Route Alignment Options Summary Report

Size: px
Start display at page:

Download "Route Alignment Options Summary Report"

Transcription

1 Brechfa Forest Connection Project February 2014

2

3 Summary report 1. RSK Environment Ltd (RSK) was commissioned by Western Power Distribution (WPD) to provide environmental consultancy support services for the connection of three proposed wind farms in Carmarthenshire to the electricity distribution network. RSK are advising WPD on the selection of a route for the proposed 132,000 kilovolt (132kV) overhead line (OHL) to connect three proposed wind farms at Brechfa Forest West 1, Bryn Llywelyn 2 and Brechfa Forest East 3, to a common grid connection point near Llandyfaelog, south of Carmarthen (the scheme). 2. This document is a summary of the Route Alignment Options Report (January 2014), which records the process undertaken to develop possible route alignment options, each 300m wide, within the preferred route corridors. Background and work completed in previous stages 3. The work undertaken to date has been carried out in a structured manner involving the following main stages (see Figure 1). Stage 1a: Primary environmental constraints review, which defined the project and the study area (area of search) and identified important environmental constraints to the installation of an OHL. Stage 1b: Primary technical constraints review, which identified potential physical or practical engineering constraints to the scheme, such as existing or planned infrastructure. Stage 2a: Route corridor options identification and appraisal, which involved desk-based review and site evaluation to identify broad route corridors that could accommodate the necessary OHL connections between the three proposed wind farms and the likely grid connection 1 Consented project 2 Planning appeal pending determination 3 Consented project Page 1 of 12

4 point. Stage 2b: Identification of the preferred route corridors, which appraised the various corridor options brought forward from Stage 2a and determined a preferred broad corridors for the connections (see Figure 2). 4. The process to select the preferred route corridors in Stage 2b was reported in the Route Corridor Selection Report (December 2013). 5. The work described in this summary report is that undertaken in Stage 3a: Identification of route alignment options, which involved development of feasible route alignments (each 300m wide to allow flexibility in choosing a final alignment) within the preferred route corridors. 6. Following consultation on the identified options, the work will progress to Stage 3b: Selection of the preferred route alignment, which will review the options shortlisted at Stage 3a to determine a preferred alignment, which will then be subject to formal EIA procedures. Stage 3a: Identification of route alignment options 7. During Stage 3a, the design development work has been progressed to identify route alignment options within the preferred route corridors that will meet the overall project objective of providing an efficient, coordinated and economic grid connection which, on balance and where possible, results in the least disturbance to the receiving natural and built environment and those who live and work within it. 8. The approach taken in Stage 3a was a combination of desk-based work, using tools such as GIS and Google Earth, based on information gathered during earlier stages of the study, including information gathered during Stage 1 Consultation, and field work to check that information and allow refinement of the options. Design workshops involving engineering and environmental specialists were held to discuss and refine various options based on potential lines of least resistance (i.e. route options that optimise Page 2 of 12

5 social and environmental outcomes as well as technical and economic considerations). 9. The main assumptions in our approach to the identification of route alignment options were as follows: The preferred route corridors from Stage 2b would be taken as the starting point; The basic principles that were applied to the identification of route corridors, such as the Holford Rules, would also apply to the identification of route alignments within the preferred corridors; Modifications or additions to the preferred route corridors 4 would be permissible if substantiated with sound reasons for instance, flexibility would be allowed for an alignment option to deviate outside a previously identified corridor if that would offer a better overall solution than an alignment wholly within a previously identified corridor; and Route alignments were identified that were based on feasible options for an OHL. However, potential mitigation options such as undergrounding of a section of OHL would be considered in order to develop an acceptable final alignment. Consideration of the need to mitigate, and the details of any specific mitigation measures, will be confirmed after Stage 2 Consultation, when the final route alignment is chosen. 10. During the Stage 3a work, various alignment options were identified, initially considering engineering issues related to ease and practicality of construction and informed by the avoidance of known environmental constraints. Preliminary route alignment options were then reviewed by the project team specialists applying professional judgement. The initial options were amended and new options were put forward for consideration. 4 Two minor modifications to the corridor boundary were made in E1 and E2 as it was recognised they may provide a better overall solution. Page 3 of 12

6 11. The evaluation of the preliminary alignment options involved a range of factors including: Physical factors (e.g. geology, landform/ land use type); Landscape and visual aspects; Ecological aspects including habitat information and protected species records; Cultural heritage aspects such as impact on the setting of key resources; Flood risk and hydrology; Areas of peat deposits and historic and active landfills; and Development Plan allocations and recent planning applications. 12. All preliminary route alignment options had to be feasible such that an engineered OHL alignment could be installed within the 300m wide route alignment, taking into account various engineering factors such as: Alignments that would achieve, where practicable, the most direct route (i.e. the shortest route length); Reducing the design and construction complexity, for instance: minimising the need for different pole types; minimising the height of the poles (and associated materials) needed; minimising route deviations (especially where angle structures/stays, etc. may be required); meeting accepted engineering tolerance such as achievable span lengths. Consideration of topography (e.g. slope steepness, change in gradients); Minimising the number of crossings (e.g. rivers, transport links, pipelines, other electrical infrastructure); Page 4 of 12

7 Retaining suitable set-back or buffer distances from built-up areas and avoiding conflicts with other infrastructure (e.g. other OHLs, wind turbines, landfills, airports/ flight paths, etc.); and Consideration of construction phase issues such as ease of access to the route, amount of site preparation required (e.g. minimal tree felling 5 ), anticipated ground conditions/ foundation requirements; and associated costs or possibility of time delay. 13. Where practicable, the environmental and engineering teams visited critical parts of each preliminary route alignment to confirm the existence or absence of potential constraints and to ensure that the resulting OHL alignment options would all be possible to construct. 14. With regard to a preliminary route alignment through preferred corridor E1, initial engineering work indicates that construction would be very challenging. Should an alignment option be taken forward within this corridor then its construction will entail substantial tree felling and the possible need for bespoke metal gantry designs or strengthened wood pole structures needed for the m span lengths required to cross steep sided valleys. Removal of tree stumps for construction would be required and is difficult due to the presence of steep slopes with poor access. The maintenance of a line would be very difficult through this corridor and will also require significant resilience tree cutting throughout its lifetime. 15. A preliminary route alignment through the River Cothi Special Landscape Area requires careful routing and consideration of span lengths and steep valley slopes. The detail surrounding this is being investigated further and this and the information that comes out from Stage 2 consultation will assist in determining the appropriateness of a final route alignment in this area. 16. The preliminary alignment options were reviewed in the context of existing physical and environmental constraint information, mapping and aerial photography (including resources such as Google Earth) as well as visits to 5 Where an OHL traverses an area of woodland, the cutting width required will be about 60m wide. Page 5 of 12

