1 ADDENDUM FORM INVITATION TO TENDER: ADDENDUM NO: 1 DATE ISSUED: June 23, 2016 ISSUED BY: Monty Thibeault DESCRIPTION: Replacement of Fire Pump and Generator Upgrade, H Building, Sexton Campus INSTRUCTIONS: Amend your copy of the Tender document as detailed below. Sign and return this addendum (attachments not necessary) with your Tender submission or indicate the number of Addenda on your Tender Summary Form as confirmation that the addendum was taken into consideration. DETAILS OF ADDENDUM: This one page addendum is issued as follows: CLARIFICATIONS: 1. Construction dates: o Construction start day: July 18, 2016 o Substantial completion date: Aug 31, Owner supplied fire pump and controller as well as Jockey pump and controller. 3. Owner supplied Kohler Generator enclosure. 4. There will a number of parts Dalhousie wants to keep for spares, list to follow. All other Terms and Conditions remain unchanged. Addenda submitted by facsimile or electronic communication will not be accepted. NAME OF FIRM: SIGNATURE:

2 ADDENDUM FORM INVITATION TO TENDER: ADDENDUM NO: 2 DATE ISSUED: June 24, 2016 ISSUED BY: Monty Thibeault DESCRIPTION: INSTRUCTIONS: Replacement of Fire Pump and Generator Upgrade, H Building, Sexton Campus Amend your copy of the Tender document as detailed below. Sign and return this addendum (attachments not necessary) with your Tender submission or indicate the number of Addenda on your Tender Summary Form as confirmation that the addendum was taken into consideration. DETAILS OF ADDENDUM: This two page addendum plus attachment is issued as follows: SPECIFICATIONS 1. Section Electrical General Requirements Delete item 1.4 in its entirety and replace with the following: 1.4 Upgrade the existing 120/208V emergency generator to comply with the latest edition of CSA C282 and as specified herein. This work includes offloading and installation of the Ownersupplied Kohler generator enclosure. 2. Section Power Generation Diesel DRAWINGS Replace this section in its entirety and replace with the revised section included in this addendum. 3. Drawing E1-1 Electrical Proposed Plans Reference Detail 1: 1. There is an existing high voltage underground ductbank that runs to the existing unit substation located in room HA29 (near the corner of the building). Locate and verify exact routing of this ductbank prior to any excavation work. If necessary to avoid the high voltage ductbank, shorten the length of the generator concrete pad to minimum 176 long. 2. Relocate the existing battery charger to the new generator enclosure. All other Terms and Conditions remain unchanged. Addenda submitted by facsimile or electronic communication will not be accepted. NAME OF FIRM: SIGNATURE:

3 4. Drawing E1-3 Electrical Partial Single Line Diagram Addendum #2/Tender /Page 2 of 2 Reference Detail 1 - Partial Single Line Diagram: 1. Field install the two (2) circuit breakers as specified within the new Kohler generator enclosure. Provide mounting structure comprised of 1-5/8 u-shaped strut with mounting feet. Coordinate final locations with the generator supplier to ensure that the breakers are accessible and do not interfere with the operation and maintenance of the generator. Connect the line side of each breaker to the generator alternator using RW90 conductors in liquid tight conduit, conductor size to match load conductors. Coordinate final terminations with the generator manufacturer. 2. Where single conductor cables enter into an electrical enclosure, provide a non-ferrous entry plate to prevent circulating currents. Reference Block Diagram 2 Emergency Generator controls 1. Verify exact cabling connections between the remote annunciator and the generator controller with the generator supplier. 2. Supply and install power connections to the existing generator auxiliaries including battery charger, block heater and strip heater.

4 DAL - Architecture Building DIESEL Page 1 PART 1 GENERAL 1.1 Scope of Work.1 This section covers the work for the modification of the existing emergency generator to comply with CSA C282, supply and installation of field wiring, start-up, testing and commissioning of the emergency generator..2 Upgrade the existing generator as indicated herein. Coordinate work related to upgrading the existing emergency generator with Sansom Equipment Ltd. and the generator manufacturer (Kohler)..3 Receive and offload the Owner-supplied sound attenuated, weatherproof drop over emergency generator enclosure. Coordinate delivery with the Owner. If necessary, safely store the enclosure unit until it can be installed. Install the enclosure as part of the generator upgrade work. 4. Complete civil works including concrete pad and bollard replacement with new. Reinstate asphalt disturbed by this work. 1.2 References.1 CSA - C282-15, Emergency Electrical Power Supply for Buildings. PART 2 PRODUCTS 2.1 Existing Equipment.1 One 94 KW, 118 kva, 208V, 3 phase Kohler diesel engine standby emergency generator set complete with non-walk in, enclosure, roof mounted silencer and sub-base fuel tank..2 Battery charger. 2.2 Owner Supplied.1 Drop over sound, attenuated, weather proof enclosure Equipment (Model GWE A2-80) as follows:.1 Weather resistant, sound attenuated aluminum drop over enclosure with access doors..2 Enclosure Dimensions: 90 High x 54 wide x 164 L + 23 Intake hood..3 External Intake hood..4 External Discharge hood..5 DC Light package..6 Incandescent light package V, 20A GFCI receptacles.

