1 DOWNTOWN ORLANDO Community Venues Land Use & Infrastructure Master Plan City of Orlando Council Work Session Prepared By: Glatting Jackson Kercher Anglin Lopez Rinehart, Inc. May 1, 2006

2 AGENDA Community Venues Land Use & Infrastructure Master Plan i. Master Plan Process ii. Schedule iv. Data Collection & Stakeholder Input v. Initial Findings and Project Framework vi. Next Steps

3 Master Plan Process

4 Colonial Drive SR 408 Study Area Tampa Ave Rosalind Ave

5 PROCESS Phase 1: Area Understanding Phase 2: Individual Facility Development Scenarios Phase 3: Facilities Master Plan

6 PROCESS Phase 1: Understanding & Assessment

7 PHASE 1 AREA UNDERSTANDING & ASSESSMENT Elements: Kick-off Meeting Data Collection & Analysis Coordination with Related Work Efforts - Parking Study - Downtown Transportation Plan - Parramore Town Center Plan Initiative Coordination & Facility Prototypes Stakeholder Interviews Physical Assessment & Planning Principles

8 PROCESS Phase 2: Individual Venue Development Scenarios

9 Elements: Community Venues Land Use & Infrastructure Master Plan PHASE 2 INDIVIDUAL VENUE MASTER PLANS Alternative Area Development & Land Use Plans Character Sketches Area Transportation and Parking Plan - Parking Strategy - Bicycle and pedestrian Strategy - Transit and Shuttle Strategy - Vehicle Circulation Strategy Street Design Concepts Phasing Diagram / Action Plan Crime Prevention Through Environmental Design (CPTED) Evaluation Infrastructure Needs Assessment

10 PROCESS Phase 3: Overall Master Plan Vetting, Documentation, And Implementation

11 PHASE 3 PROCESS Elements: Integration of Initiatives Developers Forum Draft Overall Master Plan Land Use & Infrastructure Plan Timing Priorities of Facilities Illustrative Urban Design Plan Public Open House

12 Project Schedule

13 SCHEDULE

14 Data Collection & Stakeholder Input

15 Framework Principles Current / Recent Initiatives: Downtown Transportation Plan Parramore Town Center Plan Downtown & OBT CRA Plans Downtown Outlook Downtown Task Force

16 STAKEHOLDER INTERVIEWS Elected Officials: City Commissioners (Others to be scheduled) County Commissioner Fernandez (Others to be scheduled) Departments: Planning Economic Development Transportation Public Works Fire Police Parks & Recreation Orlando Centroplex Partner Agencies Downtown CRA OBT CRA Orange County Health Department FDOT Orlando Housing Authority Orange County School Board LYNX Orlando Utilities Commission Property Owners: David Van Gelder Jones High School Salvation Army Coalition for the Homeless Hughes Supply Knap Ford School University of Central Florida Florida A&M Law School Community Venues Florida Citrus Sports Orlando Magic OPAC Hines Development

17 Initial Findings & Project Framework

18 Regional Framework Principles

19 REGIONAL FRAMEWORK Florida Hospital Baldwin Park Central Florida Fairgrounds Festival Park ORH

20 REGIONAL FRAMEWORK John Young Pkwy I-4 Old Winter Garden Rd. 408 OBT Recognize and Overcome Barriers

21 REGIONAL FRAMEWORK Connect & Strengthen the Neighborhoods

22 REGIONAL FRAMEWORK Connect Regional Parks & Open Spaces

23 REGIONAL FRAMEWORK Florida Hospital Baldwin Park Fairgrounds Arena Lake Eola Festival Park Citrus Bowl ORH Link Regional Amenities

24 REGIONAL FRAMEWORK Build Affordable Communities

25 REGIONAL FRAMEWORK Realize Value with Public Investment

26 Study Area Framework Principles

27 Colonial Drive PROJECT FRAMEWORK Tampa Ave Rosalind Ave SR 408 Study Area

28 PROJECT FRAMEWORK Events Center Citrus Bowl Church Street Corridor Performing Arts Center Study Area

29 PROJECT FRAMEWORK Existing SF Residential Existing MF Residential Planned Residential Projects Residential Land Uses

30 PROJECT FRAMEWORK Connect and Strengthen Neighborhoods

31 PROJECT FRAMEWORK Downtown Outlook Community Character Plan

32 PROJECT FRAMEWORK Match Urban Form to Community Investments

33 PROJECT FRAMEWORK Historic Districts Cultural/Community Venues Cultural & Civic Amenities

34 PROJECT FRAMEWORK Celebrate and Strengthen Cultural & Civic Amenities

35 PROJECT FRAMEWORK Religious Facilities Social Services Federal and State Buildings Existing Lymmo Proposed Lymmo Existing Bus Routes Existing Social Infrastructure

36 PROJECT FRAMEWORK Recognize Existing Social Services and Accommodate Future Needs

37 PROJECT FRAMEWORK Retail and Commercial Office Planned Office & Commercial Projects Retail and Office Uses

38 PROJECT FRAMEWORK Enhance Pedestrian Amenities in Core Retail Areas

39 PROJECT FRAMEWORK Force Mains 24 or larger Gravity Lines Lift Stations Drainage Wells OUC Chiller Plants Utility Infrastructure

40 PROJECT FRAMEWORK Leverage Public Investments to Spur Private Development

41 Maximize use of existing parking Public Parking Private Parking Community Venues Land Use & Infrastructure Master Plan PROJECT FRAMEWORK Existing Lymmo Lymmo Expansion Parking Infrastructure

