TRINITY LUTHERAN SCHOOL RENOVATIONS
|
|
- Eustace Davis
- 5 years ago
- Views:
Transcription
1 MASTER PLAN FOR PHASED IMPROVEMENTS AUGUST 26, 2013 WITH DESIGN AND PLANNING GUIDANCE FROM WIGHT & COMPANY`
2 Recognizing the importance of its school facility s general appearance, school officials initiated a feasibility study in April 2013, appointing an administrative guiding committee, school staff and community members as a focus group, and Wight & Company as design consultant. OVERVIEW OF PROPOSED IMPROVEMENTS Renovate: make like new again The study is focused on apprearance, with the goal of modernizing the school s interior and entrance features, giving students, teachers, and visitors a visual environment that corresponds with today s aesthetics in terms of color, design and material. Make the school look new again. entry addition OFFICE office remodeling: inner office outer office Through the study, and informed by the opinions of focus group, priorites were established among the many parts of the school that could benefit from an aesthetic modernization. Subsequent pages provide a little more detail into the top two priorities: priority interiors and entry addition. priority interiors including remodeling Similar detail on other potential improvements, though in consideration, are not within the purview of the study. swap locations: existing secondary interiors optional basement beneath addition OFFICE GYM GYM priority interiors secondary interiors existing site configuration August 26, 2013 Wight & Company
3 PRIORITY INTERIOR IMPROVEMENTS office or commons concept for multi-use study feature at classroom entries pre-k OPTIONS FOR REFINISHING THE INTERIORS Lobby proposed remodeling as illustrated Corridors new vinyl and walk-off carpet flooring resurfacing selected walls new acoustical ceiling with features, lighting new cabinetry, millwork, seating, furniture new vinyl composition tile flooring tackable wall surfacing classroom entry features Restrooms new porcelain tile flooring and ceiling new acoustical ceiling with lighting new lighting repaired and re-painted lockers new lavatory fixtures new counters and dispensers floor area 1,100 sq ft upper level floor area lower level floor area 800 sq ft 1,800 sq ft upper level floor area lower level floor area 500 sq ft 1,200 sq ft August 26, 2013 Wight & Company
4 ENTRY ADDITION new view of addition concept plan F view of addition existing entry area, seen from parking lot monument sign (future potential) monument sign new new (portion open for daylight) signage walls (portion open for daylight) signage walls signage wall plan A (extend facing to corner) existing plan reconfigured office space (future potential) added office added office plan B plan C plan D signage wall plan E August 26, 2013 Wight & Company
5 COLORS AND MATERIALS Interior Color Palette An aspect of the study, with a focus on apprearance, was to adopt a palette of colors and materials for all interior surfaces. Though the various improvements may be implemented in increments according to funding, each increment adheres to this coordinated groups of finishes and, with each stage, brings the overall school closer to a fully-coordinated and updated look. Alternatives were reviewed by the focus group, and this palette was preferred as being lively and energizing without being overly juvenile, appealing to all ages. The photo below is taken from a collage of actual matertial samples. The colors may not be represented accurately due to the variations in printing systems. Refer to the actual sample panel, maintained in the school office, for true color reference. This is simply a palette, and not a complete color and finish design. With each improvement, the specific