1 Parks Master Plan Interim Presentation: Long Range Vision August 3, 2016

2 Presentation Outline 1. Overview, Schedule, Needs Assessment Summary 2. Long Range Vision 3. Next Steps 4. Questions, Discussion

3 Purpose of Parks Master Plan City of Cape Coral, Request for Proposals Parks Master Plan Update (RFP-DCD15-28/CH) 1.Identify issues, needs, and opportunities of the City s Parks System for the revision of the Parks Master Plan; 2.Ensure adequate growth of the Cape Coral Parks System; 3.Modernization of the level of service (LOS) standards in the Comprehensive Plan; 4.Continual funding opportunities for the parks system; 5.Provide planning actions and acquisition needs for the Parks and Recreation Department through build out (2060).

4 Project Schedule Project Tasks Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Phase 1 Existing Conditions Analysis Phase 2 Needs + Priorities Assessment Phase 3 Visioning Phase 4 - Implementation Strategy Phase 5 Parks Master Plan Document Task Time Period Survey Public Engagement Stakeholder Committee + Council Presentations

5 Existing Conditions Analysis, Needs + Priorities Assessment Stakeholder Committee Workshop Public Outreach Meetings One-on-One Interviews Focus Group Meetings Lifestyle Analysis Qualitative Defensible + Identified Needs Observations Park Visits, Ecological Assessment Existing Plans Review Quantitative National +Regional + Local Trends Population + Demographic Analysis Level of Service Analysis Statistically Valid Mail Survey Online Survey PRORAGIS Benchmarking

6 Facilities Summary of Findings - Facilities Statistically Valid Survey Needs Assessment Techniques Public Outreach Meetings Interviews Focus Group Meetings On-Line Survey LOS Analysis Site Evaluations High Priority Needs Medium Priority Needs Lower Priority Needs Other Needs Beach X X X X Small neighborhood parks X X X Nature parks X X X Indoor fitness/cardiovascular equipment X X Large community parks X X X Trails X X X X X X Indoor running/walking track X X Fishing areas X X X Yacht club X X Boating/kayaking areas X X X X X Waterpark X X Dog Park X X Theater X X Golf Course X X X Art studio X X Central gathering place X X Gymnasium X X X Environmental Center X X X Historical Museum X X Baseball/softball fields/complex X X X Youth center X X Pickleball courts X X X X X Soccer fields X X Skate park X X Football Fields X X X Improvements to Existing Parks X X X X Festival Park/Amphitheater X X New Indoor Community Center X X Tennis Courts/Complex X Football/Soccer/Lacrosse Complex X

7 Summary of Findings - Programs Needs Assessment Techniques Programs Statistically Valid Survey Public Outreach Meetings Interviews Focus Group Meetings Special events (concerts, movies, etc.) X X X On-Line Survey High Priority Needs Adult fitness and wellness programs X X X Adult programs for 50 years and older X X X X Adult continuing education programs X X Medium Priority Needs Nature programs/environmental education X X X Water fitness programs X Adult sports programs X Sailing/boating programs X X Adult art, dance, performing arts X X Golf lessons and leagues X Youth learn to swim programs X X Programs for teens X X Youth art, dance, performing arts X Youth sports programs X Travel programs X X Tennis lessons and leagues X Other Needs Youth fitness and wellness programs Before and after school programs Programs for people with disabilities Preschool programs X X X X

8 Comparison of Top Priority Needs Per Quadrant

9 Inventory 43 parks and recreation facilities, 833 acres Preserve, 356 acres (Four-mile Cove) Athletic fields, 170 acres Specialty parks (BMX, Seahawk, etc.), 79 acres 74% of park land is restricted or specialized

10 Presentation Outline 1. Overview, Schedule, Needs Assessment Summary 2. Long Range Vision 3. Next Steps 4. Questions, Discussion

11 Visioning Workshop, May 4-5 May 4, 2016 Overview of Needs Assessment Findings, Alternative Service Delivery Models Subsystem 1 New Neighborhood and Community Parks, Nature Parks Subsystem 2 Amenities and Improvements to Existing Parks, including Pickleball, Fitness and Cardio Equipment May 5, 2016 Subsystem 3 Beach and Water Access (Kayaking, Boating) Subsystem 4 - Centralized Venues: Festival Park/ Amphitheater, Community Centers, Aquatics Center, Sports Complexes, Golf Course, Tennis Complex Subsystem 5 Centralized Venues: Renovated Yacht Club/ Waterfront, Cultural Center/Museum Subsystem 6 Programs: Special Events, Adult Fitness and Wellness, 50+ Subsystem 7 Trails and Bikeways

12 Service Delivery Models Decentralized Model: Neighborhood, Community, and Nature Parks Beach and Water Access Centralized Model: Specialized Venues (e.g. Yacht Club, Cultural Park, and Sports Complex)

13 6 Key Strategies Improve Access Create Great Places Acquire Land Maximize Resources Plan and Design Brand the Cape

14 Subsystem 1: Neighborhood, Community, and Nature Parks Existing Classification System: Special Neighborhood Community Regional Proposed: Neighborhood Parks Small, Large Community Parks Nature Parks

15 Neighborhood Parks Meet residents basic recreation, fitness, and social needs - in a warm, inviting, environment within a walking or bicycling distance (1 2 miles) from their homes 5-10 acres Basic Amenities (e.g. Joe Stonis Park): 8 wide, paved, multi-purpose path Shaded playground Shade trees Small group picnic pavilion(s) for family gatherings, birthday parties, family reunions, etc. Picnic tables, site furnishings Multi-purpose lawn areas for pick-up games, special events Restrooms

16 Small Community Parks Purpose: Meet needs of surrounding neighborhoods + plus additional facilities such as: Tennis courts Pickleball courts Athletic fields Other amenities desired by residents such as concessions, trails, and canoe/kayak access. Ideally, located within 3 miles of every resident. Several of the City s single-dimensional athletics complexes have the potential to become Small Community Parks by adding additional facilities and amenities.

