Citizen Information Meeting

Size: px
Start display at page:

Download "Citizen Information Meeting"

Transcription

1 Prince William County Government Citizen Information Meeting Vint Hill Road Extension May 11, 2016

2 Benefits: Route 28 Corridor Improvement Program Estimated significant cost savings versus bidding these as separate projects. Internal staff efficiencies and time savings. The total project duration can be reduced. Reduced citizen frustration by having a centralized point of contact for responding to their concerns as well as by having coordinated work zones that will allow for better traffic flow. 1

3 2

4 Project Overview Project is being financed with Local funds. Current project estimate is $15.6 million. Administered by the Prince William County Department of Transportation. Widens Vint Hill Road from a two lane undivided roadway to a four lane divided roadway with curb & gutter and a shared use path. Adds sidewalk and widening along both sides of Kettle Run Road to Patriot High School. Project improvements along Vint Hill Road are for 1.14 miles. Safety, Drainage, Capacity, Signals, Pedestrian Access Improvements. Utility relocations. 3

5 Vint Hill Road Typical Section (Design Speed 45 mph) 4

6 Additional Design Features & Considerations Vint Hill Road: Design Speed of 45 mph; Anticipated Posted Speed of 45 mph. Stormwater Management Ponds (2 ponds). Traffic Signal upgrades at Sudley Manor Drive and Kettle Run Road. Pedestrian and Bicycle Facilities: 10 Shared Use Path (North side of Vint Hill Road). 5 Sidewalk (South side of Vint Hill Road between Sudley Manor Drive and Kettle Run Road). 5 Sidewalk (both sides of Kettle Run Road from Vint Hill Road to Patriot H.S.). Vint Hill Road crosswalks at Sudley Manor Drive and Kettle Run Road. Kettle Run Road crosswalks at Vint Hill Road and Patriot H.S. Utility Relocations (Water/Sewer and Private Utilities). 5

7 Environmental Local Environmental Review Process (LERP) Ongoing Environmental Agency Coordination Virginia Department of Historic Resources (VDHR) Virginia Department of Game and Inland Fisheries (VDGIF) Virginia Department of Conservation and Recreation (VDCR) Virginia Department of Environmental Quality (DEQ) Other Environmental Agencies Environmental Permitting Wetland/Stream Delineation Complete Environmental Permits & Mitigation to be Completed Prior to Construction No anticipated effect on cultural resources. 6

8 Right of Way Acquisition Right of Way and easements (permanent and temporary) will be required for project construction. Impacts to 31 parcels are anticipated. Affected property owners will be contacted during land acquisition process initiation. For additional information related to right of way acquisition, please contact Prince William County Right of Way Managers, Mr. Scott Hatten or Mr. Tim Witter: Mr. Scott Hatten Prince William County Dept. of Transportation 5 County Complex Court, Suite 290 Prince William, VA shatten@pwcgov.org Telephone: Mr. Tim Witter Prince William County Dept. of Transportation 5 County Complex Court, Suite 290 Prince William, VA twitter@pwcgov.org Telephone:

9 Project Delivery This project is included as one of three projects in the Prince William County Route 28 Corridor Transportation Improvements Program. The projects are being developed using the Design Build process and are awarded as a single contract. The three projects included in the Program are: Route 28 Widen to Four Lanes (Phase 2) (Realigned Vint Hill Road to Fitzwater Drive) Vint Hill Road Extension Route 28 Widen to Six Lanes (Phase 3) (Linton Hall Road to Pennsylvania Avenue) 8

10 Tentative Project Schedule (Vint Hill Road Extension) January 2017 Award Design Build Contract Summer 2017 Initiate Right of Way Acquisition Fall 2017 Finalize Design / Begin Utility Relocations Late Fall 2017 Begin Road Construction Winter 2018/2019 Project Complete 9

11 Current Project Estimate Preliminary Engineering $1.4 M Right of Way and Utilities $2.6 M Construction $11.6 M Project Total $15.6 M Project is being financed with Local funds. 10

12 Upcoming Activities Geotechnical Investigation (Borings) May/June 2016 Complete Environmental Coordination Review Citizen Information Meeting Comments Update Preliminary Plans as necessary for County Approval Begin Procurement for PWC Route 28 Corridor Transportation Improvements Program 11

13 Questions & Comments Staff from Prince William County Department of Transportation and its consultant, Rinker Design Associates, P.C., are available to discuss the project and answer questions. Written comments can be submitted to Prince William County s Project Manager, Ms. Sherry Djouharian: By at: sdjouharian@pwcgov.org Or by mail at: Ms. Sherry Djouharian Prince William County Department of Transportation 5 County Complex Court, Suite 290 Prince William, VA

14 General Transportation Information Click Here 13

IOWA HIGHWAY 57 / WEST 1 ST STREET STUDY PUBLIC INFORMATIONAL MEETING APRIL 22, 2014

IOWA HIGHWAY 57 / WEST 1 ST STREET STUDY PUBLIC INFORMATIONAL MEETING APRIL 22, 2014 IOWA HIGHWAY 57 / WEST 1 ST STREET STUDY PUBLIC INFORMATIONAL MEETING APRIL 22, 2014 INTRODUCTION The City of Cedar Falls and the Iowa Department of Transportation are conducting a Public Informational

More information

Project Overview. Fairfax County Parkway Widening Fairfax County. Get Involved. Public Information Meeting. Contact Information

Project Overview. Fairfax County Parkway Widening Fairfax County. Get Involved. Public Information Meeting. Contact Information Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.