applications will need to be determined by the designer to both adhere to the palette and to coordinate with any foregoing applications at the time. feature at classroom entries office multi-use study paint colors, school pre-k OPTIONS FOR REFINISHING THE INTERIORS Lobby proposed remodeling as illustrated Corridors new vinyl and carpet flooring resurfacing selected walls new acoustical ceiling with features, lighting new cabinetry, millwork, seating, furniture new vinyl flooring new acoustical ceiling with lighting tackable wall surfacing classroom entry features Restrooms new porcelain tile flooring and ceiling new lighting repaired and re-painted lockers new lavatory fixtures new counters and dispensers note: The colors on this exhibit do not represent the actual proposed colors. See accompanying Colors and Materials exhibit for proposed palette of materials. All materials are contract grade products for use in commercial and institutional applications. vinyl composition tile field color paint colors, gym field color (most walls) solid surfacing modular carpet sheet vinyl for commons field pattern and color concept for walk-off carpet field color accents furniture grouping August 26, 2013 Wight & Company
CLEVELAND HEIGHTS UNIVERSITY HEIGHTS CITY SCHOOL DISTRICT MONTICELLO & ROXBORO MIDDLE SCHOOLS INTERIOR DESIGN
CLEVELAND HEIGHTS UNIVERSITY HEIGHTS CITY SCHOOL DISTRICT MONTICELLO & ROXBORO MIDDLE SCHOOLS INTERIOR DESIGN 04.13.2017 1 MONTICELLO INTERIOR FINISHES PAINT MOULDING WALLS ACCENT DOORS DOOR TRIM/STAIRS
More informationRiverview West Side Elementary 160 Isabel Avenue East
160 Isabel Avenue East Project Summary: At the center of Hispanic culture in St. Paul is Riverview Elementary - and it s truly the center of the West Side community. Our newly renovated location offers
More informationNew High School Concept
Approved Bond Projects for Alamance-Burlington Schools In November 2018, Alamance County citizens approved a $150 million bond project proposal. Bond funds will pay to construct a new high school and provide
More informationForest Hills Facilities Plan
Forest Hills Facilities Plan Extensive updates to 8 of our 9 schools Replace Wilson Elementary Enhance learning environments across the district Build additional classrooms to accommodate gradual implementation
More informationVOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED
Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological
More informationMaster Facility Planning Update School Board Meeting May 26, 2016
Master Facility Planning Update School Board Meeting May 26, 2016 Master Facilities Committee Overview Reflection of Committee Work Review of District Wide Facility Issues Identified District Wide Facility
More informationSurface Materials. Surface Material Reflectance. Acoustic Ceiling 80% Tile. Painted Gypsum 75% Wall Board. Vinyl Composition 32% Tile
Genetics Laboratory Space Description The Genetics Laboratory is located on the second floor of the laboratory building. The main functions of this space are as a learning and research area. There is a
More informationColumns REF, RESPONSIBLE and COMPL TD are provided for your numbering, assignments and control. REF ISSUE RESPONSIBLE COMPL TD
PREPARING FOR THE DESIGN OF YOUR SCHOOL CAPITAL PROJECT A Checklist of Issues March 2014, v.1 This document can be used in preparing the stakeholder team for decision-making and for documenting the input
More informationHELENA PUBLIC SCHOOLS FRONT STREET LEARNING CENTER CLEANING OUTCOMES ASSESSMENT. May 2013
HELENA PUBLIC SCHOOLS FRONT STREET LEARNING CENTER CLEANING OUTCOMES ASSESSMENT May 2013 HPS FRONT STREET LEARNING CENTER CLEANING OUTCOMES ASSESSMENT PURPOSE During the week of May 20th, 2013 BRUCO INC.
