1 Fisher Slough Tidal Marsh Restoration Project Scaling Down the Restoration Planning & Analysis Framework to Evaluate Project Alternatives Project Sponsor/Partners The Nature Conservancy Dike District #3 Drainage District #17 Skagit County WWAA Local Landowners Tech. Adv. Committee WDFW SRSC USFWS NOAA NRCS SCD Consulting Team Tetra Tech Moffatt & Nichol URS Corp. Miller Consulting River Restoration Northwest Stream Restoration Design Symposium February 2009 Photo: Kirsten Morse

2 TODAY S PRESENTATION TOPICS Project Location, Scale, Hydrologic, Geomorphic & Habitat Context Restoration Objectives & Project Constraints Scaling the Restoration Planning Framework Downward Examples of Alternatives Analysis, Projected Outcomes & Plans Lessons Learned

3 PROJECT LOCATION, SCALE, GEOMORPHIC, HYDROLOGIC & HABITAT CONTEXT (A) Skagit River Runoff & High Flows Skagit River Floodplain Skagit Bay Tidal Cycling Tributary Watersheds

4 PROJECT LOCATION, SCALE, GEOMORPHIC, HYDROLOGIC & HABITAT CONTEXT (B) FLOODGATE BIG DITCH DRAINAGE CROSSING LEVEE SETBACK & TIDAL MARSH RESTORATION

5 PRIMARY RESTORATION OBJECTIVES Create Diverse Array of Native Vegetative Tidal Marsh Communities Restore Juvenile Chinook, Skagit Delta Rearing Areas Improve Fish Passage for Coho and Chum Spawning Access Improve Flood and Sediment Storage

6 SCALING DOWN THE RESTORATION PLANNING FRAMEWORK Skagit Chinook Recovery Plan Linkages Perform Detailed Baseline Assessments Evaluate Degradation, Changes & Effects Identify Project Constraints, Risks & Uncertainties Develop Design Criteria Evaluation of Concept Design Alternatives Selection & Implementation of the Plan

7 FINAL DESIGN ALTERNATIVES ANALYSIS Phase 1 Floodgate Retrofit w/ Self Regulating Structure Phase 2 Big Ditch Crossing Realignment Alignments Phase 3 Levee Setback & Tidal Marsh Restoration

8 Phase 1 Floodgate Retrofit w/ Regulating Closure Gates

9 Elevation (ft,navd88) FLOODGATE - OBSERVED FALL/WINTER HYDROLOGY Fisher Slough - Tidal & Flood Hydrology Fall & Winter Periods SKAGIT FISHER_US (EXIST) Fisher Flood Stage EXISTING SUMMER OPS POST FLOOD GATES REOPEN GATES OPEN 10 5 FALL FLOOD OPS GATES CLOSED 0 10-Sep- 17-Sep- 24-Sep- 1-Oct- 8-Oct- 15-Oct- 22-Oct- 29-Oct- 5-Nov- 12-Nov- 19-Nov- 26-Nov- 3-Dec- Date (PST)

10 Elevation (ft,navd88) FLOODGATE - OBSERVED SPRING/SUMMER HYDROLOGY Fisher Slough - Tidal & Flood Hydrology Spring Runoff & Summer SKAGIT FISHER_US (EXIST) JUVENILE CHINOOK MIGRATION PERIOD GATES CLOSING MISS HIGH TIDES LACK OF MAINTENANCE TO LASH GATES OPEN IN 2008 SHOULD BE FULLY OPEN 0 17-Jun Jun Jun Jun Jun Jun Jun Jun-08 Date (PST)

11 Existing Floodgate Degradation & Effects Floodgate Effects Gates closed 58% of time Operations & maintenance deficiencies Increases in water temperatures

12 Regulating Floodgate Retrofit Design Criteria Floodgate Design Criteria Expand/Change Gate Operations to Coincide w/ Juvenile Chinook Occupancy Increase % Time Gates Are Open Evaluate Juvenile Salmon Swim Criteria Maximize Tidal Prism Exchange & Marsh Inundation Areas Improve in Flood Storage Evaluate 1-Pair & 3-Pair Gates to Determine Functional & Cost Differences

13 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Peak Flows (cfs) 200,000 Regulating Floodgate Redefine Seasonal Operating Periods HIGH FLOOD RISK LESS RISK LOW RISK FALL/WINTER Skagit PERIOD River, Mt. SPRING Vernon Gage SUMMER Seasonality of Annual MIGRATION Peak Flows IRRIGATION & Juvenile Chinook Occupancy Periods for Fisher Slough PERIOD PERIOD Annual Peak Flow s Juvenile Chinook Estuarine Rearing Period 175, ,000 Juvenile Chinook Estuarine Rearing Period (High Occupancy) 125, ,000 Summer Irrigation Season - Gates Continually Open Operation 75,000 50,000 25,000 Future Juvenile Chinook Spring Migration Delayed Gate Operations (Open/Close ~10ft) 0 Months Winter Flood Standard Gate Operations (Open/Close ~7ft)

14 Water Surface Elevation (ft-navd88) Velocity (fps) 3 Regulating Floodgates Fish Passage Criteria REGULATING GATES ALLOW NEARLY FULL TIDAL INUNDATION Regulating Floodgates - Spring/Summer Period w/ Levee Setback Velocity Skagit Elevation Slough Elevation EXCEEDANCE OF FISH 22-JunPASSAGE VEL. CRITERIA (MINIMAL) 24-Jun 26-Jun 28-Jun Date -8-10

