1 Nothing lasts forever planning for successful mine closure Tommi Kauppila, Geological Survey of Finland

2 All mines eventually close All mines have a finite life-of-mine (LOM): Eight years for a typical gold mine starting now Thirty years for a typical copper mine Mine sites may leave an environmental legacy that persists after mine closure Slow weathering of mineral wastes; Acid Rock Drainage Water management issues Mine closure also affects the regional economy and livelihoods Also a wealth of opportunities for the post mining period EXPLORATION (20+ yrs) PRODUCTI ON POST CLOSURE (10- eternity) CONSTRUCTION (2-3 yrs) CLOSURE (2-3 yrs)

3 What is mine closure Mine closure aims at bringing all parts of the mine site to a safe and physically, chemically and biologically stable state that facilitates the planned post mining uses of the site. Mine closure consists of two main activities: Decommissioning = permanently ending the mining and mineral processing operations and removing all the equipment and facilities that are not destined to remain in place for future use Reclamation = reclaiming the mine site for the planned sustainable post mining land uses Mine closure starts already at the planning stage of a mining project and continues long into the post mining period

4 Mine closure is a long process Interact with feasibility and planning Consult stakeholders Define post closure land uses Define closure objectives Make a Closure Management Plan Keep the CMP up to date Exploration Pre-feasibility Feasibility Financing Design & planning Constru ction Operate for closure Employ continuous closure Make the final CMP Close the mine Monitor success Operation Decision to close Final closure Post closure

5 Stakeholders are key to successful closure External stakeholders Those affected by, dependent on, or interested in the mining project. Those in a position to affect the outcomes of the closure Can provide a view of the post mining land uses and life in the area Local residents, summer home owners, municipalities, authorities, NGOs, prospective post mining users of the site Internal stakeholders Those whose work in the project affects the success of the closure process Mine closure should guide all planning, design, and operation: clear and well communicated objectives Environmental department, Health and Safety, Mining, Processing, Geology and Exploration, External relations, Financing; the corresponding departments at the corporate level

6 Objectives of working with external stakeholders Remind stakeholders that all mines close at some point and preparations are needed to sustain the benefits after closure Identify the most affected stakeholders and those crucial for successful closure Provide information to facilitate the participation of the stakeholders in the closure process Look at risks but also opportunities related to mine closure Collect, combine, understand and balance the views, expectations, and objectives of the different stakeholders Define balanced and realistic objectives for mine closure and views of the post closure uses of the site Engage stakeholders in the closure process to achieve best sustainable mine closure outcomes

7 Defining closure objectives: minimize risks, maximize opportunities

8 General closure objectives Value/objective Physical stability Geochemical stability Biological stability Aesthetics Natural resources Post-mining land use Social and economic issues Closure objectives All remaining structures and facilities are physically stable, able to withstand the environmental conditions and events, pose no threat to health and safety, and term functions as designed. Any contaminants must not be released and transported from the site at harmful to human health or biota or otherwise unacceptable. The biological environment is restored to a natural, balanced, self-sustaining the area or compatible with the planned post mining land use. The other mine must provide for physical, chemical, and hydrological conditions that enable such ecosystems. The site is brought to a visually acceptable state. Closure secures the amount and quality of the natural resources of the site mineral, energy etc.) Closure and reclamation are such that the desired post-mining land use is mining land uses have been selected using best practice approaches. Closure minimizes adverse local and regional socio-economic effects and seeks benefits. The views, expectations, and expertise of the local community are taken consideration. Financial issues Outstanding liability and risks are minimized after reclamation activities are are in place to facilitate post closure monitoring.

9 Closure Management Plan is a key document Closure Management Plan (CMP) is a key document in managing the closure process Many jurisdictions, including Finland, require a closure management plan as part of the permitting process The actual live CMP is usually a different document The level of detail increases throughout the project Conceptual Detailed Final ; engineering design, management procedures, due diligence CMP is a continuously updated document with the aim of providing confidence that the closure objectives will be met Constant reduction of uncertainties and outstanding liabilities

10 Legal requirements in Finland there must be a plan Mining Act, Section 120 & Government Proposal for Mining Act (HE 272/2009) The mining operator must take into consideration the safe termination of mining activity at every stage of the mining project. The termination of mining activity and the closing of the mine should be conducted in a planned manner. The Government Decree on Mining Activities (391/2012), Section 16: The mining application must include a reliable report regarding the termination of activities and related measures, alongside after-care measures to be performed once the mining activity is terminated A report on the measures required by the termination of mining activities and their regional scope. A report on the measures related to buildings and constructions after the termination of mining activities. A report on the objectives and primary content of mine closure measures. A report on the options available for the area s future use. An estimate of the schedule and costs of termination measures

11 Benefits of a Closure Management Plan Public participation: Public participation is essential to successful closure planning. Closure planning usually starts early in the project, at the same time with the EIA process, and relies heavily on the views of the stakeholders on what the post mining uses of the proposed mine site should be and what is their view of the local community after the mine has closed. Predictability: Commonly agreed goals for mine closure help in reducing uncertainties about what is expected from the closure process. This, together with appropriate planning and costing of the actions needed to fulfill the goals, helps in estimating the costs of closure and including the costs on balance sheets. Continuity: Changes of ownership and management are frequent in mining. A Closure Management Plan helps in maintaining the original goals and focus through these changes all the way until the end of the operations. Prevention is better than cure: The CMP defines the physical, chemical and biological conditions of the site that facilitate the agreed post mining land uses. It is usually less expensive to achieve these conditions by preventing pollution and problems of physical stability during planning and operation of the mine than to try to fix the issues at the closure phase. Continuous closure: The most common approach to mine closure is that of continuous closure in which closure actions are taken throughout the life of the mine. For instance, individual waste facilities or sections of facilities may be closed years before the cessation of mining. Continuous reduction of risks: Perhaps the most common form of continuous closure is reduction of risks and unknowns related to closure during the operation of the mine. For instance, long term weathering tests of tailings materials and cover structures are often made and the facilities that have already been closed are monitored to estimate the performance of the closure methods. Financial issues: Many jurisdictions require financial sureties to guarantee that enough funds will be available for mine closure at all times. Mine closure plans and the cost estimates involved can be used to define the amounts of funds required for closure and, with continuous closure, the estimated costs of the remaining closure actions. Demonstrating closability: An up to date CMP can be used to demonstrate that the mine can be closed safely at all times during operation. It also serves as a basis for planning the mine's transition to care and maintenance if that becomes necessary.

