEDIMENT CONTROL

EROSION & SEDIMENT CONTROL EROSION & SEDIMENT CONTROL Surface Water Protection During Well Site Construction Kelly Kees, PE WVDEP, Office of Oil and Gas SEDIMENT & EROSION CONTROL PLANS Per West Virginia State Code 22-6-6(d) 22-6A-7(c),

More information

PROTECTIVE MEASURES FOR TREES DURING CONSTRUCTION

PROTECTIVE MEASURES FOR TREES DURING CONSTRUCTION PROTECTIVE MEASURES FOR TREES DURING CONSTRUCTION NO CONSTRUCTION OR EXCAVATION IS TO OCCUR ON LOTS THAT REQUIRE TREE PRESERVATION UNTIL PROPER APPROVALS HAVE BEEN GIVEN BY A CITY ARBORIST 1. When trees

More information

Cedar Niles Future Park Site Wetland #1

Cedar Niles Future Park Site Wetland #1 Date: October 20, 2014 Site: Landowner: Johnson County Parks Designer: Thomas R. Biebighauser Individuals Present: Thomas R. Biebighauser, Dr. Eliodora Chamberlain (US EPA), Jason Daniels (US EPA), Jeannette

More information

Department of Agriculture. Conservation Service. United States. Natural Resources REVISED 8/26/16

Department of Agriculture. Conservation Service. United States. Natural Resources REVISED 8/26/16 GENERAL NOTES: SYMBOL LEGEND 1. All work shall comply with the constriction specifications, drawings, project-specific quality assurance plan and other contract requirements. 2. All notes on the drawings

More information

Structural Storm Water Best Management Practices (BMPs)

Structural Storm Water Best Management Practices (BMPs) Structural Storm Water Best Management Practices (BMPs) Storm Water Permitting: The SWPPP Revealed By Deron Austin, PE January 11, 2006 3:30-5:00 PM Orlando, Florida Presentation Outline Preface About

More information

PERMANENT SEEDING. Overview of Sedimentation and Erosion Control Practices. Practice no. 6.11

PERMANENT SEEDING. Overview of Sedimentation and Erosion Control Practices. Practice no. 6.11 Overview of Sedimentation and Erosion Control Practices Practice no. 6.11 PERMANENT SEEDING Permanent vegetation controls erosion by physically protecting a bare soil surface from raindrop impact, flowing

More information

Storm Water Basics for Construction Sites Presented by Representatives from the City of Grass Valley and Nevada County

Storm Water Basics for Construction Sites Presented by Representatives from the City of Grass Valley and Nevada County September 22nd, 2015 3:30PM Sign up at: www.stormwaterawareness.org Workshop is free! Nevada County Contractor s Association 149 Crown Point Ct. Grass Valley, CA 95945 Storm Water Basics for Construction

More information

Conistone Keld/Well/Troughs Project

Conistone Keld/Well/Troughs Project CONISTONE KELD PROJECT 2018 Conistone Keld/Well/Troughs Project Location Conistone Keld is the local name for an area where a spring feeds into three troughs.(the name derives from the Viking word Kelda

More information

4.6. Low Impact and Retentive Grading

4.6. Low Impact and Retentive Grading 4.6. Low Impact and Retentive Grading Low Impact Grading techniques focus on utilizing existing topography during Site layout to minimize cost. Proposing structures, roads, and other impervious surfaces

More information

DIVISION 40 PUMP STATION SITE WORK AND LANDSCAPING

DIVISION 40 PUMP STATION SITE WORK AND LANDSCAPING DIVISION 40 PUMP STATION SITE WORK AND LANDSCAPING 40.01 SCOPE: The contractor shall furnish all labor, materials, equipment, and supplies; and shall perform all work necessary for the installation of

More information

Soil Reclamation and Site Reinstatement

Soil Reclamation and Site Reinstatement APPENDIX 6 Soil Reclamation and Site Reinstatement Purpose To undertake soil reclamation, erosion protection, Site restoration and reinstatement, taking into account natural processes, operational requirements

