1 PHASE ONE A summary report: What the community told Alcoa during Phase One of the community engagement program for Point Henry 575. DECEMBER 2015 FEBRUARY 2016

2 INTRODUCTION In 2014 Alcoa closed its Point Henry smelting and rolling facilities after 51 years of operating in Geelong. This marked the beginning of a comprehensive closure process, with one of the goals being to develop a Master Plan for Alcoa s 575 hectares of freehold land. The Point Henry 575 Master Plan will consider remediation requirements, market data, the opportunities and the constraints of the land, supply and demand for land uses, and community aspirations. Alcoa needs to balance and consider all of these aspects with the goal to create a Master Plan that makes sense, to the community and stakeholders, and also commercially. In keeping with Alcoa s long term commitment to community engagement, Alcoa launched a process in December 2015 to capture the community s views and aspirations for the future land use of Point Henry 575. Phase One of the community engagement, undertaken between December 2015 and February 2016, enabled important community and stakeholder input into the creation of a Shared Vision incorporating themes and guiding principles to help inform the creation of the Point Henry 575 Master Plan. During Phase One participants learnt more about the decommissioning and remediation process currently underway by Alcoa, and were asked to contribute their ideas and views to five draft Shared Vision Themes. PHASE ONE - DRAFT SHARED VISION THEMES Based on Alcoa s knowledge of the site, long term association with the community and early feedback, five draft themes were created to form the basis of the Building the Shared Vision conversation: EMBRACE & CELEBRATE THE COASTAL LANDSCAPE BUILD UPON THE STRENGTHS OF THE EXISTING COMMUNITY CREATE A DIVERSE & INCLUSIVE PLACE HONOUR THE VARIOUS HISTORIES OF THE SITE FOCUS ON THE FUTURE OF THE GEELONG REGION A DEVELOPMENT THAT LEADS BY EXAMPLE 2

3 PHASE ONE: FEEDBACK SNAPSHOT The economic prosperity of Geelong Across all engagement forums (online, workshops, listening posts) there was a strong focus on the economy and what will replace the industrial and manufacturing base that has been part of the Geelong economy for so long. A significant number of participants referred to the need for jobs and employment opportunities. There were interesting discussions around whether tourism has the greatest economic potential for the Geelong region or whether the industrial elements of the Point Henry site should be preserved and re-purposed for use by an alternative industry. This focus on economic drivers permeated a significant proportion of the discussion in Phase One. A development that leads by example and complements Geelong A consistent theme within the feedback was that the development should lead by example. Comments often related back to economic drivers and showed that the participants in Phase One supported a thorough, considered and visionary approach to the master planning of Point Henry 575. The word iconic was used in varied ways, ranging from the development of new industries, including renewable energy facilities, through to theme parks that would create jobs and a spotlight on the region. The feedback included future uses that result in long-term, sustainable returns for the Geelong region. Coastal location The importance of taking advantage of the coastal location of the site was a consistent underlying theme. The discussion centered around the economic potential of harnessing the coastal landscape for tourism activities and the need to create public access to the coast for recreational purposes. The participants were conscious of the coastal and environmental attributes of the site. The location of the point was described as iconic, a landmark site and a jewel in the crown of the Bay. Honouring the histories Whilst honouring the histories of the site had the fewest comments made in relation to it, a range of people spoke passionately about the site s histories in terms of the indigenous, settler and Alcoa histories. There was also support for potential adaptation or reuse of existing infrastructure and land forms. Diverse future uses Participants, generally, desired a balance between economic benefits and public access in the future use of the land. There is support for a master plan that incorporates a range of uses that achieve economic prosperity, coastal access, public spaces for recreational or environmental activities, and lifestyle choices. 3

4 PHASE ONE: SNAPSHOT OF ENGAGEMENT Face to face engagement 2 Community listening posts 3 Community workshops 1 Community Advisory Board Workshop 30 Direct Participants (approx) 43 Participants 7 Participants Online engagement 831 Visitors to project website 47 Registered participants on project website 73 Online brainstormer/ post-it-note ideas 9 submissions Print communication and media articles FACT SHEETS AND POSTCARDS Distributed at Launch, CAB Meetings, Listening Posts and Community Workshops ABC News coverage PRESS ARTICLES 2x Geelong Advertiser 1x Business Life magazine 900+ Engaged members of the community 158 Total amount of feedback comments recorded 4

5 PHASE ONE: TOP LINE REVIEW OF FEEDBACK Initial sorting of the feedback highlighted the ideas that arose Economy Iconic Coastal Landscape Recreation Public Space Tourism Environment Complement Geelong History Infrastructure Multiple Users Residential Renewable Energy Sustainable Development Nature Park Industrial Adaptation Community Service Education Other Ideas were then further sorted into key themes The economic prosperity of Geelong Coastal location Diverse future uses A development that leads by example and complements Geelong Honouring the histories 5