42 Maximize use of existing parking Community Venues Land Use & Infrastructure Master Plan PROJECT FRAMEWORK Maximize Use of Existing Parking

43 PROJECT FRAMEWORK Highways Arterials Collectors Roadway Infrastructure

44 PROJECT FRAMEWORK Enhance the Public Realm and Connect Streets

45 PROJECT FRAMEWORK Lynx Bus Routes Existing Lymmo Proposed Lymmo Proposed Light Rail Proposed Commuter Rail Transit Infrastructure

46 Rely on alternative modes of transportation Community Venues Land Use & Infrastructure Master Plan PROJECT FRAMEWORK Rely on Alternative Modes of Transportation

47 PROJECT FRAMEWORK Design Regional Facilities as Good Neighbors

48 1. Match urban form to community investments 2. Celebrate and strengthen civic and cultural amenities 3. Enhance the public realm and connect streets 4. Enhance pedestrian amenities in key retail areas 5. Connect and strengthen neighborhoods 6. Leverage public investments to spur private development 7. Maximize use of existing parking 8. Rely on alternative modes of transportation 9. Recognize existing social services and accommodate future needs. 10. Design regional facilities as good neighbors

49 DOWNTOWN ORLANDO Community Venues Land Use & Infrastructure Master Plan City of Orlando Council Work Session Prepared By: Glatting Jackson Kercher Anglin Lopez Rinehart, Inc. May 1, 2006

Whatever you can do or dream you can, begin it. Boldness has genius, power, and magic in it. Begin it now. Johann Wolfgang von Goethe

Whatever you can do or dream you can, begin it. Boldness has genius, power, and magic in it. Begin it now. Johann Wolfgang von Goethe Whatever you can do or dream you can, begin it. Boldness has genius, power, and magic in it. Begin it now. Johann Wolfgang von Goethe Photograph courtesy of Joel Mann Table of Contents Part A: Physical

More information

Chapter 1: Introduction

Chapter 1: Introduction Chapter 1: Introduction The Penn Avenue Community Works Corridor Vision and Implementation Framework presents an integrated communitybased vision and a coordinated, long-term implementation framework for

More information

CHAPTER 7: Transportation, Mobility and Circulation

CHAPTER 7: Transportation, Mobility and Circulation AGLE AREA COMMUNITY Plan CHAPTER 7 CHAPTER 7: Transportation, Mobility and Circulation Transportation, Mobility and Circulation The purpose of the Transportation, Mobility and Circulation Chapter is to

More information

DOMINION BOULEVARD CORRIDOR STUDY AND ECONOMIC DEVELOPMENT STRATEGIC PLAN A MODEL FOR CHESAPEAKE S FUTURE

DOMINION BOULEVARD CORRIDOR STUDY AND ECONOMIC DEVELOPMENT STRATEGIC PLAN A MODEL FOR CHESAPEAKE S FUTURE DOMINION BOULEVARD CORRIDOR STUDY AND ECONOMIC DEVELOPMENT STRATEGIC PLAN A MODEL FOR CHESAPEAKE S FUTURE Overview I. Draft Plan Process II. Draft Plan Overview a. Market Analysis b. Master Land Use Plan

More information

Hillsborough County MPO Transit Study. Citizens Team Workshop Wednesday, February 28 th, 2006 Hillsborough Community College - Brandon

Hillsborough County MPO Transit Study. Citizens Team Workshop Wednesday, February 28 th, 2006 Hillsborough Community College - Brandon Hillsborough County MPO Transit Study Citizens Team Workshop Wednesday, February 28 th, 2006 Hillsborough Community College - Brandon What is the MPO Transit Study? An effort to look at the full range

More information

1 October Dear Citizens of Charlotte and Mecklenburg County,

1 October Dear Citizens of Charlotte and Mecklenburg County, 1 October 2011 Dear Citizens of Charlotte and Mecklenburg County, As co-chairs of the Center City 2020 Vision Plan Steering Committee, we are proud to present the Center City 2020 Vision Plan, which sets

More information

Gary & Regional Investment Project. October 27, Creating Tomorrow Today Comprehensive Regional Plan - NIRPC

Gary & Regional Investment Project. October 27, Creating Tomorrow Today Comprehensive Regional Plan - NIRPC Creating Tomorrow Today 2040 Comprehensive Regional Plan Gary & Regional Investment Project October 27, 2010 Creating Tomorrow Today - 2040 Comprehensive Regional Plan - NIRPC What is NIRPC? - Northwestern

More information

REVIEW AND EVALUATION OF REGIONAL LAND USE

REVIEW AND EVALUATION OF REGIONAL LAND USE REVIEW AND EVALUATION OF REGIONAL LAND USE AND TRANSPORTATION SCENARIOS #220831 Environmental Justice Task Force October 7, 2014 VISION 2050 Process Development of Guiding Vision for Land Use and Transportation

More information

Selected Area Study. Vision Plan Draft

Selected Area Study. Vision Plan Draft East Polk County Selected Area Study Draft 10.30.08 Contents Guiding Principles...4 Context Conclusions...5 Current Context...8 Scenarios...9 Scenario: Status Quo...10 Scenario: Connected & Directed Growth...12

More information

ELK GROVE GENERAL PLAN VISION

ELK GROVE GENERAL PLAN VISION 2-1 CHAPTER 2: 2-2 CREATING OUR The Community Vision for Elk Grove, expressed through a Vision Statement and a series of Supporting Principles, is a declaration of the kind of community that Elk Grove

More information

INDEPENDENCE BOULEVARD AREA PLAN. June 24, 2008

INDEPENDENCE BOULEVARD AREA PLAN. June 24, 2008 INDEPENDENCE BOULEVARD AREA PLAN Public Meeting #1 June 24, 2008 Tonight s Agenda Introduction Welcome and Ground Rules Overview Presentation Purpose of the Plan What Brings Us Here? A Tour of the Corridor

More information

Northeast Everglades Natural Area

Northeast Everglades Natural Area Northern Palm Beach County Natural Areas Master Plan Northeast Everglades Natural Area August 3, 2006 GLATTING JACKSON KERCHER ANGLIN LOPEZ RINEHART, INC. Community Planning 1 Public Land Partners Agenda

More information

Welcome! Please sign-in and participate in the activities in the registration area before finding your seat. Thank you!

