1 Consultation Document Southern Section Project LT68 Orkney Grid Connection October 2018
2 Orkney Grid Connection Consultation Document Southern Section October 2018
3 QUALITY MANAGEMENT Issue/Revision Date 14/9/18 15/10/18 Remarks DRAFT FINAL Prepared by Louise Robertson and Keith Grant Louise Robertson and Keith Grant Signature Checked by Keith Grant illiam Hazell Signature Authorised by illiam Hazell Simon Hall Signature Project number Report number File reference Scottish Hydro Electric Transmission plc Inveralmond House 200 Dunkeld Road Perth PH1 3AQ Tel: +44 (0) i
4 CONTENTS LIST OF ABBREVIATIONS III 1. INTRODUCTION Purpose of this Document Document Structure Next Steps THE PROPOSALS Need for the project Project Overview Construction activities Programme ROUTE AND ALIGNMENT SELECTION PROCESS Guidance documents Main Considerations Area of search Baseline conditions Appraisal method DESCRIPTION OF ROUTES Identification of sections Identification of route options COMPARATIVE APPRAISAL Introduction Finstown to St Mary s (FS) South Ronaldsay to St Mary s (SS) Hesta Head to South Ronaldsay / South Ronaldsay to Hoxa Head (HS/SH) Hoxa Head to Rinnigill (HR) Rinnigill to Melsetter (RM) ALIGNMENT SELECTION Introduction Alignment FS, Finstown to St Mary s Alignment SS, South Ronaldsay to St Mary s Alignment HS/SH, Hesta Head to Hoxa Head Alignment RM, Rinnigill to Melsetter Hoxa Head to Rinnigill (HR) CONSULTATION ON THE PROPOSAL Introduction Next steps 7-1 ii
5 LIST OF ABBREVIATIONS GDTE HES kv Km NSA LNCS OHL OS pspa SHE Transmission SAC SEPA SNH SPA SSSI RAG RSPB LA HS Ground ater Dependent Terrestrial Ecosystem Historic Environment Scotland Kilovolt Kilometre National Scenic Area Local Nature Conservation Site Overhead Line Ordnance Survey Proposed Special Protection Area Scottish Hydro Electric Transmission plc Special Area of Conservation Scottish Environmental Protection Agency Scottish Natural Heritage Special Protection Area Site of Special Scientific Interest Red, Amber, Green Royal Society for the Protection of Birds ild Land Areas orld Heritage Site iii
6 1. INTRODUCTION 1.1 Purpose of this Document This consultation document invites interested parties to comment on the proposals by Scottish Hydro Electric Transmission plc (SHE Transmission) to construct a single circuit 132 kv double wood pole trident overhead line (OHL) on Orkney. The consultation document outlines the process by which the preferred route and alignment for the wooden pole trident OHL has been selected. Comments are now sought from statutory authorities, key stakeholders, elected representatives and the public on the routeing process and the preferred alignment described. These comments will inform further consideration of the alignment and the eventual selection of a proposed alignment for which consent will be sought. Consultation on preferred routes was undertaken with statutory authorities and the public in April and May 2018 and this report summarises the results of this process for the overhead line running south from Finstown to South Ronaldsay and Hoy (the Southern section, see Figure 2.1). Consultation on preferred alignments was undertaken with statutory authorities and the public in September 2018 and this report summaries how the preferred alignment was selected. 1.2 Document Structure This Consultation Document comprises the following sections: Section 1: Introduction Section 2: The Proposals Section 3: Route and alignment selection process Section 4: Description of routes Section 5: Comparative appraisal Section 6: Description of alignments Section 7: Comparative appraisal Section 8: Alignment selection Section 9: Consultation on the proposals 1.3 Next Steps Following completion of the consultation process, SHE Transmission will review all comments received from statutory authorities, landowners and the public. Together with further assessment of potential environmental impacts and technical studies, the comments will be used to refine the preferred alignment into a proposed alignment. Final technical and environmental assessment will then be undertaken to provide information to support an application to Scottish Ministers for consent for the construction and operation of the overhead lines (OHLs) under section 37 of the Electricity Act A Report on Consultation will also be produced which will document all consultations received, and the decisions made in light of these responses. The intention is to submit the application for consent in Q
7 2. THE PROPOSALS 2.1 Need for the project SHE Transmission is a wholly owned subsidiary of the SSE plc group of companies. SHE Transmission owns and maintains the electricity transmission network across the north of Scotland and holds a licence under the Electricity Act 1989 to develop and maintain an efficient, co-ordinated and economical system of electricity transmission. The Orkney Islands currently have no 132 kv transmission infrastructure and are served by two 33 kv distribution subsea cables between Rackwick Bay on Hoy, and Murkle Bay near Thurso. These cables were installed in 1982 and 1998 with a total import/export capacity of 40 M. Demand on the islands varies between 7 M in summer and 46 M in winter and a standby diesel generator is located in Kirkwall to secure demand. The current connected embedded generation in Orkney uses all of the capacity of the existing 33 kv cables. At present, there are contracted connection agreements between National Grid and developers in Orkney for 461 M of new generation. This has led to the requirement for a transmission connection between Orkney and mainland Scotland. The development is in line with SHE Transmission s commitment and licence obligations to facilitate the connection of renewables generators to the grid through an economical, efficient and coordinated approach to transmission reinforcement. SHE Transmission has a duty under Section 9 of the Electricity Act 1989 to facilitate competition in the generation and supply of electricity. The preferred route and alignment is the option considered to present the best opportunity to achieve an economically viable, technically feasible and environmentally acceptable connection for two contracted renewable energy developments south of Finstown. 2.2 Project Overview The Proposed Development consists of 132 kv electricity overhead line infrastructure as illustrated on Figures 2.2 and 2.3. The technology solution proposed and appraised is a single circuit double wood pole (H pole) trident OHL. The most common height is anticipated to be 14 m although depending on terrain, the height may vary between 12 m and 17 m. The overall Orkney 132 kv Infrastructure project is required to connect contracted renewable energy developments to the new transmission network at the proposed Finstown substation. Due to its scale the project has been split into two geographical parts in order to achieve the design programme and to enable consent applications to progress in a staged manner. The parts are shown on Figure 2.1 and are: Northern Section (north of Finstown); and Southern Section (south east of Finstown via Burray, South Ronaldsay, Flotta to Hoy). This report considers the southern section only and other sections will be the subject of separate consultation reports. 2-1
