1 Section 2 EROSION PREVENTION AND SEDIMENT CONTROL PLAN 2.1 Requirements The City of Shelbyville, KY will require an Erosion Prevention and Sediment Control (EPSC) Plan for most types of development construction. When preparing the EPSC Plan, the design engineer and/or developer should determine the best practices to protect active construction sites by selecting source control and sediment containment practices. In doing so, most erosion problems can be avoided and sediment containment issues can be addressed prior to construction disturbances. Site characteristics such as soil types, topography, slopes, and geography, and construction methods should be thoroughly reviewed when selecting BMPs to implement throughout the life of the project. The design team should be mindful of how the site is changing throughout the project so that BMPs can be repaired, modified or replaced with a more suitable practice. For more information regarding the required elements of an EPSC Plan, refer to Appendix C EPSC Plans. 2.2 Minimize Disturbed Areas Some important decisions must be made prior to BMP selections for a proposed construction site. Construction planning and sequencing are the least expensive methods to reduce and control erosion and sediment. The following points should be considered when to minimize disturbed areas: 1. Do not disturb areas of the construction site that are not scheduled for improvements and keep existing vegetation, even if it is scheduled to be removed, for as long as possible. 2. Carefully schedule and phase construction. Avoid grading during wet months (December through May). Use temporary cover measures (seed or mulch) whenever construction is halted for an extended period. 3. Phase site grading to limit the amount and time of an area s exposure. Exposed areas should be stabilized immediately following the completion of grading. 4. Plan and implement permanent structures throughout the earlier phases of the project. This will maximize the utility practice s usefulness and help with erosion prevention and sediment containment. 2-1
2 5. Avoid delays and work expeditiously on any part of the site. Install landscaping fixture upon the completion of any sequence and prior to moving on to the next phase. Any exposed soil is subject to erosion and sediment transport, even by a single rain drop. Designers and contractors should make every effort to stabilize the following susceptible areas at a construction site prior to and throughout construction: Slopes Highly erosive soils Construction entrances and exits Stream channels Soil stockpiles 2.3 Site Perimeter Controls The contractor must set site perimeter controls to protect areas downstream from erosion, sediment and flooding problems. Area of Concern Disturbed areas or slopes that drain toward adjacent properties Stabilizing area after grading has been completed Off site flows that enter the constructions site Concentrated flows that leave the construction site Site Perimeter Control Continuous berms, silt fences, sandbags Mulching, seeding, planting, emulsifiers, or a combination of two or more Continuous berms, earth dikes, drainage swales and lined ditches Outlet control measures that will dissipate velocities Additional controls within the interior of construction site should supplement perimeter controls once rough grading is complete. 2.4 Internal Erosion and Drainage Design Once the perimeter controls have been selected, the issue of internal erosion and drainage controls must be addressed. Internal practices are typically more time consuming and labor intensive since they will be used in close proximity of construction activities. They are required early in the project until permanent practices can be implemented. Some of the internal erosion and drainage design practices to be used include: Check dams, geotextile mats, and under extreme circumstances concrete channel lining. 2-2
3 Terracing at regular intervals. Slope benches or ditches. Surface roughening or temporary seeding. 2.5 Maintenance and Inspection Constant inspection and maintenance of the selected practices are critical towards the success of preventing erosion and sediment transport. Maintaining a daily or weekly checklist of practices to inspect for deficiencies of those practices are critical to the success of preventing erosion and sediment displacement. A good way to ensure that all practices will be properly utilized is for the contractor to arrange a pre-construction meeting with the City of Bowling Green s Stormwater Inspector. This meeting should take place after the Notice to Proceed, but prior to the mobilization of equipment. One of the most critical aspects of maintaining the construction site s BMPs is to have a plan on when sediment should be removed from the utilized practices, and where should it be placed. The BMPs in this manual often suggest when sediment should be removed from structures, but the contractor should demonstrate sound judgment in maintaining the structures more frequently if necessary. A sound inspection and maintenance strategy should include the following: 1. Verify that sediment-laden stormwater is directed to temporary sediment traps or basins. Verify that sediment basins and traps are at low points below disturbed areas. 2. Protect all existing or newly installed storm drainage structures from sediment clogging by providing inlet protection for area drains and curb inlets. Stormwater inlet protection can utilize sand bags, sediment traps, or other similar devices. 3. Excavate permanent stormwater detention ponds early in the project, use them as sedimentation ponds during construction, remove accumulated sediment, and landscape the ponds when the upstream drainage area is stabilized. 4. Inspect temporary sediment barriers such as silt fences, rock filters, and continuous berms after every rainfall. These barriers should only be used in areas where sheet flow runoff occurs. They are ineffective if the runoff is concentrated into rill or gully flow. 5. Internal outfalls must also be protected to reduce scour from high velocity flows leaving pipes or other drainage facilities. 2-3
