1 Project Summary Request for Proposals Street Tree Planting and Tree Planting Site Preparation in the City of Pittsburgh Western Pennsylvania Conservancy Fall 2017 Tree Planting Season The Western Pennsylvania Conservancy (WPC) is seeking proposals from qualified firms to complete street tree plantings and street tree planting site preparation in the City of Pittsburgh for the fall 2017 tree planting season beginning in late October. The plantings are part of the TreeVitalize Pittsburgh tree planting project. TreeVitalize Pittsburgh is a joint project of WPC, Allegheny County, the City of Pittsburgh, the PA Department of Conservation and Natural Resources, and the non-profit Tree Pittsburgh. Working in partnership with community groups, volunteers, non-profits, and municipal agencies, TreeVitalize Pittsburgh has planted more than 28,000 trees in 72 Pittsburgh city neighborhoods, 52 Allegheny County Municipalities as well as all 9 Allegheny County Parks in order to improve the quality of life and the environment in the Pittsburgh region. With WPC as the managing partner, the program has developed a thorough tree planting methodology that engages thousands of volunteers and community residents, utilizes the expertise of local urban forestry professionals, procures local, top quality materials, and follows the latest and best urban and community forestry practices. WPC relies on contractors for completing high quality tree planting site preparation work well in advance of volunteer tree planting events throughout the fall and spring planting seasons. WPC holds all contractors accountable for timely corrections on any subpar work or damage to property. When undertaking work in the field on behalf of WPC, the contractor is responsible for upholding high professional standards and courtesy with the public. The majority of contracted work for the fall 2017 planting season will be street tree site preparation for trees that will be planted with WPC staff, partners, and volunteers. A small number of sites will include contracted tree plantings, following WPC s tree planting specifications. Bids from any qualified firm will be accepted by WPC for review. Firms may bid on the entirety of the fall 2017 work, but must bid on a minimum of 20 sites.
2 Scope of Work 40 New Standard Street Tree Pits: Cutting tree pits into concrete or brick sidewalks to the dimensions specified by WPC staff. The typical street tree pit will be 3x10. A street tree pit cut may not be smaller or larger than the specified dimensions unless otherwise indicated by WPC staff. Excavating the entirety of the tree pit to a depth of 24. The contractor is responsible for removing ANY material from the designated planting location including existing soil, concrete, rock, brick, roots, stumps up to 6 in diameter, or any other material. Backfilling pit level with the existing sidewalk with topsoil. Topsoil Installing retainers along any section of a street tree pit that contacts a brick sidewalk, typically using treated lumber. 48 Replacing Vacant Sites: Excavating the entirety of the existing tree pit to a depth of 24. The contractor is responsible for removing ANY material from the designated planting location including existing soil, concrete, rock, brick, roots, stumps up to 6 in diameter, or any other material. Backfilling pit level with the existing sidewalk with topsoil. Topsoil 59 Existing Tree Pit/Tree Lawn Expansion:
3 Partial concrete or brick sidewalk cutting to the dimensions specified by WPC staff. Typically 50% or less cutting and hardscape removal than required for a new standard tree pit. Excavating the entirety of the expanded tree pit to a depth of 24. The contractor is responsible for removing ANY material from the designated planting location including existing soil, concrete, rock, brick, roots, stumps up to 6 in diameter, or any other material. Backfilling pit level with the existing sidewalk with topsoil. Topsoil 93 Open Tree Planting Site: excavation of the site. Planting site locations will be provided to the contractor by the WPC Forester and will be marked by white paint and/or colored pin flags. Excavating a planting hole that measures 36 inches in diameter and 24 inches in depth. A planting hole may not be smaller or larger than this unless otherwise indicated by WPC staff. The contractor is responsible for removing ANY material from the designated planting location including existing soil, concrete, rock, brick, roots, stumps, or any other material. Backfilling pit level with the existing grade with a specified grade of topsoil. Topsoil specifications will be provided to the contractor by the WPC TreeVitalize Forester. A sample of the topsoil must be provided to WPC for work begins. 13 Tree Planting: Planting of a 2 inch caliper balled and burlapped tree in accordance to tree planting specifications provided by WPC staff. Each tree must be planted exactly as directed by these specifications and the specific tree species must be planted at each location. Installing a layer of undyed, hardwood mulch that is 2 inches deep over the entire 3 foot diameter planting area. No mulch containing softwood, cypress, dyes, rubber, gravel, or any other material or chemicals may be used. Coordinating delivery of all trees from Eisler Nursery, 1031 New Castle Rd, Prospect, PA
