1 Citizens Information Meeting Princess Anne Road Phase VII (CIP 2-195) Wednesday, May 5, :30 PM to 7:00 PM Red Mill Elementary School 1860 Sandbridge Road Virginia Beach, VA
2 Welcome to the Citizens Information Meeting for the Princess Anne Road Phase VII project. The purpose of this meeting is to provide the public with an opportunity to comment on the proposed roadway improvements associated with the Princess Anne Road improvements. Representatives from the City of Virginia Beach and the design consultant are present to answer your questions and discuss any concerns you may have. This is an informal meeting and questions and answers will be handled on an individual basis. We also encourage you to fill out one of the comment sheets provided and leave it in the comment box or mail it to the address on the back of this handout by May 15, Project Purpose and History The purpose of the project is to improve the traffic capacity of Princess Anne Road from General Booth Boulevard to Upton Drive, and to improve traffic circulation around existing and future commercial development in the area. Also, providing access to the new elementary school that is under construction is a key aspect of the project. Currently, several improvements are planned with this project in addition to Princess Anne Road, including: A second southbound left turn lane from General Booth Boulevard onto Princess Anne Road. Improvements to the existing traffic signal. A new access road will be constructed to provide connection to existing Princess Anne Road for access to Nimmo United Methodist Church and adjacent residences. A cul-de-sac will be provided on existing Princess Anne Road in the vicinity of the Wilson property. New turn lanes will be provided at the Newstead Drive intersection with Princess Anne Road. At Elson Green Avenue, turn lanes will be provided to the proposed Elson Green Avenue extension to Elementary School 2005, which is currently under construction. Turn lanes will also be provided to Elson Green Avenue heading north. Turn lanes will be provided at the intersection of Princess Anne Road and Upton Drive. Existing access points will be maintained at Painters Lane and the Food Lion Shopping Center. Additionally, the project contains significant drainage improvements to Princess Anne Road. The drainage improvements will be composed of a subsurface drainage system, filling in the existing roadside ditches along the entire length of Princess Anne Road, from General Booth Boulevard to Sandbridge Road, and will also include two stormwater management ponds. A stormwater management pond is proposed at the
3 western terminus of the project near the intersection of Princess Anne Road with General Booth Boulevard. A second stormwater management pond, a regional facility, will be constructed between the proposed Princess Anne Road and existing road adjacent to the future shopping center site, between Elson Green Avenue and Upton Drive. A drainage system extension will be required from this pond along Elson Green Avenue and will eventually connect to an existing system at Upton Drive. In addition to the drainage improvements, water line improvements will be included with this project. A proposed 10 water main extension from Mathews Green to Elson Green Avenue will be constructed with the Princess Anne Road improvements. Princess Anne Road at General Booth Boulevard looking east The proposed typical section of Princess Anne Road will consist of a four-lane divided highway from General Booth Boulevard to Sandbridge Road. The proposed improvements will continue along Sandbridge Road approximately 600 feet east of the Food Lion Shopping Center. Two eight-foot wide multi-use paths and extensive landscaping will also be provided along the corridor. Traffic Analysis The design consultant has conducted a traffic analysis that outlines the various anticipated impacts in the area of the project. This traffic analysis projects that over 29,000 vehicles per day by the design year of lane divided typical section Right-of-Way The proposed improvements will impact 15 properties. Two businesses and one residence will be displaced by the project. Additional temporary construction, utility and/or drainage easements may be required; the number and placement of these easements will be determined as the design progresses in the next phase. If right-of-way is required from your property, you will be contacted at a later date.