6 WHAT PARTICIPANTS TOLD ALCOA ABOUT DRAFT SHARED VISION THEMES All of the feedback received was further sorted and placed under each draft Shared Vision Theme. Key words that were stated are further highlighted in a word map for each theme EMBRACE AND CELEBRATE THE COASTAL LANDSCAPE Participants told Alcoa that the site s location and landscape are key attributes of any future land use. Public access for water sports and recreational activities to utilise the coastal and environmental attributes of the site was seen as important. Any outcome could support economic growth via tourism activities, continued industrial use or alternative mixed use. big exhibition great location vacant aquarium area point look jobs new parks city region employment precinct renewable opportunity exciting hotel titanium developed economy services theme land create energy Geelong ships hub vision technology centre development park house tourist innovation community casino infrastructure people waste service Melbourne need boat water idea conference entertainment tourism electric make business facility activities parks support pier wind site industrial 3. CREATE A DIVERSE AND INCLUSIVE PLACE Participants told Alcoa that there was a strong preference to explore multiple land uses for the site including land uses that create new opportunities for economic development in Geelong, while still retaining public access to the coast, and for recreational purposes. Conversations often outlined a mix of recreational/public access uses combined with ideas for economic activities. existing developed waterfront make city industrial fishing boat Melbourne beach Alcoa activities create believe recreation support fishing water entertainment ships land Marina region aquarium use hotel community pier need ferry cruise exciting tourist Avalon Geelong waste development tourism house park precinct small CBD great international state coast big surfing support people sports area tourism peninsula wind 2. BUILD UPON THE STRENGTHS OF THE EXISTING COMMUNITY Participants told Alcoa that there should be a strong focus on creating new economic opportunities for the Geelong region, and a need to consider the economic viability of any future land uses. Any development needs to be appropriate for the region and therefore be considerate of the planning and strategic direction for Geelong. land centre people aquarium port Geelong opportunity activities new beach grounds residential pier park Recreation wind community port future energy Melbourne see sports housing many entertainment cruise create hub ships exciting industrial many use big site area boat great boat accessibility waterfront history show ferry region development based surfing wetlands theme Alcoa need gardens exhibition diverse environment state existing tourist beach Bellarine precinct fishing

7 4. HONOUR THE VARIOUS HISTORIES OF THE SITE Participants told Alcoa that the site has a diverse history: from its indigenous history, its settler history, through to Alcoa s history on the site, and the collective impact of these histories in the wider region. There is a desire to explore the adaption and reuse of the existing infrastructure and built form on the site for alternative uses. Australia history Bellarine site pier hub recognise histories Henry historic land industrial waste cultural facility example city Australia Wathaurong area future tea western great Point recreation used port Geelong state historical activities settlers power use district opportunity making tracks most see Indigenous early people generations infrastructure water buildings many name tourist example facility existing use land area design energy making development park Geelong vision community developed Melbourne jobs world entertainment exhibition people look see waste good road new development plant make years housing everything city innovation CBD Avalon create land currently example link hub big small opportunity space over support iconic great sustainable developed industrial many iconic Harbour activities employment precinct bridge existing future tourism many something use site build 5. FOCUS ON THE FUTURE OF THE GEELONG REGION A DEVELOPMENT THAT LEADS BY EXAMPLE Participants told Alcoa that consideration should be given to an outcome that supports new jobs, a positive economic impact for the region and a long term sustainable future. 7

8 SHARED VISION: REVISED SHARED VISION THEMES & GUIDING PRINCIPLES FOLLOWING PHASE ONE Through Alcoa s engagement with the community during Phase One, Alcoa has refined the five draft Shared Vision Themes and developed a Shared Vision Statement. Shared Vision The Point Henry 575 site will be a diverse and inclusive place that celebrates its coastal location and supports the prosperity of the Geelong region, whilst recognising and honouring the site s natural landscape and history. Support and build on the prosperity of the Geelong region Guiding Principles Create opportunities for jobs Outcomes are economically sustainable Complement the Geelong region Guiding Principles Be considerate of Geelong s broader planning and strategic direction Create a place that s valued by the community Embrace and celebrate the coastal landscape Guiding Principles Provide public access to the coast Provide for recreational opportunities Consider existing landscape attributes and landforms Honour the various histories of the site Guiding Principles Recognise the significance of the indigenous, settler and Alcoa histories Explore existing built form and infrastructure for adaptation and reuse Create a diverse and inclusive place Guiding Principles 8 Offer a range of lifestyle and economic opportunities Provide for a variety of connected public open spaces

9 NEXT STEPS Alcoa is committed to engaging with the community about the future of Point Henry 575. During Phase Two of community engagement, Alcoa will provide opportunities for the community to consider and deliver feedback on the revised Shared Vision Themes and Guiding Principles. Alcoa will then publish the Shared Vision for the Point Henry 575 Master Plan. From June to September 2016 Alcoa will work to create the draft Point Henry 575 Master Plan. During Phase Three of community engagement, Alcoa will provide opportunities for the community to deliver feedback to Alcoa about the draft Master Plan April May June July August September October Community Engagement Phase Two Review revised Shared Vision. Shared Vision finalised and published Alcoa prepares Draft Master Plan Community Engagement Phase Three Master Plan released for community and stakeholder feedback 9

10 Thank you to the participants who shared their ideas during Phase One of the community engagement for Point Henry 575. Detailed summaries from all Phase One activities including Listening Posts, Online feedback and Workshops can be viewed on the Alcoa website. STAY INFORMED AND INVOLVED Visit Mail PO Box 460, Geelong VIC 3220

... on the draft Arden Vision & Framework

... on the draft Arden Vision & Framework April 2017 Integrated world-class urban renewal Feedback... on the draft Arden Vision & Framework On 1 September 2016 the Victorian Planning Authority (VPA) released the draft Arden Vision & Framework

More information

Eastern City District Plan

Eastern City District Plan OUR GREATER SYDNEY 2056 Revised Draft Eastern City District Plan OVERVIEW Bayside Burwood Canada Bay City of Sydney Inner West Randwick Strathfield Waverley Woollahra Snapshot of the Eastern City District

More information

COMMUNITY ACTIONS for a SUSTAINABLE BARWON HEADS. February 2016

COMMUNITY ACTIONS for a SUSTAINABLE BARWON HEADS. February 2016 COMMUNITY ACTIONS for a SUSTAINABLE BARWON HEADS February 2016 Acknowledgements Traditional Owners We acknowledge the traditional owners of this land and pay our respects to their elders past and present,

More information

Draft Eastern District Plan

Draft Eastern District Plan Draft Eastern District Plan Submission_id: 31238 Date of Lodgment: 13 Dec 2017 Origin of Submission: Online Organisation name: Turrulla Gardens Pty Ltd C/- Mecone Organisation type: Industry First name:

More information

Your Ideas, Our Future Stage 1 community engagement

Your Ideas, Our Future Stage 1 community engagement Your Ideas, Our Future Stage 1 community engagement Interim report February 2017 WWW.GEELONGAUSTRALIA.COM.AU This report has been prepared by : Strategy & Program Delivery City of Greater 30 Gheringhap

More information

South District Plan OVERVIEW

South District Plan OVERVIEW OUR GREATER SYDNEY 2056 Revised Draft South District Plan OVERVIEW Canterbury-Bankstown Georges River Sutherland Snapshot of the South District today and into the future The Greater Sydney Commission acknowledges

More information

SUBJECT: Waterfront Hotel Planning Study Update TO: Planning and Development Committee FROM: Department of City Building. Recommendation: Purpose:

SUBJECT: Waterfront Hotel Planning Study Update TO: Planning and Development Committee FROM: Department of City Building. Recommendation: Purpose: Page 1 of Report PB-23-18 SUBJECT: Waterfront Hotel Planning Study Update TO: Planning and Development Committee FROM: Department of City Building Report Number: PB-23-18 Wards Affected: 2 File Numbers:

More information

Wireless Hill Vision 2020

Wireless Hill Vision 2020 Wireless Hill Vision 2020 Key Themes and Objectives for the Future of Wireless Hill Revision: Draft Issue Date: 23/04/2009 Document No: Wireless Hill Vision 2020 Page 1 4/30/2009 Table of Contents 1 Overview...

More information

Yarra Strategic Plan community engagement summary

Yarra Strategic Plan community engagement summary Yarra Strategic Plan community engagement summary Between May and August 2018 Melbourne Water undertook community engagement to build the content of the draft Yarra Strategic Plan. This engagement included

More information

Thank you! Events and Entertainment in Northeast False Creek. Tuesday, March 7, 2017

Thank you! Events and Entertainment in Northeast False Creek. Tuesday, March 7, 2017 Events and Entertainment in Northeast False Creek Tuesday, March 7, 2017 Thank you! Thank you for taking the time to attend the Events and Entertainment in Northeast False Creek (NEFC) workshop in partnership

More information

OUR GREATER SYDNEY A metropolis of three cities. OVERVIEW. connecting people. DRAFT Greater Sydney Region Plan

OUR GREATER SYDNEY A metropolis of three cities. OVERVIEW. connecting people. DRAFT Greater Sydney Region Plan OUR GREATER SYDNEY 2056. A metropolis of three cities. OVERVIEW. connecting people. DRAFT Greater Sydney Region Plan October 2017 This document is an overview of the draft Greater Sydney Region Plan. To

More information

WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014

WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014 WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014 Dear Resident This Special Edition of the Whiteley Voice which has been prepared in conjunction with the North Whiteley Consortium is to

More information

Four Big Ideas. Three Key Opportunities. Principles. Draft Place Making Master Plan. 1. The Foreshore 2. Green Links. 3.

Four Big Ideas. Three Key Opportunities. Principles. Draft Place Making Master Plan. 1. The Foreshore 2. Green Links. 3. project background Four Big Ideas 1. The Healthy Thriving Place. An International Focus 3. Reclaiming Mooloolaba 4. The Resort Heart of the Coast In November 01 a big ideas workshop was held involving

More information

Institute Response to Design Guidelines: Design Quality and Housing Choice

Institute Response to Design Guidelines: Design Quality and Housing Choice Institute Response to Design Guidelines: Design Quality and Housing Choice The Australian Institute of Landscape Architects South Australian Chapter (AILA SA) is pleased to provide a response on the Draft

More information

Lynn Waterfront Master Plan

Lynn Waterfront Master Plan Lynn Waterfront Master Plan Public Meeting #2 December 10th, 2018 1 Project Schedule Update September 26, 2018 December 10, 2018 Development of the Master Harbor Plan Amendment and Revised Waterfront Master

More information

Town of Cobourg Heritage Master Plan. Statutory Public Meeting

Town of Cobourg Heritage Master Plan. Statutory Public Meeting Town of Cobourg Heritage Master Plan Statutory Public Meeting April 25 th 2016 Presentation Overview 1. Introduction 2. Project background and schedule overview 3. Review of strategic direction content

More information

ELLIOTT HEADS STRUCTURE PLAN

ELLIOTT HEADS STRUCTURE PLAN ELLIOTT HEADS STRUCTURE PLAN BACKGROUND This report has been prepared to provide an overview of the land that has been included in the Urban Footprint within the Wide Bay Burnett Regional Plan, September

More information

DRAFT GREATER SYDNEY REGION PLAN OBJECTIVES, STRATEGIES AND ACTIONS

DRAFT GREATER SYDNEY REGION PLAN OBJECTIVES, STRATEGIES AND ACTIONS Greater Sydney Commission DRAFT GREATER SYDNEY REGION PLAN OBJECTIVES, STRATEGIES AND ACTIONS Issued: 26 OCTOBER 2017 Version: 1 Subject: Greater Sydney Region and District Plans This information note

More information

RE: QUEENSLAND GOVERNMENT PLANNING POLICY REVIEW

RE: QUEENSLAND GOVERNMENT PLANNING POLICY REVIEW Planning Group Department of Infrastructure, Local Government and Planning PO Box 15009 CITY EAST QLD 4002 Via email: planningpolicy@dilgp.qld.gov.au 9 February 2017 Dear Sir/ Madam, RE: QUEENSLAND GOVERNMENT

More information

HBF Marine Study: Victoria Harbour: Water dependent and water related uses and associated land/water interface implications

HBF Marine Study: Victoria Harbour: Water dependent and water related uses and associated land/water interface implications HBF Marine Study: Victoria Harbour: Water dependent and water related uses and associated land/water interface implications Presentation on the Initial Findings 9 February 2011 Harbour Business Forum Background