5 DAL - Architecture Building DIESEL Page A, 120/208V, 1 phase load centre. Electrical components within the enclosure will be pre-wired to this panel..9 Electric space heater and thermostat..10 Motor Intake louvre(s).11 Motor discharge damper..12 Battery warmer (ships loose)..2 Roof mounted critical type silencer with mounting hardware..3 Remote Annunciator Panel 2.3 Circuit Breakers.1 Moulded case circuit breakers in accordance with Section and each complete with thermal magnetic overcurrent trip unit. Refer to drawings for quantity and ampacity ratings. The minimum short circuit rating for each circuit breaker must be 10,000A (RMS momentary symmetrical) at the rated voltage..2 Circuit breaker enclosure: NEMA 3R enclosure..3 Each circuit breaker is to be complete with provision to padlock in the OFF position and auxiliary contact (breaker open)..4 Include line and load side lugs. 2.4 Exhaust Systems.1 Include fittings, supports and accessories as required. 2.5 Auxiliary.1 One (1) remote emergency stop. Equipment.2 Modification of the generator controls to connect the new remote annunciator. PART 3 EXECUTION.3 Modification of the generator to include alarm annunciation and alarm/trouble contacts to comply with CSA C Installation.1 Disconnect, remove and safely store the existing emergency generator to facilitate removal of the existing concrete pad. Remove the existing electrical and controls wiring to the existing generator. Coordinate this work with the Owner..2 Handle, install and connect the emergency generator set in strict accordance with manufacturer's instructions. Ensure instructions are available on site when required.

6 DAL - Architecture Building DIESEL Page 3.3 Remove the existing generator concrete pad. Provide new reinforced concrete pad for the upgraded standby emergency and new drop over enclosure as specified. Verify exact conduit stub-up locations with the new drop over generator enclosure shop drawing and the existing generator layout..4 Provide cast-in-place concrete equipment attachments as required by the equipment manufacturer..5 Provide correct type and full number, size and length of anchor bolts and other connecting bolts as required by equipment manufacturer. Preset anchor bolts in concrete where convenient; otherwise leave suitable openings in concrete and set anchor bolts later using epoxy anchors or other approved fastening methods..6 Coordinate location and provide items for embedding into castin-place concrete..7 Install the existing emergency generator back in place on new concrete pad..8 Arrange and pay for Sansom Equipment Ltd./Kohler Power Systems to supervise and assist with upgrading, modifying and testing of the existing emergency generator and associated equipment to comply with CSA - C Remove and dispose the existing generator outdoor enclosure. Install the new drop over enclosure over the existing generator and sub-base fuel tank..10 Remove any rust with a wire brush, prime surface and repaint the existing generator components including the sub-base fuel tank, alternator enclosure and supports..11 Install new generator output circuit breakers as indicated and connect line side to the existing generator alternator wiring. Confirm mounting locations with the manufacturer. Connect breakers to loads as indicated. Connect open position auxiliary contacts (one per breaker) to the generator control panel for annunciation..12 Supply and install new power and control field wiring to the existing auxiliary equipment as follows: battery charger, block heater, strip heater. These devices are to be connected to a

7 DAL - Architecture Building DIESEL Page 4 120V receptacle or the 120/208V load centre within the new generator enclosure as directed by the generator manufacturer..13 Change all fluids and air filters with new..14 If not already installed, add new common alarm and common trouble dry contacts to the existing generator control panel..15 Verify existing trip level of low fuel alarm and advise Consultant if it is set at less than 2 hours of fuel..16 Add new fuel tank leakage alarm and connect to the existing generator control panel for annunciation..17 Add new low coolant level alarm and connect to the existing generator control panel for annunciation..18 Install and connect remote annunciator panel in accordance with the manufacturer's instructions. Annunciate alarms to comply with CSA C Install and connect remote emergency stop push button in accordance with the manufacturer's instructions..20 Reinstate asphalt and granular sub-base material affected by this work with new as specified on the drawings..21 Replace the existing bollards with new as specified on the drawings..22 All new generator components, if not Owner-supplied, are to be approved by or supplied by the generator manufacturer. 3.2 Responsibility of.1 Obtain written permission from the Consultant to use and test Temporary Trial Usage permanent equipment and systems prior to acceptance by the Owner..2 The guarantee period must not be affected by temporary trial use of the equipment..3 Clean and renew equipment and systems used before acceptance. Restore to original or new working condition..4 Protect equipment and systems openings from dirt, dust and other foreign materials during temporary usage.

8 DAL - Architecture Building DIESEL Page Inspection, Testing.1 Coordinate, arrange, assist and pay the factory certified And Start-Up technician to check the complete installation and be present for the start-up of the upgraded generator. Submit a written report signed by the equipment manufacturer's representative to the Consultant stating the following:.1 That a satisfactory installation of equipment has been performed and outlining any modifications that have been made as a result of the commissioning or testing of the equipment at no additional cost to the Contract..2 That the equipment is now ready for permanent operation..2 Advise in writing at least two weeks in advance of the proposed date for testing and startup..3 Replace defective material or equipment with new material or equipment. Bear costs including re-testing and repairing. 3.4 Field Quality.1 Conduct testing in accordance with CSA C282. Demonstrate: Control.1 Unit start, transfer to load, retransfer to normal power, unit shut down, on "Automatic" control..2 Unit start and shut down on "Manual" control.3 Unit start and transfer on "Test" control..4 Unit start on "Engine start" control..5 Operation of automatic alarms and shut down devices..2 Provide resistive load bank and temporary connecting cables sized for full rating of generator for full load testing. Assist Vendor as required in set-up..3 Run unit on 100% load for a minimum period of four (4) hours to show load carrying ability, stability of voltage and frequency and satisfactory performance of heat exchanger system to provide adequate engine cooling..4 After full load testing, conduct operational testing under normal building load. Run unit on under normal building load (Load Scenario #1 elevator run, fire pump off; Load Scenario #2 elevator off, fire pump run) for a minimum period of one (1) hour..5 During testing, measure sound levels at 1m and 7m. Submit test results to the Owner.