4 2.6 EPSC Preparation Guidance The EPSC Plan will consist of a site plan sheet at a scale suitable for illustrating the elements that will control erosion and sediment, and a set of directions in narrative form within the contract documents. The Owner of the development or project will be responsible for preparing the EPSC Plan. Whether it is the Owner, designer or a subcontractor to develop the plans, the matter is left up to the Owner. The plans will illustrate which practices shall be used and their placement within the project. The narrative will explain decisions concerning erosion and sediment control, and when required, show why those measures were selected, either by calculations or sound engineering judgment. This will allow the reviewer to make informed decisions on the efficiency and practicality of the BMPs selected. The level of detail shown on the drawings depends on the magnitude of the project. For single lots, a sketch may be all that is required to show the inspector. However for larger developments, such as a shopping center or industrial park, a plan sheet at an appropriate scale shall be submitted to the City for review. Here is a list of typical notes that should be added to every EPSC plan, large and small. 1. As a minimum, all erosion and sediment control practices will be constructed and maintained according to the standards located in the City of Shelbyville s BMP Manual, Stormwater Ordinances, and as required by state and federal laws. 2. A copy of the approved Erosion Prevention and Sediment Control Plans shall be maintained at the project site at all times. This copy shall be presented to the City of Shelbyville s representatives upon request. 3. Prior to commencing land-disturbing activities in any area not on the approved erosion and sediment control plan, the contractor shall submit a supplementary erosion control plan to the City of Shelbyville for review and approval. 4. All erosion and sediment control measures are to be placed prior to or as the first step in clearing and grading. The contractor is responsible for any additional erosion control measures necessary to prevent erosion and sedimentation as determined by the City of Shelbyville. 5. During dewatering operations water must be pumped through an approved filtering device. The City of Shelbyville may suspend dewatering operations if pollution is observed. 6. The contractor shall inspect all erosion and sediment control devices at least once a week and at least once a day during rainfall events. The contractor shall perform any repairs or maintenance immediately in order to ensure effective erosion and sediment control. 7. The contractor shall maintain a record of all inspections and maintenance activities at the project site. This record shall be made available to the City of Shelbyville upon request. 2-4
5 2.7 Storm Water Pollution Protection Plan Requirements of the Storm Water Pollution Protection Plan (SWPPP) are discussed in Appendix C BMP Plans. 2-5
SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE
SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE Please complete this narrative form and submit with your SWPPP drawings. Refer to Kitsap County Stormwater Design Manual Vol.
More informationSOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL
Standard Operating Procedures Central Massachusetts Regional Stormwater Coalition SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL Erosion and sedimentation from land-disturbing
More informationMANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS
MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS May 2007 SECTION 1 Responsibility of Applicant TABLE OF CONTENTS A. Stormwater Management Plan Required Information
More informationProject Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM
Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM I. PROJECT DATA Project Name Bay Meadows Development Phase II Project Address 2600
More informationA. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.
The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language
More informationProject: Developer/Designer: Reviewer: I. Narrative: 1. Project Description: Describes the nature and purpose of the land disturbing activity.
City of Charlottesville, Virginia Erosion and Sediment Control Plan Review Checklist 610 East Market Street, Charlottesville, VA 22902 Telephone 434-970-3182; Fax 434-970-3359 Project: Developer/Designer:
More informationStructural Storm Water Best Management Practices (BMPs)
Structural Storm Water Best Management Practices (BMPs) Storm Water Permitting: The SWPPP Revealed By Deron Austin, PE January 11, 2006 3:30-5:00 PM Orlando, Florida Presentation Outline Preface About
More informationCITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) (360) (FAX)
CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA 98501 (360) 754-4180 (360) 754-4126 (FAX) Email: cdd@ci.tumwater.wa.us APPENDIX II-C SHORT FORM CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN (SWPPP)
More informationA. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.