Welcome! Please sign-in and participate in the activities in the registration area before finding your seat. Thank you! Welcome! Please sign-in and participate in the activities in the registration area before finding your seat. Thank you! Planning Kickoff July 31, 2018 University of Baltimore Public Planning Kick-off Agenda

More information

St. Louis Park Wooddale LRT Station Site development guidelines

St. Louis Park Wooddale LRT Station Site development guidelines St. Louis Park Wooddale LRT Station Site development guidelines November 2013 OVERVIEW St. Louis Park s convenient location as a neighbor to Minneapolis means you re only minutes away from some of the

More information

Transit / Housing Oriented Redevelopment

Transit / Housing Oriented Redevelopment Broward County Urban Planning and Redevelopment Department Kick-Off Meeting October 24, 2007 Transit / Housing Oriented Redevelopment 1 Future Land Use 2 Broward County Charter Voters approved in 1974.

More information

CONTEXT: the Highway, the River + the Railroads run through us.

CONTEXT: the Highway, the River + the Railroads run through us. CONTEXT: the Highway, the River + the Railroads run through us. I-25 36 In the past they have divided us, now we have an opportunity to unite us. I-76 I-270 I-76 CSU I-25 LEGEND Cut + Cover River North

More information

Preliminary Plan Framework: Vision and Goals

Preliminary Plan Framework: Vision and Goals Preliminary Plan Framework: Vision and Goals Draft: May 2015 Introduction Since the Town of Milliken s comprehensive plan was last updated in 2010, the community was heavily impacted by the 2013 flood,

More information

PLAN ELEMENTS WORKSHOP. April 5, 2016

PLAN ELEMENTS WORKSHOP. April 5, 2016 PLAN ELEMENTS WORKSHOP April 5, 2016 needs more housing. But there is no one-size fits-all solution. Every neighborhood has its own character. In some places, density is not only appropriate it is badly

More information

Future Proposed Development

Future Proposed Development Future Proposed Development on and around Link light rail s Capitol Hill Station Meeting September 24, 2012 Tonight s Agenda 6:00 pm Open House 6:30 pm Introductions Richard Conlin, City of Seattle Councilmember/Sound

More information

History: a Grand Urban Boulevard

History: a Grand Urban Boulevard History: a Grand Urban Boulevard 1890 1910: At its peak, Euclid Avenue, "Millionaire's Row," was considered the second most beautiful urban street in the country next to Fifth Avenue in Manhattan. 1910-2030:

More information

4- PA - LD - LIVELY DOWNTOWN. LD - Background

4- PA - LD - LIVELY DOWNTOWN. LD - Background 4- PA - LD - LIVELY DOWNTOWN LD - Background The downtown has been the service centre for the community since the city s inception and the area continues to supply people with their personal services,

More information

A BLUEPRINT FOR BROCKTON A CITY-WIDE COMPREHENSIVE PLAN

A BLUEPRINT FOR BROCKTON A CITY-WIDE COMPREHENSIVE PLAN A BLUEPRINT FOR BROCKTON A CITY-WIDE COMPREHENSIVE PLAN Public Meeting October 2016 1 Plan Summary and Discussion Public Meeting May 4 2017 City of Brockton Bill Carpenter, Mayor Department of Planning

More information

Downtown by Design: The Bradenton CRA Master Plan. Glatting Jackson, Inc Robert Charles Lesser & Co. Downtown Bradenton Development Authority

Downtown by Design: The Bradenton CRA Master Plan. Glatting Jackson, Inc Robert Charles Lesser & Co. Downtown Bradenton Development Authority Downtown by Design: The Bradenton CRA Master Plan Glatting Jackson, Inc Robert Charles Lesser & Co. Downtown Bradenton Development Authority October 3, 2006 Our Goal for Today: Introduce Project Introduce

More information

VIRGINIA / LAKE HIGHLAND TRANSPORTATION AND LAND USE STUDY

VIRGINIA / LAKE HIGHLAND TRANSPORTATION AND LAND USE STUDY VIRGINIA / LAKE HIGHLAND TRANSPORTATION AND LAND USE STUDY COMMUNITY MEETING #2 - PRESENTATION OVERVIEW 1 INTRODUCTION 2 CONTEXT STUDIES 3 VISION FRAMEWORK 4 DEVELOPMENT SCENARIOS 2 1 INTRODUCTION Project

More information

Broadway District Specific Plan. Community Workshop #2 February 23,2016

Broadway District Specific Plan. Community Workshop #2 February 23,2016 Broadway District Specific Plan Community Workshop #2 February 23,2016 1 Agenda Introductions Project Progress Status Upcoming Milestones Emerging Framework Land Use Urban Design Circulation Infrastructure

More information

Independence Boulevard Area Plan Planning Committee Public Comment May 18, 2010

Independence Boulevard Area Plan Planning Committee Public Comment May 18, 2010 Independence Boulevard Area Plan Planning Committee Public Comment May 18, 2010 Presentation Outline Focus on Key Recommendations within Draft Plan Plan Purpose and Development Process Draft Plan Policies