9 DAL - Architecture Building DIESEL Page 6.6 At end of test run, check battery voltage to demonstrate battery charger has returned battery to fully charged state..7 Submit start up report to the Consultant within five days of successful commissioning of system..8 Provide fuel for testing.

10

.4 Do complete installation in accordance with latest Electrical Bulletins of the local inspection authority.

.4 Do complete installation in accordance with latest Electrical Bulletins of the local inspection authority. Fitness Facility Addition Page 1 1.1 CODES AND STANDARDS.1 Do complete installation in accordance with the latest edition of the CSA C22.1 as amended by the latest editions of the National Building Code

More information

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 36 23 SPEC WRITER NOTE: Use this section only for NCA projects. Delete between //--// if not applicable to project. Also, delete any other item or paragraph

More information

SECTION GENERATOR PARALLELING CONTROLS

SECTION GENERATOR PARALLELING CONTROLS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 23 13 GENERATOR PARALLELING CONTROLS SPEC WRITER NOTE: Delete between // -- // if not applicable to project. Also delete any other item or paragraph not applicable

More information

SECTION EMERGENCY POWER SYSTEMS

SECTION EMERGENCY POWER SYSTEMS SECTION 16620 EMERGENCY POWER SYSTEMS A. Standby Engine/Generator Systems 1. Installations of stationary engine/generator (e/g) systems shall be designed in strict accordance with ANSI/NFPA 70 - National

More information

B. Section Transfer Switches: Automatic transfer switch.

B. Section Transfer Switches: Automatic transfer switch. SECTION 263213 - ENGINE GENERATORS PART 1 GENERAL 1.1 SECTION INCLUDES A. Packaged engine generator set. B. Exhaust silencer and fittings. C. Remote control panel. D. Battery and charger. E. Weatherproof

More information

ENGINE GENERATORS AND ACCESSORIES

ENGINE GENERATORS AND ACCESSORIES ENGINE GENERATORS AND ACCESSORIES GENERAL INFORMATION 1.1 This section applies to engine generators and accessories. DESIGN REQUIREMENTS 2.1 The Engineer of Record will consult with the University s Engineering

More information

SECTION P01 LIGHTING AND APPLIANCE PANELBOARDS - A-SERIES

SECTION P01 LIGHTING AND APPLIANCE PANELBOARDS - A-SERIES PART 1 GENERAL A. The requirements of the Contract, Division 1, and Division 16 apply to work in this Section. 1.01 SECTION INCLUDES A. Lighting and appliance panelboards 1.02 RELATED SECTIONS A. 16475,

More information

SECTION PANELBOARDS Painting Wire and Cable Overcurrent Protective Devices.

SECTION PANELBOARDS Painting Wire and Cable Overcurrent Protective Devices. SECTION 16470 PANELBOARDS PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 09900 - Painting. 2. 16120 - Wire and Cable. 3. 16475 - Overcurrent Protective Devices. 1.02 SYSTEM DESCRIPTION A. Performance

More information

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 36 23 This section specifies the furnishing, complete installation, and connection of automatic transfer switches. 1.2 RELATED WORK A. Section 14 21 00, ELECTRIC

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/06/2018

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/06/2018 SECTION 26 2913 - ENCLOSED CONTROLLERS GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

16620 EMERGENCY POWER SYSTEMS

16620 EMERGENCY POWER SYSTEMS 16620 EMERGENCY POWER SYSTEMS PART 1: GENERAL 1.01 SUMMARY A. This Section provides the University guidelines for the installation of Emergency Power Systems. B. This standard is developed primarily to

More information

VACUUM BREAKER MEDIUM VOLTAGE AUTOMATIC TRANSFER SWITCHES

VACUUM BREAKER MEDIUM VOLTAGE AUTOMATIC TRANSFER SWITCHES Part One General 1.01 Scope A. It is the intent of this specification to provide a medium voltage automatic transfer system. B. All components, testing and services specified and required for a complete

More information

CONTENTS AUTOMATIC TRANSFER SWITCHES

CONTENTS AUTOMATIC TRANSFER SWITCHES CONTENTS AUTOMATIC TRANSFER SWITCHES PART 1 GENERAL 1.1 Related Documents 1.2 Summary 1.3 References 1.4 Quality Assurance 1.5 Submittals 1.6 Delivery, Storage and Handling 1.7 Instructions And Training

More information

1.1 REFERENCES.1 American National Standards Institute/National Fire Protection Association (ANSI/NFPA).1 ANSI/NFPA 20, Centrifugal Fire Pumps.

1.1 REFERENCES.1 American National Standards Institute/National Fire Protection Association (ANSI/NFPA).1 ANSI/NFPA 20, Centrifugal Fire Pumps. Issued 2006/08/01 Section 13920 Packaged Fire Pumps and Controllers Page 1 of 7 PART 1 GENERAL 1.1 REFERENCES.1 American National Standards Institute/National Fire Protection Association (ANSI/NFPA).1

More information

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL SECTION 16400 AUTOMATIC TRANSFER SWITCHES 1.01 RELATED DOCUMENTS PART 1 - GENERAL A. Drawings and general provisions of Contract, including General Conditions and Division 1 Specification sections, apply

More information

GARCIA GALUSKA DESOUSA Consulting Engineers

GARCIA GALUSKA DESOUSA Consulting Engineers L#57297 /Page 1/July 21, 2017 ELECTRICAL SYSTEMS NARRATIVE REPORT The following is the Electrical Systems narrative, which defines the scope of work and capacities of the Power and Lighting systems, as

More information

This Addendum includes the following changes and clarifications to the Contract Documents:

This Addendum includes the following changes and clarifications to the Contract Documents: August 17, 2018 IFB#: 2018-01 IFB Closing on: August 28, 2018 ADDENDUM NO. FIVE TO THE CONTRACT DRAWINGS AND SPECIFICATIONS FOR THE REFERENCED PROJECT, DATED JULY 11, 2018, AS PREPARED BY GRIMM + PARKER

More information

SECTION ENCLOSED CONTROLLERS

SECTION ENCLOSED CONTROLLERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes ac,

More information

CALL FOR TENDER - MUNICIPALITY OF THE DISTRICT OF CLARE LITTLE BROOK, N.S.

