Fire Code Action Committee (F-CAC) Meeting Minutes June 19-20, 2012 Chicago IL. Summary of Actions and Regional Work Group (RWG) Assignments
|
|
- Jacob Mosley
- 5 years ago
- Views:
Transcription
1 Fire Code Action Committee (F-CAC) Meeting Minutes June 19-20, 2012 Chicago IL Fire-CAC Members in Attendance Anthony Apfelbeck (Vice-Chairman) Daniel Finnegan Howard Hopper, P.E. Andrew King Kelly Nicolello Joe Pierce (Chairman) Emory Rodgers Earl Valios Audience in Attendance Patrick McLaughlin Jeffrey M. Shapiro, P.E., FSFPE Jim Tidwell Vicki Lovell ICC Staff in Attendance Bruce Johnson Bill Rehr Scott Stookey Summary of Actions and Regional Work Group (RWG) Assignments The following items have been approved by the F-CAC and will be moved forward as Track B Change Proposals: IBC- FS41 Item 23, 42, 49, 115, 128, 129 The following RWG and F-CAC assignments are for identified items and topics. F-CAC members will be at each of the RWG meetings to explain the intent and purpose of the change proposals and provide background on the F-CAC discussions on each assigned item. Fire-CAC Western RWG NE RWG Southern RWG Item 13 Item 2C Item 15 Item 15 Item 69B Item 41 Code change topic 11 Item 69E Item 70 Item 68 Code change topic 9 Item 71 Item 69 Item 73 Item 80 Code change topic 4 Item 95 Code change topic 12 Code change topic 6 Code change topic 13
2 June 19 20, 2012 Chicago Meeting Page 2 Based on the titled F-CAC 2012 Code Change Topics ( ) the following topics are new task groups or RWG assignments: Topic 4 Hotwork on Flammable & Combustible Liquid Storage Tanks. Task group is K. Nicollelo, P. McLaughlin and B. Swiecicki. Topic 6 Temporary Tents & Membrane Structures. Tasked to Western RWG Topic 9 Residential CNG Dispensing. Tasked to Southern RWG Topic 11 Fire Performance of Modular Buildings. Tasked to Northeast RWG Topic 12 H 2 O Mist Systems. Tasked to ICC staff and reviewed by F-CAC Topic 13 Class IV Organic Peroxides. Tasked to ICC staff and reviewed by F-CAC The next and final meeting of the Fire-CAC will be November 14 th and 15 th in Chicago, IL. Travel reservations notices will be sent at a later date. June 19, 2012 Meeting Minutes The meeting commenced at Committee members, participants and ICC staff offered self introductions. A review of change proposals was commenced. The Track A public comment was tabled until Wednesday. The Track B change proposals that have been reviewed and modified as a result of the teleconferences were reviewed by the F-CAC members in attendance: Item 2C: P. McLaughlin recommended providing the task group with a clean copy of the change proposal. An additional review of the change proposal as it relates to existing occupancies was also recommended. Item 13: A proposal to add optional power systems was deemed unnecessary. H. Hopper offered a proposal that clearly states the maximum standby and emergency power load transfer and minimum power duration times. His proposal eliminates a proposed table and instead clarifies all the various requirements in all the I-Codes. F-CAC desires this format. The proposal will be divided into two parts: Part I is Section and Part II are all the various I-Code sections requiring correlation. J. Shapiro noted that the definition of Standby Power includes the phrase electric utility power which could eliminate the NFPA 110 & NFPA 70 option of different utility feeds as a source of standby power. This item will be maintained by the F-CAC and not sent to a regional work group. K. Nicolello will chair the item and S. Stookey (ICC Staff) will work on the technical content. Item 42: Reviewed the revised reason statement. Accepted by F-CAC and a motion was made and accepted to move item 42 as a change proposal for Track B. Item 44: Creates a tabular form for establishing fire flow in IRC regulated buildings and proposes to reduce fire flow for dwellings sprinklered in accordance with IRC P2904 or one of the three NFPA sprinkler standards. It includes a requirement clarifying that sprinkler demand can be part of fire flow. One issue is one table is used to reference another table in the proposal, which is not consistent with ICC editorial rules. The item was tabled and B. Rehr will review. Item 49: Clarifies the Appendix C hydrant spacing requirements and allows increased hydrant spacing in buildings protected by an automatic sprinkler system. F-CAC reviewed the reason
3 June 19 20, 2012 Chicago Meeting Page 3 statement. Accepted by F-CAC and a motion was made and accepted to move item 49 as a change proposal for Track B. The F-CAC commenced a review of the document titled F-CAC 2012 Code Change Topics ( ). This document is a summary of and website messages sent to ICC that are proposals for code changes. Based on the committee s review the following topics were moved forward for further study or drafting of change proposals: Topic 4 Hotwork on Flammable & Combustible Liquid Storage Tanks. This item responded to a USCSB investigation dated April 19, 2012 of an incident involving hot work on a vinyl fluoride tank. In this incident that tank undergoing was interconnected with other unit process equipment, which was not adequately isolated. Upon commencing hot work the welder was immediately killed. F-CAC members found that the IFC does not adequately address hot work operations on hazardous process equipment. The scenario of interconnected tanks is not addressed. Other loss issues are compromised floating roof tank seals. In many cases sub contractors are involved. Section is only limited to tanks in refineries, which would not be applicable to this installation. K. Nicollelo, P. McLaughlin and B. Swiecicki to review. Topic 6 Temporary Tents & Membrane Structures. F-CAC moved this item to Western RWG with the Austin (TX) and Dallas (TX) FD amendments. The Western RWG should review the proposal and offer an opinion if there is any value in adding these local amendments to the IFC. Western RWG should not act on the amendment to the IBC as this has already been reviewed by the Building CAC and they will not move to support a change proposal. Topic 