4 Preliminary Cost Summary The current estimated cost for construction of this project is approximately $6.2 million (year 2004 dollars), excluding right of way acquisition and private utility relocation. Project Schedule The following schedule is anticipated for the completion of this project: 35% Design Spring 2004* Citizen s Meeting Spring % Design Summer 2004 Begin Right-of-Way Acquisition Fall % Design Fall 2004 Construction Summer 2005 * Element completed Additional Information Written comments to be made part of the official record of the meeting should be submitted by May 15, Mail Ms. Dena Morgan, P.E. Senior Project Manager The City of Virginia Beach Department of Public Works 2405 Courthouse Drive Virginia Beach, Virginia Fax (757) comments@sandbridgestudy.com To review current brochure/comment sheet and graphics please visit our web site at Princess Anne Road at Elson Green Avenue looking east checkin /graphics/figures/handout-april04par.p65
5 Citizens Information Meeting/Comments Sheet Princess Anne Road Phase VII CIP Wednesday, May 5, 2004/Red Mill Elementary School Send comments by mail (see address on back), fax (757) , or no later than May 15, Attn: Ms. Dena Morgan, P.E., Public Works Name Address 1. Please provide us any information or comments that you feel will assist in developing the final design of the project. 2. If your property is shown to be impacted for the road right-of-way, do you have any questions or comments? 3. Has property access been properly addressed? 4. Please provide any other information that you feel will assist in developing the design of this project. 5. Do you feel the information was clearly presented at this meeting and do you understand the components of the improvements? 6. How did you hear about this meeting? mkgr sandbridge.survey.p65
6 Return Address Place Stamp Here Post Office Will Not Deliver Without Proper Postage Ms. Dena Morgan, P.E. Senior Project Manager Municipal Center - Building 2 - Public Works 2405 Courthouse Drive Virginia Beach, VA
Citizen Information Meeting
Prince William County Government Citizen Information Meeting Vint Hill Road Extension May 11, 2016 Benefits: Route 28 Corridor Improvement Program Estimated significant cost savings versus bidding these
More information14 October 10, 2012 Public Hearing APPLICANT: MPB, INC
14 October 10, 2012 Public Hearing APPLICANT: MPB, INC PROPERTY OWNER: MUNDEN & ASSOCIATES, LP STAFF PLANNER: Karen Prochilo REQUEST: Conditional Change of Zoning (AG-1 & AG-2 to Conditional O-2) ADDRESS
More informationProject Overview. Get Involved. Public Information Meeting. Contact Information
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationThe Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass
The Illinois Department of Transportation and Lake County Division of Transportation welcome you to this Public Hearing for U.S. Route 45 from Illinois Route 132 to Illinois Route 173, including the Millburn
More informationNorth Carolina Department of Transportation Project Development and Environmental Analysis Branch
North Carolina Department of Transportation Project Development and Environmental Analysis Branch Citizens Informational Workshop I-85, from I-485 to NC 73 Mecklenburg and Cabarrus Counties October 30,
More information8 February 9, 2011 Public Hearing APPLICANT: 7-ELEVEN, INC.
. 8 February 9, 2011 Public Hearing APPLICANT: REQUEST: Conditional Use Permit for an automobile service station with a convenience store ADDRESS / DESCRIPTION: 2448 Nimmo Parkway PROPERTY OWNER: COURTHOUSE
More informationPUBLIC HEARING. Thursday, December 14, 2017 FDOT Urban Office 2198 Edison Avenue Jacksonville, FL 32204
DISTRICT TWO PUBLIC HEARING I 10 (SR 8) from I 295 to I 95 Project Development & Environment Study Duval County, Florida Financial Project Number 213326 2 22 01 Efficient Transportation Decision Making
More informationProject Overview. Fairfax County Parkway Widening Fairfax County. Get Involved. Public Information Meeting. Contact Information
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationPublic Hearing. Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, open house at 4 p.m., formal presentation at 5 p.m.
Public Hearing Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, 2019 open house at 4 p.m., formal presentation at 5 p.m. Welcome to the Public Hearing for the Harborview Road (CR 776)
More informationIOWA HIGHWAY 57 / WEST 1 ST STREET STUDY PUBLIC INFORMATIONAL MEETING APRIL 22, 2014
IOWA HIGHWAY 57 / WEST 1 ST STREET STUDY PUBLIC INFORMATIONAL MEETING APRIL 22, 2014 INTRODUCTION The City of Cedar Falls and the Iowa Department of Transportation are conducting a Public Informational
More informationPROJECT BACKGROUND. Preliminary Design Scope and Tasks
PROJECT BACKGROUND Preliminary Design Scope and Tasks The purpose of this Study is the development of preliminary designs for intersection improvements for Trunk Highway (TH) 36 at the intersections of
More informationRequest Modification of Conditions (Automobile Service Station) Staff Recommendation Approval. Staff Planner Jimmy McNamara