More information

CHAPTER 7: VISION AND ACTION STATEMENTS. Noble 2025 Vision Statement

CHAPTER 7: VISION AND ACTION STATEMENTS. Noble 2025 Vision Statement CHAPTER 7: VISION AND ACTION STATEMENTS This chapter presents the vision, policy and action statements that transform the comprehensive planning study, an analysis of Noble s past, future trends and community

More information

The University District envisions, in its neighborhood

The University District envisions, in its neighborhood Envisioning the University District Link Light Rail in Seattle s neighborhoods CIY OF SEALE CONCEP-LEVEL SAION AREA PLANNING RECOMMENDAION RESOLUION # 30165 EXHIBI L Vision 08.2000 he University District

More information

Pine Island Road Corridor Master Plan

Pine Island Road Corridor Master Plan RECOMMENDED DEVELOPMENT PLAN Figure 9: Del Prado Village District Conceptual Framework The Conceptual Framework (Figure 8) for development of the Pine Island Corridor is to encourage mixed-use development

More information

HISTORIC TOWN CENTER MASTER PLAN CITY COUNCIL PRESENTATION APRIL 3, 2012

HISTORIC TOWN CENTER MASTER PLAN CITY COUNCIL PRESENTATION APRIL 3, 2012 HISTORIC TOWN CENTER MASTER PLAN CITY COUNCIL PRESENTATION APRIL 3, 2012 REQUESTED CITY COUNCIL ACTIONS Certification of the Final Program Environmental Impact Report (PEIR); and, Approval of General Plan

More information

Corridor Vision. 1Pursue Minnehaha-Hiawatha Community Works Project. Mission of Hennepin County Community Works Program

Corridor Vision. 1Pursue Minnehaha-Hiawatha Community Works Project. Mission of Hennepin County Community Works Program 1Pursue Minnehaha-Hiawatha Community Works Project Minnehaha-Hiawatha Community Works is a project within the Hennepin Community Works (HCW) program. The mission of the HCW program is to enhance how the

More information

IMPLEMENTING SOMERSET COUNTY S INVESTMENT FRAMEWORK

IMPLEMENTING SOMERSET COUNTY S INVESTMENT FRAMEWORK IMPLEMENTING SOMERSET COUNTY S INVESTMENT FRAMEWORK SMART CONSERVATION THROUGH SMART GROWTH NJ LAND CONSERVATION RALLY March 22, 2014 Laurette Kratina, PP, AICP, Supervising Planner Somerset County Planning

More information

EXISTING COMPREHENSIVE PLAN

EXISTING COMPREHENSIVE PLAN EXISTING COMPREHENSIVE PLAN Town Center Land Use Element: V. LAND USE POLICIES Town Center Mercer Island's business district vision as described in "Your Mercer Island Citizen-Designed Downtown" was an

More information

Town Center (part of the Comprehensive Plan)

Town Center (part of the Comprehensive Plan) Town Center (part of the Comprehensive Plan) Mercer Island Town Center Looking North (2014) In 1994, a year-long process culminated in a set of design guidelines and code requirements for the Town Center

More information

Asset-Based Development Scenario

Asset-Based Development Scenario Asset-Based Development Scenario The Asset-Based development scenario emphasizes existing regional assets, concentrating future development around these assets. Regional assets include sports arenas, higher

More information

Sahuarita District & Phase 1 Master Plan. Town Council December 11, 2017

Sahuarita District & Phase 1 Master Plan. Town Council December 11, 2017 Sahuarita District & Phase 1 Master Plan Town Council December 11, 2017 Visioning Study Visioning Process Advisory Group Meetings Community Questionnaire Town Center Case Studies Community Analysis The

More information

Toronto Complete Streets Guidelines Stakeholder Advisory Group #

Toronto Complete Streets Guidelines Stakeholder Advisory Group # Toronto Complete Streets Guidelines Stakeholder Advisory Group #1 2015-03-24 What are Complete Streets? 2 Streets designed with all users in mind: pedestrians/those with disabilities cyclists street car

More information

TRANSPORTATION ELEMENT GOALS, OBJECTIVES, AND POLICIES

TRANSPORTATION ELEMENT GOALS, OBJECTIVES, AND POLICIES TRANSPORTATION ELEMENT GOALS, OBJECTIVES, AND POLICIES GOAL 2 The City shall provide a safe, convenient, effective, and energy efficient multimodal transportation system which is coordinated with the Future

More information

Danvers High Street I-1 District Study

Danvers High Street I-1 District Study Danvers High Street I-1 District Study Presentation of Final Recommendations Planning Board Presentation June 26 th, 2018 1 Introductions Metropolitan Area Planning Council Sam Cleaves AICP, Principal

More information

DRAFT City of Titusville 2040 Comprehensive Plan Future Land Use, Housing, and Transportation Elements April 16, 2018

DRAFT City of Titusville 2040 Comprehensive Plan Future Land Use, Housing, and Transportation Elements April 16, 2018 DRAFT City of Titusville 2040 Comprehensive Plan Future Land Use, Housing, and Transportation Elements April 16, 2018 Prepared by Canin Associates for the City of Titusville About the Comprehensive Plan:

More information

HILLSBOROUGH COUNTY Greenways and Trails Plan Update. Executive Summary. Date

HILLSBOROUGH COUNTY Greenways and Trails Plan Update. Executive Summary. Date HILLSBOROUGH COUNTY Greenways and Trails Plan Update Executive Summary Date PURPOSE AND PROJECT OVERVIEW The Hillsborough County Greenways Master Plan (1995) and the City of Tampa s Greenways and Trails