The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language
More informationUsing the Updated RI Soil Erosion and Sediment Control Handbook. The Introductory Workshop for RIDEM/CRMC Staff January 23, 2015
Using the Updated RI Soil Erosion and Sediment Control Handbook The Introductory Workshop for RIDEM/CRMC Staff January 23, 2015 URI Cooperative Extension NEMO URI Cooperative Extension NEMO White Oak,
More informationCity of Stoughton Erosion Control Permit Application (effective 2/6/2018)
City of Stoughton Erosion Control Permit Application (effective 2/6/2018) Incomplete applications will not be accepted Project Name: Address of subject property: Landowner Name(s): Applicant Name: Landowner
More informationStorm Water Basics for Construction Sites Presented by Representatives from the City of Grass Valley and Nevada County
September 22nd, 2015 3:30PM Sign up at: www.stormwaterawareness.org Workshop is free! Nevada County Contractor s Association 149 Crown Point Ct. Grass Valley, CA 95945 Storm Water Basics for Construction
More informationWQ-23 MOUNTAINOUS AND STEEP SLOPE SITES
Greenville County Technical Specification for: WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES 1.0 Mountainous and Steep Slope Sites 1.1 Description The geographic locations of portions of Greenville County are
More informationHuntington Stormwater Utility
Huntington Stormwater Utility Stormwater Management & Sediment and Erosion Control Requirements for Construction Sites Authorized by Huntington City Code Articles: 971, 970, 930, 935, 955, Revised April
More informationUrban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT
NOT WELL 800 - Urban Stormwater Wetlands A constructed system of shallow pools that create growing conditions for wetland plants to lessen the impacts of stormwater quality and quantity in urban areas.
More information5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion
Topics Erosion, TESC and Construction sequencing Procedures and timing Remedies for failing sites Curtis Hinman WSU Extension and Bio Systems Eng. Faculty Low Impact Development Specialist chinman@wsu.edu
More informationProtect Stormwater Quality Project and Site Management Training for General Contractors. Presenter Becky Pearson Professional Civil Engineer
Protect Stormwater Quality Project and Site Management Training for General Contractors Presenter Becky Pearson Professional Civil Engineer Part II Best Management Practices (BMPs) What is a Best Management
More informationSTORMWATER SITE PLAN INSTRUCTIONS AND SUBMITTAL TEMPLATE Medium and Large Projects
DEPARTMENT OF COMMUNITY DEVELOPMENT 621 Sheridan Street, Port Townsend, WA 98368 Tel: 360.379.4450 Fax: 360.379.4451 Web: www.co.jefferson.wa.us/communitydevelopment E-mail: dcd@co.jefferson.wa.us STORMWATER
More informationKey elements : Filter Strips must be designed within parameters required by the Fort Wayne s Development Standards/Criteria Manual.
4.4. Filter Strips Filter Strips are densely vegetated lands that treat sheet flow storm water from adjacent pervious and impervious areas. They function by slowing runoff, trapping sediment and pollutants,
More informationGeneral Information. Site Conditions. 9b 9b. 9a 1b. Best Management Practices Illustration
Model Construction SWPPP Planning & Development Services 1800 Continental Place Mount Vernon WA 98273 voice 360-416-1320 inspections 360-416-1330 www.skagitcounty.net/stormwaterpermitting Permit #: General
More informationTO BE FILLED OUT BY APPLICANT
CITY OF BAINBRIDGE ISLAND CLEARING PERMIT APPLICATION FORM MUST BE COMPLETED IN INK, PREFERABLY BLUE. PENCIL WILL NOT BE ACCEPTED. DATE STAMP FOR CITY USE ONLY PROJECT NAME: TAX ASSESSOR S NUMBER(S): TO
More informationATTACHMENT 1 WILSON MINE LECROY AREA SEMIPERMANENT DEWATERING SYSTEM
ATTACHMENT 1 WILSON MINE LECROY AREA SEMIPERMANENT DEWATERING SYSTEM Reclamation plans for the Wilson Mine Lecroy area were approved by the Arkansas Department of Environmental Quality with a passive barrier
More informationErosion & Sediment Control Plan Application Form & Checklist
Erosion & Sediment Control Plan Application Form & Checklist GENERAL INFORMATION Application Date: Project Address: Tax Map / Parcel Number(s): PROPERTY OWNER / DEVELOPER Firm Name: Contact Person: Title:
More informationIllinois Urban Manual
Illinois Urban Manual Jim Nelson: Association of Illinois Soil and Water Conservation Districts (AISWCD) Funding for this project provided, in part, by the Grand Victoria Foundation of Elgin IL, the Governor
More informationWisconsin Contractors Institute Continuing Education
Wisconsin Contractors Institute Continuing Education Erosion & Sediment Control Course # 12775 2 hours Wisconsin Contractors Institute N27 W23953 Paul Road, Suite 203 Pewaukee, WI 53072 Website: www.wicontractorsinstitute.com
More informationSECTION 6. Routine Maintenance Activity Details
SECTION 6 Routine Maintenance Activity Details 80. DEBRIS REMOVAL When Deadfall, and other objects, such as shopping carts, tires, appliances, and mattresses have accumulated in the drain. Why To prevent
More informationEROSION & SEDIMENT CONTROL
EROSION & SEDIMENT CONTROL Surface Water Protection During Well Site Construction Kelly Kees, PE WVDEP, Office of Oil and Gas SEDIMENT & EROSION CONTROL PLANS Per West Virginia State Code 22-6-6(d) 22-6A-7(c),
More informationTown of Essex Small Site Erosion Control Guide
Town of Essex Small Site Erosion Control Guide Why do we need to protect against erosion? Water Quality: Erosion and the transport of sediment and pollutants impacts the water quality of nearby streams
More informationM-231 and Water Quality. Ottawa County Water Quality Forum November 21, 2016 James Fortney, MDOT
M-231 and Water Quality Ottawa County Water Quality Forum November 21, 2016 James Fortney, MDOT M-231 Facts: 7-Miles long 2-Lane Limited Access Highway Connects I-96 and M-45 M-231 Facts: Includes Michigan
More informationGloucester County PLAN SUBMITTER'S CHECKLIST
Page 1 of 9 Gloucester County PLAN SUBMITTER'S CHECKLIST FOR EROSION AND SEDIMENT CONTROL PLANS Please fill in all blanks and please reference the plan sheets/pages where the information may be found,
More informationFlorence County Small Commercial Land Disturbance Permit Application
Florence County Small Commercial Land Disturbance Permit Application Florence County Engineering Division 518 South Irby Street Florence, S.C. 29501 Phone (843) 676-8600 Fax (843) 676-8667 Tax Map Number:
More informationSTANDARD SPECIFICATIONS SECTION TEMPORARY EROSION AND SEDIMENT CONTROL
STANDARD SPECIFICATIONS SECTION 01570 TEMPORARY EROSION AND SEDIMENT CONTROL PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements, procedures, and methods related to responsibilities for providing
More informationSOIL EROSION AND SEDIMENT CONTROL
SOIL EROSION AND SEDIMENT CONTROL SECTION 1: AUTHORITY, TITLE AND PURPOSE 11. STATUTORY AUTHORIZATION This ordinance is adopted pursuant to the provisions of the Federal Water Pollution Control Act 86
More informationPart IV(a): BMPs for Erosion, Sediment, Velocity Control
Part IV(a): BMPs for Erosion, Sediment, Velocity Control Find Design Standards and Specifications for Iowa Erosion and Sediment Control Practices at: www.iowasudas.org Erosion Control Keeping the soil
More informationA. INTRODUCTION AND SUMMARY OF FINDINGS B. EXISTING CONDITIONS. Table 10-1 Adjacent Storm Drains
Chapter 10: Stormwater Management A. INTRODUCTION AND SUMMARY OF FINDINGS This chapter describes existing and proposed stormwater management on the Site. Potential impacts to stormwater infrastructure
More informationCHAPTER 102 REQUIREMENTS CRITCAL STAGES DURING CONSTRUCTION ACTIVITIES
CHAPTER 102 REQUIREMENTS CRITCAL STAGES DURING CONSTRUCTION ACTIVITIES TOPICS Steps Prior to construction Pre-Construction Meeting Defining the Critical Stages with the Contractor Brady s Run Lake Site
More informationPlan Review Checklist
Plan Review Checklist FOR EROSION AND SEDIMENT CONTROL PLANS _ Minimum Standards - All applicable Minimum Standards must be addressed. All minimum Standards must be adhered to during the entire project
More informationDraft Rhode Island Stormwater Design and Installation Standards Manual
Draft Rhode Island Stormwater Design and Installation Standards Manual Summary The May 2009 Public Review Draft version of the RI Stormwater Design and Installation Standards Manual consists of approximately
More informationNevada Contractors Field Guide for Construction Site Best Management Practices (BMPs)