8 critical parts of the routes. Refinements were proposed, which in summary were related to the following: Geology and ground conditions 17. There are four areas where peat deposits may be encountered. Given the small footprint of the proposed infrastructure and the ability to vary span lengths and micro-site pole locations, it is considered that direct effects upon some of these peat areas could be avoided. Should this not be possible, construction best practice will ensure that any effects upon the areas of peat are minimised. The presence of peaty ground is therefore considered not to be an absolute constraint requiring the realignment of the preliminary route option. 18. The precise footprint of three landfills will be checked to ensure that the final alignment would not conflict with the facilities or result in an additional risk of pollution. A fourth landfill lies within the boundary of one route alignment option, however, should this be taken forward it may be possible to adjust the route of the overhead line to avoid this feature. Landscape and visual 19. Further review identified locations where the preliminary alignment options might be improved to: Minimise the elevation of the routes to ensure that any visually prominent local hilltops are avoided and that ridgelines are crossed at appropriate saddle locations; Further avoid areas of sloping ground where these are identified to be particularly visible from surrounding areas; Identify less prominent ways in which visible slopes could be climbed; Confirmation of the presence and principal aspects of residential properties to, wherever possible, avoid principal views from main frontages; and Page 6 of 12

9 Further detailed consideration of the landscape sensitivity of key locations particularly within special landscape areas including identification of any locations where the construction of an OHL is likely to be considered unacceptable. 20. The following locations were subject to particular scrutiny: The preliminary alignment of the OHL within the Towy Valley to the east of Carmarthen this was checked from a number of surrounding and sometimes elevated vantage points in the surrounding area to ensure that the alignment option would minimise any impact on the integrity of the valley landscape and special landscape area; The preliminary alignment option to the west of Pontarsais was revised to minimise visibility at sloping ground to the north; The final link to the Bryn Llywelyn Substation was amended to avoid impacts on the open moorland to the east or valley landscape to the west; Amendments were made to alignments in the vicinity of Brechfa village that would minimise visual effects on the settlement; and Careful consideration was given to any preliminary alignment options along or crossing the route of the River Cothi. Ecology 21. The preliminary alignment options were reviewed to understand their possible ecological effect. Given that the nature of the project will, in places, require clearance of trees under the OHL, the effects on woodland and its associated species are likely to be greater than the effects where the route passes through grasslands (where only the footprint of the wooden poles could cause a direct long-term effect on habitats). One of the key priorities in selecting the preliminary route alignment options was therefore to avoid woodland wherever possible, in particular avoiding ancient semi-natural Page 7 of 12

10 woodland (ASNW). The preliminary route alignment options were reviewed to achieve alignment options that would where possible avoid: Ancient semi-natural woodland; Peatland habitats; Semi-improved grasslands; and Linear habitats. Cultural Heritage 22. The main issues taken into account in refinement of the preliminary route alignment options were to avoid any physical effects on designated receptors, or any effects resulting from changes within their settings. The designated receptors considered include Scheduled Monuments, Listed Buildings, Conservation Areas, Registered Parks and Gardens, and Registered Landscapes of Historic Interest. To remove or reduce potential adverse effects, consideration was given to: Avoiding crossing or oversailing receptors; Maximising the setback distance from receptors Taking advantage of screening by terrain and filtering from existing vegetation; Avoidance of prominent/ dominant positioning in the landscape (e.g. breaking the skyline, on high ground, etc.); and Respecting the existing boundaries between historic landscape zones. 23. The preliminary alignment options have been developed with consideration for the above constraints and in particular the following potential cultural heritage issues were considered in the review of preliminary route alignment options: East of Gwernogle, the preliminary route alignment option passes two Page 8 of 12

11 Listed Buildings (one a church) on the road at Nant-y-Waun. Consideration should be given to maximising the distance of the final alignment from these buildings; The preliminary route alignment option in corridor E2 passes a Listed Building on the B4310 west of Abergorlech but topography and vegetation in this area should be sufficient to screen an OHL alignment; The preliminary route alignment option has been adjusted southwards where it passes a Listed Building at Forest. Keeping the final alignment to the south would reduce the potential for adverse effects on that receptor; A preliminary route alignment option south of Brechfa was dropped in favour of a more southerly option avoiding a pair of Listed Buildings on the B4310 (Brechfa House and its stables); The final alignment will be adjusted to avoid crossing directly over a scheduled cairn north of Caeglas and Cwrt Farm; The preliminary western preliminary route alignment option around Alltwalis was adjusted to allow greater setback from the western fringes of the historic settlement; Close to Rhydargaeau, the preliminary route alignment option was adjusted to the west to provide sufficient width to enable a better final alignment at this point; In the section approaching the north of Carmarthen (Peniel to the River Towy), the preliminary route alignment option was shifted slightly further from the Listed Building at NGR ; Sufficient setback has been allowed for the final route alignment option near the A485 Dolgwili roundabout to reduce potential adverse effects on a Listed Building at this location; East of Carmarthen the preliminary route alignment passes by a Listed Page 9 of 12

12 Building near Llangunnor but topography and vegetation in this area should be sufficient to screen an OHL alignment; and The preliminary route alignment option to the southern connection point has allowed for sufficient setback from the church at Llandyfaelog. Flood risk and hydrology 24. Avoidance of flood plains and watercourses (main rivers as well as minor watercourses and drainage ditches) is preferable, however it is acknowledged that in many cases they are not possible to avoid. The preliminary route option has considered the location of the flood zones and subsequent stages in the planning of the alignment will aim to ensure there is no impact on the existing hydrology and function of the floodplains. 25. It is preferable that pole positions are located outside of the 8m easement zone associated with main rivers. Any associated constructions compounds, works and excavated material should be stored out of the flood zone, where possible. This is again a more detailed matter for consideration in the planning of the final alignment. 26. The flood storage cells along the River Towy are located to the east of the A485 and are avoided by the preliminary alignment route however construction work should ensure that the effectiveness of this zone is not compromised. Planning 27. A desk-based review of relevant development plans and other sources was undertaken to identify existing and proposed land use allocations, and existing planning applications and permissions that have potential to influence the location of the preliminary route alignment options. The focus of the exercise was on areas of proposed development, although land uses such as recreation areas and conservation areas were also noted. Alignment options were refined to take these identified areas into account. Page 10 of 12