4 WPC will not be held accountable for any costs associated with utility conflicts. It is the responsibility of the contractor to utilize the PA One Call system to identify the location of utilities prior to excavation. If a utility company fails to properly identify the location of a utility within the designated time frame, the contractor can hold the utility company responsible for any costs associated with that failure. WPC staff will inspect all tree plantings and tree planting site preparation work and relay any corrections to the contractor. Corrections must be made within 3 business days after notification from WPC. Time Period This contract is for the fall 2017 planting season beginning October 19, 2017 and ending December 1, WPC may offer the contractor tree planting site preparation work for the spring 2018 tree planting season that begins in March Locations WPC staff will provide work locations, work order details, and work completion dates upon execution of the contract. Most work will occur within the City of Pittsburgh. Some planting sites will be located in Aspinwall and Brackenridge Boroughs and Harrison Township. Payment Schedule: Please provide unit costs in the format shown below. Work Specification Unit Cost New Standard Street Tree Pits (40 sites) Replacing Vacant Sites (48 sites) Existing Tree Pit/Tree Lawn Expansion (59 sites) Open Site Tree Plantings (93 sites) Street Tree Planting (13--Bid as a per-unit add-on to any of the above)
5 Proposal Submission In addition to the payment schedule table showing unit costs, please provide the following: Description of experience doing similar types of landscaping work Profiles of staff persons who will be conducting and overseeing the work, including relevant experience and skills Three references from previous clients Proposals must be submitted via to Jeffrey Bergman, WPC s Director of Community Forestry, at jbergman@paconserve.org by 4:00pm on September 13, Any questions regarding this RFP must be directed, in writing, to jbergman@paconserve.org. It is recommended that interested firms attend an informational pre-bid meeting at WPC on September 7, 2017 at 1:00pm. WPC is located at 800 Waterfront Drive, Pittsburgh, PA Please RSVP to jbergman@paconserve.org.
Western Pennsylvania Conservancy Clairton & Harrison Community Greening Assessment Projects Request for Proposals July 2018
Western Pennsylvania Conservancy Clairton & Harrison Community Greening Assessment Projects Request for Proposals July 2018 Proposal Information The Western Pennsylvania Conservancy (WPC) is seeking proposals
More informationDIVISION 40 PUMP STATION SITE WORK AND LANDSCAPING
DIVISION 40 PUMP STATION SITE WORK AND LANDSCAPING 40.01 SCOPE: The contractor shall furnish all labor, materials, equipment, and supplies; and shall perform all work necessary for the installation of
More informationXeriscape Rebate Program Manual
Xeriscape Rebate Program Manual Program Purpose & Goals Introducing the community to xeriscape Create attractive, lower-maintenance yards that will save water and withstand drought Incentivize the conversion
More informationSECTION PLANTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 329000 PLANTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Special Conditions and Division 01 Specification Sections, apply
More information2015 Community Garden Sustainability Fund
2015 Community Garden Sustainability Fund Background Information A partnership of Grow Pittsburgh and the Western Pennsylvania Conservancy, the Community Garden Sustainability Fund provides material and
More informationRequest for Qualifications For Administration of the 2016 Summer Sprout Program
Page 1 of 6 Request for Qualifications For Administration of the 2016 Summer Sprout Program Requested by: City of Cleveland, Department of Community Development 601 Lakeside Avenue, room 320 Cleveland,
More informationSECTION 605 PLANTING
SECTION 605 PLANTING I. GENERAL 1.1. DESCRIPTION OF WORK The Contractor shall furnish all labor, supervision, material (except as herein provided), tools, equipment, supplies, and services; and, shall