More information

Princess Anne Road. Phase VII (CIP 2-195) Citizens Information Meeting

Princess Anne Road. Phase VII (CIP 2-195) Citizens Information Meeting Citizens Information Meeting Princess Anne Road Phase VII (CIP 2-195) Wednesday, May 5, 2004 4:30 PM to 7:00 PM Red Mill Elementary School 1860 Sandbridge Road Virginia Beach, VA Welcome to the Citizens

More information

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass The Illinois Department of Transportation and Lake County Division of Transportation welcome you to this Public Hearing for U.S. Route 45 from Illinois Route 132 to Illinois Route 173, including the Millburn

More information

Project Overview. Get Involved. Public Information Meeting. Contact Information

Project Overview. Get Involved. Public Information Meeting. Contact Information Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.

More information

Public Hearing. Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, open house at 4 p.m., formal presentation at 5 p.m.

Public Hearing. Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, open house at 4 p.m., formal presentation at 5 p.m. Public Hearing Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, 2019 open house at 4 p.m., formal presentation at 5 p.m. Welcome to the Public Hearing for the Harborview Road (CR 776)

More information

Cottage Grove Road Reconstruction. City of Madison Engineering

Cottage Grove Road Reconstruction. City of Madison Engineering Public Informational Meeting Cottage Grove Road Reconstruction October 8, 2015 Presentation Outline Introduction Project Purpose & Need Proposed Design Overview Environmental Concerns Pedestrian Needs

More information

Fairfax County Parkway (Route 286) Widening Project

Fairfax County Parkway (Route 286) Widening Project Fairfax County Parkway (Route 286) Widening Project Route 29 (Lee Highway) to Route 123 (Ox Road) State Project No. 0286-029-259, P101; UPC 107937 Fairfax Station HOA Meeting January 30, 2018 7:00 to 9:00

More information

Capital Projects impacting Odenton Town Center

Capital Projects impacting Odenton Town Center Capital Projects impacting Odenton Town Center 1 2 E549700 W801600/ W801602 Anne Arundel County Department of Public Works Manor View Elementary School Transmission Main - MD 32 @ Meade Phase 2 $34,399,000

More information

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A WELCOME! 168 TH STREET IMPROVEMENTS 6:30 Open House 7 8 Presentation & Q&A 8 8:30 Open House WELCOME Todd Pfitzer City of Omaha Engineer Bob Stubbe City of Omaha Public Works Director Jon Meyer Project

More information

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017 Community Meeting No. 2 May 31, 2017 Transportation Projects On or Near SH 199 SH 199 from 0.3 miles south of FM 1886 to south end of Lake Worth bridge Construct freeway mainlanes and frontage roads 10-Year

More information

Prince William Street Project (Grant Avenue to Wellington Road)

Prince William Street Project (Grant Avenue to Wellington Road) Prince William Street Project (Grant Avenue to Wellington Road) 1 Goals Improve pedestrian and bike traffic safety Improve street drainage with curb & gutter Upsize water mains Enhance overall street appearance

More information

Rt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016 Rt. 29 Solutions Project Delivery Advisory Panel January 7, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Dec

More information

Chain Bridge Road Sidewalk Improvements Citizen Council Work Session

Chain Bridge Road Sidewalk Improvements Citizen Council Work Session Chain Bridge Road Sidewalk Improvements Citizen Council Work Session May 10, 2016 Project Location 2 Project Objectives Provide a continuous pedestrian facility (sidewalk) connection from Downtown City

More information

Capital Projects in and near Odenton Town Center

Capital Projects in and near Odenton Town Center Capital Projects in and near Odenton Town Center Map ID Anne Arundel County Department of Public Works This project provides for the design, right of way acquisition, and construction of approximately

More information

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25)

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25) ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25) Preliminary Design Report February 2015 Prepared For: City of Inver Grove Heights Dakota County Prepared By: Kimley-Horn and Associates,

More information

PUBLIC HEARING. Thursday, December 14, 2017 FDOT Urban Office 2198 Edison Avenue Jacksonville, FL 32204

PUBLIC HEARING. Thursday, December 14, 2017 FDOT Urban Office 2198 Edison Avenue Jacksonville, FL 32204 DISTRICT TWO PUBLIC HEARING I 10 (SR 8) from I 295 to I 95 Project Development & Environment Study Duval County, Florida Financial Project Number 213326 2 22 01 Efficient Transportation Decision Making

More information

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below:

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below: Race Road/Jessup Village Planning Study (H550601) Project Newsletter Spring 2015 Project Description The Study Team, consisting of staff from Anne Arundel County (Department of Public Works and Department