13 Final refinements to alignment route options 28. The review and refinement process resulted in many possible and feasible OHL alignment options, each lying within each of the identified 300m wide route alignment options. This improved the confidence that the outcome of Stage 3a has resulted in feasible 300m wide route alignment options for later evaluation. 29. The Stage 3a process has resulted in the identification, refinement and verification of route alignment options. The preliminary route alignment options (shown shaded in grey) are compared with the final refined alignment options (shown outlined in green) in Figures 3 and 4. These plans are referenced with numbers to indicate the main areas where the alignment options have been adjusted, as explained in the table below. Reference Location Proposed adjustment 1 Bancycapel An alignment south east of Bancycapel that would have followed a lower lying route in a valley to avoid the more elevated plateau areas to the north west of this settlement was rejected due to likely effects on woodland and ecological interests in the valley. 2 A48 Alignment discounted in favour of a route to the east, considered to have less impact on residential properties. 3 Towy Crossing Alignment adjusted to the west 4 Peniel On site checks suggested that a route slightly further west of Peniel would have less impact on the valley landscape in this area. 5 Pontarsais Alignment option to the west of Pontarsais was rejected due to potential visibility of sloping ground and prominent hill landform to the north. 6 Bryn Llywelyn link The final link to the Bryn Llywelyn Substation was realigned to avoid impacts on the open moorland to the east or valley landscape to the west. 7&8 Brechfa Identification of other OHL alignments in the vicinity of Brechfa village that would minimise visual effects on the settlement and follow a less elevated route. 9 Cothi Valley Route across the Cothi Valley was rejected due to impact on sensitive, narrow v shaped section of the valley in the SLA and due to potential visibility on elevated sloping ground to the south east in sensitive scenic views from just east of Brechfa village. The new route provides two options that would allow Page 11 of 12

14 a route avoiding ancient semi-natural woodland.. Future stages 30. Route alignment options within the preferred route corridors have been identified and the reasoning behind the selection has been described in the Route Alignment Options Report. The options will be subject to consultation in early 2014 with statutory consultees, elected representatives, local community groups and the public. 31. Following consultation, WPD will decide on their preferred route alignment and this will be subject to formal Environmental Impact Assessment in order to develop a final design that avoids, as far as possible, adverse effects on people and the environment. The scope and coverage of this assessment work will be agreed in advance with the Planning Inspectorate. 32. Formal consultation on the final design and the Environmental Statement will take place in autumn 2014 and WPD expects to submit their application to the Planning Inspectorate at the end of Page 12 of 12

Rannoch 132 / 33 kv Substation Extension

Rannoch 132 / 33 kv Substation Extension Who we are Scottish and Southern Energy Power Distribution is part of the SSE plc group of companies. We own, maintain and invest in the networks in the north of Scotland the electricity transmission network

More information

Barvills Solar Farm Environmental Statement Non-Technical Summary

Barvills Solar Farm Environmental Statement Non-Technical Summary Barvills Solar Farm Environmental Statement Non-Technical Summary 13 March 2015 Produced for Prepared by St John s House Queen Street, Manchester M2 5JB Contents Contents... 2 1 Introduction... 3 1.1 Development

More information

9 Archaeology & Cultural Heritage

9 Archaeology & Cultural Heritage High Clachaig Wind Farm Scoping Report Page 56 9 Archaeology & Cultural Heritage 9.1 Introduction Cultural heritage in this context means the above- and below-ground archaeological resources, built heritage,

More information

E16: MAINTENANCE OF LANDSCAPED AREAS

E16: MAINTENANCE OF LANDSCAPED AREAS HIGH SPEED TWO INFORMATION PAPER E16: MAINTENANCE OF LANDSCAPED AREAS This paper outlines the proposed approach to the maintenance of landscaped areas created for HS2 Phase One. It will be of particular

More information

The Place Solar Farm

The Place Solar Farm The Place Solar Farm Environmental Statement Non-Technical Summary 28 August 2014 Produced for Prepared by St John s House Queen Street, Manchester M2 5JB Contents Contents... 2 1 Introduction... 3 1.1

More information

GUIDELINES FOR THE ROUTEING OF NEW HIGH VOLTAGE OVERHEAD TRANSMISSION LINES

GUIDELINES FOR THE ROUTEING OF NEW HIGH VOLTAGE OVERHEAD TRANSMISSION LINES The Holford Rules Guidelines on overhead line routeing were first formulated in 1959 by Sir William later Lord, Holford, who was a part-time member of the CEGB. National Grid has reviewed these guidelines,

More information

7. The Landscape. 7.1 Introduction. Environmental Impact Statement (EIS) Scoping Report

7. The Landscape. 7.1 Introduction. Environmental Impact Statement (EIS) Scoping Report 7. The Landscape 7.1 Introduction The purpose of this section of the EIS Scoping Report is to describe the scope of work and methods to be applied in the identification and assessment of landscape and

More information

Grantham Southern Quadrant Link Road Environmental Statement

Grantham Southern Quadrant Link Road Environmental Statement Grantham Southern Quadrant Link Road Environmental Statement Non Technical Summary Introduction Lincolnshire County Council (LCC) is submitting a planning application for the proposed implementation of

More information

University Park, Worcester Non Technical Summary December 2011

University Park, Worcester Non Technical Summary December 2011 University Park, Worcester Non Technical Summary December 2011 Introduction UW Wrenbridge LLP, a Joint Venture Company of the University of Worcester and Wrenbridge Land Ltd (the Applicants ) intend to

More information

Replacement Golf Course Facilities and Residential Development, Churston. Environmental Statement Non-Technical Summary

Replacement Golf Course Facilities and Residential Development, Churston. Environmental Statement Non-Technical Summary Replacement Golf Course Facilities and Residential Development, Churston Environmental Statement Non-Technical Summary July 2011 Reproduced from the Ordnance Survey s map with the permission of the Controller

More information

Longhorsley Neighbourhood Plan

Longhorsley Neighbourhood Plan Site Assessment 1. The availability of the site 1.1 Is the land owner willing for their site to be made available for development? 1.2 If yes, do you have any written evidence to back this up? Planning