More information

1 Welcome! UBC Okanagan Master Plan Update - Open House

1 Welcome! UBC Okanagan Master Plan Update - Open House 1 Welcome! UBC Okanagan Master Plan Update - Open House UBC is updating the Master Plan for the Okanagan Campus. The purpose of today s Open House is to: Present the draft 2015 Master Plan Answer any questions

More information

Welcome. Walk Around. Talk to Us. Write Down Your Comments

Welcome. Walk Around. Talk to Us. Write Down Your Comments Welcome This is an information meeting introducing the applications for proposed redevelopment of the Yorkdale Shopping Centre site at 3401 Dufferin Street and 1 Yorkdale Road over the next 20+ years,

More information

George Hotel application STAFF REVIEW COMMITTEE OF THE WHOLE JANUARY 14, 2014

George Hotel application STAFF REVIEW COMMITTEE OF THE WHOLE JANUARY 14, 2014 George Hotel application STAFF REVIEW COMMITTEE OF THE WHOLE JANUARY 14, 2014 1 Presentation outline Purpose: to seek Council direction for next steps in the review process Application process to date

More information

Fishermans Bend Draft Framework. Submission to public consultation

Fishermans Bend Draft Framework. Submission to public consultation Fishermans Bend Draft Framework Submission to public consultation 14 December 2017 An opportunity for a world class innovation precinct The University of Melbourne welcomes the release of the Draft Fishermans

More information

ACKNOWLEDGEMENTS PROJECT TEAM

ACKNOWLEDGEMENTS PROJECT TEAM ACKNOWLEDGEMENTS La Trobe University proudly acknowledges the Dja Dja Wurrung people, the traditional custodians of the land upon which the Bendigo Flora Hill campus is located. We recognise that Indigenous

More information

Draft Western District Plan

Draft Western District Plan Powered by TCPDF (www.tcpdf.org) Draft Western District Plan Submission_id: 31440 Date of Lodgment: 15 Dec 2017 Origin of Submission: Online Organisation name: Goodman Property Services Australia Pty Ltd

More information

CDAC. Update: Downtown Dartmouth Update: CDAC July 25 th Motion

CDAC. Update: Downtown Dartmouth Update: CDAC July 25 th Motion CDAC Update: Downtown Dartmouth Update: CDAC July 25 th Motion 2018-10-24 Downtown Dartmouth Plan Open House October 22, 2018 6:00 pm Open House 6:30 pm Presentation + Q&A 7:20 pm Open House 8:30 pm Close

More information

AT A GLANCE... Our People, Culture & Place. A plan to sustain Ballarat s heritage (final draft)

AT A GLANCE... Our People, Culture & Place. A plan to sustain Ballarat s heritage (final draft) AT A GLANCE... Our People, Culture & Place A plan to sustain Ballarat s heritage 2017-2030 (final draft) Image: Lydiard Street, Ballarat, c1875-1938, John Henry Harvey collection, La Trobe Picture Collection,

More information

Reimagining Arnolds Creek. Community engagement report. May 2018

Reimagining Arnolds Creek. Community engagement report. May 2018 Reimagining Arnolds Creek Community engagement report May 2018 Melbourne Water is owned by the Victorian Government. We manage Melbourne s water supply catchments, remove and treat most of Melbourne s

More information

PART 02 HASTINGS POINT IN CONTEXT

PART 02 HASTINGS POINT IN CONTEXT PART 02 HASTINGS POINT IN CONTEXT 2.1 Background 2.1.1 Demographic Information 2.1.2 Existing Locality Characteristics 2.2 The Planning Framework 2.2.1 The Far North Coast Regional Strategy 2006 2.2.2

More information

North District What we heard

North District What we heard What we heard Vision to 2056 and Priorities Governance and implementation Infrastructure and funding The vision for a metropolis of three cities, and the 30 minute city. Feedback emphasised: That for the

More information

Plenty Gorge Park Draft Master Plan Consultation Report. Draft Master Plan April 2018

Plenty Gorge Park Draft Master Plan Consultation Report. Draft Master Plan April 2018 Plenty Gorge Park Draft Master Plan Consultation Report Draft Master Plan April 8 Introduction As part of the development of the Plenty Gorge Park Master Plan, Parks Victoria designed a consultation and

More information

Overview. Have your say. Distributed sites network key objectives. Planning vision. QUT Draft Estate Master Plan. Facilities Management

Overview. Have your say. Distributed sites network key objectives. Planning vision. QUT Draft Estate Master Plan. Facilities Management Facilities Management Overview QUT Draft Estate Master Plan QUT has developed a Draft Estate Master Plan for its main campuses (Gardens Point and Kelvin Grove) and the 17 distributed sites. The draft plan

More information

Draft Western District Plan

Draft Western District Plan Powered by TCPDF (www.tcpdf.org) Draft Western District Plan Submission_id: 31371 Date of Lodgment: 14 Dec 2017 Origin of Submission: Online Organisation name: Mecone Pty Ltd Organisation type: Industry

More information

CENTRAL ESTUARY PLAN AVISION FOR OAKLAND S WATERFRONT

CENTRAL ESTUARY PLAN AVISION FOR OAKLAND S WATERFRONT Central Estuary Plan A VISION FOR OAKLAND S WATERFRONT Specific Plan and Environmental Assessment Presentation to the Parks and Recreation Advisory Commission December 9, 2009 This Afternoon s Presentation

More information

EDC 016/004 Annex A. Framework Masterplan Stakeholder and public engagement

EDC 016/004 Annex A. Framework Masterplan Stakeholder and public engagement Framework Masterplan Stakeholder and public engagement A summary of stakeholder feedback received in December 2015 1 Stage 1 Emerging findings This briefing note provides the emerging findings and key

