1 REPORT N O LAND NORTH OF NETHERHOUSE COPSE, FLEET ENVIRONMENTAL STATEMENT VOLUME 3:NON-TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT PUBLIC JUNE 2016

2 LAND NORTH OF NETHERHOUSE COPSE, FLEET ENVIRONMENTAL STATEMENT VOLUME 3:NON-TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT Berkeley Strategic Land Limited V1 Public Project no: Date: June 2016 WSP House London WC2A 1AF UK Tel: +44 (0) Fax: +44 (0)

3 iii Q U A L I T Y M A N A G E M E N T ISSUE/REVISION FIRST ISSUE REVISION 1 REVISION 2 REVISION 3 Remarks Date June 2016 Prepared by Robyn Chadwick Signature Checked by Pete Collins Signature Authorised by Karen McAlister Signature Project number Report number File reference Non-Technical Summary of the Environmental Statement Project No

4 iv TABLE OF CONTENTS 1 INTRODUCTION OVERVIEW WHAT IS PROPOSED TO BE BUILT? WHAT IS AN ENVIRONMENTAL IMPACT ASSESSMENT (EIA)? WHAT IS A NON-TECHNICAL SUMMARY? THE SITE WHAT IS THE SITE AND THE SURROUNDING AREA LIKE? WHY IS THE DEVELOPMENT NEEDED AND WHY IS IT BEING BUILT HERE? HOW HAS THE DESIGN EVOLVED? WHO HAS BEEN CONSULTED ABOUT THIS DEVELOPMENT? WHEN WILL THE DEVELOPMENT BE BUILT? OVERVIEW OF THE DEVELOPMENT PARAMETERS INTRODUCTION LAND USE PARAMETER PLAN RESIDENTIAL DENSITY PARAMETER PLAN BUILDING HEIGHTS PARAMETER PLAN ACCESS AND MOVEMENT PARAMETER PLANS LANDSCAPE AND ECOLOGY STRATEGY PARAMETER PLAN ENVIRONMENTAL EFFECTS OF THE PROPOSED DEVELOPMENT WILL THE EXISTING LOCAL COMMUNITY BE DISTURBED AS A RESULT OF THE CONSTRUCTION PHASE? HOW WILL THE CONSTRUCTION TRAFFIC AFFECT THOSE WHO USE THE LOCAL ROAD AND PATH NETWORKS? WILL THE PROPOSED DEVELOPMENT BENEFIT THE LOCAL ECONOMY? Non-Technical Summary of the Environmental Statement Project No

5 v 4.4 WILL THE EXISTING COMMUNITY FACILITIES BE ABLE TO ACCOMMODATE EXISTING AND NEW RESIDENTS? HOW WILL THE PROPOSED DEVELOPMENT AFFECT THE LOCAL ROAD AND FOOTPATH NETWORKS ONCE COMPLETE? WHAT WILL HAPPEN TO THE LOCAL NOISE ENVIRONMENT DURING CONSTRUCTION AND WHEN THE DEVELOPMENT IS OCCUPIED? WHAT WILL HAPPEN TO LOCAL AIR QUALITY DURING CONSTRUCTION OF THE PROPOSED DEVELOPMENT AND ONCE IT S COMPLETED? WHAT ECOLOGICAL SURVEYS HAVE BEEN UNDERTAKEN AT THE SITE AND WHAT AFFECT WILL THE PROPOSED DEVELOPMENT HAVE ON LOCAL WILDLIFE? WHAT EFFECT WILL THE PROPOSED DEVELOPMENT HAVE ON THE LANDSCAPE CHARACTER AND VISUAL AMENITY OF THE AREA? DOES THE SITE HAVE ARCHAEOLOGICAL POTENTIAL? ARE THERE ANY CONCERNS RELATING TO CONTAMINATED LAND OR GROUND CONDITIONS WITHIN THE SITE? WILL THE PROPOSED DEVELOPMENT CHANGE THE EXISTING WATER ENVIRONMENT AND WILL THERE BE INCREASED DEMAND ON WATER RESOURCES? WILL THE DEVELOPMENT INCREASE FLOODING? WHAT WILL BE THE EFFECT OF THE PROPOSED DEVELOPMENT ON THE EXISTING AGRICULTURAL USE? WHAT MEASURES WILL BE USED TO AVOID AND REDUCE THE ENVIRONMENTAL EFFECTS OF THE PROPOSED DEVELOPMENT? WHAT HAPPENS NEXT? WHO CAN I CONTACT IF I WANT SOME MORE INFORMATION? CAN I HAVE A COPY OF THE ENVIRONMENT STATEMENT OR THIS NON-TECHNICAL SUMMARY?... 32

6 1 1 INTRODUCTION 1.1 OVERVIEW Berkeley Strategic Land Ltd ( the Applicant) is seeking outline planning permission for a new residential community (the Proposed Development ). All aspects of the Development are in outline stage with the exception of the access proposals which are submitted in detail. The Proposed Development is located to the north of Crookham Village and west of Fleet as shown in Figure 1 below The Site extends to approximately ha and consists of arable fields and woodland. The Site comprises two parcels of land separated by Hitches Lane, referred to as the Eastern and Western Sites. Within the Site are two areas of Ancient Woodland: Long Copse, located in the northwest corner of the Eastern Site; and Jack Reid s Copse, located on the south eastern part of the Western Site, adjacent to Hitches Lane. A further area of Ancient Woodland, Netherhouse Copse, is located adjacent to the southern boundary of the Eastern Site. There is also a Historic Hedgerow present on the site. Figure 1: Site Location

7 2 1.2 WHAT IS PROPOSED TO BE BUILT? The Proposed Development is for a new residential community of for up to 423 residential dwellings, a community facility, associated vehicular, pedestrian and cycle access, drainage and landscape works including provision of public open space and sports pitches. Provision of country park / SANG as an extension to Edenbrook Country Park At this stage, the application does not seek planning approval for the detailed design or external appearance of any proposed buildings; these matters will be the subject of future reserved matters planning applications, to allow for a level of flexibility A series of Parameter Plans (see Figures 3 8, provided in Section 3) have been submitted for approval as part of the Planning Application which show the broad outline of the scheme The Application is also accompanied by an illustrative Masterplan which demonstrates how the development could be built out when applying the parameters as defined and described in the Application. Reserved matters planning applications will be in general accordance with the Parameter Plans (see Section 3 Overview of the Development Parameters below). 1.3 WHAT IS AN ENVIRONMENTAL IMPACT ASSESSMENT (EIA)? EIA is a process that identifies the likely significant environmental effects of a development and suggests ways in which any significant negative effects on the environment can be prevented, reduced and/or compensated. EIA requires consideration of the likely significant environmental effects which may arise during all stages of a development, including the construction works and following completion (usually referred to as operation) The Town and Country Planning (Environmental Impact Assessment) Regulations 2011 (as amended 2015) (the EIA Regulations 2011 ) require that an EIA must be undertaken before planning permission is granted for certain types of development. For the Proposed Development Hart District Council (HDC) identified the requirement for an EIA to inform the planning application. The EIA has been undertaken in accordance with the EIA Regulations 2011 and the scope of the EIA was agreed with HDC and other statutory authorities The findings of the EIA process are reported in a document called an Environmental Statement (ES). The ES is submitted with the planning application and is available on HDC s website and at the Council offices, together with the other planning application documents, for the public to view to understand the nature and form of the Proposed Development and the outcome of the EIA process. The findings of the EIA are summarised in this document The ES comprises three volumes: Volume 1 Text and Figures, which comprises the full text of the ES and supporting figures; and Volume 2 Technical Appendices where technical reports and supporting information to the ES are presented. This Non-Technical Summary forms Volume 3 of the ES A number of other Technical Reports and Plans are also submitted with the Planning Application and relevant information from those reports has informed the ES. These reports and plans include the following: Planning Statement; Design and Access Statement; Transport Assessment; Framework Travel Plan;

8 3 Flood Risk Assessment and Drainage Strategy; Landscape Design Statement; Suitable Alternative Natural Greenspace (SANG) Management Plan; Draft Construction Environmental Management Plan; Sustainability Statement; Energy Statement; and Statement of Community Involvement. 1.4 WHAT IS A NON-TECHNICAL SUMMARY? The full results of the EIA (baseline information, survey findings and technical assessments) that have been completed for the Proposed Development are presented in the ES. The findings of these studies are summarised and presented in this summary document in non-technical language This document is structured as a series of key questions and answers regarding the Proposed Development and identifies any likely significant effects and describes how such effects are to be mitigated, prevented and/or compensated by the Applicant during the construction and throughout the lifetime of the Proposed Development.