More informationImagine RBC 2010 The Plan
Imagine RBC 2010 The Plan Creation of New Space The creation of a new Student Center will greatly relieve the demands on existing space. Currently 1,700 students, including both RBC and St. James Grammar
More informationBriar Crest Elementary
Promises Kept This document includes partial lists of major projects completed at Pattonville Schools since 1986 as part of past bond issues approved by the Pattonville community. Briar Crest Elementary
More informationNew Brunswick Campus Operations Service Guide. Maintenance repair or replacement in
Centrally Scheduled Classrooms Centrally Scheduled No Charge: Contact Digital Classroom Services Cleaning Accoustical Materials Signage Building Odors Clock Air Conditioning Pest Control Furniture: Baseboard
More informationCOSMETOLOGY September 30, 2010
COSMETOLOGY September 30, 2010 I. PROGRAM REQUIREMENTS Refer to the project-specific Schedule of Spaces for student stations, square footage, and for any requirements that may differ from the prototype
More informationCAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14
2014-2015 CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 School Item Amount a. Classroom A/R (Increase CR capacity to 804, add l Resource and tutoring spaces needed. Teacher
More information3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000
1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades Allowance $300,000 C. Tilden Entrance Upgrades D. Door and Glass Improvements Allowance $500,000 E. Alert
More informationREPORT CARD TO THE COMMUNITY MAY 15, 2018
REPORT CARD TO THE COMMUNITY MAY 15, 2018 O On May 10, 2014 voters in Greenville ISD approved a $72,275,000 bond election. BOND PROPOSAL PROJECT BOND AMOUNT CONSTRUCT A NEW BOWIE ELEMENTARY SCHOOL $17,600,000
More informationBeaufort County Community College. Maintenance and House Keeping Plan
Beaufort County Community College Maintenance and House Keeping Plan Summary: The College s facility management is handled by the Maintenance Department. The Director of Plant and Maintenance Operations
More informationCustodial Guide
Custodial Guide 2018-2019 Table of Contents Page Number 1 General Items to Note 2-3 Maintenance for Office Areas 4-5 Maintenance for Classrooms and Hallways 6 Maintenance for Lounge Areas 7 Maintenance
More informationStanfield School District Cleaning Standards
Stanfield School District Cleaning Standards Universal Precautions Always wear protective gloves. Do not use gloves that have holes or tears. Treat all body fluid spills as if they were contaminated. Items
More informationGENERAL ASSIGNMENT CLASSROOM DESIGN STANDARDS
University of Iowa FSG - Design & Construction Services Design Reference Manual 2 Design Standards 2.02 Classroom Design Standards Classroom Design Standards GENERAL ASSIGNMENT CLASSROOM DESIGN STANDARDS
More information3.2.4 OFFICE FACILITIES
3.2.4 OFFICE FACILITIES 3.2.4.1 General The guidelines in this section address offices and office support spaces. Office and office support space standards are used to provide the Project Team with design
More informationChariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15)
Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) School/Department FY 16 FY 17 FY18 FY19 FY20 Chariho Regional High School FY 16 FY 17 FY18 FY19 FY20 *Repair Bleachers
More information2014 Bond Project Guide
2014 Bond Project Guide Bush Elementary School Page 1 Instructional Technology Computers, Projectors, Mobile Carts, Document Cameras and Printers Wireless Connectivity New Construction New Tech Center
More informationJewel. Platte. of the. Plattsmouth Main Street Landscape Architecture by HDR
Jewel of the Platte Plattsmouth Main Street Landscape Architecture by HDR Plattsmouth, Nebraska is a historic community of 6,500 residents located along the west bank of the Missouri River, just south
More informationCleaning Service Levels
Restrooms Empty waste receptacles and change liner, as needed. Restock dispensers: soap, paper towel and toilet tissue. Clean mirrors; clean and disinfect urinals, toilets, and sinks. Polish stainless
More informationDesign Presentation. Chief Operations Officer Willie Burroughs
Design Presentation Chief Operations Officer Willie Burroughs Agenda Introduction Community Feedback Project updates 2 Feedback Citizens Advisory Committee meetings Growth and Development meetings Community
More informationCENTRAL CITY NEIGHBORHOOD Site Plan and Design Review Guidelines Checklist
Applicant s Name: Project Address: NEIGHBORHOOD Phone: Email: Applicant shall fill out the design guidelines checklist for all guidelines applicable to the project. Check the box if meets guideline. Indicate
More informationMaster Project List Report
Blue Hills Elementary School 01-8215 Site Utilities Replacement $52,835 01-8502 Modernization $3,135,933 01-8525 Exterior Painting $181,478 01-8552 Kindergarden Fencing $13,180 Install new backflow preventer.