June 2008 Nevada Contractors Field Guide for Construction Site Best Management Practices (BMPs) Funding for the development and production of the Nevada BMP Field Guide was provided by the Nevada Division
More informationVegetated Filter Strips and Buffers
3.15 Sediment Control Description: Buffer strips (existing vegetation) and filter strips (planted vegetation) are sections of vegetated land adjacent to disturbed areas. They are designed with low slopes
More informationC-10. Disconnected Impervious Surface
C-10. Disconnected Impervious Surface Design Objective Disconnected Impervious Surface (DIS) is the practice of directing stormwater runoff from built-upon areas to properly sized, sloped and vegetated
More informationCHAPTER 9 STORM DRAINAGE. Minimum Requirements for New Development and Redevelopment
CHAPTER 9 STORM DRAINAGE 9.01 General The standards established by this chapter are intended to represent the minimum standards for the design and construction of storm drainage facilities. 9.02 Design
More informationC-12. Dry Pond. Design Objective
C-12. Dry Pond Design Objective The primary purpose of dry pond is to attenuate and delay stormwater runoff peaks. Dry ponds hold water immediately after a storm event and drain to be almost complete dry
More information4. Contractor (and subcontractors if applicable) certification statement(s)
CHEMUNG COUNTY STORMWATER COALITION STORMWATER POLLUTION PREVENTION PLAN (SWPPP) SUBMITTAL CHECKLIST GENERAL INFORMATION: 1. Owner/Operator name, legal address, phone number 2. Copy of signed Notice of
More informationPLAN SUBMITTER'S CHECKLIST
Page 1 of 8 PLAN SUBMITTER'S CHECKLIST FOR EROSION AND SEDIMENT CONTROL PLANS Please fill in all blanks and reference the plan sheets/pages where the information may be found, where appropriate, or write
More informationEROSION & SEDIMENT CONTROL
EROSION & SEDIMENT CONTROL 1 EROSION & SEDIMENT CONTROL Effective Soil & Water Protection Whether you want to prevent soil erosion caused by rain, water and wind, or protect waterways from inevitable build
More informationA: Downtown Diversion Pipe
A: Downtown Diversion Pipe b c with modifications Map highlighting conservation easement. The diversion pipe would run along the railroad. Will divert 40-44% of total flow.; and Reduce the impact on Sand
More informationAPPLICATION FOR MINOR SITE PLAN REVIEW
www.appleton.org APPLICATION FOR MINOR SITE PLAN REVIEW Community and Economic Development Department 100 N. Appleton St. PH: 920-832-6468 Appleton, WI 54911 FAX: 920-832-5994 Stamp date received PROPERTY
More informationSoil Erosion and Sediment Control
PDHonline Course C188 (3 PDH) Soil Erosion and Sediment Control Instructor: John Poullain, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org
More informationAlternative Names: Erosion Control Matting, Erosion Control Netting, Rolled Erosion Control Products (RECP)
4.5-s EROSION CONTROL BLANKET SYSTEM Alternative Names: Erosion Control Matting, Erosion Control Netting, Rolled Erosion Control Products (RECP) DESCRIPTION Erosion control blanket systems are woven or
More information5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS
5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS Low Impact Development (LID) requires a shift in stormwater management away from conveying runoff to a small number of downstream points through hydraulically
More informationAPPLICATION FOR MINOR SITE PLAN REVIEW
www.appleton.org APPLICATION FOR MINOR SITE PLAN REVIEW Community and Economic Development Department 100 N. Appleton St. PH: 920-832-6468 Appleton, WI 54911 FAX: 920-832-5994 Stamp date received PROPERTY
More informationPERMANENT SEEDING. Overview of Sedimentation and Erosion Control Practices. Practice no. 6.11
Overview of Sedimentation and Erosion Control Practices Practice no. 6.11 PERMANENT SEEDING Permanent vegetation controls erosion by physically protecting a bare soil surface from raindrop impact, flowing
More informationDepartment of Agriculture. Conservation Service. United States. Natural Resources REVISED 8/26/16
GENERAL NOTES: SYMBOL LEGEND 1. All work shall comply with the constriction specifications, drawings, project-specific quality assurance plan and other contract requirements. 2. All notes on the drawings