More information

LAND AT WEST YELLAND. Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP

LAND AT WEST YELLAND. Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP LAND AT WEST YELLAND Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP May 2014 Quality Management Issue/revision Issue 1 Revision 1 Revision 2 Revision 3 Remarks Draft FINAL Date

More information

Public Consultation. Land at Monks Farm, North Grove. Welcome

Public Consultation. Land at Monks Farm, North Grove. Welcome Welcome Welcome to our public exhibition for development on Land at Monks Farm, orth Grove. Gallagher Estates and Gleeson Strategic Land are preparing an outline planning application for new homes, open

More information

PANSHANGER QUARRY, Hertfordshire

PANSHANGER QUARRY, Hertfordshire PANSHANGER QUARRY, Hertfordshire Proposed enhanced restoration of Phases F & H Briefing Note 1 March 2015 INERT (INACTIVE) RESTORATION MATERIALS, CONTROLS AND OPERATIONS 1 Introduction This briefing note

More information

Genex Kidston Connection Project: Draf t Environmental Assessment Report Powerlink Queensland

Genex Kidston Connection Project: Draf t Environmental Assessment Report Powerlink Queensland : Draf t Environmental Assessment Report Powerlink Queensland Chapter 14 \\autsv1fp001\projects\605x\60577456\6. Draft Docs\6.1 Reports\4. Compiled draft 17 September\Covers\Chapters\Ch 14.docx Rev ision

More information

Dorenell Wind Farm 132 kv Grid Connection

Dorenell Wind Farm 132 kv Grid Connection Who We Are Scottish and Southern Energy Power Distribution is part of the SSE plc group of companies. We own, maintain and invest in the electricity networks in the north of Scotland the electricity transmission

More information

3. Highway Landscaping Assessment

3. Highway Landscaping Assessment Guidelines for Highway Landscaping 3-1 3. Highway Landscaping Assessment 3.1 Introduction This section outlines the steps necessary to assess the highway landscaping component of a state highway construction

More information

TIDAPA Structure Plan

TIDAPA Structure Plan TIDAPA Structure Plan Prepared by Tract Consultants 28 MARCH 2017 0217-0074 Table of Contents 01 STRATEGIC CONTEXT Executive Summary Regional Context Page 3 Page 4 02 LOCAL CONTEXT Aerial Photograph Local

More information

Our approach to the design and routeing of new electricity transmission lines

Our approach to the design and routeing of new electricity transmission lines Our approach to the design and routeing of new electricity transmission lines 2012 National Grid s job is to connect people to the energy they use to warm and light their homes, to connect factories and

More information

APPENDIX 1: SCOPED ENVIRONMENTAL IMPACT STATEMENT (EIS) FORM

APPENDIX 1: SCOPED ENVIRONMENTAL IMPACT STATEMENT (EIS) FORM APPENDIX 1: SCOPED ENVIRONMENTAL IMPACT STATEMENT (EIS) FORM This form is intended for use by applicants (primarily private landowners) who need to conduct a Scoped EIS in support of minor development

More information

Reserved Matters application for a site that straddles the boundary between CBC and BBC

Reserved Matters application for a site that straddles the boundary between CBC and BBC BBC APPLICATION 15/02682/MAR NUMBER CBC APPLICATION CB/15/04294/RM NUMBER LOCATION Wixams Land at former storage depot, Bedford Road, Wilstead Bedfordshire PROPOSAL Reserved Matters Application for Strategic

More information

List of Policies. SESPlan. None applicable. Consolidated Scottish Borders Local Plan 2011: POLICY G1 - QUALITY STANDARDS FOR NEW DEVELOPMENT

List of Policies. SESPlan. None applicable. Consolidated Scottish Borders Local Plan 2011: POLICY G1 - QUALITY STANDARDS FOR NEW DEVELOPMENT List of Policies Local Review Reference: 15/00021/RREF Planning Application Reference: 15/00616/FUL Development Proposal: Installation of 16no solar photovoltaic (PV) panels to roof Location: Raebank,

More information

Highway Alignment and Route Location Survey

Highway Alignment and Route Location Survey CHAPTER 2 Highway Route Surveys and Location Introduction To determine the geometric features of road design, the following surveys must be conducted after the necessity of the road is decided. Type of

More information

Wind energy development in the South Pennines landscape

Wind energy development in the South Pennines landscape Wind energy development in the South Pennines landscape Programme for today Background Policy context South Pennines landscape Impacts of wind energy development The South Pennines Wind Energy Landscape

More information

Plumpton Neighbourhood Development Plan Revised Pre Submission Document - Regulation 14 Consultation

Plumpton Neighbourhood Development Plan Revised Pre Submission Document - Regulation 14 Consultation REPRESENTATIONS... Plumpton Parish Council Plumpton Neighbourhood Development Plan Revised Pre Submission Document - Regulation 14 Consultation Representations submitted on behalf of: Cala Homes (South

More information

Thornton Road, Pickering Environmental Statement Non-Technical Summary. January 2016

Thornton Road, Pickering Environmental Statement Non-Technical Summary. January 2016 Thornton Road, Pickering Environmental Statement Non-Technical Summary January 2016 EIA Quality This Environmental Statement, and the Environmental Impact Assessment (EIA) carried out to identify the significant

More information

BREEDON NORTHERN LIMITED

BREEDON NORTHERN LIMITED Non Technical Summary CONTENTS 1 INTRODUCTION... 1 2 SITE DESCRIPTION... 1 3 DESCRIPTION OF THE DEVELOPMENT... 6 4 NEED FOR THE DEVELOPMENT... 8 5 KEY ISSUES CONSIDERED IN THE ENVIRONMENTAL IMPACT ASSESSMENT...

More information

- - - Key Characteristics

- - - Key Characteristics S23 Dyffryn Dysynni Reproduced from the Ordnance Survey map with the permission of Ordnance Survey on behalf of the Controller of Her Majesty s Stationery Office, Crown copyright Licence No. 100023387

More information

Environmental Impact Assessment

Environmental Impact Assessment Environmental Impact Assessment Environmental impact assessment (EIA) is the process of systematically drawing together an assessment of the likely significant environmental effects of a development project.