CALL FOR TENDER - MUNICIPALITY OF THE DISTRICT OF CLARE LITTLE BROOK, N.S. CALL FOR TENDER - MUNICIPALITY OF THE DISTRICT OF CLARE LITTLE BROOK, N.S. NAME OF TENDER: CONSTRUCT, DELIVER AND COMMISSION 3 (THREE) LIFT STATION ELECTRICAL LOCATION OF WORK: 3 Separate work sites in

More information

Design & Construction Standards, Revised January

Design & Construction Standards, Revised January PART 1 GENERAL 1.01 Scope of Standard A. This standard provides general requirements of The University of Texas at Austin for fire-extinguishing systems other than water-based fire suppression systems.

More information

SMALL WORKS PROJECT REQUEST FOR SEALED BIDS

SMALL WORKS PROJECT REQUEST FOR SEALED BIDS SMALL WORKS PROJECT REQUEST FOR SEALED BIDS PIERCE COUNTY FIRE PROTECTION DISTRICT #22 18421 OLD BUCKLEY HIGHWAY BONNEY LAKE, WA 98391 (253) 863-1800 (253) 863-1848 (FAX) Date Bid Requested: 5/24/2012

More information

SECTION ISOLATED POWER SYSTEMS

SECTION ISOLATED POWER SYSTEMS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 20 11 ISOLATED POWER SYSTEMS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also, delete any other item or paragraph not applicable to

More information

STATEMENT OF WORK I. SCOPE OF WORK:

STATEMENT OF WORK I. SCOPE OF WORK: STATEMENT OF WORK Purchase and Installation of Diesel Standby Generator Set and Service Entrance Rated Automatic Transfer Switch for Sewage Treatment Plant Nockamixon State Park (Bucks County) I. SCOPE

More information

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION AUTOMATIC TRANSFER SWITCHES SECTION 26 36 23 AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. General provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

EMERGENCY POWER SYSTEMS

EMERGENCY POWER SYSTEMS 263213 EMERGENCY POWER SYSTEMS PART 1: GENERAL 1.01 SUMMARY A. Section includes: 1. University guidelines for the installation of Emergency Power Systems (EPS). 2. Addresses the design and installation

More information

FIRE & LIFE SAFTEY STANDARD

FIRE & LIFE SAFTEY STANDARD Title: Effective Date: 01/01/14 Revised Date: 1/1/14 Code References: Title 16, Chapter 16.16 of the Roseville Municipal Code, NFPA 72 Note: This standard is a summary of Fire Department clarifications

More information

SECTION PANELBOARDS. A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section.

SECTION PANELBOARDS. A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

Revitalize Building Mechanical Systems (4619)

Revitalize Building Mechanical Systems (4619) SECTION 235216 FIRE-TUBE CONDENSING BOILERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION CENTRAL BATTERY INVERTERS. A. This Section includes fast-transfer central battery inverters with the following features:

SECTION CENTRAL BATTERY INVERTERS. A. This Section includes fast-transfer central battery inverters with the following features: PART 1 - GENERAL 1.1 SUMMARY A. This Section includes fast-transfer central battery inverters with the following features: 1. Emergency-only circuits. 1.2 DEFINITIONS A. LCD: Liquid-crystal display. B.

More information

M001. Revenue Services ISSUED FOR CONSTRUCTION SEPTEMBER. 2, East State Parkway Schaumburg, Illinois Do Not Scale Drawings

M001. Revenue Services ISSUED FOR CONSTRUCTION SEPTEMBER. 2, East State Parkway Schaumburg, Illinois Do Not Scale Drawings 1 T Consultant: NOTES, SYMBOLS & ABBREVIATIONS - MECHANICAL Number Description M001 Vestibule 117 LAN/IT Coffee 115 116 Mail Room 118 114 113 112 Scanning 119 Open Office 101 FIRST FLOOR PLAN - MECHANICAL

More information

B. Provide factory test, startup by a supplier authorized by the equipment manufacturer(s), and on-site testing of the system.

B. Provide factory test, startup by a supplier authorized by the equipment manufacturer(s), and on-site testing of the system. SECTION 480V PACKAGED GENERATOR SYSTEMS 1.01 SCOPE PART 1 - GENERAL A. Provide complete factory assembled EPA certified low emission stand-by generator set equipment compatible for paralleling with the

More information

BuildingName The Description of the Project P DOCUMENTS

BuildingName The Description of the Project P DOCUMENTS ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA PART 1 - GENERAL 1.1 Background SECTION 26 00 10- ELECTRICAL DESIGN CRITERIA A. Brown University maintains it own campus electrical distribution system which serves the majority of the buildings and facilities

More information

UFGS (November 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

UFGS (November 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCESA / NASA UFGS-26 28 21.00 40 (August 2008) ----------------------------------- Preparing Activity: NASA Superseding UFGS-26 28 21.00 40 (November 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

PANELBOARDS & BUILDING DISTRIBUTION

PANELBOARDS & BUILDING DISTRIBUTION 262416 PANELBOARDS & BUILDING DISTRIBUTION PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Distribution panelboards 2. Power panelboards B. Related Sections: 1.02 POLICY 1. CU Standard 260500, Basic

More information

TYPE POS Oil Shield Sump Pump

TYPE POS Oil Shield Sump Pump Type POS Oil Shield Provides protection for the environment by preventing oil products from entering sewer systems, environmentally Sensitive River and waterways, while protecting equipment and areas from

More information

D. Reference Standards (Utilize latest editions available):

D. Reference Standards (Utilize latest editions available): 1.01 Scope of Standard A. This standard provides general requirements of The Sam Houston State University for fireextinguishing systems other than water-based fire suppression systems. This document is

More information

Student Services & Classroom Addition. A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards.