9 4 2 THE SITE 2.1 WHAT IS THE SITE AND THE SURROUNDING AREA LIKE? The Site is split into a western area and an eastern area, and comprises predominantly agricultural land, hedgerows and woodland. The land use in the surrounding area is a mix of arable and pasture farmland, interspersed by individual farmsteads, dwellings and larger settlements A number of public rights of way (PRoW) traverse the entire Site, and cycle routes in the vicinity link west Fleet with the Country Parks to the west of the town. These routes have been identified for improvement in the Fleet Town Access Plan (2011) There are no statutory designated ecological sites or listed buildings within the Site boundary. However, a non-statutory designated site is located within the Site boundary: Jack Reid s Copse Site of Importance for Nature Conservation (SINC) in the south eastern part of the Western Site, adjacent to Hitches Lane. This copse has been designated for the presence of ancient seminatural woodland. In addition, Long Copse, within the northwest corner of the Eastern site, is also classified as an area of Ancient Woodland, although is not identified as a SINC. A historic hedge is present in the western site Land uses surrounding the Western Site include Hitches Lane to the east, farmland to the south, and Edenbrook Country Park to the north. The River Hart is located adjacent to the west of the Western Site boundary, beyond which is farmland. Land uses surrounding the Eastern Site include Hitches Lane to the west, Calthorpe Park School playing fields to the north, existing residential areas of Fleet to the west, and Netherhouse Copse and farmland to the south. Further to the north of the Eastern Site are the Hart Leisure Centre and Calthorpe Park Secondary School. 2.2 WHY IS THE DEVELOPMENT NEEDED AND WHY IS IT BEING BUILT HERE? Consideration of the development of the western side of Fleet has been part of the local planning process for many years. The Site represents an opportunity for a sustainable urban extension and is considered to be a logical expansion of the town that is both well connected to the town centre, the Hart Leisure Centre and local schools, and also combines well with the nearby Edenbrook Development and the Edenbrook Country Park. These characteristics will generate a number of wider community benefits as well as contributing towards addressing housing requirements in the area Outline planning permission was granted in January 2006 for the development of the Edenbrook site (planning application reference 02/000180/OUT) for 300 dwellings, recreational uses and associated landscaping and highways. The development of Edenbrook is now nearing completion, and includes the first phase of the Edenbrook Country Park. In July 2012, approval was granted for 57 additional dwellings and associated works to the immediate west of the Edenbrook development, referred to as Edenbrook Extension (planning application reference 11/01326/MAJOR) A further planning application was submitted in November 2013 proposes a south western expansion of the Edenbrook development together with re-arrangement and expansion of the Country Park (planning application reference 13/02513/MAJOR). The proposals include the development of 193 dwellings and the provision of a site for a new indoor leisure centre for Fleet.

10 5 The location of the Proposed Development in relation to the Edenbrook Village and Edenbrook Extension is shown in Figure The Hart Core Strategy Preferred Approach identified land north of Netherhouse Copse (Grove Farm) for the development of up to 450 units in July 2011, within which the Proposed Development falls. However, as a result of local opposition to the allocation of the land based on the perceived coalescence of Crookham Village with Fleet the residential element of the allocation was removed from the evolving Core Strategy. The Core Strategy was withdrawn in 2013 after it was found to be unsound by the Planning Inspector, partly because it would not meet the housing needs of the Borough. The Proposed Development was initially submitted for planning approval in 2014, Hart District Council confirmed that the rejection of the scheme at that time should not be interpreted as a total rejection of the site, which still remains one of the strategic growth options that need to be assessed by the Council in weighing up how the District will meet future housing needs There remains a need for additional homes to be provided in Fleet and across Hart District, and the application Site is in a sustainable location within walking distance of the town centre and key local facilities.. The Proposed Development represents the final phase of the development of the western side of Fleet, and includes the final phase of the expansion of the Country Park to create a large-scale ecological and recreational resource.

11 6 Figure 2: Location of Edenbrook Developments in relation to the Proposed Development

12 7 2.3 HOW HAS THE DESIGN EVOLVED? The design of the scheme has been developed through extensive investigations into the character of Crookham Village and Fleet, and in-depth analysis of the constraints and opportunities in and surrounding the Site. The details of these constraints and opportunities are set out in the Design and Access Statement which is submitted with the Planning Application. Once the design principles were established, a network of roads, development parcels and open spaces was identified to create the initial concept masterplan Discussions regarding the design of the Proposed Development have been held with Officers at HDC since early 2010 and have resulted in several key changes to the design layout. A summary of the key stages of the design process is presented below: Review of site constraints and opportunities in and surrounding the Site; Consideration of existing services which cross the Site and the need to protecting areas of Ancient Woodland within the Site and areas associated with the River Hart; Retention of the existing public rights of way and provision of additional pedestrian and cycle connections; and Design of a highway access strategy to minimise the amount of traffic passing through Crookham Village to the south of the Site as a result of the Development. In addition, the access strategy considered the potential realignment of part of Hitches Lane in the vicinity of the Site to provide improvements to traffic Comments received from HDC and other consultees and following feedback from the public consultation events has led to revisions to the initial development layouts. The main design iterations are described below which reflect the layout and principles of the application previously refused. LAND USES Land for a single community facility is provided near the proposed extension to the sports pitches in the Eastern Site. Whilst the application includes land for a community facility, it is anticipated that this land will be transferred to a third party and subject to a separate future planning application, and the Developer will not source a tenant In order to accommodate residential units in the north of the Eastern Site it is proposed that some localised ground re-modelling is undertaken to provide a usable extension to the sports pitches for public use and/or use by the nearby Calthorpe Park School as determined appropriate by the District Council. ACCESS The initial sketch plan included two roundabouts on Hitches Lane: a three arm roundabout to the south to allow access into the Eastern Site and a further four arm roundabout to the north to enable access to both the Western and Eastern Sites. Evolution of the scheme design resulted in the re-design of the access strategy to provide a T junction to access the north of the Eastern Site and a three arm roundabout in the south of the Eastern Site. A second T junction will be provided to allow access into the car park in the Western Site. The designs of the junctions are submitted in detail and are shown on Figures 9-11 below.

13 Other options considered in relation to access included reduction of the speed limit for Hitches Lane from 60 mph to 30 mph to enhance traffic safety associated with accessing the Site and potential realignment of Hitches Lane to encourage a reduction in traffic speed. Following discussions with HCC Highways it was agreed that future consideration will be given to reduction of the speed limit to 40 mph through a separate Traffic Regulations Order. 2.4 WHO HAS BEEN CONSULTED ABOUT THIS DEVELOPMENT? Prior to the 2014 application, a public exhibition was held on 9 th and 10 th May 2014 to seek views of the local community on the proposals and respond to any questions. A summary of the feedback received is provided in the updated Statement of Community Involvement which is submitted in support of the planning application. A newsletter was issued to the local community in May A questionnaire was used to obtain information on public opinion. The most commonly raised issues received from local residents related to increased traffic and congestion in the area, insufficient capacity of current local infrastructure (such as GP surgeries and schools) and general over-development including the loss of the gap between Fleet and Crookham Village Consultation including EIA scoping was undertaken with various organisations during preparation of the original planning application and the ES, including Natural England, the Environment Agency, Hampshire County Council and HDC. The purpose of these consultations was to agree the assessment methodologies for technical studies and to identify any sensitivities or concerns associated with the Proposed Development which may need to be considered in the design process and assessed as part of the EIA. Discussions with HDC in 2016 confirmed that the original consultation still stands given the Proposed Development has not changed. 2.5 WHEN WILL THE DEVELOPMENT BE BUILT? The Site preparation and construction works will be designed and programmed to minimise disruption to local residents, businesses and the general public. Subject to obtaining planning permission, and the discharge of relevant conditions, construction of the Proposed Development is anticipated to commence in 2017 and to be completed by Construction is anticipated to occur in six main phases, as detailed below. PHASE LOCATION DATE OF COMMENCEMENT DATE OF COMPLETION 1 North-west Mid to late South-west North-east North South South The indicative phasing plan is provided as Figure 3 below.

14 9 Figure 3: Indicative Construction Phasing

15 10 3 OVERVIEW OF THE DEVELOPMENT PARAMETERS 3.1 INTRODUCTION The parameters of the Proposed Development assessed in the ES are shown on the Parameter Plans, reproduced as Figures 4 8 and Figure 12 below. These plans show the type and broad location of the land uses and define the aspects of the Proposed Development for which planning consent is being sought. 3.2 LAND USE PARAMETER PLAN The Land Use Parameter Plan (Figure 4) shows the general extent of the proposed built footprint, the disposition of land uses across the Site, the points of access and the areas of open space and attenuation. The primary land uses across the Site comprise: A SANG of approximately ha located on the Western Site as an extension to Edenbrook Country Park; Up to 423 dwellings, including up to 40% affordable housing subject to negotiations with the District Council; Land on the northern edge of the Site for the extension of sports pitches for public use or use by Calthorpe Park School as HDC deems appropriate; Drainage and landscape works; Public open space/ children s play facilities; Land for a community facility; Three points of vehicular access from Hitches Lane (two serving the Eastern Site and one serving the Western Site); Pedestrian and cycle access and preservation of public rights of way; Retention of trees and hedgerows on-site as far as possible; Enhanced buffer planting along the southern Site boundary; and A 15 m buffer to the Ancient Woodland on the southern boundary of the Site.

16 11 Figure 4: Land Use Parameter Plan

17 RESIDENTIAL DENSITY PARAMETER PLAN The Residential Density Parameter Plan (Figure 5) shows the pattern of residential densities across the Site. The densities will vary from up to 20 dwellings per hectare to up to 60 dwellings per hectare The Proposed Development will provide a mix of residential dwellings, ranging from 1 bedroom apartments to 5 bedroom houses. The Proposed Development will provide 423 new homes including up to 40% affordable housing subject to negotiation with the Council. Figure 5: Density Parameter Plan

18 BUILDING HEIGHTS PARAMETER PLAN The Building Heights Parameter Plan (Figure 6) identifies the graduation and distribution of building heights across the Development and the maximum building heights. The residential properties range from 2 to 3 storeys, with the highest buildings predominantly on the outer edges of the Eastern Site. The community facility will be a maximum of 2 storeys The landscape and visual assessment within the ES has been based on the Parameter Plans and allows for maximum building heights up to those shown on the parameter plan. Whilst the building heights across the Eastern Site are expressed in terms of storey heights, a maximum building height (to the top of the ridge and measured in metres from ground level) has been set to allow some flexibility in the future detailed design. It is not the intention that the whole built development area will be covered by buildings at those heights; rather the heights represent the maximum parameters which have been assessed for the purposes of the EIA. Specific details regarding the height of each building will be determined at the reserved matters application stage. The Design and Access Statement which is submitted with the planning application describes the proposed character areas within the Development.