12 Closure Management Plan & Action Plan Contextual information Purpose, scope and status of the plan Site operator (especially for official CMP documents) Site characteristics Legal obligations Closure management Management structure and responsibilities CMP Review schedule and procedures Commitments related to closure (if appropriate) Target outcomes of closure (objectives) Stakeholder consultation Analysis of risks and opportunities Post mining land uses Identification of closure issues to define closure objectives Scope of the CMP and the closure Closure objectives (=goals), interim goals (milestones), verification

13 Closure Management Plan & Action Plan Action plans How the individual objectives will be achieved Which issues need to be addressed to achieve the goal For each closure issue: Actions, timing, responsibilities, resources, costs Monitoring of success Costs of closure and financial arrangements Full costs of closure (estimate, incl. variation) Estimated cost schedule Financial arrangements, reference to surety Post closure management plan May be one section of the Action Plan or a separate plan Annexes Detailed plans for the actions listed in the Action Plan Reports etc. of the completed actions

14 Action Plan (Tailings Management Facility B) 2: Tailings Management Facility B Task no Action Timing Responsibility Resources Verification Cost Feasibility study Site environmental Siting 2-01 Preliminary siting of TMF B Pre feasibility manager officer + team approved $ Conceptualise post closure use Feasibility study Site environmental 2-02 and land forms Feasibility manager officer + team Report $ Site environmental Feasibility study officer + team + Report 2-03 Feasibility manager consultant approved $ Conceptualise and list cover structure options Study the geological, hydrological and geotechnical data of the TMF B site Contribute to engineering design of TMF B Compare final TMF B structures to planned and update CMP Design long term field tests for tailings materials Site environmental Site environmental 2-04 Feasibility officer officer + team $ Planning and Site environmental Review final 2-05 construction officer Environmental team design docs $ Site environmental 2-06 Construction officer Environmental team CMP updated $ Site environmental Environmental team 2-07 Startup phase officer + consultant Test plan $ Startup phase, Site environmental Environmental team Annual 2-08 Start long term field tests annually officer + consultant reports Design long term field tests for May 15th Site environmental Environmental team Approved 2-09 tailings covers 2018 officer + consultant report $ etc. etc. etc. etc. etc. etc. etc. $ $ /a (analyses)

15 Financial provisions for closure Mine closure requires considerable resources and funding. These costs should be taken into account already in the feasibility planning stage. Financial sureties are often employed to ensure that enough funds will be available for mine closure at all times Usually required in legislation. Sometimes separate for waste facilities. Determination of the correct amount is excessively difficult Enough but not prohibitive Default: Closure in absence of the mine operator The scope of the surety needs to be clearly defined as well CMP is of great help here Should not be a substitute for proper mine closure but an incentive Reduction of liabilities with continuous closure

16 CMP is kept up to date Three main ways of doing this Regular intervals The most common way; legislation or permits may require this Financial department surely likes this (reduction of liabilities) With changes in the project With new data or more advanced planning stage One of the main goals of the closure process is constant reduction of risks and uncertainties This is why many of the actions in the Action Plan aim at reducing unknowns already during operation Utilization of monitoring data Specific research and field tests to aid in closure planning

17 Updating CMP with project changes

18 Mines are operated for closure The idea behind Closure Management and regular updating of the CMP is to make sure that the mine is operated for closure. Designs, plans and operation should not jeopardize the objectives of closure but contribute to them The principle of continuous closure: close what you can when you have cash flow, personnel, and equipment in place Mines have to be able to prove that they can be closed safely at all times Especially important during long lasting care and maintenance periods Continuous reduction of risks, unknowns, and (financial) liabilities

19 The final closure phase and post closure monitoring The final closure phase starts with the decision to end mining This usually gives a maximum of a few years to prepare for final closure Transition from the operational phase to decommissioning and final closure: Technical planning for decommissioning and reclamation Making sure that all agreements related to closure are fulfilled Monitoring is employed to verify that the objectives of closure have been met and no environmental or social risks remain In some jurisdictions monitoring is required for relinquishment Some post closure maintenance is usually required (e.g., passive water treatment structures) It is advisable to analyze the closure process afterwards to learn from it

20 Thank you! mineclosure.gtk.fi

A global view of integrated closure and legacy planning

A global view of integrated closure and legacy planning 18 September 2013 A global view of integrated closure and legacy planning Mine Closure 2013, Eden Project, Cornwall Dr. William Adams General manager, Legacy and Closure A changing business climate The

More information

Slope Stability Management Framework

Slope Stability Management Framework Slope Stability Management Framework For the assessment, evaluation, prioritization and mitigation of slope stability concerns. 2013/06/19 The Slope Stability Management Framework provides guidance to

More information

Fire Sprinklers Working Group Final Report

Fire Sprinklers Working Group Final Report Introduction The Building Act received Royal Assent on March 25, 2015. The Act aims to establish more consistent building requirements across British Columbia and create a more robust and modern building

More information

Presented by: Remy Norbert DUHUZE Director/ER&PC REMA

Presented by: Remy Norbert DUHUZE Director/ER&PC REMA Presented by: Remy Norbert DUHUZE Director/ER&PC REMA 1 Presentation Outline What is Environment, Social and Economic Impact Assessment? Objectives and Principles of EIA EIA background & regulations Stakeholders

More information

Interim Advice Note 76 / 06 ASSESSMENT PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL ASSESSMENT. Contents