More informationr.i.s.e demonstration center washington, dc project category: architecture
r.i.s.e demonstration center washington, dc project category: architecture R.I.S.E. Demonstration Center is the adaptive reuse of the historic Chapel at St. Elizabeths East Campus to create an interim
More informationBethlehem University 2008 Projects Summary
2008 Projects Summary 2008 Projects Summary In Addition to following up daily engineering related issues and supervising the Maintenance and Security Departments the University Engineer is involved in
More informationUniversity of Wisconsin - Whitewater Universal Design Guidelines
University of Wisconsin - Whitewater Universal Design Guidelines The purpose of these guidelines is to foster good design and discussion that fully encompasses the principals of Universal Design (UD) into
More informationMain Street Conversion Site
Main Street Conversion Site Borough of Brooklyn, New York Preliminary Presentation Park Expansion Design & Development Committee 13 September 2012 Michael Van Valkenburgh Associates, Inc. Landscape Architects,
More information2017 Design Awards. ASID Minnesota Chapter. SUBMISSIONS DUE (by Noon) AWARDS GALA MN.ASID.ORG. 1 of 21
2017 Design Awards ASID Minnesota Chapter SUBMISSIONS DUE 09.15.2017 (by Noon) AWARDS GALA 11.30.2017 MN.ASID.ORG 1 of 21 Please select the ONE category that best describes your project RESIDENTIAL SINGULAR
More informationAllisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767
Allisonville Elementary School Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 ADA improvements are Fire alarms need to be updated Playground equipment needs to be
More informationTIFT COUNTY SCHOOLS E-SPLOST HISTORY
TIFT COUNTY SCHOOLS E-SPLOST HISTORY July 1, 1997 June 30, 2002 $28,766,187.16 collected July 1, 2002 June 30, 2007 $39,025,830.10 collected July 1, 2007 June 30, 2012 $41,886,155.46 collected July 1,
More informationMUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY
MUKWONAGO SCHOOL DISTRICT ARCHITECTURE PARK VIEW MIDDLE SCHOOL The original school building was dedicated in 1954 as the High School, with an addition in 1959, a library addition in 1970, and an addition/renovation
More informationBluejack Builders Total House: $250,000-$500,000. St. Paul
Bluejack Builders Total House: $250,000-$500,000 St. Paul PROJECT DESCRIPTION: This house, despite being located in the charming St. Paul neighborhood of Highland Park, did not have a charming inside to
More informationWILLIAM & MARY CUSTODIAL TASK & FREQUENCY LIST. PUBLIC SPACE: ENTRANCES, LOBBIES, AND CORRIDORS Daily Weekly Monthly Quarterly Yearly
WILLIAM & MARY CUSTODIAL TASK & FREQUENCY LIST PUBLIC SPACE: ENTRANCES, LOBBIES, AND CORRIDORS Daily Weekly Monthly Quarterly Yearly Collect & properly dispose of recycling as needed Dust, or wipe all
More informationWold Architects and Engineers. 332 Minnesota Street Suite W2000 Saint Paul, MN
Wold Architects and Engineers 332 Minnesota Street Suite W2000 Saint Paul, MN 55101 651 227 7773 PLANNERS ARCHITECTS ENGINEERS ISD #15 St. Francis Area Schools East Bethel Elementary School Additions and
More informationOregon Non-Residential Building Energy Code
Oregon Non-Residential Building Energy Code Interior Connected Lighting Power Requirements The requirements for interior lighting power are one of the most important sections of the Oregon Energy Code.