More information

TRCA Field Staking Protocol December 2016

TRCA Field Staking Protocol December 2016 Page 1 of 6 TRCA Field Staking Protocol December 2016 This Protocol describes TRCA staff s current practice for field staking the physical top of bank, the physical toe of slope, and the limit of existing

More information

Request for a Scoping Opinion by Provectus. Proposed Surface Mining of Coal on Land west off the A61, Hill Top Farm, Clay Cross, Derbyshire

Request for a Scoping Opinion by Provectus. Proposed Surface Mining of Coal on Land west off the A61, Hill Top Farm, Clay Cross, Derbyshire Request for a Scoping Opinion by Provectus Proposed Surface Mining of Coal on Land west off the A61, Hill Top Farm, Clay Cross, Derbyshire January 2012 Contents 1 Introduction & Background... 1 2 Site

More information

PROPOSED RESIDENTIAL DEVELOPMENT LAND AT GREEN LANE, YARM

PROPOSED RESIDENTIAL DEVELOPMENT LAND AT GREEN LANE, YARM PROPOSED RESIDENTIAL DEVELOPMENT LAND AT GREEN LANE, YARM PUBLIC CONSULTATION YOUR VIEW MATTERS TO US LOCATION PLAN Thank you for taking the time to read this information leaflet regarding a proposed residential

More information

Lower Sensitivity. VS Classification Level 2: Exposed Upland/Plateau

Lower Sensitivity. VS Classification Level 2: Exposed Upland/Plateau S04 Moel Hebog Reproduced from the Ordnance Survey map with the permission of Ordnance Survey on behalf of the Controller of Her Majesty s Stationery Office, Crown copyright Licence No. 100023387 Location

More information

AMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON

AMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON AMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON Subject: Boyne Survey Secondary Plan and Related Official Plan Amendments The following text and schedules constitute Amendment No. 30 to the

More information

Statement of Community Involvement LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE

Statement of Community Involvement LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE CONTENTS Page 1. Introduction 3 2. Pre-application Discussions 4 3. The Consultation Process 5 4. Consultation Feedback 7 5. Responses to Consultation Feedback

More information

Babergh and Mid Suffolk Joint Draft Local Plan Consultation, August 2017, Public Consultation

Babergh and Mid Suffolk Joint Draft Local Plan Consultation, August 2017, Public Consultation Babergh and Mid Suffolk Joint Draft Local Plan Consultation, August 2017, Public Consultation Having reviewed the documents, the Society has made the following response: Housing Delivery Q 7. Do you agree

More information

Assessing the impact of smallscale wind energy proposals on the natural heritage

Assessing the impact of smallscale wind energy proposals on the natural heritage Scottish Natural Heritage Assessing the impact of smallscale wind energy proposals on the natural heritage Guidance March 2016 Version 3 1 Contents 1. Introduction. 3 2. Encouraging a spatial approach

More information

TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997

TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997 TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997 APPEAL AGAINST REFUSAL OF PLANNING PERMISSION FOR CONSTRUCTION OF WIND FARM, CONSISTING OF ERECTION OF 12 NO. WIND TURBINES, HEIGHT OF 70 METRES TO HUB, ASSOCIATED

More information

Lower Sensitivity. VS Classification Level 2: Exposed Upland/Plateau

Lower Sensitivity. VS Classification Level 2: Exposed Upland/Plateau S05 Y Moelwynion Reproduced from the Ordnance Survey map with the permission of Ordnance Survey on behalf of the Controller of Her Majesty s Stationery Office, Crown copyright Licence No. 100023387 Location

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Planning and New Communities Director

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Planning and New Communities Director SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL REPORT TO: Planning Committee 9 January 2013 AUTHOR/S: Planning and New Communities Director S/2270/12/FL FEN DRAYTON 850m long flood defence embankment ranging in

More information

3.1 This evidence is based on the landscape and visual impact assessment included in Chapter 10 and Appendix I of the EIS.

3.1 This evidence is based on the landscape and visual impact assessment included in Chapter 10 and Appendix I of the EIS. LANDSCAPE & VISUAL 1 QUALIFICATIONS AND EXPERIENCE 1.1 My name is Raymond Holbeach and I am a Regional Director for RPS Planning & Environment with full responsibility for management of the RPS Belfast

More information

Cape Environmental Assessment Practitioners(Pty)

Cape Environmental Assessment Practitioners(Pty) BACKGROUND INFORMATION DOCUMENT (BID) Introduction Cape Environmental Assessment Practitioners(Pty) Ltd Reg. No. 2008/004627/07 Telephone: (044) 874 0365 First Floor, Eagles View Building Facsimile: (044)

More information

MANAGING CHANGE IN THE HISTORIC ENVIRONMENT. Historic Battlefields August 2016

MANAGING CHANGE IN THE HISTORIC ENVIRONMENT. Historic Battlefields August 2016 MANAGING CHANGE IN THE HISTORIC ENVIRONMENT Historic Battlefields August 2016 Above: Most of Culloden battlefield lay under forestry until clearance by the National Trust for Scotland in the 1980s. While

More information

Neighbourhood Planning Site Assessment Pro-forma and Guide Version 2

Neighbourhood Planning Site Assessment Pro-forma and Guide Version 2 Neighbourhood Planning Site Assessment Pro-forma and Guide Version 2 September 2014 Site HNP 006 Land East of Stanbridge Road and North of Lower Road 1. Background information Site location and use Site

More information

Environmental Impact Assessment for Waterway Restoration Projects. Chris John, Technical Director Ecus Ltd.

Environmental Impact Assessment for Waterway Restoration Projects. Chris John, Technical Director Ecus Ltd. Environmental Impact Assessment for Waterway Restoration Projects Chris John, Technical Director Ecus Ltd. Environmental Impact Assessment for Waterway Restoration Projects What is Environmental Impact

More information

INTRODUCTION. Land south of Bishopswood Lane, Tadley

INTRODUCTION. Land south of Bishopswood Lane, Tadley 0 INTRODUCTION THE SITE Introduction Gladman Developments Ltd. has successfully invested in communities throughout the UK over the past 0 years, developing high quality and sustainable residential, commercial

More information

Summary Note on Landscape and Visual Impact and Mitigation

Summary Note on Landscape and Visual Impact and Mitigation East Anglia TWO Offshore Windfarm Appendix 4.4 Summary Note on Landscape and Visual Impact and Mitigation Preliminary Environmental Information Volume 3 Document Reference EA2-DEVWF-ENV-REP-IBR- 000799_004

More information

LAND AT HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. March 2017 Our Ref: Q70433

LAND AT HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. March 2017 Our Ref: Q70433 LAND AT HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY March 2017 Our Ref: Q70433 Contents 1 INTRODUCTION AND SITE DESCRIPTION... 1 2 EIA METHODOLOGY... 5 3 ALTERNATIVES... 6 4 DESCRIPTION

More information

INTRODUCTION. Welcome to the third round of information events on the emerging Yorkshire Energy Park proposals. THE CONSULTANT TEAM WHERE IS THE SITE?