Student Services & Classroom Addition. A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. SECTION 262416 - PANELBOARDS PART 1 - GENERAL 1.1 SUMMARY A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. 1.2 PERFORMANCE REQUIREMENTS A. Seismic Performance:

More information

SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM

SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM SECTION 283111 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

PROJECT NO. CWA SEPTEMBER 24, 2014 ADDENDUM NO. 6 BESSEMER RECREATION & WELLNESS CENTER

PROJECT NO. CWA SEPTEMBER 24, 2014 ADDENDUM NO. 6 BESSEMER RECREATION & WELLNESS CENTER PROJECT NO. CWA 2013-04 SEPTEMBER 24, 2014 ADDENDUM NO. 6 BESSEMER RECREATION & WELLNESS CENTER BIDS RECEIVED: CITY HALL, CITY OF BESSEMER TIME: 2:00pm DATE: October 2, 2014 City of Bessemer --------------------------------------------------------------------------------------------------------------------------------------------

More information

Recommended location under the current MasterFormat 2004 is Section Elevator Door Smoke Containment System.

Recommended location under the current MasterFormat 2004 is Section Elevator Door Smoke Containment System. SMOKE GUARD SYSTEM MODEL 600 REV. 3 SPECIFICATION Smoke Guard, Inc 287 Maple Grove Boise, ID 83704 Toll Free: 800.574.0330 Fax: 208.639.7851 e-mail: info@smokeguard.com website: http://www.smokeguard.com/

More information

The following information shall become and form part of the contract documents.

The following information shall become and form part of the contract documents. October 4, 206 To: Attention: Re: All Bidders All Bidders JCBE Gymnasium HVAC Upgrades BC#: 206433 Edmonds Project No.: BHM6090 All bidders, The following information shall become and form part of the

More information

Baldor Electric ProSPEC MASTERFORMAT SPECIFICATION 10/26/05

Baldor Electric ProSPEC MASTERFORMAT SPECIFICATION 10/26/05 SECTION 16230 - GENERATOR ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Provide factory test, startup by a supplier authorized by the manufacturer, and on-site testing of the system. B. The generator set

More information

A. This Section includes transfer switches rated 600 V and less, including the following:

A. This Section includes transfer switches rated 600 V and less, including the following: SECTION 16415 - TRANSFER SWITCHES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

38-SDMS-03 SPECIFICATIONS FOR LV DIGITAL PANEL METERS

38-SDMS-03 SPECIFICATIONS FOR LV DIGITAL PANEL METERS SPECIFICATIONS FOR LV DIGITAL PANEL METERS This specification is property of SEC and subject to change or modification without any notice CONTENTS Clause Page 1.0 SCOPE 3 2.0 CROSS REFERENCES 3 3.0 APPLICABLE

More information

FIRE ALARM SYSTEM 1.1 GENERAL REQUIREMENTS

FIRE ALARM SYSTEM 1.1 GENERAL REQUIREMENTS VALOUR COMMUNITY CENTRE FIRE ALARM SYSTEM Section 28 00 00 GYMNASIUM ADDITION & RENOVATION Page 1 of 3 28 00 00 FIRE ALARM SYSTEM 1.1 GENERAL REQUIREMENTS 1.2 SCOPE 1. The specification covering the General

More information

Fire alarm system specification for multiple tenant retail buildings

Fire alarm system specification for multiple tenant retail buildings Date: June 20, 2011 Project name: Baederwood Shopping Center Multiple Tenant Buildings B & C City/ State: Abington, PA Landlord s Vendor Contact: Dan Morrin Jr., NECCO Security Phone: (215)638-7999 Email:

More information

INVITATION TO TENDER ITT NO. PS KILLARNEY COMMUNITY CENTRE ENERGY UPGRADE ADDENDUM NO. 2

INVITATION TO TENDER ITT NO. PS KILLARNEY COMMUNITY CENTRE ENERGY UPGRADE ADDENDUM NO. 2 FINANCE, RISK AND BUSINESS PLANNING GROUP Supply Chain Management November 4, 2015 INVITATION TO TENDER ITT NO. PS20151058 KILLARNEY COMMUNITY CENTRE ENERGY UPGRADE ADDENDUM NO. 2 RE: Insert attached Section

More information

A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards.

A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. SECTION 262416 - PANELBOARDS PART 1 - GENERAL 1.1 SUMMARY A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. 1.2 PERFORMANCE REQUIREMENTS A. Seismic Performance:

More information

SPECIFICATION MICROMIST FIRE SUPPRESSION SYSTEM WITH SHP-PRO CONTROL PANEL

SPECIFICATION MICROMIST FIRE SUPPRESSION SYSTEM WITH SHP-PRO CONTROL PANEL SECTION 1 - GENERAL CONDITIONS I. SCOPE: This specification outlines the requirements for a Fike Micromist Water Mist Fire Suppression System with automatic detection and control. The work described in

More information

SECTION LOW VOLTAGE POWER PANELBOARDS - SPECTRA

SECTION LOW VOLTAGE POWER PANELBOARDS - SPECTRA PART 1 GENERAL A. The requirements of the Contract, Division 1, and Division 16 apply to work in this Section. 1.01 SECTION INCLUDES A. Low voltage power panelboards 1.02 RELATED SECTIONS 1.03 REFERENCES

More information

IT Module. User Manual. Document Revision Number 1 07/2013

IT Module. User Manual. Document Revision Number 1 07/2013 IT Module User Manual Document Revision Number 1 07/2013 Schneider Electric IT Module User Manual Table of Contents Table of Contents... 2 1. Safety Information... 3 2. Transportation and Installation...