More informationPort Lavaca Future Land Use
Port Lavaca Future Land Use Introduction The City of Port Lavaca is beginning to see sustained growth, after many years of relative stable population. New single family homes, apartments, and businesses
More informationCenter for Health Research and Rural Advocacy
CHRRA Angela Nudy Pennsylvania State University Lighting/Electrical Option Faculty Advisor: Dr. Mistrick Images Compliments of Ewing Cole Brief Overview Location: Geisinger Health System Campus in Danville,
More informationBURLEIGH MANOR MIDDLE SCHOOL HOWARD COUNTY PUBLIC SCHOOL SYSTEM
BURLEIGH MANOR MIDDLE SCHOOL HOWARD COUNTY PUBLIC SCHOOL SYSTEM Built in 1992 108, 407 Square Feet 771 Student Population 91 Staff Population 2 Building Supervisors, 3 Custodians 102, 663 Square Feet of
More informationSPACE TYPE: JUDICIAL CHAMBER
SPACE TYPE: JUDICIAL CHAMBER Construction Criteria The unit costs for Judicial Chamber space types are based on the construction quality and design features in the following table. This information has
More informationPLANNING COMMISSION AGENDA REPORT NOVEMBER 15, 2012
PLANNING COMMISSION AGENDA REPORT NOVEMBER 15, 2012 TO: FROM: Members of the Planning Commission Michael Klein, Associate Planner FILE NO.: 120000890 PROPOSAL: APPLICANT: Request for an Administrative
More informationATTACHMENT A - Services Specifications
ATTACHMENT A - Services Specifications Notes- Annual services to be performed prior to the start of the school year (June 15-Aug 1) Schedules for clearing must be approved by each building s chief administrator
More informationBoard of Directors Meeting Minutes October 1, 7:00 p.m. in the Lobby Hallway
Board of Directors Meeting Minutes October 1, 2018 @ 7:00 p.m. in the Lobby Hallway The meeting was called to order by George Herrera at 7:00PM. Board Members Present: Bob Bellantoni (President via phone),
More informationTERMS OF REFERENCE (as of 02 April 2018)
TERMS OF REFERENCE (as of 02 April 2018) I. PROJECT TITLE : IMEX Frankfurt 2018 II. JOB SPECIFICATION: Booth design, set up, maintenance and dismantling of Philippine Pavilion III. DATE : 15-17 May 2018
More informationDesign Review of Facility Improvement Projects
Design Review of Facility Improvement Projects Agenda Board Meeting Schedule Scope of Work Summary Overall Building Plans and Scope Summary Update on Areas of Design Development Programming and Space planning
More informationSOFIA UNIVERSITY AUDITORIUM CONCEPTUAL DESIGN 08/03/2013
SOFIA UNIVERSITY AUDITORIUM CONCEPTUAL DESIGN 08/03/2013 SCHEMATIC DESIGN Existing Floor Plan Areas to be Renovated SCHEMATIC DESIGN Existing Conditions Auditorium SCHEMATIC DESIGN Existing Conditions
More informationIchabod Crane Central School District 2018 Capital Project Preliminary Estimate
Health & Safety 1,399,000 Academics & Program 17,140,800 Physical Education & Athletics 5,922,000 Building Infrastructure 3,103,800 Site Infrastructure 1,049,600 TOTAL SCOPE OF WORK 28,615,200 PROPOSED
More informationG W C C GREENMOUNT WEST COMMUNITY CENTER GWCA - COMMUNITY CENTER. design recommendations
G W C C GREENMOUNT WEST COMMUNITY CENTER design recommendations GWCA - COMMUNITY CENTER PROGRAM SIDEWALK 1... ENTRANCE/EXIT A... MECHANICAL 2... LOBBY B... ELECTRICAL 1 3... RECEPTION C... MEN S TOILET
More informationRenovation Elements Landscaping Building Entries Signage and Identity Lobbies Lobby Seating Areas Elevators Restrooms. The Pyramids at College Park
Renovation Elements Landscaping uilding Entries Signage and Identity Lobbies Lobby Seating Areas Elevators Restrooms The Pyramids at ollege Park elevators stair The Pyramids at ollege Park F J G D Typical
More informationJANITORIAL SPECIFICATIONS
JANITORIAL SPECIFICATIONS A. Office Areas 1. Empty and wipe outside wastebaskets, replacing liners, if necessary. Remove to appropriate receptacle for disposal. All bins will be returned to their original
More informationCustodial. Customer Service. Guide. What We Clean & How Often We Clean It
Custodial Customer Service Guide What We Clean & How Often We Clean It Our Goal Our goal is to provide the students, faculty, staff, and guests of Shawnee State University a clean and healthy environment.