INTRODUCTION. Welcome to the third round of information events on the emerging Yorkshire Energy Park proposals. THE CONSULTANT TEAM WHERE IS THE SITE? 1 INTRODUCTION Welcome to the third round of information events on the emerging Yorkshire Energy Park proposals. This is the third round of information events that we have undertaken on the project, following

More information

volume 11 environmental assessment section 2 environmental impact assessment Part 4 ha 204/08 scoping of environmental impact assessments

volume 11 environmental assessment section 2 environmental impact assessment Part 4 ha 204/08 scoping of environmental impact assessments DESIGN MANUAL FOR ROADS AND BRIDGES volume 11 environmental assessment section 2 environmental impact assessment Part 4 ha 204/08 scoping of environmental impact assessments SUMMARY This Advice Note provides

More information

CA//16/00504/FUL. Canterbury City Council Military Road Canterbury Kent CT1 1YW. Crown copyright and database rights 2016 Ordnance Survey

CA//16/00504/FUL. Canterbury City Council Military Road Canterbury Kent CT1 1YW. Crown copyright and database rights 2016 Ordnance Survey O Scale 1:1,250 Map Dated: 09/05/2016 CA//16/00504/FUL Crown copyright and database rights 2016 Ordnance Survey 100019614 Canterbury City Council Military Road Canterbury Kent CT1 1YW AGENDA ITEM NO 13

More information

Site Assessment Technical Document Appendix A: Glossary

Site Assessment Technical Document Appendix A: Glossary Central Bedfordshire Council www.centralbedfordshire.gov.uk Site Assessment Technical Document Appendix A: Glossary July 2017 1.1.11-1 - ii Appendix A: Glossary Term Agricultural Land Classification AONB

More information

Lower Sensitivity. VS Classification Level 2: Exposed Upland/Plateau

Lower Sensitivity. VS Classification Level 2: Exposed Upland/Plateau S02 Y Carneddau Reproduced from the Ordnance Survey map with the permission of Ordnance Survey on behalf of the Controller of Her Majesty s Stationery Office, Crown copyright Licence No. 100023387 Location

More information

West of Chichester Proposals for land to the west of Centurion Way 1 Welcome Introduction

West of Chichester Proposals for land to the west of Centurion Way 1 Welcome Introduction West of Chichester Proposals for land to the west of Centurion Way Welcome Introduction Welcome to this public exhibition for Linden and Miller Homes in connection with their proposals for a 600 home mixed

More information

volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08

volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08 DESIGN MANUAL FOR ROADS AND BRIDGES volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08 glossary of terms Used in DMRB Volume 11, Sections 1 and 2 SUMMARY This

More information

SAN RAFAEL GENERAL PLAN 2040 INTRODUCTION AND OVERVIEW

SAN RAFAEL GENERAL PLAN 2040 INTRODUCTION AND OVERVIEW SAN RAFAEL GENERAL PLAN 2040 INTRODUCTION AND OVERVIEW Steering Committee Presentation February 14, 2018 Purpose of General Plan Guide land use and development decisions Coordinate transportation, infrastructure,

More information

ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville. Environmental Screening Report

ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville. Environmental Screening Report Page 1 of 18 ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville Environmental Screening Report July 2011 Page 2 of 18 Table of Contents 1.0 INTRODUCTION

More information

A payment of 1080 is due in this instance, for a meeting and follow up written response, and will be made by card over the phone.

A payment of 1080 is due in this instance, for a meeting and follow up written response, and will be made by card over the phone. JPPC ref: AG/6002 18 th September 2014 Planning Services Vale of White Horse District Council Benson Lane Crowmarsh Gifford Wallingford OX10 8ED Dear Sir/Madam REQUEST FOR PRE-APPLICATION ADVICE RE: RESIDENTIAL

More information

SUSTAINABLE MANAGEMENT

SUSTAINABLE MANAGEMENT . Sustainable Management.1 The Concept of Sustainable Management The concept of sustainable management recognises there are limits to the use of natural and physical resources and there is a need to balance

More information

Contents. Annexes. Annex 1 Process Diagram for the discharge of the DCO Requirements. Annex 2 Design Sheet Power Generation Plant

Contents. Annexes. Annex 1 Process Diagram for the discharge of the DCO Requirements. Annex 2 Design Sheet Power Generation Plant Design Principles Document December 2014 Contents Summary... 2 Purpose of this Statement... 2 Design Parameters... 2 Guidance Documents... 3 Additional Design Considerations... 3 Public involvement and

More information

UTT/16/1466/DFO GREAT DUNMOW MAJOR

UTT/16/1466/DFO GREAT DUNMOW MAJOR UTT/16/1466/DFO GREAT DUNMOW MAJOR PROPOSAL: LOCATION: APPLICANT: AGENT: Reserved matters approval for the accesses to the site and principal roads within the site including spine road following outline

More information

Comments on the proposed scope are requested from WCC/NBBC officers to be provided to SLC Rail by 25 th March 2016 and sent to

Comments on the proposed scope are requested from WCC/NBBC officers to be provided to SLC Rail by 25 th March 2016 and sent to Introduction WCC have indicated that in advance of the surveys and assessments being undertaken consultation should be undertaken with technical officers of both Warwickshire CC and Nuneaton and Bedworth

More information

Circular L8/08 2 September Water Services Investment and Rural Water Programmes Protection of Natural Heritage and National Monuments

Circular L8/08 2 September Water Services Investment and Rural Water Programmes Protection of Natural Heritage and National Monuments Circular L8/08 2 September 2008 Water Services Investment and Rural Water Programmes Protection of Natural Heritage and National Monuments 1. The purpose of this Circular is to provide local authorities

More information

Cranbrook EXPANSION ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY PRODUCED BY DAVID LOCK ASSOCIATES

Cranbrook EXPANSION ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY PRODUCED BY DAVID LOCK ASSOCIATES Cranbrook EXPANSION ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY PRODUCED BY DECEMBER 2014 CRANBROOK EXPANSION AREAS ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY Submitted in support of Outline Planning

More information

Chapter 8: Cultural Heritage Assessment

Chapter 8: Cultural Heritage Assessment Chapter 8: Cultural Heritage Assessment Cultural Heritage Assessment 8. Cultural Heritage Assessment... 2 8.1 Introduction... 2 8.2 Baseline Assessment... 2 8.3 Results / Assessment Findings... 3 8.4 Mitigation...