9 Residential CNG Dispensing. Review IFGC to determine if the requirements can be improved using reference to, or requirements from, NFPA 52. F-CAC directed Southern Regional Work Group to review IFC Chapter 52, NFPA 52 and IFGC. It appears a link back to the IFC Chapter 23 and IRC for residential CNG dispensers is needed. Topic 11 Fire Performance of Modular Housing. F-CAC referred to the NE RWG. Proposal will need approval by the Building CAC. No action can occur until the 2018 IBC Code Development cycle. Topic 12 Water Mist Systems. Table references NFPA 750 for the inspection, testing and maintenance (IT&M) of water mist systems IFC Section , exception 1.5 recognizes these systems as an alternative fire-extinguishing system for dry cleaning plants. However, Section 904 has no guidance on IT&M or any requirements for their installation. The I-Codes don t define what constitutes a water mist system - it would be good to add some criteria for these systems. Bill Rehr has drafted a change proposal that was added to the Track B Matrix Analysis of Change Proposals. Topic 13 Organic Peroxides. The IFC requirements for Class IV organic peroxides are less restrictive than the current requirements in NFPA 400. NFPA 400 allows these materials in a Group S-1 occupancy but requires automatic sprinkler protection, spill control and mechanical ventilation. The I-Codes need to be correlated as this was a recent change. F-CAC asked S. Stookey to draft a change proposal. The F-CAC reviewed new change proposals. These are items in the Track B Matrix Analysis of Change proposals. Change items 115, 128 and 129 were recommended to be submitted by the F-CAC as Track B change proposals. Any other proposals in the range of item were returned to the
4 June 19 20, 2012 Chicago Meeting Page 4 proponent due to technical issues. The committee comments are shown in the Track B Matrix Analysis of Change Proposals. The Tuesday meeting concluded at 4:50 PM. Minutes of Building CAC and Fire CAC Joint Meeting on June 20, 2012 The meeting commenced at 8:08 AM. F-CAC reviewed the following tabled items: 15, 23, 68, 69B, 69E, 70, 73, 95, 111, 112, 113. The committee comments are shown in the Track B Matrix Analysis of Change Proposals. Notes from F CAC and Building CAC Meeting on June 20, 2012 IFC Chapter 11, IBC Chapter 34 & IEBC Building-CAC has concerns with IFC Chapter 11 in relation to IBC Chapter 34. Steve McDaniel of the B- CAC is handling the revisions to the IEBC and IBC Chapter 34. There are conflicting provisions between IFC Chapter 11 versus Chapter 34 of the IBC and the IEBC. For example, Phase I service in IFC Section 604 has retroactive requirements. Conflicts were identified between IFC Chapter 11 and the IEBC. F- CAC noted that in some jurisdictions the IEBC is not adopted. Jim Tidwell noted that the reason for the creation of Chapter 11 was to identify and articulate the retroactive provisions and to determine if there are correlation issues. Emory Rogers noted this is a jurisdiction scoping issue in Virginia. One major concern of the B-CAC is the protection of vertical openings, which originated from the legacy Uniform Fire Code. S. Winkle with the B-CAC indicated issues regarding historic buildings which can require additional analysis that may not be needed. Chairman J. Pierce proposed a task group between F-CAC and B-CAC: Emory Rogers, Anthony Apfelbeck, Steve Winkle (B-CAC) and Steve McDaniel (B-CAC). Attic Access Question concerning R807.1 attic access in one- and two- family dwellings or townhomes. Is this provision necessary for interior firefighting operations? F-CAC believes this is for equipment the fire service just takes advantage of the opening. This was not a fire service provision. Standby Power & Emergency Power IFC K. Nicolello explained purpose of the modifications to Item 13. D. Bowman indicated IBC Chapter 27 is part of the Track B proposal. Carbon Monoxide (CO) Alarms IFC H. Hopper introduced proposals for changes concerning CO alarms. F-CAC has a large body of stakeholders. Currently IRC has 4 paragraphs on CO alarms. F-CAC is clarifying these requirements to be more reasonable and correlated to current IRC provisions. Informational Appendix in IRC in one- and two-family dwellings IFC A. King explained a proposed information annex on application of P2904. B-CAC indicated this could be useful information for H2O purveyors. The meeting was concluded at 1:10 PM.
5 June 19 20, 2012 Chicago Meeting Page 5 Upcoming Regional Workgroup Meetings The Southern Fire Regional Work Group is hosting a meeting at the Marietta (GA) HQ fire station located at 112 Haynes Street. The meeting is scheduled from 8:00 AM to 5:00 PM on August, and from 8:00 AM to 12:00 PM on August 17, Hotel rooms are available at the Hilton Inn in Marietta located at 500 Powder Springs Rd., Marietta, GA (Telephone: ). The meeting coordinator is Mel Cosgrove. F-CAC member is Alan Perdue. The Midwestern Fire Regional Work Group is a hosting a meeting at the Aloft (Chicago O Hare) Hotel located 9700 Balmoral Avenue in Rosemont, IL. The meeting is scheduled from 8:00 AM to 5:00 PM on August 8, 2012 and from 8:00 AM to 12:00 PM on August 9, Telephone number is The meeting coordinator is Bob Neale. F-CAC members are Dan Finnegan and Earl Valois. The Western Fire Regional Work Group is a hosting a meeting at the Park City Fire Service District Administrative Offices located at 736 West Bitner Road in Park City, UT. The meeting is scheduled from 8:00 AM to 5:00 PM on August 1, 2012 and from 8:00 AM to 12:00 PM on August 2, Point of contact is Fire Marshal/Assistant Chief Scott Adams. The meeting coordinator is David Nichols. F-CAC member is Kelly Nicolello. The Northeast Fire Regional Work Group is a hosting a meeting at the Massachusetts Department of Fire Services located at 1 State Road in Stow, MA. The meeting is scheduled from 9:00 AM to 5:00 PM on August 22, 2012 and from 8:00 AM to 12:00 PM on August 23, The point of contact is Timothee Rodrique. The meeting coordinator is Roland Hall. F-CAC members are Ken Bush and Emory Rodgers.