Applicant Larae Tucker Property Owner Doswell Ventures, LLC Public Hearing May 10, 2017 City Council Election District Princess Anne Agenda Item 3 Request Modification of Conditions (Automobile Service
More information12 January 12, 2011 Public Hearing APPLICANT: TAILWIND DEVELOPMENT GROUP,LLC PROPERTY OWNER: CITY OF VIRGINIA BEACH
12 January 12, 2011 Public Hearing APPLICANT: TAILWIND DEVELOPMENT GROUP,LLC PROPERTY OWNER: CITY OF VIRGINIA BEACH STAFF PLANNER: Faith Christie REQUEST: Conditional Change of Zoning (from PD-H1 Planned
More informationQUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project
QUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project PROJECT OVERVIEW Windsor Woods, Princess Anne Plaza and The Lakes are neighborhoods located in what was once
More informationOpen House Public Involvement Meeting Howland High School Cafeteria, 200 Shaffer Drive NE, Warren, Ohio. Informational Handout
Open House Public Involvement Meeting Howland High School Cafeteria, 200 Shaffer Drive NE, Warren, Ohio SR 46 (Niles Cortland Road) and SR 82 Proposed Improvements Howland Township, Trumbull County, Ohio
More informationPennsy Greenway Trail
Town of Schererville Pennsy Greenway Trail DES. #s: 0401062, 1173595 & 1382661 Construction of Pennsy Greenway Trail beginning at Wilhelm Street and continuing northwest along the former Penn Central railroad
More informationMichael D, Harvey, Current Planning Supervisor. This project was originally approved in 2012 by the BOCC and is summarized as follows:
PLANNING & INSPECTIONS DEPARTMENT Craig N. Benedict, AICP, Director Current Planning (919) 245-2575 (919) 644-3002 (FAX) www.orangecountync.gov 131 W. Margaret Lane Suite 201 P. O. Box 8181 Hillsborough,
More informationBOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Endorsement of Design for Route 7/George Washington Boulevard Overpass. Algonkian and Broad Run
BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM Date of Meeting: March 7, 2017 # 14 SUBJECT: ELECTION DISTRICTS: CRITICAL ACTION DATE: STAFF CONTACTS: Endorsement of Design for Route 7/George Washington
More informationBurton Station Village Community Meeting February 26, 2014
February 26, 2014 SGA Plan Overview Recent announcements by the City of Norfolk regarding the closure of Lake Wright Golf Course and retail development proposals Update on infrastructure improvement plans
More information12 November 10, 2010 Public Hearing APPLICANT: CHUNMA TAE KWON DO
12 November 10, 2010 Public Hearing APPLICANT: CHUNMA TAE KWON DO PROPERTY OWNER: MOUNTAIN VENTURES VIRGINIA BEACH, LLC REQUEST: Conditional Use Permit (indoor recreational facility) STAFF PLANNER: Leslie
More informationDescriptive Summary of the Comprehensive Plan Amendment
Applicant City of Virginia Beach Public Hearing October 12, 2016 2016 Comprehensive Plan Amendment Establishing the Historic Seatack & Vicinity Suburban Focus Area (SFA) in Chapter 1, Section 1.3 Agenda
More informationQUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project
QUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project Project Overview... 2 Thalia Creek (Windsor Woods) Tide Gate... 6 Club House Road Drainage Project... 9 Updated
More information2 January 13, 2010 Public Hearing APPLICANT: AUTOBELL CAR WASH, INC
REQUEST: Conditional Use Permit (car wash) 2 January 13, 2010 Public Hearing APPLICANT: AUTOBELL CAR WASH, INC PROPERTY OWNER: MESSER 1060 INDEPENDENCE BOULEVARD STAFF PLANNER: Carolyn A.K. Smith ADDRESS
More informationCottage Grove Road Reconstruction. City of Madison Engineering
Public Informational Meeting Cottage Grove Road Reconstruction October 8, 2015 Presentation Outline Introduction Project Purpose & Need Proposed Design Overview Environmental Concerns Pedestrian Needs
More informationSECTION 4(f) DE MINIMIS DOCUMENTATION
SECTION 4(f) DE MINIMIS DOCUMENTATION Illinois Route 60/83 IL 176 to the intersection of IL 60 (Townline Road) Lake County P-91-084-07 Mundelein Park and Recreation District Project Limit SECTION 4(f)
More informationCity of Cornwall Municipal Class Environmental Assessment. Proposed Improvement and Extension of Lemay Street
Welcome City of Cornwall Municipal Class Environmental Assessment Proposed Improvement and Extension of Lemay Street Redevelopment and Design of the Municipal Works Yard Public Information Centre #1 Thursday,
More informationRequest Conditional Use Permit (Car Wash Facility) Staff Recommendation Approval. Staff Planner Jonathan Sanders
Applicant Property Owner SunTrust Bank Public Hearing October 10, 2018 City Council Election District Princess Anne Agenda Item 2 Request Conditional Use Permit (Car Wash Facility) Staff Recommendation
More informationDESIGN PUBLIC HEARING. Phase II
CITY OF SYRACUSE DEPARTMENT OF ENGINEERING STEPHANIE A. MINER, Mayor MARY E. ROBISON, City Engineer DESIGN PUBLIC HEARING Phase II City of Syracuse Onondaga County Tuesday, July 26, 2016 at 7:00 P.M. Southwest
More informationI. DESCRIPTION OF PROPOSED ACTION... 1 A. General Description... 1 B. Historical Resume and Project Status... 2 C. Cost Estimates...