More informationREQUEST FOR BIDS LANDSCAPING SERVICES HAYMARKET, VIRGINIA
REQUEST FOR BIDS LANDSCAPING SERVICES HAYMARKET, VIRGINIA The Town of Haymarket, Virginia is requesting bids (RFBs) from professional landscaping companies which wish to be considered for providing landscaping
More informationValley Line LRT. Project Update & Citizen Working Groups Overview Public At Large Recruitment Meeting Citizen Working Group A Downtown
Valley Line LRT Project Update & Citizen Working Groups Overview Public At Large Recruitment Meeting Citizen Working Group A Downtown Agenda Welcome & meeting purpose Project overview & status update Citizen
More informationCommunity Garden Sustainability Fund - Frequently Asked Questions
Community Garden Sustainability Fund - Frequently Asked Questions Updated August 2017 1. What is the Community Garden Sustainability Fund (CGSF)? The CGSF is a project of the Western Pennsylvania Conservancy
More informationOVERALL LANDSCAPE PLAN
OVERALL LANDSCAPE PLAN : LIC. NO: SM RECORD COPY BY: L.0 OVERALL LANDSCAPE PLAN Scale: " = 40'-0" 0 40' 80' Scale: " = 40' L.0 L2.0 TREE PLANTING PLAN Scale: " = 40'-0" 0 Scale: " = 40' 40' wsbeng.com
More informationDIVISION 32 EXTERIOR IMPROVEMENTS LANDSCAPING TREES
PART 1 - GENERAL 1.01 SCOPE A. Work covered by this section includes all of the planning, compliance, design, installation, and warranty elements for new landscaping using trees. Contractor shall furnish
More informationCITY OF ALPHARETTA, GEORGIA LANDSCAPE STANDARDS INDEX
CITY OF ALPHARETTA, GEORGIA LANDSCAPE STANDARDS INDEX L-1 TREE PLANTING (TYPICAL SECTION) L-2 TREE ANCHORING - TYPE A (FOR TREES LARGER THAN 2 INCHES CALIPER) L-3 TREE ANCHORING - TYPE B (FOR TREES UP
More informationCITY OF VISALIA. Parks & Urban Forestry Guidelines. Street Tree Standards For Residential And Commercal Development
CITY OF VISALIA Parks & Urban Forestry Guidelines Street Tree Standards For Residential And Commercal Development City of Visalia Street Tree Development Standards 2 These guidelines have been established
More informationSECTION TREES, PLANTS AND GROUND COVERS
SECTION 02950 TREES, PLANTS AND GROUND COVERS PART 1 - GENERAL 1.1 SUMMARY: A. Section Includes: 1. Trees. 2. Plants and shrubs. 3. Ground covers. 4. Non-plant materials required to complete installation
More informationCITY OF EAU CLAIRE, WISCONSIN REQUEST FOR PROPOSALS
CITY OF EAU CLAIRE, WISCONSIN REQUEST FOR PROPOSALS Commercial Development Opportunity 617 South Barstow Street Parcel 02-0071 The City of Eau Claire is seeking proposals for the commercial development
More informationMEADOWVIEW HOMEOWNERS ASSOCIATION
MEADOWVIEW HOMEOWNERS ASSOCIATION November 2, 2016 Mr. Justin V. Yaich, Township Manager West Bradford Township 1385 Campus Drive Downingtown, PA 19335 RE: Meadowview Development Home Owner s Association
More informationPROTECTIVE MEASURES FOR TREES DURING CONSTRUCTION
PROTECTIVE MEASURES FOR TREES DURING CONSTRUCTION NO CONSTRUCTION OR EXCAVATION IS TO OCCUR ON LOTS THAT REQUIRE TREE PRESERVATION UNTIL PROPER APPROVALS HAVE BEEN GIVEN BY A CITY ARBORIST 1. When trees
More informationSmall Town Sustainable Stormwater Solutions
Small Town Sustainable Stormwater Solutions Kathryn Hamilton, RLA, ASLA Westmoreland Conservation District PA/DE ASLA Annual Meeting April 8-9, 8 2011 Urban, Industrial, Residential, Agricultural Flooding,
More informationDIVISION II PLANTING SECTION 02950
Subdivision Requirements Manual Page 1 of 9 PART I - GENERAL 1.1 Related Work.1 Topsoil and Finish Grade : Section 02212.2 Seeding : Section 02933.3 Hydraulic Seeding : Section 02934.4 Sodding : Section
More informationConstruction Specification for Planting
Engineering and Construction Services Division Standard Specifications for Road Works TS 5.30 April 2014 for Planting Table of Contents TS 5.30.01 SCOPE... 3 TS 5.30.02 REFERENCES... 3 TS 5.30.03 DEFINITIONS
More informationApplication for 2015 Garden Program. The!Allegheny!Grows!Community!Garden!Program! !Application!Timeline! ! Tuesday,!August!26!!application!released!
TheAlleghenyGrowsCommunityGardenProgram ApplicationTimeline Tuesday,August26 applicationreleased Saturday,September6,10:30AM applicationinfosession Thursday,September11,6:00PMBapplicationinfosession Friday,September26,5:00PM
More informationGrand River Ravines Georgetown Township
Grand River Ravines Georgetown Township Project Description: The Grand River Ravines County Park property is composed of the 68-acre former Fillmore at the Bend Open Space purchased in 1999 and two more
More informationSECTION PLANTS. A. Includes But Not Limited To: 1. Furnish and install landscaping plants as described in Contract Documents.