8 EC ER Northern Section Route EC Route ER Route FE Southern Section Route FS Route HR Route HS/SH Route RM Route SS FE FS Kilometers ± HR SS SCALE: See Scale Bar SIZE: A3 VERSION: A03 DRAN: B RM HS/SH PROJECT: DATE: 04/09/2018 Figure 2.1 Overview of All Routes CHECKED: KG APPROVED: H PROJECTION: British National Grid SOURCE: OpenStreetMap (and) contributors, CC-BY-SA Path: \\ukedidc01\data\edinburgh\projects\ Orkney - Site selection.kg\00 GIS\MAPS\Overview Figures\ _RouteOverview_A03.mxd
9 Figure 2.2 Example of a trident H wood pole Figure 2.3 Comparison drawing of proposed 132 kv trident H pole against scale of existing 33 kv infrastructure on Orkney 2.3 Construction activities Key tasks during construction will involve: Potential localised improvements to the public road network to allow safe construction access; Establishment of suitable construction compound and laydown areas for materials; Upgrades to existing tracks and potential installation of temporary track solutions where required for safe construction access; Delivery of structures and materials to pole positions; Assembly and erection of wood pole structures and stays; and Stringing of conductors using hauling ropes and winches. Installation of the wood poles would involve the following tasks: Excavation of a suitable area for the wood poles, and backfilling after installation of the pole; In some pole locations, it may be necessary to add imported hardcore backfill around the pole foundations to provide additional stability in areas where the natural sub soils have poor compaction qualities; Conductors would be installed on the wood poles using full tension stringing to prevent the conductor coming into contact with the ground; and Remedial works would be carried out to reinstate the immediate vicinity of the structure, and ground disturbed, to pre-existing use. 2.4 Programme A summary of the indicative development programme is provided in Table
10 Table 2.1 Indicative Development Programme Date Tasks 2016/ 2017 Identify possible overhead line routes. Identify technology options of overhead line routes, and outline designs for substation sites. Development of overhead line routes including site walkovers, desk based assessments and appraisals. 2017/ 2018 Selection of preferred overhead line route options Consider feedback, and make modifications to preferred overhead line routes, as necessary. Confirmation of proposed overhead line routes Baseline environmental surveys of overhead line routes, including bird surveys, otter surveys and habitat surveys. 2018/2019 Identification of preferred overhead line alignments, including pole locations. Screening for the Environmental Impact Assessments (EIAs) and scoping if required Undertake environmental assessments, and modify proposed overhead line alignments as necessary Consider feedback from public consultation events and make amendments, as necessary Submit Section 37 applications for overhead lines 2019/ 2020 Receipt of consents and determination of planning applications 2020 Subject to all consents, construction work starts on site 2022 Construction complete, commissioning and energisation 2-4
11 3. ROUTE AND ALIGNMENT SELECTION PROCESS 3.1 Guidance documents The approach to route and alignment selection is informed by the following SHE Transmission guidance: High Voltage ood Pole Transmission and Distribution Main Interconnector Lines in Rural Landscapes: Detailed Routeing Guidelines (TG_PS_651) High Voltage ood Pole Transmission and Distribution Main Interconnector Lines in Rural Landscapes: Strategic Routeing Principles (Adapted From Holford Rules For Overhead Transmission Line Routeing) (TG-PS-650) Procedures for Routeing Overhead Lines of 132 kv or above, SHE Transmission, The guidance develops a process which aims to balance environmental, technical and economic considerations throughout the route and alignment optioneering process. In consideration of these principles, the method of identifying an environmentally preferred route and alignment in this study has involved the following four key tasks: Identification of the baseline situation; Identification of alternative route/alignment options; Environmental, technical and economic analysis of route/alignment options; and Identification of a preferred route/alignment option. The approach to route selection is informed by SHE Transmission s guidance The SHE Transmission Approach to Routeing of Overhead Lines. This new guidance broadens the basis for routeing decisions to reflect contemporary practice, and ensures environmental, technical and economic considerations are identified and appraised at each stage of the routeing process. The guidance splits a project into six stages, as follows: Pre-Routeing Activities: Selection of proposed connection option Stage 0: Routeing strategy development Stage 1: Corridor Selection Stage 2: Route Selection Stage 3: Alignment Selection Stage 4: Consenting This consultation document presents the appraisal completed at stages 2 and Main Considerations Route options were identified following site appraisals, taking into account the most notable constraints identified during the baseline studies. Considerations have included a review of the steps outlined in the Holford Rules and SHE Transmission s approach to routeing. In summary, the following has been taken into account as far as is practicable at the routeing and alignment selection stages: Avoid if possible major areas of highest amenity value (including those covered by national and international designations and other sensitive landscapes); Avoid by deviation, smaller areas of high amenity value; Try to avoid sharp changes of direction and reduce the number of larger angle towers required; Avoid sky lining the route in key views and where necessary, cross ridges obliquely where a dip in the ridge provides an opportunity; Target the route towards open valleys and woods where the apparent height of towers will be reduced and views broken by trees (avoid slicing through landscape types and try to keep to edges and landscape transitions); Consider the appearance of other lines in the landscape to avoid a dominating or confusing wirescape impact; and 3-1