More information

SECTION SECURITY TESTING AND COMMISSIONING

SECTION SECURITY TESTING AND COMMISSIONING SECTION 280800 - SECURITY TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 WORK INCLUDES A. General Description: This specification section covers the provision of preliminary testing, acceptance testing,

More information

SECTION AIR DOORS

SECTION AIR DOORS SECTION 23 34 33 AIR DOORS Berner Series VSA air doors are designed for openings up to 12 ft for environmental separation and up to 10 ft for insect control. Berner Series VSB air doors are designed for

More information

1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load centers.

1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load centers. September 2012, rev. 00 26 2416 Panelboards PART 1. GENERAL 1.01 Summary A. Section includes: 1.02 Definitions 1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load

More information

38-SDMS-01 SPECIFICATIONS FOR FAULT INDICATORS FOR UNDERGROUND DISTRIBUTION NETWORKS

38-SDMS-01 SPECIFICATIONS FOR FAULT INDICATORS FOR UNDERGROUND DISTRIBUTION NETWORKS SPECIFICATIONS FOR FAULT INDICATORS FOR UNDERGROUND DISTRIBUTION NETWORKS This specification is property of SEC and subject to change or modification without any notice CONTENTS Clause Page 1.0 SCOPE 3

More information

PART 4 ELECTRICAL STANDARDS

PART 4 ELECTRICAL STANDARDS PART 4 ELECTRICAL STANDARDS 1.0 INTRODUCTION AND SCOPE: These standards reflect the general requirements and recommendations of elevator contractors, with respect to the power distribution system to achieve

More information

SPECIFICATION MICROMIST FIRE SUPPRESSION SYSTEM WITH CHEETAH Xi 50 CONTROL PANEL

SPECIFICATION MICROMIST FIRE SUPPRESSION SYSTEM WITH CHEETAH Xi 50 CONTROL PANEL SECTION 1 - GENERAL CONDITIONS I. SCOPE: This specification outlines the requirements for a Fike Micromist Water Mist Fire Suppression System with a Cheetah Xi 50 addressable detection and control system.

More information

PART GENERAL 1.01 SECTION INCLUDES

PART GENERAL 1.01 SECTION INCLUDES Specification Number: 26 24 16.06 Product Name: Emergency Lighting Control NQ Circuit Panelboards: 240 Vac, 48 Vdc Maximum SECTION 26 24 16.06 Emergency Lighting Control NQ Circuit Panelboards: 240 Vac,

More information

A. Drawings and general provisions of Contract, including General and Supplementary Conditions apply to work of this section.

A. Drawings and general provisions of Contract, including General and Supplementary Conditions apply to work of this section. SECTION 16770 PAGE 1 PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. Drawings and general provisions of Contract, including General and Supplementary Conditions apply to work of this section. B. Division 16

More information

SECTION (16460) - LOW-VOLTAGE TRANSFORMERS

SECTION (16460) - LOW-VOLTAGE TRANSFORMERS PART 1 GENERAL 1.01 SUMMARY SECTION 26 22 00 (16460) - LOW-VOLTAGE TRANSFORMERS A. Section Includes: 1. Dry-Type Distribution And Specialty Transformers Rated 1000 V And Less. a. General-Purpose Distribution

More information

elite Model ELN Centralized Emergency Lighting Inverter Systems 550 W to 1.5 KW Systems

elite Model ELN Centralized Emergency Lighting Inverter Systems 550 W to 1.5 KW Systems 5/25/16 rev 6 elite Model ELN General Specification 550 W to 1.5 KW elite Model ELN Centralized Emergency Lighting Inverter Systems 550 W to 1.5 KW Systems 1.0 General General Specification This specification

More information

SECTION DOMESTIC WATER PRESSURE BOOSTING SYSTEMS (VFD) PART 1 - GENERAL 1.1 SUMMARY

SECTION DOMESTIC WATER PRESSURE BOOSTING SYSTEMS (VFD) PART 1 - GENERAL 1.1 SUMMARY SECTION 22 11 23.13 DOMESTIC WATER PRESSURE BOOSTING PART 1 - GENERAL 1.1 SUMMARY A. Where utility water pressure cannot adequately meet the pressure requirements of the domestic water systems and where

More information

SECTION DOMESTIC WATER HEATERS

SECTION DOMESTIC WATER HEATERS SECTION 223500 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to

More information

SECTION ELECTRICAL GENERAL PROVISIONS

SECTION ELECTRICAL GENERAL PROVISIONS PART 1 GENERAL 1.01 SECTION INCLUDES A. General provisions for Electrical Systems B. Wire and cable for 600 volts and less. C. Wiring connectors. D. Electrical tape. E. Heat shrink tubing. F. Wire pulling

More information

Electrical Design Guidelines Table of Contents

Electrical Design Guidelines Table of Contents C: Compliant Rev. 3 Dated June 13 11 NC: Non-Compliant NA: Not Applicable Page1 16.1 General 16.2 Single Line Diagrams 16.3 Electric Motor Equipment and Controls 16.4 Lighting 16.5 Emergency Lighting 16.6