17 Purpose: Large, multi-purpose parks that offer something for everyone. Large Community Parks In addition to the facilities and amenities provided by the Neighborhood and Small Community Parks, Large Community Parks may also provide: Natural areas Food truck staging areas Dog parks Outdoor cafes Skate parks Tennis or pickleball complexes Trails system Moveable outdoor seating and hammocks Equipment rentals for bicycles, kayaks, paddleboards, fishing rods, and/or other recreation equipment Anchored by +/- 50,000 sf Indoor Recreation Centers

18 1. Existing Community Parks LOS

19 2. Existing Community Parks LOS w/ Canal Bridges

20 3. Existing & Proposed Community Parks LOS

21 4. Existing & Proposed Community Parks LOS w/ Canal Bridges

22 5. Existing Neighborhood Parks LOS

23 6. Existing Neighborhood & Community Parks LOS

24 7. Existing Neighborhood & Community Parks LOS w/ Canal Bridges

25 8. Existing Neighborhood Parks & Existing & Proposed Community Parks LOS

26 9. Existing Neighborhood Parks & Existing & Proposed Community Parks LOS w/ Canal Bridges

27 10. Existing Neighborhood Parks & Existing & Proposed Community Parks & Proposed Park Improvements LOS

28 11. Existing Neighborhood Parks & Existing & Proposed Community Parks & Proposed Park Improvements & School Sites LOS

29 12. Existing Neighborhood Parks & Existing & Proposed Community Parks & Proposed Park Improvements & School Sites & Proposed Neighborhood Parks LOS

30 13. Private HOA Parks Quadran # of Units Clubhouse Rec Ctr Project Master Planned Community t (@buildout) ft² Acreage Other Amenities Bella Vida NE 469 (70% built) soccer field, softball field, tot lot¹ Cape Harbour (SingFam + coach home sec) SW 274 (90%+ built) N/A N/A Coral Lakes NE swimming pool, volleyball court, playground² Emerald Cove SW 101 (built-out) N/A³ approx 40 swimming pool² Heatherwood Lakes SW 159¹ (b-o)? swimming pool² La Vida NW 12 (50% built) N/A N/A Sandoval SW 1,081 SF, 488 MF 5, swimming pool, volleyball court, playground, 4 tennis courts, basketball court, bocchi courts² Tarpon Pointe SW 47 SF, 929 MF swimming pools, 2 tennis courts, 2 bocchi courts, 2 shuffleboard courts² Trafalgar Woods SW 49 (b-o) N/A one tennis court² West Cape Estates NW 27 (40% built) N/A one tennis court²

31 14. Nature Parks

32 Existing Level-of-Service (LOS) - Acreage 2014 Population Estimates 169,854 City Build-Out Population 400,000 Park Acreage Calculation City of Cape Coral Comprehensive Plan Acreage LOS Target Acreage 2014 Target Acreage Acreage Need / Surplus City Build- Out Target Acreage Acreage Need / Surplus Total Park Acreage , (614) 3, (2,570) Regional Park (314) 1, (1,235) Community Park Neighborhood Park (281) (741) (280) (740) Specialty Park

33 Existing LOS Acreage (NRPA PRORAGIS Benchmarking) City of Cape Coral National Acreage LOS Median for Agencies with Population Density s between 500 to 1,500 per Square Mile (Acres per 1,000 population) Acreage LOS Target (Acres per 1,000 population) 2014 Acreage LOS (Acres per 1,000 population) City Build-Out Acreage LOS (Acres per 1,000 population)

34 Proposed LOS Acreage (NRPA PRORAGIS Benchmarking) City of Cape Coral National Acreage LOS Median for Agencies with Population Density s between 500 to 1,500 per Square Mile (Acres per 1,000 population) Acreage LOS Target (Acres per 1,000 population) 2014 Acreage LOS (Acres per 1,000 population) City Build-Out Acreage LOS (Acres per 1,000 population) acres City-owned Land + 66 acres Privately-owned Land = 172 acres 5.9

35 Subsystem 2: Additional Amenities to Existing Parks Outdoor fitness equipment Spray pads Multi-purpose tennis/ pickleball courts Multi-purpose basketball courts Dog friendly (on-leash) incl. dog drinking fountains, poop stations Shuffleboard, horseshoes, and/or other games Equipment storage Fire pit(s), grills Wi-fi Canoe/ kayak access Shade trees Native plantings, butterfly gardens Hammocks Adirondack chairs Performers Amphitheater Ramps and rails Cafes Transit stops Stages, amphitheaters Open mic, jam nights Moveable furniture

36 Placemaking (PPS) Key Attributes Characteristics Metrics

37

38

39 Power of Ten 1. Get something to eat 2. Play bocce ball 3. Throw a frisbee 4. Fly a kite 5. Swing 6. Sunbathe 7. Read a book 8. Wi-Fi access 9. Rent a kayak 10.Use the playground

40 Subsystem 3: Special Venues

41 City s premier waterfront venue: Yacht Club Resort-like atmosphere Views to the Caloosahatchee River Historic Ballroom Swimming Pool Waterfront Restaurant Marina Beach Pedestrian-oriented, walkable environment Parking structure with a rooftop restaurant/ bar with views to the river Additional boat docks and finger piers along the canal Ship s store, snack bar, bar, and ice cream shop Splash pad, water slide, and/or other amenities to convert the pool into a small water park New clubhouse, restrooms, and dockmaster facility Non water-related uses, including the tennis courts, pavilion, and Senior Center, should be relocated to other sites to increase water-related capacity.

42 Festival Park/ North Cape Sports Complex City s premier Special Events Park, Community Park, and Sports Complex: Sea Hawk model aircraft park and buffer zone Amphitheater Recreation center with indoor fitness/ cardiovascular equipment Freshwater beach Trails Restored natural areas North Cape Sports Complex Typical community park amenities Traffic management: multiple access points, onsite and off-site parking, and bus and trolley service from off-site lots Infrastructure for special events, e.g. restrooms (permanent and portable), food establishments, power for vendors, lighting, a fixed stage, large open lawn Multiple public and private partners

43 Cape Coral Cultural Park City s premier cultural campus: Cape Coral Historical Society and Museum, the Cultural Park Theatre, and the Cape Coral Art League Rose garden Large open multipurpose field Unified, garden-like cultural campus Renovated buildings with common theme Variety of outdoor spaces Unified through landscape and garden design Café and indoor/ outdoor seating area to provide a central gathering space for snacks and beverages, lunch, Wi-fi, rest, and relaxation. Programmed as a single venue including common web sites, brochures, flyers, social media, and staff Tennis and Pickleball Complex Located at Kennedy Park courts Pro shop Fitness center Concessions Shade, bleachers

44 Subsystem 4: Beaches and Water Access

45 Subsystem 4: Trails and Bikeways

46 Subsystem 5: Signage and Wayfinding: Celebrate the Cape!

47 Priority Projects Project Est. Costs Est. Annual O & M Festival Park Master Plan, Phase 1 (Amphitheater) $1 M Net $300k Retrofit Athletic Field Lighting $1.5 M $20k savings Upgrade Cultural Park, Phase 1 $4 M Net $650k Master Plans for 5 New Neighborhood Parks $175k New Neighborhood Parks $12.5 M $1 M Improve Existing Parks $5 M $500k New/ Improved Beaches $1.25 M $1 M New Trails (allowance) $5 M $15k New Freshwater and Saltwater Ramps and Access $5 M $23 k Yacht Club Master Plan, Redevelopment $ M) Net $650K Yellow Fever Creek Community Park $7.5 M $900k Tennis Complex/ Kennedy Park Master Plan, Development New Parkland (allowance) $2.575 M Net $150k $5 M $ M $5.17 M

