TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 No Projects US-19E Under Development in Carter County

Size: px
Start display at page:

Download "TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 No Projects US-19E Under Development in Carter County"

Transcription

1 CARTER COUNTY SR-37 No Projects US-19E Under Development in Carter County PIN: AT LM 8.7 (ROCKFALL MITIGATION) Length (Mitigation - Rockfall) CARTER COUNTY SR-91EXT PIN: FROM SR-67 (US-321) TO SR-37 (US-19E) (IA) Length (Construction-New) CARTER COUNTY PIN: (ELK AVENUE), BRIDGE OVER DOE RIVER Length (Bridge Rehabilitation) The engineering is scheduled to begin in the 1st Quarter Calendar Year CARTER COUNTY PIN: GAP CREEK ROAD, BRIDGE OVER GAP CREEK, LM 2.73 (IA) The engineering is scheduled to begin in the 1st Quarter Calendar Year Page: 1

2 CARTER COUNTY SR-67 No Projects Under Construction in Carter County INTERSECTIONS AT SR-359 (MILLIGAN HIGHWAY) AND WEST MILL STREET/MCARTHUR AVENUE IN ELIZABETHTON (SIGNALIZATION) CONTRACT NO.: CNR249 LET TO CONTRACT: 8/18/2017 STANSELL ELECTRIC COMPANY, INC. BID PRICE : $342, EST. COMPLETION DATE: MAY, 2018 Page: 2

3 GREENE COUNTY I-81 No Projects Under Development in Greene County PIN: GREEN COUNTY REST AREA RENOVATION (IA) Length (Weigh Station or Rest Area Improvements) GREENE COUNTY SR-34 US-11E PIN: (GREENEVILLE BYPASS); FROM US-11E, WEST OF GREENEVILLE TO US-11E, EAST OF GREENEVILLE (EPD) (IA) Length (Environmental Studies) GREENE COUNTY SR-34 PIN: FROM WEST OF NORTH SPRING STREET TO EAST OF DULANEY ROAD/RAILROAD STREET Length (Intersection Improvements) GREENE COUNTY SR-34 PIN: FROM SOUTH OF TUSCULUM HEIGHTS DRIVE TO SOUTH OF BALL ROAD Length (Intersection Improvements and Signals) GREENE COUNTY SR-35 US-321 PIN: FROM NORTH OF COCKE COUNTY LINE TO NORTH OF NOLICHUCKY RIVER(BRIGHT HOPE ROAD) (EPD) (IA) Length (Reconstruction) The right-of-way and/or utility process is underway. GREENE COUNTY SR-35 US-321 PIN: (NEWPORT HIGHWAY) BRIDGE OVER NOLICHUCKY RIVER, LM 3.07 (IA) GREENE COUNTY SR-35 US-321 PIN: FROM NORTH OF NOLICHUCKY RIVER NEAR BRIGHT HOPE ROAD TO MILES SOUTH OF SR-349 (WARRENSBURG ROAD) NEAR PATE LANE (EPD) (IA) Length (Construction-New) The engineering is scheduled to begin in the 1st Quarter Calendar Year Page: 3

4 GREENE COUNTY SR-35 US-321 PIN: FROM SR-349 (WARRENSBURG ROAD) NEAR PATES LANE TO SR-34 (US-11E) (EPD) (IA) Length (Construction-New) HAMBLEN - HAWKINS - GREENE COUNTIES SR-34 US-11E PIN: (ANDREW JOHNSON HWY.) FROM STEADMAN RD. TO I-81 (IA) Length (Widen) Page: 4

5 No Projects Under Construction in Greene County Page: 5

6 HANCOCK - HAWKINS No COUNTIES Projects Under SR-31 Development in Hancock County PIN: FROM SPRUCE PINE ROAD IN HAWKINS CO. TO SR-131 IN HANCOCK CO.(RSAR) Length (Miscellaneous Safety Improvements) The planning report is complete. HANCOCK COUNTY SR-33 PIN: (MAIN STREET), BRIDGE OVER GREASY ROCK CREEK, LM (IA) The engineering is scheduled to begin in the 2nd Quarter Calendar Year Page: 6

7 No Projects Under Construction in Hancock County Page: 7

8 HAMBLEN - HAWKINS - No GREENE Projects COUNTY Under Development SR-34 US-11E in Hawkins County PIN: (ANDREW JOHNSON HWY.) FROM STEADMAN RD. TO I-81 (IA) Length (Widen) HANCOCK - SR-31 PIN: FROM SPRUCE PINE ROAD IN HAWKINS CO. TO SR-131 IN HANCOCK CO.(RSAR) Length (Miscellaneous Safety Improvements) The planning report is complete. SR-1 PIN: INTERSECTIONS AT BELMONT AVENUE AND ENGLEWOOD AVENUE IN MT. CARMEL Length (Intersection Improvements and Signals) SR-1 US-11W PIN: (W. STONE DR.), BRIDGE OVER NORTH FORK HOLSTON RIVER LM (LL) (IA) SR-1 US-11W PIN: (W. STONE DR.), BRIDGE OVER NORTH FORK HOLSTON RIVER LM (RL) (IA) SR-31 PIN: FROM MOORESBURG TO ADAMS LANE (EPD) (IA) Length (Reconstruction) SR-31 PIN: BRIDGE OVER POOR VALLEY CREEK, LM 4.17 (IA) The engineering is scheduled to begin in the 1st Quarter Calendar Year Page: 8

9 SR-66 PIN: FROM SR-34 IN BULLS GAP TO SOUTH OF SPEEDWELL RD/OLD HWY 66 (IA) Length (Reconstruction) SR-66 PIN: FROM NEAR FOREST HILLS ROAD TO NEAR RAMP AT WEST MAIN STREET (RSAR) Length (Miscellaneous Safety Improvements) The environmental studies are complete. PIN: OKALONA ROAD, INTERSECTION AT CARTER'S VALLEY ROAD (RSAR) Length (Miscellaneous Safety Improvements) The environmental studies are complete. PIN: HAMMOND AVENUE, FROM WEST MAIN STREET TO LOYDS CHAPEL ROAD IN MT. CARMEL Length (Miscellaneous Safety Improvements) The environmental studies are complete. SR-70 PIN: BRIDGE OVER NORFOLK SOUTHERN RAILROAD, LM 6.19 (IA) The engineering is scheduled to begin in the 1st Quarter Calendar Year SR-70 PIN: BRIDGE OVER CANEY CREEK (IA) SR-346 PIN: (E. MAIN ST.), BRIDGE OVER SURGOINSVILLE CREEK (IA) Page: 9

10 PIN: INDEPENDENCE AVENUE, NORTH OF EAST ELLIS LANE TO SR-1 IN MOUNT CARMEL Length (RSAR) The planning document is underway. PIN: S. ARMSTRONG ROAD, BRIDGE OVER CROCKETT CREEK, LM 0.27 (IA) The planning report is complete. Page: 10

11 No SR-70 Projects Under Construction in Hawkins County EMERGENCY SLIDE REPAIRS AT LM 16.2 (MITIGATION - SLIDE) CONTRACT NO.: CNR344 LET TO CONTRACT: 12/8/2017 SUMMERS-TAYLOR, INC. BID PRICE : $482, EST. COMPLETION DATE: JUNE, 2018 Page: 11