Interim Advice Note 76 / 06 ASSESSMENT PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL ASSESSMENT. Contents Interim Advice Note 76 / 06 VOLUME 11 SECTION 1: ENVIRONMENTAL ASSESSMENT INTRODUCTION PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL ASSESSMENT Contents 1. Introduction and Application 2. Aims and Objectives

More information

Non-Metallic Mining Reclamation Checklist

Non-Metallic Mining Reclamation Checklist Eau Claire County DEPARTMENT OF PLANNING AND DEVELOPMENT Eau Claire County Courthouse, Rm. 1510 721 Oxford Avenue Eau Claire, Wisconsin 54703-5481 (715) 839-4741 f Housing & Community Development 839-6240

More information

VCA Guidance Note. Contents

VCA Guidance Note. Contents Contents 1. Introduction... 2 2. Who can register a VCA?... 2 3. VCAs and sustainable development... 3 4. Verifying conservation performance... 4 4.1 Transparent, voluntary commitments... 4 4.2 Independent

More information

SOCIETY OF FIRE PROTECTION ENGINEERS POSITION STATEMENT P THE ROLE OF THE FIRE PROTECTION ENGINEER IN THE CONSTRUCTION DESIGN PROCESS

SOCIETY OF FIRE PROTECTION ENGINEERS POSITION STATEMENT P THE ROLE OF THE FIRE PROTECTION ENGINEER IN THE CONSTRUCTION DESIGN PROCESS SOCIETY OF FIRE PROTECTION ENGINEERS POSITION STATEMENT P-02-07 THE ROLE OF THE FIRE PROTECTION ENGINEER IN THE CONSTRUCTION DESIGN PROCESS March, 2007 Society of Fire Protection Engineers - 1 - Position

More information

FAQ S about Restoration Planning FROM THE Department of Ecology WEBSITE:

FAQ S about Restoration Planning FROM THE Department of Ecology WEBSITE: FAQ S about Restoration Planning FROM THE Department of Ecology WEBSITE: http://www.ecy.wa.gov/programs/sea/sma/st_guide/smp/restoration/qanda.html Notations in parentheses are staff notes directing you

More information

Mining as a scar on the landscape

Mining as a scar on the landscape Mine Closure 2012 A.B. Fourie and M. Tibbett (eds) 2012 Australian Centre for Geomechanics, Perth, ISBN 978-0-9870937-0-7 https://papers.acg.uwa.edu.au/p/1208_21_burge/ H. Burge Environmental Resources

More information

MADRID MINING LANDSCAPE Western Planner/Nevada APA Conference. A New Mexico Abandoned Mine Land (AML) Program Community-Based Planning Project

MADRID MINING LANDSCAPE Western Planner/Nevada APA Conference. A New Mexico Abandoned Mine Land (AML) Program Community-Based Planning Project MADRID MINING LANDSCAPE 2013 Western Planner/Nevada APA Conference A New Mexico Abandoned Mine Land (AML) Program Community-Based Planning Project Presented by: Ken Romig, ASLA Associate, Dekker/Perich/Sabatini

More information

for Biosphere Reserves

for Biosphere Reserves Sustainable Tourism in Biosphere Reserves in Central and Eastern Europe Tourism Management Plans for Biosphere Reserves Ecological Tourism in Europe - E.T.E. e.v. Page 1 What is a Tourism Management Plan?

More information

Aim to Reclaim. Introduction

Aim to Reclaim. Introduction Aim to Reclaim Introduction Welcome to Aim to Reclaim, a virtual lab that takes you inside the world of copper mining. You may remember that the mining process involves four important phases: Exploration,

More information

Sustainable Port Master Planning

Sustainable Port Master Planning Sustainable Port Master Planning AAPA Energy & Environment Seminar Vancouver, BC John D. Pauling, P.E., BCEE National Transportation Director September 14, 2016 What is Sustainable Port Master Planning?

More information

SECTION E. Realizing the Plan

SECTION E. Realizing the Plan SECTION E Realizing the Plan 60 DESIGN REGINA - OFFICIAL COMMUNITY PLAN SECTION E Realizing the Plan Design Regina has been an ambitious plan-making exercise, with a high level of community, stakeholder,

More information

DRR in URBAN PLANNING PROCESS in ISTANBUL

DRR in URBAN PLANNING PROCESS in ISTANBUL DRR in URBAN PLANNING PROCESS in ISTANBUL Geomatic Engineer, MSc. Emin Yahya MENTEŞE Directorate of Earthquake & Ground Analysis ISTANBUL-Some facts Housing more than 15 million inhabitants Most crowded

More information

ITS Concept Development Activity Descriptions

ITS Concept Development Activity Descriptions ITS Concept Development Activity Descriptions October 2015 Procedures are subject to change without notice. Check the NJDOT website to ensure this is the current version. Table of Contents Concept Development

More information

Resolution XII NOTING also that with the increasingly rapid urbanization, wetlands are being threatened in two principle ways:

Resolution XII NOTING also that with the increasingly rapid urbanization, wetlands are being threatened in two principle ways: 12 th Meeting of the Conference of the Parties to the Convention on Wetlands (Ramsar, Iran, 1971) Punta del Este, Uruguay, 1-9 June 2015 Resolution XII.10 Wetland City 1 Accreditation of the Ramsar Convention

More information

SEMSWA s Role in the Land Development Process

SEMSWA s Role in the Land Development Process SEMSWA s Role in the Land Development Process One of SEMSWA s responsibilities is to ensure that any new development or redevelopment within its service area is designed and constructed in compliance with

More information

Surface-Mining Land Reclamation Program KANSAS

Surface-Mining Land Reclamation Program KANSAS Surface-Mining Land Reclamation Program KANSAS Division of Conservation Responsibilities Administering Surface-Mining Land Conservation & Reclamation Act (SMLCRA) Surface Mining Land Conservation & Reclamation

More information

Biodiversity Action Plan Background Information for discussion purposes

Biodiversity Action Plan Background Information for discussion purposes Biodiversity Action Plan Background Information for discussion purposes Our commitment As directed by Council, The City of Calgary has agreed to sign the Durban Commitment, an international agreement on