More information

Gryme s Dyke, Stanway Green

Gryme s Dyke, Stanway Green Gryme s Dyke, Stanway Green A short assessment of the archaeological impact of contractor s groundworks at the southern end of the Gryme s Dyke Middle earthwork February 2000 Archive report on behalf of

More information

Illinois Urban Manual

Illinois Urban Manual Illinois Urban Manual Jim Nelson: Association of Illinois Soil and Water Conservation Districts (AISWCD) Funding for this project provided, in part, by the Grand Victoria Foundation of Elgin IL, the Governor

More information

Homeowners Guide to Stormwater BMP Maintenance

Homeowners Guide to Stormwater BMP Maintenance Homeowners Guide to Stormwater BMP Maintenance What You Need to Know to Take Care of Your Property Rain Barrel Dry Well Rain Garden Pervious Asphalt Porous Pavers City of El Monte Stormwater BMP Management

More information

SOIL EROSION AND SEDIMENT CONTROL

SOIL EROSION AND SEDIMENT CONTROL SOIL EROSION AND SEDIMENT CONTROL SECTION 1: AUTHORITY, TITLE AND PURPOSE 11. STATUTORY AUTHORIZATION This ordinance is adopted pursuant to the provisions of the Federal Water Pollution Control Act 86

More information

Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM

Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM I. PROJECT DATA Project Name Bay Meadows Development Phase II Project Address 2600

More information

RAIN GARDEN ILLINOIS URBAN MANUAL PRACTICE STANDARD. (feet) CODE 897 DEFINITION

RAIN GARDEN ILLINOIS URBAN MANUAL PRACTICE STANDARD. (feet) CODE 897 DEFINITION ILLINOIS URBAN MANUAL PRACTICE STANDARD RAIN GARDEN (feet) CODE 897 Source: Kendall County Soil and Water Conservation District DEFINITION Rain gardens are small, shallow, flat bottomed depressions constructed

More information

Homeowners Guide to Stormwater BMP Maintenance

Homeowners Guide to Stormwater BMP Maintenance Homeowners Guide to Stormwater BMP Maintenance What You Need to Know to Take Care of Your Property Rain Barrel Dry Well Rain Garden Pervious Pavers Pervious Asphalt About Stormwater Management SW Regulations

More information

POND Construction. Perry L. Oakes, PE State Conservation Engineer Natural Resources Conservation Service

POND Construction. Perry L. Oakes, PE State Conservation Engineer Natural Resources Conservation Service POND Construction Perry L. Oakes, PE State Conservation Engineer Natural Resources Conservation Service DdY Did You Know? Alabama is the only state without any safe dams legislation. Alabama has a very

More information

Lesson 2: Stormwater Best Management Practices (BMPs)

Lesson 2: Stormwater Best Management Practices (BMPs) Lesson 2: Stormwater Best Management Practices (BMPs) Environmental Stewards Class Christopher C. Obropta, Ph.D., P.E. Extension Specialist in Water Resources 732-932-9800 ext. 6209 obropta@envsci.rutgers.edu

More information

ENVIRONMENTAL ENGINEERING LAND SURVEYING

ENVIRONMENTAL ENGINEERING LAND SURVEYING ENVIRONMENTAL ENGINEERING LAND SURVEYING Closure Plan Scrubber Solids Pond No. 3 Sherburne County Generating Plant Introduction This plan describes the closure requirements for Scrubber Solids Pond No.

More information

ARROW BOWEN PIPELINE ENVIRONMENTAL MANAGEMENT PLAN OUTLINE SOIL MANAGEMENT PLAN

ARROW BOWEN PIPELINE ENVIRONMENTAL MANAGEMENT PLAN OUTLINE SOIL MANAGEMENT PLAN APPENDIX J ARROW BOWEN PIPELINE ENVIRONMENTAL MANAGEMENT PLAN OUTLINE SOIL MANAGEMENT PLAN Contents 1 Introduction... 1 1.1 Purpose of the Soil Management Plan... 1 1.2 Project description... 1 1.3 Legislation

More information

SECTION SEEDING

SECTION SEEDING SECTION 32 92 19 SEEDING PART 1 GENERAL 1.01 DESCRIPTION A. The WORK under this section consists of the revegetation with seeded grasses. CONTRACTOR shall furnish all labor, materials, equipment, tools,