12 JOHNSON COUNTY SR-67 No Projects Under Development in Johnson County PIN: INTERSECTION AT PEDRO SHOUN LANE/SPRUCEY LANE Length (Turn Lanes) A contract for construction is scheduled to be let in the 1st Quarter Calendar Year JOHNSON COUNTY SR-91 PIN: FROM NEAR COLD SPRINGS ROAD TO THE VIRGINIA STATE LINE (IA) Length (Widen) JOHNSON COUNTY SR-167 PIN: FROM LITTLE DRY RUN ROAD TO BIG DRY RUN ROAD (RSA) Length (Miscellaneous Safety Improvements) The environmental studies are complete. SULLIVAN - JOHNSON COUNTIES SR-34 US-421 PIN: FROM SR-435 TO MOUNTAIN CITY CITY LIMITS (RSAR) Length (Miscellaneous Safety Improvements) The environmental studies are complete. Page: 12

13 JOHNSON COUNTY No Projects Under Construction in Johnson County FAIRGROUND LANE, BRIDGE OVER FURNACE CREEK IN MOUNTAIN CITY, LM 0.02 (BRIDGE REPLACEMENT) LENGTH CONTRACT NO.: CNR228 LET TO CONTRACT: 8/18/2017 ADAMS CONTRACTING, LLC BID PRICE : $723, EST. COMPLETION DATE: APRIL, 2018 JOHNSON COUNTY CIRCLE DRIVE, BRIDGE OVER FURNACE CREEK IN MOUNTAIN CITY, LM 0.84 (BRIDGE REPLACEMENT) LENGTH CONTRACT NO.: CNR228 LET TO CONTRACT: 8/18/2017 ADAMS CONTRACTING, LLC BID PRICE : $616, EST. COMPLETION DATE: APRIL, 2018 JOHNSON COUNTY FORGE ROAD, BRIDGE OVER FORGE CREEK, LM 1.86 (BRIDGE REPLACEMENT) LENGTH CONTRACT NO.: CNR940 LET TO CONTRACT: 6/23/2017 ADAMS CONTRACTING, LLC BID PRICE : $596, EST. COMPLETION DATE: MARCH, 2018 Page: 13

14 I-81 No Projects Under Development in Sullivan County PIN: ITS EXPANSION ALONG I-81 BETWEEN I-26 (EXIT 57) INTERCHANGE AND VIRGINIA STATE LINE (IA) Length (Intelligent Transportation System) SR-1 PIN: AT ANDREW JACKSON ELEMENTARY SCHOOL Length (Signalization) The right-of-way and/or utility process is underway. SR-34 PIN: FROM NORTH OF SR-37 TO NORTH OF RIVER ROAD Length (Miscellaneous Safety Improvements) SULLIVAN - JOHNSON COUNTIES SR-34 US-421 PIN: FROM SR-435 TO MOUNTAIN CITY CITY LIMITS (RSAR) Length (Miscellaneous Safety Improvements) The environmental studies are complete. SR-36 PIN: INTERSECTION AT MORELAND DRIVE / HEMLOCK ROAD IN KINGSPORT, LM 4.31 Length (Intersection Improvements and Signals) A contract for construction is scheduled to be let in the 1st Quarter Calendar Year SR-36 PIN: FROM LINE TO NORTH OF LAKESIDE LANE Length (Miscellaneous Safety Improvements) A contract for construction is scheduled to be let in the 2nd Quarter Calendar Year SR-36 PIN: FROM WESLEY ROAD TO NORTHBOUND SR-93 RAMP (RSA) Length (Miscellaneous Safety Improvements) A contract for construction is scheduled to be let in the 2nd Quarter Calendar Year Page: 14

15 SR-36 PIN: FROM TRANBARGER DRIVE TO NEAR ADAMS AVENUE (RSA) Length (Miscellaneous Safety Improvements) A contract for construction is scheduled to be let in the 2nd Quarter Calendar Year SR-36 PIN: AT JOHN F. KENNEDY ELEMENTARY SCHOOL Length (Signalization) The right-of-way and/or utility process is underway. SR-36 PIN: INTERSECTION AT SR-126(MEMORIAL BLVD) AND SHERWOOD ROAD Length (Turn Lanes with Signal) SR-36 PIN: FT. HENRY DR. BRIDGE OVER SOUTH HOLSTON RIVER LM 5.02 (RL) (IA) SR-36 PIN: FT. HENRY DR. BRIDGE OVER SOUTH HOLSTON RIVER LM 5.03 (LL) (IA) SR-44 PIN: DRY BRANCH RD. BRIDGE OVER BRANCH (IA) SR-75 PIN: FROM NORTH OF SR-357 DRIVE TO NORTH OF CENTENARY ROAD (RSAR) Length (Intersection Improvements and Signals) Page: 15

16 SR-93 PIN: JOHN B. DENNIS HWY. BRIDGE OVER CSX RAILROAD (IA) SULLIVAN - WASHINGTON COUNTIES SR-93 PIN: FROM MORGAN LANE TO SOUTH OF BAILEYTON ROAD IN SULLIVAN CO (TPR OPTION 5, SPOT IMPROVMENT 3) (IA) Length (Miscellaneous Improvements) The right-of-way and/or utility process is underway. SR-93 PIN: FROM SOUTH OF HORSE CREEK TO NORTH OF DERBY DRIVE (TPR OPTION 5, SPOT IMPROVMENT 4 & 5) (IA) Length (Reconstruction) The right-of-way and/or utility process is underway. SR-93 PIN: AT SULLIVAN NORTH HIGH SCHOOL Length (Signalization) The right-of-way and/or utility process is underway. SR-126 PIN: EAST CENTER STREET IN KINGSPORT TO I-81 Length (Environmental Studies) The environmental studies are complete. SR-126 PIN: FROM EAST CENTER STREET IN KINGSPORT TO EAST OF COOKS VALLEY ROAD (IA) Length (Widen) SR-126 PIN: (MEMORIAL BLVD.), FROM EAST OF COOKS VALLEY ROAD TO I-81 IN KINGSPORT (IA) Length (Widen) The engineering is scheduled to begin in the 1st Quarter Calendar Year Page: 16

17 SR-347 PIN: (ROCK SPRINGS ROAD) FROM COX HOLLOW RD (LM 9.52) TO I-26 (US-23) (LM 10.73) Length (Widen) SR-355 PIN: INDUSTRY DR. BRIDGE OVER REEDY CREEK (IA) SR-357 PIN: FROM HOSPITALITY PLACE/FLAGSHIP DRIVE TO I-81 NB RAMPS Length (Intersection Improvements and Signals) A contract for construction is scheduled to be let in the 1st Quarter Calendar Year PIN: FORT ROBINSON DRIVE, BRIDGE OVER DRY HOLLOW, LM 0.39 IN KINGSPORT (IA) SIA PIN: INDUSTRIAL ACCESS ROAD SERVING RECLAIMED RESOURCES, INC Length (Construction-New) The right-of-way and/or utility process is underway. SR-PROP PIN: FROM US 11E (SR 34) NEAR BRISTOL MOTOR SPEEDWAY TO US 11W(SR 1) NEAR PINNACLE PARKWAY (IA) (Construction-New) The engineering is scheduled to begin in the 1st Quarter Calendar Year WASHINGTON - SULLIVAN COUNTIES SR-36 PIN: (FORT HENRY DR.) FROM SR-75 TO I-81 (IA) Length (Widen) Page: 17