15 Regulating Floodgate Design Alts. Summary Criteria Exist 1-Pair 3-Pair % Time Open (Total) 42% 80% 80% % Time Fish Passage (Velocity) N/A 95% >95% Tidal Inundation Area (acres) Tidal Prism Volume (acre-ft) Flood Tidal Peak Risks N/A Mixed Gates Flood Storage

16 Phase 2 Big Ditch Drainage Crossing Realignment

17 Phase 2 Big Ditch Drainage Crossing Realignment

18 Phase 3 Levee Setback, Tidal Marsh Restoration Evaluating 2 Distinct Alternatives Passive Marsh Restoration Active Marsh Restoration Hydraulic Modeling of Alternatives Simple Semi-quantitative Conceptual Models Vegetation Occurrence Erosion and Sedimentation Potential

19 Phase 3 Levee Setback, Tidal Marsh Restoration Passive Approach

20 Phase 3 Levee Setback, Tidal Marsh Restoration Passive Approach

21 Phase 3 Levee Setback, Tidal Marsh Restoration Active Approach

22 Phase 3 Levee Setback, Tidal Marsh Restoration Active Approach

23 Elevation (ft,navd88) Levee Setback & Tidal Marsh Restoration Flood Storage Improvements Fisher Slough - Tidal & Flood Hydrology Fall & Winter Periods SKAGIT FISHER_US (EXIST) Fisher Flood Stage FISHER_ACTIVE ft Reduction In Flood Stage Sep- 17-Sep- 24-Sep- 1-Oct- 8-Oct- 15-Oct- 22-Oct- 29-Oct- 5-Nov- 12-Nov- 19-Nov- 26-Nov- 3-Dec- Date (PST)

24 Lessons Learned & Closing Complex Sites Need Detailed Site Assessments, Characterization & Data Collection Design Guidance for Tide/Floodgates Needed Vegetation & Inundation Data Collection & Modeling Collaborative Process is Successful Salmon Habitat Restoration and Floodplain Management Complimentary Benefits

25 Thank you.

Boulder County Comprehensive Drilling Plan Surface Owner Meeting. Thursday, Oct. 19, 2017

Boulder County Comprehensive Drilling Plan Surface Owner Meeting. Thursday, Oct. 19, 2017 Boulder County Comprehensive Drilling Plan Surface Owner Meeting Thursday, Oct. 19, 2017 Contact Crestone Crestone Peak Resources Quick Facts www.crestonepeakresources.com cdpboulder@crestonepr.com (720)

More information

Regional Open Space Conservation Plan. Regional Staff Committee January 18, 2018

Regional Open Space Conservation Plan. Regional Staff Committee January 18, 2018 Regional Open Space Conservation Plan Regional Staff Committee January 18, 2018 Schedule We are here Task 1 - Stakeholder Input & Work Plan Dev. v z 2016 2017 2018 Oct Nov Dec Jan Feb Mar Apr May Jun Jul

More information

Boulder County Comprehensive Drilling Plan Surface Owner Meeting. Thursday, Nov. 2, 2017

Boulder County Comprehensive Drilling Plan Surface Owner Meeting. Thursday, Nov. 2, 2017 Boulder County Comprehensive Drilling Plan Surface Owner Meeting Thursday, Nov. 2, 2017 Contact Crestone Crestone Peak Resources Quick Facts www.crestonepeakresources.com cdpboulder@crestonepr.com (720)

More information

Design Guidelines for the Enhancement and Creation of Estuarine Habitats in the Middle Reaches of the Lower Columbia River

Design Guidelines for the Enhancement and Creation of Estuarine Habitats in the Middle Reaches of the Lower Columbia River Design Guidelines for the Enhancement and Creation of Estuarine Habitats in the Middle Reaches of the Lower Columbia River Astoria, May 16, 2012 1 Outline I. Nature of Project/Background II. Approach to

More information

Prioritizing Tidal Wetlands: A Landscape Approach

Prioritizing Tidal Wetlands: A Landscape Approach Prioritizing Tidal Wetlands: A Landscape Approach Laura Brophy Director, Estuary Technical Group Institute for Applied Ecology Corvallis, OR College of Earth, Ocean and Atmospheric Sciences, Oregon State

More information

Iona Island Wastewater Treatment Plant Project. Welcome to Community Workshop 1 January 9, 2019

Iona Island Wastewater Treatment Plant Project. Welcome to Community Workshop 1 January 9, 2019 Iona Island Wastewater Treatment Plant Project Welcome to Community Workshop 1 January 9, 2019 Iona Island Wastewater Treatment Plant Project Lena Zordan POLICY COORDINATOR, LIQUID WASTE SERVICES January

More information

MASTER PLAN KICK-OFF Open House #1A, April 28, 2015

MASTER PLAN KICK-OFF Open House #1A, April 28, 2015 "The beginning is the most important part of the work." Plato, The Republic MASTER PLAN KICK-OFF Open House #1A, April 28, 2015 YOUR CAMPUS PLANNING TEAM Campus Planners Landscape Architects Urban Designers

More information

The Effects of Woody Vegetation on Levees

The Effects of Woody Vegetation on Levees The Effects of Woody Vegetation on Levees Maureen K. Corcoran Assistant Technical Director, Water Resources Infrastructure Vicksburg, MS 26 February 2010 US Army Corps of Engineers Problem Statement What

More information

FISH RESTORATION PROGRAM AGREEMENT Implementing Habitat Restoration Requirements Of The Biological Opinions

FISH RESTORATION PROGRAM AGREEMENT Implementing Habitat Restoration Requirements Of The Biological Opinions FISH RESTORATION PROGRAM AGREEMENT Implementing Habitat Restoration Requirements Of The Biological Opinions Dennis McEwan Department of Water Resources waterways tidal wetlands Whipple et al. 2012: Sacramento-San

More information

Snail Lake Overflow/Grass Lake Optimization Studies. May 2, Ramsey-Washington Metro Watershed District.