International Code Council Fire Code Action Committee Group B Topics (Revised February 2, 2015)
International Code Council Fire Code Action Committee Group B Topics - 2015 (Revised February 2, 2015) Topics for Work Group Work Group Leader highlighted 1. High-rise Combustible (wood) Structures and
More informationPreliminary Agenda Technical Committee on Liquefied Petroleum Gas
Preliminary Agenda Technical Committee on Liquefied Petroleum Gas Tuesday, March 10; All Day Wednesday, March 11; All Day DRURY PLAZA HOTEL San Antonio Riverwalk 0. Administrative. A. Meeting Schedule.
More informationOklahoma. 265: Incorporated national codes and standards The following national codes and standards are incorporated by reference:
Oklahoma 310:451-1-3. Adopted references The Board of Health hereby incorporates by reference the International Code Council (ICC) 2006 (IBC) Edition International Building Code; the 2007 Edition Standard
More informationAD HOC HEALTHCARE COMMITTEE MEANS OF EGRESS WORK GROUP APPROVED CODE CHANGE DRAFTS CODE GROUP B MOE COMMITTEE
AD HOC HEALTHCARE COMMITTEE MEANS OF EGRESS WORK GROUP APPROVED CODE CHANGE DRAFTS CODE GROUP B MOE COMMITTEE This report includes 6 code change proposals from the Adhoc Health Care, Means of Egress committee
More informationM E M O R A N D U M. NFPA Technical Committee on Building Services and Fire Protection Equipment
M E M O R A N D U M TO: FROM: NFPA Technical Committee on Building Services and Fire Protection Equipment Linda MacKay DATE: November 10, 2009 SUBJECT: NFPA 5000 A2011 ROP Letter Ballot Final Results The
More information2012 International Fire Code Significant Changes. IFC Background. Purpose IBC and 2012 NFPA 101 Significant Means of Egress Changes
2012 International Fire Code Significant Changes Andrew M. Schneider, P.E. Senior Fire Protection Engineer aschneider@koffel.com Koffel Associates, Inc. www.koffel.com Expertly Engineering Safety From
More informationM E M O R A N D U M. NFPA 5000 A2011 ROP Letter Ballot
M E M O R A N D U M TO: FROM: NFPA Technical Committee on Building Service and Fire Protection Equipment Gregory Harrington, P.E., Staff Liaison DATE: October 1, 2009 SUBJECT: NFPA 5000 A2011 ROP Letter
More informationU.S. Codes & Standards for Energy Storage Systems. Joe Cain, P.E. Chair, SEIA Codes & Standards Working Group
U.S. Codes & Standards for Energy Storage Systems Joe Cain, P.E. Chair, SEIA Codes & Standards Working Group Regulatory Update: U.S. Codes & Standards Agenda NFPA 70 (NEC) UL 1973 & 9540 Fire Codes NFPA
More informationIFC Significant Changes from the 2009 to the 2015 Edition Tier 1
IFC Significant Changes from the 2009 to the 2015 Edition Tier 1 Several medical care definitions were created and revised in Chapter 2 of the 2012 IBC, as well as through the occupancy descriptions, and
More informationHistorical Perspectives for Hydrogen Safety, Regulations, Codes and Standards (California and U.S.A.)
Historical Perspectives for Hydrogen Safety, Regulations, Codes and Standards (California and U.S.A.) Jennifer Hamilton 11 September, 2013 CA overview CaFCP hydrogen fueling station West Sacramento» Second
More informationH gh-p led Combust ble Storage. Application Guide 2009 Edition
H gh-p led Combust ble Storage Application Guide 2009 Edition Table of Contents Preface... v About the International Code Council... vi About the Author... vii Acknowledgements... ix Chapter 1 Introduction
More informationVILLAGE OF DOWNERS GROVE Report for the Village Council Meeting
ORD 2017-7420 Page 1 of 8 VILLAGE OF DOWNERS GROVE Report for the Village Council Meeting SUBJECT: Adoption of 2015 ICC Building and Fire Codes SUBMITTED BY: Stan Popovich, AICP Director of Community Development
More informationTECHNICAL COMMITTEE MEMBERS WHO PARTICIPATED
MEETING MINUTES NFPA Correlating Committee on Safety to Life (SAF-AAC) November 7, 2013 Second Draft Meeting Embassy Suites Atlanta Hartsfield Airport Hotel Atlanta, GA 1. Call to Order. The meeting was
More informationSACRAMENTO FIRE DEPARTMENT FIRE PREVENTION DIVISION FIRE DEPARTMENT DEVELOPMENT SERVICES UNIT CONTRATOR INFORMATION PACKET
SACRAMENTO FIRE DEPARTMENT FIRE PREVENTION DIVISION FIRE DEPARTMENT DEVELOPMENT SERVICES UNIT CONTRATOR INFORMATION PACKET 1 SACRAMENTO FIRE DEPARTMENT FIRE PREVENTION DIVISION FIRE DEPARTMENT DEVELOPMENT
More informationRecommended Amendments to the 2015 International Existing Building Code North Central Texas Council of Governments Region
Recommended Amendments to the 2015 International Existing Building Code North Central Texas Council of Governments Region The following sections, paragraphs, and sentences of the 2015 International Existing
More information2018 IFC Update. Based on the 2018 International Fire Code, (IFC ) Goal. Objectives. Content
Based on the 2018 International Fire Code, (IFC ) The International Fire Code (IFC ), establishes minimum regulations for fire safety. This handout will identify important changes in the IFC from 2015