More information

Draft Resolution XII.10

Draft Resolution XII.10 12 th Meeting of the Conference of the Parties to the Convention on Wetlands (Ramsar, Iran, 1971) Punta del Este, Uruguay, 1-9 June 2015 Ramsar COP12 DR10, Rev. 2 21:45, 8 June Draft Resolution XII.10

More information

A Notification under Article 12 of Regulation (EU) No 1025/2012 1

A Notification under Article 12 of Regulation (EU) No 1025/2012 1 EUROPEAN COMMISSION ENTERPRISE AND INDUSTRY DIRECTORATE-GENERAL Sustainable Growth and EU 2020 Standards for Boosting Competitiveness Brussels, 02/07/2014 A Notification under Article 12 of Regulation

More information

Gord McKenna PEng, PGeol 1 Richard Dawson PhD, PEng, PGeol 2

Gord McKenna PEng, PGeol 1 Richard Dawson PhD, PEng, PGeol 2 CLOSURE PLANNING PRACTICE AND LANDSCAPE PERFORMANCE AT 57 CANADIAN AND U.S. MINES Gord McKenna PEng, PGeol 1 Richard Dawson PhD, PEng, PGeol 2 1 Syncrude Canada Ltd, PO Bag 4009 MD X302, Fort McMurray,

More information

IMAS nd Edition Director, United Nations Mine Action Service (UNMAS), DC2 0650, United Nations, New York, NY 10017, USA

IMAS nd Edition Director, United Nations Mine Action Service (UNMAS), DC2 0650, United Nations, New York, NY 10017, USA 2 nd Edition 2003-01-01 Marking Mine and UXO hazards Director, United Nations Mine Action Service (UNMAS), DC2 0650, United Nations, New York, NY 10017, USA E-mail: mineaction@un.org Telephone: (1 212)

More information

Spatial / Land Use Planning System in Slovakia

Spatial / Land Use Planning System in Slovakia SEA and spatial planning in Slovakia: Current practices and lessons for practical application of the EC Directive Szentendre, April 14-16, 2004 Spatial / Land Use Planning System in Slovakia Spatial planning

More information

Procedure for the Approval of New Fire Detection and Alarm Technologies

Procedure for the Approval of New Fire Detection and Alarm Technologies VdS Guidelines for Automatic Fire Detection and Fire Alarm Systems VdS 3469en Procedure for the Approval of New Fire Detection and Alarm Technologies VdS 3469en : 2016-01 (01) Publisher and publishing

More information

Environmental Impact Assessment. York Glasgow Edinburgh

Environmental Impact Assessment. York Glasgow Edinburgh Environmental Impact Assessment York Glasgow Edinburgh Our Services Our Approach EIA (Environmental Impact Assessment) ASSESSMENTS Environmental Impact Assessment (EIA) Environmental Statements and Reports

More information

Managing our Landscapes Conversations for Change

Managing our Landscapes Conversations for Change Managing our Landscapes Conversations for Change Frequently Asked Questions The new State Government is committed to a significant reform program that will change the way natural resources are managed.

More information

Appendix A. Planning Processes. Introduction

Appendix A. Planning Processes. Introduction 1 Planning Processes Introduction This appendix outlines a number of planning processes which are used in the Auckland Region to support the effective management of development in the region s rural and

More information

Manitoba. Round Table. for Sustainable. Development

Manitoba. Round Table. for Sustainable. Development Annual Report 2004-2005 Manitoba Round Table for Sustainable Development Manitoba Round Table for Sustainable Development Annual Report 2004 2005 (1 April 2004 to 31 March 2005) 1 Table of Contents MESSAGE

More information

JOINT DECLARATION BETWEEN THE EUROPEAN UNION AND THE REPUBLIC OF INDIA ON A PARTNERSHIP FOR SMART & SUSTAINABLE URBANISATION. New Delhi, 6 Oct 2017

JOINT DECLARATION BETWEEN THE EUROPEAN UNION AND THE REPUBLIC OF INDIA ON A PARTNERSHIP FOR SMART & SUSTAINABLE URBANISATION. New Delhi, 6 Oct 2017 JOINT DECLARATION BETWEEN THE EUROPEAN UNION AND THE REPUBLIC OF INDIA ON A PARTNERSHIP FOR SMART & SUSTAINABLE URBANISATION New Delhi, 6 Oct 2017 The Republic of India and the European Union, CONSIDERING

More information

Securities Dealing Policy

Securities Dealing Policy Securities Dealing Policy INTRODUCTION PURPOSE AND OBJECTIVES As a public company, CSL is bound by laws governing the conduct for buying, selling and otherwise dealing in securities. This document sets

More information

Land Development. Remediation Stakeholders in a Challenging Economy. Jim Purves, B.Sc., P.Ag. Presented By:

Land Development. Remediation Stakeholders in a Challenging Economy. Jim Purves, B.Sc., P.Ag. Presented By: Land Development Remediation Stakeholders in a Challenging Economy Presented By: Jim Purves, B.Sc., P.Ag. OUTLINE Former oil and gas activities on traditionally agricultural land are now being re-evaluated

More information

Western Pennsylvania Conservancy Clairton & Harrison Community Greening Assessment Projects Request for Proposals July 2018

Western Pennsylvania Conservancy Clairton & Harrison Community Greening Assessment Projects Request for Proposals July 2018 Western Pennsylvania Conservancy Clairton & Harrison Community Greening Assessment Projects Request for Proposals July 2018 Proposal Information The Western Pennsylvania Conservancy (WPC) is seeking proposals

More information

Green Infrastructure and Adaptive Management

Green Infrastructure and Adaptive Management Green Infrastructure and Adaptive Management A New Synergy One Water August 27, 2014 Tina Wolff, PE Imagine 1 23 September the result 2014 Prepared by the Green Infrastructure Implementation Task Force

More information

5. Initiating a restoration project

5. Initiating a restoration project 5. Initiating a restoration project CONTRIBUTING TO CONSERVATION In many parts of the country, restoration planting is your last and only option for repairing or rebuilding damaged native communities so