Snail Lake Overflow/Grass Lake Optimization Studies. May 2, Ramsey-Washington Metro Watershed District. Snail Lake Overflow/Grass Lake Optimization Studies May 2, 2018 Ramsey-Washington Metro Watershed District. Purpose Purpose: 1. Summarize what s been done 2. Update board on cost vs. benefits of various

More information

The Napa River Flood Protection Project

The Napa River Flood Protection Project The Napa River Flood Protection Project Creating Flood Protection and Restoring Geomorphic and Biological Processes Jeremy Sarrow, Napa County Flood Control & Water Conservation District June 2, 2014.

More information

Millburn, NJ, Residential Area Stormwater Analyses

Millburn, NJ, Residential Area Stormwater Analyses Base Conditions Parameter Files: Millburn, NJ, Residential Area Stormwater Analyses R. Pitt March 12, 2012 1 Millburn Typical Medium Density Home: Source Area Area (acres) Description Roofs 1 0.08 Pitch

More information

Don t Flood The Rodeo! Preparing for Fort Worth s New Arena

Don t Flood The Rodeo! Preparing for Fort Worth s New Arena Don t Flood The Rodeo! Preparing for Fort Worth s New Arena T F M A S P R I N G C O N F E R E N C E APRI L 27 2017 Scott Hubley, P.E., CFM Justin Oswald, P.E., CFM Christopher Johnson, P.E., CFM PHOTO

More information

Restoring Water Ecosystems in NYC Parks

Restoring Water Ecosystems in NYC Parks Restoring Water Ecosystems in NYC Parks Hooked on our Waters Con October 19, 2013 - CUNY Graduate Center Marit Larson NYC Parks Landscape and ecosystem focus Watershed Streams Freshwater wetlands Tidal

More information

Santa Cruz River Master Plan. Presented to the Arizona Floodplain Management Association Spring Conference June 8-10, 2011

Santa Cruz River Master Plan. Presented to the Arizona Floodplain Management Association Spring Conference June 8-10, 2011 Santa Cruz River Master Plan Presented to the Arizona Floodplain Management Association Spring Conference June 8-10, 2011 Introduction Who is FICO? 2 Project Team Kimley-Horn and Associates, Inc. River

More information

Port of San Diego Sea Level Rise Ad Hoc Committee Meeting 1 of 3.. September 18, 2018

Port of San Diego Sea Level Rise Ad Hoc Committee Meeting 1 of 3.. September 18, 2018 Port of San Diego Sea Level Rise Ad Hoc Committee Meeting 1 of 3. September 18, 2018 Agenda Welcome Introductions Rules of the Ad-Hoc Presentation Background Vulnerability Assessment Results Non-Agenda

More information

North Branch of Cypress Creek Ecological Restoration: A Comprehensive Approach to Stream Restoration

North Branch of Cypress Creek Ecological Restoration: A Comprehensive Approach to Stream Restoration North Branch of Cypress Creek Ecological Restoration: A Comprehensive Approach to Stream Restoration Rocky Powell Clear Creeks Consulting, LLC Keith D. Tate, P.E. BayLand Consultants & Designers, Inc.

More information

Lake Nokomis Shoreline Enhancement Project

Lake Nokomis Shoreline Enhancement Project Lake Nokomis Shoreline Enhancement Project Community Meeting 2 February 13, 2018 Agenda Current Problems Project Goals Project Status Existing Conditions Community Input Draft Schematic Design Long-term

More information

WLAC Facilities Committee Meeting. May 15, 2017

WLAC Facilities Committee Meeting. May 15, 2017 Campus Program Report WLAC Facilities Committee Meeting May 15, 2017 Page 1 DSA completed the initial review June 24, 2016 and the Design Builder is proceeding through the back check process. DSA reports

More information

BASS PONDS, MARSH, & WETLAND HABITAT RESTORATION PROJECT

BASS PONDS, MARSH, & WETLAND HABITAT RESTORATION PROJECT FACT SHEET BASS PONDS, MARSH, & WETLAND HABITAT RESTORATION PROJECT MINNESOTA VALLEY NATIONAL WILDLIFE REFUGE, MINNESOTA ENVIRONMENTAL MANAGEMENT PROGRAM LOCATION Three areas located on the Minnesota Valley

More information

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY Revision No.: 3 Page 1 of 6 I. PURPOSE This policy establishes the steps required for performing the monthly fixed systems inspections and the semi-annual systems testing. Fixed systems include; wet chemical

More information

Ted Perkins, Hydraulic Engineer US Army Corps of Engineers, Seattle District 8/9/2007

Ted Perkins, Hydraulic Engineer US Army Corps of Engineers, Seattle District 8/9/2007 Skagit River Revised Flood Insurance Study Levee Scenario Discussion Ted Perkins, Hydraulic Engineer US Army Corps of Engineers, Seattle District 8/9/2007 Skagit Levee Failure Scenarios Challenges of Defining

More information

LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP ACTIVITIES. Powerpoint Templates. MS4 Statewide Stormwater Summit June 18, 2013

LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP ACTIVITIES. Powerpoint Templates. MS4 Statewide Stormwater Summit June 18, 2013 LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP ACTIVITIES MS4 Statewide Stormwater Summit June 18, 2013 Powerpoint Templates Evan Canfield, Ph.D, P.E. Pima County Regional Flood Control Outline

More information

Chapter PROJECT AUTHORIZATIONS

Chapter PROJECT AUTHORIZATIONS Chapter 1 1.1. PROJECT AUTHORIZATIONS The Mississippi River Nine-Foot Channel Navigation Project was originally authorized by the River and Harbor Act of 1930 (Seventy-First Congress, Session 2, Chapter