More information

PMP PRINTING SITE COMMUNITY ENGAGEMENT - PHASE 2

PMP PRINTING SITE COMMUNITY ENGAGEMENT - PHASE 2 PMP PRINTING SITE COMMUNITY ENGAGEMENT - PHASE 2 FEBRUARY 2019 0317-0511 - PMP Printng - M001 (8 -Floors) -Final date 14.11.2018 Vision: The PMP Printing site will be transformed into a contemporary mixed-use

More information

New Westminster Downtown Parking Strategy Public Open House #1 September 13, 2012

New Westminster Downtown Parking Strategy Public Open House #1 September 13, 2012 New Westminster Downtown Parking Strategy Public Open House #1 September 13, 2012 The City is preparing a strategy for parking in Downtown New Westminster. The study team and a group of key stakeholders

More information

Workshop 3. City of Burlington Waterfront Hotel Planning Study. September 14, The Planning Partnership

Workshop 3. City of Burlington Waterfront Hotel Planning Study. September 14, The Planning Partnership Workshop 3 City of Burlington Waterfront Hotel Planning Study September 14, 2017 The Planning Partnership The Waterfront Hotel Planning Study 01 The Brant & Lakeshore Planning Study will establish a Strategic

More information

PLANNING ADVISORY BOARD AGENDA OCTOBER

PLANNING ADVISORY BOARD AGENDA OCTOBER ! City of Langley PLANNING ADVISORY BOARD AGENDA OCTOBER 1, 2014 3-5pm LANGLEY CITY HALL - 112 2 nd Street, Langley WA 1) Call to Order and Roll Call 2) Approval of the Minutes September 10, 2014 3) Public

More information

Point Nepean National Park Master Plan. Community update and discussion paper January 2016

Point Nepean National Park Master Plan. Community update and discussion paper January 2016 Point Nepean National Park Master Plan Community update and discussion paper January 2016 Purpose The Victorian Government is reaffirming the direction for management of Point Nepean National Park and

More information

Edward R. Sajecki Commissioner of Planning and Building

Edward R. Sajecki Commissioner of Planning and Building Corporate Report Clerk s Files Originator s Files CD.03.POR DATE: TO: FROM: SUBJECT: Chair and Members of Planning and Development Committee Meeting Date: February 27, 2012 Edward R. Sajecki Commissioner

More information

Ship Creek Redevelopment

Ship Creek Redevelopment Ship Creek Redevelopment Three Concepts May 2013 Cambridge ARCHITECTURE Philadelphia ENGINEERING Raleigh INTERIORS San Francisco PLANNING Washington, DC www.klingstubbins.com contact@klingstubbins.com

More information

See the West Melbourne Transport and Access Study (Phillip Boyle and Associates) for more information on the proposed Spencer Street tram.

See the West Melbourne Transport and Access Study (Phillip Boyle and Associates) for more information on the proposed Spencer Street tram. West Melbourne Ideas Workshop - Saturday 18 February 2017 Issues, concerns, ideas and comments On Saturday 18 February, around 150 people attended an ideas workshop at the Angliss Conference Centre to

More information

Summary Community Workshop #1 Fruitvale San Antonio Senior Center Monday, March 23, :00-9:00 p.m.

Summary Community Workshop #1 Fruitvale San Antonio Senior Center Monday, March 23, :00-9:00 p.m. Summary Community Workshop #1 Fruitvale San Antonio Senior Center Monday, March 23, 2009 7:00-9:00 p.m. Workshop Format and Process The City of Oakland is preparing a Specific Plan that will help define

More information

Chelsea Creek Municipal Harbor Plan

Chelsea Creek Municipal Harbor Plan Chelsea Creek Municipal Harbor Plan Public Meeting #1 June 11th, 2018 1 Presentation outline I. Introduction: Why are we doing this plan? II. Evolution of Chelsea Creek III. State of Chelsea Creek IV.

More information

Moving from Vision to Action

Moving from Vision to Action Moving from Vision to Action Photo: John Carvalho What does it mean for a city to move? To see its people belong and connect? To prosper? To become green? Those are the pillars that are helping Mississauga

More information

Inclusive and Engaging City

Inclusive and Engaging City Inclusive and Engaging City An Inclusive City welcomes and enables all people to participate fully in City life. Population, housing, services, social inclusion and liveability are important elements of

More information

DRAFT: NOT FINAL DESIGN

DRAFT: NOT FINAL DESIGN T H E M E S O F S T A K E H O L D E R I N P U T GREEN INFRAST RUCTURE & EDGES STEWARDSHIP THROUGH P ARTNERSHIP AMENITIES & ANCHORS DESTINATION DISTRICT sustainable landscapes & infrastructure that are

More information

Draft Newcastle Urban Renewal Strategy Submission by Planning Institute of Australia (NSW Division)

Draft Newcastle Urban Renewal Strategy Submission by Planning Institute of Australia (NSW Division) Draft Newcastle Urban Renewal Strategy Submission by Planning Institute of Australia (NSW Division) March 2013 The Planning The Planning Institute of Australia (PIA) is the peak body representing professionals

More information

Municipal Development Plan 2013

Municipal Development Plan 2013 UNIQUELY STONY PLAIN: Municipal Development Plan 2013 Quick Reference Guide What is a Municipal Development Plan (MDP)? The Town s highest-level planning document Sets the long-term vision and key themes

More information

SBPO BOARD MEETING MARCH 20, 2018

SBPO BOARD MEETING MARCH 20, 2018 SBPO BOARD MEETING MARCH 20, 2018 TODAY'S AGENDA > Booker Middle School Outreach > Property Information > Schedule > Guiding Principles > Three Concepts Booker Middle School Outreach Property Information

More information

Auckland City Council

Auckland City Council Auckland City Council Future planning framework version 3.0 9 September 2010 Find out more: Telephone (09) 379 2020 or visit www.aucklandcity.govt.nz www.itsmybackyard.co.nz Foreword Future planning framework

More information

A COMMUNITY VISION. For the County of Brant

A COMMUNITY VISION. For the County of Brant A COMMUNITY VISION For the County of Brant May 2013 THE COMMUNITY VISIONING PROCESS In 2011, the Council of the County of Brant approved the undertaking of a Community Visioning exercise. The Community

More information

Managing our Landscapes Conversations for Change

Managing our Landscapes Conversations for Change Managing our Landscapes Conversations for Change Frequently Asked Questions The new State Government is committed to a significant reform program that will change the way natural resources are managed.