More information

B. Configuration of system shall be through Schneider Electric in Homewood, Illinois (Jerry Lanfear ).

B. Configuration of system shall be through Schneider Electric in Homewood, Illinois (Jerry Lanfear ). SECTION 28 13 00 - ACCESS CONTROL PART I - GENERAL 1.1 SUMMARY A. This specification section describes the furnishing, installation, commissioning, and programming of a complete, turnkey, hardwired Andover

More information

SUGGESTED SPECIFICATION For Series 300 Manual Transfer Switches (3MTS)

SUGGESTED SPECIFICATION For Series 300 Manual Transfer Switches (3MTS) SUGGESTED SPECIFICATION For Series 300 Manual Transfer Switches (3MTS) PART 1 GENERAL 1.01 Scope Furnish and install manual transfer switches (3MTS) with number of poles, amperage, voltage, and withstand

More information

PWGSC Ontario MULTIPLEX FIRE ALARM SYSTEM Sect Region Project Page 1 Number R

PWGSC Ontario MULTIPLEX FIRE ALARM SYSTEM Sect Region Project Page 1 Number R Region Project Page 1 PART 1 - GENERAL 1.1 REFERENCES.1 CAN/ULC-S524-2006, Standard for the Installation of Fire Alarm Systems..2 CAN/ULC-S525-2007, Audible Signal Device for Fire Alarm Systems..3 CAN/ULC-S526-2007,

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-21 21 03.00 10 February 2009) ---------------------------------- Preparing Activity: USACE Superseding UFGS-21 21 03.00 10 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

UltraLITE Model ELU Centralized Emergency Lighting Inverter 4.2 KW- 5 KW

UltraLITE Model ELU Centralized Emergency Lighting Inverter 4.2 KW- 5 KW 12/23/16 Rev 9 UltraLITE Model ELU General Specification 4.2 KW to 5 KW UltraLITE Model ELU Centralized Emergency Lighting Inverter 4.2 KW- 5 KW 1.0 General General Specification This specification describes

More information

Brighton Area Fire Authority

Brighton Area Fire Authority 615 W. Grand River Ave. Brighton, MI 48116 o: 810-229-6640 f: 810-229-1619 January 14, 2019 Fire Alarm Contractors RE: Fire Alarm Credential & Submittal Requirements To Whom It May Concern: The following

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 26 2416 - PANELBOARDS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

DIVISION 08 OPENINGS HARDWARE AND KEYING PART 1 - GENERAL 1.01 SUMMARY

DIVISION 08 OPENINGS HARDWARE AND KEYING PART 1 - GENERAL 1.01 SUMMARY 08 70 00 PART 1 - GENERAL 1.01 SUMMARY A. Section includes the design and coordination for all necessary hardware and coordination for all doors. Hardware shall include but not necessarily be limited to

More information

CHAPTER 20 SERVICE EQUIPMENT

CHAPTER 20 SERVICE EQUIPMENT SERVICE EQUIPMENT CHAPTER 20 SERVICE EQUIPMENT Service equipment includes service cabinets and the equipment and materials necessary for installation. 20.1 Signal Service Cabinet For MnDOT traffic control

More information

C. ASME Compliance: Fabricate and label water chiller heat exchangers to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

C. ASME Compliance: Fabricate and label water chiller heat exchangers to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1. SECTION 236426 - ROTARY-SCREW WATER CHILLERS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes packaged, water cooled or air cooled as scheduled, electric-motor-driven, rotary-screw water chillers

More information

UFGS (August 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS

UFGS (August 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-26 28 21.00 40 (August 2014) --------------------------------- Preparing Activity: NASA Superseding UFGS-26 28 21.00 40 (August 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

Update all extract references to NFPA documents (including NFPA 72) in Chapter 3 and related annex material to the latest editions.

Update all extract references to NFPA documents (including NFPA 72) in Chapter 3 and related annex material to the latest editions. 11/16/12 TerraView First Revision No. 15-NFPA 720-2012 [ Global Input ] Update all extract references to NFPA documents (including NFPA 72) in Chapter 3 and related annex material to the latest editions.

More information

SECTION HEATING BOILER FEEDWATER EQUIPMENT

SECTION HEATING BOILER FEEDWATER EQUIPMENT SECTION 23 53 00 HEATING BOILER FEEDWATER EQUIPMENT PART 1 - GENERAL 1.1 SUMMARY A. Section includes boiler feedwater pumps, de-aerators, accessories, controls and tanks. 1.2 REFERENCES A. ASME (American

More information

SECTION AIR COILS

SECTION AIR COILS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:

More information

SECTION Fire Pumps

SECTION Fire Pumps SECTION 21 30 00 Fire Pumps PART 1 GENERAL 1.1 WORK INCLUDED A. Furnish, install and test a motor-driven fire pump, jockey pump, and controllers in the space provided and as shown in the contract drawings.

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-28 31 75.00 10 (November 2008) ----------------------------------- Preparing Activity: USACE Superseding UFGS-28 31 75.00 10 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

DONALD H. BERG, ARCHITECT

DONALD H. BERG, ARCHITECT DONALD H. BERG, ARCHITECT DVA PROJECT 632-CSI-402 PET/CT ROOM #A0-10 RENOVATION BASEMENT LEVEL, BUILDING 200 ARCHITECT S PROJECT No. 0917-02 ADDENDUM NO. 1 JUNE 25, 2018 Page 1 of 1 ARCHITECTURAL 1. Specifications:

More information

performed by City of Virginia Beach Public Utilities

performed by City of Virginia Beach Public Utilities City of Virginia Beach Public Utilities Sanitary Sewer Pump Station Specifications - Amendments Section Sub-Section Name Date Modification 1502 3.01 Pump Station Flow Control 6/24/2014 Add the following