More informationElement C Interiors Interior Construction
Fittings and Interior PART 1 - GENERAL 1.01 OVERVIEW A. Includes marker and tack boards, lockers, storage shelving, handrails and wall protection, access doors, aquariums, fire extinguishers, and signage.
More informationMotor City Re-Store Design Guidelines
DESIGN GUIDELINES Table of Contents 1. Introduction 2. General 3. Signage 4. Awning and Canopies 5. Colors and Materials 6. Doors and Windows 7. Storefront Security 8. Exterior Lighting 9. Off-street Parking
More informationSagebrush Elementary School East Temple Place Aurora, Colorado 80015
Sagebrush Elementary School 14700 East Temple Place Aurora, Colorado 80015 Year Opened 1977 Current Square Footage 57,100 Site Acreage 7.66 sagebrush.cherrycreekschools.org Asphalt and concrete work; electrical
More informationEdith Wolford Elementary School Site Improvement Committee
Edith Wolford Elementary School Site Improvement Committee School Site Improvement Committee Members Bob Wedel Principal Robin Lowery Assistant Principal Toby Williams Building Manager Amalia De Ramon
More informationCampus Outdoor Lighting Plan
University of Oregon November 2004 Campus Planning Committee and Ad Hoc Committee on Campus Lighting I. Purpose: The purpose of this plan is to interpret and enhance the existing Long Range Campus Development
More informationAlbany Senior Center Remodel
Albany Senior Center Remodel Todd Jersey Architecture June 13, 2011 Todd Jersey Architecture Albany Senior Center Project Overview The main focus of the Albany Senior Center renovation is in the Lobby,
More informationDepth Work Part 1: Lighting Design
During the upcoming spring semester I will be investigating and redesigning some of the systems in Redifer Commons. This thesis study will be composed of three sections, which will all end up intertwining.
More informationFORT ERIE SECONDARY SCHOOL FACILITY INFORMATION. Lake Erie Corridor Secondary Schools Accommodation Review
FORT ERIE SECONDARY SCHOOL FACILITY INFORMATION Lake Erie Corridor Secondary Schools Accommodation Review November 2012 LAKE ERIE CORRIDOR SECONDARY SCHOOLS ACCOMMODATION REVIEW Fort Erie Secondary School
More informationWest Hartford Public School District
West Hartford Public School District Agenda Item: Adoption of Capital Improvement Plan for 2018-19 Meeting Date: February 6, 2018 From: Through: Andy Morrow, Assistant Superintendent for Administration
More informationTHEODORE ROOSEVELT SENIOR HIGH SCHOOL WASHINGTON,DC
THEODORE ROOSEVELT SENIOR HIGH SCHOOL WASHINGTON,DC PROJECT SUMMARY Project Name: Theodore Roosevelt Senior High School Modernization Client: DC Department of General Services Program: Roosevelt Senior
More informationSUBCHAPTER 4-B GUIDELINES FOR THE B-3 COMMERCIAL CHARACTER AREA
1 SUBCHAPTER 4-B GUIDELINES FOR THE B-3 COMMERCIAL CHARACTER AREA Downtown Bozeman should be the location of buildings of greatest height and intensity in the community. The following guidelines apply
More informationJohn Palmer Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationHOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District
HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the
More informationRETAIL DESIGN GUIDELINES
STOREFRONT MATERIALS LIGHTING STOREFRONT: EVOLVE YOUR SHOP TO DELIVER AN INNOVATIVE EXPERIENCE. Create a cohesive composition Height to match criteria for each zone An element of full height glazing is
More informationPROCEDURE: FURNITURE, ART, & DÉCOR STANDARDS & REQUESTS
Office of Planning, Design, and Construction 2500 North State Street Jackson, Mississippi 39216-4505 Phone (601) 984-1410 Date: July 7, 2017 PROCEDURE: FURNITURE, ART, & DÉCOR STANDARDS & REQUESTS 1.1
More informationCommunity Design Plan
Gardena General Plan 2006 Authority While the is not a required element of a General Plan, it is included because improving the community appearance and image is paramount to the overall quality of life