48 Funding Priorities: City Manager, Parks Staff Project Est. Costs Est. Annual O & M 2. Festival Park Master Plan, Phase 1 (Amphitheater) $1 M Net $300k Retrofit Athletic Field Lighting $1.5 M $20k savings Upgrade Cultural Park, Phase 1 $4 M Net $650k 1. Master Plans for 5 New Neighborhood Parks $175 k 1. New Neighborhood Parks $12.5 M $1 M Improve Existing Parks $5 M $500k New/ Improved Beaches $1.25 M $1 M New Trails (allowance) $5 M $15k New Freshwater and Saltwater Ramps and Access $5 M $23 k 3. Yacht Club Master Plan, Redevelopment $ M Net $650K Yellow Fever Creek Community Park $7.5 M $900k 4. Tennis and Pickleball Complex/ Kennedy Park Master Plan, Development $2.575 M Net $150k 5. New Parkland (allowance) $5 M $ M $2.1 M

49 Combine parks recommendations with bike/ped master plan Include Yellow Fever Park in Phase 1, e.g. trailhead and trails Include water quality, habitat restoration in park improvements Integrate environmental education throughout the entire system Communicate value of park investments to build support for funding Stakeholder Committee Comments August 3, 2016 Build an environmental /green culture on the Cape Develop computer images to communicate big ideas Build initial support with improvements to existing neighborhood parks, small green spaces ( Low hanging fruit ) Develop a detailed, phased implementation strategy for one project at a time Establish a Friends Group or Foundation to initiate a fund-raising campaign

50 Presentation Outline 1. Overview, Schedule, Needs Assessment Summary 2. Long Range Vision 3. Next Steps 4. Questions, Discussion

51 Implementation Workshop, August 4 Needs Assessment + Long Range Vision + Estimated Costs + Projected Funding + Prioritization Criteria = PRELIMINARY FUNDING AND PHASING STRATEGY

52 Facilities Summary of Findings - Facilities Statistically Valid Survey Needs Assessment Techniques Public Outreach Meetings Interviews Focus Group Meetings On-Line Survey LOS Analysis Site Evaluations High Priority Needs Medium Priority Needs Lower Priority Needs Other Needs Beach X X X X Small neighborhood parks X X X Nature parks X X X Indoor fitness/cardiovascular equipment X X Large community parks X X X Trails X X X X X X Indoor running/walking track X X Fishing areas X X X Yacht club X X Boating/kayaking areas X X X X X Waterpark X X Dog Park X X Theater X X Golf Course X X X Art studio X X Central gathering place X X Gymnasium X X X Environmental Center X X X Historical Museum X X Baseball/softball fields/complex X X X Youth center X X Pickleball courts X X X X X Soccer fields X X Skate park X X Football Fields X X X Improvements to Existing Parks X X X X Festival Park/Amphitheater X X New Indoor Community Center X X Tennis Courts/Complex X Football/Soccer/Lacrosse Complex X

53 FY Adopted Operating Budget 1. Increase economic development and development in the City. 2. Enhance financial sustainability during all economic times. 3. Invest in community infrastructure, including utilities expansion improvements to enhance the City s ability to meet the needs of its current and future residents. 4. Improve the City s image with the purpose of building lasting relationships with our residents and valuable partnerships with other organizations. 5. Increase quality of life for our citizens by delivering programs and services that foster a safe community.

54 Alternative Funding Sources Urban Forest Health Initiative $24,000 Energy Efficiency Grant Program $1.24 M Recreation Development Assistance Program $200,000 DOT Highway Beautification $300,000 Transportation Enhancement Program $500,000 Urban & Community Forestry Grants $10 25,000 Water Project Grant Program $50, M Clean Energy Grants $500,000 Historic Preservation $350,000 Boating Improvement Fund $200,000 Economic Development Administration Varies Lowe s Neighborhood Grants $200,000 Land and Water Conservation Fund Varies Recreational Trails Program $200,000 Broadband Technology Opp. Program Varies NFL Grant Practice Fields $50 200,000 USTA Public Facilities Grant $4 50,000 MLB Tomorrow Fund $50,000 Community Development Block Grants Varies Boating Infrastructure Grant Program $15, M

55 Implement!

56 Presentation Outline 1. Overview, Schedule, Needs Assessment Summary 2. Long Range Vision 3. Next Steps 4. Questions, Discussion

City of Naples Parks Master Plan

City of Naples Parks Master Plan Parks Master Plan Draft Master Plan Presentation January 19, 2015 Presentation Outline Overview Needs Assessment Recap Response to Needs Implementation Strategy Questions, Discussion 2 OVERVIEW Project

More information

City of Naples Parks Master Plan (Draft)

City of Naples Parks Master Plan (Draft) City of Naples (Draft) CSAB April 12, 2016 OVERVIEW Presentation Outline Overview Needs Assessment Recap Response to Needs Implementation Strategy Questions, Discussion Preserving Naples: A vision plan

More information

1. Parks & Recreation Neighborhood Parks Community Parks Special Use Sites 2. Open Space 3. Trails

1. Parks & Recreation Neighborhood Parks Community Parks Special Use Sites 2. Open Space 3. Trails Appendix A: Park Classifications The intent of parks and recreation classifications is to aid in making acquisition and design decisions for park sites, facilities and the organization of recreation space

More information

Support the implementation of Cape Coral's Comprehensive Plan. Protect and utilize the unique natural resources in the City.

Support the implementation of Cape Coral's Comprehensive Plan. Protect and utilize the unique natural resources in the City. 7.0 OVERVIEW - RECOMMENDATIONS Chapter 7 The preparation of the Cape Coral Parks and Recreation Master Plan spanned a period of approximately 12 months. Plan preparation included the input of a wide range

More information

Parks, and Recreation & Cultural Arts Master Plan Update

Parks, and Recreation & Cultural Arts Master Plan Update Parks, and Recreation & Cultural Arts Master Plan Update Community Profile Public Input Summary: Staff Interviews conducted April 14 and 15, 2014 Citizens Workshop - conducted April 15 th and 24 th, May

More information

PARTF Scoring System for Grants

PARTF Scoring System for Grants PARTF Scoring System for Grants The members of the N.C. Parks and Recreation Authority use the PARTF scoring system as one of several tools to select grant recipients. Please provide all of the information

More information

Emerson Park Master Plan Update. Public Meeting III August 27, 2014

Emerson Park Master Plan Update. Public Meeting III August 27, 2014 Emerson Park Master Plan Update Public Meeting III August 27, 2014 Meeting Agenda: Project Update Presentation of Master Plan Components Discussion and Feedback The Path Forward: Building on the Concept

More information

City Council March 27, Parks, Recreation, and Trails Master Plan

City Council March 27, Parks, Recreation, and Trails Master Plan City Council March 27, 2018 Parks, Recreation, and Trails Master Plan Planning Process Develop Goals and Objectives Inventory of Areas and Facilities Needs Assessment And Identification Public Participation

More information

Focus Groups. 8 Focus Group meetings including 2 with staff, 1 with seniors, and 1 with students