More information

Special Provision No. 682S27 June This Special Provision refers to the following standards, specifications or publications:

Special Provision No. 682S27 June This Special Provision refers to the following standards, specifications or publications: CONTROLLER CABINETS, POLE MOUNTED - Item No. Special Provision No. 682S27 June 2017 1. SCOPE This Special Provision covers the requirements for the installation of pole mounted controller cabinets and

More information

A. AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION (AAMA) 101: Appendix Dissimilar Materials.

A. AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION (AAMA) 101: Appendix Dissimilar Materials. B B11.0 DIVISION 08 - OPENINGS SECTION 08 17 00 INTEGRATED DOOR OPENING ASSEMBLIES Specifier Note: Coordinate and edit articles and paragraphs below to suit project requirements. Add section numbers and

More information

SECTION FIRE DETECTION AND ALARM

SECTION FIRE DETECTION AND ALARM PART 1 - GENERAL 1.1 RELATED SECTIONS: Refer to Section 15300 for requirements regarding fire protection systems. 1.2 SCOPE OF SECTION: This section contains the requirements for equipment and installation

More information

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION SECTION 237433, PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to

More information

ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT. February 29, NO CHANGE: March 8, 2012 / NOT LATER THAN 2:00 PM

ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT. February 29, NO CHANGE: March 8, 2012 / NOT LATER THAN 2:00 PM ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT February 29, 2012 RFP NO: 17 PROJECT: Josephine County Justice Center HVAC Upgrades BID CLOSING DATE: NO CHANGE: March 8, 2012 / NOT LATER

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Magnetic Flowmeters C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Magnetic Flowmeters C O N T E N T S Revised 04/13/16 SPECIFICATIONS - DETAILED PROVISIONS Section 17210 - Magnetic Flowmeters C O N T E N T S PART 1 - GENERAL... 1 1.01 GENERAL REQUIREMENTS... 1 1.02 PROJECT SPECIFIC REQUIREMENTS... 1 1.03

More information

Installation Guide. Heating cables. Thin concrete (< 3 cm) Intelligent solutions with lasting effect. Visit DEVI.com

Installation Guide. Heating cables. Thin concrete (< 3 cm) Intelligent solutions with lasting effect. Visit DEVI.com Installation Guide Heating cables Thin concrete (< 3 cm) Intelligent solutions with lasting effect Visit DEVI.com Table of contents 1 Introduction.................... 2 1.1 Safety Instructions...............2

More information

Florida Department of Transportation

Florida Department of Transportation Page 1 of 7 RICK SCOTT GOVERNOR Florida Department of Transportation 1109 S. Marion Avenue Lake City, Florida 32025 ANANTH PRASAD SECRETARY September 27, 2011 To: Proposal Holders Addendum No: 1, E2Q23,

More information

Architect s Project Number of 12 Fire Alarm/Smoke Detection Systems District Master Specs 2013 Edition

Architect s Project Number of 12 Fire Alarm/Smoke Detection Systems District Master Specs 2013 Edition PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 28 31 00 FIRE ALARM AND SMOKE DETECTION SYSTEMS A. Fire alarm and smoke detection systems 1.2 REFERENCES A. NFPA 72 B. NFPA 101 1.3 REGULATORY REQUIREMENTS A.

More information

TENDER DOCUMENT FOR SUPPLY OF EPOXY MIXING & POURING PLANT

TENDER DOCUMENT FOR SUPPLY OF EPOXY MIXING & POURING PLANT BHARAT HEAVY ELECTRICALS LTD., CORPORATE R&D DIVISION VIKAS NAGAR, HYDERABAD-500093 (INDIA) Enquiry : Date : PURCHASE SECTION TECHNICAL SECTION SPEC.NO. 91 40 2377 8474 PHONE 91 40 2377 4494 Ext.7326 ST:ICH:08:001

More information

PowerWave 2 Busway System

PowerWave 2 Busway System PowerWave 2 Busway System Guide Specifications (Revision 004, 11/17/2017) 1 GENERAL 1.1 Summary This specification covers the electrical characteristics and general requirements for a continuous opening,

More information

SECTION FIRE ALARM AND SMOKE DETECTION SYSTEMS

SECTION FIRE ALARM AND SMOKE DETECTION SYSTEMS PART 1 GENERAL 1.1 SECTION INCLUDES A. Fire alarm and smoke detection systems 1.2 REFERENCES A. NFPA 72 B. NFPA 101 1.3 REGULATORY REQUIREMENTS A. System: UL listed B. Conform to requirements of NFPA 101

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 26 3323 - CENTRAL BATTERY EQUIPMENT [for Evanston campus only] PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

LABORATORY AIR COMPRESSORS AND VACUUM PUMPING SYSTEMS

LABORATORY AIR COMPRESSORS AND VACUUM PUMPING SYSTEMS SECTION 22 20 00 LABORATORY AIR COMPRESSORS AND VACUUM PUMPING SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Division 1, "General Requirements",

More information

EG Controls. SLIMVIEW 120 VOLT FLOAT SERIES DUPLEX PUMP CONTROL PANEL SPECIFICATION for CITY OF E G

EG Controls. SLIMVIEW 120 VOLT FLOAT SERIES DUPLEX PUMP CONTROL PANEL SPECIFICATION for CITY OF E G E SLIMVIEW 120 VOLT FLOAT SERIES DUPLEX PUMP CONTROL PANEL SPECIFICATION for CITY OF DATE: 11/13/06 2/1/07 1 Copyright, E, Inc. E 1. ENERAL...4 1.1 Scope Of Work... 4 1.2 Codes and Standards... 4 2. PRODUCTS...5