More information

Mapping and the 2013 Colorado Floods. Mapping before, during, and after

Mapping and the 2013 Colorado Floods. Mapping before, during, and after Mapping and the 2013 Colorado Floods Mapping before, during, and after Presented by Outline 2013 Floods Floodplain Mapping Before During After 20 counties 21,000 households 6000 sq. mi. 2,132 NFIP claims

More information

City of Norfolk Coastal Flood Mitigation Program. March 13, 2013

City of Norfolk Coastal Flood Mitigation Program. March 13, 2013 City of Norfolk Coastal Flood Mitigation Program March 13, 2013 Topics Brief overview of Norfolk s Coastal Flood Program Data-driven analysis and decision making City-wide vulnerability, project concepts,

More information

Proposed Ranked List of Projects for Capital Budget Funding

Proposed Ranked List of Projects for Capital Budget Funding Proposed Ranked List of Projects for 2015-17 Capital Budget Funding Ecology Publication #: 14-06-033 October 2014 Ecology Publication #: 14-06-033 October 2014 Focus on Proposed Projects for FY 15-17 Floodplains

More information

Regional Restoration Planning:

Regional Restoration Planning: Regional Restoration Planning: A Case Study in Collaborative Restoration Science and Planning Campbell Ingram, Executive Officer NCER August 28, 2018 Co-Equal Responsibilities Act as a primary state agency

More information

TITLOW SHORELINE AND ESTUARY RESTORATION PROJECT DESIGN DEVELOPMENT

TITLOW SHORELINE AND ESTUARY RESTORATION PROJECT DESIGN DEVELOPMENT TITLOW SHORELINE AND ESTUARY RESTORATION PROJECT DESIGN DEVELOPMENT Request for Qualifications South Puget Sound Salmon Enhancement Group with EarthCorps and Metro Parks Tacoma Request for Qualifications:

More information

MEASURED PERFORMANCE DATA FOR

MEASURED PERFORMANCE DATA FOR MEASURED PERFORMANCE DATA FOR HOUSE #4 INVERNESS GARDENS MILLER HOMES FEBRUARY 2013 Submitted to: NYSERDA 17 Columbia Circle Albany, NY 12203 Submitted by: HOMEPIC Team CDH Energy Corp. PO Box 641 Cazenovia,

More information

Heritage Park Irrigation System Inspection Review of Water Use Estimated Water Budget Potential for Savings

Heritage Park Irrigation System Inspection Review of Water Use Estimated Water Budget Potential for Savings Heritage Park Irrigation System Inspection Review of Water Use Estimated Water Budget Potential for Savings Site Visit: January 17, 2008 Address: 611 Village Drive, Suisun City Key Action Items Re-nozzle

More information

Roof Runoff Harvesting Benefits for Regional Conditions in Low Density and Medium Density Residential Areas. Leila Talebi 1 and Robert Pitt 2

Roof Runoff Harvesting Benefits for Regional Conditions in Low Density and Medium Density Residential Areas. Leila Talebi 1 and Robert Pitt 2 Roof Runoff Harvesting Benefits for Regional Conditions in Low Density and Medium Density Residential Areas Leila Talebi 1 and Robert Pitt 2 1Graduate Student, Department of Civil, Construction, and Environmental

More information

Presentation to Parks and Open Space Advisory. Committee September 22, 2016

Presentation to Parks and Open Space Advisory. Committee September 22, 2016 Flood Planning & Preliminary Design Services for South St. Vrain Creek Restoration at Hall Ranch Presentation to Parks and Open Space Advisory Prepared for: Boulder County, Colorado Committee September

More information

Our Wetland Restoration Plan

Our Wetland Restoration Plan Our Wetland Restoration Plan Name/Property name Date Wetland Restoration/Management Template SITE DETAILS Owner Occupier (if different to owner) Location (e.g. access/street address, topographic grid reference

More information

The Ed Roberts Campus Berkeley, CA

The Ed Roberts Campus Berkeley, CA The Ed Roberts Campus Berkeley, CA Anderson Clemenceau Mechanical Option Penn State A.E. Senior Thesis April 14, 2015 Leddy Maytum Stacy Architects, Photo by Tim Griffith ASHRAE Climate Zone 3C 99.6% Heating

More information

Mechanical System Redesign. Dedicated Outdoor Air System. Design Criteria

Mechanical System Redesign. Dedicated Outdoor Air System. Design Criteria Mechanical System Redesign Dedicated Outdoor Air System Design Criteria The outdoor air conditions used were for Philadelphia, Pennsylvania IAP at a 0.4% occurrence. The supply air conditions were developed

More information

WLAC Facilities Committee Meeting. September 18, 2017

WLAC Facilities Committee Meeting. September 18, 2017 Campus Program Report WLAC Facilities Committee Meeting September 18, 2017 Page 1 DSA approved the plans on May 15, 2017. Notice to Proceed was issued June 8, 2017 and the project remains on schedule for

More information

2011 ASLA Design Awards. Westside Creeks Restoration Plan Merit Award AECOM, Fort Collins. Planning & Urban Design

2011 ASLA Design Awards. Westside Creeks Restoration Plan Merit Award AECOM, Fort Collins. Planning & Urban Design 2011 ASLA Design Awards Westside Creeks Restoration Plan Merit Award AECOM, Fort Collins Planning & Urban Design Project Fact Sheet Category of Entry: Rotating Specialty Award: 2011 2011 ASLA Colorado

