PHASE III: Reserved Matters Submission

Size: px
Start display at page:

Download "PHASE III: Reserved Matters Submission"

Transcription

1 Statement of Compliance with the outline approval for the proposed residential development of land at: BURGES LANE, WIVELISCOMBE PHASE III: Reserved Matters Submission

2 Foreword Contents: This Statement of Compliance has been produced by pad Design on behalf of Lone Star Land in support of the reserved matters submission package for Land at Burges Lane, Wiveliscombe, Phase 3, and the detail provided of layout, scale, and appearance. The detail of the landscape design will be submitted at a later date. pad Design, 2015 Background... 1 Development Principles... 2 Use & Amount... 3 Layout... 4 Scale... 6 Access... 7 Appearance & Landscape... 8 Summary... 9 issue record date 29/04/15 document draft revision - author checked authorised NH MNR MNR

3 Background Outline permission was granted, in February 2014 for the erection of up to 71 dwellings with associated access and infrastructure (application ref: 49/13/0015). The outline permission is subject to 8 conditions. This submission pack will discharge conditions 1 and 2 in relation to the detail of the reserved matters for layout, scale and appearance. The approved Design and Access Statement, approved as part of the outline application, and referred to throughout this document as the 'approved document', establishes the context of the development and sets out the principle of development and the parameters in respect of use and amount, layout, scale, access and appearance. This reserved matters submission package includes: 13115_1030 Location Plan 13115_5000 Planning Layout 13115_5001 Materials Layout 13115_ House Type Drawings 13115_7001 Street Scenes Condition 1 requires the approval of the details of the layout, scale, appearance and landscaping of the site shall be obtained from the Local Planning Authority in writing before any development is commenced. Condition 2 requires that the development shall be carried out in accordance with the following plans and this document will demonstrate how the proposed detailed design is in accordance with this requirement: 13115/1030A Location Plan 13115/4010A Access and Movement Parameter Plan 13115/1000A Illustrative Framework Plan 13115/1030B Location Plan This document will refer to the structure of the Design section of the approved document to demonstrate how the scheme design is in accordance with the outline approval. This document demonstrates the compliance of the proposed detail included as part of this reserved matters submission with the approved document. This document will also provide further detail in respect of the reserved matters, where appropriate. 1

4 Development Principles The detail included implements the vision for a high quality residential development that will create a sustainable extension to Phases 1 and 2 of Land at Burges Lane, Wiveliscombe. The scheme implements a well designed, locally distinctive, residential development that follows the principles of sustainable development. The scheme delivers 71 new homes that includes a mix of housing types and tenures to encourage a mixed and socially inclusive community. The scheme integrates the new development with its surroundings. This is in accordance with the General Objectives of the Development Principles set out within the approved document. The scheme design retains and enhances valuable visual and ecological landscape structure where possible, and new planting, including additional trees, hedges and shrubs provides environmental enhancement. Safe pedestrian links and routes have been included as part of the detailed layout. This is in accordance with the Environmental Objectives of the Development Principles set out within the approved document. A range of densities have been implemented across the site, delivering an average of 30 dwellings per hectare across the site, this is appropriate to the site, context and local planning policy. The scheme implements a sequence of key spaces, identified through key buildings and distinction of material or building element, to aid in legibility through the site. The scheme implements the block structure set out in the outline approval, the framework plan and the approved document, maximising the potential and quality of out of the site. Where the development backs onto existing development (along the western boundary, onto phase 1), a minimum back to back distance of 28m has been implemented to ensure that the privacy of surrounding residents are protected. This is in accordance with the Development Objectives of the Development Principles set out within the approved document The scheme has been designed through the principles of Secured by Design, providing active streets and a clear definition of public and private realms, providing a safe and secure environment. 2

5 Use & Amount The approved document establishes how the site can deliver a residential development appropriate to its context, including the following key elements: approximately 70 residential dwellings (permission is granted for up to 71 dwellings) delivered at an average density of 30 dwellings per hectare across the site a mix of housing types and sizes that will reflect local context and serve local need a range of tenure including a mix of affordable housing to be agreed with the Local Authority The proposed scheme that forms this reserved matters submission is for 71 new residential dwellings. The scheme is delivered at 30 dwellings per hectares across the site, with localised ranges, reflecting different housing types and arrangements, and responding to their context. There is a range of housing types, including 1, 2, 3 and 4 bed houses. The housing range includes an element of affordable house types. This was agreed to be delivered at 25% and the detail set out in the Section 106 Agreement that was signed in February The affordable housing mix includes 18 dwellings and is provided at 60% socially rented accommodation and 40% intermediate housing, that includes shared equity and low cost homes. Indicative description Unit Number NO. Of Beds HOUSE TYPE A 10 2 HOUSE TYPE B 9 3 HOUSE TYPE C 8 3 HOUSE TYPE D 2 3 HOUSE TYPE E 8 4 HOUSE TYPE F 4 4 HOUSE TYPE G (V1) 1 4 HOUSE TYPE G (V2) 4 4 HOUSE TYPE H 4 3 HOUSE TYPE J 3 4 1B 2P 3 1 2B 4P (V1) 9 2 2B 4P (V2) 1 2 3B 6P 5 3 Total 71 Schedule of accommodation This is in accordance with the approved document and with the detail set out in the Section 106 agreement. 3

6 Layout The approved document proposes a series of design principles to be implemented within the proposed layout. The approved framework plan within the approved document indicates how these design principles could be implemented and the proposed detailed layout, as shown opposite, demonstrates how these have been implemented. These have been implemented within the detailed planning layout and are indicated as follows: 1. New development to front on to Burges Lane 2. Potential key space including focal buildings 3. Proposed parking court for existing residents on Burges Lane 4. Existing hedge to be retained 5. Footpath link to recently approved Public Open Space area (Phase 1) 6. Approved Phase 1 development proposals 7. Phase 2 development proposals 8. Existing public footpath 9. Proposed highway link road (phase 2) 10. Proposed dwellings to overlook existing footpath 11. Proposed dwellings to front onto Heathstock Hill 12. Vehicular access to development off of proposed highway 13. Highway link to Style Road and Golden Hill towards the Town centre 14. Proposed allotments 15. Public Open Space and play opportunity within approved Phase 1 development Approved framework plan This is in accordance with detail set out within the approved document. 4