More information

Newton Town Centre. Land Use, Urban Design & Transportation Plan

Newton Town Centre. Land Use, Urban Design & Transportation Plan Newton Town Centre Land Use, Urban Design & Transportation Plan Public Workshop - June 2-4, 2009 6:15 6:30 Sign-in & conversations Tonight s Agenda 6:30 6:55 Project introduction and summary of previous

More information

Plano Tomorrow Vision and Policies

Plano Tomorrow Vision and Policies Plano Tomorrow Vision and Policies PLANO TOMORROW PILLARS The Built Environment The Social Environment The Natural Environment The Economic Environment Land Use and Urban Design Transportation Housing

More information

INDEPENDENCE BOULEVARD AREA PLAN. Economic Development Committee Overview May 25, 2010

INDEPENDENCE BOULEVARD AREA PLAN. Economic Development Committee Overview May 25, 2010 INDEPENDENCE BOULEVARD AREA PLAN Economic Development Committee Overview May 25, 2010 Presentation Outline Plan Purpose and Development Process Draft Plan Policies and Implementation Strategies Request

More information

6. REGIONAL AND COMMUNITY FACILITIES DESIGNATIONS 6.1. OBJECTIVES FOR REGIONAL AND COMMUNITY FACILITIES LAND USE DESIGNATIONS

6. REGIONAL AND COMMUNITY FACILITIES DESIGNATIONS 6.1. OBJECTIVES FOR REGIONAL AND COMMUNITY FACILITIES LAND USE DESIGNATIONS 6. REGIONAL AND COMMUNITY FACILITIES DESIGNATIONS INTRODUCTION The Regional and land use designations provide the primary locations for uses which satisfy the health, education and other service needs

More information

SMART Plan East-West Corridor Land Use Scenario & Visioning Planning

SMART Plan East-West Corridor Land Use Scenario & Visioning Planning SMART Plan East-West Corridor Land Use Scenario & Visioning Planning Implementation Plan Charrettes January 2018 Presentation Outline 1. SMART Plan and Land Use Visioning Study Overview 2. Live Polling

More information

Unique. Livable. Connected. Sustainable. Anticipate and Manage Change. Variety of Housing Choices. Enhanced Arterial Corridors

Unique. Livable. Connected. Sustainable. Anticipate and Manage Change. Variety of Housing Choices. Enhanced Arterial Corridors Neighborhood Vision The Old Town Neighborhoods are Unique, Livable, Connected, and Sustainable. As mature, established neighborhoods, many of the ideas and opportunities expressed by stakeholders in support

More information

2035 General Plan Update and Belmont Village Specific Plan. Joint Study Session with the City Council and Planning Commission April 12, 2016

2035 General Plan Update and Belmont Village Specific Plan. Joint Study Session with the City Council and Planning Commission April 12, 2016 2035 General Plan Update and Belmont Village Specific Plan Joint Study with the City Council and Planning Commission April 12, 2016 Agenda 1. Welcome and Introductions 2. General Plan Update Status of

More information

JANUARY 19, 2011 CENTRAL AVENUE-METRO BLUE LINE TRANSIT-ORIENTED DEVELOPMENT IMPLEMENTATION PROJECT COMMUNITY FORUM

JANUARY 19, 2011 CENTRAL AVENUE-METRO BLUE LINE TRANSIT-ORIENTED DEVELOPMENT IMPLEMENTATION PROJECT COMMUNITY FORUM CENTRAL AVENUE-METRO BLUE LINE TRANSIT-ORIENTED DEVELOPMENT IMPLEMENTATION PROJECT COMMUNITY FORUM JANUARY 19, 2011 THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION PRINCE GEORGE S COUNTY PLANNING

More information

Developer s Program. The Station at East 54

Developer s Program. The Station at East 54 Developer s Program The Station at East 54 Existing Conditions The Station at East 54 is proposed for a 1.12 acre site at the northeast corner of Hamilton Road and Prestwick Road, tucked between the East

More information

DOWNTOWN JACKSONVILLE MASTER PLAN S T R E E T H I E R A R C H Y

DOWNTOWN JACKSONVILLE MASTER PLAN S T R E E T H I E R A R C H Y DOWNTOWN JACKSONVILLE MASTER PLAN S T R E E T H I E R A R C H Y Gateway Intra-District Business Inter-District 44 CELEBRATING THE RIVER: A PLAN FOR DOWNTOWN JACKSONVILLE The Transportation Network This

More information

Pace University Land Use and Sustainable Development Conference Tensions and Opportunities in Urban Revitalization

Pace University Land Use and Sustainable Development Conference Tensions and Opportunities in Urban Revitalization Pace University Land Use and Sustainable Development Conference Tensions and Opportunities in Urban Revitalization Ken Schwartz, Principal, VHB December 6, 1013 Pace University Land Use and Sustainable

More information

Gratigny Parkway East Extension Project Development & Environment (PD&E) Study

Gratigny Parkway East Extension Project Development & Environment (PD&E) Study Gratigny Parkway East Extension Project Development & Environment (PD&E) Study Session 4: Presentation of Charrette Results December 8, 2010 MDX Work Program #: 92407 ETDM#: 11500 Project Location & Description

More information

Nassau County Cultivating Opportunities for Sustainable Development Nassau County Infill Redevelopment Feasibility Study