PROJECT COMMITMENTS SUMMARY... S-1 1. Type of Action... S-1 2. Description of Action... S-1 3. Summary of Purpose and Need... S-1 4. Alternatives Considered... S-2 5. NCDOT Alternatives Carried Forward...
More informationPublic Open House. Welcome! Presentation at 5:15 p.m. Please sign-in at the registration table
Public Open House Welcome! Presentation at 5:15 p.m. Please sign-in at the registration table The Grand Avenue Extension Location and Environmental Study will determine the location of the extension of
More information7 February 9, 2011 Public Hearing APPLICANT: 7-ELEVEN, INC.
7 February 9, 2011 Public Hearing APPLICANT: PROPERTY OWNER: COURTHOUSE MARKETPLACE OUTPARCELS, L.L.C. STAFF PLANNER: Faith Christie REQUEST: Modification of Conditional Change of Zoning approved by the
More informationARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25)
ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25) Preliminary Design Report February 2015 Prepared For: City of Inver Grove Heights Dakota County Prepared By: Kimley-Horn and Associates,
More informationPARISH OF ASCENSION OFFICE OF PLANNING AND DEVELOPMENT PLANNING DEPARTMENT. Joint Planning and Zoning Meeting
1. Call To Order 2. Roll Call of Members 3. Chairman's Comments PARISH OF ASCENSION OFFICE OF PLANNING AND DEVELOPMENT PLANNING DEPARTMENT Joint Planning and Zoning Meeting January 11, 2017 6:00 PM Courthouse
More informationSR-2 Freeway Terminus Improvement Project
SR-2 Freeway Terminus Improvement Project Welcome! Public Hearing, Mayberry Elementary June 16, 2009, 6:30 p.m. 8:30 p.m. Agenda 6:30 PM 6:50 PM Registration and Open House 6:50 PM 7:00 PM Welcome and
More informationWelcome. Date: Thursday March 2, 2017 Time: 6:30 p.m. 9:00 p.m. Location: Woodview School Gym, 69 Flatt Road, Burlington Presentation Time: 7:00 p.m.
Welcome Public Information Centre No.2 City of Burlington, City of Hamilton, Region of Halton Waterdown Road Widening Detailed Design Craven Avenue to Mountain Brow Road Date: Thursday March 2, 2017 Time:
More informationScope of Services. River Oaks Boulevard (SH 183) Corridor Master Plan
Scope of Services River Oaks Boulevard (SH 183) Corridor Master Plan PROJECT AREA The project area consists of the River Oaks Boulevard (SH 183) corridor bounded by SH 199 at the northern end and the Trinity
More informationD1 September 11, 2013 Public Hearing APPLICANT:
D1 September 11, 2013 Public Hearing APPLICANT: BEACH MUNICIPAL FEDERAL CREDIT UNION PROPERTY OWNER: SISTERS II, LLC STAFF PLANNER: Karen Prochilo REQUEST: Conditional Change of Zoning (AG-2 Agriculture
More informationAlternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below:
Race Road/Jessup Village Planning Study (H550601) Project Newsletter Spring 2015 Project Description The Study Team, consisting of staff from Anne Arundel County (Department of Public Works and Department
More informationAsbury Chapel Subdivision Sketch Plan
Asbury Chapel Subdivision Sketch Plan PART 1: PROJECT SUMMARY Applicant: NVR Inc. Project Size: +/- 76.13 acres Parcel Numbers: 02101112,02116101,02116112, 02116113 Current Zoning: Transitional Residential
More informationDRAFT SECTION 4(f) EVALUATION INTERSTATE 73 FEIS: I-95 to I-73/I-74 in North Carolina
DRAFT SECTION 4(f) EVALUATION INTERSTATE 73 FEIS: I-95 to I-73/I-74 in North Carolina 1.0 INTRODUCTION Section 4(f) of the Department of Transportation Act of 1966, 49 U.S.C. 303, requires that prior to
More informationD2 April 10, 2013 Public Hearing APPLICANT:
D2 April 10, 2013 Public Hearing APPLICANT: ARMADA HOFFLER DEVELOPMENT COMPANY, LLC PROPERTY OWNER: DAVID B. HILL, JR., LUKE H. HILL, AND SUSIE WOOD HILL STAFF PLANNER: Faith Christie REQUEST: Conditional
More informationBostwick Road. Municipal Class Environmental Assessment. Public Information Centre #2 June 14, City of London
Bostwick Road Municipal Class Environmental Assessment Public Information Centre #2 June 14, 2017 Welcome! Welcome to the 2 nd Public Information Centre for the. Representatives from the and the consulting
More informationSH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017
Community Meeting No. 2 May 31, 2017 Transportation Projects On or Near SH 199 SH 199 from 0.3 miles south of FM 1886 to south end of Lake Worth bridge Construct freeway mainlanes and frontage roads 10-Year
More informationPROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING. 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S.
PROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S. 67 HEARING LOCATION: ERICKSEN COMMUNITY CENTER 1401 11 TH AVENUE NORTH
More informationPREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY
PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY SEPTEMBER 2016 Introduction The Platteview Road Corridor Study was led by the Metropolitan Area Planning Agency (MAPA) with assistance from
More information3 November 10, 2010 Public Hearing APPLICANT AND PROPERTY OWNER :
3 November 10, 2010 Public Hearing APPLICANT AND PROPERTY OWNER : TRUSTEES OF ST. ANDREWS UNITED METHODIST CHURCH STAFF PLANNER: Faith Christie REQUEST: Modification of a Conditional Use Permit for a church
More informationPRELIMINARY REPORT. HIGHWAY 18 CORRIDOR NEIGHBORHOOD PLAN VILLAGE OF DOUSMAN November, 2014
PRELIMINARY REPORT HIGHWAY 18 CORRIDOR NEIGHBORHOOD PLAN VILLAGE OF DOUSMAN November, 2014 This preliminary report presents the initial recommendations for land use within the Highway 18 corridor along
More informationPublic Meeting. US Highway 14 (6TH Street) from Main Ave to Medary Ave Urban Reconstruction Project Brookings, SD P-PH 0014(179)419 PCN 027B
Public Meeting US Highway 14 (6TH Street) from Main Ave to Medary Ave Urban Reconstruction Project Brookings, SD P-PH 0014(179)419 PCN 027B Mark Leiferman Chief Road Design Engineer April 28, 2014 Why
More informationDevelopment of land adjacent to Braggs Farm Lane and Rumbush Lane, Dickens Heath. Welcome. Today s exhibition. The proposal site
Welcome Welcome to this event to discuss the development of land adjacent to Braggs Farm Lane. is currently in the preliminary stages of designing proposals to sensitively develop this site with high-quality
More informationREQUEST FOR COUNCIL ACTION 6A AGENDA ITEM ORIGINATING DEPT. AGENDA ITEM CITY ADMINISTRATOR APPROVAL
DATE REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM ORIGINATING DEPT. AGENDA ITEM CITY ADMINISTRATOR APPROVAL Community Development Territorial Greens PUD Concept Plan Development Stage Plan Subdivision (Preliminary
More informationPreserving Green Streetscape Character on Hillside Drive
STAFF REPORT ACTION REQUIRED Preserving Green Streetscape Character on Hillside Drive Date: February 19, 2014 To: From: Toronto and East York Community Council Deputy City Manager, Cluster B Wards: Toronto-Danforth,
More informationDESIGN PUBLIC HEARING APRIL 24, 2018 MUNICIPAL OFFICE BUILDING HARDWICK, MASSACHUSETTS 7:00 PM FOR THE PROPOSED
DESIGN PUBLIC HEARING APRIL 24, 2018 AT MUNICIPAL OFFICE BUILDING HARDWICK, MASSACHUSETTS 7:00 PM FOR THE PROPOSED ROUTE 32/32A GILBERTVILLE VILLAGE RECONSTRUCTION PROJECT Roadway Project Management Section
More informationWelcome. Northern Segment of Hwy 100 I-90 to South of Madison Street Meeting Goals:
Welcome Northern Segment of Hwy 100 I-90 to South of Madison Street Meeting Goals: - Review Environmental Assessment - Share Preferred Alternative -Receive Public Comments 2003 EA Preferred Alternative
More informationCenterville SGA. virginia beach, va. Prepared for the City of Virginia Beach February,
Centerville SGA virginia beach, va Phase 3 presentation Prepared for the City of 12-13 February, 2013 www.vbgov.com/centervilleplan urban design associates miles agency, rclco, urs, vhb & wpl A Three Phase
More informationWEST HILL BUSINESS PARK AREA STRUCTURE PLAN
MUNICIPAL DISTRICT OF PEACE NO. 135 WEST HILL BUSINESS PARK AREA STRUCTURE PLAN Prepared by: TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Purpose of Plan........ 1 1.2 Plan Area..... 1 1.3 Existing Conditions...