12 Technical issues related to clearances, connectivity, outages, maintenance and faults. 3.3 Area of search Overhead lines are required between up to six potential new substations in Orkney. Substation site locations will be determined by renewable energy developers at Costa Head, Rendall, South Ronaldsay and East Hoy. A proposed new grid substation location near Finstown has been identified by SHE Transmission. Developer substation site selection is underway and proposed sites are yet to be identified. For the purposes of route selection, route options start and end at a central point in the substation search areas, or where appropriate, cover all substation site options being considered. Routes and alignments between the following start and end points are considered in this document: Finstown to St Mary s (FS) Rinnigill to Melsetter (RM) Hesta Head to Hoxa Head (HS/SH) South Ronaldsay to St Mary s (SS) Hoxa Head to Rinnigill (Flotta) (HR) 3.4 Baseline conditions Initial desk studies established the key environmental features of the study area. Identification of environmental designated sites and other constraints, utilising GIS datasets available via SNHi Site Link and other sources; Identification of archaeological designations and other recorded sites, utilising GIS datasets available via Historic Environment Scotland Data Services and Local Historic Environment Teams; Review of the Orkney Local Development Plan 2017; Review of landscape character assessments of relevance to the study area; Review of ordnance survey mapping (OS) (1:50,000 and 1:25,000 and online GIS data sources from OS OpenData) and aerial photography (where available) to identify other potential constraints such as settlement, properties, walking routes, cycling routes etc.; Extrapolation of OS Vectormap GIS data to identify further environmental constraint including locations of watercourses and waterbodies, roads classifications and degree of slope; and Review of other local information through online and published media such as tourism sites. In addition, a suite of environmental surveys has been undertaken to provide additional baseline information, these covered: Landscape and visual walkover survey by landscape architects; Cultural heritage walkover survey by archaeologists; Bird survey including for wildfowl, raptors, breeding birds and wintering birds; Habitat survey; Otter survey; and Peat survey. Site visits were also undertaken by SHE Transmission OHL engineers and other project team members to help inform the technical and economic appraisal of options. 3.5 Appraisal method Appraisal of route options has involved systematic consideration against the following environmental, technical and economic topic areas: Environmental: 3-2
13 Natural Heritage (Designations, Protected Species, Habitats, Ornithology and Geology, Hydrology and Hydrogeology); Cultural Heritage (Designations and Cultural Heritage Assets); People (proximity to dwellings); Landscape (Designations and Character); and Land Use (Agriculture, Forestry and Recreation). Environmental sensitivity has been considered qualitatively, based on professional judgement and utilising the red, amber, green (RAG) rating. It has been applied to each topic area indicating potential impacts. This rating is based on a three point scale as described in Figure 3.1 below. SSE guidance Procedures for Routeing Overhead Lines of 132 kv or above has been followed. Figure 3.1 RAG Rating for Comparative Analysis Most Preferred Lower Impact Low potential for the development to be constrained Moderate Impact Intermediate potential for the development to be constrained Least Preferred Higher Impact High potential for the development to be constrained 3-3
14 4. DESCRIPTION OF ROUTES 4.1 Identification of sections This report considers the southern section routes of the Orkney Grid Connection Project which are: Finstown to St Mary s (FS) Rinnigill to Melsetter (RM) Hesta Head to Hoxa Head (HS/SH) South Ronaldsay to St Mary s (SS) Hoxa Head to Rinnigill (Flotta) (HR) 4.2 Identification of route options Finstown to St Mary s (FS) Three route options were identified: Route FS heads south along Germiston Road to the west of Loch Kirbiser, turns east along the route of the A964 passing south of Kirkwall before picking up the route of the A961 and a minor road as far as Bay of Cornquoy. Route FS1 passes down the Loch Kirbister Valley to the east of Loch Kirbister before heading east along the A961 and same route as route FS as far as Bay of Cornquoy. Route FS2 runs east from Finstown to the north of the hills as far as ideford Hill before it passes to the south and picks up the same route options FS and FS1 as far as the Bay of Cornquoy. The routes are illustrated on Figures 4.1, 4.2 and 4.3 together with environmental designations. 4-1
15 Listed Building: A B C Scheduled Monument orld Heritage Site Sensitive Ridgeline Proposed OHL Route Other Proposed OHL Route Special Protection Area (SPA) Special Area Conservation (SAC) Ramsar Site Heart of Neolithic Orkney orld Heritage: Site Boundary Site Buffer Zone Site Sensitive Area National Scenic Area RSPB Reserve ildland G G GGardens Designed Landscape G G G Site of Special Scientific Interest (SSSI) Geological Conservation Review Area Proposed SPA ROUTE FS OpenStreetMap (and) contributors, CC-BY-SA ± Kilometres SCALE: See Scale Bar SIZE: A3 PROJECT: VERSION: A01 DRAN: B CHECKED: KG DATE: 21/06/2018 APPROVED: H Figure 4.1 Proposed Overhead Line Route: FS PROJECTION: British National Grid SOURCE: See Map Frame; Reproduced by permission of Ordnance Survey on behalf of HMSO. Crown copyright and database right [2016] all rights reserved. Ordnance Survey Licence number EL273236; Natural England copyright. Contains Ordnance Survey data Crown copyright and database right Path: \\ukedidc01\data\edinburgh\projects\ Orkney - Site selection.kg\00 GIS\MAPS\orking\ _ERMProposedOHLCorridors_Original_A01.mxd
16 Listed Building: A B C Scheduled Monument orld Heritage Site Sensitive Ridgeline Proposed OHL Route Other Proposed OHL Route Special Protection Area (SPA) Special Area Conservation (SAC) Ramsar Site Heart of Neolithic Orkney orld Heritage: Site Boundary Site Buffer Zone Site Sensitive Area National Scenic Area RSPB Reserve ildland G G GGardens Designed Landscape G G G Site of Special Scientific Interest (SSSI) Geological Conservation Review Area Proposed SPA ROUTE FS1 OpenStreetMap (and) contributors, CC-BY-SA ± Kilometres SCALE: See Scale Bar SIZE: A3 PROJECT: VERSION: A01 DRAN: B CHECKED: KG DATE: 21/06/2018 APPROVED: H Figure 4.2 Proposed Overhead Line Route: FS1 PROJECTION: British National Grid SOURCE: See Map Frame; Reproduced by permission of Ordnance Survey on behalf of HMSO. Crown copyright and database right [2016] all rights reserved. Ordnance Survey Licence number EL273236; Natural England copyright. Contains Ordnance Survey data Crown copyright and database right Path: \\ukedidc01\data\edinburgh\projects\ Orkney - Site selection.kg\00 GIS\MAPS\orking\ _ERMProposedOHLCorridors_Original_A01.mxd
17 Listed Building: A B C Scheduled Monument orld Heritage Site Sensitive Ridgeline Proposed OHL Route Other Proposed OHL Route Special Protection Area (SPA) Special Area Conservation (SAC) Ramsar Site Heart of Neolithic Orkney orld Heritage: Site Boundary Site Buffer Zone Site Sensitive Area National Scenic Area RSPB Reserve ildland G G GGardens Designed Landscape G G G Site of Special Scientific Interest (SSSI) Geological Conservation Review Area Proposed SPA ROUTE FS2 OpenStreetMap (and) contributors, CC-BY-SA ± Kilometres SCALE: See Scale Bar SIZE: A3 PROJECT: VERSION: A01 DRAN: B CHECKED: KG DATE: 21/06/2018 APPROVED: H Figure 4.3 Proposed Overhead Line Route: FS2 PROJECTION: British National Grid SOURCE: See Map Frame; Reproduced by permission of Ordnance Survey on behalf of HMSO. Crown copyright and database right [2016] all rights reserved. Ordnance Survey Licence number EL273236; Natural England copyright. Contains Ordnance Survey data Crown copyright and database right Path: \\ukedidc01\data\edinburgh\projects\ Orkney - Site selection.kg\00 GIS\MAPS\orking\ _ERMProposedOHLCorridors_Original_A01.mxd