More informationEROSION PREVENTION BMP SUGGESTED USES MATRIX
EROSION PREVENTION SUGGESTED USES MATRIX Processed Based Tools Software Aids Slope Waterway Surface Concentrated Flows Large Flat Stock Pile Borrow Adjacent Property Impacts Erosion Prevention Measures
More informationPost Construction BMPs
Post Construction BMPs Why are Post Construction BMPs important? With increased development brings the increase of impervious cover Parking lots, rooftops, driveways Storm water runoff volume increases
More informationTable of Contents. Preface... xv
Table of Contents Preface... xv Objective... xv Organization of this Manual...xvi How to Use this Manual...xvii Development of Best Management Practices (BMPs) for Stormwater Management...xviii Best Management
More informationTOWNSHIP OF LOGAN SOIL & FILL IMPORTATION AND PLACEMENT APPLICATION SUBMITTAL CHECKLIST
TOWNSHIP OF LOGAN SOIL & FILL IMPORTATION AND PLACEMENT APPLICATION SUBMITTAL CHECKLIST Applications: 5 copies of application - Applicant will reproduce the copies at his/her costs. The Township Clerk
More information2.1.4 Roof Downspout Rain Gardens
2008 SWMM, 2010 Revision City of Tacoma 2.1.4 Roof Downspout Rain Gardens Purpose and Definition Bioretention areas are shallow stormwater retention facilities designed to mimic forested systems by controlling
More informationCase Study Bioretention Installation and Maintenance
Case Study Bioretention Installation and Maintenance Bioretention Crime Scene Investigation A reality TV series where you get to watch disturbing bioretention crimes and use advanced forensics to solve
More informationAppendix F Construction phase management
Appendix F Construction phase management F.1. Introduction... 1 F.2. Core principles of sediment and erosion control... 2 F.3. Planning... 3 F.4. Occupational health and safety... 7 F.5. References / further
More informationErosion Control for Home Builders in the. City of Jacksonville
Erosion Control for Home Builders in the City of Jacksonville Eroding construction sites are a leading cause of water quality problems in Jacksonville. For every acre under construction, about a dump truck
More information6.1 Bioretention Areas
SAN MATEO COUNTYWIDE WATER POLLUTION PREVENTION PROGRAM 6.1 Bioretention Areas Figure 6-1. Bioretention Area. Source: City of Brisbane Bioretention areas 1, or rain gardens, are concave landscaped areas
More informationChapter 4 - Preparation of Stormwater Site Plans
Chapter 4 - Preparation of Stormwater Site Plans The Stormwater Site Plan is the comprehensive report containing all of the technical information and analysis necessary for the City to evaluate a proposed
More information5.0 Storm Water Landscape Guidance Introduction
5.0 Storm Water Landscape Guidance Introduction Landscaping is a critical element to improve both the function and appearance of storm water management practices. Integrated storm water landscapes can
More informationCHAPTER 4. SPECIAL CONDITION EROSION CONTROL MEASURES
CHAPTER 4. SPECIAL CONDITION EROSION CONTROL MEASURES 4.1 INFILTRATION BASIN AND TRENCH Figure 4.1. Infiltration basin and trench (Source: Department of Civil, Construction, and Environmental Engineering,
More informationBIORETENTION FACILITY
ILLINOIS URBAN MANUAL PRACTICE STANDARD BIORETENTION FACILITY (feet) CODE 800 Source: Jessica Cocroft, Winnebago Soil and Water Conservation District DEFINITION Facility that utilizes a soil media, mulch,
More informationORDINANCE NO LC
ORDINANCE NO. 07-52-LC AN ORDINANCE OF THE CITY OF DESTIN, FLORIDA RELATING TO EROSION AND SEDIMENT CONTROL; PROVIDING FOR AUTHORITY; PROVIDING FOR FINDINGS OF FACT; PROVIDING FOR THE CREATION OF LAND
More informationThe Low Risk Site Handbook
The Low Risk Site Handbook for Erosion Prevention and Sediment Control The content of this Handbook is adapted from the New York State Standards and Specifications for Erosion and Sediment Control-August
More informationNew Development Stormwater Guidelines
New Development Stormwater Guidelines CITY OF MOUNTLAKE TERRACE Table of Contents Introduction... 2 Ecology s Minimum Requirements for stormwater management... 2 Description of the 9 Minimum Requirements...