SECTION 32 9300 PLANTS PART 1 - GENERAL 1.1 SUMMARY A. Includes But Not Limited To: 1. Furnish and install landscaping plants as described in Contract Documents. B. Related Sections: 1. Section 32 9001:
More informationLANDSCAPE GUIDELINES. Submitted by the Landscape Committee of The Village Townhomeowners Association
LANDSCAPE GUIDELINES Submitted by the Landscape Committee of The Village Townhomeowners Association Approved by the THOA Board of Directors April 2015 THE VILLAGE TOWNHOMEOWNERS ASSOCIATION BRADFORD WOODS,
More informationHALIFAX REGIONAL MUNICIPALITY
[PROJECT NAME] PLANTING OF TREES, SHRUBS PART 1 - GENERAL 1.1 Work Included 1.2 Related Sections 1.3 Reference Standards 1.4 Quality Control 1.5 Delivery, Storage and Protection 1.6 Samples 1.7 Warranty
More informationFHWA 534_J031. TEA-5A01(833) EN , P101,M501 See Tabulation Below for Section Numbers
FHWA 534_J31 TEA-5A1(833), P1,M51 See Tabulation Below for Section Numbers ALL CONSTRUCTION IS TO BE PERFORMED WITHIN EXISTING RIGHT OF WAY STP-5A1(611) M51 TEA-5A1(833) RECOMMENDED FOR CONSTRUCTION 12/28/216
More informationArchaeological evaluation at Willowdene, Chelmsford Road, Felsted, Essex
Archaeological evaluation at Willowdene, Chelmsford Road, Felsted, Essex August 2013 report prepared by Ben Holloway on behalf of Mr Anthony McGurren Planning reference: UTT/13/0235 CAT project ref.: 13/07g
More informationNOTICE INVITING TENDER
NOTICE INVITING TENDER Ref No.: SCOPEMINAR/MMO/18-19/183 Dated :- 06.12.2018 1. Online e-tenders are invited by Dy.General Manager, SCOPE on behalf of Constituents of SCOPE MINAR, Laxmi Nagar Delhi- 110092
More informationContact Phone Number: (609) Fax: (609)
Quote Name: Landscaping Description: SEE BELOW FOR FURTHER INFORMATION Township Contact: Andy Baran Contact Phone Number: (609) 361-6672 Fax: (609) 361-7624 Quote Number: Q16-21 Posted Date: April 4, 2016
More informationPresentation Title. Subtitle (optional) Wastewater Treatment Operations. O&M Contract Procurement. Vancouver City Council Workshop/Public Hearing
Wastewater Treatment Operations Presentation Title O&M Contract Procurement Subtitle (optional) Date July 20, 2015 Vancouver City Council Workshop/Public Hearing Brian Carlson, Public Works Director Staff,
More informationEXTERIOR PLANTS
c. Fertilize immediately prior to sodding or immediately after the sodding operation at a rate of.5 pounds of nitrogen per 1000 square feet. d. Work is to be done at typically accepted sodding times in
More information2-B-18-UR. Revised: 3/27/2018
Revised: 3/27/2018 Revised: 3/27/2018 GI FOR KIDS A MEDICAL OFFICE BLDG. 0000 BOARDWALK BLVD. KNOXVILLE, TENNESSEE CONSTRUCTION PRELIMINARY - NOT FOR Landscape Plan Target Publix Town Center Boulevard
More informationX X W W W W W W W W W W W W UG UG OHE OHE OHE OHE OHE OHE OHE FO UGE FO FO UGE UGE FO FO FO FO FO FO FO UGE UGE UGE UGE UGE UGE OHE OHE OHE OHE OHE OHE OHE OHE OHE OHE OHE OHE OHE OHE OHE OHE EXISTING
More information7301 SCOPE. Furnish materials, labor and equipment necessary to install landscaping as specified and as indicated on the plans.
SECTION 7300 LANDSCAPING 7301 SCOPE. Furnish materials, labor and equipment necessary to install landscaping as specified and as indicated on the plans. 7302 QUALITY ASSURANCE. A. Qualifications of Personnel.
More informationDARTMOUTH COLLEGE DESIGN March 15, 2003 & CONSTRUCTION GUIDELINES
PART 1 DESIGN DIRECTIVES 1.1 GENERAL SECTION 02951 PLANTING DETAILS A. This section consists of AutoCad drawings depicting typical landscape details governing the installation of plant materials on the
More informationBrewer Park Community Garden Constitution
1 Brewer Park Community Garden Constitution I. NAME AND PURPOSE OF THE ORGANIZATION 1. Name The organization shall be known as Brewer Park Community Garden. 2. Mission Statement The Brewer Park Community
More informationSECTION 808 PLANTING TREES, SHRUBS AND OTHER PLANTS
SECTION 808 PLANTING TREES, SHRUBS AND OTHER PLANTS 808.1 Description. This work shall consist of furnishing and planting material in the locations designated on the plans or established by the engineer.
More informationEast Midtown Greenway East 53 rd 61 st Street. Community Board 8 Project Introduction November 16, 2017
East Midtown Greenway East 53 rd 61 st Street Community Board 8 Project Introduction November 16, 2017 Agenda Overview - Development of the East Midtown Waterfront Esplanade Current East Midtown Greenway
More informationCorridor Management Committee. September 29, 2017
Corridor Management Committee September 29, 2017 1 Today s Topics Chair s Update Proposed Corridor Protection Wall Aesthetic Design Overview Public Outreach Environmental Review Civil Construction Update
More informationSouth of Eastern Strategic Direction Status Update
STAFF REPORT ACTION REQUIRED South of Eastern Strategic Direction Status Update Date: July 10, 2014 To: From: Planning and Growth Management Committee Chief Planner and Executive Director, City Planning
More informationA. Contractor shall provide product data for each type of product indicated.