Focus Groups. 8 Focus Group meetings including 2 with staff, 1 with seniors, and 1 with students Project Team Nan Lanahan, Parks & Recreation Jason Gallo, Parks & Recreation Rob Leslie, DEDP John Smolinsky, Planning Board Brent Meredith, Highway Joan Gavrilik, Friends of Parks & Rec MaryLyn Koval,

More information

NEW MODELS AND METRICS FOR PARKS SYSTEM PLANNING Wednesday, January 31st, 11:45 am - 1:00 pm. David Barth, PhD, AICP, CPRP, RLA

NEW MODELS AND METRICS FOR PARKS SYSTEM PLANNING Wednesday, January 31st, 11:45 am - 1:00 pm. David Barth, PhD, AICP, CPRP, RLA NEW MODELS AND METRICS FOR PARKS SYSTEM PLANNING Wednesday, January 31st, 11:45 am - 1:00 pm David Barth, PhD, AICP, CPRP, RLA david@barthassoc.com https://www.planning.org/pas/memo/2016/may/ WHY DO

More information

CITY OF GAINESVILLE PARKS, RECREATION AND CULTURAL AFFAIRS DEPARTMENT VISION 2020

CITY OF GAINESVILLE PARKS, RECREATION AND CULTURAL AFFAIRS DEPARTMENT VISION 2020 CITY OF GAINESVILLE PARKS, RECREATION AND CULTURAL AFFAIRS DEPARTMENT VISION 2020 A BLUE PRINT FOR THE NEXT 20 YEARS The PRCA Vision 2020 Master Plan, adopted in November 2012, addresses the current state

More information

PARKS & RECREATION SUBCOMMITTEE. Oct. 1, 2015

PARKS & RECREATION SUBCOMMITTEE. Oct. 1, 2015 PARKS & RECREATION SUBCOMMITTEE Oct. 1, 2015 1999 Bond - $22,000,000 Land Acquisition Allen Station Phase II Neighborhood Parks PREVIOUS BOND ELECTIONS 1999 & 2007 2002 Bond - $4,000,000 Allen Senior Recreation

More information

PUBLIC SPACES MASTER PLAN UPDATE (POPS) Crystal City Citizen s Review Council October 24, 2018

PUBLIC SPACES MASTER PLAN UPDATE (POPS) Crystal City Citizen s Review Council October 24, 2018 PUBLIC SPACES MASTER PLAN UPDATE (POPS) Crystal City Citizen s Review Council October 24, 2018 1 PLANNING CONTEXT Arlington County Comprehensive Plan UPDATE Related Documents: CIP Sector Plans Area Plans

More information

Canal Winchester Parks Master Plan. Public Meeting 2 Thursday, February 2 6:30pm

Canal Winchester Parks Master Plan. Public Meeting 2 Thursday, February 2 6:30pm Canal Winchester Parks Master Plan Public Meeting 2 Thursday, February 2 6:30pm Meeting Agenda 1. Project overview 2. Project schedule 3. Public input results Survey Public Meeting #1 Stakeholder Interviews

More information

CITY OF BOCA RATON GOVERNMENTAL CAMPUS Master Plan Progress August 22, 2017

CITY OF BOCA RATON GOVERNMENTAL CAMPUS Master Plan Progress August 22, 2017 CITY OF BOCA RATON GOVERNMENTAL CAMPUS Master Plan Progress August 22, 2017 This is a rare moment in the City s history which affords us the opportunity to create a civic landmark born of comprehensive

More information

PIERCE COUNTY IMPACT FEE WORKING GROUP. Pierce County s Park System

PIERCE COUNTY IMPACT FEE WORKING GROUP. Pierce County s Park System PIERCE COUNTY IMPACT FEE WORKING GROUP Pierce County s Park System Project Title 2/25/2016 1 Pierce County s Park System Park System Concept Park Classifications Current Park Inventory Park System Comparison

More information

SOUTHEAST SPORTS COMPLEX MASTER PLAN

SOUTHEAST SPORTS COMPLEX MASTER PLAN REPORT TO SOUTHGATE NEIGHBORHOOD COUNCIL APRIL 13, 2016 Visioning Process April 30: Stakeholder Meeting with Sports Groups May 5: Stakeholder Meeting with Southgate Land Use Committee May 13: SNC Meeting

More information

CHAPPLES PARK MASTER PLAN

CHAPPLES PARK MASTER PLAN CHAPPLES PARK MASTER PLAN Presentation of Preliminary Development Options Public Open House #2 Wednesday November 2 nd, 2016 TONIGHT S AGENDA 1. Welcome & Introductions 2. Presentation by Sierra Planning

More information

Comprehensive Park System Master Plan

Comprehensive Park System Master Plan PARKS AND RECREATION Comprehensive Park System Master Plan Citizen Advisory Committee, June 5, 2012 - Meeting Notes Transcription MIG met with the Parks Citizen Advisory Committee on Tuesday, June 5th,

More information

a) Inventory of all existing privately-owned, state-owned, or local governmentowned recreational facilities and open spaces within the context area

a) Inventory of all existing privately-owned, state-owned, or local governmentowned recreational facilities and open spaces within the context area 8.0 RECREATION AND OPEN SPACE ELEMENT (1) DATA REQUIREMENTS a) Inventory of all existing privately-owned, state-owned, or local governmentowned recreational facilities and open spaces within the context

More information

Provide and maintain sufficient public parks, recreation facilities, and open space to meet the recreational needs of County residents and visitors.

Provide and maintain sufficient public parks, recreation facilities, and open space to meet the recreational needs of County residents and visitors. (ROS) Goal Provide and maintain sufficient public parks, recreation facilities, and open space to meet the recreational needs of County residents and visitors. OBJECTIVE ROS.01 The County shall acquire,

More information

RECREATION AND OPEN SPACE ELEMENT

RECREATION AND OPEN SPACE ELEMENT RECREATION AND OPEN SPACE ELEMENT Last amended August 19, 2008 Table of Contents Objective Page 5.1 Park system defined... 5-1 5.2 Access to parks and recreational facilities... 5-2 5.3 Recreation and

More information

PLANNING & DEVELOPMENT BOARD

PLANNING & DEVELOPMENT BOARD PLANNING & DEVELOPMENT BOARD AGENDA The regular meeting of the PLANNING & DEVELOPMENT BOARD will be held at 6:00 p.m. on DECEMBER 19TH, 2017 in COMMON COUNCIL CHAMBERS, City Hall, 108 E. Green Street,

More information

Courthouse Planning Area

Courthouse Planning Area Courthouse Planning Area Current Reality The Courthouse Planning Area is the characterized by expansive suburbanscale residential areas as well as the community resource planned area of athletic, educational,

More information

RECREATION AND OPEN SPACE ELEMENT GOALS, OBJECTIVES, AND POLICIES

RECREATION AND OPEN SPACE ELEMENT GOALS, OBJECTIVES, AND POLICIES RECREATION AND OPEN SPACE ELEMENT GOALS, OBJECTIVES, AND POLICIES Goal 7 To provide park facilities, recreation programs, and open space resources that are safe, adequate, and accessible to all City residents,

More information

Chapter 6. Overall Vision RECOMMENDATIONS. More Trail and Trail. Connections. Equal Access to Park. Facilities and Programs. Water Access.