More information

2018 Annual Landfill Inspection Report

2018 Annual Landfill Inspection Report 2018 Annual Landfill Inspection Report Landfill H.W. Pirkey Plant Southwestern Electric Power Company Hallsville, Texas December 17, 2018 Prepared for: Southwestern Electric Power Company H.W. Pirkey Plant

More information

WQ-07 INFILTRATION TRENCH

WQ-07 INFILTRATION TRENCH Greenville County Technical Specification for: WQ-07 INFILTRATION TRENCH 1.0 Infiltration Trench 1.1 Description Infiltration Trenches are excavations filled with stone to create an underground reservoir

More information

SECTION 6. Routine Maintenance Activity Details

SECTION 6. Routine Maintenance Activity Details SECTION 6 Routine Maintenance Activity Details 80. DEBRIS REMOVAL When Deadfall, and other objects, such as shopping carts, tires, appliances, and mattresses have accumulated in the drain. Why To prevent

More information

RECOMMENDED BEST MANAGEMENT PRACTICES FOR RESTORATION OF WETLANDS AFTER TEMPORARY IMPACTS

RECOMMENDED BEST MANAGEMENT PRACTICES FOR RESTORATION OF WETLANDS AFTER TEMPORARY IMPACTS RECOMMENDED BEST MANAGEMENT PRACTICES FOR RESTORATION OF WETLANDS AFTER TEMPORARY IMPACTS Prepared in partial fulfillment of a U.S. Environmental Protection Agency State Wetland Program Development Grant

More information

Breakthrough Innovations

Breakthrough Innovations Breakthrough Innovations Project Title: Bioengineering for Stabilization of Critical Slopes Project Team: Lori Belz Principle Investigator John Benson Steve Kortuem Leo Holm Introduction: One of the problems

More information

Archaeological evaluation at Willowdene, Chelmsford Road, Felsted, Essex

Archaeological evaluation at Willowdene, Chelmsford Road, Felsted, Essex Archaeological evaluation at Willowdene, Chelmsford Road, Felsted, Essex August 2013 report prepared by Ben Holloway on behalf of Mr Anthony McGurren Planning reference: UTT/13/0235 CAT project ref.: 13/07g

More information

Erosion Control for Home Builders in the. City of Jacksonville

Erosion Control for Home Builders in the. City of Jacksonville Erosion Control for Home Builders in the City of Jacksonville Eroding construction sites are a leading cause of water quality problems in Jacksonville. For every acre under construction, about a dump truck

More information

Guidance on Preparation of Construction and Maintenance Costs

Guidance on Preparation of Construction and Maintenance Costs INVER GROVE HEIGHTS Northwest Area Appendix F Guidance on Preparation of Construction and Maintenance Costs Northwest Area (NWA) Inver Grove Heights Stormwater Manual Guidance on Preparation of Construction

More information

ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville. Environmental Screening Report

ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville. Environmental Screening Report Page 1 of 18 ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville Environmental Screening Report July 2011 Page 2 of 18 Table of Contents 1.0 INTRODUCTION

More information

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion Topics Erosion, TESC and Construction sequencing Procedures and timing Remedies for failing sites Curtis Hinman WSU Extension and Bio Systems Eng. Faculty Low Impact Development Specialist chinman@wsu.edu

More information

SECTION LANDSCAPE MAINTENANCE FOR 90 DAYS. A. Section includes requirements for 90 day landscape maintenance for the following:

SECTION LANDSCAPE MAINTENANCE FOR 90 DAYS. A. Section includes requirements for 90 day landscape maintenance for the following: SECTION 320190.13 LANDSCAPE MAINTENANCE FOR 90 DAYS PART 1 - GENERAL 1.1 SUMMARY A. Section includes requirements for 90 day landscape maintenance for the following: 1. Watering trees and grass. 2. Monitoring

More information

SECTION PLANTING SOIL for SOIL CELLS. This specification defines material and performance requirements for soils which are to be used