7 NORTH m Proposed detailed layout 5

8 Scale The approved document indicates that the majority of the development should be no more than 2 storeys in height and a small area to the south and the centre of the site could allow for buildings of no more than 3 storeys. All of the proposed dwellings will be no more than 2 storeys in height. The proposed scheme also includes a limited number of single storey dwellings. The approved document indicates a range of typical measurements for the length and width of dwellings and these are as follows: Scale parameter dwelling length: 4-40m dwelling width: 5-25m All proposed houses within the scheme are within these development parameters. This is in accordance with the detail set out within the approved document. Proposed two storey development 6

9 Access The approved framework plan and the approved document indicate how the proposed scheme can be implemented. In particular, the site will be accessed through a new highway link taken from Style Road (to the west), connecting through to Heathstock Hill (along the eastern boundary), via Burges Lane, along the south of the site. This new primary route will form the main spine of the development. This route will move through a series of junctions and key spaces that will act as subtle traffic management features and implement a design speed of 20mph or less. The Section 106 Agreement that was signed in February 2014, in conjunction with the outline approval, includes the detail of the proposed new primary access route and the proposed scheme reflects the detail of this design. A series of secondary streets will provide access to the remainder of the development. The majority of these streets will be shared surface streets and provide equal priority to all users, including pedestrians, cyclists and vehicles, in accordance with the guidance set out in Manual for Streets. Two access points will be taken from the primary street to access the secondary streets. A number of private accesses will be taken from Heathstock Hill. Where the secondary streets are not shared surfaces, good pedestrian footpaths will be provided along site these streets and cyclist will still be provided for within the road. All secondary streets, where appropriate, will provide access to the area of Public Open Space and the allotments located to the north of the site and that will be delivered as part of this scheme. This is in accordance with the detail set out in the approved document, the approved Transport Assessment and the information included in the Section 108 Agreement. Movement parameter Proposed access and movement 7

10 Appearance & Landscape The submission package for this reserved matters application includes a range of house types (refer to drawing numbers included within this submission pack). These house types implement a limited pallet of materials and reflect the local context. The architectural style responds to the variety of styles and materials within the immediate surroundings of the site. No detailed landscape design has been included as part of this submission package and approval for the landscape reserved matter will be sought at a later date. However the detailed planning layout includes a suggested landscape approach that supports the principles set out within the approved document. This scheme indicates how the landscape design could support the proposed detailed layout. The proposed buildings and their siting implement a consistent theme in respect of form, massing and general architectural design. Subtle differences are implemented and the separate nodes of the development are identified through cohesive use of materials and building types. This is in accordance with the detail set out within the approved document. The landscape scheme will retain and strengthen the existing trees and hedges where possible and proposes new native planting to support the existing landscape context. The proposed landscape scheme will help to integrate the proposed built development into the existing context and provide visual screening where necessary. New structural landscaping should be introduced along the northern boundary to allow the proposed scheme to integrate into its context. This is in accordance with the detail set out within the approved document. 8

11 Summary The outline approval established the in principle development of the site at Land at Burges Lane, Wiveliscombe. The approved framework plan, the approved document and the associated parameter plans, have established a clear vision for the proposed development of Phase 3 of Land at Burges Lane, Wiveliscombe. The detail included as part of this reserved matters submission reflects the intention and vision of the approved scheme. This document, and submission package, has provided information to describe the detail of the layout, scale, landscape and appearance, in order to discharge condition 1 of the outline approval and for the approval of the reserved matters for this scheme. This document has demonstrated how the proposed detail of this reserved matters submission is in compliance with the approved framework plan, the approved document and the associated parameters for development. 9

12

Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS. A New Garden Neighbourhood Matford Barton 17

Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS. A New Garden Neighbourhood Matford Barton 17 Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS A New Garden Neighbourhood Matford Barton 17 2.1. SUMMARY AND STATUS OF THE PROPOSALS 2.1.1. The parameter plans and associated wording in this chapter

More information

Newcourt Masterplan. November Exeter Local Development Framework

Newcourt Masterplan. November Exeter Local Development Framework Newcourt Masterplan November 2010 Exeter Local Development Framework Background The Exeter Core Strategy Proposed Submission sets out the vision, objectives and strategy for the development of Exeter up

More information

DESIGN & ACCESS STATEMENT

DESIGN & ACCESS STATEMENT DESIGN & ACCESS STATEMENT January 2016 Contents Introduction section 1 Section 1 - Introduction Section 2 - Assessment Section 3 - Involvement Section 4 - Evaluation Section 5 - Design Section 6 - Layout

More information

Application Recommended for Approval Hapton with Park Ward

Application Recommended for Approval Hapton with Park Ward Application Recommended for Approval Hapton with Park Ward APP/2017/0036 Outline Planning Application Outline application for the construction of a new 3 bedroom dwelling (with all matters reserved for

More information

Kibworth Harcourt. Introduction. Introduction

Kibworth Harcourt. Introduction. Introduction Introduction Introduction Welcome to this public exhibition on the proposals for the delivery of new homes on land at The Kibworths. The purpose of today s exhibition is to give you the opportunity to

More information

Harrow Lane, St Leonards-on-Sea, East Sussex, TN37 7JZ ERECTION OF 113 DWELLINGS TOGETHER WITH ESTATE ROADS (DETAILED SUBMISSION)