18 WASHINGTON - SULLIVAN COUNTIES SR-93 PIN: FROM I-81 TO SR-347(LONE STAR ROAD) (TPR OPTION 5, SPOT IMPROVMENT) Length (Preliminary Engineering) Page: 18

19 No SR-34 Projects Under Construction in Sullivan County INTERSECTION AT COX STREET (L.M ) RSAR (MISCELLANEOUS SAFETY IMPROVEMENTS) CONTRACT NO.: CNR337 LET TO CONTRACT: 12/8/2017 SUMMERS-TAYLOR, INC. BID PRICE : $747, EST. COMPLETION DATE: JUNE, 2018 SIA INDUSTRIAL ACCESS SERVING BRISTOL METALS 2015 (CONSTRUCTION-NEW) LENGTH CONTRACT NO.: CNR251 LET TO CONTRACT: 10/6/2017 BAKER'S CONSTRUCTION SERVICES, INC. BID PRICE : $702, EST. COMPLETION DATE: MAY, 2018 I-81 EASTBOUND TRUCK CLIMBING LANE AT MILE MARKER 60 (WIDEN) LENGTH CONTRACT NO.: CNQ304 LET TO CONTRACT: 10/7/2016 SUMMERS-TAYLOR, INC. BID PRICE : $8,369, EST. COMPLETION DATE: OCTOBER, 2018 Page: 19

20 UNICOI COUNTY SR-107 No Projects Under Development in Unicoi County PIN: (UNICOI DRIVE), BRIDGE OVER INDIAN CREEK, LM 5.37 IN ERWIN. (IA) The engineering is scheduled to begin in the 1st Quarter Calendar Year UNICOI COUNTY PIN: ROCKY FORK STATE PARK ACCESS ROAD (Construction-New) Page: 20

21 UNICOI - WASHINGTON No COUNTIES Projects Under SR-81 Construction in Unicoi County FROM EAST WALNUT STREET TO ARNOLD ROAD IN (RSAR) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH CONTRACT NO.: CNR194 LET TO CONTRACT: 5/12/2017 BALDWIN PAVING CO., INC. BID PRICE : $446, EST. COMPLETION DATE: OCTOBER, 2017 UNICOI COUNTY SR-36 US-19W FROM NORTH CAROLINA STATE LINE TO I-26 INTERCHANGE (RSAR) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH CONTRACT NO.: CNR194 LET TO CONTRACT: 5/12/2017 BALDWIN PAVING CO., INC. BID PRICE : $205, EST. COMPLETION DATE: OCTOBER, 2017 Page: 21

22 No Projects SR-36 Under Development in Washington County PIN: FROM NEAR SR-75 TO LINE LM 6.99 TO LM Length (Miscellaneous Safety Improvements) A contract for construction is scheduled to be let in the 2nd Quarter Calendar Year SULLIVAN - SR-93 PIN: FROM MORGAN LANE TO SOUTH OF BAILEYTON ROAD IN SULLIVAN CO (TPR OPTION 5, SPOT IMPROVMENT 3) (IA) Length (Miscellaneous Improvements) The right-of-way and/or utility process is underway. I-26 PIN: INTERCHANGE AT SR-354(EXIT 17) (IA) Length (Modify Interchange) SR-34 US-11E PIN: FROM BIG LIMESTONE ROAD/MCINTURFF ROAD TO LM 2.02 (RSAR) Length (Miscellaneous Safety Improvements) SR-34 PIN: FROM BIG LIMESTONE ROAD TO CULVER ROAD Length (RSAR) SR-34 US-11E PIN: W. MARKET ST. BRIDGE OVER CSX RAILROAD (IA) SR-36 PIN: INTERSECTION AT MOUNTAIN VIEW ROAD, LM 0.77 IN JOHNSON CITY Length (Signalization) A contract for construction is scheduled to be let in the 1st Quarter Calendar Year Page: 22

23 WASHINGTON - SULLIVAN COUNTIES SR-36 PIN: (FORT HENRY DR.) FROM SR-75 TO I-81 (IA) Length (Widen) SR-81 PIN: INTERSECTION AT PERSIMMON RIDGE ROAD, LM IN JONESBOROUGH Length (Intersection Improvements) A contract for construction is scheduled to be let in the 2nd Quarter Calendar Year WASHINGTON - SULLIVAN COUNTIES SR-93 PIN: FROM I-81 TO SR-347(LONE STAR ROAD) (TPR OPTION 5, SPOT IMPROVMENT) Length (Preliminary Engineering) SR-93 PIN: FROM NORTH OF DAVIS ROAD TO NORTH OF FIRE HALL ROAD (TPR OPTION 5, SPOT IMPROVMENT 1 & 2) (IA) Length (Miscellaneous Improvements) The right-of-way and/or utility process is underway. SR-107 PIN: FROM GREENE COUNTY LINE TO SR-81 (RSAR) Length (Miscellaneous Safety Improvements) A contract for construction is scheduled to be let in the 1st Quarter Calendar Year PIN: BOONES STATION ROAD, FROM P. KEEFAUVER ROAD TO KEEFAUVER ROAD IN JOHNSON CITY Length (Safety) A contract for construction is scheduled to be let in the 1st Quarter Calendar Year PIN: KNOB CREEK ROAD, FROM SR-354 (BOONES CREEK ROAD) TO MIZPAH HILLS DRIVE Length (Safety) A contract for construction is scheduled to be let in the 1st Quarter Calendar Year Page: 23

24 SR-353 PIN: (OLD SR-34), BRIDGE OVER LITTLE LIMESTONE CREEK, LM (IA) The engineering is scheduled to begin in the 2nd Quarter Calendar Year SR-354 PIN: INTERSECTION AT BUGABOO SPRINGS RD, LM Length (Intersection Improvements) SR-381 US-321 PIN: INTERSECTION AT HARRIS DRIVE, LM 1.45 IN JOHNSON CITY Length (Signalization) SR-PROP PIN: (KNOB CREEK RD.) FROM SR-354 (BOONES CREEK RD.) TO MIZPAH HILLS DR. (IA) Length (Widen) SIA PIN: INDUSTRIAL ACCESS ROAD SERVING CLINICAL MANAGEMENT CONCEPTS IN JOHNSON CITY Length (Construction-New) A contract for construction is scheduled to be let in the 1st Quarter Calendar Year Page: 24

25 No Projects SR-353 Under Construction in Washington County CULVERT OVER BRANCH, LM 3.23 (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH CONTRACT NO.: CNR323 LET TO CONTRACT: 12/8/2017 SUMMERS-TAYLOR, INC. BID PRICE : $1,187, EST. COMPLETION DATE: JULY, 2018 SR-34 US-11E (EAST JACKSON BOULEVARD), INTERSECTION AT SR-354(BOONES CREEK ROAD), LM IN JONESBOROUGH (INTERSECTION IMPROVEMENTS AND SIGNALS) LENGTH CONTRACT NO.: CNR238 LET TO CONTRACT: 6/23/2017 SUMMERS-TAYLOR, INC. BID PRICE : $2,619, EST. COMPLETION DATE: MAY, 2018 UNICOI - SR-81 FROM EAST WALNUT STREET TO ARNOLD ROAD IN (RSAR) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH CONTRACT NO.: CNR194 LET TO CONTRACT: 5/12/2017 BALDWIN PAVING CO., INC. BID PRICE : $446, EST. COMPLETION DATE: OCTOBER, 2017 I-26 EAST OF SR-91 TO SR-67 INTERCHANGE (EASTBOUND ONLY) (WIDEN) LENGTH CONTRACT NO.: CNQ301 LET TO CONTRACT: 10/7/2016 SUMMERS-TAYLOR, INC. BID PRICE : $3,422, EST. COMPLETION DATE: MAY, 2018 Page: 25