More information

SECTION 4(f) DE MINIMIS DOCUMENTATION

SECTION 4(f) DE MINIMIS DOCUMENTATION SECTION 4(f) DE MINIMIS DOCUMENTATION Illinois Route 60/83 IL 176 to the intersection of IL 60 (Townline Road) Lake County P-91-084-07 Mundelein Park and Recreation District Project Limit SECTION 4(f)

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Endorsement of Design for Route 7/George Washington Boulevard Overpass. Algonkian and Broad Run

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Endorsement of Design for Route 7/George Washington Boulevard Overpass. Algonkian and Broad Run BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM Date of Meeting: March 7, 2017 # 14 SUBJECT: ELECTION DISTRICTS: CRITICAL ACTION DATE: STAFF CONTACTS: Endorsement of Design for Route 7/George Washington

More information

Elgin O Hare Western Access Project Local Advisory Committee. February 10, 2014

Elgin O Hare Western Access Project Local Advisory Committee. February 10, 2014 Elgin O Hare Western Access Project Local Advisory Committee February 10, 2014 Agenda Project status update Design and construction Funding Aesthetics Project events and outreach Land acquisition Next

More information

Bostwick Road. Municipal Class Environmental Assessment. Public Information Centre #2 June 14, City of London

Bostwick Road. Municipal Class Environmental Assessment. Public Information Centre #2 June 14, City of London Bostwick Road Municipal Class Environmental Assessment Public Information Centre #2 June 14, 2017 Welcome! Welcome to the 2 nd Public Information Centre for the. Representatives from the and the consulting

More information

OVERMOUNTAIN VICTORY TRAIL BURKE CALDELL CORRIDOR FEASIBLITY STUDY REQUEST FOR QUALIFICATIONS CALDWELL COUNTY PATHWAYS

OVERMOUNTAIN VICTORY TRAIL BURKE CALDELL CORRIDOR FEASIBLITY STUDY REQUEST FOR QUALIFICATIONS CALDWELL COUNTY PATHWAYS OVERMOUNTAIN VICTORY TRAIL BURKE CALDELL CORRIDOR FEASIBLITY STUDY REQUEST FOR QUALIFICATIONS CALDWELL COUNTY PATHWAYS Caldwell County Pathways along with our co-partners City of Lenoir, Town of Gamewell,

More information

PennDOT Public Meeting. S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project

PennDOT Public Meeting. S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project PennDOT Public Meeting S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project Mt Lebanon Township, Allegheny County Mt Lebanon Township Municipal Building November 6, 2014 1 Project

More information

DESIGN PUBLIC HEARING. Phase II

DESIGN PUBLIC HEARING. Phase II CITY OF SYRACUSE DEPARTMENT OF ENGINEERING STEPHANIE A. MINER, Mayor MARY E. ROBISON, City Engineer DESIGN PUBLIC HEARING Phase II City of Syracuse Onondaga County Tuesday, July 26, 2016 at 7:00 P.M. Southwest

More information

Meeting Purpose: Date and Time: Location: Attendance: Handouts:

Meeting Purpose: Date and Time: Location: Attendance: Handouts: Meeting Purpose: Date and Time: Location: Attendance: Handouts: PA Turnpike / I-95 Interchange Project Design Advisory Committee (DAC)/Public Officials Meeting #8 April 12, 2012 at 1:30 p.m. Project Office,

More information

Kankakee River Bridge & Track Improvements Supplemental Environmental Assessment. May 5, 2016

Kankakee River Bridge & Track Improvements Supplemental Environmental Assessment. May 5, 2016 Kankakee River Bridge & Track Improvements Supplemental Environmental Assessment May 5, 2016 1 History: Chicago-St. Louis Corridor Since 1980 s IDOT has been looking at this corridor for high-speed service

More information

5-Year Street Reconstruction Plan ( )

5-Year Street Reconstruction Plan ( ) 5-Year Street Reconstruction Plan (2006-2010) City of Delano Wenck File #0564-37 Prepared for: CITY OF DELANO 234 2 nd Street West Delano, MN 55328 Prepared by: WENCK ASSOCIATES, INC. 1800 Pioneer Creek

More information

2040 Long Range Transportation Plan

2040 Long Range Transportation Plan 2040 Long Range Transportation Plan Adopted: April 15, 2013 APPENDIX D HIGHWAY NEEDS PLAN PROJECTS FREDERICKSBURG Existing and Committed Projects Fall Hill Avenue/Mary Washington Blvd. (Fredericksburg)

More information

BENJAMIN BANNEKER PARK FRAMEWORK PLAN (PLAN ADOPTION)

BENJAMIN BANNEKER PARK FRAMEWORK PLAN (PLAN ADOPTION) BENJAMIN BANNEKER PARK FRAMEWORK PLAN (PLAN ADOPTION) COUNTY BOARD MEETING DECEMBER 16, 2017 County Board Consideration: Adopt the Benjamin Banneker Park Framework Plan and Design Guidelines Framework

More information

ALMA DRIVE CONSTRUCTION Project Public Meeting June 18, :00 pm

ALMA DRIVE CONSTRUCTION Project Public Meeting June 18, :00 pm ALMA DRIVE CONSTRUCTION Project Public Meeting June 18, 2015 6:00 pm Tim Porter, P.E. Program Manager 214.509.4581 tporter@cityofallen.org Angela Mosley, P.E. Project Manager 214.509.4579 amosley@cityofallen.org