Harrow Lane, St Leonards-on-Sea, East Sussex, TN37 7JZ ERECTION OF 113 DWELLINGS TOGETHER WITH ESTATE ROADS (DETAILED SUBMISSION) AGENDA ITEM NO: Report to: PLANNING BOARD Date: 10 September, 2003 Report from: Borough Planning Officer Application Address: Proposal: Application No: Recommendation: Ward: File No: Applicant: Interest:

More information

UTT/16/1466/DFO GREAT DUNMOW MAJOR

UTT/16/1466/DFO GREAT DUNMOW MAJOR UTT/16/1466/DFO GREAT DUNMOW MAJOR PROPOSAL: LOCATION: APPLICANT: AGENT: Reserved matters approval for the accesses to the site and principal roads within the site including spine road following outline

More information

BLETCHLEY PARK AREA - DEVELOPMENT FRAMEWORK

BLETCHLEY PARK AREA - DEVELOPMENT FRAMEWORK ANNEX A To Item 9 REVISED TEXT: additions shown bold and underlined, deletions in (brackets and in italics). BLETCHLEY PARK AREA - DEVELOPMENT FRAMEWORK This framework sets out the key objectives and requirements

More information

WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014

WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014 WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014 Dear Resident This Special Edition of the Whiteley Voice which has been prepared in conjunction with the North Whiteley Consortium is to

More information

Public Consultation. Land at Monks Farm, North Grove. Welcome

Public Consultation. Land at Monks Farm, North Grove. Welcome Welcome Welcome to our public exhibition for development on Land at Monks Farm, orth Grove. Gallagher Estates and Gleeson Strategic Land are preparing an outline planning application for new homes, open

More information

Former North Works, Lickey Road, Longbridge, Birmingham

Former North Works, Lickey Road, Longbridge, Birmingham Committee Date: 14/11/2013 Application Number: 2013/06431/PA Accepted: 27/08/2013 Application Type: Full Planning Target Date: 26/11/2013 Ward: Longbridge Former North Works, Lickey Road, Longbridge, Birmingham

More information

Warren Farm, Ampthill

Warren Farm, Ampthill 1 Welcome The developers of the Warren Farm site, Bloor Homes and Connolly Homes, are holding this exhibition on the emerging Design Codes for the development prior to their formal submission to Central

More information

Carterton Construction Ltd is bringing forward plans for up to 85 new family homes and extra care facilities on land east of Burford.

Carterton Construction Ltd is bringing forward plans for up to 85 new family homes and extra care facilities on land east of Burford. Welcome Carterton Construction Ltd is bringing forward plans for up to 85 new family homes and extra care facilities on land east of. We are at the early stages of designing our proposals and have a number

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Director of Development Services

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Director of Development Services SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL REPORT TO: Development and Conservation Control Committee 5 th April 2006 AUTHOR/S: Director of Development Services S/2290/05/F Haslingfield House (Revised Design)

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Executive Director (Operational Services) Corporate Manager (Planning and New Communities)

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Executive Director (Operational Services) Corporate Manager (Planning and New Communities) SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL REPORT TO: Planning Committee 12 January 2011 AUTHOR/S: Executive Director (Operational Services) Corporate Manager (Planning and New Communities) Notes: S/1848/10

More information

It is recommended that the Committee resolve to APPROVE the application and grant planning permission subject to the following conditions:

It is recommended that the Committee resolve to APPROVE the application and grant planning permission subject to the following conditions: LOCATION: Phase 2A Millbrook Park (Site of Former Inglis Barracks), Mill Hill East, London, NW7 1PZ REFERENCE: H/04606/12 Received: 04 December 2012 Accepted: 17 December 2012 WARD: Mill Hill Expiry: 18

More information

Site north of Hattersley Road West (east of Fields Farm Road), Hattersley

Site north of Hattersley Road West (east of Fields Farm Road), Hattersley Application Number 17/00982/REM Proposal Site Applicant Recommendation Reason for report Application for the approval of reserved matters (means of access, landscaping, layout, scale and appearance) relating

More information

Derry City and Strabane District Council Planning Committee Report. Amended layout from approval A/2004/0462/F with reduction from 166 units

Derry City and Strabane District Council Planning Committee Report. Amended layout from approval A/2004/0462/F with reduction from 166 units Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 1 st February 2017 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: Full Planning application Amended

More information

Former Temple Cowley Pools, Oxford TEMPLE COWLEY LIBRARY * ELEVATION SHOWN IS INDICATIVE AND SUBJECT TO FINAL DESIGN AND AGREEMENT.

Former Temple Cowley Pools, Oxford TEMPLE COWLEY LIBRARY * ELEVATION SHOWN IS INDICATIVE AND SUBJECT TO FINAL DESIGN AND AGREEMENT. OPEN SPACE TEMPLE COWLEY LIBRARY library beyond Proposed apartments Proposed apartments Proposed houses Temple Road * ELEVATION SHOWN IS INDICATIVE AND SUBJECT TO FINAL DESIGN AND AGREEMENT. * Welcome

More information

Chapter 5 Urban Design and Public Realm

Chapter 5 Urban Design and Public Realm 5.1 Introduction Public realm is all areas of the urban fabric to which the public have access. It is where physical interaction takes place between people. It therefore, includes buildings and their design,

More information

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of WELCOME The developers are preparing an outline planning application for a residential led development and need the community s views in order to develop the proposals further WHAT IS PROPOSED? A high

More information

8.0 Design and Form of Development 43/

8.0 Design and Form of Development 43/ 42/ 8.0 Design and Form of Development 43/ Rothwells Farm, Golborne/ Development Statement Figure 7. Site Constraints Key 44/ Site Boundary 360 Bus Route/Stops Existing Trees Underground Water Pipe Sensitive

More information

WELCOME. Land North of STEVENAGE. We would like to thank you for attending our public exhibition today.