More informationAlessandro Volta Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationFacilities Management State-Funded and Billable Services
Facilities Management State-Funded and Billable Services Facilities Management receives funding to provide maintenance in eligible state-supported areas only, per UCOP guidelines. State-supported areas,
More informationEXISTING CONDITIONS SUMMARY
SITE Fire alarm system does meet current requirements Accessible path of travel lacking throughout campus Announcer s booth at Football Field booth not ADA compliant Covered and non covered outdoor eating
More informationSchool District of New London. Community Listening Session & Referendum Consideration
School District of New London Community Listening Session & Referendum Consideration 1 Why? Significant facility, maintenance, safety, energy efficiency needs Independent Facility Study identified millions
More information5 Year Capital Improvement Plan Update
5 Year Capital Improvement Plan Update Board Approved May 10, 2016 Collierville Schools Board of Education Wanda Chism Wright Cox Mark Hansen, Chairman Cathy Messerly Kevin Vaughan Superintendent John
More informationF & S Caretaking Department Design Standards For New or Renovated U of T Premises February 2015
F & S Caretaking Department Design Standards For New or Renovated U of T Premises February 2015 Caretaking Department Space Requirements: Caretaking Manager must sign off on Caretaking space allocations.
More informationH BUTCH BROWNING FIRE MARSHAL BUILDING REHABILITATION
STATE OF LOUISIANA Department of Public Safety and Corrections Office of State Fire Marshal Code Enforcement and Building Safety 8181 Independence Boulevard Baton Rouge, Louisiana 70806 225-925-4920 H
More information7/14/2016 CITY HALL ADA ENHANCEMENT/REMODEL ACTION PLAN 1978 Construction
CITY HALL ADA ENHANCEMENT/REMODEL 2016 ACTION PLAN 1978 Construction 1 HISTORY At the February 2, 2016 Council Workshop Council Motions included: The direction to staff to move forward with the City Hall
More informationMeasure W Review. East Nicolaus High School District March 9, 2017
Measure W Review East Nicolaus High School District March 9, 2017 To improve the quality of education with funding that cannot be taken by the State; repair or replace leaky roofs; modernize outdated classrooms,
More informationFacilities Management Services
Facilities Management Services Operating Budget Facilities Management (FM) receives an Operating Budget each year predicated on funding the routine, predictable costs of cleaning, maintaining,, and repairing,
More informationPreliminary Capital Fund Appeal Renovation Priorities
New York Avenue Presbyterian Church Vision 2020 Preliminary Capital Fund Appeal Renovation Priorities Dialogue Sessions Sunday, June 21 & Sunday, June 28 Following the Worship Service Please return the
More informationPalmyra High School 07/16 Addition and Renovation Palmyra, Nebraska
Palmyra High School 07/16 Addition and Renovation Palmyra, Nebraska 845-001-14 DOCUMENT 00 31 26 - EXISTING HAZARDOUS MATERIAL INFORMATION 1.1 EXISTING HAZARDOUS MATERIAL INFORMATION A. This Document with
More informationChurch Restoration & Renovations
Church Restoration & Renovations Whether you are looking to restore your church to her former glory, or renovating to add seating capacity, improve lighting and upgrade the chancel area, Artech Church
More informationSome Basics of School Library Design
Some Basics of School Library Design Fred Schlipf and Ann Ohms 2018 Pull functional requirements together and put them in print BEFORE building planning begins In addition to the various items listed below,
More informationimplementation r expression in landscape
6 ubc okanagan implementation campus plan r expression in landscape 68 6 implementation campus plan sections The Campus Plan supports the academic mission, values and commitments of the University by providing
More informationHawthorn Building. Penn State Altoona Campus Altoona, PA. Walter Nichols. Lighting/Electrical Option Faculty Advisor: Dr.