More informationSITE PLAN REVIEW ITEMS - REFERENCE CHECKLIST
City of Seminole 9199 113 th Street N. Seminole, FL 33772 Ph: (727) 392-1966 Fx: (727) 319-6583 SITE PLAN REVIEW ITEMS - REFERENCE CHECKLIST Note: This checklist is designed to aid designers in the review
More informationThe proper use of erosion and sediment controls will allow the following objectives to be met:
Chapter 5 5.0 Introduction During construction activities, soil is typically moved or disturbed in a way that affects stormwater drainage. The use of Best Management Practices (BMPs) during construction
More informationChecklists. Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Applicant: Contact Name: Phone Number:
Applicant: Contact Name: Phone Number: Email: Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Concept Plan Requirements: I. General Project Information 1. Address or parcel number
More informationKittson Parkway / Watershed Park Parking Lot
Kittson Parkway / Watershed Park Parking Lot Date Constructed: Summer 2005 Site Location / Description: Kittson Parkway, North Delta, British Columbia. Permeable parking lot adjacent to Watershed Park;
More information4. CONCEPT PLAN DEVELOPMENT
4. CONCEPT PLAN DEVELOPMENT Concept Plan Step 1: Identify Site Constraints and Opportunities Review the existing site to identify constraints and opportunities for GI Practices to meet the RRv. Constraints
More informationPhase II Storm Water Permit Program MS4 Permit
Phase II Storm Water Permit Program MS4 Permit Karen Katamay Environmental Protection Engineer/CPESC Illinois EPA Des Plaines Regional Office karen.katamay@illinois.gov 847-294-4043 Types of Storm Water
More informationRAIN GARDEN ILLINOIS URBAN MANUAL PRACTICE STANDARD. (feet) CODE 897 DEFINITION
ILLINOIS URBAN MANUAL PRACTICE STANDARD RAIN GARDEN (feet) CODE 897 Source: Kendall County Soil and Water Conservation District DEFINITION Rain gardens are small, shallow, flat bottomed depressions constructed
More informationChapter 14. Stormwater Quality Introduction
14.0 Introduction This chapter addresses requirements and design criteria related to post-construction stormwater best management practices (requirements for construction erosion and sediment control are
More informationST. MARY S SOIL CONSERVATION DISTRICT (SMSCD) AND DPW&T CONCEPT EROSION AND SEDIMENT CONTROL AND STORMWATER MANAGEMENT GUIDELINES AND CHECKLIST
St. Mary s Soil Conservation District 26737 Radio Station Way, Suite B Leonardtown, MD 20650 Phone: 301-475-8402 ext. 3 Fax: 301-475-8391 www.stmarysscd.com St. Mary s County Government Department of Public
More informationPreventing Storm Water Pollution: What We Can Do
Preventing Storm Water Pollution: What We Can Do ~Employee Training Series~ Land Disturbances PREPARED IN COOPERATION WITH THE Texas Commission on Environmental Quality AND U.S. ENVIRONMENTAL PROTECTION
More informationSoil Erosion & Sediment Control Plan Requirements for Submittal to the Cape Atlantic Conservation District
Soil Erosion & Sediment Control Plan Requirements for Submittal to the Cape Atlantic Conservation District The following is a list of the minimum requirements required on Soil Erosion and Sediment Control
More informationAPPENDIX E DESIGN CRITERIA FOR POST-CONSTRUCTION WATER QUALITY BMPS
APPENDIX E DESIGN CRITERIA FOR POST-CONSTRUCTION WATER QUALITY BMPS This Appendix presents design criteria for Post-Construction Water Quality BMPs to meet 80% TSS removal for use on SCDOT projects: Section
More information4.6. Low Impact and Retentive Grading
4.6. Low Impact and Retentive Grading Low Impact Grading techniques focus on utilizing existing topography during Site layout to minimize cost. Proposing structures, roads, and other impervious surfaces
More informationImage: Montana NRCS USDA
Vegetated Swale Vegetated Swales are broad shallow channels topped with vegetation, also known as bioswales. Swales are designed to slow runoff, promote infiltration, and filter out pollutants and sediments.
More informationVegetated Filter Strips and Buffers
3.15 Sediment Control Description: Buffer strips (existing vegetation) and filter strips (planted vegetation) are sections of vegetated land adjacent to disturbed areas. They are designed with low slopes
More informationEach of these categories and BMPs are described in the following sections.