WELCOME. Land North of STEVENAGE.   We would like to thank you for attending our public exhibition today. WELCOME We would like to thank you for attending our public exhibition today. The purpose of this event is to share our proposals and hear your thoughts on our ideas. Members of the project team are on

More information

SUBMISSION TO DRAFT FINGAL COUNTY DEVELOPMENT PLAN RE: LANDS AT CASTLEKNOCK VILLAGE CENTRE

SUBMISSION TO DRAFT FINGAL COUNTY DEVELOPMENT PLAN RE: LANDS AT CASTLEKNOCK VILLAGE CENTRE April 2016 SUBMISSION TO DRAFT FINGAL COUNTY DEVELOPMENT PLAN 2017-2023 RE: LANDS AT CASTLEKNOCK VILLAGE CENTRE On behalf of: Lidl Ireland GmbH Submitted to: Planning & Strategic Infrastructure Department

More information

DELEGATED DECISION on 1st September 2015

DELEGATED DECISION on 1st September 2015 Application N o : 14/04810/OUT LONDON BOROUGH OF BROMLEY TOWN PLANNING RENEWAL AND RECREATION DEPARTMENT DELEGATED DECISION on 1st September 2015 14/04810/OUT Claire Harris 4 Oaklands Road Bromley BR1

More information

Welcome to our exhibition

Welcome to our exhibition Welcome to our exhibition housing development A46 Wildmoor Alcester Road Canal Quarter A422 Town Centre housing development Warwickshire-based IM Properties, one of the UK s largest privately owned property

More information

Story Homes. Land at Thirsk Road, Kirklevington. An Introduction to Story Homes. Our Foundations. Commitment to Consultation.

Story Homes. Land at Thirsk Road, Kirklevington. An Introduction to Story Homes. Our Foundations. Commitment to Consultation. Story Homes An Introduction to Story Homes Founded by Fred Story in 1987, Story Homes has a long and successful reputation of building high quality and high specification homes. The family owned business

More information

1. Welcome. Background

1. Welcome. Background 1. Welcome The purpose of this exhibition is to provide you with an update on progress on the Kilnwood Vale Scheme. In order to improve the scheme and deliver key facilities earlier in the development,

More information

South of Hillside Road West, Rothbury. Design and Access Statement with Design Code. Outline Planning Application May 2016

South of Hillside Road West, Rothbury. Design and Access Statement with Design Code. Outline Planning Application May 2016 Outline Planning Application May 2016 Design and Access Statement with Design Code Jane Darbyshire and David Kendall Ltd This Design and Access Statement has been produced by Jane Darbyshire and David

More information

3.1 The hybrid planning application proposes the following description of development:

3.1 The hybrid planning application proposes the following description of development: CHAPTER 3: PROPOSED DEVELOPMENT 3.1 The hybrid planning application proposes the following description of development: Hybrid (part-outline/part-full) planning application for a single composite development

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Planning and New Communities Director. Linton. Yes

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Planning and New Communities Director. Linton. Yes SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL REPORT TO: Planning Committee 2 July 2014 AUTHOR/S: Planning and New Communities Director Application Number: Parish(es): Proposal: Site address: Applicant(s): Recommendation:

More information

Welcome to our exhibition

Welcome to our exhibition Welcome to our exhibition The Homes & Communities Agency (HCA) welcomes you to this public exhibition explaining our proposals for the redevelopment of the former Lea Castle Hospital site. About the Homes

More information

Welcome. Walk Around. Talk to Us. Write Down Your Comments

Welcome. Walk Around. Talk to Us. Write Down Your Comments Welcome This is an information meeting introducing the applications for proposed redevelopment of the Yorkdale Shopping Centre site at 3401 Dufferin Street and 1 Yorkdale Road over the next 20+ years,

More information

OKEFORD FITZPAINE NEIGHBOURHOOD PLAN

OKEFORD FITZPAINE NEIGHBOURHOOD PLAN OKEFORD FITZPAINE NEIGHBOURHOOD PLAN Dear Parishioner, The Neighbourhood Plan Project Team have prepared this leaflet to summarise the full Neighbourhood Plan document. It provides a summary of the Vision,

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 23rd March 2016 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: LA11/2015/0263/O Outline Planning

More information

Welcome. Proposals for land at Smug Oak Lane BRICKET WOOD

Welcome. Proposals for land at Smug Oak Lane BRICKET WOOD Proposals for land at Smug Oak Lane BRICKET WOOD Previous Linden Homes and Wates Developments scheme Welcome Welcome to Linden Homes and Wates Developments public exhibition. Working together as joint

More information

Persimmon Homes Thames Valley Date received: 2 nd April week date(major): 2 nd July 2014 Ward: Nascot

Persimmon Homes Thames Valley Date received: 2 nd April week date(major): 2 nd July 2014 Ward: Nascot PART A Report of: DEVELOPMENT MANAGEMENT SECTION HEAD Date of Committee: 26 th June 2014 Site address: Rounton, 28, Nascot Wood Road Reference Number: 14/00497/REM Description of Development: Reserved

More information

Description Details submitted pursuant to discharge of condition 5 (Design Code) attached to planning permission 13/01729/OUT.

Description Details submitted pursuant to discharge of condition 5 (Design Code) attached to planning permission 13/01729/OUT. ITEM 9 Application Number: 18/00266/DISCON Description Details submitted pursuant to discharge of condition 5 (Design Code) attached to planning permission 13/01729/OUT. AT The Point, 602 Midsummer Boulevard,

More information

Site: Essex Police & La Plata House London Road Brentwood Essex CM14 4QJ

Site: Essex Police & La Plata House London Road Brentwood Essex CM14 4QJ Reference: 16/01805/OUT Ward: Brentwood West Site: Essex Police & La Plata House London Road Brentwood Essex CM14 4QJ Proposal: Outline application for demolition of existing police station buildings,

More information

BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY

BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY SITE LOCATION The site of the existing AECC lies in an area of predominately residential and business use in Bridge of Don and extends approximately 50 acres.