More information

SUNBRIDGE PARKWAY PRELIMINARY DESIGN STUDY. Board of County Commissioners Public Hearing

SUNBRIDGE PARKWAY PRELIMINARY DESIGN STUDY. Board of County Commissioners Public Hearing SUNBRIDGE PARKWAY PRELIMINARY DESIGN STUDY Board of County Commissioners Public Hearing March 20, 2018 Presentation Overview Study Overview Existing Conditions Project Development Plan Public Involvement

More information

PROJECT BACKGROUND. Preliminary Design Scope and Tasks

PROJECT BACKGROUND. Preliminary Design Scope and Tasks PROJECT BACKGROUND Preliminary Design Scope and Tasks The purpose of this Study is the development of preliminary designs for intersection improvements for Trunk Highway (TH) 36 at the intersections of

More information

SR-2 Freeway Terminus Improvement Project

SR-2 Freeway Terminus Improvement Project SR-2 Freeway Terminus Improvement Project Welcome! Public Hearing, Mayberry Elementary June 16, 2009, 6:30 p.m. 8:30 p.m. Agenda 6:30 PM 6:50 PM Registration and Open House 6:50 PM 7:00 PM Welcome and

More information

Commissioners Road West Realignment Environmental Assessment

Commissioners Road West Realignment Environmental Assessment City of London Commissioners Road West Realignment Environmental Assessment Public Information Centre No. 1 March 30, 2017 Welcome to the Public Information Centre This first Public Information Centre

More information

COLLIER BOULEVARD (CR 951) CORRIDOR

COLLIER BOULEVARD (CR 951) CORRIDOR Project(s) Goals Improve Traffic Circulation, Capacity & Safety Focus on Safety During Design & Construction Address Public Concerns Design an Aesthetically Pleasing Project Limit Environmental Impacts

More information

DESIGN CRITERIA PACKAGE

DESIGN CRITERIA PACKAGE RFQ: 17-C-00003 DESIGN-BUILD SERVICES FOR THE DESIGN CRITERIA PACKAGE PREPARED BY: JAMES E. JACKSON, JR. AIA CITY ARCHITECT CONTRACT ADMINISTRATION DEPARTMENT and INTERFLOW ENGINEERING, L.L.C DESIGN CRITERIA

More information

Errol Heights Park and Community Garden Frequently Asked Questions March 22, 2018

Errol Heights Park and Community Garden Frequently Asked Questions March 22, 2018 Errol Heights Park and Community Garden Frequently Asked Questions March 22, 2018 Question 1: What improvements are planned for Errol Heights Park? How will the community be engaged in the process to shape

More information

SR 15 SECTION 088 CSVT SOUTHERN SECTION PUBLIC MEETING JUNE 16, 2015

SR 15 SECTION 088 CSVT SOUTHERN SECTION PUBLIC MEETING JUNE 16, 2015 PUBLIC MEETING JUNE 16, 2015 AGENDA PROJECT HISTORY NORTHERN SECTION UPDATE SOUTHERN SECTION OVERVIEW INTERCHANGES PROJECT SCHEDULE UPCOMING ACTIVITIES OPEN DISCUSSION & GROUP QUESTIONS ONE-ON-ONE QUESTIONS

More information

Rt. 29 Solutions Project Delivery Advisory Panel. December 3, 2015

Rt. 29 Solutions Project Delivery Advisory Panel. December 3, 2015 Rt. 29 Solutions Project Delivery Advisory Panel December 3, 2015 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Nov

More information

14 October 10, 2012 Public Hearing APPLICANT: MPB, INC

14 October 10, 2012 Public Hearing APPLICANT: MPB, INC 14 October 10, 2012 Public Hearing APPLICANT: MPB, INC PROPERTY OWNER: MUNDEN & ASSOCIATES, LP STAFF PLANNER: Karen Prochilo REQUEST: Conditional Change of Zoning (AG-1 & AG-2 to Conditional O-2) ADDRESS

More information

Request for Proposal

Request for Proposal Request for Proposal 10 th Street Corridor Master Plan Department of Planning and Zoning 500 Quartermaster Court Suite 200 Jeffersonville, IN 47130 April 18, 2017 For further information contact: Chad

More information

9 th Street Sub Area Plan

9 th Street Sub Area Plan 9 th Street Sub Area Plan In the 1990 s, when the Township prepared the last Master Plan, the 9 th Street corridor was studied as part of a larger 9 th Street Focus Area that included the West Main Street

More information

2017 General Obligation Bond

2017 General Obligation Bond 2017 General Obligation Bond Presentation of Public and Council Projects to the Transportation & Mobility Stakeholder Committee April 13, 2017 Agenda Deferred Maintenance Project Development Process Projects

More information

Public Officials/Design Advisory Meeting #12. Bensalem Township Municipal building, 2400 Byberry Road Bensalem, PA

Public Officials/Design Advisory Meeting #12. Bensalem Township Municipal building, 2400 Byberry Road Bensalem, PA Meeting Purpose: Date and Time: Location: Attendance: Materials: PA Turnpike/I 95 Interchange Project Public Officials/Design Advisory Meeting #12 June 2, 2016 at 11:00 a.m. Bensalem Township Municipal

More information

Welcome. Date: Thursday March 2, 2017 Time: 6:30 p.m. 9:00 p.m. Location: Woodview School Gym, 69 Flatt Road, Burlington Presentation Time: 7:00 p.m.