19 14 Figure 6: Building Heights Parameter Plan

20 ACCESS AND MOVEMENT PARAMETER PLANS The Movement and Access Parameter Plans (Figures 7 and 8) show the key vehicular, pedestrian and cycle accesses and routes within the Proposed Development and links with the wider network Three vehicular access points into the Proposed Development will be provided from Hitches Lane. The primary vehicular access point into the Development will be provided via a three arm roundabout. The secondary vehicular access point will be provided via a T junction to the north of this, near the land proposed for a community facility in the Eastern Site. The third access point will provide access to the car park in the Western Site Two amenity parking areas will be provided within the development: to the north of the Eastern Site associated with the community facility; and within the Western Site associated with the Country Park extension. Parking associated with the residential dwellings within the Proposed Development will be provided in accordance with HDC standards The exact alignment and routing of the new internal roads shown on the Movement and Access (Vehicular) Parameter Plan can only be defined in conjunction with the associated layout of the future phases of development, which will be the subject of reserved matters approvals. The proposed access points to the site are fixed and are the only element of the Proposed Development for which full planning permission is being sought Two existing public rights of way (PRoW) cross the Eastern Site, one of which extends from east to west across the centre of the Eastern Site, and one PRoW extends across the Western Site to the south of Jack Reid s Copse. All PRoW will be retained within the Proposed Development The Proposed Development will also provide new footpaths, including: Proposed footpaths throughout the Eastern Site, linking the residential dwellings and in the Western Site to provide recreational access to the extension to the Country Park; and A proposed cycle route extending from the primary access points, crossing the Eastern Site The route, alignment and design of the internal routes including provision for public transport and routes for pedestrians and cyclists will be within the access corridors as shown on the Access and Movement Parameter Plans. Such design will come forward in conjunction with the layout of the future phases of development and will be the subject of reserved matters approvals Consent for access into the Site from Hitches Lane is sought as part of this application, as shown on Figures 9-11.

21 16 Figure 7: Movement and Access Vehicular Parameter Plan

22 17 Figure 8: Movement and Access Pedestrian and Cycle Parameter Plan

23 18 Figure 9: Northern Residential Access

24 19 Figure 10: Southern Roundabout Site Access

25 20 Figure 11: Country Park Ste Access and Road Crossing for SANG Areas

26 LANDSCAPE AND ECOLOGY STRATEGY PARAMETER PLAN The Landscape and Ecology Strategy Parameter Plan (Figure 12) identifies the following principles: The retention of existing woodland in the north and south of both the Eastern and Western Sites; Extension of the existing country park / SANG provision; Provision of a series of public spaces, including formal public open space, play areas and privately maintained open space; provision of sports pitches for public use and/or use by Calthorpe Park School as determined appropriate by the District Council; Retention of existing ditch in the south of the Eastern Site; Provision of four water attenuation areas; Provision of a buffer either side of the retained ditches in the Eastern Site; and Retention of other hedgerows and trees where practicable.

27 22 Figure 12: Landscape and Ecology Parameter Plan

28 23 4 ENVIRONMENTAL EFFECTS OF THE PROPOSED DEVELOPMENT 4.1 WILL THE EXISTING LOCAL COMMUNITY BE DISTURBED AS A RESULT OF THE CONSTRUCTION PHASE? Construction works may result in disturbances to nearby residents. Examples of disturbances include noise from construction works and machinery, dust during certain activities, and construction traffic. To mitigate adverse effects, a Construction Environmental Management Plan (CEMP) will be agreed with HDC and the contractor will sign up to the Considerate Constructors Scheme. The CEMP will set out the management measures that the contractors will adopt and implement during construction to avoid and manage any construction effects on the environment and the local community. In addition, regular liaison with the local community will be held throughout the construction period. The construction phase is not anticipated to have significant long-term negative effects on the local community. 4.2 HOW WILL THE CONSTRUCTION TRAFFIC AFFECT THOSE WHO USE THE LOCAL ROAD AND PATH NETWORKS? Construction traffic will use main roads to access Site and the exact routing arrangements will be agreed with HDC prior to commencement of construction; no Heavy Goods Vehicles (HGVs) will be permitted to travel south on Hitches Lane through Crookham Village. The CEMP will include provisions relating to construction traffic in order to manage any impacts from HGVs on the local highway network. It is also proposed that the movement of HGVs will be restricted to avoid school start and finish times During construction there will be the equivalent of one HGV movement every 10 minutes, however, it is not anticipated that this will cause any noticeable delay to vehicles using Hitches Lane There are expected to be effects on severance and pedestrian amenity on Hitches Lane in the vicinity of the Calthorpe Park School during construction. The effects are caused by the passage of HGVs. In order to mitigate this it is proposed to implement a restriction on the working hours of HGVs along Hitches Lane to avoid school start and finish times. This mitigation will mean that any effects on severance and pedestrian amenity will be negligible, and there will be no other significant effects. 4.3 WILL THE PROPOSED DEVELOPMENT BENEFIT THE LOCAL ECONOMY? During the construction works it is anticipated that the Proposed Development will provide up to 99 full time equivalent jobs, which would be expected to be filled in part by workers from the local area. Additional jobs are expected to also be created through indirect and induced employment The Proposed Development will provide a range of homes, including up to 40% affordable housing subject to negotiations with the District Council, which will help to meet the housing demand in the Hart District. In addition, the new residents of the Proposed Development will increase spending in the local area, providing an economic benefit to the district. The new community facility may also result in benefits to the local economy.

29 WILL THE EXISTING COMMUNITY FACILITIES BE ABLE TO ACCOMMODATE EXISTING AND NEW RESIDENTS? Due to the increase in the population following the completion of the Proposed Development, it is anticipated that there will be an increase in demand on local healthcare facilities. However, a review of existing facilities indicates that the three local GP surgeries and two NHS dental practices in the local area are accepting new NHS patients Based on data provided by HCC, there is a shortage of primary school places in the District in 2014, an issue that is expected to continue until at least There was also a shortage of secondary school places in 2014, although there is predicted to be a slight surplus in The Applicant will provide a contribution to schools capacity in the local area, sufficient to offset the effects of the additional child yield created by the Proposed Development The Proposed Development provides land and financial contributions for a range of local recreational and community facilities to serve the local area, including the provision of land for the delivery of a new community building within the site, the extension to the Country Park, open space and play facilities. The Proposed Development will also provide improvements to the local footway and cycleway network 4.5 HOW WILL THE PROPOSED DEVELOPMENT AFFECT THE LOCAL ROAD AND FOOTPATH NETWORKS ONCE COMPLETE? The Proposed Development will improve public rights of way that cross the Site and enhance pedestrian and cycle links around the local area by providing a pedestrian refuge on Hitches Lane, improved footway provision and contributions for improvements to off-site pedestrian and cycle routes. The provision of a bus service for the Proposed Development is also likely to benefit other residents in the area In order for residents of the Edenbrook development to access the eastern side of Hitches Lane, including Calthorpe Park School and the leisure centre, a pedestrian island will be provided to link to a pedestrian route to Old Hitches Lane that provides access to the school and leisure centre and other areas (see Figure 11). The Proposed Development will also deliver a new pedestrian island north of the northern site access into the Eastern Site that will assist residents to cross Hitches Lane safely and conveniently and will facilitate pedestrian movement between the Eastern Site and the Country Park. This will also improve access across Hitches Lane for other members of the public who use the existing PRoW that follows the north-eastern boundary of the Eastern Site and crosses Hitches Lane Other design solutions which will be implemented in order to prevent adverse effects comprise: Improvements to the footway along the eastern side of Hitches Lane between the northern site access into the Eastern Site and the Country Park; Improvements to the surfacing and lighting of the existing public rights of way that pass through the Site and link south to Crookham village, west to Hitches lane (linking to both the north and the south of the Site) and east to the existing residential areas of Fleet, local schools and Cycle Route 3 that provides a high quality off-road pedestrian and cycle route to Fleet town centre; A new dropped kerb crossing on Hitches Lane to improve pedestrian access to the Country Park, particularly for those accessing the new extension of the Country Park from the north; Improvements to the Hitches Lane/Elvetham Road roundabout and the A323/Elvetham Heath Way roundabout;

30 25 A Travel Plan to reduce the number of trips taken by single occupancy private cars and to encourage walking, cycling and travel by public transport; and Transport contributions that will be used to improve the pedestrian and cycle networks in the area (for example, improved surfacing of the existing right of way that runs immediately to the east of the Site boundary in the vicinity of Tavistock Infants School and the All Saints Church of England Junior School) and to improve roads in the local area; and Transport contributions that will be used to enhance public transport services in the vicinity of the Site. The Site has been designed to allow buses to enter at one access point on Hitches Lane, travel through the site and leave by the other access point in order to minimise walk distances to the bus stops within the Site and minimise the time taken for buses to divert from Hitches Lane The possible impact of the Proposed Development on the operation of the Elvetham Road roundabout and the A323/Elvetham Heath Way roundabout has been assessed in the Transport Assessment and improvements of the roundabouts have been designed in response. These improvements, comprising the widening of the Hitches Lane, Reading Road North and Elvetham Road arms mitigate the impact of traffic associated with the Proposed Development in terms of queues and delays. 4.6 WHAT WILL HAPPEN TO THE LOCAL NOISE ENVIRONMENT DURING CONSTRUCTION AND WHEN THE DEVELOPMENT IS OCCUPIED? From on-site observations, the dominant noise sources in the local area are from road traffic on the local highway network which is to the west of the Site Construction activities are unavoidably noisy and can result in effects on residents that live nearby. The implementation of appropriate control measures and good practice through a CEMP will ensure that the amount of noise generated is as low as possible. Such measures include activities such as siting machinery away from residential properties where possible and defined construction hours, which are anticipated to be 07: Monday to Friday, on Saturdays, with no work taking place on Sundays or Bank Holidays. As a result of these measures, there will not be any significant long-term negative impacts on residents in the area During the operational phase the additional traffic movements resulting from the Proposed Development are not predicted to lead to any measurable increase in noise levels during the day or night time. However, noise levels are expected to be higher once the development is completed compared to existing levels due to changes in traffic flows on the local highway network from traffic growth and due to other developments in the local area. Suitable measures will be taken by the developer to ensure that road noise levels at the proposed dwellings comply with the relevant requirements including current Building Regulations, meaning a significant sound reduction will be achieved. For example, the use of sound-reducing double glazed windows with acoustically attenuated ventilation. 4.7 WHAT WILL HAPPEN TO LOCAL AIR QUALITY DURING CONSTRUCTION OF THE PROPOSED DEVELOPMENT AND ONCE IT S COMPLETED? The Proposed Development has the potential to generate dust during the construction works. However, the effect of dust will be reduced through good site practice and the implementation of appropriate mitigation measures as part of the CEMP; for example through the use of appropriate equipment and implementation of screening and dampening measures Localised temporary effects of exhaust emissions from construction traffic and machinery used during the construction works will arise in the areas immediately adjacent to the main site