More information

Statement of Community Involvement LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE

Statement of Community Involvement LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE CONTENTS Page 1. Introduction 3 2. Pre-application Discussions 4 3. The Consultation Process 5 4. Consultation Feedback 7 5. Responses to Consultation Feedback

More information

LAND USE AMENDMENT CORNERSTONE (WARD 3) 60 STREET NE AND COUNTRY HILLS BOULEVARD NE MAP 26NE BYLAW 22D2017

LAND USE AMENDMENT CORNERSTONE (WARD 3) 60 STREET NE AND COUNTRY HILLS BOULEVARD NE MAP 26NE BYLAW 22D2017 Page 1 of 14 EXECUTIVE SUMMARY This Land Use Amendment application covers an area of 43.76 hectares ± (108.14 acres ±) located in northeast Calgary, bound by Country Hills Boulevard NE to the south and

More information

SOUTH YORKSHIRE RESIDENTIAL DESIGN GUIDE

SOUTH YORKSHIRE RESIDENTIAL DESIGN GUIDE SOUTH YORKSHIRE RESIDENTIAL DESIGN GUIDE 2011 INTEGRATED VITAL, ACTIVE AND WELL MANAGED EQUITABLE, COHESIVE, INCLUSIVE AND SAFE LOCAL, DISTINCTIVE AND ATTRACTIVE EFFICIENT, FLEXIBLE AND ADAPTABLE Metropolitan

More information

Figure 1- Site Plan Concept

Figure 1- Site Plan Concept Figure 1- Site Plan Concept Parking will be provided underground on three levels at rate of 1.0 space/ unit; this rate includes all visitors parking. MMM Group has prepared a parking assessment (April,

More information

Land Adj. 63 Sunny Bank Road, Sutton Coldfield, Birmingham, B73 5RJ

Land Adj. 63 Sunny Bank Road, Sutton Coldfield, Birmingham, B73 5RJ Committee Date: 11/07/2013 Application Number: 2013/03520/PA Accepted: 20/05/2013 Application Type: Full Planning Target Date: 15/07/2013 Ward: Sutton Vesey Land Adj. 63 Sunny Bank Road, Sutton Coldfield,

More information

Aylesbury Estate, Southwark. Notting Hill Housing Trust. Planning Statement Revised February 2015

Aylesbury Estate, Southwark. Notting Hill Housing Trust. Planning Statement Revised February 2015 Aylesbury Estate, Southwark Notting Hill Housing Trust Planning Statement Revised February 2015 Planning Statement / February 2015 / Deloitte Real Estate Contents 1 Introduction 1 2 Aylesbury Estate Site

More information

TRANSPORT AND WORKS ACT 1992 TRANSPORT AND WORKS (APPLICATIONS AND OBJECTIONS PROCEDURE)(ENGLAND AND WALES) RULES 2006

TRANSPORT AND WORKS ACT 1992 TRANSPORT AND WORKS (APPLICATIONS AND OBJECTIONS PROCEDURE)(ENGLAND AND WALES) RULES 2006 TRANSPORT AND WORKS ACT 1992 TRANSPORT AND WORKS (APPLICATIONS AND OBJECTIONS PROCEDURE)(ENGLAND AND WALES) RULES 2006 THE MIDLAND METRO (BIRMINGHAM CITY CENTRE EXTENSION LAND ACQUISITION AND VARIATION)

More information

Land at Rampton Road. Cottenham

Land at Rampton Road. Cottenham Land at Rampton Road Cottenham Introduction TEP is preparing an outline planning application for 54 dwellings on 6.9 hectares of land adjacent to Rampton Road, Cottenham on behalf of the owners Cambridgeshire

More information

Land at Fiddington Hill Nursery, Market Lavington

Land at Fiddington Hill Nursery, Market Lavington Land at Fiddington Hill Nursery, Market Lavington Briefing Report for Market Lavington Parish Council Persimmon Homes (Wessex) April 2016 Background This brief report has been prepared following the Market

More information

Perth and Kinross Council Development Management Committee 8 June Pre-Application Report by Development Quality Manager

Perth and Kinross Council Development Management Committee 8 June Pre-Application Report by Development Quality Manager Perth and Kinross Council Development Management Committee 8 June 2016 5(3)(i) 16/259 Pre-Application Report by Development Quality Manager Residential development at St Martins Road, Land 120 metres West

More information

Development of land adjacent to Braggs Farm Lane and Rumbush Lane, Dickens Heath. Welcome. Today s exhibition. The proposal site

Development of land adjacent to Braggs Farm Lane and Rumbush Lane, Dickens Heath. Welcome. Today s exhibition. The proposal site Welcome Welcome to this event to discuss the development of land adjacent to Braggs Farm Lane. is currently in the preliminary stages of designing proposals to sensitively develop this site with high-quality

More information

Residential Development at Menehay Farm, Bickland Water Road, Falmouth Design and Access Statement

Residential Development at Menehay Farm, Bickland Water Road, Falmouth Design and Access Statement Residential Development at Menehay Farm, Bickland Water Road, Falmouth Design and Access Statement Galliford Try STRIDE TREGLOWN JOB NO. PREPARED BY CHECKED BY DATE REVISION REVISION NO. 150220 Coral Ducroq

More information

Welcome to our public exhibition

Welcome to our public exhibition About our development Welcome to our public exhibition This exhibition gives you the chance to view and comment on our proposals for a new residential development of 165 high-quality homes, along with

More information

PLANNING COMMITTEE REPORT

PLANNING COMMITTEE REPORT PLANNING COMMITTEE REPORT TO: BY: Planning Committee North Head of Development DATE: 6 March 2018 DEVELOPMENT: Outline planning application for the development of approximately 227 dwellings (between 204

More information

ADMINISTRATION RECOMMENDATION 2016 November 03. That Calgary Planning Commission recommends APPROVAL of the proposed Land Use Amendment.