Chapter 6. Overall Vision RECOMMENDATIONS. More Trail and Trail. Connections. Equal Access to Park. Facilities and Programs. Water Access. Overall Vision More Trail and Trail Connections Equal Access to Park Facilities and Programs Water Access Environment Variety Chapter 6 RECOMMENDATIONS Chapter 6 The following recommendations for park,

More information

TAO S PARKS MASTER PLAN

TAO S PARKS MASTER PLAN TAO S PARKS MASTER PLAN December 2017 Kit Carson Park Fred aca Park Eco Park Youth + Family Center Eco Park TAOS PARKS MASTER PLAN December 2017 SCOPE OF WORK Town of Taos Parks + Recreation Master Plan

More information

Appendix A. Park Land Definitions

Appendix A. Park Land Definitions Appendix A Park Land Definitions Mini Park May serve specific function for any and all ages, depending on need of the user area. Size range 1-5 acres with optimum size being 3 acres. Service area is sub-neighborhood

More information

Great Neck Planning Area

Great Neck Planning Area Great Neck Planning Area Current Reality The Great Neck Planning area is characterized primarily by large lot/lowdensity residential development with the majority of recreational opportunity existing as

More information

29 Bella Fontaine Park

29 Bella Fontaine Park 29 Bella Fontaine Park 9565 Bellefontaine Road St. Louis County Parks Master Plan Planning Zone 2 Visit Date: July 2016 Page 1 129 Bella Fontaine Park 9565 Bellefontaine Road St. Louis County Parks Master

More information

TOWN COUNCIL / PLANNING COMMISSION

TOWN COUNCIL / PLANNING COMMISSION Workshop #3 TOWN COUNCIL / PLANNING COMMISSION January 20, 2011 Consultant Team In Attendance Tonight BMS Design Group Nevada City and San Francisco Michael Smiley, AICP, ASLA Partner-in-Charge Nancy L.

More information

M-NCPPC Park System in

M-NCPPC Park System in Park Planning & Stewardship Division Park & Trail Planning Section East County Science Center Master Plan Parks, Recreation, Trails, and Open Space- Issues and Opportunities PARK PLANNING & STEWARDSHIP

More information

CITY OF ANN ARBOR // Parks + Recreation. Hillary Hanzel Park Planner + Landscape Architect

CITY OF ANN ARBOR // Parks + Recreation. Hillary Hanzel Park Planner + Landscape Architect CITY OF ANN ARBOR // Parks + Recreation Hillary Hanzel Park Planner + Landscape Architect CITY OF ANN ARBOR // Parks + Recreation 1. Overview of Parks System 2. Recent + Upcoming Capital Projects 3. History

More information

STAFF RECOMMENDATION: Adopt the Parks and Recreation Master Plan 2013, or take other action as deemed appropriate.

STAFF RECOMMENDATION: Adopt the Parks and Recreation Master Plan 2013, or take other action as deemed appropriate. Regular 7. CITY COUNCIL AGENDA Meeting Date: 12/02/2013 TITLE: Parks and Recreation Master Plan 2013 Adoption Proposal - Dwight Curtis Responsible Staff: Dwight Curtis Backup Material: Backup material

More information

South East Sports Complex Phase I

South East Sports Complex Phase I South East Sports Complex Phase I City of Spokane Design Review Board August 29, 2018 (Revised) Objectives 1. Early discussion and collaboration. 2. Provide framework / catalyst for future improvements

More information

Workshop #3 June 13, 2016

Workshop #3 June 13, 2016 Downtown Ocoee Master Plan Workshop #3 June 13, 2016 Our Team Our Team and Tonight s Goal Quick Recap: Why a Downtown Plan? How are we developing the plan? How can you still be involved? What s left to

More information

Parks & Recreation. Michael Versen & Associates Landscape Architecture Land Planning

Parks & Recreation. Michael Versen & Associates Landscape Architecture Land Planning Michael Versen & Associates Landscape Architecture Land Planning 299 N. Weisgarber Road Suite 201 Knoxville, TN. 37919 website: www.versenassociates.com telephone: 865-588 588-1331 fax: 865-251 251-4086

More information

nokomis-hiawatha regional park master plan and park improvements

nokomis-hiawatha regional park master plan and park improvements master plan and park improvements CAC Workshop # August 26th, 2014 charge of the cac The Nokomis Hiawatha Regional Park CAC shall: Become knowledgeable about the project and its scope Understand and represent

More information

Pungo/Blackwater Planning Area

Pungo/Blackwater Planning Area Pungo/Blackwater Planning Area Current Reality The Pungo/Blackwater Planning Area represents the rural landscape and lifestyle that encompasses nearly 40% of Virginia Beach. The Agricultural Reserve Program

More information

City of Plattsburgh DRI: Downtown Streetscapes & Riverfront Access. Downtown Streetscape and Riverfront Access Design

City of Plattsburgh DRI: Downtown Streetscapes & Riverfront Access. Downtown Streetscape and Riverfront Access Design City of Plattsburgh DRI: Downtown Streetscapes & Riverfront Access Welcome Thank you for coming this evening. Agenda PART I - Project Context The Downtown Revitalization Program Our DRI Projects Other

More information

Little Neck Planning Area

Little Neck Planning Area Little Neck Planning Area Current Reality The Little Neck Planning Area is characterized by established residential neighborhoods, Town Center and Pembroke. The Eastern and Western Branches of the Lynnhaven

More information

ELLENBERGER PARK FAMILY CENTER

ELLENBERGER PARK FAMILY CENTER COMMUNITY MEETING: NOVEMBER 16, 2011 Healthy Lifestyles Exercise, Wellness, Social Interaction Family and Inter-generational Use Accessibility, Transparency, Flexibility, Safety Sustainability Revenue

More information

PUBLIC SPACES MASTER PLAN UPDATE (POPS) Joint Facilities Advisory Commission (JFAC) November 28, 2018

PUBLIC SPACES MASTER PLAN UPDATE (POPS) Joint Facilities Advisory Commission (JFAC) November 28, 2018 PUBLIC SPACES MASTER PLAN UPDATE (POPS) Joint Facilities Advisory Commission (JFAC) November 28, 2018 1 AGENDA POPS Planning Context Timeline Public Input Final POPS Draft Next Steps 2 PLANNING CONTEXT

More information

RECREATION AND OPEN SPACE ELEMENT

RECREATION AND OPEN SPACE ELEMENT RECREATION AND OPEN SPACE ELEMENT TOWN OF HOWEY-IN-THE-HILLS LAKE COUNTY, FLORIDA ADOPTED ON OCTOBER 11, 2010 RECREATION AND OPEN SPACE ELEMENT TABLE OF CONTENTS A. INTRODUCTION...1 1. PURPOSE...1 B. EXISTING

More information

PARK M A I N T E N A N C E REPORT CARD

PARK M A I N T E N A N C E REPORT CARD PARK M A I N T E N A N C E REPORT CARD Park Name: Date: General Instructions: Your Name: Phone: Contact Information Optional: Email: SAMPLE The Report Card consists of six specific park areas to be graded.