26 SR-34 BRIDGE OVER LIMESTONE CREEK (SBL), LM 1.72 (BRIDGE REPLACEMENT) CONTRACT NO.: CNQ308 LET TO CONTRACT: 10/7/2016 SUMMERS-TAYLOR, INC. BID PRICE : $3,045, EST. COMPLETION DATE: JULY, 2018 Page: 26

TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 US-19E No Projects Under Development in Carter County

TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 US-19E No Projects Under Development in Carter County CARTER COUNTY SR-37 US-19E No Projects Under Development in Carter County PIN: 125256.00 AT LM 8.7 (ROCKFALL MITIGATION) Length - 0.0 (Mitigation - Rockfall) CARTER COUNTY SR-91EXT PIN: 043975.01 FROM

More information

TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. No Projects Under Development in Campbell County

TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. No Projects Under Development in Campbell County I-75 No Projects Under Development in Campbell County PIN: 115778.00 TRUCK CLIMBING LANE, MP 135.5 TO MP 140.1(NBL) Length - 4.6 (Widen) The right-of-way and/or utility process is underway. I-75 PIN: 115778.01

More information

2040 Long Range Transportation Plan

2040 Long Range Transportation Plan 2040 Long Range Transportation Plan Adopted: April 15, 2013 APPENDIX D HIGHWAY NEEDS PLAN PROJECTS FREDERICKSBURG Existing and Committed Projects Fall Hill Avenue/Mary Washington Blvd. (Fredericksburg)

More information

March 1, PWG Meeting #4

March 1, PWG Meeting #4 March 1, 2013 PWG Meeting #4 1 Meeting Agenda 2 History & Overview Circle Interchange was built in the late 1950 s and early 1960 s, and the facility is in need of major repair or reconstruction. 3 History

More information

Welcome. Northern Segment of Hwy 100 I-90 to South of Madison Street Meeting Goals:

Welcome. Northern Segment of Hwy 100 I-90 to South of Madison Street Meeting Goals: Welcome Northern Segment of Hwy 100 I-90 to South of Madison Street Meeting Goals: - Review Environmental Assessment - Share Preferred Alternative -Receive Public Comments 2003 EA Preferred Alternative

More information

BALL CAMP PIKE Phase II From Middlebrook Pike to Andes Road NEW CONSTRUCTION Spring 2007

BALL CAMP PIKE Phase II From Middlebrook Pike to Andes Road NEW CONSTRUCTION Spring 2007 COUNTY LOCAL PROJECTS BALL CAMP PIKE Phase II From Middlebrook Pike to Andes Road NEW ION Spring 00 DRY GAP PIKE From Dante Road to Beaver Creek WIDENING Summer 00 DUTCHTOWN ROAD From Pellissippi Parkway

More information

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects Schooleys Mountain Bridge Rehabilitation Project ID Numbers: N1707 / 173470 Schooleys Mountain Road Bridge was built in 1920 and widened in 1937. The project is a replacement of the bridge structure and

More information

Index to Projects by Project Name

Index to Projects by Project Name Index to Projects by Project Name Project # PROJECT NAME PAGE 2134 2119 PR-1109 Clayton Road (Market Street to Oakland Avenue) Sidewalk Repair 911 System Replacement and Dispatch Room Remodel ADA Barrier

More information

Creative Engineering Group Inc, (Creative) Construction Engineering and Inspection (CEI) Professionals

Creative Engineering Group Inc, (Creative) Construction Engineering and Inspection (CEI) Professionals ABOUT US Creative Engineering Group Inc, (Creative) is a Construction Engineering and Inspection (CEI) firm established in 2006 by two Principals Rick Estripeaut & Sri Mavanur. In the last decade Creative

More information

Municipality of Anchorage. Community Council Survey Capital Projects Needs Ranking Survey (ALPHABETICAL) Airport Heights

Municipality of Anchorage. Community Council Survey Capital Projects Needs Ranking Survey (ALPHABETICAL) Airport Heights ANCHORAGE PARKS & RECREATION Nichols Park Design and improve neighborhood park 2008 Challenge Grant applicant. 2008 $500K State Grant for Neighborhood Parks. Tikishla Park Lighting, paved parking, hockey

More information

Transportation Projects Quarterly Report. Morrisville Planning Department May 22, 2018

Transportation Projects Quarterly Report. Morrisville Planning Department May 22, 2018 Transportation Projects Quarterly Report Morrisville Planning Department May 22, 2018 Transportation Improvements Most Common Ways the Town secures transportation improvements: 1. Development 2. Grant

More information

Thursday, April 13, 2017 Page 1 of 3 7/1/2017. Electricians are installing lights and continue to pull wire. Preliminary Design underway.

Thursday, April 13, 2017 Page 1 of 3 7/1/2017. Electricians are installing lights and continue to pull wire. Preliminary Design underway. Status Updates on Active Projects sorted by Cost $13,733,749.69 Niki Ensor Niki Ensor Raw Water Intake Replacement (1.5 M EDA Grant) $7,500,000.00 Ryan McReynolds Thompson, Michael SR 347 (Rock Springs

More information

2010 Tentative Enhancement Program Allocations (FY11)

2010 Tentative Enhancement Program Allocations (FY11) Bristol 10011 Buchanan County Buchanan County project cost $1,190,332 Bull Creek Trail - construction of a pedestrian/bicycle trail along abandoned request amount $240,323 railroad right of way. allocation

More information

Henderson County Project Prioritization Discussion

Henderson County Project Prioritization Discussion French Broad River MPO Henderson County Project Prioritization Discussion A discussion on projects considered for MPO Local Input Points in the tier for P 5.0 French Broad River MPO 8-8-2018 INTRODUCTION

More information

City of Cedar Rapids Public Works Tentative Bid Schedule Issued December 4, 2017 *Subject to Change*

City of Cedar Rapids Public Works Tentative Bid Schedule Issued December 4, 2017 *Subject to Change* 12/6/2017 3012115-03 Northwood Dr NE, Glass to s/o Brookland $980,000.00 J. 4/16/2018 12/13/2017 3012121-02 O Ave NW, 16th to Ellis $4,065,000.00 Tippe; Lee J. 3/19/2018 Collins Rd NE from E of Northland

More information

YORK COUNTY GOVERNMENT

YORK COUNTY GOVERNMENT YORK COUNTY GOVERNMENT Planning & Development Services MEMORANDUM TO: FROM: RE: DATE: May 9, 2016 York County Council York County Planning Commission Eddie Moore, Development Services Manager PROPOSED

More information

Capital Projects impacting Odenton Town Center

Capital Projects impacting Odenton Town Center Capital Projects impacting Odenton Town Center 1 2 E549700 W801600/ W801602 Anne Arundel County Department of Public Works Manor View Elementary School Transmission Main - MD 32 @ Meade Phase 2 $34,399,000