ADMINISTRATION RECOMMENDATION 2016 November 03. That Calgary Planning Commission recommends APPROVAL of the proposed Land Use Amendment. Page 1 of 12 EXECUTIVE SUMMARY This Land Use Amendment application covers an area of 75.76 hectares ± (187.20 acres ±) located in northeast Calgary, bound by Stoney Trail NE to the north, 128 Avenue NE

More information

Planning Statement. November On behalf of Barton Oxford LLP

Planning Statement. November On behalf of Barton Oxford LLP Planning Statement November 2014 On behalf of Barton Oxford LLP Design + Planning Barton Oxford LLP November 2014 Barton Park, Oxford Planning Statement In support of Reserved Matters Application, pursuant

More information

Public Consultation 23 January Peel Hall, Warrington Board 1. A message from Satnam... Site history...

Public Consultation 23 January Peel Hall, Warrington Board 1. A message from Satnam... Site history... Board 1 A message from Satnam... Thank you for attending today s public consultation about proposals to develop a new residential neighbourhood at. The display boards show why the development is needed

More information

an Inspector appointed by the Secretary of State for Communities and Local Government

an Inspector appointed by the Secretary of State for Communities and Local Government Appeal Decision Site visit made on 24 October 2017 by Jonathan Price BA(Hons) DMS DipTP MRTPI an Inspector appointed by the Secretary of State for Communities and Local Government Decision date: 22 ND

More information

Briefing Document of CNP. June 2017

Briefing Document of CNP. June 2017 Cholsey Parish Council Cholsey Neighbourhood Plan Briefing Document of CNP June 2017 Cholsey Neighbourhood Plan Page! 1 of! 8 Cholsey Plan Briefing v1.4 Page Left Intentionally Blank Cholsey Neighbourhood

More information

LAND OFF WELHAM CROFT SHIRLEY SOLIHULL

LAND OFF WELHAM CROFT SHIRLEY SOLIHULL 2010/670 LAND OFF WELHAM CROFT SHIRLEY Application No: Ward/Area: Location: 2010/670/S BLYTHE LAND OFF WELHAM CROFT SHIRLEY SOLIHULL Date Registered: 30/04/2010 Applicant: Proposal: CAMERON HOMES LTD OUTLINE

More information

WELCOME. Welcome and thank you for visiting today.

WELCOME.   Welcome and thank you for visiting today. WELCOME Welcome and thank you for visiting today. Bellway Homes Ltd (Yorkshire) are preparing a reserved matters planning application for a residential development of 293 homes at land North of Yew Tree

More information

Birmingham University, Pritchatts Road, Adjacent to Gisbert Kapp Building, Edgbaston, Birmingham, B15

Birmingham University, Pritchatts Road, Adjacent to Gisbert Kapp Building, Edgbaston, Birmingham, B15 Committee Date: 07/03/2013 Application Number: 2013/00181/PA Accepted: 10/01/2013 Application Type: Reserved Matters Target Date: 11/04/2013 Development Ward: Edgbaston Birmingham University, Pritchatts

More information

LAND USE AMENDMENT CORNERSTONE (WARD 3) COUNTRY HILLS BOULEVARD AND STONEY TRAIL NE BYLAW 9D2017

LAND USE AMENDMENT CORNERSTONE (WARD 3) COUNTRY HILLS BOULEVARD AND STONEY TRAIL NE BYLAW 9D2017 Page 1 of 12 EXECUTIVE SUMMARY This Land Use Amendment application covers an area of 54.92 hectares ± (135.71 acres ±) located in northeast Calgary, bound by Country Hills Boulevard NE to the north and

More information

Croxley Rail Link Watford Vicarage Road Station Reference Number :

Croxley Rail Link Watford Vicarage Road Station Reference Number : PART A Report to: Development Management Section Head To Committee: Date of Committee: 3 rd April 2014 Site address: Croxley Rail Link Watford Vicarage Road Station Reference Number : 14/00101/DISCON Description

More information

Ebbsfleet Development Corporation

Ebbsfleet Development Corporation Title of Paper Planning and Housing Delivery Report September 2018 Presented by Sub-Committee Mark Pullin, Chief Planning Officer Planning Committee Purpose of Paper and Executive Summary This paper provides

More information

INTRODUCTION. Land West of Main Road, Stanton Harcourt THE SITE. Why is the Site Suitable for Development?

INTRODUCTION. Land West of Main Road, Stanton Harcourt THE SITE. Why is the Site Suitable for Development? 0 INTRODUCTION THE SITE Application Boundary Gladman Developments Ltd has successfully invested in communities throughout the UK over the past 0 years, developing high quality and sustainable residential,

More information

Replacement Golf Course Facilities and Residential Development, Churston. Environmental Statement Non-Technical Summary

Replacement Golf Course Facilities and Residential Development, Churston. Environmental Statement Non-Technical Summary Replacement Golf Course Facilities and Residential Development, Churston Environmental Statement Non-Technical Summary July 2011 Reproduced from the Ordnance Survey s map with the permission of the Controller

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. REPORT TO: Planning Committee 1 April 2015 Planning and New Communities Director

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. REPORT TO: Planning Committee 1 April 2015 Planning and New Communities Director SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL REPORT TO: Planning Committee 1 April 2015 AUTHOR/S: Planning and New Communities Director Application Number: Parish(es): Proposal: Site address: Applicant(s): Recommendation:

More information

LIST OF LIVE AND DETERMINED PLANNING APPLICATIONS RELATING TO THE WIDER BRENT CROSS CRICKLEWOOD REGENERATION SCHEME

LIST OF LIVE AND DETERMINED PLANNING APPLICATIONS RELATING TO THE WIDER BRENT CROSS CRICKLEWOOD REGENERATION SCHEME LIST OF LIVE AND DETERMINED PLANNING APPLICATIONS RELATING TO THE WIDER BRENT CROSS CRICKLEWOOD REGENERATION SCHEME BRENT CROSS NORTH PHASE 1A (NORTH) PRE-RESERVED MATTERS APPLICATION S 1.9 1.10 1.17 1.18