Nassau County Cultivating Opportunities for Sustainable Development Nassau County Infill Redevelopment Feasibility Study Nassau County Cultivating Opportunities for Sustainable Development Nassau County Infill Redevelopment Feasibility Study NY-CT Sustainable Communities Steering Committee Meeting March 14, 2014 Project

More information

Public Meeting March 10 th 2011

Public Meeting March 10 th 2011 Public Meeting March 10 th 2011 Agenda 6:00-6:15 6:15-7:00 7:00-8:00 8:00-8:30 8:30-9:00 9:00 Welcome and Introductions Presentation» Project Overview» Recap Existing Conditions / Issues & Opportunities»

More information

North Fair Oaks Community Plan Summary and Information

North Fair Oaks Community Plan Summary and Information North Fair Oaks Community Plan Summary and Information WHAT IS THE NORTH FAIR OAKS COMMUNITY PLAN? The North Fair Oaks Community Plan is part of the San Mateo County General Plan, and establishes policies

More information

FOUR MILE RUN VALLEY WORKING GROUP AND CHARGE

FOUR MILE RUN VALLEY WORKING GROUP AND CHARGE FOUR MILE RUN VALLEY WORKING GROUP AND CHARGE Adopted April 16, 2016 Amended July 19, 2016 Overview of Integrated Effort The overall goal of the Four Mile Run Valley (4MRV) initiative is to develop a comprehensive

More information

West Ocala Vision & Community Plan City Council Work Session. Presented by West Ocala Community Plan Steering Committee

West Ocala Vision & Community Plan City Council Work Session. Presented by West Ocala Community Plan Steering Committee West Ocala Vision & Community Plan City Council Work Session Presented by West Ocala Community Plan Steering Committee November 29,2011 Ocala 2035 Vision West Ocala Community Vision & Master Plan West

More information

Activities for All Ages. Small Community Feel. Entertainment. Mix of Uses

Activities for All Ages. Small Community Feel. Entertainment. Mix of Uses DRAFT PROPOSALS Safety Walkability Open Space/Views to Ocean/Beach Access Activities for All Ages Small Community Feel Entertainment Mix of Uses Gathering Place Celebrate Our Assets: Enhance the four major

More information

REGIONAL ACTIVITY CENTER

REGIONAL ACTIVITY CENTER DRAFT REGIONAL ACTIVITY CENTER 70 EAST BENCH MASTER PLAN DRAFT 06 Introduction The East Bench Regional Activity center is comprised of large educational, research, medical, and employment centers. These

More information

12/9/2013. HOLLYWOOD/PINES CORRIDOR PROJECT AMPO 2013 Annual Conference October 24, Our Perspective. Broward.

12/9/2013. HOLLYWOOD/PINES CORRIDOR PROJECT AMPO 2013 Annual Conference October 24, Our Perspective. Broward. HOLLYWOOD/PINES CORRIDOR PROJECT AMPO 2013 Annual Conference October 24, 2013 Our Perspective Broward Fort Lauderdale 1 Broward Metropolitan Planning Organization Fort Lauderdale Fort Lauderdale Skyline

More information

Concord Community Reuse Project Goals and Guiding Principles. Overarching Goals (OG)

Concord Community Reuse Project Goals and Guiding Principles. Overarching Goals (OG) Concord Community Reuse Project Goals and Guiding Principles Overarching Goals (OG) No priority is implied by the order of presentation of the goals and guiding principles. Overarching goals for the Concord

More information

2040 LUP is a part of the Comprehensive Plan and carries the same legal authority. Economic Challenges

2040 LUP is a part of the Comprehensive Plan and carries the same legal authority. Economic Challenges 1.1. Guiding Anchorage s Growth Where will new residents settle over the next two decades? Where will people work, shop, and play? Will there be enough room to grow? How will Anchorage look? Will growth

More information

DRAFT Subject to Modifications

DRAFT Subject to Modifications TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 8 From: Date: Subject: Staff May 19, 2017 Council Meeting Florida Department of Transportation Complete Streets

More information

Downtown Elkton Station Area Plan, Elkton, MD. Difficult enough to get support for new starts challenge to fund Houston transit

Downtown Elkton Station Area Plan, Elkton, MD. Difficult enough to get support for new starts challenge to fund Houston transit Difficult enough to get support for new starts challenge to fund Houston transit More difficult to build Community Support for dense development at station areas Major Concerns: Traffic, Property values,

More information

Stockton Waterfront Master Plan. Waterfront Master Plan

Stockton Waterfront Master Plan. Waterfront Master Plan Stockton Waterfront Master Plan Presentation Objectives Process update Planning observations Planning Goals Planning Principles Review of planning activities Summary and next steps Planning Activities

More information

iii. Visioning framework

iii. Visioning framework III. VISION iii. Visioning framework III.1 Overview A vision is a clear and succinct description of what an institution and its community should look like after it successfully implements its goals and

More information

Por favor, levanten la mano si necesita traduccion en espanol Please raise your hand if you need Spanish translation

Por favor, levanten la mano si necesita traduccion en espanol Please raise your hand if you need Spanish translation FEDERAL BOULEVARD CORRIDOR WIDE STUDY PUBLIC MEETING #1 APRIL 27, 2016 Por favor, levanten la mano si necesita traduccion en espanol Please raise your hand if you need Spanish translation HDR DESIGN WORKSHOP

More information

Chapter 1.0 Introduction

Chapter 1.0 Introduction Chapter 1.0 Introduction 1.1 Background The North Metro commuter rail line is part of the RTD FasTracks regional transit system expansion program to build more than 100 miles of rail transit throughout

More information

BRYN MAWR. Tier 2 Characteristics: Location: Lancaster Avenue from Old Lancaster Road on the east to Norwood Avenue on the west