Welcome. Date: Thursday March 2, 2017 Time: 6:30 p.m. 9:00 p.m. Location: Woodview School Gym, 69 Flatt Road, Burlington Presentation Time: 7:00 p.m. Welcome Public Information Centre No.2 City of Burlington, City of Hamilton, Region of Halton Waterdown Road Widening Detailed Design Craven Avenue to Mountain Brow Road Date: Thursday March 2, 2017 Time:

More information

Construction Engineering & Inspection

Construction Engineering & Inspection Construction Engineering & Inspection Serving Florida for 20 Years CEI Engineering Planning Landscape Architecture Urban Design Construction Engineering & Inspection (CEI) I N T R O D U C T I O N Over

More information

Lower Hill Infrastructure Project Meeting Minutes

Lower Hill Infrastructure Project Meeting Minutes Lower Hill Infrastructure Project Meeting Minutes SUBJECT: Scoping Field View MEETING DATE: January 28, 2014 (Revised 3-17-14 to address comments received from R. Collins, J. Bucher) MEETING TIME: 9:00

More information

Burton Station Village Community Meeting February 26, 2014

Burton Station Village Community Meeting February 26, 2014 February 26, 2014 SGA Plan Overview Recent announcements by the City of Norfolk regarding the closure of Lake Wright Golf Course and retail development proposals Update on infrastructure improvement plans

More information

Pasco County Watershed Meeting for Flood Impacted Areas Port Richey Watershed

Pasco County Watershed Meeting for Flood Impacted Areas Port Richey Watershed Pasco County Watershed Meeting for Flood Impacted Areas March 15, 2017 Regency Park Library, 9701 Little Road, New Port Richey, Pasco County The following is a summary of the meeting held on March 15,

More information

PROJECT SHOWING MINUTES

PROJECT SHOWING MINUTES PROJECT SHOWING MINUTES North Lynn Street Esplanade Improvements Project No. 0029-000-859, C501, B605 UPC No. 109813 November 1, 2017 10:00 a.m. 1911 North Ft. Myer Drive, LL-10, Arlington, VA Overview

More information

CHAPTER VIII Implementation

CHAPTER VIII Implementation CHAPTER VIII Implementation VIII. Implementation The vision for the Marlboro Pike Corridor will require that a variety of participants work together to make it a reality. The following action steps outline

More information

RFP REQUEST FOR PROPOSALS CITY OF PORTSMOUTH, NH. DESIGN ENGINEERING SERVICES North Mill Pond Trail and Greenway

RFP REQUEST FOR PROPOSALS CITY OF PORTSMOUTH, NH. DESIGN ENGINEERING SERVICES North Mill Pond Trail and Greenway RFP 61-18 REQUEST FOR PROPOSALS CITY OF PORTSMOUTH, NH DESIGN ENGINEERING SERVICES North Mill Pond Trail and Greenway Sealed Requests for Proposals, plainly marked RFP 61-18 Design Engineering Services

More information

Public Meeting. US Highway 14 (6TH Street) from Main Ave to Medary Ave Urban Reconstruction Project Brookings, SD P-PH 0014(179)419 PCN 027B

Public Meeting. US Highway 14 (6TH Street) from Main Ave to Medary Ave Urban Reconstruction Project Brookings, SD P-PH 0014(179)419 PCN 027B Public Meeting US Highway 14 (6TH Street) from Main Ave to Medary Ave Urban Reconstruction Project Brookings, SD P-PH 0014(179)419 PCN 027B Mark Leiferman Chief Road Design Engineer April 28, 2014 Why

More information

Middlebury RS 0174(8)

Middlebury RS 0174(8) Middlebury RS 0174(8) Preferred Alternative Meeting VT 125 Bridge #13 over Middlebury River August 6, 2012 Presented to Presented by Town of Middlebury VTrans & VHB Introductions: Jennifer Fitch VTrans

More information

The transportation system in a community is an

The transportation system in a community is an 7 TRANSPORTATION The transportation system in a community is an important factor contributing to the quality of life of the residents. Without a sound transportation system to bring both goods and patrons

More information

Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL

Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL Agenda Design Concept Report Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Questions Design Concept Report

More information

BOISE, IDAHO COUNCIL WORK SESSION AGENDA September 19, :00 PM City Hall - Council Chambers

BOISE, IDAHO COUNCIL WORK SESSION AGENDA September 19, :00 PM City Hall - Council Chambers BOISE, IDAHO COUNCIL WORK SESSION AGENDA September 19, 2017 5:00 PM City Hall - Council Chambers I. CALL TO ORDER II. WORK SESSION ITEMS 1. Interim Changes (10 mins) Presenter: Brent Davis, Finance and