More information

PARK AND RECREATION MASTER PLAN UPDATE

PARK AND RECREATION MASTER PLAN UPDATE PARK AND RECREATION MASTER PLAN UPDATE 2014-2018 Prepared for: Avon Parks, Recreation and Beautification Council (PRBC) and Town of Avon Prepared by: Lehman & Lehman, Inc. 24-Apr-14 Mission Statement The

More information

Citizen s Advisory Committee

Citizen s Advisory Committee Citizen s Advisory Committee 13 Members 6 Meetings (5 Locations) 1 Public Meeting Numerous Report Drafts Countless Hours of Review Immeasurable Input Special Thank You To: Jack Cohen Brian Kile George

More information

I-70 Highway Cover Study MARCH 4, 2015 COMMUNITY WORKSHOP SUMMARY

I-70 Highway Cover Study MARCH 4, 2015 COMMUNITY WORKSHOP SUMMARY I-70 Highway Cover Study MARCH 4, 2015 COMMUNITY WORKSHOP SUMMARY MARCH 2015 COMMUNITY WORKSHOP CDOT and the City and County of Denver joined together to engage the community and gather ideas to explore

More information

CHAPTER 9: Parks, Recreation, and Open Space Element

CHAPTER 9: Parks, Recreation, and Open Space Element CHAPTER 9: Parks, Recreation, and Open Space Element INTRODUCTION: The Parks, Recreation, and Open Space Element is a comprehensive representation of the City s vision and goals for the future of the park,

More information

CHAPPLES PARK MASTER PLAN. Presentation to Council April 10, 2017

CHAPPLES PARK MASTER PLAN. Presentation to Council April 10, 2017 CHAPPLES PARK MASTER PLAN Presentation to Council April 10, 2017 1 PRESENTATION AGENDA 1. Project Background, Aim and Process 2. The Site Issues and Opportunities 3. Community Engagement 4. Vision and

More information

City of La Center Park, Recreation and Open Space Master Plan. March 2016 Draft

City of La Center Park, Recreation and Open Space Master Plan. March 2016 Draft City of La Center Park, Recreation and Open Space Master Plan March 2016 Draft Table of Contents. Chapter 1: Introduction... 1 1.1 Community Profile... 3 1.2 Master Plan Overview... 3 1.3 Planning Process...

More information

Section Three Recreation Standards & Needs Assessment

Section Three Recreation Standards & Needs Assessment Section Three Recreation Standards & Needs Assessment William M. Hargraves Center Introduction This section contains the analysis and assessment on which the recommendations of this Comprehensive Parks

More information

City of Pigeon Forge

City of Pigeon Forge City of Pigeon Forge Comprehensive Parks and Recreation Master Plan Executive Summary Prepared for the City of Pigeon Forge May 15, 2009 Prepared by: City of Pigeon Forge Comprehensive Parks and Recreation

More information

The Five Components of the McLoughlin Area Plan

The Five Components of the McLoughlin Area Plan The Five Components of the McLoughlin Area Plan This documents contains the complete language of the five components of the McLoughlin Area Plan: The Vision Statement The Values The Guiding Principles

More information

ROBERTS FIELD BRANDING GOALS NEW BRANDING PROJECT

ROBERTS FIELD BRANDING GOALS NEW BRANDING PROJECT ROBERTS FIELD NEW BRANDING PROJECT Create branding and logos for Roberts Field and park areas including Friendship Park, The Wildlife Sanctuary and The Playing Fields. Best define use and expectations

More information

City of Bonney Lake Allan Yorke Park. MASTER PLAN SUMMARY REPORT June 30, 2016

City of Bonney Lake Allan Yorke Park. MASTER PLAN SUMMARY REPORT June 30, 2016 City of Bonney Lake Allan Yorke Park MASTER PLAN SUMMARY REPORT June 30, 2016 TABLE OF CONTENTS INTRODUCTION PUBLIC INVOLVEMENT PROCESS MASTER PLAN North Park Central Park South Park East Park Field Development

More information

RECREATION AND OPEN SPACE VISION

RECREATION AND OPEN SPACE VISION City of South Lake Tahoe General Plan Policy Document Recreation and Open Space Element INTRODUCTION This element provides the policy context for the City of South Lake Tahoe to achieve its vision for

More information

Montana Rail Link Park

Montana Rail Link Park Montana Rail Link Park Neighborhood Open House A Missoula Community Partnership WITH LEADERSHIP FROM THE FRANKLIN TO THE FORT & SOUTHGATE TRIANGLE NEIGHBORHOODS Sovereign Hope Church, (1919 North Ave.)

More information

Las Colonias Park Master Plan

Las Colonias Park Master Plan 2013 Las Colonias Park Master Plan City of Grand Junction June 2013 Introduction Las Colonias Park, a 101 acre parcel on the edge of the Colorado River south of downtown, was deeded to the City of Grand

More information

COMPREHENSIVE PLAN & UNIFIED DEVELOPMENT ORDINANCE

COMPREHENSIVE PLAN & UNIFIED DEVELOPMENT ORDINANCE Village of Forsyth COMPREHENSIVE PLAN & UNIFIED DEVELOPMENT ORDINANCE Community Planning #6 Prepared by: Vision Statement We envision the Forsyth Community as one which will continue to maintain a small

More information

Outdoor Recreation Facilities Inventory

Outdoor Recreation Facilities Inventory Outdoor Recreation Facilities Inventory Allouez Neighborhood Parks: East Lawn Park (4.90 acres) is located in the northeastern corner of Allouez near Boyd Street. This site contains: Baseball diamond with

More information

MISSISSIPPI GORGE REGIONAL PARK MASTER PLAN

MISSISSIPPI GORGE REGIONAL PARK MASTER PLAN MISSISSIPPI GORGE REGIONAL PARK MASTER PLAN Minneapolis Park and Recreation Board CAC MEETING #1 APRIL 23, 2018 AGENDA Mississippi Gorge Regional Park Master Plan CAC #1 01 / Welcome and Calling Circle

More information

GOODY CLANCY WITH KITTELSON & ASSOCIATES RHODESIDE & HARWELL FARR ASSOCIATES W-ZHA

GOODY CLANCY WITH KITTELSON & ASSOCIATES RHODESIDE & HARWELL FARR ASSOCIATES W-ZHA 1 1. Welcome 5 min. 2. Follow-up from 9/22 / Corridor of Light, ground floor uses 20 min. 3. Small on-site open spaces / Overview of types, identities 15 min. 4. Rosslyn Plaza Park / Rosslyn Plaza PDSP