31 26 entrance and along designated haulage routes. However, these effects will be short-lived and intermittent Once operational, the Proposed Development is expected to have no significant effects upon air quality given that it is a residential development. 4.8 WHAT ECOLOGICAL SURVEYS HAVE BEEN UNDERTAKEN AT THE SITE AND WHAT AFFECT WILL THE PROPOSED DEVELOPMENT HAVE ON LOCAL WILDLIFE? A number of ecological surveys have been carried out to understand the potential effects on features and species of nature conservation interest within the Site as a result of the Proposed Development. This has included surveys for bats, badger, water vole, otter, reptiles, great crested newts, and birds (both wintering and breeding birds) The main habitats present vary between the Eastern and Western Sites: the Eastern Site mainly consists of arable land, which is subject to intensive arable cereal crop rotation; in the Western Site the grassland has been subject to agricultural improvement and is of low value to wildlife. Areas of woodland (including Long Copse and Jack Reid s Copse areas of Ancient Woodland) and hedgerows with associated ditches are also present within the Site. A pond is present within the Eastern Site and the River Hart forms the western boundary to the Western Site. Habitats within the Site considered to be of ecological value include hedgerows, scattered trees and the River Hart, as well as areas of broad-leaved Ancient Woodland. Netherhouse Copse Ancient Woodland and Site of Importance for Nature Conservation (SINC) is located adjacent to the southern boundary of the Eastern Site Surveys confirmed that the Site supports four species of foraging bat. No confirmed evidence of bat roosting was found on the Site although trees with roosting potential are present. The Site provides good foraging and commuting opportunities for badgers. A number of protected and notable bird species have also been recorded on the Site. Protected reptiles have been found within the Site as well as a number of other mammal, amphibian and invertebrate species The Site is not considered to provide suitable habitat for Otter, with no substantial watercourses present within the Site. The adjacent River Hart provides some, limited opportunities for this species, although no evidence for the presence of Otter was recorded during the survey along this offsite watercourse. The ditches associated with hedgerows within the Site are considered to provide unsuitable habitat for this species, containing very low water levels, supporting little aquatic or emergent vegetation and being unconnected to areas of more suitable habitat The adjacent River Hart, the pond within the eastern parcel and the ditch running though the western parcel were considered to provide suitable habitat for Water Vole, although no evidence of the presence of Water Vole was recorded during the survey With the exception of some non-statutory designations within or adjacent to the Site, ecologically designated areas the closest being Basingstoke Canal Site of Special Scientific Interest, 300 m away are considered unlikely to be affected by the Proposed Development, however, a range of potential effects have been identified on habitats and fauna. Mitigation and enhancement measures are proposed, including tree and shrub planting and grassland and wetland habitat creation. These measures will provide new areas of valuable wildlife habitat, providing significant benefits to a wide variety of faunal species. Measures are also proposed to avoid effects resulting from construction activities, human interaction, lighting and changes to hydrology Following mitigation including landscaping and habitat improvement, it is expected that the Proposed Development would result in measurable enhancements to the existing ecological

32 27 interest of the Site, with benefits in respect of habitats, bats and other mammals as well as birds, amphibians, reptiles and invertebrates. 4.9 WHAT EFFECT WILL THE PROPOSED DEVELOPMENT HAVE ON THE LANDSCAPE CHARACTER AND VISUAL AMENITY OF THE AREA? The Site currently comprises arable and pasture farmland with hedgerows predominantly defining the field boundaries; ditches and two areas of Ancient Woodland are present within the Site, Jack Reid s Copse in the Western Site and Long Copse in the Eastern Site. To the south of the Eastern Site is Netherhouse Copse Ancient Woodland. Several PRoW cross the Site and provide links to the Country Park to the west, Church Crookham to the south and Fleet to the east Whilst the Proposed Development would change the land use of the Site from agriculture to residential development, the Proposed Development would affect a small part of the landscape character of the local area. The majority of the existing trees and hedgerows on-site will be retained within the Proposed Development, with the exception of some areas where unavoidable loss will be required to facilitate development and access into the Eastern Site via Hitches Lane. New native planting and individual tree planting is proposed on the northern, southern, eastern and western boundaries of the Eastern Site. This planting will limit views of the Development from external areas, providing further visual containment of the Proposed Development in the wider area The Proposed Development will maintain and reinforce key landscape resources. Views of the Eastern Site are limited to those immediately adjacent to the Eastern Site. The Proposed Development will be evident as a new element within the landscape, extending the existing built form of Fleet further to the west Within the Proposed Development areas of green infrastructure will be provided in consideration of national and local planning policy guidance at this outline stage. These spaces will accommodate a range of play areas located all around the Eastern Site and to a degree the SANGS (within the Western Site) and integrated fully into the landscape through the detailed design process The landscape strategy within the Eastern Site has been designed to ensure that the existing landscape constraints are considered. Large areas of open space are being provided throughout the Eastern Site which will maintain a natural transition in the landscape. Existing landscape vegetation is being retained, such as the boundary vegetation along the majority of the Eastern Site and the areas of Ancient Woodland. This will help maintain the landscape character of the Eastern Site. Furthermore, a landscape management plan will be produced to ensure the landscape proposals and existing landscape features are maintained in perpetuity and will be reviewed as each phase is developed Outside the application boundary the applicant proposes that the land shown coloured green in Figure 3.11 will be bound by provisions contained within a Section 106 agreement which will restrict the ability to develop this land in the future and hence protect the green gap between the boundary of the development site and Crookham Village As with the development of any green field site, a range of adverse effects will occur on the site level landscape receptors and local visual receptors. However, it is considered that the location and scale of the Proposed Development, set within a landscape structure that allows the opportunity for tree planting to supplement the existing treed framework, effects have been minimised as far as possible.

33 DOES THE SITE HAVE ARCHAEOLOGICAL POTENTIAL? A review of designated and non-designated heritage features within 1.5 km of the Site identified that there are three designated features within the Site: one Historic Hedgerow and two areas of Ancient Woodland; and two non-designated heritage assets within the Site - former historic farmsteads (known from historic mapping). There is generally a high potential for buried archaeological deposits of prehistoric to Romano-British/post-medieval date in the Site. Unknown, buried archaeological sites may exist within the Site which could be affected by ground works required during construction of the Proposed Development Mitigation measures have been agreed in principle by HCC as part of the assessment. The effects on archaeology will be reduced by the implementation of appropriate mitigation comprising a programme of further archaeological fieldwork secured through a condition attached to the planning consent. This will comprise a geophysical survey and field evaluation of buried archaeological deposits by trial trenching, with further mitigation comprising preservation in situ or by record (excavation) if required, and archaeological monitoring of groundworks affecting the hedgerow. Following implementation of mitigation measures, the Proposed Development is unlikely to have a significant effect on archaeology The proposed mitigation measures allow for dissemination of the results of the archaeological work to the local and wider community, thereby increasing public knowledge and enjoyment of the historic environment of Fleet and Crookham Village ARE THERE ANY CONCERNS RELATING TO CONTAMINATED LAND OR GROUND CONDITIONS WITHIN THE SITE? Current and historical land uses of the Site are unlikely to have resulted in contamination of the soil. Preliminary ground investigations undertaken have not identified any contamination in the topsoil. However, there is a potential risk of contamination in shallow soils in localised areas, and further investigation will be undertaken prior to construction and if necessary any remedial works will be implemented during the construction works Due to the nature of the ground conditions within the Site there is a potential for ground gas to be produced on-site (from Alluvium deposits) and from off-site sources (a historic landfill). To date, ground gas monitoring has not recorded any elevated concentrations of ground gas. Further monitoring will be undertaken prior to construction and if necessary appropriate mitigation and protection measures will be implemented into the scheme design Implementation of the CEMP will ensure the adoption of safe working systems and good environmental practices during the construction phase. If any contaminants are encountered, these measures will ensure the protection of water receptors and local residents, thus removing the risk of contamination WILL THE PROPOSED DEVELOPMENT CHANGE THE EXISTING WATER ENVIRONMENT AND WILL THERE BE INCREASED DEMAND ON WATER RESOURCES? The introduction of non-permeable areas (such as roads, hardstanding, buildings and compacted soil) at the Site will alter the existing drainage characteristics of the Site. Following completion of the Proposed Development surface water from the Site will continue to drain through a network of ditches and discharge into the River Hart, via Sustainable Drainage Systems (SuDS). The implementation of SuDS and other mitigation measures will control the amount of surface water run-off and ensure that there will be no significant effects on water quality, drainage, or on important and sensitive water resources during either construction or operation.