More information

INEEL (1500) [45] 5.6 C 217 mm 60. Precipitation (mm) Temperature (oc) Month

INEEL (1500) [45] 5.6 C 217 mm 60. Precipitation (mm) Temperature (oc) Month Figure 1. Water balance of a vegetated plot. Plants extract water from throughout the soil profile, to depths that may exceed 2 m in deep soils. In contrast, most water lost by direct evaporation comes

More information

Southeast Extension to RidgeGate Parkway Scoping Booklet

Southeast Extension to RidgeGate Parkway Scoping Booklet Southeast Extension to RidgeGate Parkway Scoping Booklet PUBLIC SCOPING MEETING SCHEDULE Public Scoping Meeting Wednesday, November 2, 2011 6:00pm to 7:30pm City of Lone Tree Recreation Center Willow Room

More information

Shifting Patterns of Water Demand: Socio-Demographic Challenges for Water Managers

Shifting Patterns of Water Demand: Socio-Demographic Challenges for Water Managers Intro Page Shifting Patterns of Water Demand: Socio-Demographic Challenges for Water Managers Gary Woodard, Ass t. Director NSF STC for Sustainability of Semi-Arid Hydrology and Riparian Areas (SAHRA)

More information

New Westminster Downtown Parking Strategy Public Open House #1 September 13, 2012

New Westminster Downtown Parking Strategy Public Open House #1 September 13, 2012 New Westminster Downtown Parking Strategy Public Open House #1 September 13, 2012 The City is preparing a strategy for parking in Downtown New Westminster. The study team and a group of key stakeholders

More information

edmonton.ca/ribbonofgreen #ribbonofgreen

edmonton.ca/ribbonofgreen #ribbonofgreen WHAT IS THE RIBBON OF GREEN? The Ribbon of Green is Edmonton s entire river valley and ravine system. The Ribbon of Green (2018) Project will provide strategic guidance for the southwest and northeast

More information

Terra Nova Rural Park Plan

Terra Nova Rural Park Plan Terra Nova Rural Park Plan Part 1 Getting to know the land The Surrounding Area North Side Airport, River, Trail East Side - Residential West Side- Sturgeon Banks, West Dyke Trail South Side:Terra Nova

More information

Draft Rhode Island Stormwater Design and Installation Standards Manual

Draft Rhode Island Stormwater Design and Installation Standards Manual Draft Rhode Island Stormwater Design and Installation Standards Manual Summary The May 2009 Public Review Draft version of the RI Stormwater Design and Installation Standards Manual consists of approximately

More information

Rt 29 Solutions Hydraulic Planning Advisory Panel. September 14, 2017

Rt 29 Solutions Hydraulic Planning Advisory Panel. September 14, 2017 Hydraulic Planning Advisory Panel September 14, 2017 Agenda Item 1: Introductions Hydraulic Planning Advisory Panel members Technical Team members 2 Agenda item 2: Public Interaction and Feedback Live

More information

Rt 29 Solutions Hydraulic Planning Advisory Panel. September 28, 2017

Rt 29 Solutions Hydraulic Planning Advisory Panel. September 28, 2017 Hydraulic Planning Advisory Panel September 28, 2017 Agenda Item 1: Introductions Hydraulic Planning Advisory Panel members Technical Team members 2 Agenda item 2: Public Interaction and Feedback Live

More information

Microirrigation of Young Blueberries in Florida 1

Microirrigation of Young Blueberries in Florida 1 BULLETIN 301 Microirrigation of Young Blueberries in Florida 1 Dorota Z. Haman, Allen G. Smajstrla, Fedro S. Zazueta, Paul M. Lyrene, Robert T. Pritchard 2 Blueberry production shows great promise as a

More information

(Exhibit A) Site Plan Adoption Detail and Support Information

(Exhibit A) Site Plan Adoption Detail and Support Information McCormick Park Master Site Plan (Exhibit A) Site Plan Adoption Detail and Support Information July, 2003 McCormick Park Site Plans.... 2-3 McCormick Park Site Plan Comparison... 4 Basic Assumptions about

More information

A TWENTY YEAR PLAN TO RESTORE NAPLES BAY. Natural Resources Manager

A TWENTY YEAR PLAN TO RESTORE NAPLES BAY. Natural Resources Manager A TWENTY YEAR PLAN (and visionary guide) TO RESTORE NAPLES BAY Michael R. Bauer, Ph.D. Natural Resources Manager City of Naples City of Naples Natural Resources Division Management Science Restoration

More information

Understanding Drainage Options What s Feasible and Legal. February 2019

Understanding Drainage Options What s Feasible and Legal. February 2019 Understanding Drainage Options What s Feasible and Legal February 2019 Outline for the Presentation Do you need a permit? Does common law apply? Does local government approve it? Will my neighbor allow

More information

PICAYUNE STRAND RESTORATION PROJECT

PICAYUNE STRAND RESTORATION PROJECT PICAYUNE STRAND RESTORATION PROJECT An accelerated design/build restoration of the world s largest sub-division US ARMY CORPS OF ENGINEERS JACKSONVILLE DISTRICT Golden Gate Estates Map showing grid of

More information

HISTORICAL ECOLOGY OF THE DELTA Emerging Concepts about a Spatially Complex and Temporally Dynamic System

HISTORICAL ECOLOGY OF THE DELTA Emerging Concepts about a Spatially Complex and Temporally Dynamic System ITEM REMOVED DUE TO COPYRIGHT STATUS HISTORICAL ECOLOGY OF THE DELTA Emerging Concepts about a Spatially Complex and Temporally Dynamic System Robin Grossinger and Alison Whipple San Francisco Estuary