BRYN MAWR. Tier 2 Characteristics: Location: Lancaster Avenue from Old Lancaster Road on the east to Norwood Avenue on the west BRYN MAWR Tier 2 Characteristics: Transit-oriented Mixed use Along Lancaster Avenue Serve township-wide needs Civic space Employment centers Location: Lancaster Avenue from Old Lancaster Road on the east

More information

open public hearing and allow public comment request to continue LPA public hearing to January 16, 2014 at 10:30 am

open public hearing and allow public comment request to continue LPA public hearing to January 16, 2014 at 10:30 am TODAY S AGENDA Work Session LPA Transmittal Public Hearing open public hearing and allow public comment request to continue LPA public hearing to January 16, 2014 at 10:30 am staff will issue a recommendation

More information

Equitable Growth Through TOD Planning

Equitable Growth Through TOD Planning Equitable Growth Through TOD Planning Community Meeting # 2 November 2017 Goals Objectives Extend investment from downtown Connect neighborhoods physically and economically Enhance places based on local

More information

The Floyds Fork Area Plan

The Floyds Fork Area Plan The Floyds Fork Area Plan Growth Framework and Design Principles Presented by: Wallace Roberts & Todd, LLC March 24, 2009 Ted Wathen / Quadrant Agenda Project overview and purpose Growth framework Design

More information

Bloor Street East Potential Ravine Portal Overlook and Access Passage to the Rosedale Valley and Don River Valley Ravine, Toronto, Canada

Bloor Street East Potential Ravine Portal Overlook and Access Passage to the Rosedale Valley and Don River Valley Ravine, Toronto, Canada TRANSFORMATIVE IDEA 2. GREAT STREETS Bloor Street Christie Pits Park Bloor St Spadina Ave Bathurst St Shaw St 1 Recognize the significant public realm improvements along Bloor Street and extend and enhance

More information

8implementation. strategies

8implementation. strategies PROGRAM STRATEGIES 8implementation strategies T he implementation actions of this chapter are designed to support and carry out the land use, economic development, transportation, urban design, and program

More information

DRAFT MAJOR CORRIDORS 48 EAST BENCH MASTER PLAN

DRAFT MAJOR CORRIDORS 48 EAST BENCH MASTER PLAN DRAFT MAJOR CORRIDORS 48 EAST BENCH MASTER PLAN DRAFT 05 Introduction Foothill Drive, Parley s Way, Sunnyside Avenue and 1300 East serve as thoroughfares into the City and are important pieces in the regional

More information

Beachside Redevelopment Committee

Beachside Redevelopment Committee Beachside Redevelopment Committee DRAFT FINAL RECOMMENDATIONS MARCH 22, 2018 This is a new slide 2 This is a new slide Table of Contents I. Introduction and Overview II. III. Community Improvements and

More information

Introduction and Overview

Introduction and Overview Introduction and Overview Articulate local values and priorities Guide land use and development decisions Coordinate transportation, infrastructure, and City services with expected growth and available

More information

CITY S GOALS DRIVE MODE CHOICE IN WINSTON-SALEM, NC

CITY S GOALS DRIVE MODE CHOICE IN WINSTON-SALEM, NC CITY S GOALS DRIVE MODE CHOICE IN WINSTON-SALEM, NC Taiwo Jaiyeoba HDR, Transit Principal, Atlanta, GA Claire Brinkley HDR, Transit Planner, Charlotte, NC AGENDA 1. Project Background 2. Project Process

More information

Blueprint Denver Task Force Meeting #

Blueprint Denver Task Force Meeting # Blueprint Denver Task Force Meeting #1 6.23.16 1. Welcome and Introductions Your name and affiliation Name 1 thing you love about Denver Name 1 thing you d change about Denver All in 30 seconds! Ready,

More information

3.9 Systems Interrelationships

3.9 Systems Interrelationships 191 Sustainability Building Blocks: The Comprehensive Plan Systems Community Form Economy Social Transportation Natural Resources Housing and Neighborhoods Utilities and Infrastructure Institutions.9 Systems

More information

Town of Oakville Streetscape Strategy

Town of Oakville Streetscape Strategy Town of Oakville Streetscape Strategy Endorsed by PDC on February 10, 2014 (PD-011-14) Town of Oakville Streetscape Strategy [endorsed by PDC February 10, 2014] 0 Town of Oakville Streetscape Strategy

More information

THEMES, VISION, + PRINCIPLES

THEMES, VISION, + PRINCIPLES CHAPTER 2: THEMES, VISION, + PRINCIPLES This page intentionally left blank. 20 VISION DRAFT AUGUST 2018 2 2 THEMES, VISION, + GUIDING PRINCIPLES The Key Themes, Vision, and Guiding Principles presented

More information

Robbinsdale LRT Station. CDI Development Guidelines. August Overview

Robbinsdale LRT Station. CDI Development Guidelines. August Overview Robbinsdale LRT Station August 2018 Overview The City of Robbinsdale may have the coolest opportunity site along the 13 mile stretch of the Bottineau LRT corridor / Blue Line extension. Located a block

More information

Corridor-Level Approaches to Creating Transit-Oriented Districts

Corridor-Level Approaches to Creating Transit-Oriented Districts Corridor-Level Approaches to Creating Transit-Oriented Districts Dena Belzer Strategic Economics and Center for Transit-Oriented Development August 2011 5-year old partnership dedicated to improving practice