18 4.2.2 Rinnigill to Melsetter (RM) One route option was identified: Route RM runs from Rinnigill to Melsetter. Given the number of environmental designations and the topography of Hoy, no further route have been identified. The route is illustrated in Figure 4.4 together with environmental designations Hesta Head to South Ronaldsay Switching Station/ South Ronaldsay Switching Station to Hoxa Head (HS/SH) One route option was identified: Route HS/SH heads north from the proposed Hesta Head wind farm east of the A961 before heading west south of St Margaret s Hope to the north of the B9043. The route is illustrated on Figure 4.5 alongside environmental designations. 4-5
19 Listed Building: A B C Scheduled Monument orld Heritage Site Sensitive Ridgeline Proposed OHL Route Other Proposed OHL Route Proposed Subsea Route Special Protection Area (SPA) Special Area Conservation (SAC) Ramsar Site Heart of Neolithic Orkney orld Heritage: Site Boundary Site Buffer Zone Site Sensitive Area National Scenic Area RSPB Reserve ildland G G G Gardens Designed Landscape G G G Site of Special Scientific Interest (SSSI) Geological Conservation Review Area Proposed SPA ROUTE RM OpenStreetMap (and) contributors, CC-BY-SA ± Kilometres SCALE: See Scale Bar SIZE: A3 PROJECT: VERSION: A04 DRAN: B CHECKED: KG DATE: 18/06/2018 APPROVED: H Figure 4.4 Proposed Overhead Line Route: RM PROJECTION: British National Grid SOURCE: See Map Frame; Reproduced by permission of Ordnance Survey on behalf of HMSO. Crown copyright and database right [2016] all rights reserved. Ordnance Survey Licence number EL273236; Natural England copyright. Contains Ordnance Survey data Crown copyright and database right Path: \\ukedidc01\data\edinburgh\projects\ Orkney - Site selection.kg\00 GIS\MAPS\orking\ _ERMProposedOHLCorridors_Revised_A01.mxd
20 Listed Building: A B C Scheduled Monument orld Heritage Site Sensitive Ridgeline Proposed OHL Route Other Proposed OHL Route Special Protection Area (SPA) Special Area Conservation (SAC) Ramsar Site Heart of Neolithic Orkney orld Heritage: Site Boundary Site Buffer Zone Site Sensitive Area National Scenic Area RSPB Reserve ildland G G GGardens Designed Landscape G G G Site of Special Scientific Interest (SSSI) Geological Conservation Review Area Proposed SPA ROUTE HS/SH OpenStreetMap (and) contributors, CC-BY-SA ± Kilometres SCALE: See Scale Bar SIZE: A3 PROJECT: VERSION: A01 DRAN: B CHECKED: KG DATE: 21/06/2018 APPROVED: H Figure 4.5 Proposed Overhead Line Route: HS/SH PROJECTION: British National Grid SOURCE: See Map Frame; Reproduced by permission of Ordnance Survey on behalf of HMSO. Crown copyright and database right [2016] all rights reserved. Ordnance Survey Licence number EL273236; Natural England copyright. Contains Ordnance Survey data Crown copyright and database right Path: \\ukedidc01\data\edinburgh\projects\ Orkney - Site selection.kg\00 GIS\MAPS\orking\ _ERMProposedOHLCorridors_Original_A01.mxd
21 4.2.5 South Ronaldsay to St Mary s (SS) One route option was identified: Route SS heads north east from the proposes switching station on South Ronaldsay to Bu sand on Burray. The route is illustrated in Figure 4.6 together with environmental designations Hoxa Head to Rinnigill (Flotta) (HR) One route option was identified: Route HR passes through the centre part of Flotta. The route is illustrated in Figure 4.7 together with environmental designations. 4-8
22 Listed Building: A B C Scheduled Monument orld Heritage Site Sensitive Ridgeline Proposed OHL Route Other Proposed OHL Route Proposed Subsea Route Special Protection Area (SPA) Special Area Conservation (SAC) Ramsar Site Heart of Neolithic Orkney orld Heritage: Site Boundary Site Buffer Zone Site Sensitive Area National Scenic Area RSPB Reserve ildland G G G Gardens Designed Landscape G G G Site of Special Scientific Interest (SSSI) Geological Conservation Review Area Proposed SPA ROUTE SS OpenStreetMap (and) contributors, CC-BY-SA ± Kilometres SCALE: See Scale Bar SIZE: A3 PROJECT: VERSION: A04 DRAN: B CHECKED: KG DATE: 18/06/2018 APPROVED: H Figure 4.6 Proposed Overhead Line Route: SS PROJECTION: British National Grid SOURCE: See Map Frame; Reproduced by permission of Ordnance Survey on behalf of HMSO. Crown copyright and database right [2016] all rights reserved. Ordnance Survey Licence number EL273236; Natural England copyright. Contains Ordnance Survey data Crown copyright and database right Path: \\ukedidc01\data\edinburgh\projects\ Orkney - Site selection.kg\00 GIS\MAPS\orking\ _ERMProposedOHLCorridors_Revised_A01.mxd
23 Listed Building: A B C Scheduled Monument orld Heritage Site Sensitive Ridgeline Proposed OHL Route Other Proposed OHL Route Proposed Subsea Route Special Protection Area (SPA) Special Area Conservation (SAC) Ramsar Site Heart of Neolithic Orkney orld Heritage: Site Boundary Site Buffer Zone Site Sensitive Area National Scenic Area RSPB Reserve ildland G G G Gardens Designed Landscape G G G Site of Special Scientific Interest (SSSI) Geological Conservation Review Area Proposed SPA ROUTE HR OpenStreetMap (and) contributors, CC-BY-SA ± Kilometres SCALE: See Scale Bar SIZE: A3 PROJECT: VERSION: A04 DRAN: B CHECKED: KG DATE: 18/06/2018 APPROVED: H Figure 4.7 Proposed Overhead Line Route: HR PROJECTION: British National Grid SOURCE: See Map Frame; Reproduced by permission of Ordnance Survey on behalf of HMSO. Crown copyright and database right [2016] all rights reserved. Ordnance Survey Licence number EL273236; Natural England copyright. Contains Ordnance Survey data Crown copyright and database right Path: \\ukedidc01\data\edinburgh\projects\ Orkney - Site selection.kg\00 GIS\MAPS\orking\ _ERMProposedOHLCorridors_Revised_A01.mxd
Rannoch 132 / 33 kv Substation Extension
Who we are Scottish and Southern Energy Power Distribution is part of the SSE plc group of companies. We own, maintain and invest in the networks in the north of Scotland the electricity transmission network
More informationDorenell Wind Farm 132 kv Grid Connection
Who We Are Scottish and Southern Energy Power Distribution is part of the SSE plc group of companies. We own, maintain and invest in the electricity networks in the north of Scotland the electricity transmission
More informationRoute Alignment Options Summary Report
Brechfa Forest Connection Project February 2014 Summary report 1. RSK Environment Ltd (RSK) was commissioned by Western Power Distribution (WPD) to provide environmental consultancy support services for
More informationAssessing the impact of smallscale wind energy proposals on the natural heritage
Scottish Natural Heritage Assessing the impact of smallscale wind energy proposals on the natural heritage Guidance March 2016 Version 3 1 Contents 1. Introduction. 3 2. Encouraging a spatial approach
More informationConsultation Document - Alignment Selection. Creag Dhubh substation to Dalmally substation. 275kV Overhead Line REF: LT000029
Consultation Document - Alignment Selection Creag Dhubh substation to Dalmally substation 275kV Overhead Line REF: LT000029 Approved for publication The owner of this document Name: Paul McQuillan Job
More informationIntroduction. Who we are. Purpose of this public consultation
Introduction Who we are Purpose of this public consultation SHE Transmission are proposing to submit a planning application for our proposed Development of a High Voltage Direct Current Switching Station
More informationCaithness HVDC Switching Station Pre Application Consultation Event. August 2016