More information

Sustainable Urban Drainage Systems (SuDS): Design and Implementation

Sustainable Urban Drainage Systems (SuDS): Design and Implementation Sustainable Urban Drainage Systems (SuDS): Design and Implementation Climate Northern Ireland in collaboration with Institution of Civil Engineers and Business in the Community/Arena Network Thursday 5th

More information

TORONTO DISTRICT SCHOOL BOARD SCHOOLS WITHIN MIXED USE BUILDINGS: COMMERCIAL AND CONDOMINIUM BUILDINGS. Planning and Priorities Committee

TORONTO DISTRICT SCHOOL BOARD SCHOOLS WITHIN MIXED USE BUILDINGS: COMMERCIAL AND CONDOMINIUM BUILDINGS. Planning and Priorities Committee 23 Report No. 15-05-2615 TORONTO DISTRICT SCHOOL BOARD SCHOOLS WITHIN MIXED USE BUILDINGS: COMMERCIAL AND CONDOMINIUM BUILDINGS TO Planning and Priorities Committee 10 June 2015 RECOMMENDATION IT IS RECOMMENDED

More information

Policy for management and protection of the coast

Policy for management and protection of the coast Policy for management and protection of the coast Policy for management and protection of the coast Mona Ohlsson Samhällsbyggnadsförvaltningen Ystads kommun, 2008 3 THE MUNICIPALITY GUIDELINES REGARDING

More information

Highland Council Allotment Policy

Highland Council Allotment Policy Highland Council Allotment Policy 1. Introduction 1.1 Allotment gardening offers the benefit of a healthy lifestyle all year round that is active, sustainable and socially inclusive. The Highland Council

More information

The New EMC Directive 2004/108/EC

The New EMC Directive 2004/108/EC The New EMC Directive 2004/108/EC In the process of this review I have tried to spell out in words what is often referred to as a section number while also keeping to location information as used in the

More information

(1135/2016) Translation from Finnish Legally binding only in Finnish and Swedish Ministry of Economic Affairs and Employment, Finland

(1135/2016) Translation from Finnish Legally binding only in Finnish and Swedish Ministry of Economic Affairs and Employment, Finland Translation from Finnish Legally binding only in Finnish and Swedish Ministry of Economic Affairs and Employment, Finland Electrical Safety Act (1135/2016) By decision of Parliament, the following is enacted:

More information

COMMISSION DELEGATED REGULATION (EU) /... of

COMMISSION DELEGATED REGULATION (EU) /... of EUROPEAN COMMISSION Brussels, 29.6.2017 C(2017) 4408 final COMMISSION DELEGATED REGULATION (EU) /... of 29.6.2017 amending Commission Delegated Regulation (EU) No 151/2013 of 19 December 2012 supplementing

More information

20 International Conference of The Coastal Society THE ROLE OF PLANNED UNIT DEVELOPMENTS IN ENVIRONMENTAL MANAGEMENT IN THE COASTAL ZONE

20 International Conference of The Coastal Society THE ROLE OF PLANNED UNIT DEVELOPMENTS IN ENVIRONMENTAL MANAGEMENT IN THE COASTAL ZONE th 20 International Conference of The Coastal Society THE ROLE OF PLANNED UNIT DEVELOPMENTS IN ENVIRONMENTAL MANAGEMENT IN THE COASTAL ZONE Kathleen E. Semon, University of South Carolina Braxton C. Davis,

More information

Managing technical risks

Managing technical risks Aon Global Risk Consulting Managing technical risks Choosing the right protection for your investments. Our offer at a glance Introduction...3 Fire Protection...5 Fire protection advice and planning Design

More information

RIAWA Revegetation Planning Workshop. Mine Closure Planning. By Suellen Davey 18 April

RIAWA Revegetation Planning Workshop. Mine Closure Planning. By Suellen Davey 18 April RIAWA Revegetation Planning Workshop Mine Closure Planning By Suellen Davey 18 April 2007 www.doir.wa.gov.au Closure Plan Guidelines DoIR aim to release Draft Closure Plan Guidelines by July 07 for general

More information

ST. MARY S SOIL CONSERVATION DISTRICT (SMSCD) AND DPW&T CONCEPT EROSION AND SEDIMENT CONTROL AND STORMWATER MANAGEMENT GUIDELINES AND CHECKLIST

ST. MARY S SOIL CONSERVATION DISTRICT (SMSCD) AND DPW&T CONCEPT EROSION AND SEDIMENT CONTROL AND STORMWATER MANAGEMENT GUIDELINES AND CHECKLIST St. Mary s Soil Conservation District 26737 Radio Station Way, Suite B Leonardtown, MD 20650 Phone: 301-475-8402 ext. 3 Fax: 301-475-8391 www.stmarysscd.com St. Mary s County Government Department of Public

More information

The New EMC Directive 2004/108/EC

The New EMC Directive 2004/108/EC The New EMC Directive 2004/108/EC In the process of the review I have tried to spell out in words what is often referred to as a section number. This helps reduce the need to flip pages as one reads this.

More information

Amy Burbidge North Northants Joint Planning and Delivery Unit Tresham Garden Village

Amy Burbidge North Northants Joint Planning and Delivery Unit Tresham Garden Village Amy Burbidge North Northants Joint Planning and Delivery Unit Tresham Garden Village Location Location Background Garden Village promoted through preparation of Joint Core Strategy ENC supportive, others

More information

Nature & Biodiversity

Nature & Biodiversity Nature & Biodiversity Urban ecosystems are key to protecting biodiversity in cities and other urban areas. Cities can play an important role in hosting rare and endangered species and habitat types. Biodiversity

More information

QUARRY REHABILITATION PLANS Specifications (version 1.3)

QUARRY REHABILITATION PLANS Specifications (version 1.3) For all our quarries, a rehabilitation plan must be developed from the outset. It is an integral part of the quarrying plan and provides for progressive and co-ordinated rehabilitation whenever possible.