SECTION PLANTING SOIL for SOIL CELLS. This specification defines material and performance requirements for soils which are to be used This specification defines material and performance requirements for soils which are to be used within the Silva Cell system. The SPECIFICATION EDITOR must select the type of soil appropriate to each particular

More information

City of Stoughton Erosion Control Permit Application (effective 2/6/2018)

City of Stoughton Erosion Control Permit Application (effective 2/6/2018) City of Stoughton Erosion Control Permit Application (effective 2/6/2018) Incomplete applications will not be accepted Project Name: Address of subject property: Landowner Name(s): Applicant Name: Landowner

More information

SECTION EARTHWORK

SECTION EARTHWORK SECTION 02200 - EARTHWORK PART 1 GENERAL 1.1 SECTION INCLUDES A. Grading and Excavation B. Trenching C. Bedding D. Backfill and Compaction (New and Native) E. Aggregate Material F. Geotextile Fabric PART

More information

2012 FINAL SOILS AREA 2 Envirothon Questions Answer KEY

2012 FINAL SOILS AREA 2 Envirothon Questions Answer KEY 2012 FINAL SOILS AREA 2 Envirothon Questions Answer KEY Questions 1-6 to be answered at the soil pit: 1. Soil scientists categorize soils by drainage classes. What is the drainage class of the soil at

More information

Advanced Foundation Engineering. Soil Exploration

Advanced Foundation Engineering. Soil Exploration Shahrood University of Technology Department of Geotechnical Engineering Advanced Foundation Engineering Soil Exploration Mohsen Keramati, Ph.D. Assistant Professor 1 - Introduction The field and laboratory

More information

2016 Annual Inspection Report

2016 Annual Inspection Report 2016 Annual Inspection Report for Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Hayden Station 13125 U.S. Highway 40 Hayden, Colorado 81638 January 18, 2017 Table of Contents Certification...

More information

OPERATION & MAINTENANCE

OPERATION & MAINTENANCE OPERATION & MAINTENANCE Bio Clean Environmental Services, Inc. www.biocleanenvironmental.com 2972 San Luis Rey Road P 760-433-7640 Oceanside, CA 92054 F 760-433-3176 OPERATION & MAINTENANCE Maintenance

More information

OPERATION & MAINTENANCE

OPERATION & MAINTENANCE Curb Inlet Filter OPERATION & MAINTENANCE Bio Clean Environmental Services, Inc. 398 Via El Centro Oceanside, CA 92058 www.biocleanenvironmental.com p: 760.433.7640 f: 760.433.3176 OPERATION & MAINTENANCE

More information

SECTION SOIL PREPARATION

SECTION SOIL PREPARATION SECTION 329113 SOIL PREPARATION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Components of planting mediums. 2. Testing and certification of components. 3. Mixing of planting mediums. 4. Transporting

More information

VILLAGE OF MOUNT PROSPECT 2016 STREET RESURFACING PROGRAM Frequently Asked Questions (FAQ s)

VILLAGE OF MOUNT PROSPECT 2016 STREET RESURFACING PROGRAM Frequently Asked Questions (FAQ s) VILLAGE OF MOUNT PROSPECT 2016 STREET RESURFACING PROGRAM Frequently Asked Questions (FAQ s) How will I be notified that major street repairs will occur on my block? Why can t you tell me the exact date

More information

Public Works Department 104 W. Magnolia Street, Suite 109 Bellingham, WA (360)

Public Works Department 104 W. Magnolia Street, Suite 109 Bellingham, WA (360) Public Works Department 104 W. Magnolia Street, Suite 109 Bellingham, WA 98225 (360) 778-7900 STORMWATER PERMIT SUBMITTAL REQUIREMENTS Most development within the City of Bellingham that involves disruption

More information

Eric Konzelmann, CPESC, CPSWQ Assistant District Manager. Montgomery County Conservation District

Eric Konzelmann, CPESC, CPSWQ Assistant District Manager. Montgomery County Conservation District Eric Konzelmann, CPESC, CPSWQ Assistant District Manager Montgomery County Conservation District Topics Covered E&S Conveyance & Inlet Protection Soil Stabilization Requirements & Effectiveness Soil Compaction

More information

CropHealth Advising & Research Kelowna, B.C.