More information

Public Workshop 2 December 11, 2014 OLIN

Public Workshop 2 December 11, 2014 OLIN Public Workshop 2 December 11, 2014 OLIN TRIPLE IMAGE PANORAMA A NEW VISION FOR THE RIVERFRONT PROMENADE Burlington s Riverfront has historically been a defining character of the City s identity. This

More information

Washington Park Diagonal

Washington Park Diagonal Public Input Meeting August 3, 2011 Nicole Stahly RLA DPR Project Manager Jesse Clark RLA, LEED Stream Design Paul Thomas RLA Stream Design Kerry White RLA Urban Play Studio Tonight s Agenda 1st Meeting:

More information

VIRGINIA KEY CONSENSUS MASTER PLAN

VIRGINIA KEY CONSENSUS MASTER PLAN VIRGINIA KEY CONSENSUS MASTER PLAN JULY 2010 Existing Conditions JULY 2010 STAKEHOLDER INTERVIEW PROCESS, January 18-22, 2007 PUBLIC MEETING #1: SITE INVENTORY AND ANALYSIS, March 29, 2007 PUBLIC MEETING

More information

APPENDIX D: PARKS AND RECREATION ACTION PLAN

APPENDIX D: PARKS AND RECREATION ACTION PLAN APPENDIX D: PARKS AND RECREATION ACTION PLAN Goals The following goals are specific to the development, maintenance, and operation of the existing parks in the Township, as well as the acquisition and

More information

PARKS AND RECREATION ELEMENT

PARKS AND RECREATION ELEMENT PARKS AND RECREATION ELEMENT TABLE -3 First Priority 1 2 POTENTIAL SAN CARLOS TRAIL CONNECTIONS Crestview to Pulgas Ridge Open Space Preserve and San Francisco Watershed Lands Unimproved City-Owned Parcel

More information

Comprehensive Parks and Recreation Master Plan. Executive Summary. Submitted To: City of Milton, GA October 2012

Comprehensive Parks and Recreation Master Plan. Executive Summary. Submitted To: City of Milton, GA October 2012 Comprehensive Parks and Recreation Master Plan Executive Summary Submitted To: City of Milton, GA October 2012 Executive Summary The City of Milton envisioned the need for an effective Master Planning

More information

ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET ARROYO PROJECTS

ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET ARROYO PROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET ARROYO PROJECTS HAHAMONGNA FY 212-216 Capital Improvement Program Priority Description Total Estimated Costs Appropriated Through FY 211 Adopted FY 212 FY 213

More information

Kempsville Planning Area

Kempsville Planning Area Kempsville Planning Area Current Reality The Kempsville Planning Area is by far the most populated planning area in the City. The preservation of the 1,422 Stumpy Lake Natural Area, the largest City-owned

More information

Rotary Park / Railroad Lake

Rotary Park / Railroad Lake Rotary Park / Railroad Lake Park Location: 600 NW Vesper St. Park Land Established: 1975 Park Size: 12 acres Developed Acres: 12 acres Undeveloped Acres: 0 acres Park Type: Community Park Amenities: 2

More information

REPORT SPECIAL COUNCIL MEETING MEETING DATE: MAY 2, Five Year Review of the 2012 Parks, Recreation and Library Facilities Master Plan

REPORT SPECIAL COUNCIL MEETING MEETING DATE: MAY 2, Five Year Review of the 2012 Parks, Recreation and Library Facilities Master Plan REPORT SPECIAL COUNCIL MEETING MEETING DATE: MAY 2, 2017 FROM: Recreation and Culture Department DATE: April 25, 2017 SUBJECT: Five Year Review of the 2012 Parks, Recreation and Library Facilities Master

More information

3. VISION AND GOALS. Vision Statement. Goals, Objectives and Policies

3. VISION AND GOALS. Vision Statement. Goals, Objectives and Policies Vision Statement Queen Creek s interconnected network of parks, trails, open spaces and recreation opportunities provide safe and diverse activities and programs that sustain its unique, small town, equestrian

More information

900 Innes & India Basin Shoreline Park

900 Innes & India Basin Shoreline Park India Basin Waterfront Study Task Force A. Philip Randolph Institute Golden Gate Audubon Society Bay Institute Aquarium Foundation Build Inc. Five Points Green Action for Health and Environmental Justice

More information

LAKEVIEW VILLAGE VISION & MASTERPLAN PRESENTATION TO CITY OF MISSISSAUGA. April 9, 2018

LAKEVIEW VILLAGE VISION & MASTERPLAN PRESENTATION TO CITY OF MISSISSAUGA. April 9, 2018 LAKEVIEW VILLAGE VISION & MASTERPLAN PRESENTATION TO CITY OF MISSISSAUGA April 9, 2018 AGENDA Introduction Vision Plan Comparison The Big Moves Trail Connections Plan Overview Districts Conveyance Comparison

More information

Appendix 4 Park, Trail, and Recreation Facilities For more information, call the Park Planning and Stewardship Division at

Appendix 4 Park, Trail, and Recreation Facilities For more information, call the Park Planning and Stewardship Division at Appendix 4 Park, Trail, and Recreation Facilities For more information, call the Park Planning and Stewardship Division at 301-650-4380 montgomery county planning board maryland-national capital park and

More information

(Exhibit A) Site Plan Adoption Detail and Support Information

(Exhibit A) Site Plan Adoption Detail and Support Information McCormick Park Master Site Plan (Exhibit A) Site Plan Adoption Detail and Support Information July, 2003 McCormick Park Site Plans.... 2-3 McCormick Park Site Plan Comparison... 4 Basic Assumptions about

More information

APPENDIX D2: PARKS AND TRAILS

APPENDIX D2: PARKS AND TRAILS APPENDIX D2: PARKS AND TRAILS Cultivate Hopkins Comprehensive Plan 8/15/18 DRAFT Cultivate Hopkins Appendix D2 1 Existing Conditions Local Parks and Trails Figure D2.1 shows the existing park and trail

More information

LIDO KEY RESIDENTS ASSOCIATION CITY OF SARASOTA PRESENTATION

LIDO KEY RESIDENTS ASSOCIATION CITY OF SARASOTA PRESENTATION LIDO KEY RESIDENTS ASSOCIATION CITY OF SARASOTA PRESENTATION Presented By The Ad-Hoc Lido Pool Committee January 17, 2012 The Ad-Hoc Lido Pool Committee Committee Members Blair Ashby Anne Franklin Tony

More information

WARM SPRINGS PARK MASTER PLAN

WARM SPRINGS PARK MASTER PLAN TABLE OF CONTENTS page 1.0 Introduction and Overview 1 2.0 Information Gathering 2 3.0 Conceptual Alternative Development 8 4.0 Master Plan Development 14 5.0 Construction Cost Estimates 19 LIST OF FIGURES

More information

4. RECREATION & CONSERVATION AREAS

4. RECREATION & CONSERVATION AREAS VISION Block Island will offer a variety of recreational activities that encourage healthy lifestyles and provide attractive and accessible places for the recreational pursuits of its residents and many

More information

CARMODY PARK MASTER PLAN

CARMODY PARK MASTER PLAN the site Smith Reservoir Cottonwood Lake Kendrick Lake Carmody Rec Center Carmody Middle School Pool Court Play Carmody Pond Sanderson Ditch Sports Fields Foothills Ice Arena Open Field why a master plan?