More information

Hunts Point Landing, Bronx, New York

Hunts Point Landing, Bronx, New York Hunts Point Landing, Bronx, New York Sustainable Shorelines in an Urban Environment John Roebig, PhD. HDR Engineering, Inc. John.Roebig@hdrinc.com Promoting Resilient Shorelines along the Hudson River

More information

Public Information Meeting

Public Information Meeting Lavon Lake Master Plan Revision Public Information Meeting March 10, 2015 Presented By Michael Kinard Lake Manager U.S. Army Corps of Engineers Fort Worth District US Army Corps of Engineers Purpose of

More information

After the Storms: Planning for Louisiana s Future. Larry Ardoin Coastal Protection and Restoration Authority Integrated Planning Team

After the Storms: Planning for Louisiana s Future. Larry Ardoin Coastal Protection and Restoration Authority Integrated Planning Team After the Storms: Planning for Louisiana s Future Larry Ardoin Coastal Protection and Restoration Authority Integrated Planning Team Today s Presentation Background Objectives Draft Master Plan Upcoming

More information

STEERING COMMITTEE MEETING # 5 SEPTEMBER 18, 2018

STEERING COMMITTEE MEETING # 5 SEPTEMBER 18, 2018 STEERING COMMITTEE MEETING # 5 SEPTEMBER 18, 2018 STEERING COMMITTEE MEETING #5 AGENDA 1. Introduction 2. Market Conditions 3. Preliminary Development Concepts 4. Open Discussion 5. Next Steps PLANNING

More information

Construction Progress Report

Construction Progress Report Report Date: 4/8/2017 Subject: Construction Week 2 70% Complete Project: Sunset Pond EWP Stream Reclamation, Fourmile Creek, Boulder County, CO Report By: TJ Burr, Civil Engineer/Stream Restoration Specialist,

More information

Wallkill River. Floodplain Bench Project Phase 1. OCSWCD Kevin Sumner. October 2016 Orange County. Wendell Buckman

Wallkill River. Floodplain Bench Project Phase 1. OCSWCD Kevin Sumner. October 2016 Orange County. Wendell Buckman Wallkill River Floodplain Bench Project Phase 1 October 2016 Orange County OCSWCD Kevin Sumner Wendell Buckman Introduction Location Define the Problem History Location MIDDLETOWN NEWBURGH PROJECT Location

More information

Transfer Station Recycling Update SWANA Technical Session-Waste Diversion 4 2/24/2017 2/28/2017

Transfer Station Recycling Update SWANA Technical Session-Waste Diversion 4 2/24/2017 2/28/2017 Transfer Station Recycling Update SWANA Technical Session-Waste Diversion 4 2/24/2017 1 Todays Outline Roadmap to 70% A look back on how we started.. Vashon yard & food waste Styrofoam & plastic film Resource

More information

Imperviousness & Runoff

Imperviousness & Runoff North Texas Alternative Futures Imperviousness & Runoff A key indicator for comparing alternative future scenarios This powerpoint presents: What is this key indicator? How do the alternative future scenarios

More information

Ecosystem Restoration Business Line Budgeting A Systems Approach

Ecosystem Restoration Business Line Budgeting A Systems Approach Ecosystem Restoration Business Line Budgeting A Systems Approach Laura Orr (NWS), Shawn Phillips (MVM), Greg Steele (NAO) Introduction Chesapeake Bay Bridge Mouth of Mississippi River Bonneville Dam Fish

More information

SECTION 5: REACH RECOMMENDATIONS/MAPS

SECTION 5: REACH RECOMMENDATIONS/MAPS SECTION 5: REACH RECOMMENDATIONS/MAPS This section describes areas of concern and provides specific recommendations for each project reach. Locations of stormwater drains were from GIS coverage supplied

More information

Equipment ATA 12 April 2016

Equipment ATA 12 April 2016 05-00-01 Time limits and Maintenance Frequencies Various JUN 14 1 25-00-01 Charging Head Mk 2 & Accessories WKA26592 WKA26592A 25-60-15 Submersion Actuator K38215 58178-001 AUG 92 JAN 15 Initial Issue

More information

Building Ecological Solutions to Coastal Community Hazards: Guidance and NJ Coastal Community Assistance

Building Ecological Solutions to Coastal Community Hazards: Guidance and NJ Coastal Community Assistance Building Ecological Solutions to Coastal Community Hazards: Guidance and NJ Coastal Community Assistance Stacy Small-Lorenz National Wildlife Federation Restore America s Estuaries Summit New Orleans,

More information

Chapter 5: Natural Resources and Environment

Chapter 5: Natural Resources and Environment NATURAL RESOURCES AND ENVIRONMENT 5-1 5 Chapter 5: Natural Resources and Environment BACKGROUND AND INTENT Urban expansion represents the greatest risk for the future degradation of existing natural areas,

More information

Tri-County Transportation & Land Use Study. Steering Committee Meeting May 14, 2009

Tri-County Transportation & Land Use Study. Steering Committee Meeting May 14, 2009 Tri-County Transportation & Land Use Study Steering Committee Meeting May 14, 2009 Agenda Recap of Study Goals and Objectives Update on CV Land Use Model: Business as Usual (BAU) Growth Scenario Pros vs

More information

Salmon Safe and Stormwater LID Practices

Salmon Safe and Stormwater LID Practices Salmon Safe and Stormwater LID Practices Tye Simpson, PE, LEED AP Director of Engineering /Principal Only 22 of at least 37 historic Chinook populations remain. - State of the Sound 2007, Puget Sound Action

More information

C. WATER. 1. Surface Water Runoff. See Section C.3, Flood Hazard/Mudflow Hazard, page Ground Water

C. WATER. 1. Surface Water Runoff. See Section C.3, Flood Hazard/Mudflow Hazard, page Ground Water C. WATER 1. Surface Water Runoff See Section C.3, Flood Hazard/Mudflow Hazard, page 67. 2. Ground Water Determined not significant by the October 1984 and January 1999 Initial Studies conducted by the