More information

ORANGE COUNTY IMPLEMENTING THE FOUR C s

ORANGE COUNTY IMPLEMENTING THE FOUR C s ORANGE COUNTY IMPLEMENTING THE FOUR C s East Central Florida Corridor Task Force O R A N G E COUN TY P LA N N I N G DIVISION C O M M U N I T Y, E N V I R O N M E N T A L A N D D E V E L O P M E N T S E

More information

Streets, Connectivity & Built Environment Working Group August 2, 2017

Streets, Connectivity & Built Environment Working Group August 2, 2017 Streets, Connectivity & Built Environment Working Group August 2, 2017 DOWNTOWN OAKLAND SPECIFIC PLAN WELCOME Streets, Connectivity & Built Environment Working Group Social Equity Meeting August 2, 2017

More information

Imagining Ward 3 Session #2. April 18, :00 pm 8:30 pm

Imagining Ward 3 Session #2. April 18, :00 pm 8:30 pm Imagining Ward 3 Session #2 April 18, 2016 7:00 pm 8:30 pm Project Team City of Mississauga Karen Crouse, Project Leader, Policy Planning Division Frank Marzo, Planner, Policy Planning Division Brook McIlroy

More information

Elliot Park 4. Neighborhood Master Plan. The Master Plan

Elliot Park 4. Neighborhood Master Plan. The Master Plan Elliot Park 4 Neighborhood Master Plan August 2002 Why Master Plan? Construction cranes signal new growth downtown as the backdrop to this smaller scale, quiet neighborhood. Do nothing or plan for the

More information

FDOT D4 Complete Streets

FDOT D4 Complete Streets FDOT D4 Complete Streets Context Sensitive Solutions Directs that complete street solutions will complement the context of the community. Collaborative approach to decision making, project development,

More information

Study Area. Capitol Way. Greening America s Capitals 11/13/2014. A Greening America s Capitals Project

Study Area. Capitol Way. Greening America s Capitals 11/13/2014. A Greening America s Capitals Project Olympia, WA: Greening Capitol Way Supporting Communities move towards sustainability is a priority for the federal government. A Greening America s Capitals Project Office of Sustainable Communities U.S.

More information

Mississippi Skyway Preliminary Engineering Report

Mississippi Skyway Preliminary Engineering Report EXECUTIVE SUMMARY Mississippi Skyway Preliminary Engineering Report CITY OF RAMSEY, MINNESOTA DECEMBER 2014 City of RAMSEY EXECUTIVE SUMMARY Project Need and Intent The Mississippi Skyway pedestrian bridge

More information

Integrating Land Use and Transportation

Integrating Land Use and Transportation FEATURE Integrating Land Use and Transportation For years the transportation profession has emphasized mobility in the development of plans, programs, and projects. This emphasis on mobility moving people

More information

Planning for TOD Implementation at a Corridor Scale

Planning for TOD Implementation at a Corridor Scale Planning for TOD Implementation at a Corridor Scale Catherine Cox Blair, Reconnecting America Presentation to Northwest Corridor Working Group November 6, 2013 What is Reconnecting America? Reconnecting

More information

ORDINANCE AN ORDINANCE TO ADD A NEW SECTION 4.N. IN THE ZONING CODE FOR THE TOWN OF MIDDLETOWN, RELATING TO MIXED-USE DEVELOPMENT

ORDINANCE AN ORDINANCE TO ADD A NEW SECTION 4.N. IN THE ZONING CODE FOR THE TOWN OF MIDDLETOWN, RELATING TO MIXED-USE DEVELOPMENT Introduced: November 5, 2018 Approved: ORDINANCE 18-11-01 AN ORDINANCE TO ADD A NEW SECTION 4.N. IN THE ZONING CODE FOR THE TOWN OF MIDDLETOWN, RELATING TO MIXED-USE DEVELOPMENT BE IT ENACTED BY THE MAYOR

More information

Early in the scoping process, several groups submitted a letter that reflected our collective values for Sound Transit 3. These values include:

Early in the scoping process, several groups submitted a letter that reflected our collective values for Sound Transit 3. These values include: October 3, 2018 TO: West Seattle and Ballard Link Extension Elected Leadership Group FROM: Transit Access Stakeholders: Transportation Choices Coalition, Futurewise, Feet First, Cascade Bicycle Club, Housing

More information

Atlanta BeltLine Corridor Environmental Study. Scoping Meeting August 2008

Atlanta BeltLine Corridor Environmental Study. Scoping Meeting August 2008 Atlanta BeltLine Corridor Environmental Study Scoping Meeting August 2008 What Will We Be Discussing Today? Study Overview - How Did We Get Here? - What Is the Study About? - Who Is Involved? - Where Is

More information

Economic Development & Housing Council Committee Comprehensive Plan Update September 20, 2005

Economic Development & Housing Council Committee Comprehensive Plan Update September 20, 2005 1 Economic Development & Housing Council Committee Comprehensive Plan Update September 20, 2005 Purpose To update the Committee on the ForwardDallas! Plan, including: Status Anticipated Products Public

More information

City of Tacoma Planning and Development Services

City of Tacoma Planning and Development Services Agenda Item E-1 City of Tacoma Planning and Development Services To: Planning Commission From: Elliott Barnett, Planning Services Division Subject: Tacoma Mall Regional Center Subarea Plan and EIS Meeting

More information

Planning Commission April 4, 2013 BOCC Workshop Page 1

Planning Commission April 4, 2013 BOCC Workshop Page 1 Planning Commission April 4, 2013 BOCC Workshop Page 1 Planning Commission April 4, 2013 BOCC Workshop Page 2 Planning Commission April 4, 2013 BOCC Workshop Page 3 Planning Commission April 4, 2013 BOCC

More information