Caithness HVDC Switching Station Pre Application Consultation Event August 2016 Introduction Who we are Purpose of this public consultation Other SSE Businesses SHE Transmission are proposing to submit
More informationGUIDELINES FOR THE ROUTEING OF NEW HIGH VOLTAGE OVERHEAD TRANSMISSION LINES
The Holford Rules Guidelines on overhead line routeing were first formulated in 1959 by Sir William later Lord, Holford, who was a part-time member of the CEGB. National Grid has reviewed these guidelines,
More information7. The Landscape. 7.1 Introduction. Environmental Impact Statement (EIS) Scoping Report
7. The Landscape 7.1 Introduction The purpose of this section of the EIS Scoping Report is to describe the scope of work and methods to be applied in the identification and assessment of landscape and
More informationTOPIC PAPER 2: Links to other sustainability tools
TOPIC PAPER 2: INTRODUCTION 1.1 Landscape Character Assessment can inform a range of other sustainability tools and methodologies. Equally these other tools may assist in reaching decisions concerning
More informationAn Bord Pleanála. Eirgrid Plc. Meath County Council Cavan County Council Monaghan County Council
An Bord Pleanála Ref: PL02.VS0002 Prospective Applicant: Eirgrid Plc. Local Authorities: Meath County Council Cavan County Council Monaghan County Council Nature of Application: Written opinion on information
More informationHigh Speed Rail (London- West Midlands)
High Speed Rail (London- West Midlands) Draft Environmental Minimum Requirements Annex 3: Draft Heritage Memorandum November 2013 ESA 4.4 High Speed Rail (London- West Midlands) Draft Environmental Minimum
More informationOur approach to the design and routeing of new electricity transmission lines
Our approach to the design and routeing of new electricity transmission lines 2012 National Grid s job is to connect people to the energy they use to warm and light their homes, to connect factories and
More informationExamination of South Cambridgeshire Local Plan
Matter SC6A - Policy SS/5 Waterbeach New Town Historic England( formerly English Heritage) 874 Rep Nos 59748, 60250, 60253 Examination of South Cambridgeshire Local Plan Historic England, Hearing Statement
More informationPerth and Kinross Council Development Management Committee 20 February 2013 Report of Handling by Development Quality Manager
Perth and Kinross Council Development Management Committee 20 February 2013 Report of Handling by Development Quality Manager 4(4)(iii) 13/81 Erection of sports hall, associated changing facilities, offices
More information9 Archaeology & Cultural Heritage
High Clachaig Wind Farm Scoping Report Page 56 9 Archaeology & Cultural Heritage 9.1 Introduction Cultural heritage in this context means the above- and below-ground archaeological resources, built heritage,
More informationCaithness HVDC Switching Station Consultation
Caithness HVDC Switching Station Consultation March 2016 Aberdeen Who are we? Building the North s future energy network The north of Scotland s electricity network is currently seeing the most sustained
More informationPURPOSE OF MEETING MEETING GUIDELINES PROJECT BACKGROUND ESKOM CLOCOLAN-FICKSBURG 88 KV POWERLINE, FREE STATE
ESKOM CLOCOLAN-FICKSBURG 88 KV POWERLINE, FREE STATE DRAFT BASIC ASSESSMENT REPORT PUBLIC REVIEW LANDOWNERS MEETING FICKSBURG 23 JULY 2013 T his project is being conducted on behalf of Eskom PRESENTATION
More informationvolume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08
DESIGN MANUAL FOR ROADS AND BRIDGES volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08 glossary of terms Used in DMRB Volume 11, Sections 1 and 2 SUMMARY This
More informationIdentify matters regarding the project which inform the preparation of the Environmental Impact Statement (EIS);
3 SCOPING THE EIS 3.1 INTRODUCTION 1 Consultation is an important part of the Environmental Impact Assessment (EIA) process; in this context, consultation with statutory agencies, interested parties, the
More informationPerth and Kinross Council Development Management Committee 24 April 2013 Report of Handling by Development Quality Manager
Perth and Kinross Council Development Management Committee 24 April 2013 Report of Handling by Development Quality Manager Alterations,Carpenter House, Carpenter Street, Perth, PH1 5GB Ref. No: 13/00303/FLL
More informationPerth and Kinross Council Development Control Committee 28 November 2012 Report of Handling by Development Quality Manager
Perth and Kinross Council Development Control Committee 28 November 2012 Report of Handling by Development Quality Manager 4(3)(iii) 12/538 Erection of a 90m meteorological monitoring structure for a temporary
More information6B.1 INTRODUCTION B.1.1 Background B.1.2 Purpose of the Study... 2
CONTENTS 6B.1 INTRODUCTION... 1 6B.1.1 Background... 1 6B.1.2 Purpose of the Study... 2 6B.2 STUDY METHODOLOGY... 3 6B.2.1 Approach... 3 6B.2.2 Collation of Baseline... 3 6B.2.3 Consultation... 4 6B.2.4
More informationTandridge Local Plan Assessing the Ecological Suitability of 183 sites considered for development Tandridge District Council, Surrey
Tandridge Local Plan Assessing the Ecological Suitability of 183 sites considered for development Tandridge District Council, Surrey PLANNING I DESIGN I ENVIRONMENT 1.0 INTRODUCTION TEP conducted Site
More informationTara Skryne Landscape Conservation Area Project: Progress Report: Phase 1
Tara Skryne Landscape Conservation Area Project: Progress Report: Phase 1 A partnership project between Meath County Council, the Heritage Council and the Department of Environment, Heritage and Local
More informationPolicy DM19: Development and Nature Conservation
Avonmouth Wetland Habitat Project October 2010 and December 2011 (the Cresswell study). Policy Links Bristol Local Plan Core Strategy Lead Policy BCS4: Avonmouth and Bristol Port BCS9: Green Infrastructure
More informationNewcombe House & Kensington Church Street
Newcombe House & Kensington Church Street Archaeological Evaluation September 2017 Summary Site name: Newcombe House, Kensington Church Street, Notting Hill, London Grid reference: TQ 25318 80372 Site
More informationCONSULTING SERVICES FOR THE WHITEBELT VISIONING EXERCISE ADDENDUM TO THE GTA WEST LAND USE STUDY WORK PROGRAM
CONSULTING SERVICES FOR THE WHITEBELT VISIONING EXERCISE ADDENDUM TO THE GTA WEST LAND USE STUDY 1. Introduction WORK PROGRAM The Town of Caledon is a large, local municipality located in the Greater Toronto
More informationDelegated Report. Application Type: Full Planning Permission. Recommendation - Approve subject to conditions. Ward - Wigtown West
Steve Rogers Head of Planning & Regulatory Services Kirkbank, English Street, Dumfries, DG1 2HS Telephone (01387) 260199 - Fax (01387) 260188 Delegated Report CHANGE OF USE OF PART OF ARTILLERY RANGE TO
More informationEbbsfleet Development Corporation
Title of Paper Planning and Housing Delivery Report September 2018 Presented by Sub-Committee Mark Pullin, Chief Planning Officer Planning Committee Purpose of Paper and Executive Summary This paper provides
More informationPerth and Kinross Council Development Management Committee 8 June Pre-Application Report by Development Quality Manager