More information9/23/ :20 AM. Second Revision No NFPA [ Section No ] Supplemental Information. Submitter Information Verification
of 4 9/23/2016 10:20 AM Second Revision No. 6501-NFPA 5000-2016 [ Section No. 17.2.2.2.4 ] 17.2.2.2.4* Classroom Door Locking to Prevent Unwanted Entry. Classroom doors shall be permitted to be locked
More informationNational Fire Protection Association. 1 Batterymarch Park, Quincy, MA Phone: Fax:
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org MEMORANDUM TO: FROM: Technical Committee on Residential Occupancies Kelly
More informationCTC Meeting #27 JUNE 17 18, 2013 NIST report on the Charleston sofa store fire
CTC Meeting #27 JUNE 17 18, 2013 NIST report on the Charleston sofa store fire The following 2013 Group B changes have been compiled for the above noted CTC Area of Study. Code changes with an (*) indicate
More informationCode Technology Committee Meeting #31 March 31-April 1, 2015 Care_WTC Recommendations/Elevators
Code Technology Committee Meeting #31 March 31-April 1, 2015 Care_WTC Recommendations/Elevators This list is a compilation of 2015 Cycle code changes related to the above CTC Area of Study. E 42-15 Page
More informationMEETING AGENDA High Rise Building Safety Advisory Committee
MEETING AGENDA High Rise Building Safety Advisory Committee Renaissance Blackstone Chicago 636 South Michigan Avenue, Chicago, IL 60605 May 13-14, 2014 Chicago, IL 1. Call to Order. Call the meeting to
More informationLOCAL AMENDMENTS TO THE INTERNATIONAL FIRE CODE 2006 EDITION
CHAPTER 23.45 Sections LOCAL AMENDMENTS TO THE INTERNATIONAL FIRE CODE 2006 EDITION 23.45.100 Local amendments to the International Fire Code, 2006 Edition... 2 23.45.102.1 Construction and design provisions...
More informationCODE TECHNOLOGIES COMMITTEE NURSING CARE FACILITIES WORK GROUP APPROVED CODE CHANGE DRAFTS CODE GROUP B
CODE TECHNOLOGIES COMMITTEE NURSING CARE FACILITIES WORK GROUP APPROVED CODE CHANGE DRAFTS CODE GROUP B This report includes 3 code change proposal from the CTC Nursing Care Facilities Coordination committee
More informationCode Technologies Committee Report Fire Rated Glazing Group A changes: Fire rated glazing
Code Technologies Committee Report Rated Glazing Group A changes: There are 11 areas of study currently listed under CTC. 1. Balanced Protection 1.1. Vertical Opening 1.2. Roof Vents 2. Carbon Monoxide
More informationNational Fire Protection Association (NFPA) Fire Service Occupational Safety and Health Technical Committee Meeting. October 10 12, 2011 Baltimore, MD
National Fire Protection Association (NFPA) Fire Service Occupational Safety and Health Technical Committee Meeting October 10 12, 2011 Baltimore, MD Chairman Glenn Benarick called the meeting to order
More informationPre-First Draft Meeting Technical Committee on Wastewater Treatment Plants On line/conference Call November 20, PM EDT
Pre-First Draft Meeting Technical Committee on Wastewater Treatment Plants On line/conference Call vember 20, 2012 2-4 PM EDT (1-3 PM CT; 12-2 PM MT; 11-1 PM PT) 1. Welcome-Glenn McGinley, Committee Chair
More informationNational Fire Protection Association (NFPA) Fire Service Occupational Safety and Health Technical Committee Meeting March 14 15, 2012 San Diego, CA
National Fire Protection Association (NFPA) Fire Service Occupational Safety and Health Technical Committee Meeting March 14 15, 2012 San Diego, CA The NFPA 1521 Task Group and NFPA 1561 Task Group, established
More informationCode Technology Committee 2006/2007 Cycle Area of study Carbon monoxide alarms Public comments
Code Technology Committee 2006/2007 Cycle Area of study Carbon monoxide alarms Public comments The following are code changes for which the CTC has established a position and testified at the 2006 Code
More informationSignificant Changes to the 2012 IFC Semiconductor Fabrication Facilities. Scott Stookey Senior Technical Staff International Code Council, Austin TX
Significant Changes to the 2012 IFC Semiconductor Fabrication Facilities Scott Stookey Senior Technical Staff International Code Council, Austin TX Introduction This presentation reviews the significant
More informationFire Plan Review and Inspection Guidelines
Fire Plan Review and Inspection Guidelines 2009 Edition Mike Thrapp Fire Plan Review and Inspection Guidelines ISBN: 978-1-58001-881-4 Cover Design: Publications Manager: Manager of Development: Illustrator/Interior
More informationMinutes. NFPA Technical Committee on Fire Code. NFPA First Draft Meeting
Minutes NFPA Technical Committee on Fire Code NFPA 1-2018 First Draft Meeting October 8-9, 2015 Doubletree by Hilton Hotel San Diego Downtown San Diego, California 1. Call to order. Chair Jeffrey Collins
More informationNational Fire Protection Association. 1 Batterymarch Park, Quincy, MA Phone: Fax:
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org M E M O R A N D U M TO: FROM: NFPA Technical Committee on Mercantile and