34 Consultation with Southeast Water has identified that there is sufficient capacity in the existing network to supply the Proposed Development. Water efficiency measures will be applied to reduce the volume of water required by future residents and the amount of wastewater that is produced. Consultation with Thames Water has shown that a scheme is planned to improve operation of the sewerage system at Hitches Lane Pumping Station, which will provide the necessary capacity in the network to accommodate the new community. Overall, the Proposed Development will not result in any significant effects on water demand and foul sewerage infrastructure WILL THE DEVELOPMENT INCREASE FLOODING? The Western Site, where the extension to the Country Park will be located, is at risk from flooding since a large part of this area is within the floodplain of the River Hart. There will be no built development within the Western Site which will affect the river or its floodplain The Eastern Site, where the residential development will be located, is not at risk from tidal, fluvial, groundwater or sewer flooding, neither will the Proposed Development displace any areas of floodplain. The Proposed Development of the Eastern Site will not increase the likelihood of flooding occurring in the area. The drainage strategy for the Proposed Development includes SuDS measures, which will mimic the natural drainage patterns currently in existence during operation WHAT WILL BE THE EFFECT OF THE PROPOSED DEVELOPMENT ON THE EXISTING AGRICULTURAL USE? Surveys have shown the agricultural land at the Site to be of very good, good and moderate quality. Construction of the Proposed Development will result in the loss of approximately 31.9 ha of agricultural land and the potential loss of or damage to the soil resource from ground works and localised excavation Measures to mitigate the effects on the soil resources relate to following a soil resources plan, implementing best practices for handling and storage of soil, and re-using or disposing of surplus soil resources in a sustainable manner WHAT MEASURES WILL BE USED TO AVOID AND REDUCE THE ENVIRONMENTAL EFFECTS OF THE PROPOSED DEVELOPMENT? A summary of the measures which will be implemented to avoid and reduce any negative environmental effects and enhance environmental benefits associated with the Proposed Development is provided in the table below. TOPIC AREA Socio- Economic Effects Traffic and Transportation Noise and Vibration MEASURES TO AVOID OR OFFSET POTENTIAL NEGATIVE ENVIRONMENTAL EFFECTS / ENHANCEMENT MEASURES CONSTRUCTION PHASE Where feasible, the Applicant will employ local people during construction works. Restriction of HGV operating hours on Hitches Lane including to avoid school start and finish times. COMPLETED DEVELOPMENT Developer contribution to schools capacity None proposed. Best practicable means will be used to minimise None proposed. construction noise through the implementation of the recommendations set out in BS5228 by means of a Construction Environmental Management Plan

University Park, Worcester Non Technical Summary December 2011

University Park, Worcester Non Technical Summary December 2011 University Park, Worcester Non Technical Summary December 2011 Introduction UW Wrenbridge LLP, a Joint Venture Company of the University of Worcester and Wrenbridge Land Ltd (the Applicants ) intend to

More information

LAND AT WEST YELLAND. Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP

LAND AT WEST YELLAND. Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP LAND AT WEST YELLAND Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP May 2014 Quality Management Issue/revision Issue 1 Revision 1 Revision 2 Revision 3 Remarks Draft FINAL Date

More information

Grantham Southern Quadrant Link Road Environmental Statement

Grantham Southern Quadrant Link Road Environmental Statement Grantham Southern Quadrant Link Road Environmental Statement Non Technical Summary Introduction Lincolnshire County Council (LCC) is submitting a planning application for the proposed implementation of

More information

WELCOME. Land North of STEVENAGE. We would like to thank you for attending our public exhibition today.

WELCOME. Land North of STEVENAGE.   We would like to thank you for attending our public exhibition today. WELCOME We would like to thank you for attending our public exhibition today. The purpose of this event is to share our proposals and hear your thoughts on our ideas. Members of the project team are on

More information

Replacement Golf Course Facilities and Residential Development, Churston. Environmental Statement Non-Technical Summary

Replacement Golf Course Facilities and Residential Development, Churston. Environmental Statement Non-Technical Summary Replacement Golf Course Facilities and Residential Development, Churston Environmental Statement Non-Technical Summary July 2011 Reproduced from the Ordnance Survey s map with the permission of the Controller

More information

Statement of Community Involvement LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE

Statement of Community Involvement LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE CONTENTS Page 1. Introduction 3 2. Pre-application Discussions 4 3. The Consultation Process 5 4. Consultation Feedback 7 5. Responses to Consultation Feedback

More information

Welcome to our exhibition

Welcome to our exhibition Welcome to our exhibition The Homes & Communities Agency (HCA) welcomes you to this public exhibition explaining our proposals for the redevelopment of the former Lea Castle Hospital site. About the Homes

More information

The Place Solar Farm

The Place Solar Farm The Place Solar Farm Environmental Statement Non-Technical Summary 28 August 2014 Produced for Prepared by St John s House Queen Street, Manchester M2 5JB Contents Contents... 2 1 Introduction... 3 1.1

More information

Public Consultation. Land at Monks Farm, North Grove. Welcome

Public Consultation. Land at Monks Farm, North Grove. Welcome Welcome Welcome to our public exhibition for development on Land at Monks Farm, orth Grove. Gallagher Estates and Gleeson Strategic Land are preparing an outline planning application for new homes, open

More information

LAND AT HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. March 2017 Our Ref: Q70433

LAND AT HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. March 2017 Our Ref: Q70433 LAND AT HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY March 2017 Our Ref: Q70433 Contents 1 INTRODUCTION AND SITE DESCRIPTION... 1 2 EIA METHODOLOGY... 5 3 ALTERNATIVES... 6 4 DESCRIPTION

More information

SOUTH EAST LINCOLNSHIRE LOCAL PLAN: HOUSING PAPER DONINGTON (JUNE 2016)

SOUTH EAST LINCOLNSHIRE LOCAL PLAN: HOUSING PAPER DONINGTON (JUNE 2016) SOUTH EAST LINCOLNSHIRE LOCAL PLAN: HOUSING PAPER DONINGTON (JUNE 2016) 1 DONINGTON S PLACE IN THE SPATIAL STRATEGY 1.1 Policy 2 of the South East Lincolnshire Local Plan 2011-2036 Draft for Public Consultation

More information

South Whitehaven, Cumbria EIA

South Whitehaven, Cumbria EIA South Whitehaven, Cumbria EIA Environmental Statement - Non Technical Summary June 2013 in association with 1. Introduction Story Homes is applying to Copeland Borough Council (CBC) for a new residential

More information

Welcome to our Public Consultation

Welcome to our Public Consultation About our development This exhibition gives you the chance to view and comment on our emerging plans for a proposed residential development located on land to the West of Alwyn Road, Rugby. Welcome to

More information

Frequently Asked Questions

Frequently Asked Questions 1. Where is Aylesbury Woodlands? Frequently Asked Questions Aylesbury Woodlands lies to the east of Aylesbury. It is bounded to the south by the A41. To the north is the Aylesbury Arm of the Grand Union

More information

LAND SECURITIES REDEVELOPMENT OF NEWNHAM COURT SHOPPING VILLAGE, MAIDSTONE

LAND SECURITIES REDEVELOPMENT OF NEWNHAM COURT SHOPPING VILLAGE, MAIDSTONE LAND SECURITIES REDEVELOPMENT OF NEWNHAM COURT SHOPPING VILLAGE, MAIDSTONE Land at Environmental Statement: Non-Technical Summary Introduction Land Securities plc is applying to Maidstone Borough Council

More information

Development of land adjacent to Braggs Farm Lane and Rumbush Lane, Dickens Heath. Welcome. Today s exhibition. The proposal site

Development of land adjacent to Braggs Farm Lane and Rumbush Lane, Dickens Heath. Welcome. Today s exhibition. The proposal site Welcome Welcome to this event to discuss the development of land adjacent to Braggs Farm Lane. is currently in the preliminary stages of designing proposals to sensitively develop this site with high-quality

More information

Meridian Water Phase 1 Application

Meridian Water Phase 1 Application Meridian Water Phase 1 Application MW11 Environmental Statement Non-Technical Summary London Borough of Enfield March 2016 Contents 1 Introduction 1 2 The proposed development 2 3 Evolution of the proposed

More information

Land at Rampton Road. Cottenham

Land at Rampton Road. Cottenham Land at Rampton Road Cottenham Introduction TEP is preparing an outline planning application for 54 dwellings on 6.9 hectares of land adjacent to Rampton Road, Cottenham on behalf of the owners Cambridgeshire

More information

Elvetham Chase, Fleet. Environmental Statement: Non-Technical Summary. November New Fetter Lane London EC4A 1AZ United Kingdom

Elvetham Chase, Fleet. Environmental Statement: Non-Technical Summary. November New Fetter Lane London EC4A 1AZ United Kingdom Elvetham Chase, Fleet Environmental Statement: Non-Technical Summary November 2016 A Ne w F e tte r P lace 8-10 New Fetter Lane London EC4A 1AZ United Kingdom T +44 (0) 20 7467 1470 F +44 (0) 20 7467 1471

More information

BREEDON NORTHERN LIMITED

BREEDON NORTHERN LIMITED Non Technical Summary CONTENTS 1 INTRODUCTION... 1 2 SITE DESCRIPTION... 1 3 DESCRIPTION OF THE DEVELOPMENT... 6 4 NEED FOR THE DEVELOPMENT... 8 5 KEY ISSUES CONSIDERED IN THE ENVIRONMENTAL IMPACT ASSESSMENT...

More information

VALLEY PARK, DIDCOT. Non-Technical Summary. December On behalf of Taylor Wimpey UK Limited, Persimmon Homes and Hallam Land Management Ltd.

VALLEY PARK, DIDCOT. Non-Technical Summary. December On behalf of Taylor Wimpey UK Limited, Persimmon Homes and Hallam Land Management Ltd. VALLEY PARK, DIDCOT Non-Technical Summary December 2014 On behalf of Taylor Wimpey UK Limited, Persimmon Homes and Hallam Land Management Ltd. CONTENTS 1 Introduction... 2 2 The Proposed Development...