CropHealth Advising & Research Kelowna, B.C. To CropHealth Advising & Research Kelowna, B.C. www.crophealth.com Date Thursday April 23, 2009 5 pages from Mario Lanthier The Up By Roots regional workshop was held on April 14 in Oregon City, near Portland.

More information

Soil Restoration in Accordance with. The NYSDEC 2015 Stormwater Management Design Manual

Soil Restoration in Accordance with. The NYSDEC 2015 Stormwater Management Design Manual Soil Restoration in Accordance with The NYSDEC 2015 Stormwater Management Design Manual William Buetow CPESC, CPSS TRC Solutions Clifton Park, NY Implementation of Soil Restoration as a Green Infrastructure

More information

SECTION SOIL BIOENGINEERING OR SHORELINE STABILIZATION

SECTION SOIL BIOENGINEERING OR SHORELINE STABILIZATION SECTION 32 93 43 SOIL BIOENGINEERING OR SHORELINE STABILIZATION PART 1 GENERAL 1.01 SECTION INCLUDES A. CONTRACTOR shall furnish all labor, materials, supplies, equipment, tools and transportation; perform

More information

ACTIVITY: Tree Preservation & Maintenance TP 01

ACTIVITY: Tree Preservation & Maintenance TP 01 ACTIVITY: Tree Preservation & Maintenance TP 01 Targeted Constituents Significant Benefit Partial Benefit Low or Unknown Benefit Sediment Heavy Metals Floatable Materials Oxygen Demanding Substances Nutrients

More information

General Information. Site Conditions. 9b 9b. 9a 1b. Best Management Practices Illustration

General Information. Site Conditions. 9b 9b. 9a 1b. Best Management Practices Illustration Model Construction SWPPP Planning & Development Services 1800 Continental Place Mount Vernon WA 98273 voice 360-416-1320 inspections 360-416-1330 www.skagitcounty.net/stormwaterpermitting Permit #: General

More information

I N D U S T R I A L Y A R D S

I N D U S T R I A L Y A R D S I N D U S T R I A L Y A R D S GEOTEXTILES INDUSTRIAL YARDS 1.0 Features of INDUSTRIAL PG 2 YARDS 2.0 How Typar geotextiles PG 2 work 4.0 Installation guide PG 7 5.0 Overlap and joining PG 8 6.0 Setting

More information

Erosion & Sediment Control Plan Application Form & Checklist

Erosion & Sediment Control Plan Application Form & Checklist Erosion & Sediment Control Plan Application Form & Checklist GENERAL INFORMATION Application Date: Project Address: Tax Map / Parcel Number(s): PROPERTY OWNER / DEVELOPER Firm Name: Contact Person: Title:

More information

STANDARD SPECIFICATIONS SECTION TEMPORARY EROSION AND SEDIMENT CONTROL

STANDARD SPECIFICATIONS SECTION TEMPORARY EROSION AND SEDIMENT CONTROL STANDARD SPECIFICATIONS SECTION 01570 TEMPORARY EROSION AND SEDIMENT CONTROL PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements, procedures, and methods related to responsibilities for providing

More information

Construction Management & Engineering Division. Understanding Swales

Construction Management & Engineering Division. Understanding Swales Construction Management & Engineering Division Understanding Swales The Florida hydrological cycle it all starts and ends here. Rainfall becomes stormwater when it can no longer soak into the ground and

More information

Inspection and Maintenance of Stormwater Best Management Practices

Inspection and Maintenance of Stormwater Best Management Practices FAC T S H E E T Inspection and Maintenance of Stormwater Best Management Practices is a general term that refers to vegetated stormwater best management practices (BMPs) that temporarily store rainwater

More information

Triangle Land Conservancy Conservation Area Monitoring Report Carolina North

Triangle Land Conservancy Conservation Area Monitoring Report Carolina North Triangle Land Conservancy Conservation Area Monitoring Report Carolina North Property Name: Bolin Creek West Conservation Area Date of visit: April 11, 2018 County: Orange Property Type: Restrictive Covenants