More information

Standardization Programme ( ) Building & Construction Standards Committee

Standardization Programme ( ) Building & Construction Standards Committee Standardization Programme (2012-2013) Building & Construction Standards Committee Projects Title 2012 2013 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1 EN 12811: 2 EN 197-1:2011

More information

San Joaquin River Restoration Program Mendota Pool Bypass and Reach 2B Improvements Project. Restoration Goal Technical Feedback Group

San Joaquin River Restoration Program Mendota Pool Bypass and Reach 2B Improvements Project. Restoration Goal Technical Feedback Group San Joaquin River Restoration Program Mendota Pool Bypass and Reach 2B Improvements Project Restoration Goal Technical Feedback Group March 20, 2014 1:30 pm San Luis and Delta-Mendota Water Authority 842

More information

Stream Restoration: Working with Nature?

Stream Restoration: Working with Nature? Stream Restoration: Working with Nature? Greg Jennings, PhD, PE jenningsenv@gmail.com Ecosystem Restoration activities that initiate or accelerate the recovery of ecosystem health, integrity, and sustainability

More information

Stream Restoration: Working with Nature? Greg Jennings, PhD, PE

Stream Restoration: Working with Nature? Greg Jennings, PhD, PE Stream Restoration: Working with Nature? Greg Jennings, PhD, PE jenningsenv@gmail.com Ecosystem Restoration activities that initiate or accelerate the recovery of ecosystem health, integrity, and sustainability

More information

American Rainwater Catchment Systems Association Introduction to Rainwater Harvesting 100 Level

American Rainwater Catchment Systems Association   Introduction to Rainwater Harvesting 100 Level American Rainwater Catchment Systems Association www.arcsa.org Introduction to Rainwater Harvesting 100 Level Welcome!! Doug Pushard - ARCSA Instructor Jeffrey Adams ARCSA Instructor Level 100 Agenda Morning

More information

Conservation in South Jersey Being Creative with Restoration

Conservation in South Jersey Being Creative with Restoration Conservation in South Jersey Being Creative with Restoration Stewardship on a Shoestring: Public Land Management in Fiscally Constrained Times November, 30, 2011 Conservation and Restoration for Open Space

More information

City of Kingston. North King s Town Secondary Plan Open House + Workshop #1 February 28, 2018

City of Kingston. North King s Town Secondary Plan Open House + Workshop #1 February 28, 2018 City of Kingston North King s Town Secondary Plan Open House + Workshop #1 February 28, 2018 1 event agenda 30 min Panel Review + Discussion 30 min Presentation + Q&A 75 min Workshop Session 15 min Report

More information

An Integrated Approach for Water Management Examples from The Netherlands. Addressing Climate Change and Sea Level Rise

An Integrated Approach for Water Management Examples from The Netherlands. Addressing Climate Change and Sea Level Rise An Integrated Approach for Water Management Examples from The Netherlands Addressing Climate Change and Sea Level Rise Superstorm Sandy Forum College of Staten Island March 8 2013 Water: a challenge and

More information

Green Roof Technology. Karen Liu, Ph.D. Xero Flor International

Green Roof Technology. Karen Liu, Ph.D. Xero Flor International Green Roof Technology Materials, Performance and Design Karen Liu, Ph.D. Xero Flor International Baptist University, October 11 th, 2010 Green Roof, Eco Roof, Roof Garden? specialized roofing system that

More information

The Role of the Landscape Contractor to Conserve Water

The Role of the Landscape Contractor to Conserve Water The Role of the Landscape Contractor to Conserve Water By Richard Restuccia, Sales Leader Western U.S. ValleyCrest Landscape Maintenance rrestuccia@valleycrest.com Abstract Opportunities abound for property

More information

Reducing the Storm Water Footprint of GVSU through BMP s

Reducing the Storm Water Footprint of GVSU through BMP s Reducing the Storm Water Footprint of GVSU through BMP s Association of State Floodplain Managers Grand Rapids, MI June 22, 2016 Dr. Peter J. Wampler 1 Talk Road Map Brief Geomorphic History of the Grand

More information

CHECKLIST FOR PHASE II DRAINAGE REPORT

CHECKLIST FOR PHASE II DRAINAGE REPORT I. COVER SHEET CHECKLIST FOR PHASE II DRAINAGE REPORT A. Name of Project B. Address C. Owner D. Developer E. Engineer F. Submittal date and revision dates as applicable II. GENERAL LOCATION AND DESCRIPTION

More information

Green Design Principles

Green Design Principles Green Design Principles restoration planting Ecosystem restoration, including preserving and enhancing existing vegetation and where feasible, introducing new vegetative communities, benefits the stream

More information

Scarborough Waterfront Project

Scarborough Waterfront Project Scarborough Waterfront Project Public Information Centre #1 Environmental Assessment Terms of Reference September 10, 2014 Agenda Open House Presentation 7:00 to 7:30 pm Presentation 7:30 to 8:15 pm History

More information

Auburn University Basketball Arena:

Auburn University Basketball Arena: Auburn University Basketball Arena: How Building Data Analytics Achieved Energy and O&M Savings While Improving Comfort and Sustainability Eric Moore, PE, CEM, Auburn University Hadas Webb, CEM, Cimetrics

More information

Is a Riparian Restoration Still Viable After 100-year Storm Events Alter the Original Design?