31 13 00 SELECTIVE TREE AND SHRUB REMOVAL AND TRIMMING SECTION 1 GENERAL 1.1 SUMMARY A. This section includes general protection and pruning of existing trees and plants that are affected by execution
More informationBRINGING ORDER TO THE TECHNICAL DYSFUNCTION WITHIN THE URBAN FOREST 1
Journal of Arboriculture 18(2): March 1992 85 BRINGING ORDER TO THE TECHNICAL DYSFUNCTION WITHIN THE URBAN FOREST 1 by James Urban In order to increase the success rate of trees planted in the urban environment,
More informationCOUNCIL POLICY. 1. Removals. a) Dead or Hazardous Trees
COUNCIL POLICY SUBJECT: BOULEVARD TREE POLICY DATE: MARCH 14, 1988 REFERENCE: 88/CW Revised: June 27/88, Jan. 2/90, Jan. 27/92, Jan. 4/93, March 15/93, Jan. 17/94 1. Removals a) Dead or Hazardous Trees
More informationMilpitas College Extension Milpitas Dry Landscape
SAN JOSÉ / EVERGREEN COMMUNITY COLLEGE DISTRICT Milpitas College Extension Milpitas Dry Landscape PROJECT MANUAL VOLUME II TABLE OF CONTENTS DIVISION 02 through 30 Not Used DIVISION 31 - EARTHWORK Document
More informationTown of Fuquay-Varina
170 LANDSCAPING 170.01 GENERAL 170.01.01 Street trees shall be provided in accordance with the Land Development Ordinance for site plans and subdivisions 170.01.02 Street trees, landscape areas, landscape
More informationHighway & Bridge Capabilities
Highway & Bridge Capabilities Part of a diversified family of solutions www.jmt.com An Employee Owned Company I-95/I-295/I-495 Interchange, Woodrow Wilson Memorial Bridge, Prince George s County, MD Our
More informationTerwillegar Community Garden
The vision of the Program is: To tend to an enduring and evolving, environmentally conscious and sustainable community garden; endeavoring to cultivate comradery and extend enriching and educational experiences
More informationGATEWAY BUILDING ELEVATOR AND ESCALATOR SERVICES
29 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro.net SYSTEM SAFETY AND OPERATIONS COMMITTEE JANUARY 16, 2014 SUBJECT: ACTION: GATEWAY BUILDING ELEVATOR AND ESCALATOR SERVICES APPROVE
More informationSewanee Village + Request for Builder/Developer Proposals
Sewanee Village + Request for Builder/Developer Proposals Contact: Frank X. Gladu Special Assistant to the Vice Chancellor University of the South 735 University Ave Version 3 Sewanee TN 37383 Released:
More informationREQUEST FOR QUALIFICATIONS
REQUEST FOR QUALIFICATIONS for the City of Lake Forest Issue Date: September 23, 2015 Bid Due Date: October 19, 2015 The City of Lake Forest 800 N. Field Drive Lake Forest, Illinois 60045 THE CITY OF LAKE
More informationPLANT MATERIAL AND PLANTING. C. Maintaining and replacing plants for completed planting work.
PART 1 - GENERAL PLANT MATERIAL AND PLANTING 1.01 SECTION INCLUDES A. Plant Material and Planting B. Tree Drainage Wells C. Warranty for Plant Material 1.02 DESCRIPTION OF WORK A. Furnishing and installing
More informationPennDOT Public Meeting. S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project
PennDOT Public Meeting S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project Mt Lebanon Township, Allegheny County Mt Lebanon Township Municipal Building November 6, 2014 1 Project
More informationExhibit II - Expanded Scope of Work. Xeriscaping / Rain Water Harvesting Sustainability Program
Exhibit II - Expanded Scope of Work Xeriscaping / Rain Water Harvesting Sustainability Program National Guard Armory, Located at 308 North Fiske Boulevard Cocoa, FL 32922 PART 1 GENERAL 1.01 BACKGROUND
More informationRFP REQUEST FOR PROPOSALS CITY OF PORTSMOUTH, NH. DESIGN ENGINEERING SERVICES North Mill Pond Trail and Greenway
RFP 61-18 REQUEST FOR PROPOSALS CITY OF PORTSMOUTH, NH DESIGN ENGINEERING SERVICES North Mill Pond Trail and Greenway Sealed Requests for Proposals, plainly marked RFP 61-18 Design Engineering Services
More informationSpecimen trees are those that are either of a larger grade than normally planted or have been specified as such by the Engineer.