More information

Community Development Rezoning Report REZ14-006

Community Development Rezoning Report REZ14-006 Community Development Rezoning Report REZ14-006 Planning Commission Board of Supervisors March 4, 2014 March 26, 2014 Applicant M & N Real Estate, LLC Tax Map Id 125-(A)- L20E,125-(A)- L20E1, portion of

More information

Route 7 Reconstruction and Widening, Wilton. State Project Nos & 124. Wolf Pit Road to just north of Olmstead Hill Road

Route 7 Reconstruction and Widening, Wilton. State Project Nos & 124. Wolf Pit Road to just north of Olmstead Hill Road Route 7 Reconstruction and Widening, Wilton State Project Nos. 161-118 & 124 Wolf Pit Road to just north of Olmstead Hill Road Tonight s Agenda Introduction Bill Brennan, Wilton First Selectman Construction

More information

AGENDA ITEM: IOWA. west] that were not FISCAL IMPACT. the City of Clive. STAFF REVIEW. Resolution II. Amendment PREPARED BY: REVIEWED BY:

AGENDA ITEM: IOWA. west] that were not FISCAL IMPACT. the City of Clive. STAFF REVIEW. Resolution II. Amendment PREPARED BY: REVIEWED BY: AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: March 7, 2016 AGENDA ITEM: Consideration of approval of a resolution approving Engineering Services Amendment No. 1 with

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Landscape Architecture Program NUMBER: SPECIFIC SUBJECT: Integration of Landscape

More information

TIRZ 17/Redevelopment Authority Capital Improvements Plan Projects

TIRZ 17/Redevelopment Authority Capital Improvements Plan Projects Gessner Widening: T-1701 What: Widen the road from a six-lane divided boulevard to an eight-lane divided boulevard street section, increase turn lanes, update traffic signal system, improve drainage by

More information

Open House RIVER DES PERES GREENWAY: LANSDOWNE SHREWSBURY METROLINK TO FRANCIS R. SLAY PARK

Open House RIVER DES PERES GREENWAY: LANSDOWNE SHREWSBURY METROLINK TO FRANCIS R. SLAY PARK Open House 10.12.16 RIVER DES PERES GREENWAY: LANSDOWNE SHREWSBURY METROLINK TO FRANCIS R. SLAY PARK MEETING AGENDA Great Rivers Greenway and Project Partners River des Peres Greenway Overview Project

More information

DRAFT MAP AMENDMENT FLU 04-4

DRAFT MAP AMENDMENT FLU 04-4 DRAFT MAP AMENDMENT FLU 04-4 SW 24 TH AVENUE ROADWAY CORRIDOR The University of Florida participates with the Metropolitan Transportation Planning Organization (MTPO) in its responsibilities for the continuing,

More information

September 28, 2017 Wentworth Avenue (CR 8) Sidewalk Improvements Open House

September 28, 2017 Wentworth Avenue (CR 8) Sidewalk Improvements Open House TIME Anytime from 5:00 PM to 7:00 PM LOCATION City Hall Council Chambers Learn about the project Speak with project representatives Provide input YOU RE INVITED! September 28, 2017 Wentworth Avenue (CR

More information

McDonald s Restaurant - Purcellville Town of Purcellville Special Use Permit Statement of Justification July 24, 2014

McDonald s Restaurant - Purcellville Town of Purcellville Special Use Permit Statement of Justification July 24, 2014 Introduction / Written Statement McDonald s Restaurant - Purcellville McDonald s Corporation is proposing to redevelop the existing McDonald s eating establishment with a drive-through located at 121 N

More information

THREE-YEAR CAPITAL IMPROVEMENT PLAN FY

THREE-YEAR CAPITAL IMPROVEMENT PLAN FY THREE-YEAR CAPITAL IMPROVEMENT PLAN FY2016 2018 Annual CIP Development Process Public Works & Engineering Divisions Prepare List of Capital Needs and Recommended Deferred Maintenance Public Works & Engineering

More information

City of Manassas Park Proposed Stormwater Management Funding

City of Manassas Park Proposed Stormwater Management Funding City of Manassas Park Proposed Stormwater Management Funding October 5, 2010 State and Federal Storm Water Mandates The State mandates implementation of ordinance, programs, and practices to meet storm

More information

AGENDA ACTION ITEMS INFORMATION ITEMS

AGENDA ACTION ITEMS INFORMATION ITEMS NOACA Bicycle and Pedestrian Advisory Council Meeting Friday, March 21 st, 2014 10:30 a.m. NOACA Office 1299 Superior Avenue Cleveland, Ohio 44114 Phone: (216) 241-2414; website: www.noaca.org AGENDA ACTION

More information

CHARLES COUNTY GOVERNMENT RFP NO POPES CREEK RAIL TRAIL DESIGN

CHARLES COUNTY GOVERNMENT RFP NO POPES CREEK RAIL TRAIL DESIGN CHARLES COUNTY GOVERNMENT Department of Fiscal and Administrative Services Purchasing Division Telephone: 301-645-0656 July 7, 2015 RFP NO. 16-02 POPES CREEK RAIL TRAIL DESIGN ADDENDUM NUMBER ONE TO: All