More information

Installation Manual May 9/14 No revision

Installation Manual May 9/14 No revision 815 NE 172 nd Avenue Vancouver, WA 98684 877-694-0141 Installation Manual May 9/14 No revision Installation steps include job planning, layout, excavating and preparing the soil subgrade, applying geotextiles

More information

River Mile 10.9 Removal Action Overview

River Mile 10.9 Removal Action Overview River Mile 10.9 Removal Action Overview November 13, 2014 CAG Meeting Modified from CPG s RM10.9 Removal Action Final Design Report dated Nov. 2013 1 River Mile 10.9 Removal Action Activities Dredging:

More information

APPENDIX G-3 Agricultural Impact Mitigation Plan Ohio

APPENDIX G-3 Agricultural Impact Mitigation Plan Ohio APPENDIX G-3 Agricultural Impact Mitigation Plan Ohio G3-1 Appendix G-3 Appendix G-3 G3-2 ROVER PIPELINE LLC Rover Pipeline Project AGRICULTURAL IMPACT MITIGATION PLAN OHIO April 2015 G3-3 Appendix G-3

More information

Tour of Nonpoint Source Pollution Reduction Projects in the Western Lake Superior Watershed

Tour of Nonpoint Source Pollution Reduction Projects in the Western Lake Superior Watershed Tour of Nonpoint Source Pollution Reduction Projects in the Western Lake Superior Watershed On September 8 th, 2006 Minnesota's Lake Superior Coastal Program and the South St Louis Soil and Water Conservation

More information

A. INTRODUCTION AND SUMMARY OF FINDINGS B. EXISTING CONDITIONS. Table 10-1 Adjacent Storm Drains

A. INTRODUCTION AND SUMMARY OF FINDINGS B. EXISTING CONDITIONS. Table 10-1 Adjacent Storm Drains Chapter 10: Stormwater Management A. INTRODUCTION AND SUMMARY OF FINDINGS This chapter describes existing and proposed stormwater management on the Site. Potential impacts to stormwater infrastructure

More information

Mosquito Control Guidelines

Mosquito Control Guidelines Appendix F Mosquito Control Guidelines This appendix presents guidance from the Countywide Program s Vector Control Plan for designing and maintaining stormwater treatment measures to control mosquitoes.

More information

SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL

SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL Standard Operating Procedures Central Massachusetts Regional Stormwater Coalition SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL Erosion and sedimentation from land-disturbing

More information

TECH. BULLETIN ISSUE TWENTY

TECH. BULLETIN ISSUE TWENTY 1.0 Scope The scope of this Guideline is to: Define construction techniques associated with cold weather installation of the backfill zone; and, Identify measures that have been used successfully to allow

More information

Protect Stormwater Quality Project and Site Management Training for General Contractors. Presenter Becky Pearson Professional Civil Engineer

Protect Stormwater Quality Project and Site Management Training for General Contractors. Presenter Becky Pearson Professional Civil Engineer Protect Stormwater Quality Project and Site Management Training for General Contractors Presenter Becky Pearson Professional Civil Engineer Part II Best Management Practices (BMPs) What is a Best Management

More information

Feet. Overland. Drainage Area Boundary. To Swale. Swale. To Catch Basin. Culvert Pipe. To Drain Outfall. NRCS Soil Area Boundary

Feet. Overland. Drainage Area Boundary. To Swale. Swale. To Catch Basin. Culvert Pipe. To Drain Outfall. NRCS Soil Area Boundary 0 25 50 00 Feet Parcel Boundary, Approximate 202 LIDAR 2 FT CONTOURS, VCGI BING AERIAL NRCS SOIL MAPPING MMI FIELD DATA Culvert Pipe Swale 0 Scale: "=40' SOURCE(S): NRCS Soil Area Boundary Overland st

More information

Kittson Parkway / Watershed Park Parking Lot

Kittson Parkway / Watershed Park Parking Lot Kittson Parkway / Watershed Park Parking Lot Date Constructed: Summer 2005 Site Location / Description: Kittson Parkway, North Delta, British Columbia. Permeable parking lot adjacent to Watershed Park;

More information