7.0 EROSION AND SEDIMENT 7.1 General It is important to recognize the difference between erosion control measures and sediment control measures when preparing an effective erosion and sediment control
More informationOPERATIONS & MAINTENANCE MANUAL STORMWATER CONTROL STRUCTURE DRY DETENTION POND
OPERATIONS & MAINTENANCE MANUAL STORMWATER CONTROL STRUCTURE DRY DETENTION POND Owner(s): Address: Phone Number: Site/Subdivision Plan # Location: Prepared by: Receiving Water Course: Date: Date Constructed:
More information12/7/2007. Christopher B. Burke Engineering West, Ltd Aux Sable Creek Watershed Plan Update 1
The ABC s of BMP s Aux Sable Watershed Plan St. Charles, IL Why are BMP s Important Best Management Practices (BMPs) developed as a set of practices which help to achieve goals of the Clean Water Act and
More informationUse of Best Management Practices
Use of Best Management Practices Presented at the ANJEC Flood Hazard Workshop Bordentown, NJ March 13, 2008 Stormwater BMPs "a technique, measure or structural control that is used for a given set of conditions
More informationStep 2/3: Sediment & Stormwater Management Plan Review Checklist
Step 2/3: Sediment & Stormwater Management Plan Review Checklist DATE RECEIVED: PROJECT NUMBER: PROJECT NAME: The items contained on this checklist are necessary to properly evaluate and determine the
More informationHomeowners Guide to Stormwater BMP Maintenance
Homeowners Guide to Stormwater BMP Maintenance What You Need to Know to Take Care of Your Property Rain Barrel Dry Well Rain Garden Pervious Asphalt Porous Pavers City of El Monte Stormwater BMP Management
More informationSTORMWATER PERMIT SUBMITTAL REQUIREMENTS
STORMWATER PERMIT SUBMITTAL REQUIREMENTS Most development within the City of Bellingham that involves disruption of soils, or construction of buildings, streets, parking lots, etc. requires a Stormwater
More informationJune Pennsylvania Department of Transportation Engineering District Herr Street Harrisburg, PA 17103
EROSION & SEDIMENT CONTROL REPORT FOR S.R. 0462 BOX CULVERT REPLACEMENT OVER TRIBUTARY TO STRICKLER RUN WEST HEMPFIELD TWP., LANCASTER CO. Prepared for: June 2006 Pennsylvania Department of Transportation
More informationCHECKLIST FOR PHASE II DRAINAGE REPORT
I. COVER SHEET CHECKLIST FOR PHASE II DRAINAGE REPORT A. Name of Project B. Address C. Owner D. Developer E. Engineer F. Submittal date and revision dates as applicable II. GENERAL LOCATION AND DESCRIPTION
More information4.5 City of Indianapolis Stormwater Green Infrastructure Guidance: Bioretention (rain gardens) Bioretention Fact Sheet Bioretention Technical Design
4.5 City of Indianapolis Stormwater Green Infrastructure Guidance: Bioretention (rain gardens) Bioretention Fact Sheet Bioretention Technical Design Specification Bioretention O & M Manual Draft Green
More informationSTORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE
STORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE Codes analyses for each subcommittee were completed to assist participants of the Richland County Site Planning Roundtable.
More informationPAVING PARKING AREAS AND ROADS DESCRIPTION. Alternate Names: Pavement Practices, Impervious Paving
4.2-i PAVING PARKING AREAS AND ROADS Alternate Names: Pavement Practices, Impervious Paving DESCRIPTION All roads, driveways, and parking lots proposed for year-round use shall be paved with a hard plowable
More informationBowling Green, Kentucky Stormwater Best Management Practices (BMPs) Erosion Prevention Practices (EPPs) Activity: Nets and Mats (N and M)
Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Erosion Prevention Practices (EPPs) Activity: Nets and Mats (N and M) EPP-11 PLANNING CONSIDERATIONS: Design Life: 1 yr Acreage Needed:
More informationAll materials in this presentation are taken from materials produced by:
1 PART I 2 All materials in this presentation are taken from materials produced by: Georgia Soil and Water Conservation Commission 4310 Lexington Road P.O. Box 8024 Athens, GA 30603 706-542-3065 Fax 706-542-4242
More informationBioretention. Matt Scharver Northeast Ohio Regional Sewer District. #ProjectCleanLake
Bioretention Matt Scharver Northeast Ohio Regional Sewer District Stormwater Management Training for MS4 Municipal Employees Training Session Agenda Pre-Training Survey Presentation & Site Visit Post-Training
More information