More information

AGENDA ITEM: IOWA. west] that were not FISCAL IMPACT. the City of Clive. STAFF REVIEW. Resolution II. Amendment PREPARED BY: REVIEWED BY:

AGENDA ITEM: IOWA. west] that were not FISCAL IMPACT. the City of Clive. STAFF REVIEW. Resolution II. Amendment PREPARED BY: REVIEWED BY: AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: March 7, 2016 AGENDA ITEM: Consideration of approval of a resolution approving Engineering Services Amendment No. 1 with

More information

Miami Valley Regional Planning Commission Regional Land Use Planning

Miami Valley Regional Planning Commission Regional Land Use Planning Miami Valley Regional Planning Commission Regional Land Use Planning This document provides an overall approach on the region-based land use planning process, outlining the major tasks and work elements

More information

Geological disposal program of Switzerland

Geological disposal program of Switzerland Lucoex-Conference and Workshop 2015 Geological disposal program of Switzerland June 2015 Tim Vietor Geological repositories for Switzerland HLW repository (period analysed: 1 Mio. a) L/ILW repository (period

More information

CHAPTER 12 IMPLEMENTATION

CHAPTER 12 IMPLEMENTATION CHAPTER 12 IMPLEMENTATION The 2010 Town of Denton Comprehensive Plan is intended to capture a vision of the future of Denton. As such, it provides a basis for a wide variety of public and private actions

More information

Exemptions Interprofessional practice: Architects and engineers are exempt for work which is incidental to their practice.

Exemptions Interprofessional practice: Architects and engineers are exempt for work which is incidental to their practice. Landscape Architecture Licensure Laws ASLA Summary of Provisions MAINE Maine Revised Statutes: Title 32, Chapter 3 A Code of Maine Rules: Chapter 2, Section 288 Type of Law: Title act. Maine State Board

More information

Post - Construction Hydromodification Development Requirements

Post - Construction Hydromodification Development Requirements Condensed Version - Interim Low Impact Development / Hydromodification Guidelines, City of Lompoc 1 Post - Construction Hydromodification Development Requirements I. PURPOSE A. The purpose of these requirements

More information

I. INTRODUCTION SITE DESCRIPTION

I. INTRODUCTION SITE DESCRIPTION Request for Proposals Design Services for the Visitor Access and Engagement Project at Roy s Redwoods Open Space Preserve Marin County Parks & Open Space Preserve Woodacre, Marin County, CA November 12,

More information

ASSA ABLOY ANTI-BRIBERY POLICY

ASSA ABLOY ANTI-BRIBERY POLICY 1(11) ASSA ABLOY ANTI-BRIBERY POLICY 2(11) Dear Colleague, Stockholm, 1 November 2011 ASSA ABLOY is committed to growing its business and conducting itself in accordance with the highest ethical standards

More information

Arun Nayar Senior Vice President, Finance and Treasurer

Arun Nayar Senior Vice President, Finance and Treasurer Arun Nayar Senior Vice President, Finance and Treasurer November 18, 2010 Forward-Looking Statements / Safe Harbor Certain statements in this presentation are forward-looking statements within the meaning

More information

PART 1. Background to the Study. Avenue Study. The Danforth

PART 1. Background to the Study. Avenue Study. The Danforth The Danforth 1.1/ Study Purpose & Key Municipal Goals 1.2/ The Local Advisory Committee 1.3/ The Project Team 1.4/ Study Process/Summary of Method 1.5/ Summary of Consultation 1.1 Study Purpose and Key

More information

Spatial and Economic Master Planning. Resilient, healthy and happy places to live, work and learn

Spatial and Economic Master Planning. Resilient, healthy and happy places to live, work and learn Spatial and Economic Master Planning Resilient, healthy and happy places to live, work and learn Leisure Integrated planning expertise Economy Driven Design By 2050, 70% of the world s population will

More information

Procedures for Environmental Impact Assessment in Cambodia

Procedures for Environmental Impact Assessment in Cambodia Investment Seminar Tokyo, 15 March 2013 Procedures for Environmental Impact Assessment in Cambodia Prepared by: Mr. DUONG Samkeat, Deputy Director of EIA Department, Ministry of Environment, Kingdom of

More information

RECLAMATION. We help you plan, assess, design, construct and manage your mine reclamation and closure project.

RECLAMATION. We help you plan, assess, design, construct and manage your mine reclamation and closure project. RECLAMATION We help you plan, assess, design, construct and manage your mine reclamation and closure project. RWE Technology International 18/04/2017 PAGE 1 CLOSURE PLANING Any professional mine closure

More information

HOUSING ELEMENT GOALS, OBJECTIVES, AND POLICIES

HOUSING ELEMENT GOALS, OBJECTIVES, AND POLICIES HOUSING ELEMENT GOALS, OBJECTIVES, AND POLICIES Goal 6 Maintain and enhance the supply of decent, safe, energy efficient and affordable housing and maximize viable options and opportunities for present

More information

AILA CPD TREE OF KNOWLEDGE DESIGNING AND CONSTRUCTING

AILA CPD TREE OF KNOWLEDGE DESIGNING AND CONSTRUCTING AILA CPD TREE OF KNOWLEDGE This Tree of Knowledge provides a list of core competencies on which the CPD framework will evolve, and is designed to provide a filing repository for future CPD resources. DESIGNING

More information

RESOLUTION TO REMOVE THE STATUE OF ROBERT E. LEE FROM LEE PARK

RESOLUTION TO REMOVE THE STATUE OF ROBERT E. LEE FROM LEE PARK ATTACHMENT B RESOLUTION TO REMOVE THE STATUE OF ROBERT E. LEE FROM LEE PARK BE IT RESOLVED that the City of Charlottesville shall remove the statue of Robert E. Lee from the park currently known as Lee

More information

Describing the Integrated Land Management Approach

Describing the Integrated Land Management Approach Describing the Integrated Land Management Approach ISBN No. 978-0-7785-8902-0 (Online Edition) Pub No. I/422 What is Integrated Land Management? Integrated land management (ILM) is the strategic, planned