Perth and Kinross Council Development Management Committee 8 June 2016 5(3)(i) 16/259 Pre-Application Report by Development Quality Manager Residential development at St Martins Road, Land 120 metres West
More informationCAIRNGORMS NATIONAL PARK AUTHORITY
Title: Prepared by: CONSULTATION FROM ANGUS COUNCIL KATHERINE DONNACHIE, PLANNING OFFICER (DEVELOPMENT MANAGEMENT) DEVELOPMENT PROPOSED: (1) ERECTION OF GAIA TURBINE OF 18 M. HUB HEIGHT AND 23.5 M. TO
More informationLower Sensitivity. VS Classification Level 2: Exposed Upland/Plateau
S05 Y Moelwynion Reproduced from the Ordnance Survey map with the permission of Ordnance Survey on behalf of the Controller of Her Majesty s Stationery Office, Crown copyright Licence No. 100023387 Location
More informationEnvironmental Assessment (Scotland) Act 2005: Clackmannanshire Council Sustainability Strategy Scoping Request
TAYSIDE & CLACKMANNANSHIRE Tel: 01738 458582(direct line) Fax: 01738 458616 e-mail addresses: denise.reed@snh.gov.uk Niall Urquhart Team Leader Sustainability Clackmannanshire Council Kilncraigs Greenside
More informationCORRECTIONS WITHIN DESIGN MANUAL FOR ROADS AND BRIDGES AUGUST 2009
DESIGN MANUAL FOR ROADS AND BRIDGES CORRECTIONS WITHIN DESIGN MANUAL FOR ROADS AND BRIDGES AUGUST 2009 SUMMARY OF CORRECTION HA 200/08 VOLUME 11, SECTION 1, PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL
More informationProposed 132kV Grid Connection to Lorg and Longburn Wind Farms
Proposed 132kV Grid Connection to Lorg and Longburn Wind Farms Routeing Consultation Report REPORT N O 70016687-001 LORG AND LONGBURN GRID CONNECTION ROUTEING CONSULTATION REPORT APRIL 2017 ii TABLE OF
More informationCAIRNGORMS NATIONAL PARK AUTHORITY
Title: REPORT ON CALLED-IN PLANNING APPLICATION Prepared by: KATHERINE DONNACHIE (SENIOR PLANNING OFFICER, DEVELOPMENT MANAGEMENT) DEVELOPMENT PROPOSED: FULL PLANNING PERMISSION FOR REPLACEMENT BRIDGE
More informationAlternative Route Selection
Alternative Route Selection Multiple routes are developed within the Alternative Corridors Developed by Project Team taking into account all information gathered to date Buildings St. Vital Station to
More informationDESIGN AND MANAGEMENT OBJECTIVES PART 5 HA 90/01 PLANNING AND POLICY FEATURES SUMMARY
DESIGN MANUAL FOR ROADS AND BRIDGES VOLUME 10 SECTION 0 ENVIRONMENTAL DESIGN AND MANAGEMENT ENVIRONMENTAL OBJECTIVES PART 5 HA 90/01 PLANNING AND POLICY FEATURES SUMMARY This Advice Note describes the
More informationReplacement Golf Course Facilities and Residential Development, Churston. Environmental Statement Non-Technical Summary
Replacement Golf Course Facilities and Residential Development, Churston Environmental Statement Non-Technical Summary July 2011 Reproduced from the Ordnance Survey s map with the permission of the Controller
More informationPANSHANGER QUARRY, Hertfordshire
PANSHANGER QUARRY, Hertfordshire Proposed enhanced restoration of Phases F & H Briefing Note 1 March 2015 INERT (INACTIVE) RESTORATION MATERIALS, CONTROLS AND OPERATIONS 1 Introduction This briefing note
More informationTOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997
TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997 APPEAL AGAINST REFUSAL OF PLANNING PERMISSION FOR CONSTRUCTION OF WIND FARM, CONSISTING OF ERECTION OF 12 NO. WIND TURBINES, HEIGHT OF 70 METRES TO HUB, ASSOCIATED
More informationAlternative Routes. St. Vital to La Verendrye Station - Southern Loop Transmission Corridor. 20 different segments 4 segments common to all routes
Alternative Routes St. Vital to La Verendrye Station - Southern Loop Transmission Corridor In a fixed right-of-way St. Vital to Letellier Station 20 different segments 4 segments common to all routes Goal
More informationWind energy development in the South Pennines landscape
Wind energy development in the South Pennines landscape Programme for today Background Policy context South Pennines landscape Impacts of wind energy development The South Pennines Wind Energy Landscape
More informationBREEDON NORTHERN LIMITED
Non Technical Summary CONTENTS 1 INTRODUCTION... 1 2 SITE DESCRIPTION... 1 3 DESCRIPTION OF THE DEVELOPMENT... 6 4 NEED FOR THE DEVELOPMENT... 8 5 KEY ISSUES CONSIDERED IN THE ENVIRONMENTAL IMPACT ASSESSMENT...
More informationHeart of Neolithic Orkney World Heritage Site: Statement of Outstanding Universal Value
Heart of Neolithic Orkney World Heritage Site: Statement of Outstanding Universal Value Adopted by UNESCO World Heritage Committee Thirty-seventh session, Phnom Penh, Cambodia, June 2013 http://whc.unesco.org/en/list/514
More informationWyvern Park Skipton Environmental Statement. Non-technical Summary - April 2015
Wyvern Park Skipton Environmental Statement Non-technical Summary - April 2015 BWB Consulting Ltd Whitehall Waterfront 2 Riverside Way Leeds LS1 4EH Telephone: +44(0)113 233 8000 Copyright This Report
More informationArchaeological Monitoring of Land at 29 Royal Pier Road, Gravesend, Kent
Archaeological Monitoring of Land at 29 Royal Pier Road, Gravesend, Kent Site Code ROY/WB/15 Report for Dr Maxted Date of report 06/10/2015 SWAT ARCHAEOLOGY Swale and Thames Archaeological Survey Company
More informationGuide to Transmission Equipment Maintenance
Guide to Transmission Equipment Maintenance March 2018 Revision History Issue Date Update 1 September 2013 First Issue 2 March 2016 Updated in response to SEM-15-071 Decision Paper Outturn Availability.
More informationRURAL ZONE - POLICY. Rural Zone Policy. Issue: Rural Environment. Ruapehu District Plan Page 1 of 8
Rural Zone Policy RU2 RURAL ZONE - POLICY RU2.1 Introduction The natural resources of the rural environment in the Ruapehu District provide the basis for the existing and potential character, intensity
More informationForm to Submit Land for Residential Evidence Gathering Shepway Strategic Housing Land Availability Assessment (SHLAA) Partial Review
Form to Submit Land for Residential Evidence Gathering Shepway Strategic Housing Land Availability Assessment (SHLAA) Partial Review All organisations and individuals who wish to put forward land for consideration
More informationCircular L8/08 2 September Water Services Investment and Rural Water Programmes Protection of Natural Heritage and National Monuments
Circular L8/08 2 September 2008 Water Services Investment and Rural Water Programmes Protection of Natural Heritage and National Monuments 1. The purpose of this Circular is to provide local authorities
More informationThank you for coming. We want to hear your views on proposed improvements to the A1 between junction 65 (Birtley) and junction 67 (Coal House).
Welcome Thank you for coming. We want to hear your views on proposed improvements to the between junction 65 (Birtley) and junction 67 (Coal House). This is your opportunity to provide comments on our
More informationAndershaw to Coalburn 132kV Overhead Line Environmental Statement. April 2009
Andershaw to Coalburn 132kV Overhead Line Environmental Statement April 2009 This document has been prepared by Faber Maunsell Limited ( Faber Maunsell ) for the sole use of our client (the Client ) and
More informationEnvironmental Impact Assessment
Environmental Impact Assessment Environmental impact assessment (EIA) is the process of systematically drawing together an assessment of the likely significant environmental effects of a development project.