More information

Background Summary Report

Background Summary Report Background Summary Report May 2014 Submitted by Macaulay Shiomi Howson Ltd. In association with AMEC MMM Group Brook McIlroy Inc. Hemson Consulting Ltd. Table of Contents 1. Introduction... 1 2. Why is

More information

Kier Infrastructure and Overseas Limited Greenburn Surface Mine, Dalgig Farm Site

Kier Infrastructure and Overseas Limited Greenburn Surface Mine, Dalgig Farm Site Kier Infrastructure and Overseas Limited Greenburn Surface Mine, Dalgig Farm Site Planning application pursuant to s.42 Town and Country Planning (Scotland) Act 1997 to amend the restoration scheme Volume

More information

Examination of South Cambridgeshire Local Plan

Examination of South Cambridgeshire Local Plan Matter SC6A - Policy SS/5 Waterbeach New Town Historic England( formerly English Heritage) 874 Rep Nos 59748, 60250, 60253 Examination of South Cambridgeshire Local Plan Historic England, Hearing Statement

More information

Welcome to the Public Consultation Exhibition

Welcome to the Public Consultation Exhibition Welcome to the Public Consultation Exhibition Today is your opportunity to: Speak to the team Learn more about the project Leave feedback on the plans The Secretary of State for Transport has recognised

More information

The Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion

The Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion Mr Graham Clark Berrys Newchurch Farm Kinnersley Hereford HR3 6QQ BY EMAIL The Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion SC/2017/0001

More information

Land at BROOK STREET PROPERTIES TENCREEK FARM, LISKEARD. Environmental Statement: Non-Technical Summary

Land at BROOK STREET PROPERTIES TENCREEK FARM, LISKEARD. Environmental Statement: Non-Technical Summary BROOK STREET PROPERTIES TENCREEK FARM, LISKEARD Land at Environmental Statement: Non-Technical Summary Introduction Brook Street Properties is applying to Cornwall Council for outline planning permission

More information

Introduction. Grounds of Objection

Introduction. Grounds of Objection Planning application ref. number 18/04496/APP Planning application to Aylesbury Vale District Council for the erection of 17 dwellings and associated works to the South of Hogshaw Road Granborough. Granborough

More information

Chapter 3 Site Planning and Low Impact Development

Chapter 3 Site Planning and Low Impact Development CHAPTER 3 Site Planning and Low Impact Development Chapter 3 Site Planning and Low Impact Development 3.0 Introduction The City of Charleston requires that major residential, large commercial (>1 acre),

More information

Site ref: AS06 Site Name or Address: Murreys Court, Agates Lane

Site ref: AS06 Site Name or Address: Murreys Court, Agates Lane Site ref: AS06 Site Name or Address: Murreys Court, Agates Lane Proposed Land Use: Total Site Area (Ha): Housing 1.85 Ha Description: It is understood that the owner has no plans to dispose of the site

More information

Former RAF Sealand Site EIA

Former RAF Sealand Site EIA Praxis (Holdings) Ltd. Former RAF Sealand Site EIA Environmental Statement - Non Technical Summary February 2012 in association with P a g e 1 1. Introduction Praxis (Holdings) Ltd. is applying to Flintshire

More information

RURAL ZONE - POLICY. Rural Zone Policy. Issue: Rural Environment. Ruapehu District Plan Page 1 of 8

RURAL ZONE - POLICY. Rural Zone Policy. Issue: Rural Environment. Ruapehu District Plan Page 1 of 8 Rural Zone Policy RU2 RURAL ZONE - POLICY RU2.1 Introduction The natural resources of the rural environment in the Ruapehu District provide the basis for the existing and potential character, intensity

More information

Application for Certificate of Environmental Compatibility and Public Need

Application for Certificate of Environmental Compatibility and Public Need Application for Certificate of Environmental Compatibility and Public Need Central Hudson Gas & Electric A and C Lines Towns of Pleasant Valley, LaGrange, Wappinger, and East Fishkill Dutchess County,

More information

LAND EAST OF SUDBURY ROAD, HALSTEAD PUBLIC CONSULTATION. Proposed Residential Development

LAND EAST OF SUDBURY ROAD, HALSTEAD PUBLIC CONSULTATION. Proposed Residential Development LAND EAST OF SUDBURY ROAD, HALSTEAD PUBLIC CONSULTATION Proposed Residential Development YOUR VIEW MATTERS TO US PROPOSED RESIDENTIAL DEVELOPMENT AREA Thank you for taking the time to read this information

More information

Form to Submit Land for Residential Evidence Gathering Shepway Strategic Housing Land Availability Assessment (SHLAA) Partial Review

Form to Submit Land for Residential Evidence Gathering Shepway Strategic Housing Land Availability Assessment (SHLAA) Partial Review Form to Submit Land for Residential Evidence Gathering Shepway Strategic Housing Land Availability Assessment (SHLAA) Partial Review All organisations and individuals who wish to put forward land for consideration

More information

SEABANK 3. Interim Landscape and Design Statement

SEABANK 3. Interim Landscape and Design Statement SEABANK 3 Interim Landscape and Design Statement Prepared for: SSE plc URS Infrastructure & Environment UK Limited. Scott House Alencon Link Basingstoke Hampshire RG21 7PP UK 1 TABLE OF CONTENTS 1 INTRODUCTION...