More informationUS 95 Phase 2B/5 Open House
US 95 Phase 2B/5 Open House www.us95nw.com Wednesday, Mountain Crest Community Center 4701 N Durango Drive Las Vegas, NV 89129 Brian Sandoval Governor Rudy Malfabon Director Nevada Department of Transportation
More informationProject Purpose. Project Need
Project Purpose The purpose of the project is to implement a bridge improvement solution that corrects the existing safety problem at the Strasburg Pike Bridge. The project will provide a structurally
More informationREQUEST: Conditional Change of Zoning (AG-1, B-1,R-15 to Conditional R-7.5)
REQUEST: Conditional Change of Zoning (AG-1, B-1,R-15 to Conditional R-7.5) 26 March 14, 2012 Public Hearing APPLICANT: KROLL ENTERPRISES, INC. PROPERTY OWNER: N&K PROPERTIES, LLC/B&W DEVELOPMENT LLC STAFF
More informationOP Council Resolution June 16, Planning and Development Services
OP-08-01 Council Resolution June 16, 2008 Planning and Development Services Kingsgate Landing Outline Plan Table of Contents 1.0 Introduction 1 1.1 Purpose of Plan 1 1.2 Plan Area Location 1 1.3 Ownership
More informationFairfax County Parkway (Route 286) Widening Project
Fairfax County Parkway (Route 286) Widening Project Route 29 (Lee Highway) to Route 123 (Ox Road) State Project No. 0286-029-259, P101; UPC 107937 Fairfax Station HOA Meeting January 30, 2018 7:00 to 9:00
More informationOVERMOUNTAIN VICTORY TRAIL BURKE CALDELL CORRIDOR FEASIBLITY STUDY REQUEST FOR QUALIFICATIONS CALDWELL COUNTY PATHWAYS
OVERMOUNTAIN VICTORY TRAIL BURKE CALDELL CORRIDOR FEASIBLITY STUDY REQUEST FOR QUALIFICATIONS CALDWELL COUNTY PATHWAYS Caldwell County Pathways along with our co-partners City of Lenoir, Town of Gamewell,
More informationDESIGN & GREEN INFRASTRUCTURE UPDATE December 13, 2016
DESIGN & GREEN INFRASTRUCTURE UPDATE December 13, 2016 Welcome & Introduction Michael J. Finn, P.E. City Engineer Summary of Public Outreach to Date Ground the work in established principles December 2015
More informationMavis Road Class Environmental Assessment
Mavis Road Class Environmental Assessment Public Information Centre #2 Wednesday November 9, 2016 6:00 to 8:00 p.m. Please sign in and complete a comment sheet Review the displays on your own or join in
More information2040 Long Range Transportation Plan
2040 Long Range Transportation Plan Adopted: April 15, 2013 APPENDIX D HIGHWAY NEEDS PLAN PROJECTS FREDERICKSBURG Existing and Committed Projects Fall Hill Avenue/Mary Washington Blvd. (Fredericksburg)
More information12 February 9, 2011 Public Hearing APPLICANT: WILDLIFE RESPONSE, INC.
12 February 9, 2011 Public Hearing APPLICANT: WILDLIFE RESPONSE, INC. PROPERTY OWNER: CITY OF VIRGINIA BEACH REQUEST: Conditional Use Permit (Wildlife Rehabilitation Center) STAFF PLANNER: Karen Prochilo
More informationINDEX EXECUTIVE SUMMARY...1 BASIC INFORMATION AND PROCEDURES...3 EXISTING CONDITIONS EXISTING UTILITIES
INDEX EXECUTIVE SUMMARY...1 INTRODUCTION...2 BASIC INFORMATION AND PROCEDURES...3 EXISTING CONDITIONS... 4-5 EXISTING UTILITIES... 6-7 MEDIAN BREAKS AND TURN LANE STORAGE REQUIREMENTS...8 PRELIMINARY DESIGN
More informationWELCOME 50 street cp rail grade separation + road widening. public information session #1 June 26, pm to 8 pm
WELCOME 50 street cp rail grade separation + road widening public information session #1 June 26, 2018 5 pm to 8 pm session purpose To provide residents, businesses, and users of 50 Street with the opportunity
More information10 October 14, 2015 Public Hearing
10 October 14, 2015 Public Hearing APPLICANT: PROPERTY OWNER: VIRGINIA BEACH BEACON BAPTIST CHURCH STAFF PLANNER: Stephen J. White REQUESTS: A. Change of Zoning (R-20 Residential District to Conditional
More informationRequest Conditional Rezoning (R-15 Residential to Conditional A-24 Apartment) Staff Recommendation Approval. Staff Planner Jimmy McNamara
Applicant Franklin Johnston Group Management & Development, LLC Property Owner Virginia Wesleyan College Public Hearing July 12, 2017 City Council Election District Bayside Agenda Item 3 Request Conditional
More informationCourthouse Planning Area
Courthouse Planning Area Current Reality The Courthouse Planning Area is the characterized by expansive suburbanscale residential areas as well as the community resource planned area of athletic, educational,
More information2 August 14, 2013 Public Hearing APPLICANT: CRESCENT COMMUNITY CENTER CORP. PROPERTY OWNER: S. L. ETHERIDGE, LLC
2 August 14, 2013 Public Hearing APPLICANT: CRESCENT COMMUNITY CENTER CORP. PROPERTY OWNER: S. L. ETHERIDGE, LLC REQUEST: Conditional Use Permit (religious use) STAFF PLANNER: Karen Prochilo ADDRESS /