Authorised by : Parks & Gardens Manager Section 5 Page 1 of 6 SECTION 5: STREET TREE PLANTING 1.0 GENERAL This section describes the work to be carried out to prepare planting sites and complete planting
More informationEntegra Roof Tile: Bermuda Natural Gray Roof Tile with no antique
Entegra Roof Tile: Bermuda Natural Gray Roof Tile with no antique ONE STORY RESIDENCES IN THE AREA 6610 S.W. 62 ND Court 6620 S.W. 62 ND Court (Subject Property) 6630 S.W. 62 ND Court 6700 S.W. 62 ND
More informationClient #: Dawson /91. NRCS Tract #(s): Location: Fleming Memorial Park Field #(s): Program(s): Urban Project Name: Date:
Natural Resource Stewardship Plan Jackson Soil and Water Conservation District 89 Alder Street Central Point, Oregon 97502 Ph. (541) 664-1070 www.jswcd.org Client Name: Elisa Dawson, City of Rogue River
More informationDelaware River Waterfront Corporation
Delaware River Waterfront Corporation Delaware River Waterfront Corporation Created in January 2009 to replace Penn s Landing Corporation o Open, accountable, effective leadership o New Board of Directors
More informationWMU Tree Care Plan and Policies
WMU Tree Care Plan and Policies PURPOSE The purpose of the Western Michigan University Tree Care Plan and Policies is to define protocols and give guidance and direction as to the best practices for any
More informationPART E SPECIFICATIONS
PART E SPECIFICATIONS Bid Opportunity No. 386-2004 Page 1 of 9 PART E - SPECIFICATIONS GENERAL E1. APPLICABLE SPECIFICATIONS, STANDARD DETAILS AND DRAWINGS E1.1 The City of Winnipeg Standard Construction
More informationISSUANCES FINAL 4.1 SITE PLAN SUBMISSION
CHAISE LOUNGES, TYP. LOUNGE FURNITURE POOL LOUNGE TABLE RAISED MODULAR PLANTER PEDESTAL PAVERS RAISED MODULAR PLANTER LOUNGE FURNITURE RAISED MASONRY PLANTER PLANTING FLUSH WER FEURE FLUSH LOUNGING PLFORM
More informationCamden SMART Initiative Stormwater Management and Resource Training
Camden SMART Initiative Stormwater Management and Resource Training www.camdensmart.com Camden s Struggle with Stormwater 1 The City of Camden is served by a combined sewer system, which uses the same
More informationSTAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Residential Demolition Application 595 Vaughan Road Date: December 15, 2011 To: From: Wards: Reference Numbers: North York Community Council Director and Deputy Chief Building
More information2013 Summer Recap. Rockaway Beach
2013 Summer Recap and Discussion on Rockaway Beach Reconstruction Tonight s Agenda Summer Beach Update Phase 2 Assumptions, Constraints and Regulations Rebuilding the Boardwalk Coastal Protection Rockaway
More informationSTREETSCAPE IMPROVEMENTS OF MARLBORO PIKE, COMMERCIAL BUSINESS DISTRICT (PART OF THE FAÇADE & INFRASTRUCTURE IMPROVEMENT PROGRAM PHASE II)
STREETSCAPE IMPROVEMENTS OF MARLBORO PIKE, COMMERCIAL BUSINESS DISTRICT (PART OF THE FAÇADE & INFRASTRUCTURE IMPROVEMENT PROGRAM PHASE II) September 2012 1 Advertisement City of District Heights Request
More informationBOARD OF EXAMINERS OF LANDSCAPE ARCHITECTS
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS BOARD OF EXAMINERS OF LANDSCAPE ARCHITECTS RULES AND REGULATIONS Revised RHODE ISLAND STATE BOARD OF EXAMINERS OF LANDSCAPE ARCHITECTS RULES OF THE BOARD
More informationNetwork Chapter Leader Handbook and Other Updates from the October Advisory Board Meeting
Volume 51 September/October 2018 Welcome to the September/October Network Pulse Newsletter. The Network Advisory Board is excited to announce the release of the Draft Community Leader Handbook and some
More informationENVIRONMENTAL ETHICS AND PROJECT MANAGEMENT OF ARCHITECTURE
19-004 The 2005 World Sustainable Building Conference, ENVIRONMENTAL ETHICS AND PROJECT MANAGEMENT OF ARCHITECTURE Seiki TAGAWA Ph.D 1 1 Department of Design and ure, Hokkaido Tokai University, 224 Chuwa
More informationRECEIVE AN UPDATE ON THE ALMOND GROVE PHASE II PROJECT
TOWN OF LOS GATOS COUNCIL AGENDA REPORT MEETING DATE: 12/20/2016 ITEM NO: 12 DATE: TO: FROM: SUBJECT: MAYOR AND TOWN COUNCIL LAUREL PREVETTI, TOWN MANAGER RECEIVE AN UPDATE ON THE ALMOND GROVE PHASE II
More informationCITY COUNCIL STAFF REPORT
CITY COUNCIL STAFF REPORT TO: Honorable Mayor and City Council DATE: April 3, 2017 FROM: PREPARED BY: SUBJECT: Matthew Bronson, City Manager Gregory A. Ray, Public Works Director/City Engineer Kathy Petker,
More informationRequest for Proposal
Request for Proposal Intent: The State of New Jersey Department of Environmental Protection Division of Parks and Forestry, Forest Service (NJFS) has been awarded a grant under the federal American Recovery
More informationThis section covers the planting of seed, sod, trees and vegetation.