More informationCAIRNGORMS NATIONAL PARK AUTHORITY
DEVELOPMENT PROPOSED: Removal of Gravel Embankments at Allt an t-slugain, Invercauld Estate, Braemar REFERENCE: 2016/0082/DET APPLICANT: Scottish Natural Heritage DATE CALLED-IN: 5 th April 2016 RECOMMENDATION:
More informationREFERENCE: B/03745/12 Received: 02 October 2012 Accepted: 05 October 2012 WARD(S): Totteridge Expiry: 30 November 2012.
LOCATION: 15A Pyecombe Corner, London, N12 7AJ REFERENCE: B/03745/12 Received: 02 October 2012 Accepted: 05 October 2012 WARD(S): Totteridge Expiry: 30 November 2012 Final Revisions: APPLICANT: PROPOSAL:
More informationThe Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion
Mr Graham Clark Berrys Newchurch Farm Kinnersley Hereford HR3 6QQ BY EMAIL The Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion SC/2017/0001
More informationLAND AT WEST YELLAND. Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP
LAND AT WEST YELLAND Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP May 2014 Quality Management Issue/revision Issue 1 Revision 1 Revision 2 Revision 3 Remarks Draft FINAL Date
More informationMAKING SENSE OF PLACE
MAKING SENSE OF PLACE Landscape Character Assessment Summary Guidance for England and Scotland MAKING SENSE OF PLACE People can welcome development if it is well designed and contributes to quality of
More informationWelcome to the Public Consultation Exhibition
Welcome to the Public Consultation Exhibition Today is your opportunity to: Speak to the team Learn more about the project Leave feedback on the plans The Secretary of State for Transport has recognised
More informationA21. Start of works exhibition Tonbridge to Pembury. Welcome. Dualling Scheme
Welcome We would like to welcome you to our start of works exhibition for the. On display you will see information about what is currently taking place and what will be happening during the coming months
More informationPRESENTATION TO THE CROSS PARTY GROUP ON ARCHITECTURE AND THE BUILT ENVIRONMENT A MANIFESTO FOR THE BUILT EMVIRONMENT
PRESENTATION TO THE CROSS PARTY GROUP ON ARCHITECTURE AND THE BUILT ENVIRONMENT A MANIFESTO FOR THE BUILT EMVIRONMENT Scottish Parliament 6 October 2015 1 Photo Mark Turnbull Introduction to Landscape
More informationLand East of Cromwell Lane
Land East of Cromwell Lane VISION DOCUMENT AUGUST 2016 The proposals for Land East of Cromwell Lane will be defined by existing landscape features, ensuring that the development offers a quality place
More informationSite Assessment Technical Document Appendix A: Glossary
Central Bedfordshire Council www.centralbedfordshire.gov.uk Site Assessment Technical Document Appendix A: Glossary July 2017 1.1.11-1 - ii Appendix A: Glossary Term Agricultural Land Classification AONB
More informationInterim Advice Note 76 / 06 ASSESSMENT PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL ASSESSMENT. Contents
Interim Advice Note 76 / 06 VOLUME 11 SECTION 1: ENVIRONMENTAL ASSESSMENT INTRODUCTION PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL ASSESSMENT Contents 1. Introduction and Application 2. Aims and Objectives
More informationProposed St. Vital Transmission Complex
Proposed St. Vital Transmission Complex Round 2 Preferred Route for the St. Vital to Letellier Line What is it? Manitoba Hydro is proposing construction of two 230-kilovolt (kv) transmission lines to improve
More informationKier Infrastructure and Overseas Limited Greenburn Surface Mine, Dalgig Farm Site
Kier Infrastructure and Overseas Limited Greenburn Surface Mine, Dalgig Farm Site Planning application pursuant to s.42 Town and Country Planning (Scotland) Act 1997 to amend the restoration scheme Volume
More informationNOTICE OF PREPARATION
Date: June 30, 2017 CITY OF CITRUS HEIGHTS COMMUNITY & ECONOMIC DEVELOPMENT DEPARTMENT, PLANNING DIVISION 6360 Fountain Square Drive, Citrus Heights, CA 95621 (916) 727-4740 NOTICE OF PREPARATION To: Subject:
More informationReport reference: LT/WTE/LZH/1655/01/SCOPING June 2015
PROPOSALS FOR THE SCOPE AND CONTENT OF AN APPLICATION FOR PLANNING PERMISSION AND AN ENVIRONMENTAL STATEMENT FOR THE EXTRACTION OF LIMESTONE FROM EXTENSION AREAS AT WHITWELL QUARRY, DERBYSHIRE Report reference:
More information14 Visual Amenity 14-1
Visual Amenity 14 CONTENTS 14 Visual Amenity 14.1 14.1 Introduction Introduction 14.2 14.2 Project Setting Project Setting 14.3 14.3 Project Overview Project Overview 14.4 14.4 Viewing Locations Viewing
More informationPHASE 1 ARCHAEOLOGICAL IMPACT ASSESSMENT PROPOSED DEVELOPMENT ERF 3 ROBERTSON WESTERN CAPE PROVINCE
PHASE 1 ARCHAEOLOGICAL IMPACT ASSESSMENT PROPOSED DEVELOPMENT ERF 3 ROBERTSON WESTERN CAPE PROVINCE Prepared for BOLAND ENVIRO Att: Mr Nik Wullschleger PO Box 250 Worcester 6849 Fax: (023) 347 0336 By
More informationLondon Road, Derker. Non Technical Summary. Introduction
London Road, Derker Non Technical Summary Introduction The Oldham Rochdale Housing Market Pathfinder was set up to tackle longstanding problems of poor quality housing and to provide the framework for
More informationVelindre Cancer Centre Environmental Statement Vol.1: Environmental Statement Text. Chapter 1: Introduction
Velindre Cancer Centre Environmental Statement Vol.1: Environmental Statement Text Chapter 1: Introduction Draft - March 2017 Prepared by: Address: Email: Website: Mott McDonald, The Urbanists and HLM
More informationHERITAGE POLICY...Safeguarding the Built Heritage. Conservation Plans. A Guide to the Preparation of Conservation Plans
HERITAGE POLICY...Safeguarding the Built Heritage Conservation Plans A Guide to the Preparation of Conservation Plans 1 2 1.0 INTRODUCTION 1.1 Scotland has a diverse built heritage: ancient monuments and
More informationNorth Wales Wind Farm Connections. Route Corridor Report
North Wales Wind Farm Connections Route Corridor Report May 2013 Contents Section 1.0 Section 2.0 Section 3.0 Section 4.0 Section 5.0 Section 6.0 Figures: Figure 1.1 Figure 1.2 Figure 4.1 Figure 4.2 Figure
More informationOverhead Line Insulators
Electricity Specification 400I4 Issue 4 January 2016 Overhead Line Insulators Contents 1 Introduction 2 Scope 3 Definitions 4 General Requirements for Approvals and Testing 5 Requirements for Type and
More informationPUBLIC NOTICE UNDER CLAUSE 5 OF SCHEDULE 1 OF THE RESOURCE MANAGEMENT ACT 1991 PLAN CHANGE 12 TO THE OPERATIVE CITY OF NAPIER DISTRICT PLAN