More informationPROPOSED CODE CHANGES FOR REVIEW BY THE FIRE CODE ACTION COMMITTEE
PROPOSED CODE CHANGES FOR REVIEW BY THE FIRE CODE ACTION COMMITTEE Developed by the Midwestern Regional Work Group CONTENTS Item 15 Limited area sprinkler systems Item 20 Scope of IFC Ch 7 Item 21 Fire-resistance-rated
More informationBuilding Code Basics: Fire. Based on the 2012 International Fire Code
Building Code Basics: Fire Based on the 2012 International Fire Code Building Code Basics: Fire, Based on the 2012 International Fire Code Kevin H. Scott International Code Council Executive Vice President
More informationRancho Cucamonga Fire Protection District Prevention Bureau Standard
Rancho Cucamonga Fire Protection District Prevention Bureau Standard Title: Fire Alarm and Monitoring Systems Standard # 9-3 Effective: May 2002 Number of Pages: 7 Updated: December 2016 for consistency
More informationInternational Code Council
Page 1 of 7 International Code Council ICC 300-2012 edition Committee Actions Report for Committee Actions taken at the March 9th, 2011 meeting The ICC Standard Development Committee for Bleacher Safety
More informationUNIFIED INTERPRETATION OF PROVISIONS OF IMO SAFETY, SECURITY, AND ENVIRONMENT-RELATED CONVENTIONS
E SUB-COMMITTEE ON SHIP SYSTEMS AND EQUIPMENT 5th session Agenda item 12 SSE 5/12/4 4 January 2018 Original: ENGLISH UNIFIED INTERPRETATION OF PROVISIONS OF IMO SAFETY, SECURITY, AND ENVIRONMENT-RELATED
More informationHealth Chapter ALABAMA STATE BOARD OF HEALTH ALABAMA DEPARTMENT OF PUBLIC HEALTH ADMINISTRATIVE CODE
Health Chapter 420-5-22 ALABAMA STATE BOARD OF HEALTH ALABAMA DEPARTMENT OF PUBLIC HEALTH ADMINISTRATIVE CODE CHAPTER 420-5-22 SUBMISSION OF PLANS AND SPECIFICATIONS FOR HEALTH CARE FACILITIES TABLE OF
More informationDelayed Action Closer. Mechanical self-closing device that incorporates an adjustable delay prior to the initiation of closing.
9/20/2016 2:27 PM Second Revision No. 5006-NFPA 101-2016 [ Section No. 3.3.56 ] 3.3.56 Delayed Action Closer. Self-closing device that incorporates a delay prior to the initiation of closing. Mechanical
More informationPublic Input No. 52-NFPA [ Section No [Excluding any Sub-Sections] ]
8 of 93 11/6/2015 7:41 AM Public Input No. 52-NFPA 30-2015 [ Section No. 21.2 [Excluding any Sub-Sections] ] For the purpose of this chapter, the term in this section shall have the definitions given.
More informationCCC 2018 GROUP A PROPOSED CHANGES TO THE I-CODES COLUMBUS COMMITTEE ACTION HEARINGS. April 15 23, 2018 Columbus Convention Center Columbus, Ohio
CCC 2018 GROUP A PROPOSED CHANGES TO THE I-CODES COLUMBUS COMMITTEE ACTION HEARINGS April 15 23, 2018 Columbus Convention Center Columbus, Ohio First Printing Publication Date: February 2018 Copyright
More informationNational Fire Protection Association. 1 Batterymarch Park, Quincy, MA Phone: Fax:
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org M E M O R A N D U M TO: FROM: NFPA Technical Committee on Mercantile and
More informationREPRESENTING. Honolulu Fire Dept., Rep. International Association of Fire Fighters. API/Petroleum Safety Consultants
NFPA Technical Committee on Fire Code (FCC-AAA) NFPA 1-2018 PRE-FIRST DRAFT MEETING MINUTES June 4-5, 2015 Hilton Orlando Lake Buena Vista Lake Buena Vista, Florida 1. Call to Order. The meeting was called
More informationMEMORANDUM. NFPA Technical Committee on Fire Code (FCC-AAA) Subject: NFPA 1 Proposed Tentative Interim Amendment (TIA) No.1045
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org MEMORANDUM To: From: NFPA Technical Committee on Fire Code (FCC-AAA) Gregory
More information2007/2008 PROPOSED CHANGES TO THE INTERNATIONAL FIRE CODE FIRE CODE COMMITTEE
2007/2008 PROPOSED CHANGES TO THE INTERNATIONAL FIRE CODE FIRE CODE COMMITTEE Rolland M. Crawford Chair Division Chief/Fire Marshal City of Loma Linda Loma Linda, CA John F. Mueller Vice Chair Acting State
More informationInternational Fire Code
Significant Changes to the International Fire Code 2015 Edition Significant Changes to the INTERNATIONAL FIRE CODE 2015 EDITION International Code Council icc Staff : Executive Vice President and Director
More informationFire Flow Requirements Standard
Fire Flow Requirements Standard Scope This standard documents the requirements for fire flow within the Fresno County Fire Protection District (FCFPD). This includes areas that have a water purveyor who
More informationANSI/NETA Standards Update
Specifications and Standards Activity ANSI/NETA Standards Update NOW AVAILABALE!!!! NETA Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems The NETA Acceptance Testing
More informationBeehive Chapter of ICC. Annual Spring Training April 23 thru April 25, 2018
Beehive Chapter of ICC Annual Spring Training April 23 thru April 25, 2018 Utah Valley Convention Center 220 W. Center Street Provo, Utah 84601 The Beehive Chapter is an approved ICC Preferred Provider.