More information

STATEMENT OF OBJECTION TO THE PROPOSED DEVELOPMENT OF LAND AT CHURCH CLIFF DRIVE FILEY

STATEMENT OF OBJECTION TO THE PROPOSED DEVELOPMENT OF LAND AT CHURCH CLIFF DRIVE FILEY STATEMENT OF OBJECTION TO THE PROPOSED DEVELOPMENT OF LAND AT CHURCH CLIFF DRIVE FILEY You will be aware that Scarborough borough council have adopted a new local plan that includes land at Church Cliff

More information

Land North of Hall Road, Rochford. Rochford District Council. Planning Application Index. Prepared on behalf of Bellway Homes Ltd

Land North of Hall Road, Rochford. Rochford District Council. Planning Application Index. Prepared on behalf of Bellway Homes Ltd Land North of Hall Road, Rochford Rochford District Council Planning Application Index Prepared on behalf of Bellway Homes Ltd April 2010 Land North of Hall Road, Rochford Rochford District Council Scope

More information

CAERNARFON DEPENDENCY CATCHMENT AREA

CAERNARFON DEPENDENCY CATCHMENT AREA CAERNARFON DEPENDENCY CATCHMENT AREA GWYNEDD UNITARY DEVELOPMENT PLAN - HOUSING Map not to scale Dependency Catchment Area Location 2 Caernarfon Topic Housing To the rear of Bro Eglwys, Bethel. Grid Ref.

More information

Schedule of Planning Applications Committee Date: 23 May Reference: 06/17/0726/F Parish: Hemsby Officer: Mr J Beck Expiry Date:

Schedule of Planning Applications Committee Date: 23 May Reference: 06/17/0726/F Parish: Hemsby Officer: Mr J Beck Expiry Date: Schedule of Planning Applications Committee Date: 23 May 2018 Reference: 06/17/0726/F Parish: Hemsby Officer: Mr J Beck Expiry Date: 22-05-2018 Applicant: Proposal: Site: Mr Gillett Change of use to the

More information

PLANNING COMMITTEE REPORT

PLANNING COMMITTEE REPORT PLANNING COMMITTEE REPORT TO: BY: Planning Committee South Head of Development DATE: 19 December 2017 DEVELOPMENT: SITE: WARD: APPLICATION: APPLICANT: Conversion of existing water storage reservoir to

More information

LAND EAST OF MILL LANE, SHERBURN VILLAGE PLANNING STATEMENT

LAND EAST OF MILL LANE, SHERBURN VILLAGE PLANNING STATEMENT LAND EAST OF MILL LANE, SHERBURN VILLAGE PLANNING STATEMENT On behalf of The Church Commissioners for England Land East of Mill Lane, Sherburn Village Planning Statement On Behalf of The Church Commissioners

More information

10 Proposed Redevelopment, Tewkesbury Road, Cheltenham SCHEME EVOLUTION STARBUCKS

10 Proposed Redevelopment, Tewkesbury Road, Cheltenham SCHEME EVOLUTION STARBUCKS SCHEME EVOLUTION STARBUCKS The proposed Starbucks Drive Thru alongside the proposed food store provides an appropriate mix of uses, suitable for this location. The proposed store is bespoke, designed specifically

More information

2.0 Strategic Context 4

2.0 Strategic Context 4 2.0 Strategic Context 4 2.1 The Area Action Plan is a non-statutory plan, which forms a corporate policy document, expressing particular issues and areas of concern while also providing a vision for the

More information

ACU DEVELOPMENT PLAN OBJECTION RESPONSE

ACU DEVELOPMENT PLAN OBJECTION RESPONSE Inappropriate location for consolidation of ACU campus Intentions for remaining ACU land unknown; residents would like to see a full master plan of all ACU sites proposed for the next 10-15 years ACU has

More information

Departure from the Development Plan. Town Council objection to a major application. DETERMINE

Departure from the Development Plan. Town Council objection to a major application. DETERMINE Item No. 9 APPLICATION NUMBER CB/17/01642/OUT LOCATION Land rear of 43 to 91 Silver Birch Avenue South of Alder Green and Aspen Gardens, Aspen Gardens, Stotfold PROPOSAL Outline application for up to 95

More information

Next Steps / Development Process. Structure Plan. June submitted to City of Fremantle. Structure Plan. July supported for advertising

Next Steps / Development Process. Structure Plan. June submitted to City of Fremantle. Structure Plan. July supported for advertising overview What is today about? In July 0, the City of Fremantle resolved that the be advertised for public comment. Today is about: Understanding the history and context of the site Having your say on the

More information

LDF. Development Management DPD: Preferred Policy Options Document. Local Development Framework. Rochford District Council

LDF. Development Management DPD: Preferred Policy Options Document. Local Development Framework.   Rochford District Council December 2011 Local Development Framework Development Management DPD: Preferred Policy Options Document LDF www.rochford.gov.uk Contents Page 1 Introduction...3 The Role of the Development Management Development

More information

Southend-on-Sea Borough Council Department for Place! Peter Geraghty Head of Planning & Transport

Southend-on-Sea Borough Council Department for Place! Peter Geraghty Head of Planning & Transport Southend-on-Sea Borough Council Department for Place! Peter Geraghty Head of Planning & Transport Our ref: 15/00889/PREAPF Telephone: 01702 215004 ext 4848 Your ref: Fax: 01702 215672 Date: 3 rd August

More information

WELCOME TO THE NEW WILTON PARK

WELCOME TO THE NEW WILTON PARK WELCOME TO THE NEW WILTON PARK VISION HISTORY OF WILTON PARK TOWARDS A PLANNING APPLICATION Our objective is to create a truly outstanding environment at Wilton Park. At the heart of our proposals is a