Tender 1, 2017 Page 1 of 5 1. INTENT This section covers the planting of seed, sod, trees and vegetation. 1.1 REFERENCES Agriculture and Agri-Food Canada; The Canadian System of Soil Classification, Third
More informationSPL-2.2 MECHANICALS POOL LAWN. 3rd FLOOR TERRACES AMENITY RESTAURANT 230 EAST AVENUE AMENITY NORWALK, CT
8 8 CONCRETE RAMP WOOD STEPS SWIMMING POOL 8 METAL POOL ENCLOSURE FENCE 9 SINGLE LEAF METAL GATE 0 LAWN HANGING CANOPY WITH DOWN LIGHTS METAL & GLASS AWNING AMENITY ROOM WITH FOLDING GLASS WALLS CONCRETE
More informationREQUEST FOR PROPOSAL
REQUEST FOR PROPOSAL The City of Poughkeepsie seeks qualified not for profit organizations interested in leasing property located at 36 North Clover Street in the City of Poughkeepsie for the purpose of
More informationSIUE LANDSCAPE UPGRADE
SIUE LANDSCAPE UPGRADE Project Introduction The Southern Illinois University Edwardsville campus was established and built in the mid-1960's, based on a landscape master plan by HOK. The landscape plan
More informationRequest for Proposal
Request for Proposal 10 th Street Corridor Master Plan Department of Planning and Zoning 500 Quartermaster Court Suite 200 Jeffersonville, IN 47130 April 18, 2017 For further information contact: Chad
More informationRevise A.5 Description to read: Supplying and Placing Base Course Material
Corporate Finance Department Materials Management Division 39-2017 ADDENDUM No. 2 Page 1 of 9 4R WINNIPEG DEPOT EAST WINNIPEG COMMUNITY RESOURCE RECOVERY CENTRE URGENT PLEASE FORWARD THIS DOCUMENT TO WHOEVER
More informationCREEKSIDE VILLAGE HOMEOWNERS ASSOCIATION LANDSCAPE RULES CONTENTS
CREEKSIDE VILLAGE HOMEOWNERS ASSOCIATION LANDSCAPE RULES CONTENTS 1. Landscape Charter 2. General 3. Open Area a. Restrictions b. Excavation c. Bees, Wasps & Yellow Jackets d. Moles, Gophers and other
More informationA. Section Includes: Labor, materials, necessary equipment and services to complete the tree relocation work.
SECTION 02910 TREE RELOCATION PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Labor, materials, necessary equipment and services to complete the tree relocation work. B. Related Section: 1. 02900 - Landscaping.
More informationRequest for Proposals A Revised Master Plan for Waterfront Planning Area, City of Lynn
Request for Proposals A Revised Master Plan for Waterfront Planning Area, City of Lynn In this Request for Proposals The City of Lynn, Massachusetts (the City) acting through the Economic Development Industrial
More informationSection 815. LANDSCAPING
815.01 Section 815. LANDSCAPING 815.01. Description. This work consists of providing and planting trees, shrubs, and other plants, including replacements, classified as nursery stock. The Engineer may
More informationC7.1 PUBLIC ROADWAY PLAN TRILLIUM AVENUE RESOURCE INTERNATIONAL INC. Description. Issued By Drawing Issue & Revision Status. Date.
C7.1 www.resourceinternational.com 6350 PRESIDENTIAL GATEWAY COLUMBUS, OHIO 43231 PHONE: (614) 823-4949 FAX: (614) 823-4990 RESOURCE INTERNATIONAL INC. OUTLOT "A" OUTLOT "B" WINCHESTER PIKE WATER LINE
More informationUniversity of Delaware
SECTION 01 56 18 _ Tree Protection University Contact: UD Assistant Director of Grounds: Office (302) 831 2797 UD Landscape Planner: Office (302) 831 1817 PART 1 GENERAL 1.1 SUMMARY Information in this
More informationPotomac Headwaters Leaders of Watersheds Spring 2019 Application
Potomac Headwaters Leaders of Watersheds Spring 2019 Application Educating future generations of environmental stewards through classroom education and on the ground conservation practices at schools.