More informationTable EXIT ACCESS TRAVEL DISTANCE a OCCUPANCY SYSTEM SYSTEM. A, E, F-1, I-1, M, b,d R, S-1. B c. F-2, S-2, U c
Table 1015.1 EXIT ACCESS TRAVEL DISTANCE a WITHOUT SPRINKLER WITH SPRINKLER OCCUPANCY SYSTEM SYSTEM A, E, F-1, I-1, M, 200 250 b,d R, S-1 B 200 300 c F-2, S-2, U 300 400 c No Change to Other Entries in
More information9/20/2016 2:53 PM. Second Revision No NFPA [ Section No ] Supplemental Information. Submitter Information Verification
Second Revision No. 2011-NFPA 101-2016 [ Section No. 14.2.2.2.4 ] 14.2.2.2.4* Classroom Door Locking to Prevent Unwanted Entry. Classroom doors shall be permitted to be locked to prevent unwanted entry
More informationFire Prevention Coffee Break Training. May 2017
Fire Prevention Coffee Break Training May 2017 Agenda Introduction Submittals - Phelan Changes to NFPA 13 - Phelan Questions and Answers Open Forum Please welcome our S ummer Intern Charlie Poppe Small
More informationSecond Revision No. 104-NFPA [ Section No ] Submitter Information Verification. Committee Statement
of 1 9/22/2014 1:38 PM Second Revision No. 104-NFPA 72-2014 [ Section No. 3.3.3 ] 3.3.3 Accessible, Readily (Readily Accessible). Capable of being reached quickly for operation, renewal, or inspections
More informationFire & Life Safety Section International Association of Fire Chiefs. Group A Code Change Cycle Report
Fire & Life Safety Section International Association of Fire Chiefs Group A Code Change Cycle Report March 1, 2016 Initial s by IAFC Fire & Life Safety Section SUMMARY took a position on 117 Public (15
More informationTABLE OF CONTENTS Part 6 Legal Basis for Fire Safety Planning... 2
TABLE OF CONTENTS Part 6 Legal Basis for Fire Safety Planning... 2 6.1] GENERAL... 2 6.2] EXCERPTS FROM 2012 BC FIRE CODE PART 2 BUILDING AND OCCUPANT FIRE SAFETY... 3 6.3] EXCERPTS FROM 2012 BC FIRE CODE
More informationIMO UNIFIED INTERPRETATIONS TO SOLAS CHAPTER II-2 AND RELATED FIRE TEST PROCEDURES
INTERNATIONAL MARITIME ORGANIZATION E IMO SUB-COMMITTEE ON FIRE PROTECTION 46th session Agenda item 5 FP 46/5 30 November 2001 Original: ENGLISH UNIFIED INTERPRETATIONS TO SOLAS CHAPTER II-2 AND RELATED
More informationFIRE-FLOW REQUIREMENTS FOR BUILDINGS Based on the 2012 Edition of the International Fire Code
FIRE-FLOW REQUIREMENTS FOR BUILDINGS Based on the 2012 Edition of the International Fire Code One of the basic essentials needed to control and extinguish a structure fire is an adequate water supply.
More informationAmerican Fire Sprinkler Association. An Introduction to the IBC and IFC
American Fire Sprinkler Association Presents An Introduction to the IBC and IFC October 13, 2005 Speaker Roland Huggins, P.E. Vice President of Engineering and Technical Services American Fire Sprinkler
More informationMinutes of the Pre-ROP Meeting of the T/C on Protected Premises Signaling September 22-23, 2010 Indianapolis, IN
Minutes of the Pre-ROP Meeting of the T/C on Protected Premises Signaling September 22-23, 2010 Indianapolis, IN Mr. Merton Bunker, Committee Chair, called the meeting to order at 8:05 on Wednesday September
More informationMULTI-PHASED FIRE ALARM AND MASS NOTIFICATION SYSTEM UPGRADES: The Authority Having Jurisdiction (AHJ) and Proper Planning
CAMPUS FIRE SAFETY CODE TALK Campus Fire Safety e-newzone MULTI-PHASED FIRE ALARM AND MASS NOTIFICATION SYSTEM UPGRADES: The Authority Having Jurisdiction (AHJ) and Proper Planning By Ernesto Vega Janica,
More informationUnderstanding, Applying and Enforcing NFPA 25. James D. Lake NFSA Director of Training
Understanding, Applying and Enforcing NFPA 25 James D. Lake NFSA Director of Training When Sprinklers Are Ineffective Water did not reach fire 8% 7% 7% 5% 44% Not enough water released Damaged Component
More informationAdobe Connect - Invitation to NFPA 385 Second Draft Web Conference
Matthews, Diane Subject: Location: Start: End: Show Time As: Recurrence: Meeting Status: Organizer: Required Attendees: Adobe Connect - Invitation to NFPA 385 Second Draft Web Conference http://nfpa.adobeconnect.com/rpbmeet/
More informationCommerc al K tchen Hood
Commerc al K tchen Hood Application Guide 2009 Edition Larr Simpson Commercial Kitchen Hood Application Guide, 2009 Edition ISBN: 978-1-58001-959-0 Cover Art Design: Project Manager: Publications Manager:
More informationCALIFORNIA DEPARTMENT of FORESTRY and FIRE PROTECTION OFFICE OF THE STATE FIRE MARSHAL UL 300
CALIFORNIA DEPARTMENT of FORESTRY and FIRE PROTECTION OFFICE OF THE STATE FIRE MARSHAL UL 300 FREQUENTLY ASKED QUESTIONS CONCERNING COMMERCIAL COOKING PROTECTION Published by FIRE ENGINEERING DIVISION
More informationRonny J. Coleman President
On behalf of the IRC Fire Sprinkler Coalition and the more than 100 organizations who support our mission, I would like to thank you for supporting residential fire sprinklers at the ICC Hearing in Baltimore.