PUBLIC NOTICE UNDER CLAUSE 5 OF SCHEDULE 1 OF THE RESOURCE MANAGEMENT ACT 1991 PLAN CHANGE 12 TO THE OPERATIVE CITY OF NAPIER DISTRICT PLAN Public notice is given in accordance with Clause 5 of Schedule
More informationUTT/17/2075/FUL - (BERDEN) (Referred to Committee by Councillor Janice Loughlin. Reason: In the Public Interest)
UTT/17/2075/FUL - (BERDEN) (Referred to Committee by Councillor Janice Loughlin. Reason: In the Public Interest) PROPOSAL: LOCATION: APPLICANT: Amendments to the design of a scheme for a 49.99MW battery
More informationTown of Cobourg Heritage Master Plan. Statutory Public Meeting
Town of Cobourg Heritage Master Plan Statutory Public Meeting April 25 th 2016 Presentation Overview 1. Introduction 2. Project background and schedule overview 3. Review of strategic direction content
More informationPublic Consultation. Land at Monks Farm, North Grove. Welcome
Welcome Welcome to our public exhibition for development on Land at Monks Farm, orth Grove. Gallagher Estates and Gleeson Strategic Land are preparing an outline planning application for new homes, open
More informationNatural Heritage Guidance and Information. 6 th of December 2007 Brendan Turvey
Natural Heritage Guidance and Information 6 th of December 2007 Brendan Turvey Outline Guidance available New guidance Guidance in the pipeline Revision of SLG Sitelink / Natural spaces Wind farm footprint
More information3. Highway Landscaping Assessment
Guidelines for Highway Landscaping 3-1 3. Highway Landscaping Assessment 3.1 Introduction This section outlines the steps necessary to assess the highway landscaping component of a state highway construction
More informationorld Heritage Site W
World Heritage Site Stonehenge Historic England Avebury Henge and Stone Circle Historic England The Great Wall of China The Pyramids of Giza, Egypt Stonehenge Mike Goddard Stonehenge and Avebury WHS Vision
More informationSettlement Boundaries Methodology North Northumberland Coast Neighbourhood Plan (August 2016)
Introduction This background paper sets out a methodology for the definition of settlement boundaries in the North Northumberland Coast Neighbourhood Plan. The neighbourhood plan is planning positively
More informationRequest for a Scoping Opinion by Provectus. Proposed Surface Mining of Coal on Land west off the A61, Hill Top Farm, Clay Cross, Derbyshire
Request for a Scoping Opinion by Provectus Proposed Surface Mining of Coal on Land west off the A61, Hill Top Farm, Clay Cross, Derbyshire January 2012 Contents 1 Introduction & Background... 1 2 Site
More informationGrantham Southern Quadrant Link Road Environmental Statement
Grantham Southern Quadrant Link Road Environmental Statement Non Technical Summary Introduction Lincolnshire County Council (LCC) is submitting a planning application for the proposed implementation of
More informationREPORT CLIENT: COMPANY: EirGrid PLC The Oval 160 Shelbourne Road Ballsbridge Dublin 4
REPORT PROJECT: Grid West Project CLIENT: EirGrid PLC The Oval 160 Shelbourne Road Ballsbridge Dublin 4 COMPANY: TOBIN Consulting Engineers Block 10-4 Blanchardstown Corporate Park Dublin 15 www.tobin.ie
More informationLand to the North of Main Road, Wybunbury
Land to the North of Main Road, Wybunbury Environmental Statement Non-Technical Summary November 2014 Land to the North of Main Road, Wybunbury Environmental Statement Non-Technical Summary Prepared on
More informationNON TECHNICAL SUMMARY
CONTENTS Introduction...1 Site Setting and Description...3 Proposed Development...3 Proposed Time Extension...4 Proposed Lateral Extension...4 Improvement of the main access road (Downs Lane)...4 Restoration
More informationCape Environmental Assessment Practitioners(Pty)
BACKGROUND INFORMATION DOCUMENT (BID) Introduction Cape Environmental Assessment Practitioners(Pty) Ltd Reg. No. 2008/004627/07 Telephone: (044) 874 0365 First Floor, Eagles View Building Facsimile: (044)
More informationFinal Revisions: Reason: For the avoidance of doubt and in the interests of proper planning.
LOCATION: Totteridge Village Hall, Badgers Croft, London, N20 8AH REFERENCE: B/01780/12 Received: 11 May 2012 Accepted: 25 May 2012 WARD(S): Totteridge Expiry: 20 July 2012 Final Revisions: APPLICANT:
More informationLeaside to Main Infrastructure Refurbishment Project
N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:22 PM Page 1 Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood N6667_Leaside
More informationCITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016
Item 11, Report No. 38, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan on November 15, 2016. Regional Councillor Di Biase declared an interest
More informationVaughan Metropolitan Centre (VMC) Black Creek Renewal CLASS ENVIRONMENTAL ASSESSMENT
PUBLIC INFORMATION CENTRE Vaughan Metropolitan Centre (VMC) Black Creek Renewal Wednesday, May 10, 2017 6:00 p.m. to 8:00 p.m. Add photo Project Management, Environmental Assessment, Stormwater Management
More informationNorthbury Farm, Castle End Road, Ruscombe, Berkshire
Northbury Farm, Castle End Road, Ruscombe, Berkshire An Archaeological Watching Brief For Sir Colin and Lady Southgate by Danielle Milbank Thames Valley Archaeological Services Ltd Site Code NFR 07/120
More informationResponse by The Dartington Hall Trust
Consultation Response by The Dartington Hall Trust Site Reference: SH_39_02_08/13 Contents Introduction 1 Site Description 2 Development Proposal and Context 3 Site Technical Assessment 4 Planning Policy
More informationFinal Revisions: Provision of single storey modular classroom and associated works.
LOCATION: St Catherines Catholic Primary School, Vale Drive, Barnet, Herts, EN5 2ED REFERENCE: B/01924/12 Received: 17 May 2012 Accepted: 28 May 2012 WARD(S): Underhill Expiry: 23 July 2012 Final Revisions:
More informationCardiff International Sports Village Waterfront Development Volume IV : Non-Technical Summary of the Environmental Statement
Greenbank Partnerships Ltd October 2012 Cardiff International Sports Village Waterfront Development Volume IV : Non-Technical Summary of the Environmental Statement Environmental Statement - Non Technical
More informationScottish Hydro Electric Transmission Visual Impact of Scottish Transmission Assets (VISTA) Inverness 11 November 2015
Scottish Hydro Electric Transmission Visual Impact of Scottish Transmission Assets (VISTA) Inverness 11 November 2015 Content 1. Background 2. What's changed? 3. Who is involved? 4. Why are we consulting?
More information