More informationTREE PLANTING AND ESTABLISHMENT. Keith Wood Colorado State Forest Service
TREE PLANTING AND ESTABLISHMENT Keith Wood Colorado State Forest Service Select the Right Tree for the Right Place Match the Tree to the Site: Growth Habit, Water Needs, Durability (Hardiness) Insect and
More informationEU Delegation to Albania Vlora Municipality Albanian Development Fund
VISIBILITY ARTWORK COMPETITION FOR THE VLORA WATERFRONT VISIBILITY ARTWORK COMPETITION FOR THE VLORA WATERFRONT INVITATION We invite figurative arts artists to participate in an Arts Competition. The Vlora
More informationCampus Wide Fire Alarm Repairs
BID # 15-24 Campus Wide Fire Alarm Repairs SECTION "C" TECHNICAL SPECIFICATIONS OWNER Board of Trustees Middlesex County College 2600 Woodbridge Avenue P.O. Box 3050 Edison, New Jersey 08818-3050 PREPARED
More informationREQUEST FOR PROPOSAL. Grounds Maintenance
REQUEST FOR PROPOSAL Grounds Maintenance March 1, 2019 Invitation Syracuse City invites contractors to submit a bid to perform grounds maintenance of Syracuse City Hall, Police Station, and Museum. Bid
More informationRequest for Statement of Interest in Implementation of the Roosevelt Road Redevelopment Plan
425 Hillside Avenue Request for Statement of Interest in Implementation of the Roosevelt Road Redevelopment Plan I. INTRODUCTION The is seeking the services of a qualified consulting firm to prepare plans
More informationPart 3: Interior Landscape Installation and Maintenance
Part 3: Interior Landscape Installation and Maintenance Contents 1.0. General Conditions...1 1.1. Scope and Coordination... 1 1.2. Foliage Plant Standards... 1 1.3. Guarantee and Maintenance Period...
More informationLocal Technical Assistance Program FREE Road Maintenance and Safety Training for Municipal Employees
Local Technical Assistance Program FREE Road Maintenance and Safety Training for Municipal Employees The Pennsylvania Local Technical Assistance Program (LTAP) was created to share transportation knowledge,
More informationCohoes Housing Authority 100 Manor Sites Cohoes, NY P: F:
Cohoes Housing Authority 100 Manor Sites Cohoes, NY 12047 P: 518-235-4500 F: Authority wide Landscaping Improvements The Cohoes Housing Authority of the City of Cohoes, New York is receiving proposals
More information2018 Marketing Opportunities
Oregon Landscape Contractors Association 2018 Marketing Opportunities By partnering with OLCA, you will help to further educate and develop the landscape industry OLCA can connect you with individuals
More informationThe planning and zoning board held workshops on January 11, 2016, January 18, 2016 and January 25, 2016 to discuss the issue.
MIAMI SHORES DEPARTMENT OF PLANNING & ZONING 10050 NE 2 nd Avenue Miami Shores FL 33037-2304 www.miamishoresvillage.com David A. Dacquisto AICP, Director Main Number: 305-795-2207 Fax Number: 305-756-8972
More informationIFLA Regional Office for Latin America and the Caribbean: Call for Applications to host the Regional Office
IFLA Regional Office for Latin America and the Caribbean: Call for Applications to host the Regional Office Introduction The International Federation of Library Associations and Institutions http://www.ifla.org
More informationCONSTRUCTION SPECIFICATION FOR RIP RAP, ROCK PROTECTION AND GRAVEL SHEETING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 511 FEBRUARY 1990 CONSTRUCTION SPECIFICATION FOR RIP RAP, ROCK PROTECTION AND GRAVEL SHEETING 511.01 SCOPE 511.02 REFERENCES 511.03 DEFINITIONS 511.04
More informationBritish Columbia Landscape Standard. Published by:
British Columbia Landscape Standard Published by: British Columbia Society of Landscape Architects British Columbia Landscape and Nursery Association BC Landscape Standard 2012 The British Columbia Landscape
More informationExhibit A Section 1: Commerce City Right Of Way Landscape Maintenance Scope of Service
Exhibit A Section 1: Commerce City Right Of Way Landscape Maintenance Scope of Service A. Scope: (i) Services: At the City s direction, the Contractor shall provide programmatic and nonprogrammatic Right
More informationDISCOUNT TIRE - IAD 10739
1229 NW 86TH STREET CLIVE, IOWA 50325 PRELIMINARY ENGINEERING PLANS PLAN INDEX SITE LOCATION TITLE SHEET PLAN DATE: 07/13/2015 Beyond Surveying and Engineering NW 86th STREET 0 20 40 EXISTING CONDITIONS
More information