More informationFIRE PREVENTION CODE
164.01 Purpose 164.03 Amendments to Fire Prevention Code 164.02 Adoption of Fire Prevention Code 164.04 Board of Appeals 164.01 PURPOSE. The purpose of this chapter is to prescribe regulations governing
More informationUNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY
Revision No.: 11 Page 1 of 12 I. PURPOSE This procedure establishes a tool to help maintain a safe environment for all patients, visitors and staff by evaluating the loss of a life safety feature during
More information2015 International Code Adoption. And 2014 Electrical Code
2015 International Code Adoption And 2014 Electrical Code Why adopt building codes? Codes establish a minimum standard for life, health and safety for buildings in City of Garland. Intended to provided
More informationFire Flow Requirements Standard
Fire Flow Requirements Standard Scope This standard documents the requirements for fire flow within the Fresno County Fire Protection District (FCFPD). This includes areas that have a water purveyor who
More informationINTERNATIONAL FIRE CODE
SIGNIFICANT CHANGES TO THE INTERNATIONAL FIRE CODE 2018 EDITION SIGNIFICANT CHANGES TO THE INTERNATIONAL FIRE CODE 2018 EDITION Kevin H. Scott, Author Additional contributions by Robert A. Neale ISBN:
More information1. The meeting was called to order by Chair James Lathrop at 8:00 AM (CDT) on Wednesday, August 26, 2015.
MINUTES NFPA Technical Committee on Residential Occupancies NFPA 101 and NFPA 5000 First Draft Meeting Wednesday, August 26, 2015 InterContinental Milwaukee Milwaukee, WI 1. The meeting was called to order
More informationFire Protection System Contractors and Systems. Submission of the Application for a Water-Based Fire Protection Inspector Permit
NOTICE OF PROPOSED RULE DEPARTMENT OF FINANCIAL SERVICES DIVISION OF STATE FIRE MARSHAL RULE CHAPTER: RULE CHAPTER TITLE: 69A-46, F.A.C. Fire Protection System Contractors and Systems RULE: RULE TITLE:
More informationSOMERSWORTH CODE FIRE PREVENTION AND LIFE SAFETY CHAPTER 21
SOMERSWORTH CODE FIRE PREVENTION AND LIFE SAFETY CHAPTER 21 ARTICLE I FIRE PREVENTION CODE 21-1. Statutory authority 21-2. Adoption of standards 21-3. Definitions 21-4. Exceptions to Fire Prevention Code
More informationNFPA Talking Points on NFPA 1 Fire Code update to the 2015 Edition:
NFPA Talking Points on NFPA 1 Fire Code update to the 2015 Edition: The legislative study committee established by HB 427 report dated November 1, 2016 reads Members support uniformity for the most fundamental
More informationMEMORANDUM. Technical Committee on Mercantile and Business Occupancies. NFPA 101 Second Draft Technical Committee FINAL Ballot Results (A2017)
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org MEMORANDUM TO: FROM: Technical Committee on Mercantile and Business Occupancies
More informationREPORT OF THE NFPA MOTIONS COMMITTEE* ON FALL 2013 REVISION CYCLE STANDARDS
REPORT OF THE NFPA MOTIONS COMMITTEE* ON FALL 2013 REVISION CYCLE STANDARDS I. Introduction. This is the Motions Committee Report on Standards in the Fall 2013 Revision Cycle. The report identifies Certified
More informationhome smoke candles alarms electrical burns smoking medical oxygen cooking FIREFIGHTING MATCHES & LIGHTERS SPRINKLERS
FIREFIGHTING home smoke alarms REGULATIONS GOVERNING THE NFPA EDUCATIONAL MESSAGES DESK REFERENCE FOR THE FIRE SERVICE AND FIRE AND LIFE SAFETY EDUCATORS MATCHES & LIGHTERS medical oxygen cooking FIRE
More informationFire Department Fees.
Fire Department Fees. North Liberty Fire Department 25 W. Cherry St., North Liberty, IA Phone: (319) 626-5717 Fax: (319) 626-3238 Fire Department Fee Schedule Council Members, I just wanted to take a moment
More informationSTATE FIRE MARSHAL S REQUIRED FIRE PROTECTION SYSTEMS NARRATIVE REPORT
STATE FIRE MARSHAL S REQUIRED FIRE PROTECTION SYSTEMS NARRATIVE REPORT The interaction of fire protection systems can be extremely complex. The detection of a fire in a building by an automatic device
More informationChanges in NFPA
Changes in NFPA 72-2002 2002 Oregon Fire Code Committee November 25, 2003 Michael B. Baker, SET Automatic Fire Alarm Association MikeBaker@afaa.org 2003 Michael B. Baker 1 Table of Contents 1. Administration
More informationMinimum Standards for Engineers Practicing Fire Protection Engineering in the State of Oklahoma September 14, 2016
1. Introduction The intent of this document is to establish minimum standards for the practice of fire protection engineering within the State of Oklahoma as conducted by licensed professional engineers.
More informationSC # /16/17/18/19/23/24 D#03-24
SC #03-7-15/16/17/18/19/23/24 D#03-24 Casey C. Grant, P.E. Secretary, Standards Council 26 July 2003 To: Interested Parties Subject: Standards Council Decision (Final): D#03-24 Standards Council Agenda
More informationCorrelating Committee on Automatic Sprinklers
Correlating Committee on Automatic Sprinklers First Draft Correlating Committee Meeting December 6, 2016 MEETING MINUTES 1. Call to Order. CC Chair Ken Linder called the meeting to order at 8AM. 2. Self-Introductions
More informationThis guide is intended to provide assistance in the application of the fire code in all areas served by Tualatin Valley Fire & Rescue.