More information

REVISED DRAFT NORTH DISTRICT PLAN PLANNING PRIORITIES AND ACTIONS

REVISED DRAFT NORTH DISTRICT PLAN PLANNING PRIORITIES AND ACTIONS Greater Sydney Commission REVISED DRAFT NORTH DISTRICT PLAN PLANNING PRIORITIES AND ACTIONS Issued: 26 OCTOBER 2017 Version: 1 Subject: Greater Sydney Region and District Plans This information note is

More information

project background relationship to the spit Guiding Principles Mooloolaba Spit Futures Plan (2009) Vision one

project background relationship to the spit Guiding Principles Mooloolaba Spit Futures Plan (2009) Vision one one project background relationship to the spit The Spit is an important part of Mooloolaba and a key contributor to the natural beauty of the town. The Spit is cherished by local residents and visitors

More information

A1 Scotswood to North Brunton Public Information Exhibition Executive Summary

A1 Scotswood to North Brunton Public Information Exhibition Executive Summary A1 Scotswood to North Brunton Public Information Exhibition Executive Summary Introduction The A1 Scotswood to North Brunton scheme is proposed on the A1 Newcastle Gateshead Western Bypass (NGWB) between

More information

INCREMENTAL CHANGE AREA REVIEW March 2015 Page 1

INCREMENTAL CHANGE AREA REVIEW March 2015 Page 1 INCREMENTAL CHANGE AREA REVIEW March 2015 Page 1 Table of Contents Introduction... 3 Background to Review... 3 Comparison of the Schedules to the General Residential Zone... 7 Methodology... 7 Policy Context...

More information

University of Saskatchewan CAMPUS MASTER PLAN. Senate Meeting Preliminary Presentation. April 21, 2018 DIALOG ECS DA WATT

University of Saskatchewan CAMPUS MASTER PLAN. Senate Meeting Preliminary Presentation. April 21, 2018 DIALOG ECS DA WATT University of Saskatchewan CAMPUS MASTER PLAN Senate Meeting Preliminary Presentation April 21, 2018 DIALOG ECS DA WATT project process presentation agenda Stakeholder Engagement Project Control phase1

More information

Highest & Best Use Study Marina Park Lands

Highest & Best Use Study Marina Park Lands Executive Summary of Report MARCH 2006 TABLE OF CONTENTS 1. Introduction...1 2. Study Process...2 3. Highest And Best Use Program...3 4. Concept Plan...8 5. Public Area Animation...9 6. Marina Park Implementation

More information

Central City District Plan

Central City District Plan OUR GREATER SYDNEY 2056 Revised Draft Central City District Plan OVERVIEW Blacktown Cumberland Parramatta The Hills Snapshot of the Central City District today and into the future People Population, age

More information

REPORTING BACK TO YOU ON THE RIG NETWORK SURVEYS A snapshot of findings

REPORTING BACK TO YOU ON THE RIG NETWORK SURVEYS A snapshot of findings REPORTING BACK TO YOU ON THE RIG NETWORK SURVEYS A snapshot of findings We d like to thank everyone who participated in RIG Network s recent surveys and who sent the survey information on to other people.

More information

South of Eastern Strategic Direction Status Update

South of Eastern Strategic Direction Status Update STAFF REPORT ACTION REQUIRED South of Eastern Strategic Direction Status Update Date: July 10, 2014 To: From: Planning and Growth Management Committee Chief Planner and Executive Director, City Planning

More information

TOWN OF MIDLAND TERMS OF REFERENCE AND REQUEST FOR PROPOSALS

TOWN OF MIDLAND TERMS OF REFERENCE AND REQUEST FOR PROPOSALS TOWN OF MIDLAND TERMS OF REFERENCE AND REQUEST FOR PROPOSALS UNIMIN WATERFRONT LANDS MASTER PLAN STUDY August 2012 Town of Midland 575 Dominion Avenue Midland, Ontario L4R 1R2 705-526-4275 TOWN OF MIDLAND

More information

Report to: Development Services Committee Report Date: April 24, 2017

Report to: Development Services Committee Report Date: April 24, 2017 SUBJECT: Cornell Rouge National Urban Park Gateway - Report on Design Charrette and Next Steps PREPARED BY: Lilli Duoba, MES, MCIP, RPP, Manager, Natural Heritage (ext. 7925) REVIEWED BY: Marg Wouters,

More information

BELLARINE PENINSULA Draft Localised Planning Statement JUNE 2014

BELLARINE PENINSULA Draft Localised Planning Statement JUNE 2014 BELLARINE PENINSULA Draft Localised Planning Statement JUNE 2014 BELLARINE PENINSULA Draft Localised Planning Statement JUNE 2014 The Bellarine Peninsula Draft Localised Planning Statement has been developed

More information

The importance of Partnerships Showcasing Arden. Emily Mottram, Director Urban Renewal 31 March 2017

The importance of Partnerships Showcasing Arden. Emily Mottram, Director Urban Renewal 31 March 2017 The importance of Partnerships Showcasing Arden Emily Mottram, Director Urban Renewal 31 March 2017 Presentation Overview 1. Precincts and partnerships are a priority 2. Evolution of the central city 3.