More information

BID RESULTS OCTOBER 24, 2007

BID RESULTS OCTOBER 24, 2007 INTERSTATE A20 83068 (NF0)PM04-026-248, N501 IM-PM04(223) VARIOUS LOCATIONS DINWIDDIE CO. ASPHALT PAVING & GUARDRAIL UPGRADE B. P. SHORT & SON PAVING CO., INC. PETERSBURG, VA 1 $1,262,410.02 N9J CM408A09431

More information

SR 483 Clyde Morris Boulevard FDOT District 5

SR 483 Clyde Morris Boulevard FDOT District 5 This project occurs on a 3.0 mile section of SR 483 (Clyde Morris Blvd.) south of Beville Road (SR 400) to north of International Speedway Boulevard (SR 600). Ghyabi is providing project management and

More information

Capital Projects in and near Odenton Town Center

Capital Projects in and near Odenton Town Center Capital Projects in and near Odenton Town Center Map ID Anne Arundel County Department of Public Works This project provides for the design, right of way acquisition, and construction of approximately

More information

I-4 Beyond the Ultimate. Florida Transportation Builders Association February 9, 2018

I-4 Beyond the Ultimate. Florida Transportation Builders Association February 9, 2018 I-4 Beyond the Ultimate Florida Transportation Builders Association February 9, 2018 FDOT: Improving Mobility & Safety in Central Florida FDOT is Designing and building a better I-4 through Central Florida

More information

City of Jersey City. Department of Administration Division of Engineering Traffic and Transportation

City of Jersey City. Department of Administration Division of Engineering Traffic and Transportation Division of Engineering Traffic and Transportation : Duncan Avenue Road Program Bergen Avenue Road Program PSE&G Gas System Modernization Program NJDOT Municipal Aid FY2015 Road Program Ogden Dog Park

More information

Index to Projects by Project Name

Index to Projects by Project Name Index to Projects by Project Name 2062 1701 & 1711 Concord Avenue Purchase and Demolition of Structures 85 1279 1024 UF-802 UF-803 Affordable Housing 77 Annual CIP/TIP Management Program 105 Arnold Industrial

More information

Welcome to the. Citizen Information Meeting for the Martinsville Southern Connector Study. The purpose of this meeting is to:

Welcome to the. Citizen Information Meeting for the Martinsville Southern Connector Study. The purpose of this meeting is to: Route Environmental Impact Statement Welcome to the Citizen Information Meeting for the Martinsville Southern Connector Study The purpose of this meeting is to: Introduce the Martinsville Southern Connector

More information

Moving The Metro. A special construction update for the metro Omaha area.

Moving The Metro. A special construction update for the metro Omaha area. Moving The Metro A special construction update for the metro Omaha area. ebraska Department of Roads Spring/Summer 2017 I-80 / I-480 / US-75 Interchange The improvements on this project consist of bridge

More information

CITY OF LAKEWOOD 2012 THREE-MILE PLAN

CITY OF LAKEWOOD 2012 THREE-MILE PLAN CITY OF LAKEWOOD 2012 THREE-MILE PLAN SECTION 1: INTRODUCTION This document constitutes the s Three-Mile Plan for the unincorporated area three miles in width around the City s perimeter, as required by

More information

Construction Engineering & Inspection

Construction Engineering & Inspection Construction Engineering & Inspection Serving Florida for 20 Years CEI Engineering Planning Landscape Architecture Urban Design Construction Engineering & Inspection (CEI) I N T R O D U C T I O N Over

More information

TOWNSHIP OF HOWELL TOWNSHIP OF HOWELL ENGINEERING PROJECTS STATUS REPORT OCTOBER 19, Resurfacing of Aldrich Road West Contract # 11-06

TOWNSHIP OF HOWELL TOWNSHIP OF HOWELL ENGINEERING PROJECTS STATUS REPORT OCTOBER 19, Resurfacing of Aldrich Road West Contract # 11-06 TOWNSHIP OF HOWELL DEPARTMENT OF COMMUNITY DEVELOPMENT & LAND USE DIVISION OF ENGINEERING 251 Preventorium Road Phone: (732) 938-4500 x2300 Post Office Box 580 Fax: (732) 919-1080 Howell, NJ 07731-0580

More information

I-66 EASTBOUND WIDENING INSIDE THE BELTWAY PARDON OUR DUST MEETING

I-66 EASTBOUND WIDENING INSIDE THE BELTWAY PARDON OUR DUST MEETING I-66 EASTBOUND WIDENING INSIDE THE BELTWAY From the Dulles Connector Road (Route 267) to Fairfax Drive (Route 237) PARDON OUR DUST MEETING Bill Cuttler, PE (VDOT District Construction Engineer, Northern

More information

Exhibit A. SH 161 RTC Work Program of New Projects. Collin County

Exhibit A. SH 161 RTC Work Program of New Projects. Collin County Exhibit A SH 161 RTC Work Program of New Projects Collin County 0918-24-969 N/A 0918-24-970 N/A 0918-24-973 N/A 2351-01-020 N/A 2679-03-010 N/A On Exchange Parkway from US 75 to Allen Heights On Country

More information

AWARD ARTERIAL. Bid Amount: Less Than 5 Million. Report created on : 1/12/19 Letting Date: 12/19/2018. Estimated Construction Cost.

AWARD ARTERIAL. Bid Amount: Less Than 5 Million. Report created on : 1/12/19 Letting Date: 12/19/2018. Estimated Construction Cost. ARTERIAL A46 09889 LOCATION: DISTRICTWIDE THE TRUESDELL CORPORATION 9999-96-437,N50 TEMPE HSIP-96-(08) AZ Construction 7 $55,55.00 $788,739.07 BRISTOL DISTRICT HIGH FRICTION SURFACE TREATMENT PAVING Recommended

More information

Planning & Zoning Board Meeting. DRAFT Comprehensive Transportation Plan Update, February 23, 2018 version

Planning & Zoning Board Meeting. DRAFT Comprehensive Transportation Plan Update, February 23, 2018 version Planning & Zoning Board Meeting DRAFT Comprehensive Transportation Plan Update, February 23, 2018 version May 10, 2018 Overview Overview of Agency Comments Overview of proposed modifications to the Draft

More information

Minutes from the Main Street Markham Committee meeting held on March 16, City of Markham Canada Room - Civic Centre

Minutes from the Main Street Markham Committee meeting held on March 16, City of Markham Canada Room - Civic Centre Minutes from the Main Street Markham Committee meeting held on City of Markham Canada Room - Civic Centre Members Councillor Karen Rea, Chair Councillor Colin Campbell, Vice Chair Siobhán Covington Graham

More information

Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL

Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL Agenda Design Concept Report Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Questions Design Concept Report

More information

Public Officials/Design Advisory Meeting #12. Bensalem Township Municipal building, 2400 Byberry Road Bensalem, PA

Public Officials/Design Advisory Meeting #12. Bensalem Township Municipal building, 2400 Byberry Road Bensalem, PA Meeting Purpose: Date and Time: Location: Attendance: Materials: PA Turnpike/I 95 Interchange Project Public Officials/Design Advisory Meeting #12 June 2, 2016 at 11:00 a.m. Bensalem Township Municipal

More information

Wilson County Projects

Wilson County Projects Wilson Projects SR-109 Reconstruction & Widening TIP # 2009-72-036 Road Widening TDOT Wilson Length 3.50 Regional Plan ID 1072-348-2 Air Quality Status Non-Exempt TDOT PIN 100281.03 $34,000,000.00 SR-109

More information

Interstate Traffic Interruptions Weekend of Oct 9, 2015-Oct 12, 2015

Interstate Traffic Interruptions Weekend of Oct 9, 2015-Oct 12, 2015 Interstate Traffic Interruptions Weekend of Oct 9, 2015-Oct 12, 2015 District 1 10/9/15 10/12/15 D Gwinnett/Hall I-985 NB MP 0 (I-85) 9pm 5am 1 right lane of 2 458462 to MP 20 (SR 60) ROLLING CLOSURE 10/9/15

More information

ALTERNATIVES. NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives).