More information

WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014

WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014 WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014 Dear Resident This Special Edition of the Whiteley Voice which has been prepared in conjunction with the North Whiteley Consortium is to

More information

NON-TECHNICAL SUMMARY

NON-TECHNICAL SUMMARY Proposed Sand and Gravel Extraction and Associated Processing Operations with Restoration to a Mixture of Agriculture and Nature Conservation including Areas of Shallow Water at Hedgeley, Northumberland

More information

London Road, Derker. Non Technical Summary. Introduction

London Road, Derker. Non Technical Summary. Introduction London Road, Derker Non Technical Summary Introduction The Oldham Rochdale Housing Market Pathfinder was set up to tackle longstanding problems of poor quality housing and to provide the framework for

More information

Welcome. Site/11/04. Site/11/03. Proposed Site. 11,400 new homes needed in east Cambs

Welcome. Site/11/04. Site/11/03. Proposed Site. 11,400 new homes needed in east Cambs Welcome Welcome to our consultation on our proposals for new homes on land north east of Soham Road, Fordham. Members of the project team are available to answer any questions you have and listen to feedback.

More information

ABBEY MANOR GROUP/SAINSBURY S SUPERMARKETS LTD

ABBEY MANOR GROUP/SAINSBURY S SUPERMARKETS LTD ABBEY MANOR GROUP/SAINSBURY S SUPERMARKETS LTD Mixed Use Development including Business Park and Foodstore Land at Bunford Park, Bunford Lane, Yeovil Environmental Statement: Non-Technical Report June

More information

Wyvern Park Skipton Environmental Statement. Non-technical Summary - April 2015

Wyvern Park Skipton Environmental Statement. Non-technical Summary - April 2015 Wyvern Park Skipton Environmental Statement Non-technical Summary - April 2015 BWB Consulting Ltd Whitehall Waterfront 2 Riverside Way Leeds LS1 4EH Telephone: +44(0)113 233 8000 Copyright This Report

More information

Barvills Solar Farm Environmental Statement Non-Technical Summary

Barvills Solar Farm Environmental Statement Non-Technical Summary Barvills Solar Farm Environmental Statement Non-Technical Summary 13 March 2015 Produced for Prepared by St John s House Queen Street, Manchester M2 5JB Contents Contents... 2 1 Introduction... 3 1.1 Development

More information

Longbridge Town Centre Phase 2 Planning Application

Longbridge Town Centre Phase 2 Planning Application Longbridge Town Centre Phase 2 Planning Application Non-Technical Summary of the Environmental Statement December 2013 Introduction A full application for Planning Permission has been submitted to Birmingham

More information

Land at BROOK STREET PROPERTIES TENCREEK FARM, LISKEARD. Environmental Statement: Non-Technical Summary

Land at BROOK STREET PROPERTIES TENCREEK FARM, LISKEARD. Environmental Statement: Non-Technical Summary BROOK STREET PROPERTIES TENCREEK FARM, LISKEARD Land at Environmental Statement: Non-Technical Summary Introduction Brook Street Properties is applying to Cornwall Council for outline planning permission

More information

South Macclesfield Development Area Environmental Statement Non-Technical Summary March 2017

South Macclesfield Development Area Environmental Statement Non-Technical Summary March 2017 South Macclesfield Development Area Environmental Statement March 2017 Contents 1.0 Introduction... 2 1.1 Background... 2 1.2 Environmental Assessment... 2 1.3 Site Description... 2 2.0 The Proposals...

More information

LAND AT MIDDLETON STONEY ROAD AND HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. June 2017 Our Ref: Q70433

LAND AT MIDDLETON STONEY ROAD AND HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. June 2017 Our Ref: Q70433 LAND AT MIDDLETON STONEY ROAD AND HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY June 2017 Our Ref: Q70433 Contents 1 INTRODUCTION... 2 2 SITE DESCRIPTION... 5 3 EIA METHODOLOGY...

More information

Reserved Matters application for a site that straddles the boundary between CBC and BBC

Reserved Matters application for a site that straddles the boundary between CBC and BBC BBC APPLICATION 15/02682/MAR NUMBER CBC APPLICATION CB/15/04294/RM NUMBER LOCATION Wixams Land at former storage depot, Bedford Road, Wilstead Bedfordshire PROPOSAL Reserved Matters Application for Strategic

More information

BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY

BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY SITE LOCATION The site of the existing AECC lies in an area of predominately residential and business use in Bridge of Don and extends approximately 50 acres.

More information

Welcome to our public exhibition

Welcome to our public exhibition About our development Welcome to our public exhibition This exhibition gives you the chance to view and comment on our proposals for a new residential development of 165 high-quality homes, along with

More information

Newcourt Masterplan. November Exeter Local Development Framework

Newcourt Masterplan. November Exeter Local Development Framework Newcourt Masterplan November 2010 Exeter Local Development Framework Background The Exeter Core Strategy Proposed Submission sets out the vision, objectives and strategy for the development of Exeter up

More information

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of WELCOME The developers are preparing an outline planning application for a residential led development and need the community s views in order to develop the proposals further WHAT IS PROPOSED? A high

More information

Hunts Grove, Gloucestershire

Hunts Grove, Gloucestershire Hunts Grove, Gloucestershire Environmental Statement Non Technical Summary February 2007 ISSUING OFFICE OXFORD T: 01865 887050 F: 01865 887055 E: info@lda-design.co.uk HUNTS GROVE, GLOUCESTERSHIRE ENVIRONMENTAL

More information

Thornton Road, Pickering Environmental Statement Non-Technical Summary. January 2016

Thornton Road, Pickering Environmental Statement Non-Technical Summary. January 2016 Thornton Road, Pickering Environmental Statement Non-Technical Summary January 2016 EIA Quality This Environmental Statement, and the Environmental Impact Assessment (EIA) carried out to identify the significant

More information

PHASE III: Reserved Matters Submission

PHASE III: Reserved Matters Submission Statement of Compliance with the outline approval for the proposed residential development of land at: BURGES LANE, WIVELISCOMBE PHASE III: Reserved Matters Submission Foreword Contents: This Statement

More information

Former RAF Sealand Site EIA

Former RAF Sealand Site EIA Praxis (Holdings) Ltd. Former RAF Sealand Site EIA Environmental Statement - Non Technical Summary February 2012 in association with P a g e 1 1. Introduction Praxis (Holdings) Ltd. is applying to Flintshire

More information

ES 5. Drakelow Park. Environmental Statement. Volume 5: Non Technical Summary. Lead Author Waterman Energy, Environment and Design Ltd

ES 5. Drakelow Park. Environmental Statement. Volume 5: Non Technical Summary. Lead Author Waterman Energy, Environment and Design Ltd Drakelow Park ES 5 Environmental Statement Volume 5: Non Technical Summary Lead Author Waterman Energy, Environment and Design Ltd April 2009 Environmental Statement Volume 5: Non-Technical Summary DRAKELOW

More information

CENTRAL CHELMSFORD DEVELOPMENT AGENCY: CITY PARK WEST (PHASE 2)

CENTRAL CHELMSFORD DEVELOPMENT AGENCY: CITY PARK WEST (PHASE 2) CENTRAL CHELMSFORD DEVELOPMENT AGENCY: CITY PARK WEST (PHASE 2) Central Chelmsford Development Agency / Genesis 27/08/2014 Central Chelmsford Development Agency: Environmental Statement Quality Management

More information

Chapter 4. Route Window C12: Mile End Park and Eleanor Street Shafts

Chapter 4. Route Window C12: Mile End Park and Eleanor Street Shafts Chapter 4 Route Window C12: Mile End Park and Eleanor Street Shafts 48 Crossrail Amendment of Provisions 4 Route Window C12: Mile End Park and Eleanor Street Shafts Location plan of Mile End Park and Eleanor

More information

Welcome to our public exhibition

Welcome to our public exhibition About Our Scheme Welcome to our public exhibition This exhibition gives you the chance to view and comment upon our emerging proposals for a new residential development of 68 new homes on the site of the

More information

The Trustees of the Standen Estate Land South of Clitheroe Non-Technical Summary

The Trustees of the Standen Estate Land South of Clitheroe Non-Technical Summary 1 The Trustees of the Standen Estate Land South of Clitheroe Non-Technical Summary 1. Introduction This report summarises the results of an assessment that has been undertaken to determine how a proposed

More information

Kibworth Harcourt. Introduction. Introduction

Kibworth Harcourt. Introduction. Introduction Introduction Introduction Welcome to this public exhibition on the proposals for the delivery of new homes on land at The Kibworths. The purpose of today s exhibition is to give you the opportunity to

More information

CENTRAL BEDFORDSHIRE COMMITTED TO WORKING TOGETHER WITH LOCAL COMMUNITIES

CENTRAL BEDFORDSHIRE COMMITTED TO WORKING TOGETHER WITH LOCAL COMMUNITIES WELCOME Thank you for coming to our consultation event to find out more about our emerging proposals for Hayfield Park, a residential development jointly promoted by the Hayfield Consortium: Martin Grant

More information

Bloor Homes Stubbocks Walk North Hertfordshire ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY

Bloor Homes Stubbocks Walk North Hertfordshire ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY Bloor Homes Stubbocks Walk North Hertfordshire ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY December 2016 Environmental Statement: Non-Technical Summary Stubbocks Walk, North Hertfordshire J S Bloor

More information

PANSHANGER QUARRY, Hertfordshire

PANSHANGER QUARRY, Hertfordshire PANSHANGER QUARRY, Hertfordshire Proposed enhanced restoration of Phases F & H Briefing Note 1 March 2015 INERT (INACTIVE) RESTORATION MATERIALS, CONTROLS AND OPERATIONS 1 Introduction This briefing note

More information

an Inspector appointed by the Secretary of State for Communities and Local Government

an Inspector appointed by the Secretary of State for Communities and Local Government Appeal Decision Site visit made on 14 July 2015 by I Radcliffe BSc(Hons) MCIEH DMS an Inspector appointed by the Secretary of State for Communities and Local Government Decision date: 18 August 2015 Appeal

More information

WELCOME. Welcome and thank you for visiting today.