More information

2013 Summer Recap. Rockaway Beach

2013 Summer Recap. Rockaway Beach 2013 Summer Recap and Discussion on Rockaway Beach Reconstruction Tonight s Agenda Summer Beach Update Phase 2 Assumptions, Constraints and Regulations Rebuilding the Boardwalk Coastal Protection Rockaway

More information

Official Plan Review

Official Plan Review Official Plan Review Summary Report - The Built Environment August 2014 Part 1: Introduction Planning for a healthy, prosperous and sustainable community is an important goal for our municipality. From

More information

Overview of Land Use Framework for Victoria Harbourfront. Planning Department February 2011

Overview of Land Use Framework for Victoria Harbourfront. Planning Department February 2011 Overview of Land Use Framework for Victoria Harbourfront Planning Department February 2011 Background TPB set out Vision Statement for the Victoria Harbour in 1999 To make Victoria Harbour attractive,

More information

MOUNTAIN RESILIENCE PLAN

MOUNTAIN RESILIENCE PLAN LARIMER COUNTY COMMUNITY DEVELOPMENT MOUNTAIN RESILIENCE PLAN PHASE 1 OF A NEW COMPREHENSIVE PLAN VISIONING: PRELIMINARY RESULTS AUGUST 2017 200 W. Oak Street, Fort Collins, CO 80521 970.498.7000 larimer.org

More information

CITY CORE 2050 A VISION FOR THE HEART OF THE REGION

CITY CORE 2050 A VISION FOR THE HEART OF THE REGION CITY CORE 2050 A VISION FOR THE HEART OF THE REGION INITIAL SCOPE OF WORK OCTOBER 17, 2017 CITY CORE 2050 Phase 1 January to July 2018 A public conversation about challenges and opportunities A preliminary

More information

MAGALIESBURG DEVELOPMENT INITIATIVE (MDI)

MAGALIESBURG DEVELOPMENT INITIATIVE (MDI) INTRODUCTION The recently launched Magaliesburg Development Initiative (MDI) is a combination of technical and professional input based on an approved municipal precinct plan, a deliberate emphasis on

More information

Central City District What we heard

Central City District What we heard What we heard Vision to 2056 and Priorities Governance and implementation Infrastructure and funding The vision for a metropolis of three cities, and the 30 minute city. Feedback requested: Clearer communication

More information

Hobart A Strategic Framework

Hobart A Strategic Framework Hobart 2025 A Strategic Framework Adopted by the Hobart City Council 15 October 2007 Table of Contents Introduction...2 Vision and Future Directions...3 FD1 Offers opportunities for all ages and a city

More information

QUEEN S WHARF BRISBANE PRIORITY DEVELOPMENT AREA PROPOSED DEVELOPMENT SCHEME AILA COMMENTS

QUEEN S WHARF BRISBANE PRIORITY DEVELOPMENT AREA PROPOSED DEVELOPMENT SCHEME AILA COMMENTS Section Heading Section Number Background 2.1 Background Instruction Include (but stated as extrinsic to the PDS) strategic context for the declaration of the PDA publicly accessible link to Master Planning,

More information

Inspiring Technovation

Inspiring Technovation 1 2 Table of content List of table and figures... Executive summary... 1. Introduction... 2. Material and methods... 3. Results... 3.1 Today s facts about Versailles: a diagnostic approach... 3.1 Vision

More information

Whitemarsh Comprehensive Plan Update: Housing & Land Use. Public Workshop #3: September 20, 2018

Whitemarsh Comprehensive Plan Update: Housing & Land Use. Public Workshop #3: September 20, 2018 Whitemarsh Comprehensive Plan Update: Housing & Land Use Public Workshop #3: September 20, 2018 Agenda Welcome Process Recap What We ve Heard The Plan Framework Review of Recommended Actions Land Use Housing

More information

PDA SUBMISSION: Queen s Wharf, Brisbane (DEV2017/846)

PDA SUBMISSION: Queen s Wharf, Brisbane (DEV2017/846) PDA SUBMISSION: Queen s Wharf, Brisbane (DEV2017/846) Date:: 17 October 2017 Contact Officer: Jonathon Fisher Chief Executive Officer Email: heritage@nationaltrustqld.org Phone: 07 3223 6666 NATIONAL TRUST

More information

It Takes A Village.. Preserving Rural Character In Standish

It Takes A Village.. Preserving Rural Character In Standish It Takes A Village.. Preserving Rural Character In Standish A Public Workshop Hosted by Conservation and Open Space Plan Committee & Standish Corner Village Implementation Committee June 12, 2008 Desired

More information

Ashbridges Bay Erosion and Sediment Control Project

Ashbridges Bay Erosion and Sediment Control Project Ashbridges Bay Erosion and Sediment Control Project Project Brief Overview Toronto and Region Conservation Authority, in partnership with the City of Toronto, intends to carry out remedial erosion control

More information

Lynn Waterfront Master Plan

Lynn Waterfront Master Plan Lynn Waterfront Master Plan DECEMBER ALTERNATIVES PRESENTATION City of Lynn / EDIC ZHA / GEI Work Schedule June Kick-Off June September Site Analysis & Property Owner / Stakeholder Meetings September Analysis

More information

CENTRAL BEDFORDSHIRE COMMITTED TO WORKING TOGETHER WITH LOCAL COMMUNITIES

CENTRAL BEDFORDSHIRE COMMITTED TO WORKING TOGETHER WITH LOCAL COMMUNITIES WELCOME Thank you for coming to our consultation event to find out more about our emerging proposals for Hayfield Park, a residential development jointly promoted by the Hayfield Consortium: Martin Grant