Is a Riparian Restoration Still Viable After 100-year Storm Events Alter the Original Design? Is a Riparian Restoration Still Viable After 100-year Storm Events Alter the Original Design? Sarah Spear Cooke, Ph.D. Seattle, Washington Presentation Outline Introduction The site pre-restoration Restoration

More information

Copyright 2003 IBACOS, Inc. All rights reserved.

Copyright 2003 IBACOS, Inc. All rights reserved. Domestic Hot Water Research Research conducted by Bill Rittelmann Presented by Duncan Prahl Partners for High Performance Homes Meeting Westminster, CO, June 23, 2005 DHW Systems: Current Technologies

More information

Welcome. Tannery and Waterworks Parks Shoreline Improvements Environmental Assessment. Public Information Centre #1 November 27, pm to 8 pm

Welcome. Tannery and Waterworks Parks Shoreline Improvements Environmental Assessment. Public Information Centre #1 November 27, pm to 8 pm Welcome Tannery and Waterworks Parks Shoreline Improvements, Environmental Assessment Tannery and Waterworks Parks Shoreline Improvements Environmental Assessment #1 6 pm to 8 pm Why We Are Here Tannery

More information

Low Impact Development in Coastal South Carolina: A Planning and Design Guide

Low Impact Development in Coastal South Carolina: A Planning and Design Guide Low Impact Development in Coastal South Carolina: A Planning and Design Guide ACE Basin & North Inlet-Winyah Bay National Estuarine Research Reserves Network of 28 Reserves NOAA Program Research, Stewardship,

More information

Efficient Irrigation, Smart Controllers and Climate Appropriate Shade Trees. Clovis Community College Center Clovis, CA

Efficient Irrigation, Smart Controllers and Climate Appropriate Shade Trees. Clovis Community College Center Clovis, CA Efficient Irrigation, Smart Controllers and Climate Appropriate Shade Trees Clovis Community College Center Clovis, CA June 28, 2017 Evapotranspiration Adjustment Factor Study Department of Water Resources

More information

URBAN DESIGN LONDON TRAINING PROGRAMME UDL are pleased to present our programme for April 2013 to March 2014.

URBAN DESIGN LONDON TRAINING PROGRAMME UDL are pleased to present our programme for April 2013 to March 2014. URBAN DESIGN LONDON TRAINING PROGRAMME UDL are pleased to present our programme for April 2013 to March 2014. To help us decide what to focus on we asked our members which subjects they most wanted help

More information

Improving Communities Through the Arroyo Seco Sustainability Campaign and Watershed Assessment

Improving Communities Through the Arroyo Seco Sustainability Campaign and Watershed Assessment Improving Communities Through the Arroyo Seco Sustainability Campaign and Watershed Assessment Arroyo Seco Headwaters in the San Gabriel Mountains Major tributary to the Los Angeles River 44 square mile

More information

Heating and Hot Water

Heating and Hot Water Heating and Hot Water Funding Funding for this class was provided by the Alaska Housing Finance Corporation (AHFC). This course is designed to empower homeowners with the knowledge to live in and maintain

More information

Washington County, Maryland Division of Public Works Policy Manual

Washington County, Maryland Division of Public Works Policy Manual Washington County, Maryland Division of Public Works Policy Manual Subject: Downstream Drainage Easement Category: Land Development Engineering Number: 7-4.1 Date: June 1, 2009 (effective) PURPOSE: The

More information

A watershed is an area of land where all the rain that t falls drains into one water body such as Dickinson Bayou.

A watershed is an area of land where all the rain that t falls drains into one water body such as Dickinson Bayou. A watershed is an area of land where all the rain that t falls drains into one water body such as Dickinson Bayou. How it all works You live in a watershed! You can make a difference! Your storm drain

More information

Old Mill Community Association Bioretention Facility

Old Mill Community Association Bioretention Facility Project Overview This project will install a bioretention facility in a community recreation area owned by the Old Mill Community Association, Inc. Drainage from the area is currently unmanaged and has

More information

April 11, 2016 Park Board Chair and Commissioners General Manager Vancouver Board of Parks and Recreation New Brighton Salt Marsh - Preferred Concept

April 11, 2016 Park Board Chair and Commissioners General Manager Vancouver Board of Parks and Recreation New Brighton Salt Marsh - Preferred Concept TO: FROM: SUBJECT: April 11, 2016 Park Board Chair and Commissioners General Manager Vancouver Board of Parks and Recreation New Brighton Salt Marsh - Preferred Concept RECOMMENDATION A. THAT the Vancouver

More information

River Road New Castle Marsh Restoration Recommendations

River Road New Castle Marsh Restoration Recommendations University of New Hampshire University of New Hampshire Scholars' Repository PREP Reports & Publications Institute for the Study of Earth, Oceans, and Space (EOS) 6-2010 River Road New Castle Marsh Restoration

More information

STREAM BUFFERS

STREAM BUFFERS 88-415 STREAM BUFFERS 88-415-01 PURPOSE In the Kansas City region and throughout the nation, vegetated stream buffers have been clearly shown to protect stream stability and related infrastructure, improve

More information

Canyon Lake Master Plan Revision Public Information Meeting March 18, 2016

Canyon Lake Master Plan Revision Public Information Meeting March 18, 2016 Canyon Lake Master Plan Revision Public Information Meeting March 18, 2016 Marcus Schimank Canyon Lake Manager Capital Regional Office U.S. Army Corps of Engineers Fort Worth District US Army Corps of

More information

Chapter 3 Site Planning and Low Impact Development

Chapter 3 Site Planning and Low Impact Development CHAPTER 3 Site Planning and Low Impact Development Chapter 3 Site Planning and Low Impact Development 3.0 Introduction The City of Charleston requires that major residential, large commercial (>1 acre),

More information