Hawthorn Building Penn State Altoona Campus Altoona, PA Walter Nichols Lighting/Electrical Option Faculty Advisor: Dr. Richard Mistrick 58,800 sq.ft. 2 Stories above grade Steel frame with curtain wall
More informationRequest for Proposals Design Services for Kitchen Remodel and Second Floor Layout
Request for Proposals Design Services for Kitchen Remodel and Second Floor Layout I. About the Agency StopWaste helps Alameda County s businesses, residents and schools waste less, recycle more and use
More informationPLATTEVILLE MIDDLE SCHOOL
Architectural The building has aluminum clad wood awning windows in combination with aluminum fixed glass units. They appear to be exterior glazed with insulated glazing. See photo 2. Platteville Middle
More informationHVAC / Boilers / Hot Water. Expected Life Span. very rough estimates Condition/Issue Age. Athletics / Gyms
$4,013,500.00 $4,013,500.00 $ 1,155,000.00 $ 1,000,000.00 $ 205,000.00 $ 275,000.00 $ 300,000.00 $ 360,000.00 $ 438,500.00 $ 280,000.00 School Status Item HS Boilers boiler controls replaced 2017 2002
More informationATLANTA-FULTON PUBLIC LIBRARY SYSTEM CENTRAL LIBRARY RENOVATION
ATLANTA-FULTON PUBLIC LIBRARY SYSTEM CENTRAL LIBRARY RENOVATION APRIL 11, 2018 VINES ARCHITECTURE AGENDA: CONCEPT DEVELOPMENT EXTERIOR PLAZA STRATEGY PLAN DISTRIBUTION CONCEPT DEVELOPMENT EMERGING PRINCIPLES
More informationSidney Sawyer Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationNUUC CONGREGATIONAL MEETING
NUUC CONGREGATIONAL MEETING MARCH 10, 2019 1. BUILDING PROPOSAL PRESENTATION INTRODUCTION DEE BURLISON BUDGET REVIEW BUILDING COMMITTEE REQUIREMENTS REVIEW BUILDING COMMITTEE WHAT OPTIONS WERE REVIEWED
More informationWATER WISE SURV EY. Santa Barbara City College
WATER WISE SURV EY FI N AL REPORT Santa Barbara City College August 21, 2013 Prepared By City of Santa Barbara Water Conservation Program WATER WISE SURVEY OF SANTA BARBARA CITY COLLEGE EXECUTIVE SUMMARY
More informationLEASIDE UNITED CHURCH FEASIBILITY STUDY TORONTO, ONTARIO
LEASIDE UNITED CHURCH FEASIBILITY STUDY TORONTO, ONTARIO Public Presentation October 21, 2018 11:30am Mission The Mission of Leaside United Church is to grow a caring and vibrant spiritual community that
More information2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect
1 Site Summary Address 7200 Bluff Springs Road Austin, TX 78744 Number of Permanent Campus Facilities 2 Original Year of Construction 2014 Total Campus Building Area (combined) 25,314 SF Introduction The
More informationPhilip A. Ginsburg, General Manager Toks Ajike, Acting Planning and Capital Program Director
Date: March 7, 2018 To: Through: From: Subject: Recreation and Park Commission Capital Committee Philip A. Ginsburg, General Manager Toks Ajike, Acting Planning and Capital Program Director Dan Mauer,
More informationInterior signs are an extension of the exterior sign system and their content and design should take this into consideration.
General Guideline The Interior Sign standard is developed to address the need for a cost effective, functional, flexible and serviceable sign system. The intent is to assure code compliance, consistency
More informationGreenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111
Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Year Opened 1958 Current Square Footage 50,504 Site Acreage 8.53 greenwood.cherrycreekschools.org $220,720 Electrical
More informationHonorable Mayor and Members of the City Council. Submitted by: Eric Angstadt, Director, Planning and Development
Office of the City Manager ACTION CALENDAR January 29, 2013 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Eric Angstadt, Director, Planning and
More information