More informationA PPEARANCE REVIEW BOARD
Staff Comments A PPEARANCE REVIEW BOARD NOVEMBER 19, 2015 Case Number A GENDA ITEM 1 455 N. GARLAND AVE. LYNX GERTRUDE S WALK EXTENSION ARB2015-00070 Applicant Laura Minns, AICP LYNX Property Location
More informationLong Branch-Wayne Local Park Renovation Project
Montgomery Parks Long Branch-Wayne Local Park Renovation Project Community Meeting #2 September 20, 2016 Oak View Elementary School 7:00-9:00 PM Welcome / Team Introductions M-NCPPC (Montgomery Parks)
More informationWELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A
WELCOME! 168 TH STREET IMPROVEMENTS 6:30 Open House 7 8 Presentation & Q&A 8 8:30 Open House WELCOME Todd Pfitzer City of Omaha Engineer Bob Stubbe City of Omaha Public Works Director Jon Meyer Project
More informationBostwick Road. Municipal Class Environmental Assessment. October 13, City of London. Bostwick Road Municipal Class Environmental Assessment
Bostwick Road Municipal Class Environmental Assessment October 13, 2016 Welcome! Welcome to the first Public Information Centre for the Bostwick Road Municipal Class Environmental Assessment. Representatives
More informationHighway 427 Industrial Secondary Plan Area 47 Schedule C Class Environmental Assessment For Arterial Roadways
Welcome to Pubic Information Centre #1 Highway 427 Industrial Secondary Plan Area 47 Schedule C Class Environmental Assessment For Arterial Roadways Welcome to Open House # 1 Tonight, we invite you to.
More information8 October 14, 2015 Public Hearing
8 October 14, 2015 Public Hearing APPLICANT & PROPERTY OWNER: PRICE S HOLDINGS, LLC STAFF PLANNER: Karen Lasley REQUEST: A. Conditional Use Permit (Automobile Repair Garage) B. Change in Nonconforming
More informationARLINGTON COUNTY, VIRGINIA
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of September 19, 2015 DATE: September 11, 2015 SUBJECTS: Outdoor Café at Citizen Burger Bar A. SP# 418 Site Plan Amendment to modify an approved
More informationLOCATION AND DESIGN DIVISION
VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Landscape Architecture Program NUMBER: SPECIFIC SUBJECT: Integration of Landscape
More informationOPEN HOUSE. Sunnyside Avenue Traffic Calming & Green Street Treatments. February 19, 2014
OPEN HOUSE Sunnyside Avenue Traffic Calming & Green Street Treatments Aquafor Beech 2010 Aquafor Beech 2010 February 19, 2014 1 Welcome The Old Ottawa South Area Traffic Management (ATM) Study, completed
More informationKick-off Meeting. FM No: ETDM No: 14050
Kick-off Meeting FM No: 433511-1-22-01 ETDM No: 14050 June 26, 2014 FM No. 433511 1 22 01 Project Location 2 Project Purpose and Need Improve traffic operations and safety conditions at the intersections
More informationCITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA
CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA Agenda Date: December 16, 2013 Action Required: Adoption of Resolution Presenter: Staff Contacts: Title: James E. Tolbert, AICP, Director of NDS James
More informationPublic Information Centre #1
and Highway 401 Interchange Improvements WELCOME Public Information Centre #1 Veterans Memorial Parkway Extension and Highway 401 Interchange Improvements Study May 23, 2012 4 p.m. to 7 p.m. Brief Overview
More informationI-494 Rehabilitation Project SP (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination
I-494 Rehabilitation Project SP 2785-330 (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination State Project Number 2785-330 Federal Project No. NHPP-I494 (002) Trunk Highway:
More information6:00 8:00 PM I-95 FROM EXIT 57 TO EXIT 60 PROJECT
PUBLIC INFORMATIONAL MEETING TUESDAY, APRIL 27, 2010 AT NEWBURYPORT CITY HALL, AUDITORIUM 60 PLEASANT STREET NEWBURYPORT, MASSACHUSETTS 6:00 8:00 PM FOR THE PROPOSED WHITTIER BRIDGE / I-95 IMPROVEMENTS
More informationHunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL
Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL Agenda Design Concept Report Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Questions Design Concept Report
More informationENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville. Environmental Screening Report
Page 1 of 18 ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville Environmental Screening Report July 2011 Page 2 of 18 Table of Contents 1.0 INTRODUCTION
More informationWELCOME TO OPEN HOUSE TWO November 28, 2018
Langstaff Road Weston Road to Highway 7 Class Environmental Assessment Study WELCOME TO OPEN HOUSE TWO November 28, 2018 Please sign in and join our mailing list Study Overview York Region is conducting
More informationALTERNATIVES. NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives).