ALTERNATIVES. NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives). III. ALTERNATIVES A. CONSTRUCTION METHOD ALTERNATIVES NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives). One of the

More information

Mavis Road Class Environmental Assessment

Mavis Road Class Environmental Assessment Mavis Road Class Environmental Assessment Public Information Centre #2 Wednesday November 9, 2016 6:00 to 8:00 p.m. Please sign in and complete a comment sheet Review the displays on your own or join in

More information

New Stanton Project Update July 3, 2012

New Stanton Project Update July 3, 2012 New Stanton Project Update July 3, 2012 The Needs BACKGROUND INFO I-70 Geometric Concerns Substandard Horizontal & Vertical Clearance at Center Ave. Bridge (The Center Avenue Bridge is Replaced in all

More information

Proposed FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

Proposed FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects Carteret Industrial Road 98547 This project will address the upgrade of Carteret Industrial Road. The federal Transportation Equity Act for the 21st Century (TEA-21) provided funding for this project under

More information

2017 Asphalt Contractors Association of Florida Pavement Awards

2017 Asphalt Contractors Association of Florida Pavement Awards 2017 Asphalt Contractors Association of Florida Pavement Awards Special Projects Any project of a special or unique nature requiring specialized equipment, techniques, materials, time restrictions, or

More information

Fall 2017 Construction Update

Fall 2017 Construction Update Fall 2017 Construction Update Ward 4 Southeast Engineering Department Riverwalk Red Multi-Use Trail Bridge Rehabilitation The Riverwalk Red Multi Use Trail Bridge was awarded to Cramer and Associates,

More information

North Carolina Department of Transportation Project Development and Environmental Analysis Branch

North Carolina Department of Transportation Project Development and Environmental Analysis Branch North Carolina Department of Transportation Project Development and Environmental Analysis Branch Citizens Informational Workshop I-85, from I-485 to NC 73 Mecklenburg and Cabarrus Counties October 30,

More information

Derby-Shelton Bridge Pedestrian and Bicyclist Enhancements [1]

Derby-Shelton Bridge Pedestrian and Bicyclist Enhancements [1] nhancements [1] STATUS OF PROJECT: The project has recently moved from the Preliminary Design Phase to the Final Design Phase following the most recent Public Involvement Meeting held on January 9, 2019

More information

Spring 2018 Construction Update

Spring 2018 Construction Update Spring 2018 Construction Update Ward 3 Southwest Engineering Department Locust Street Bridge over the Des Moines River The Locust Street Bridge over the Des Moines River project is being let through the

More information

Const. ROADS - Description

Const. ROADS - Description Road Projects make up the bulk of the capital expenditures for the township. For the term of this CIP, road projects total $9,843,000 or 72.0% of the total capital expenditures for all capital projects

More information

TIRZ 17/Redevelopment Authority Capital Improvements Plan Projects

TIRZ 17/Redevelopment Authority Capital Improvements Plan Projects Gessner Widening: T-1701 What: Widen the road from a six-lane divided boulevard to an eight-lane divided boulevard street section, increase turn lanes, update traffic signal system, improve drainage by

More information

STP DA Candidate Pedestrian Projects Funding Recommendations

STP DA Candidate Pedestrian Projects Funding Recommendations STP DA Candidate Pedestrian Projects Funding Recommendations Rank Municipality Project Description Total Cost STP DA Local Notes Cumulative STP DA Funding Request Date 1 Winston Martin Luther King Jr.

More information

Town of Cornelius Bond Update August, 2017

Town of Cornelius Bond Update August, 2017 Town of Cornelius Bond Update August, 2017 Referendum Results Roads, Intersections, & Sidewalks ($11.15 mil) Pass rate 81.38% in favor Parks and Recreation ($5.25 mil) Pass rate 72.09% in favor Town Center

More information

Hays County Candidate Projects PROPOSED ROAD BOND PROGRAM WORKSESSION

Hays County Candidate Projects PROPOSED ROAD BOND PROGRAM WORKSESSION Hays County Candidate Projects PROPOSED ROAD BOND PROGRAM WORKSESSION July 19, 2016 Candidate Projects Identified by Commissioners Complete projects currently in the planning process Priority projects

More information

Subject: 2014 Regional Transportation Plan Amendment No. 1

Subject: 2014 Regional Transportation Plan Amendment No. 1 Agenda Item: 6 Memorandum To: Board of Directors From: Grant Leonard, Transportation Planner Meeting Date: April 27, 2016 Subject: 2014 Regional Transportation Plan Amendment No. 1 RECOMMENDED ACTIONS

More information

PROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING. 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S.

PROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING. 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S. PROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S. 67 HEARING LOCATION: ERICKSEN COMMUNITY CENTER 1401 11 TH AVENUE NORTH

More information

FDOT/FTBA Construction Conference Work Plan

FDOT/FTBA Construction Conference Work Plan FDOT/FTBA Construction Conference 19 2019 2023 Work Plan Ben Dreiling, P.E., Director of Construction Central Florida Expressway Authority January 18, 2019 Major Projects Map FY 2019-2023 Work Plan 2 FY

More information

2017 Capital Improvements Report

2017 Capital Improvements Report 2017 Capital Improvements Report March 20, 2017 Board of County Commissioners Butler County Government Services Center 315 High Street Hamilton, Ohio 45011-2759 RE: 2017 Capital Improvements Report Board

More information

We d like to thank you for attending this Wekiva Parkway Section 8 Preliminary Design Update hosted by the Florida Department of Transportation.