This guide is intended to provide assistance in the application of the fire code in all areas served by Tualatin Valley Fire & Rescue. North Operating Center 11945 SW 70 th Avenue Tigard, OR 97223 Phone:
More informationPublic Input No. 1-NFPA [ Global Input ] Additional Proposed Changes. Statement of Problem and Substantiation for Public Input
of 280 2/6/2015 12:06 PM Public Input No. 1-NFPA 58-2013 [ Global Input ] NOTE: This public input originates from Tentative Interim Amendment 58-14-1 (TIA 1079) issued by the Standards Council on August
More informationNZS 4517:2010. New Zealand Standard. Fire sprinkler systems for houses. Superseding NZS 4517:2002 NZS 4517:2010
New Zealand Standard Fire sprinkler systems for houses Superseding NZS 4517:2002 NZS 4517:2010 NZS 4517:2010 COMMITTEE REPRESENTATION This Standard was prepared under the supervision of the P 4517 Committee,
More informationREQUEST FOR QUALIFICATIONS
REQUEST FOR QUALIFICATIONS for the City of Lake Forest Issue Date: September 23, 2015 Bid Due Date: October 19, 2015 The City of Lake Forest 800 N. Field Drive Lake Forest, Illinois 60045 THE CITY OF LAKE
More informationNGV MAINTENANCE FACILITIES Code Related Modifications For NGVs In Existing Maintenance Facilities
DELAWARE VALLEY REGIONAL PLANNING COMMISSION NGV MAINTENANCE FACILITIES Code Related Modifications For NGVs In Existing Maintenance Facilities Steve Arnold, P.E. - Engineering Vice President Brian Bogar,
More informationCAN/ULC-S1001, INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION & LIFE SAFETY SYSTEMS Simon Crosby, LEL, CET, CFPS October 21, 2015
CAN/ULC-S1001, INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION & LIFE SAFETY SYSTEMS Simon Crosby, LEL, CET, CFPS October 21, 2015 Fire Commissioning in Canadian Codes and Standards BACKGROUND Why Commissioning?
More informationSurviving the Survivable Cable Crunch
Fire Alarm Notebook by Dean K. Wilson. P.E. Page 1 Surviving the Survivable Cable Crunch by Dean K. Wilson, P.E. Question: I am a fire inspector in a mid-western city. We have recently received preliminary
More informationBold items are particular to the City of Euless
EULESS FIRE DEPARTMENT FIRE MARSHAL S OFFICE INFORMATION LINE: Revised 8/2004 Fire Chief Lee Koontz Fire Marshal Paul Smith EFD-FMO 3-1 2003 International Fire & Building Code as Amended NFPA Standards
More informationICC CODE TECHNOLOGY COMMITTEE Area of Study Labeling of Fire Rated Glazing
ICC CODE TECHNOLOGY COMMITTEE Area of Study Labeling of Fire Rated Glazing Code Change History for 2006 IBC Section 75 Opening Protectives October, 2008 2006 IBC 200 IBC 2000 IBC APPLICABLE CODE CHANGES
More informationNarrative Reports As Regulated by 780 CMR, Section 903.0
EXHIBIT 20 Narrative Reports As Regulated by 780 CMR, Section 903.0 903.1.1 - FIRE PROTECTION CONSTRUCTION DOCUMENTS a. Basis (methodology) of design for the protection of the occupancy and hazard for
More informationNational Fire Protection Association. 1 Batterymarch Park, Quincy, MA Phone: Fax:
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org M E M O R A N D U M TO: FROM: NFPA Technical Committee on Mercantile and
More informationFire Protection System Contractors and Systems. Submission of the Application for a Water-Based Fire Protection Inspector
NOTICE OF PROPOSED RULE DEVELOPMENT DEPARTMENT OF FINANCIAL SERVICES DIVISION OF STATE FIRE MARSHAL RULE CHAPTER: 69A-46, F.A.C. RULE: 69A-46.0165, F.A.C. RULE CHAPTER TITLE: Fire Protection System Contractors
More informationAGENDA TECHNICAL COMMITTEE ON CARBON MONOXIDE DETECTION OCTOBER 7, 2010 TELECONFERENCE (10:00 A.M. ET)
AGENDA TECHNICAL COMMITTEE ON CARBON MONOXIDE DETECTION OCTOBER 7, 2010 TELECONFERENCE (10:00 A.M. ET) Item No. Subject 10-10-1 Call to Order (10:00 A.M.) 10-10-2 Roll Call 10-10-3 Staff Remarks 10-10-4
More informationFirst Revision No NFPA [ Global Input ] Submitter Information Verification. Committee Statement
of 43 10/20/2015 4:02 PM First Revision No. 2035-NFPA 101-2015 [ Global Input ] To 14.3.4.4.1, add an item (4) to read: (4) Carbon monoxide detectors shall be installed centrally located within occupiable
More informationM E M O R A N D U M. NFPA 1 First Draft Technical Committee FINAL Ballot Results (A2017)
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org M E M O R A N D U M TO: FROM: Technical Committee on Fire Code Kelly Carey,
More informationIRC - BUILDING - ELECTRICAL - ELECTRICAL TAC
IRC - BUILDING - ELECTRICAL - ELECTRICAL TAC W A R N I N G Copyright Notice: This document has been reproduced solely for considering proposed changes to the Florida Building Code with the permission of
More informationItem Referenced and Amendments Building 1 Building 2 Analysis, Review and Remarks. Page 1 of 15
N/A N/A 2015 International Fire Code 2015 International Building Code Codes Jurisdictions for Fire and Building Codes Source of Information Building Fire Plumbing Mechanical Electrical Energy Code Accessibility
More information