More information

Lead Local Flood Authority SuDS Policy Statement

Lead Local Flood Authority SuDS Policy Statement Lead Local Flood Authority SuDS Policy Statement Meeting Sustainable Drainage System Standards in Hertfordshire Addendum to the Local Flood Risk Management Strategy for Hertfordshire March 2015 Contents

More information

8.0 Design and Form of Development 43/

8.0 Design and Form of Development 43/ 42/ 8.0 Design and Form of Development 43/ Rothwells Farm, Golborne/ Development Statement Figure 7. Site Constraints Key 44/ Site Boundary 360 Bus Route/Stops Existing Trees Underground Water Pipe Sensitive

More information

Woodland Conservation and the Master Plan

Woodland Conservation and the Master Plan 1 WHAT IS A MASTER PLAN? A Vision for the Future of Your Community Woodland Conservation and the Master Plan Goals Objectives Strategies 2 How Will Your Community Look? TREE PRESERVATION AND THE MASTER

More information

Derry City and Strabane District Council Planning Committee Report. Amended layout from approval A/2004/0462/F with reduction from 166 units

Derry City and Strabane District Council Planning Committee Report. Amended layout from approval A/2004/0462/F with reduction from 166 units Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 1 st February 2017 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: Full Planning application Amended

More information

Copyright Nigel Deeley and licensed for reuse under this Creative Commons Licence

Copyright Nigel Deeley and licensed for reuse under this Creative Commons Licence 1 Copyright Nigel Deeley and licensed for reuse under this Creative Commons Licence Prepared by the Neighbourhood Plan Steering Group on behalf of Garway Parish Council with assistance from 2 Table of

More information

North York Moors National Park Authority Planning Committee

North York Moors National Park Authority Planning Committee Item 8 North York Moors National Park Authority Planning Committee 12 December 2013 Consultation from Redcar and Cleveland Borough Council on proposed Wind Farm at Bank Field Guisborough 1. Purpose of

More information

Strategic Environmental Assessment Screening Report. Dublin Port Masterplan Review 2017

Strategic Environmental Assessment Screening Report. Dublin Port Masterplan Review 2017 Strategic Environmental Assessment Screening Report Dublin Port Masterplan Review 2017 Table of Contents 1 Introduction... 1 2 Purpose of the Masterplan... 2 3 Task 1.1 Pre-Screening Check... 5 4 Task

More information

TOWN AND COUNTRY PLANNING ACT 1990 (AS AMENDED).

TOWN AND COUNTRY PLANNING ACT 1990 (AS AMENDED). FAO: D. Williams Isle of Anglesey County Council Council Offices Llangefni Anglesey LL77 7TW 16 November 2017 DCRM Ref. No: WN0904-QUD-OS-LET-00002_English Dear Mr Williams TOWN AND COUNTRY PLANNING ACT

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 20.12.2017 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: A/2014/0495/F Full Construction of

More information

BRE Strategic Ecological Framework LI Technical Information Note 03/2016

BRE Strategic Ecological Framework LI Technical Information Note 03/2016 BRE Strategic Ecological Framework Technical Information Note 03/2016 September 2016 Contents 1. Introduction 2. Aims of BRE s Strategic Ecological Framework 3. How SEF is different from previous approaches

More information

SPG 1. * the northern and western sections which are open fields used for pasture and grazing;

SPG 1. * the northern and western sections which are open fields used for pasture and grazing; SPG 1 1.0 INTRODUCTION This development brief is based on the allocation of the Priors Hall site for employment and countryside recreational purposes in the Corby Borough Local Plan. The brief is intended

More information

North Wales Wind Farm Connections. Route Corridor Report

North Wales Wind Farm Connections. Route Corridor Report North Wales Wind Farm Connections Route Corridor Report May 2013 Contents Section 1.0 Section 2.0 Section 3.0 Section 4.0 Section 5.0 Section 6.0 Figures: Figure 1.1 Figure 1.2 Figure 4.1 Figure 4.2 Figure

More information

Master Environmental Servicing Plan & Secondary Plan

Master Environmental Servicing Plan & Secondary Plan East Side Lands Stage 2 1 Master Environmental Servicing Plan & Secondary Plan Public Information Centre #1 June 16, 2016 Welcome! Today s Agenda Please sign in at the front desk. 5:30 pm 6:30 pm: Open

More information

Appendix G Response to Comments

Appendix G Response to Comments Appendix G Response to Comments This appendix contains the comments received during the public circulation and comment period (May 27, 2008 to July 11, 2008). The comments have been numbered (Comment Set

More information

Response by the Wiltshire Archaeological and Natural History Society

Response by the Wiltshire Archaeological and Natural History Society Highways England Consultation A303 Stonehenge Response by the Wiltshire Archaeological and Natural History Society Background About the Society Founded in 1853 to educate the public by promoting, fostering

More information

Section 6A 6A Purpose of the Natural Features and Landscapes Provisions

Section 6A 6A Purpose of the Natural Features and Landscapes Provisions Section 6A 6A Purpose of the Natural Features and Landscapes Provisions This Chapter addresses the protection and management of natural features and landscapes within the City. The City has a number of

More information

ROCHFORD LOCAL DEVELOPMENT FRAMEWORK: Sustainability Appraisal/ Strategic Environmental Assessment. Rochford Core Strategy Preferred Options Document

ROCHFORD LOCAL DEVELOPMENT FRAMEWORK: Sustainability Appraisal/ Strategic Environmental Assessment. Rochford Core Strategy Preferred Options Document ROCHFORD LOCAL DEVELOPMENT FRAMEWORK: Sustainability Appraisal/ Strategic Environmental Assessment Non Technical Summary Rochford Core Strategy Preferred Options Document October 2008 SUSTAINABILITY APPRAISAL

More information

Powys (Mid Wales) Conjoined Windfarm Inquiry Llanbrynmair Windfarm Supplementary Environmental Information February 2014

Powys (Mid Wales) Conjoined Windfarm Inquiry Llanbrynmair Windfarm Supplementary Environmental Information February 2014 Ein cyf/our ref: Eich cyf/your ref: Ladywell House Park Street Newtown Powys SY16 1RD FAO Claire Hughes Jones Banks Solutions 21 Glendale Close Horsham West Sussex RH12 4GR Ebost/Email: carol.fielding@cyfoethnaturiolcymru.gov.uk

More information

64 Mineral Extraction Area Rules

64 Mineral Extraction Area Rules 64 Mineral Extraction Area Rules 64.1 Introduction For the purposes of this Chapter: Active Area, in relation to a Mineral Extraction Area (MEA), is that part of the Mineral Extraction Area which is owned

More information

DEFGH. Crystal Place Park. Environmental Impact Assessment (EIA) Elin Thomas and Emily Low Waterman Environmental

DEFGH. Crystal Place Park. Environmental Impact Assessment (EIA) Elin Thomas and Emily Low Waterman Environmental DEFGH Crystal Place Park Environmental Impact Assessment (EIA) Elin Thomas and Emily Low Waterman Environmental 10.12.07 EIA Presentation Content What is EIA? Legal Requirements Process Q&A Key Topics

More information