More information

Reconnecting New Haven: Downtown Crossing

Reconnecting New Haven: Downtown Crossing Reconnecting New Haven: Downtown Crossing Phase 2 Update Introduction to Phase 3 November 16, 2017 City of New Haven, Connecticut Toni N. Harp, Mayor Reconnecting New Haven Introduction Project Overview

More information

City of Los Angeles Department of Public Works

City of Los Angeles Department of Public Works City of Los Angeles Department of Public Works Environmental Scoping Meeting for the Proposed Sixth Street Park, Arts, River & Connectivity Improvements (PARC) Project May 3, 2017 1 Agenda Introductions

More information

COMMUNITY DESIGN. GOAL: Create livable and attractive communities. Intent

COMMUNITY DESIGN. GOAL: Create livable and attractive communities. Intent COMMUNITY DESIGN Intent An attractive, well-designed County will attract quality development, instill civic pride, improve the visual character of the community, and create a strong, positive image for

More information

GLX Project Green Line Extension Project GLX WORKING GROUP PRESENTATION OCTOBER 2, 2014

GLX Project Green Line Extension Project GLX WORKING GROUP PRESENTATION OCTOBER 2, 2014 GLX Project Green Line Extension Project 1 Agenda Welcome GLX Sustainability Project Overview & Updates Upcoming Public Meetings Station Meeting Lechmere Station Meeting Union Sq. & Washington St. Working

More information

East Corridor Final Environmental Impact Statement

East Corridor Final Environmental Impact Statement East Corridor Final Environmental Impact Statement Alternatives Considered Operating Plan The requirements for opening day operations versus year 2030 are based on ridership and operations. Opening day

More information

Metro Orange Line Extension Four Years Early and $61 Million Under Budget

Metro Orange Line Extension Four Years Early and $61 Million Under Budget White Paper: Metro Orange Line Extension Four Years Early and $61 Million Under Budget July 2013 Innovation for better mobility Metro Orange Line Extension Iteris, Inc. was the prime consultant leading

More information

Expo Light Rail Line. Expo Line Community Meeting Phase 2 Design Update November 2011

Expo Light Rail Line. Expo Line Community Meeting Phase 2 Design Update November 2011 Expo Line Community Meeting Phase 2 Design Update November 2011 Meeting Agenda Phase 2 Design Update Meeting Meeting Purpose and Format Project Status Update Overview of Design Progress Next Steps Open

More information

New Braunfels Growth & Development. Garry Ford, Jr., P.E., PTOE City Engineer City of New Braunfels

New Braunfels Growth & Development. Garry Ford, Jr., P.E., PTOE City Engineer City of New Braunfels New Braunfels Growth & Development Garry Ford, Jr., P.E., PTOE City Engineer City of New Braunfels Overview Growth Development Transportation Water Challenges Addressing the Growth, Development and Challenges

More information

City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01

City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01 City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01 July 27, 2009 TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Plan Area Location & Context... 1 1.2 Ownership

More information

Public Services Department

Public Services Department Public Services Department PAUL SMITH PUBLIC SERVICES DIRECTOR Memorandum Date: July 24, 2018 To: Honorable Mayor and Board of Commissioners Through: Mark LeCouris, City Manager From: Paul Smith, Public

More information

Agenda. Background Review of public process Recent project activities Current Status Next steps for construction

Agenda. Background Review of public process Recent project activities Current Status Next steps for construction January 30, 2019 Agenda Background Review of public process Recent project activities Current Status Next steps for construction Pond Background The pond was initially built as a dry pond to collect stormwater

More information

INDEX EXECUTIVE SUMMARY...1 BASIC INFORMATION AND PROCEDURES...3 EXISTING CONDITIONS EXISTING UTILITIES

INDEX EXECUTIVE SUMMARY...1 BASIC INFORMATION AND PROCEDURES...3 EXISTING CONDITIONS EXISTING UTILITIES INDEX EXECUTIVE SUMMARY...1 INTRODUCTION...2 BASIC INFORMATION AND PROCEDURES...3 EXISTING CONDITIONS... 4-5 EXISTING UTILITIES... 6-7 MEDIAN BREAKS AND TURN LANE STORAGE REQUIREMENTS...8 PRELIMINARY DESIGN

More information

4/8/2015 Item #10D Page 1

4/8/2015 Item #10D Page 1 MEETING DATE: April 8, 2015 PREPARED BY: Christy Villa, Associate Civil Engineer DEPT. DIRECTOR: Glenn Pruim DEPARTMENT: Public Works CITY MANAGER: Larry Watt SUBJECT: NORTH COAST HIGHWAY 101 STREETSCAPE

More information

I-4 Beyond the Ultimate. Florida Transportation Builders Association February 9, 2018

I-4 Beyond the Ultimate. Florida Transportation Builders Association February 9, 2018 I-4 Beyond the Ultimate Florida Transportation Builders Association February 9, 2018 FDOT: Improving Mobility & Safety in Central Florida FDOT is Designing and building a better I-4 through Central Florida

More information

Panama City Beach Community Redevelopment Agency ON THE MOVE IN PCB

Panama City Beach Community Redevelopment Agency ON THE MOVE IN PCB Panama City Beach Community Redevelopment Agency ON THE MOVE IN PCB Program Goals, Activities and Accomplishments I. Beach Front Multi-modal Transportation, Aesthetic and Parking Improvements III. Connector

More information

Drexel, Barrell & Co.