WELCOME.   Welcome and thank you for visiting today. WELCOME Welcome and thank you for visiting today. Bellway Homes Ltd (Yorkshire) are preparing a reserved matters planning application for a residential development of 293 homes at land North of Yew Tree

More information

DEFGH. Crystal Place Park. Environmental Impact Assessment (EIA) Elin Thomas and Emily Low Waterman Environmental

DEFGH. Crystal Place Park. Environmental Impact Assessment (EIA) Elin Thomas and Emily Low Waterman Environmental DEFGH Crystal Place Park Environmental Impact Assessment (EIA) Elin Thomas and Emily Low Waterman Environmental 10.12.07 EIA Presentation Content What is EIA? Legal Requirements Process Q&A Key Topics

More information

Application Guide. Should you have any questions on the Outline Application please contact:

Application Guide. Should you have any questions on the Outline Application please contact: Application Guide Application Guide This guide describes the structure of the Outline Application, explains the different documents that have been submitted with it and identifies what will happen next.

More information

Cranbrook EXPANSION ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY PRODUCED BY DAVID LOCK ASSOCIATES

Cranbrook EXPANSION ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY PRODUCED BY DAVID LOCK ASSOCIATES Cranbrook EXPANSION ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY PRODUCED BY DECEMBER 2014 CRANBROOK EXPANSION AREAS ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY Submitted in support of Outline Planning

More information

1. Welcome. Background

1. Welcome. Background 1. Welcome The purpose of this exhibition is to provide you with an update on progress on the Kilnwood Vale Scheme. In order to improve the scheme and deliver key facilities earlier in the development,

More information

Ʊ ± ªº Œª ºª ø ª ª ± ª

Ʊ ± ªº Œª ºª ø ª ª ± ª Ʊ ± ªº Œª ºª ø ª ª ± ª ø º Õ± ± ± Œ±øºÙ Õ ß Æª ø檺 ±Æ ƪ ø檺 æß Æ± Ʊ ª ø ø fl ª ª ± ê ø Õ øæß ª ª æªæ Ó ÔÌ Non-Technical Summary Introduction A planning application has been submitted to the Vale

More information

PROPOSED RESIDENTIAL DEVELOPMENT LAND AT GREEN LANE, YARM

PROPOSED RESIDENTIAL DEVELOPMENT LAND AT GREEN LANE, YARM PROPOSED RESIDENTIAL DEVELOPMENT LAND AT GREEN LANE, YARM PUBLIC CONSULTATION YOUR VIEW MATTERS TO US LOCATION PLAN Thank you for taking the time to read this information leaflet regarding a proposed residential

More information

Neighbourhood Planning Site Assessment Pro-forma and Guide Version 2

Neighbourhood Planning Site Assessment Pro-forma and Guide Version 2 Neighbourhood Planning Site Assessment Pro-forma and Guide Version 2 September 2014 Site HNP 006 Land East of Stanbridge Road and North of Lower Road 1. Background information Site location and use Site

More information

Carterton Construction Ltd is bringing forward plans for up to 85 new family homes and extra care facilities on land east of Burford.

Carterton Construction Ltd is bringing forward plans for up to 85 new family homes and extra care facilities on land east of Burford. Welcome Carterton Construction Ltd is bringing forward plans for up to 85 new family homes and extra care facilities on land east of. We are at the early stages of designing our proposals and have a number

More information

LONDON BRIDGE STATION ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY

LONDON BRIDGE STATION ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY LONDON BRIDGE STATION ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY June 2011 1 EXECUTIVE SUMMARY 2 INTRODUCTION CONTENTS Page 2.1 Introduction 4 2.2 The Site 4 3 THE DEVELOPMENT 3.1 What is it? 5 3.2

More information

Lower Herne Village Hollamby Estates (2005) Ltd Environmental Statement Non-Technical Summary June 2015 INSERT PICTURE HERE

Lower Herne Village Hollamby Estates (2005) Ltd Environmental Statement Non-Technical Summary June 2015 INSERT PICTURE HERE Environmental Statement Non-Technical Summary June 2015 INSERT PICTURE HERE Table of Contents 1 INTRODUCTION 1 2 SITE LOCATION AND PROPOSED DEVELOPMENT 3 3 THE ASSESSMENT 8 4 CONCLUSIONS 16 5 WHAT HAPPENS

More information

SOUTH WOKINGHAM STRATEGIC DEVELOPMENT LOCATION PUBLIC CONSULTATION

SOUTH WOKINGHAM STRATEGIC DEVELOPMENT LOCATION PUBLIC CONSULTATION 01 WELCOME Croudace Homes, Gleeson Strategic Land, Kier Ventures, Lightwood Strategic and Miller Homes are delighted to welcome you to this public exhibition. Proposals for the site have been developing

More information

LAND NORTH OF STAFFORD

LAND NORTH OF STAFFORD REPORT N O 62000589-ESVOL3 LAND NORTH OF STAFFORD ENVIRONMENTAL STATEMENT VOLUME 3: NON-TECHNICAL SUMMARY JULY 2016 LAND NORTH OF STAFFORD ENVIRONMENTAL STATEMENT VOLUME 3: NON-TECHNICAL SUMMARY Akzo Nobel

More information

Kings Road Industrial Development, Immingham. Environmental Impact Assessment. Non Technical Summary

Kings Road Industrial Development, Immingham. Environmental Impact Assessment. Non Technical Summary Environmental Impact Assessment Non Technical Summary Report prepared by: Ecus Ltd. Brook Holt 3 Blackburn Road Sheffield S61 2DW 0114 266 9292 December 2013 Page left intentionally blank INTRODUCTION

More information

The Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion

The Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion Mr Graham Clark Berrys Newchurch Farm Kinnersley Hereford HR3 6QQ BY EMAIL The Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion SC/2017/0001

More information

WELCOME. North East Haverhill. The Planning Process

WELCOME. North East Haverhill. The Planning Process WELCOME North East The site to the North East of, known as Great Wilsey Park, is identified by St Edmundsbury Borough Council in its Core Strategy as capable of delivering a Sustainable Urban Extension.

More information

8.0 Design and Form of Development 43/

8.0 Design and Form of Development 43/ 42/ 8.0 Design and Form of Development 43/ Rothwells Farm, Golborne/ Development Statement Figure 7. Site Constraints Key 44/ Site Boundary 360 Bus Route/Stops Existing Trees Underground Water Pipe Sensitive

More information

Linden Homes Proposals for land off Ringwood Road, Verwood

Linden Homes Proposals for land off Ringwood Road, Verwood Welcome Welcome to Linden Homes first public exhibition displaying proposals for new homes on land off Ringwood Road in Verwood. Award-winning house builder Linden Homes, part of the Galliford Try Group,

More information

INTRODUCTION NORTH HEYBRIDGE GARDEN SUBURB

INTRODUCTION NORTH HEYBRIDGE GARDEN SUBURB INTRODUCTION This event is being hosted by the promoters of the proposed North Heybridge Garden Suburb who are working with Maldon District Council and other key stakeholders on the preparation of a comprehensive

More information

Kilnw Envir ood Vale onmental Statement Volume 3: Non Technical Summary July 2010

Kilnw Envir ood Vale onmental Statement Volume 3: Non Technical Summary July 2010 Kilnwood Vale Environmental Statement Volume 3: Non Technical Summary July 2010 Kilnwood Vale Environmental Impact Assessment Environmental Statement Volume 3 KILNWOOD VALE ENVIRONMENTAL STATEMENT NON-TECHNICAL

More information

NON TECHNICAL SUMMARY

NON TECHNICAL SUMMARY NON TECHNICAL SUMMARY INTRODUCTION NTS.1 CEMEX UK Properties Limited is applying for planning permission to South Cambridgeshire District Council (SCDC) for the redevelopment of the former CEMEX cement

More information

Causeway Farm, Petersfield Environmental Statement Non-Technical Summary October 2015

Causeway Farm, Petersfield Environmental Statement Non-Technical Summary October 2015 Causeway Farm, Petersfield Environmental Statement October 2015 2 Contents 1.0 Introduction... 1 1.1 Background... 1 1.2 Environmental Assessment... 1 1.3 Site Description... 3 2.0 The Proposals... 6 2.1

More information

A38 Derby Junctions. Preliminary Environmental Information Report: Non-Technical Summary

A38 Derby Junctions. Preliminary Environmental Information Report: Non-Technical Summary Preliminary Environmental Information Report: Preliminary Environmental Information Report Report No: P01 S4 September 2018 Table of contents Introduction... 1 The proposed scheme... 2 Scheme details...

More information

17A. Wind Microclimate

17A. Wind Microclimate 17A. Wind Microclimate 17A.1 Introduction 17A.1.1 17A.1.2 17A.1.3 17A.1.4 This Chapter, which has been prepared by Waterman and BMT, provides further information with regard to the potential wind microclimate

More information

Burgess Hill, Land South of Freeks Farm Phase 1 of Burgess Hill Northern Arc East Environmental Statement Non-Technical Summary September 2016

Burgess Hill, Land South of Freeks Farm Phase 1 of Burgess Hill Northern Arc East Environmental Statement Non-Technical Summary September 2016 Burgess Hill, Land South of Freeks Farm Phase 1 of Burgess Hill Northern Arc East Environmental Statement September 2016 Contents 1.0 Introduction... 1 1.1 Background... 1 1.2 Environmental Assessment...