More information

FIRE AND LIFE SAFETY EDUCATOR II NFPA 1035, Chapter 5, 2015 Edition

FIRE AND LIFE SAFETY EDUCATOR II NFPA 1035, Chapter 5, 2015 Edition Official Skill Sheets for Practical Skills Evaluation Ontario, Canada NFPA 1035, Chapter 5, 2015 Edition National Fire Protection Association Standard for Fire and Life Safety Educator Professional Qualifications

More information

CITY OF EAU CLAIRE, WISCONSIN REQUEST FOR PROPOSALS

CITY OF EAU CLAIRE, WISCONSIN REQUEST FOR PROPOSALS CITY OF EAU CLAIRE, WISCONSIN REQUEST FOR PROPOSALS Commercial Development Opportunity 617 South Barstow Street Parcel 02-0071 The City of Eau Claire is seeking proposals for the commercial development

More information

IUCN World Heritage Advice Note Environmental Assessment & World Heritage

IUCN World Heritage Advice Note Environmental Assessment & World Heritage FINAL DRAFT, 07 June 2013 1 IUCN World Heritage Advice Note Environmental Assessment & World Heritage This Advice Note is intended to provide States Parties and other stakeholders with guidance on integrating

More information

Planning and Growth Management Committee

Planning and Growth Management Committee STAFF REPORT ACTION REQUIRED By-law to Require and Govern the Construction of Green Roofs in Toronto Date: October 29, 2008 To: From: Wards: Reference Number: Planning and Growth Management Committee Chief

More information

Implementing sustainable water strategy through development industry engagement

Implementing sustainable water strategy through development industry engagement Implementing sustainable water strategy through development industry engagement Ian Director, Organica Engineering, Melbourne, Australia E-mail: iadams@organicaeng.com.au Edward Cotter Sustainability Leader,

More information

SOUTH AFRICA S PREPARATIONS FOR HABITAT III COMMON AFRICAN POSITION FOR HABITAT III. Habitat III Urban Breakfast 5 October 2016

SOUTH AFRICA S PREPARATIONS FOR HABITAT III COMMON AFRICAN POSITION FOR HABITAT III. Habitat III Urban Breakfast 5 October 2016 SOUTH AFRICA S PREPARATIONS FOR HABITAT III COMMON AFRICAN POSITION FOR HABITAT III Habitat III Urban Breakfast 5 October 2016 Context and Background 1. Africa intends actively shaping the New Urban Agenda,

More information

Ashbridges Bay Erosion and Sediment Control Project

Ashbridges Bay Erosion and Sediment Control Project Ashbridges Bay Erosion and Sediment Control Project Project Brief Overview Toronto and Region Conservation Authority, in partnership with the City of Toronto, intends to carry out remedial erosion control

More information

Environmental Impact Assessment for Waterway Restoration Projects. Chris John, Technical Director Ecus Ltd.

Environmental Impact Assessment for Waterway Restoration Projects. Chris John, Technical Director Ecus Ltd. Environmental Impact Assessment for Waterway Restoration Projects Chris John, Technical Director Ecus Ltd. Environmental Impact Assessment for Waterway Restoration Projects What is Environmental Impact

More information

Coastal Climate Change Vulnerability and Flexible Adaptation Planning: the Cockburn Sound Coastal Alliance Experience

Coastal Climate Change Vulnerability and Flexible Adaptation Planning: the Cockburn Sound Coastal Alliance Experience Coastal Climate Change Vulnerability and Flexible Adaptation Planning: the Cockburn Sound Coastal Alliance Experience Presentation to Climate Change Forum by Doug Vickery Manager Infrastructure Services,

More information

RULEBOOK ON ELECTROMAGNETIC COMPATIBILITY

RULEBOOK ON ELECTROMAGNETIC COMPATIBILITY RULEBOOK ON ELECTROMAGNETIC COMPATIBILITY ("Official Gazette of RS, issue No. 13/2010) I INTRODUCTION Scope Article 1 This Rulebook stipulates the essential requirements that shall be met with regard to

More information

Making equipment decisions

Making equipment decisions Making equipment decisions in a changing landscape of refrigerant legislation A QUICK GUIDE As the HVAC and building management industry navigates the complex and ever-changing refrigerant landscape, many

More information

Y. ORMIERES. Fire risk analysis method for nuclear installations

Y. ORMIERES. Fire risk analysis method for nuclear installations Y. ORMIERES Fire risk analysis method for nuclear installations 2 Fire risk analysis method for nuclear installations A position on the management of fire safety analysis in nuclear installations by specifying:

More information

OPEN SPACE CHAPTER 7: OVERVIEW. Preserve open space to protect natural resources, enhance character and provide passive recreation opportunities

OPEN SPACE CHAPTER 7: OVERVIEW. Preserve open space to protect natural resources, enhance character and provide passive recreation opportunities CHAPTER 7: OPEN SPACE OVERVIEW Ridgefield has made tremendous progress permanently preserving areas of town as open space. Open space preservation can serve many important purposes, including: protect

More information

Assessing the impact of smallscale wind energy proposals on the natural heritage

Assessing the impact of smallscale wind energy proposals on the natural heritage Scottish Natural Heritage Assessing the impact of smallscale wind energy proposals on the natural heritage Guidance March 2016 Version 3 1 Contents 1. Introduction. 3 2. Encouraging a spatial approach

More information

Event Management CHECKLIST

Event Management CHECKLIST CHECKLIST Event Management The following Checklist is intended to provide general information to assist clients in managing and minimising the risks associated with organising and conducting an event.