More information

Creating a culture of Place Making

Creating a culture of Place Making Place Making Creating a culture of Place Making People and place come first; start with the community not the experts Develop and allow collaborative, inter-disciplinary approaches & processes Be open

More information

Tauranga City Centre Spatial Framework

Tauranga City Centre Spatial Framework Tauranga City Centre Spatial Framework Stakeholder Engagement Workshop 15 October 2015 Project Design Team Beca & LandLAB Our team Henry Crothers (LandLab) Landscape Architect/Urban Designer Urban and

More information

SUBJECT: Proposed Downtown Mobility Hub Precinct Plan and Proposed Official Plan Policies

SUBJECT: Proposed Downtown Mobility Hub Precinct Plan and Proposed Official Plan Policies Page 1 of Report PB-81-17 SUBJECT: Proposed Downtown Mobility Hub Precinct Plan and Proposed Official Plan Policies TO: FROM: Committee of the Whole Planning and Building Department Report Number: PB-81-17

More information

POLICY The Trillium Park Master Plan was approved by the Board on April 4, 2012.

POLICY The Trillium Park Master Plan was approved by the Board on April 4, 2012. TO: FROM: SUBJECT: Date: June 2, 2014 Board Members Vancouver Park Board General Manager Parks and Recreation Proposed Trillium North Park Artists Garden RECOMMENDATION THAT the Board approve the new arts-focused

More information

City Center Neighborhood Plan

City Center Neighborhood Plan [1] City Center Neighborhood Plan As adopted by Ordinance No. 2014-09-049 and amended by Ordinance Nos. Formerly CBD Neighborhood as adopted by Ordinance No. 8868 and amended by Ordinance Nos. 8946, 9693,

More information

Cold Lake Marina Master Plan

Cold Lake Marina Master Plan Cold Lake Marina Master Plan Intro to Team Moffatt & Nichol is recognized throughout the world for our role in the revitalization and redevelopment of urban waterfronts, including the evolution of modern

More information

2.0 Urban Design Concepts

2.0 Urban Design Concepts 0 Urban Design Concepts Urban Design Concept diagrams The Waterfront Axis The Park Axis The Wharf Axis Waterfront Precincts 0.1 The Four Key Concepts: This Concept for the Wynyard Quarter establishes four

More information

Public Workshop #2 October , Welcome. Former Kingston Penitentiary & Portsmouth Olympic Harbour

Public Workshop #2 October , Welcome. Former Kingston Penitentiary & Portsmouth Olympic Harbour Public Workshop #2 October 12 + 13, 2016 Welcome Former Kingston Penitentiary & Portsmouth Olympic Harbour Cataraqui Golf and Country Club Portsmouth Avenue St. Lawrence College Sir John A. Macdonald Blvd

More information

Online Survey Results 1 Port Street East

Online Survey Results 1 Port Street East Online Survey Results 1 Port Street East Inspiration Port Credit is about envisioning a bright, new future for the Port Credit waterfront. Through an online survey in the fall of 2014, we asked what the

More information

SUBJECT: GO Station Mobility Hubs Preferred Concepts: Aldershot GO, Burlington GO and Appleby GO. Planning and Development Committee - Public Meeting

SUBJECT: GO Station Mobility Hubs Preferred Concepts: Aldershot GO, Burlington GO and Appleby GO. Planning and Development Committee - Public Meeting Page 1 of Report PB-76-17 SUBJECT: GO Station Mobility Hubs Preferred Concepts: Aldershot GO, Burlington GO and Appleby GO TO: FROM: Planning and Development Committee - Public Meeting Planning and Building

More information

ELK GROVE GENERAL PLAN VISION

ELK GROVE GENERAL PLAN VISION 2-1 CHAPTER 2: 2-2 CREATING OUR The Community Vision for Elk Grove, expressed through a Vision Statement and a series of Supporting Principles, is a declaration of the kind of community that Elk Grove

More information

Parks Master Plan Implementation: Phase I Waterfront Use and Design REPORT #: September 7, 2016 File #

Parks Master Plan Implementation: Phase I Waterfront Use and Design REPORT #: September 7, 2016 File # 0 'O DI Lan-171-14 1 - THE CORPORATION OF THE TOWN OF COBOURG..,. STAFF REPORT TO: FROM: Mayor and Members of Council Dean A. Hustwick, Director of Recreation and Culture DATE OF MEETING: Committee of

More information

CHAPTER 2: PLANNING PRINCIPLES

CHAPTER 2: PLANNING PRINCIPLES CHAPTER 2: PLANNING PRINCIPLES 2 Comprehensive Principles The following overarching Principles provide the basis for the goals and policies included in the Mendocino County General Plan. These Principles

More information

The Chinese University of Hong Kong Campus Master Plan Stage 3 Stakeholders' Engagement Report

The Chinese University of Hong Kong Campus Master Plan Stage 3 Stakeholders' Engagement Report The Chinese University of Hong Kong Campus Master Plan Stage 3 Stakeholders' Engagement Report CONTENTS 1.0 OVERVIEW... 2 2.0 KEY FINDINGS... 3 2.1 Conserving Places of Value... 3 2.2 Places for Academic

More information

Public Open House. Overview of the Downtown Plan Official Plan Amendment April 23, 2018

Public Open House. Overview of the Downtown Plan Official Plan Amendment April 23, 2018 Public Open House Overview of the Downtown Plan Official Plan Amendment April 23, 2018 1 A 25-Year Plan for Downtown To ensure growth contributes positively to Toronto s Downtown as a great place to live,

More information

Statement of. Planning Intent. Mick Gentleman MLA Minister for Planning

Statement of. Planning Intent. Mick Gentleman MLA Minister for Planning Statement of Planning Intent 2 015 Mick Gentleman MLA Minister for Planning Minister s message As Minister for Planning, I would like Canberra to be a city renowned not only for its liveability, but its

More information