Drexel, Barrell & Co. Drexel, Barrell & Co. December 21, 2018 Engineers/Surveyors Boulder Colorado Springs Greeley 3 South 7 th Street Colorado Springs, Colorado 80905-1501 719 260-0887 719 260-8352 Fax El Paso County Planning

More information

Project Goal. RRRC Living Towns Planning Workshp. Town of Halifax Revitalization Project. Dynamic Planning & Management Duo: July 12, 2006

Project Goal. RRRC Living Towns Planning Workshp. Town of Halifax Revitalization Project. Dynamic Planning & Management Duo: July 12, 2006 Project Goal Town of Halifax Revitalization Project RRRC Living Towns Planning Workshp July 12, 2006 Town of Halifax Halifax County *** Revitalization Project Goal*** To create Economic Opportunity and

More information

Fall 2017 Construction Update

Fall 2017 Construction Update Fall 2017 Construction Update Ward 4 Southeast Engineering Department Riverwalk Red Multi-Use Trail Bridge Rehabilitation The Riverwalk Red Multi Use Trail Bridge was awarded to Cramer and Associates,

More information

9IMPLEMENTATION AND PHASING

9IMPLEMENTATION AND PHASING 9IMPLEMENTATION AND PHASING Purpose A key objective of the Railyard Master Plan is the integration of the public and private realm to provide a network of places that connect to and complement Commercial

More information

Strachan Ave. Overpass Community Design Update. October 26, 2010 Stephen Lipkus Executive Director Georgetown South Project GO Transit

Strachan Ave. Overpass Community Design Update. October 26, 2010 Stephen Lipkus Executive Director Georgetown South Project GO Transit Strachan Ave. Overpass Community Design Update October 26, 2010 Stephen Lipkus Executive Director Georgetown South Project GO Transit Welcome Program Overview 6:30 8:30 p.m.: Storyboard Review Project

More information

Scope of Services. River Oaks Boulevard (SH 183) Corridor Master Plan

Scope of Services. River Oaks Boulevard (SH 183) Corridor Master Plan Scope of Services River Oaks Boulevard (SH 183) Corridor Master Plan PROJECT AREA The project area consists of the River Oaks Boulevard (SH 183) corridor bounded by SH 199 at the northern end and the Trinity

More information

Flooding Hearing: Long and Short Term Strategies

Flooding Hearing: Long and Short Term Strategies Services of the San Francisco Public Utilities Commission Flooding Hearing: Long and Short Term Strategies Presentation to San Francisco Board of Supervisors Public Safety and Neighborhood Services Subcommittee

More information

Pine Island Road Corridor Master Plan

Pine Island Road Corridor Master Plan RECOMMENDED DEVELOPMENT PLAN Figure 9: Del Prado Village District Conceptual Framework The Conceptual Framework (Figure 8) for development of the Pine Island Corridor is to encourage mixed-use development

More information

I-494 Rehabilitation Project SP (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination

I-494 Rehabilitation Project SP (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination I-494 Rehabilitation Project SP 2785-330 (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination State Project Number 2785-330 Federal Project No. NHPP-I494 (002) Trunk Highway:

More information

Ann Arbor Intermodal Station Environmental Review

Ann Arbor Intermodal Station Environmental Review Ann Arbor Intermodal Station Environmental Review Park Advisory Commission September 19, 2017 AGENDA 1. Project Update 2. Draft Environmental Assessment 3. Draft Preferred Alternative 4. Next Steps 5.

More information

Welcome to the. Open House

Welcome to the. Open House Welcome to the 5th Street to Kinsman Road Open House November 14 5:30 7:00 p.m. Please sign in Project Overview In December 2016, City Council adopted SW 5th Street as the preferred alignment to connect

More information

Asbury Chapel Subdivision Sketch Plan

Asbury Chapel Subdivision Sketch Plan Asbury Chapel Subdivision Sketch Plan PART 1: PROJECT SUMMARY Applicant: NVR Inc. Project Size: +/- 76.13 acres Parcel Numbers: 02101112,02116101,02116112, 02116113 Current Zoning: Transitional Residential

More information

Public Works Project Delivery Report

Public Works Project Delivery Report Public Works Project Delivery Report May 2017 San Gabriel Public Works delivers reliable infrastructure & welcoming public spaces by designing, constructing, operating & maintaining the City s streets,

More information

St. Clair Avenue West Area Transportation Master Plan

St. Clair Avenue West Area Transportation Master Plan 1 (Between Keele Street and Old Weston Road) Public Information Centre 1 December 2, 2015 2 Welcome Welcome to the first Public Information Centre for the St. Clair Avenue West Area. The panels will present

More information