We d like to thank you for attending this Wekiva Parkway Section 8 Preliminary Design Update hosted by the Florida Department of Transportation. We d like to thank you for attending this Wekiva Parkway Section 8 Preliminary Design Update hosted by the Florida Department of Transportation. We will provide you information on the overall project and

More information

2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director

2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director 2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director 1 Jefferson County, Missouri Road and Bridge Sales Tax: Jefferson County has a one-half cent sales tax that

More information

Delaware Valley Regional Planning Commission (DVRPC)

Delaware Valley Regional Planning Commission (DVRPC) Delaware Valley Regional Planning Commission (DVRPC) Major Project Status Report State Transportation Improvement Program (STIP) for Pennsylvania (FY2013-2016) Federal regulations require that the STIP

More information

2018 Primary Road Capital Improvement Plan (CIP) Projects Preservation / Structural Improvement, Non-motorized and Engineering Design Projects

2018 Primary Road Capital Improvement Plan (CIP) Projects Preservation / Structural Improvement, Non-motorized and Engineering Design Projects 2018 Primary Road Capital Improvement Plan (CIP) Projects Preservation / Structural Improvement, Non-motorized and Engineering Design Projects Preservation / Structural Improvement Projects in 2018 Ravine

More information

Proposed FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

Proposed FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects 30 130 Collingswood/Pennsauken ( B) 155C Vicinity of Cooper River Bridge at Park Drive to 200 feet north of PATCO Railroad Bridge This project may provide for the construction of a proposed new bridge

More information

Highway & Bridge Capabilities

Highway & Bridge Capabilities Highway & Bridge Capabilities Part of a diversified family of solutions www.jmt.com An Employee Owned Company I-95/I-295/I-495 Interchange, Woodrow Wilson Memorial Bridge, Prince George s County, MD Our

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects ROUTE/ Project ID No. TIP No. Burlington County Computerized Signal Control, IV D9911 D9911 This ITS project will be a traffic responsive signal system, consisting of 24 intersections--9 on CR 607, 4 on

More information

4.1 Build Alternative 1 Construction Phasing

4.1 Build Alternative 1 Construction Phasing SECTION 4 Implementation Plan This section discusses potential segmentation of the build alternatives into multiple projects for implementation of improvements to the NSH from Rabbit Creek Road to 36th

More information

2018 Capital Improvements Report

2018 Capital Improvements Report 2018 Capital Improvements Report March 19, 2018 Board of County Commissioners Butler County Government Services Center 315 High Street Hamilton, Ohio 45011-2759 RE: 2018 Capital Improvements Report Board

More information

Places29: List of Implementation Projects

Places29: List of Implementation Projects Important Points to Keep in Mind When Using This List Places29: List of s Each of the projects in this List represents an action needed to implement the Places29 Master Plan. The projects are grouped first

More information

COLLIER BOULEVARD (CR 951) CORRIDOR

COLLIER BOULEVARD (CR 951) CORRIDOR Project(s) Goals Improve Traffic Circulation, Capacity & Safety Focus on Safety During Design & Construction Address Public Concerns Design an Aesthetically Pleasing Project Limit Environmental Impacts

More information

4. INITIAL CONCEPT DEVELOPMENT AND SCREENING

4. INITIAL CONCEPT DEVELOPMENT AND SCREENING 4. INITIAL CONCEPT DEVELOPMENT AND SCREENING A coordinated effort by the project team and members of the three oversight committees (Citizen Advisory, Technical Advisory, and Steering) led to 17 initial

More information

Visitor's Guide to Historic Bridge Park

Visitor's Guide to Historic Bridge Park Visitor's Guide to Historic Bridge Park Located in Calhoun County, Michigan, southeast of Battle Creek, the park is open year-round from 8:00 AM to 8:00 PM. Entry to the park is free of charge. Guide produced

More information

RICHLAND COUNTY TRANSPORTATION PROGRAM 2016 ANNUAL REPORT

RICHLAND COUNTY TRANSPORTATION PROGRAM 2016 ANNUAL REPORT RICHLAND COUNTY TRANSPORTATION PROGRAM 2016 ANNUAL REPORT Richland County Transportation Program 2016 ANNUAL REPORT Program Overview 1 By the Numbers 2 Finance 3 SLBE Figures 5 2016 Projects Status 6 The

More information

The bid shall include the following items: 1) Bidder s Name. Address. Telephone Number. Address. 2) The amount of the bid per acre to Mow.

The bid shall include the following items: 1) Bidder s Name. Address. Telephone Number.  Address. 2) The amount of the bid per acre to Mow. Beautification and Rough Mowing Services Bid #066-17 The City of Lucas is seeking bids for Beautification and Rough Mowing Services on 30 acres of land. The Mowing Season is 40 week long between March

More information

Stafford VDOT Cooperative Activities

Stafford VDOT Cooperative Activities Stafford VDOT Cooperative Activities February 21, 2012 General Areas of Cooperation Financial Road Safety & RTMP Design County Projects VDOT Projects Street Acceptance Rural Addition/Rural Paving Maintenance

More information

I-75/I-475 Interchange Upgrade Project Informational Meeting Tuesday, July 27, 2010

I-75/I-475 Interchange Upgrade Project Informational Meeting Tuesday, July 27, 2010 I-75/I-475 Interchange Upgrade Project Informational Meeting Tuesday, July 27, 2010 I-75/I-475 Interchange Upgrade Project David R. Dysard, AICP District Two Deputy Director Theresa Pollick Public Information

More information

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER SUMNER NASHVILLE AREA MPO FY -2017 TIP - ADOPTED DECEMBER 11, 2013 Rockland Road Widening TIP # 2002-028 Road Widening Hendersonville Sumner Length 1.50 Regional Plan ID 1052-177 Air Quality Status Non-Exempt

More information

Turkey Creek Corridor

Turkey Creek Corridor A NATURAL SANCTUARY Creek Corridor Creek Corridor.1 Kimberly BLOUNT ST CLAIR rro w sr Ro 79 oa 75 d A ad Pinson High School Jackson Creek Nature Preserve H B. D Pinson Dug Hollow Rd d o fo rl oo p er Rd

More information

See Yellow Highlighted for Major Closures

See Yellow Highlighted for Major Closures Projects Report Week of May 21-27, 2018 Street/Intersection From To CURRENT PROJECTS Ashcroft Ln. Cobblestone Row North Dead End 5/14/18 6/15/18 Ave. A Maple Eagle 3/19/18 6/30/18 Bonnie Brae St. Roselawn

More information

City of Kearney Capital Improvement Update October 1, TH STREET AND 17TH AVENUE IMPROVEMENTS

City of Kearney Capital Improvement Update October 1, TH STREET AND 17TH AVENUE IMPROVEMENTS 56TH STREET AND 17TH AVENUE IMPROVEMENTS FUNDING: Bonded ESTIMATED COST: $3,885,000 COMPLETION DATE: Fall 2018 SCOPE OF PROJECT: Widening of 56th Street from 6th Avenue to 19th Avenue, and widening 17th

More information

Northeast Anthony Henday Drive Manning Freeway to Whitemud Drive Welcome to this Construction Information Session

Northeast Anthony Henday Drive Manning Freeway to Whitemud Drive Welcome to this Construction Information Session Manning Freeway to Whitemud Drive Welcome to this Construction Information Session Purpose To inform interested residents and businesses about the plans accommodation. Background: The Government of Alberta

More information

Panama City Beach Community Redevelopment Agency Condo Con Property Owner Conference & Expo November 14, 2014

Panama City Beach Community Redevelopment Agency Condo Con Property Owner Conference & Expo November 14, 2014 Panama City Beach Community Redevelopment Agency Condo Con Property Owner Conference & Expo November 14, 2014 Front Beach Road CRA On November 30, 2000, the City created the Panama City Beach Community

More information

CHAPTER House Bill No. 385

CHAPTER House Bill No. 385 CHAPTER 2005-292 House Bill No. 385 An act relating to state facility designations; designating Ramon Puig Way, Shawn O Dare Way, Marge Pearlson Way, and Jorge L. Cabrera Way in Miami-Dade County; designating