More information

HS2 Interchange Station Design

HS2 Interchange Station Design Working on behalf of HS2 Interchange Station Design October 2018 www.hs2.org.uk 1 Interchange Station, Solihull Introduction In February 2018, HS2 Ltd appointed Arup to take forward the design of Interchange

More information

LAND OFF TOLLBAR WAY, HEDGE END PUBLIC CONSULTATION. Proposed Residential Development

LAND OFF TOLLBAR WAY, HEDGE END PUBLIC CONSULTATION. Proposed Residential Development LAND OFF TOLLBAR WAY, HEDGE END PUBLC CONSULTATON Proposed Residential Development YOUR VEW MATTERS TO US PROPOSED STE AREA Thank you for taking the time to read this information leaflet regarding a proposed

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 29 th November 2017 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: LA11/2016/0854/O Outline Shared

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Planning and New Communities Director

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Planning and New Communities Director SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL REPORT TO: Planning Committee 9 January 2013 AUTHOR/S: Planning and New Communities Director S/2064/12/FL WATERBEACH Demolition of existing 35 no. shared amenity apartments

More information

4. MASTERPLAN FRAMEWORK

4. MASTERPLAN FRAMEWORK 6a 6b 4. MASTERPLAN FRAMEWORK 6. Car Parks 6c Car Parks 6a and 6b will provide permanent parking. Area 6a will serve the foodstore with tarmac surfacing within a defined area to the west of the adjacent

More information

The term 'development' in the conditions below means the development permitted by this consent.

The term 'development' in the conditions below means the development permitted by this consent. APPENDIX 1 Conditions The term 'development' in the conditions below means the development permitted by this consent. 1 Approved plans The development hereby permitted shall be carried out in accordance

More information

Case Officer: Sarah Kay File No: CHE/14/00515/REM Tel. No: (01246) Plot No: 2/6132 Ctte Date: 15 th September 2014 ITEM 1

Case Officer: Sarah Kay File No: CHE/14/00515/REM Tel. No: (01246) Plot No: 2/6132 Ctte Date: 15 th September 2014 ITEM 1 Case Officer: Sarah Kay File No: CHE/14/00515/REM Tel. No: (01246) 345786 Plot No: 2/6132 Ctte Date: 15 th September 2014 ITEM 1 APPROVAL OF RESERVED MATTERS FROM APPLICATION CHE/12/00234/OUT (1) LAYOUT,

More information

South fields. Community Architectural Design Guidelines. The Planning Partnership

South fields. Community Architectural Design Guidelines. The Planning Partnership South fields Community Architectural Design Guidelines The Planning Partnership Table Of Contents Table of Contents 1.0 GUIDING PRINCIPLES 1.1 Function of Architectural Design Guidelines 1.2 Administration

More information

HARDWICK GREEN, King s Lynn. Welcome to our Exhibition. What are your views? Introduction to the site and proposals. About us

HARDWICK GREEN, King s Lynn. Welcome to our Exhibition. What are your views? Introduction to the site and proposals. About us HARDWICK GREE, King s Lynn Welcome to our Exhibition Welcome to our exhibition, which is being held to provide you with the opportunity to understand and comment upon our proposals for new residential

More information

Introduction to MP3. MP3 H4 Park Central (North)

Introduction to MP3. MP3 H4 Park Central (North) MP H4 Park Central (North) Introduction to MP A visualisation of the Illustrative Masterplan with MP shaded in blue MP is the third phase of the Elephant Park regeneration and is bounded by on the north,

More information

Plumpton Neighbourhood Development Plan Revised Pre Submission Document - Regulation 14 Consultation

Plumpton Neighbourhood Development Plan Revised Pre Submission Document - Regulation 14 Consultation REPRESENTATIONS... Plumpton Parish Council Plumpton Neighbourhood Development Plan Revised Pre Submission Document - Regulation 14 Consultation Representations submitted on behalf of: Cala Homes (South

More information

Our Site Plan and Block Plan Drawing Nos /101B and /102C have been amended to reflect the following revisions:

Our Site Plan and Block Plan Drawing Nos /101B and /102C have been amended to reflect the following revisions: Our Ref: AS/130520/P14 3 rd June 2014 Rebecca Hughes Development Services Central Area Wiltshire Council County Hall Bythesea Road Trowbridge Wiltshire BA14 8JN Dear Ms Hughes, Site A Erection of 9 no.

More information

Longbridge Town Centre Phase 2 Planning Application

Longbridge Town Centre Phase 2 Planning Application Longbridge Town Centre Phase 2 Planning Application Non-Technical Summary of the Environmental Statement December 2013 Introduction A full application for Planning Permission has been submitted to Birmingham

More information

Welcome to our public exhibition

Welcome to our public exhibition About our scheme Welcome to our public exhibition Taylor Wimpey East Anglia intends to submit a detailed planning application for a new residential development of 39 high-quality homes at the B&M Concrete

More information

Welcome to our public exhibition

Welcome to our public exhibition About Our Scheme Welcome to our public exhibition This exhibition gives you the chance to view and comment upon our emerging proposals for a new residential development of 68 new homes on the site of the

More information

AGINCOURT SECONDARY PLAN

AGINCOURT SECONDARY PLAN 1 AGINCOURT SECONDARY PLAN 1. AGINCOURT SECONDARY PLAN The following policies and principles apply to the area herein referred to as Agincourt, as outlined on Map 1-1. 1. GENERAL POLICIES 1.1 This Secondary

More information

26 September 2014 CONSULTATION EXPIRY : APPLICATION EXPIRY : 22 July 2014 SUMMARY RECOMMENDATION: PERMISSION

26 September 2014 CONSULTATION EXPIRY : APPLICATION EXPIRY : 22 July 2014 SUMMARY RECOMMENDATION: PERMISSION Item No.: 5 The information, recommendations and advice contained in this report are correct as at the date of preparation, which is more than one week in advance of the Committee meeting. Because of the

More information