More information

Y Sports Complex PROGRAMMING Capitol Improvement Plan. Anticipated/Suggested Improvements. Sedgwick County Park: Sports Complex:

Y Sports Complex PROGRAMMING Capitol Improvement Plan. Anticipated/Suggested Improvements. Sedgwick County Park: Sports Complex: PROJECT OVERVIEW Location: East of Ridge Road, between 21 st Street and 13 th Street, not including SCZ In conjunction with The Sedgwick County Park Facilities Observation Report Compilation of improvements

More information

EXCHANGE PARKWAY RECREATION CENTER FEASIBILITY STUDY PUBLIC MEETING ONE APRIL O4, 2019

EXCHANGE PARKWAY RECREATION CENTER FEASIBILITY STUDY PUBLIC MEETING ONE APRIL O4, 2019 EXCHANGE PARKWAY RECREATION CENTER FEASIBILITY STUDY ONE APRIL O4, 2019 COMMUNITY ENGAGEMENT & INPUT AGENDA INTRODUCTIONS PROJECT HISTORY & GOALS SITE ANALYSIS AND INFLUENCES TRENDS IN RECREATION PROGRAMMING

More information

[THIS PAGE INTENTIONALLY LEFT BLANK]

[THIS PAGE INTENTIONALLY LEFT BLANK] [THIS PAGE INTENTIONALLY LEFT BLANK] RECREATION AND OPEN SPACE ELEMENT TABLE OF CONTENTS Page No. INTRODUCTION... 2 PURPOSE AND SCOPE... 2 DESCRIPTION OF PARK TYPES... 2 NEIGHBORHOOD PARK... 2 Community

More information

ARROYO PROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET

ARROYO PROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET A RROYO P ROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET FISCAL YEARS 214-218 HAHAMONGNA Priority Description 1 Hahamongna Watershed Park - Implement Master Plan 211,6 211,6 (77565) 2 Hahamongna -

More information

6. RECREATION AND OPEN SPACE ELEMENT

6. RECREATION AND OPEN SPACE ELEMENT 6. RECREATION AND OPEN SPACE Introduction This Recreation and Open Space Element includes Goals, Objectives and Policies (GOP) that apply to the main campus in Gainesville and the Lake Wauburg Recreation

More information

Presented by Meg Parker Public Health Outreach Coordinator

Presented by Meg Parker Public Health Outreach Coordinator Presented by Meg Parker Public Health Outreach Coordinator Essex County Public Health Creating Healthy Places (grant funded program from New York State Department of Health) Three learning objectives List

More information

edmonton.ca/ribbonofgreen #ribbonofgreen

edmonton.ca/ribbonofgreen #ribbonofgreen WHAT IS THE RIBBON OF GREEN? The Ribbon of Green is Edmonton s entire river valley and ravine system. The Ribbon of Green (2018) Project will provide strategic guidance for the southwest and northeast

More information

Dowdy Park. Concept Plans TOWN OF NAGS HEAD NORTH CAROLINA. Developed by: Albemarle & Associates, Ltd VHB/ Vanasse Hangen Brustlin, Inc.

Dowdy Park. Concept Plans TOWN OF NAGS HEAD NORTH CAROLINA. Developed by: Albemarle & Associates, Ltd VHB/ Vanasse Hangen Brustlin, Inc. TOWN OF NAGS HEAD NORTH CAROLINA Concept Plans Developed by: Albemarle & Associates, Ltd VHB/ Vanasse Hangen Brustlin, Inc. Site Looking Southeast Dowdy Park Existing Conditions Nags Head Woods Sound Future

More information

Durango Parks & Recreation Department. Strategic Plan

Durango Parks & Recreation Department. Strategic Plan Durango Parks & Recreation Department Strategic 2019-2023 Adopted April 2019 Overview The purpose of the adopted 2010 Parks, Open Space, Trails and Recreation Master is to provide a 10-year road map for

More information

Regional Open Space Conservation Plan. Regional Staff Committee January 18, 2018

Regional Open Space Conservation Plan. Regional Staff Committee January 18, 2018 Regional Open Space Conservation Plan Regional Staff Committee January 18, 2018 Schedule We are here Task 1 - Stakeholder Input & Work Plan Dev. v z 2016 2017 2018 Oct Nov Dec Jan Feb Mar Apr May Jun Jul

More information

MARINA MARKET & WATERFRONT DEVELOPMENT STUDY PORT ARANSAS, TEXAS

MARINA MARKET & WATERFRONT DEVELOPMENT STUDY PORT ARANSAS, TEXAS MARINA MARKET & WATERFRONT DEVELOPMENT STUDY PORT ARANSAS, TEXAS FEBRUARY 2015 PRESENTATION OUTLINE 1 2 3 4 5 6 7 REGIONAL POSITIONING SITE IMPRESSIONS PLANNING & DESIGN PRINCIPLES EXISTING IMPROVEMENTS

More information

Appendix E Section 4(f) Evaluation

Appendix E Section 4(f) Evaluation Appendix E Section 4(f) Evaluation Appendix E Draft Section 4(f) Evaluation E.1 Introduction This appendix addresses a federal regulation known as Section 4(f), which protects parks, recreation areas,

More information

Chapter 11 PARKS, RECREATION AND OPEN SPACE

Chapter 11 PARKS, RECREATION AND OPEN SPACE Chapter 11 PARKS, RECREATION AND OPEN SPACE INTRODUCTION The 2016 Parks, Recreation and Open Space Plan (Park Plan) for Gig Harbor represents the City s vision and provides goals and objectives for the

More information

Special Revenue Funds

Special Revenue Funds Special Revenue Funds Special Revenue Funds account for the proceeds of specific revenue sources (other than special assessments for major capital projects) that are legally restricted to expenditures

More information

PARKS. Chapter Introduction

PARKS. Chapter Introduction Chapter 4. PARKS 4.1. Introduction This Parks Element of the 2016 Comprehensive Plan Update provides direction and guidance, based on citizen input, in order to improve and maintain the City s existing

More information

Rio/29 Small Area Plan. Design Plan & Implementation Framework Open House - January 25, 2018

Rio/29 Small Area Plan. Design Plan & Implementation Framework Open House - January 25, 2018 Rio/29 Small Area Plan Design Plan & Implementation Framework Open House - January 25, 2018 MEETING PURPOSE PRESENTATION 1. Orient to the updated design plans 2. Introduce implementing options 3. Explain

More information

Element 0X Parks, Recreation and Open Space

Element 0X Parks, Recreation and Open Space Element 0X Parks, Recreation and Open Space Table of Contents 1. Introduction 2. Major Issues, Concerns, and Citizen Input 3. Parks, Recreation and Open Space Goals & Policies 4. Analysis Background and