More information

Case Study Presentation of the Downtown Brampton Flood Protection Class EA

Case Study Presentation of the Downtown Brampton Flood Protection Class EA Case Study Presentation of the Downtown Brampton Flood Protection Class EA Presented by: Kenneth M. Dion, Project Director Port Lands Integration, Waterfront Toronto (formerly Senior Manager, TRCA) At:

More information

HERITAGE A SUPLEMENT TO TOOLKIT ON FORMULATION OF CITY DEVELOPMENT PLAN. Focus on. Ministry Of Housing and Urban Poverty Alleviation

HERITAGE A SUPLEMENT TO TOOLKIT ON FORMULATION OF CITY DEVELOPMENT PLAN. Focus on. Ministry Of Housing and Urban Poverty Alleviation A SUPLEMENT TO TOOLKIT ON FORMULATION OF CITY DEVELOPMENT PLAN Focus on HERITAGE Ministry Of Urban Development Ministry Of Housing and Urban Poverty Alleviation GOVERNMENT OF INDIA SUPLEMENT TOOLKIT ON

More information

TABLE OF CONTENTS HISTORIC PRESERVATION ELEMENT I. INTRODUCTION HP. A. Purpose HP B. Assessment and Conclusions...

TABLE OF CONTENTS HISTORIC PRESERVATION ELEMENT I. INTRODUCTION HP. A. Purpose HP B. Assessment and Conclusions... TABLE OF CONTENTS HISTORIC PRESERVATION ELEMENT I. INTRODUCTION... 1 - HP A. Purpose... 1 - HP B. Assessment and Conclusions... 1 - HP II. GOAL, OBJECTIVES AND POLICIES... 3 - HP GOAL 1: PROTECTION AND

More information

EIA process in Malaysia. Approaches and Strategies. Way Forward

EIA process in Malaysia. Approaches and Strategies. Way Forward PUBLIC PARTICIPATION APPROACHES AND STRATEGIES UNDER THE EIA PROCESS IN MALAYSIA By Norhayati Mohamad Yusof Principal Assistant Director Department of Environment Malaysia AECEN REGIONAL WORKSHOP Strengthening

More information

TEHRAN LONG TERM URBAN RAIL PLAN

TEHRAN LONG TERM URBAN RAIL PLAN TEHRAN LONG TERM URBAN RAIL PLAN Introduction and Methodology Introduction Greater Tehran is currently one of the most populated mega cities in the world with an estimated population of 14 million inhabitants

More information

For the Design, Installation, Commissioning & Maintenance of Fire Detection and Fire Alarm Systems

For the Design, Installation, Commissioning & Maintenance of Fire Detection and Fire Alarm Systems BAFE Scheme: SP203-1 Version 7.1: January 2019 FIRE SAFETY REGISTER Fire Protection Industry Scheme, Reference SP203-1 For the Design, Installation, Commissioning & Maintenance of Fire Detection and Fire

More information

Scope of Services. River Oaks Boulevard (SH 183) Corridor Master Plan

Scope of Services. River Oaks Boulevard (SH 183) Corridor Master Plan Scope of Services River Oaks Boulevard (SH 183) Corridor Master Plan PROJECT AREA The project area consists of the River Oaks Boulevard (SH 183) corridor bounded by SH 199 at the northern end and the Trinity

More information

WELCOME TO THE CHOUTEAU GREENWAY ECONOMIC DEVELOPMENT WORKING GROUP!

WELCOME TO THE CHOUTEAU GREENWAY ECONOMIC DEVELOPMENT WORKING GROUP! WELCOME TO THE CHOUTEAU GREENWAY ECONOMIC DEVELOPMENT WORKING GROUP! Chouteau Greenway Steering Committee and Working Groups Overview Overview January 9, 2019 Chouteau Greenway will transform St. Louis

More information

Guidance Note 8 Cultural Heritage

Guidance Note 8 Cultural Heritage This Guidance Note 8 corresponds to Performance Standard 8. Please also refer to the Performance Standards 1-7 as well as the corresponding Guidance Notes for additional information. Bibliographical information

More information

Parks Master Plan Implementation: Phase I Waterfront Use and Design REPORT #: September 7, 2016 File #

Parks Master Plan Implementation: Phase I Waterfront Use and Design REPORT #: September 7, 2016 File # 0 'O DI Lan-171-14 1 - THE CORPORATION OF THE TOWN OF COBOURG..,. STAFF REPORT TO: FROM: Mayor and Members of Council Dean A. Hustwick, Director of Recreation and Culture DATE OF MEETING: Committee of

More information

Chapter 1 Introduction

Chapter 1 Introduction Chapter 1 Introduction Chapter 1 provides an overview of the fundamental aspects of the industries that influence electronic safety and security (ESS) design. Table of Contents Introduction to Safety

More information

PUBLIC SERVICES ELEMENT GOALS / POLICIES / MEASURES

PUBLIC SERVICES ELEMENT GOALS / POLICIES / MEASURES PUBLIC SERVICES ELEMENT GOALS / POLICIES GOALS / POLICIES / MEASURES Authority The Public Services Element addresses provision of municipal services to City residents. The following paragraphs provide

More information

On the way to HARMONY. Ewa Kaczmarczyk

On the way to HARMONY. Ewa Kaczmarczyk On the way to HARMONY Ewa Kaczmarczyk 1 The structure of Poland The transport network Road s influence on a landscape Recent political changes in Poland What was done in previous years The SWOT analyses

More information

Request for Proposals For the purchase and redevelopment of Cityowned property in the Historic Downtown. 109 South Boyd Street

Request for Proposals For the purchase and redevelopment of Cityowned property in the Historic Downtown. 109 South Boyd Street 300 West Plant Street Winter Garden, FL 407-656-4111 RFP # 15-103 Request for Proposals For the purchase and redevelopment of Cityowned property in the Historic Downtown District, generally located at:

More information

V. Vision and Guiding Principles

V. Vision and Guiding Principles V. Vision and Guiding Principles The Master Plan for the Powers Ferry Corridor seeks a foundation in the desires of the community. At times, various elements of the community offered opposing viewpoints,

More information

Humber Bay Shores Precinct Plan Final Report

Humber Bay Shores Precinct Plan Final Report STAFF REPORT ACTION REQUIRED Humber Bay Shores Precinct Plan Final Report Date: May 21, 2010 To: From: Wards: Reference Number: Etobicoke York Community Council Director, Community Planning, Etobicoke

More information