More information

SPG 1. * the northern and western sections which are open fields used for pasture and grazing;

SPG 1. * the northern and western sections which are open fields used for pasture and grazing; SPG 1 1.0 INTRODUCTION This development brief is based on the allocation of the Priors Hall site for employment and countryside recreational purposes in the Corby Borough Local Plan. The brief is intended

More information

Sustainability Statement. Whitby Business Park Area Action Plan

Sustainability Statement. Whitby Business Park Area Action Plan Sustainability Statement Whitby Business Park Area Action Plan November 2014 Contents Page 1. Introduction 1 2. Scoping 3 3. Sustainability Appraisal of Options 6 4. Assessment of Draft Area Action Plan

More information

Applicant: Mr C Fletcher Agent: Ms B Stala Case Officer: Sally Smith (HBC) Jill Lee (WCC) Ward: Stakes Parish Southwick and Widley

Applicant: Mr C Fletcher Agent: Ms B Stala Case Officer: Sally Smith (HBC) Jill Lee (WCC) Ward: Stakes Parish Southwick and Widley Site Address: Berewood Phase 2 Development Site, London Road, Purbrook, Waterlooville Proposal: Reserved Matters Application for landscaping of Phase A of the Town Park (under Condition 6(i)d)), together

More information

Derry City and Strabane District Council Planning Committee Report. Amended layout from approval A/2004/0462/F with reduction from 166 units

Derry City and Strabane District Council Planning Committee Report. Amended layout from approval A/2004/0462/F with reduction from 166 units Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 1 st February 2017 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: Full Planning application Amended

More information

NON-TECHNICAL SUMMARY

NON-TECHNICAL SUMMARY NON-TECHNICAL SUMMARY THE HIDE, BISHOP AUCKLAND PROPOSED ECO CHALET DEVELOPMENT NON-TECHNICAL SUMMARY 1 Introduction 1.1.1 This non-technical summary for the (ES) prepared in relation to the proposed eco-chalet

More information

Cardiff International Sports Village Waterfront Development Volume IV : Non-Technical Summary of the Environmental Statement

Cardiff International Sports Village Waterfront Development Volume IV : Non-Technical Summary of the Environmental Statement Greenbank Partnerships Ltd October 2012 Cardiff International Sports Village Waterfront Development Volume IV : Non-Technical Summary of the Environmental Statement Environmental Statement - Non Technical

More information

INTRODUCTION. Land south of Bishopswood Lane, Tadley

INTRODUCTION. Land south of Bishopswood Lane, Tadley 0 INTRODUCTION THE SITE Introduction Gladman Developments Ltd. has successfully invested in communities throughout the UK over the past 0 years, developing high quality and sustainable residential, commercial

More information

Moat Lane Regeneration Project Environmental Statement

Moat Lane Regeneration Project Environmental Statement AECOM Environment Towcester Regeneration Ltd. October 2012 Moat Lane Regeneration Project Environmental Statement Non-Technical Summary Prepared by:... Checked by:... Sophie Collins Scott Wilson Environmental

More information

DESIGN & ACCESS STATEMENT

DESIGN & ACCESS STATEMENT DESIGN & ACCESS STATEMENT January 2016 Contents Introduction section 1 Section 1 - Introduction Section 2 - Assessment Section 3 - Involvement Section 4 - Evaluation Section 5 - Design Section 6 - Layout

More information

Re-location of Rugby Farmers Mart

Re-location of Rugby Farmers Mart Re-location of Rugby Farmers Mart LaSalle Investment Management Barberry Logo here Environmental Statement Non-Technical Summary August 2017 Re-location of Rugby Farmers Mart Non-Technical Summary Report

More information

LAND AT PARK MILL FARM, PRINCES RISBOROUGH ENVIRONMENTAL STATEMENT SUPPLEMENT NON-TECHNICAL SUMMARY

LAND AT PARK MILL FARM, PRINCES RISBOROUGH ENVIRONMENTAL STATEMENT SUPPLEMENT NON-TECHNICAL SUMMARY LAND AT PARK MILL FARM, PRINCES RISBOROUGH ENVIRONMENTAL STATEMENT SUPPLEMENT NON-TECHNICAL SUMMARY May 2016 CONTENTS CONTENTS... i 1 Introduction... 1 2 The Proposed Development... 3 3 Need and Alternatives

More information

It is recommended that the Committee resolve to APPROVE the application and grant planning permission subject to the following conditions:

It is recommended that the Committee resolve to APPROVE the application and grant planning permission subject to the following conditions: LOCATION: Phase 2A Millbrook Park (Site of Former Inglis Barracks), Mill Hill East, London, NW7 1PZ REFERENCE: H/04606/12 Received: 04 December 2012 Accepted: 17 December 2012 WARD: Mill Hill Expiry: 18

More information

Land to the North of Main Road, Wybunbury

Land to the North of Main Road, Wybunbury Land to the North of Main Road, Wybunbury Environmental Statement Non-Technical Summary November 2014 Land to the North of Main Road, Wybunbury Environmental Statement Non-Technical Summary Prepared on

More information

Hounsome Fields, Basingstoke Environmental Statement Non- Technical Summary. For Wates Developments Ltd and Pellipar Investments Ltd

Hounsome Fields, Basingstoke Environmental Statement Non- Technical Summary. For Wates Developments Ltd and Pellipar Investments Ltd Hounsome Fields, Basingstoke Environmental Statement Non- Technical Summary For Wates Developments Ltd and Pellipar Investments Ltd December 2015 Contents 1 Introduction 3 2 The Proposals 8 3 Environmental

More information

MAIDSTONE MEDICAL CAMPUS LTD LAND AT NEWNHAM PARK, MAIDSTONE

MAIDSTONE MEDICAL CAMPUS LTD LAND AT NEWNHAM PARK, MAIDSTONE MAIDSTONE MEDICAL CAMPUS LTD LAND AT NEWNHAM PARK, MAIDSTONE Land at Environmental Statement: Non-Technical Summary Introduction Maidstone Medical Campus Ltd is applying to Maidstone Borough Council for

More information

PERRYFIELDS BROMSGROVE. ENVIRONMENTAL STATEMENT - NON-TECHNICAL SUMMARY December 2015

PERRYFIELDS BROMSGROVE. ENVIRONMENTAL STATEMENT - NON-TECHNICAL SUMMARY December 2015 PERRYFIELDS BROMSGROVE ENVIRONMENTAL STATEMENT - NON-TECHNICAL SUMMARY December 2015 Environmental Statement Non-technical summary CONTENTS 1 Introduction 2 The Site and local context 3 Description of

More information

Lower Hollow Copse. Questions and Answers on Proposals for Permanent Gypsy and Traveller Accommodation

Lower Hollow Copse. Questions and Answers on Proposals for Permanent Gypsy and Traveller Accommodation Lower Hollow Copse Questions and Answers on Proposals for Permanent Gypsy and Traveller Accommodation 0 Why does Mid Sussex District Council need to provide permanent gypsy and traveller accommodation?

More information

PINEWOODS HOLIDAY PARK: HORSE PADDOCK. Non-Technical Summary

PINEWOODS HOLIDAY PARK: HORSE PADDOCK. Non-Technical Summary PINEWOODS HOLIDAY PARK: HORSE PADDOCK June 2014 1 Introduction 1.1 The existing Pinewoods Holiday Park is located approximately 1 km to the north of Wells-nextthe-Sea on the north Norfolk coast. Pinewoods

More information

HARDWICK GREEN, King s Lynn. Welcome to our Exhibition. What are your views? Introduction to the site and proposals. About us

HARDWICK GREEN, King s Lynn. Welcome to our Exhibition. What are your views? Introduction to the site and proposals. About us HARDWICK GREE, King s Lynn Welcome to our Exhibition Welcome to our exhibition, which is being held to provide you with the opportunity to understand and comment upon our proposals for new residential

More information

Welcome to our public consultation

Welcome to our public consultation About our development Welcome to our public consultation This exhibition gives you the chance to view and comment on our proposals for a residential development of up to 187 high-quality homes, along with

More information

Schedule of Planning Applications Committee Date: 23 May Reference: 06/17/0726/F Parish: Hemsby Officer: Mr J Beck Expiry Date:

Schedule of Planning Applications Committee Date: 23 May Reference: 06/17/0726/F Parish: Hemsby Officer: Mr J Beck Expiry Date: Schedule of Planning Applications Committee Date: 23 May 2018 Reference: 06/17/0726/F Parish: Hemsby Officer: Mr J Beck Expiry Date: 22-05-2018 Applicant: Proposal: Site: Mr Gillett Change of use to the

More information

Taylor Wimpey UK Ltd Proposed Development at Haydock Grange, Hoyles Lane, Preston Non-Technical Summary Revision 1 October 2011

Taylor Wimpey UK Ltd Proposed Development at Haydock Grange, Hoyles Lane, Preston Non-Technical Summary Revision 1 October 2011 Taylor Wimpey UK Ltd Proposed Development at Haydock Grange, Hoyles Lane, Preston Non-Technical Summary Revision 1 October 2011 Introduction An application for outline planning permission has been submitted

More information

1.0 INTRODUCTION. Brantham Industrial Area Regeneration - Factory Lane - Brantham

1.0 INTRODUCTION. Brantham Industrial Area Regeneration - Factory Lane - Brantham 1.0 INTRODUCTION Welcome to this exhibition of our proposals for the regeneration of the Brantham Industrial Area located off Factory Lane in Brantham. This presentation will give you an opportunity to

More information

Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS. A New Garden Neighbourhood Matford Barton 17

Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS. A New Garden Neighbourhood Matford Barton 17 Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS A New Garden Neighbourhood Matford Barton 17 2.1. SUMMARY AND STATUS OF THE PROPOSALS 2.1.1. The parameter plans and associated wording in this chapter

More information