More information

Knoxville Area Transit (KAT) Transit Development Plan Corridor Analysis

Knoxville Area Transit (KAT) Transit Development Plan Corridor Analysis Knoxville Area Transit (KAT) Transit Development Plan Submitted to: Knoxville-Knox County Metropolitan Planning Commission Submitted by: PB Americas, Inc. Under contract to: The Corradino Group, Inc. October

More information

Special Revenue Funds

Special Revenue Funds Special Revenue Funds Special Revenue Funds account for the proceeds of specific revenue sources (other than special assessments for major capital projects) that are legally restricted to expenditures

More information

IMPLEMENTATION STRATEGIES. In This Chapter. Goals & Strategies 182 Project List 183 Future Land Use 186 CHAPTER 11 IMPLEMENTATION STRATEGIES

IMPLEMENTATION STRATEGIES. In This Chapter. Goals & Strategies 182 Project List 183 Future Land Use 186 CHAPTER 11 IMPLEMENTATION STRATEGIES In This Chapter Goals & Strategies 182 Project List 183 Future Land Use 186 11 IMPLEMENTATION STRATEGIES NORTH AUGUSTA, SC 2017 COMPREHENSIVE PLAN 179 Individual commitment to a group effort that is what

More information

Abbott Loop. Community Council Survey Capital Projects Needs Ranking Survey. Comm Council Priority Rank. Rank # ABBOTT LOOP COMMUNITY PARK

Abbott Loop. Community Council Survey Capital Projects Needs Ranking Survey. Comm Council Priority Rank. Rank # ABBOTT LOOP COMMUNITY PARK Municipality of Anchorage Community Council Survey ABBOTT LOOP COMMUNITY PARK This state funding request would be used to implement the remaining elements of the Community Park Master Plan Vision including

More information

PROPOSED IMPROVEMENTS

PROPOSED IMPROVEMENTS IV. PROPOSED IMPROVEMENTS The proposed improvements for each alternative carried forward are discussed below. A. FUNCTIONAL CLASSIFICATION AND ROADWAY CROSS-SECTIONS The classifications of the roadways

More information

3.1 Survey Monument Preservation Guidelines for New and Reconstruction Projects. B. After construction and prior to recording Notice of Completion:

3.1 Survey Monument Preservation Guidelines for New and Reconstruction Projects. B. After construction and prior to recording Notice of Completion: 3.0 SURVEY 3.1 Survey Monument Preservation Guidelines for New and Reconstruction Projects A. Prior to construction: 1. Public survey records are to be researched for the location of all possible survey

More information

Project Status. Construction is underway for Phase 3. Overall Project Area and Schedule. Schedule of Current Construction Phases.

Project Status. Construction is underway for Phase 3. Overall Project Area and Schedule. Schedule of Current Construction Phases. I-95 Avenue Interchange Project Status Construction is underway for Phase 3. Overall Project Area and Schedule Phase 0: Completed 2010 Section GR0: Completed in Fallin 2010 Phase 2: Completed Section GR2:

More information

Turkey Creek Streamway Corridor

Turkey Creek Streamway Corridor Turkey Creek Streamway Corridor Turkey Creek Corridor Overview History Watershed Corridor Inventory Coalition Corridor Plan Stages of Development Benefits Funding Turkey Creek History Kansas and Missouri

More information

Brick names: Old Carbondale & Ironworks. RESIDENTIAL BRICK - EARTH TONES generalshale.com

Brick names: Old Carbondale & Ironworks. RESIDENTIAL BRICK - EARTH TONES generalshale.com Brick names: Old Carbondale & Ironworks RESIDENTIAL BRICK - EARTH TONES generalshale.com Brick Product: Old Carbondale & Ironworks Brick Product: Old Carbondale & Ironworks Brick Product: Walnut Creek

More information

Introduction to the Project

Introduction to the Project Chapter 1 Introduction to the Project 1.1 Project Introduction The New Hampshire Department of Transportation (NHDOT) and the Federal Highway Administration (FHWA) have prepared this Environmental Assessment/Draft

More information

STREET IMPROVEMENT AND MAINTENANCE PROGRAMS

STREET IMPROVEMENT AND MAINTENANCE PROGRAMS 2018-2019 STREET IMPROVEMENT AND MAINTENANCE PROGRAMS Engineering Department Pamela S. Cooksey, City Engineer Public Works Department Jonathan Gano, Public Works Director April 2018 Attached for your information

More information

FY 2005 TRANSPORTATION CAPITAL PROGRAM

FY 2005 TRANSPORTATION CAPITAL PROGRAM Camden County Civic Center Access Study, Pennsauken 03340 This project will address operational and access improvements on Routes 30, 73 and 90 related to the Crossroads redevelopment project around the

More information

US 24 & SR 66 Interchange Modification and Corridor Improvement Project Public Involvement Meeting December 5, 2007

US 24 & SR 66 Interchange Modification and Corridor Improvement Project Public Involvement Meeting December 5, 2007 US 24 & SR 66 Interchange Modification and Corridor Improvement Project Public Involvement Meeting December 5, 2007 Sponsored by: The Ohio Department of Transportation and The City of Defiance Project

More information

Revised Long Range Transportation Plan

Revised Long Range Transportation Plan Revised Long Range Transportation Plan Auburn, Alabama Prepared for: City of Auburn, Alabama Prepared by: Skipper Consulting, Inc. June 2006 Revised Long Range Transportation Plan City of Auburn, Alabama

More information

I-95 Girard Avenue Interchange Near Neighbors Meeting. Project Status

I-95 Girard Avenue Interchange Near Neighbors Meeting. Project Status I-95 Girard Avenue Interchange Project Status Construction is underway for Phase 1 and 2. Phase 3 construction will begin early 2014. Overall Project Area and Schedule GR0: Completed GR0: Completed in

More information

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017 Community Meeting No. 2 May 31, 2017 Transportation Projects On or Near SH 199 SH 199 from 0.3 miles south of FM 1886 to south end of Lake Worth bridge Construct freeway mainlanes and frontage roads 10-Year

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects Garden State Parkway, Interchange 67, at Bay Avenue, CR 554 NS0210 NS0210 This project will provide new and modified movements to the Garden State Parkway, Interchange 67 at Bay Avenue (CR 554). Currently,

More information

The Grand Army of the Republic Corridor

The Grand Army of the Republic Corridor The Grand Army of the Republic Corridor CORRIDOR 11 This east-west corridor is northern Pennsylvania s Main Street. It is consistently rated as one of the most scenic drives in the nation. In addition

More information

Guide to the Rhode Island Department of Transportation Historic Resources Archive Documentation and Archaeology Series records

Guide to the Rhode Island Department of Transportation Historic Resources Archive Documentation and Archaeology Series records Page 1 of 18 Guide to the Rhode Island Department of Transportation Historic Resources Archive Documentation and Archaeology Series records 1997-2015 337 Westminster Street Providence, RI 02903 Tel: 401-222-2353

More information

VDOT s HRTAC and Mega- Projects Program

VDOT s HRTAC and Mega- Projects Program VDOT s HRTAC and Mega- Projects Program November 18, 2015 James W. Long, III, P.E., DBIA District Major Projects Delivery Director Hampton Roads District Agenda 1. Hampton Roads Transportation Accountability

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects 69th Street Bridge 02311 02311 A grade separation at 69th Street would eliminate the current at-grade crossing which causes frequent automobile delays due to long freight trains moving through this area.

More information