III. ALTERNATIVES A. CONSTRUCTION METHOD ALTERNATIVES NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives). One of the
More informationBexar County Public Works Department Flood Control Program
Bexar County Public Works Department Flood Control Program Bulverde Rd. at Mud Creek Trib. A (SC-27) February 23 rd, 2016 Agenda Introductions Bexar County Flood Control (Engineering and PR) Office of
More informationDESIGN PUBLIC HEARING MAY 10, 2018 GRANBY TOWN HALL FIRST FLOOR CONFERENCE ROOM 10 WEST STATE STREET GRANBY, MASSACHUSETTS 7:00 PM FOR THE PROPOSED
DESIGN PUBLIC HEARING MAY 10, 2018 AT GRANBY TOWN HALL FIRST FLOOR CONFERENCE ROOM 10 WEST STATE STREET GRANBY, MASSACHUSETTS 7:00 PM FOR THE PROPOSED Reconstruction of Granby Road/West State Street (Route
More informationSt. Clair Avenue West Area Transportation Master Plan
1 (Between Keele Street and Old Weston Road) Public Information Centre 1 December 2, 2015 2 Welcome Welcome to the first Public Information Centre for the St. Clair Avenue West Area. The panels will present
More informationAnderson Memorial Bridge Rehabilitation Project Boston/Cambridge
Anderson Memorial Bridge Rehabilitation Project Boston/Cambridge MEPA Meeting, EEA#14702 Wednesday, March 2, 2011 6:30 PM Dr. Martin Luther King, Jr. School 100 Putnam Avenue, Cambridge, MA Rendering by:
More informationHeritage Road Improvements from Steeles Avenue to Rivermont Road
The Corporation of the City of Brampton Heritage Road Improvements from Steeles Avenue to Rivermont Road Class Environmental Assessment Study (Schedule C) September 19, 2013 The Corporation of the City
More informationHighway 15 Project - Hutchinson
Highway 15 Project - Hutchinson Agenda What are we going to talk about today? Goals and benefits of the project Details about the proposed work Project schedule and costs Any questions you may have about
More informationCapital Projects in and near Odenton Town Center
Capital Projects in and near Odenton Town Center Map ID Anne Arundel County Department of Public Works This project provides for the design, right of way acquisition, and construction of approximately
More information7 June 13, 2012 Public Hearing
7 June 13, 2012 Public Hearing REQUEST: Conditional Use Permit (Childcare) APPLICANT: BASILEIA EMPOWERING MINISTRIES PROPERTY OWNER: CONNEMARA ASSOCIATES, LLC STAFF PLANNER: Faith Christie ADDRESS / DESCRIPTION:
More informationOverall Map. Chicago. St. Louis. Summit. Joliet. Dwight. Pontiac. Bloomington-Normal Lincoln. Springfield. Carlinville. Alton EXPERIENCE IT YOURSELF.
Overall Map Summit Chicago Bloomington-Normal Lincoln New Station Planned New Station Planned Dwight Pontiac Joliet Pedestrian overpass and second platform planned Higher speed service began in this section
More informationRight-of-Way Acquisitions and Relocations Technical Memorandum
Right-of-Way Acquisitions and Relocations Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional
More informationStrachan Ave. Overpass Community Design Update. October 26, 2010 Stephen Lipkus Executive Director Georgetown South Project GO Transit
Strachan Ave. Overpass Community Design Update October 26, 2010 Stephen Lipkus Executive Director Georgetown South Project GO Transit Welcome Program Overview 6:30 8:30 p.m.: Storyboard Review Project