1 Design Manual Chapter 5 - Roadway Design 5K - Permeable Interlocking Pavers 5K-1 Permeable Interlocking Pavers A. General Permeable pavements are designed to infiltrate runoff, whereas runoff sheds off the surface of conventional pavements. In permeable pavements, runoff passes through the surface and is stored in the aggregate base. In pervious soils, the runoff infiltrates the soil; in less permeable soils, a subdrain system is placed to slowly discharge the runoff. Runoff volume reduction is achieved as the water is infiltrated into the underlying soils. The peak runoff rate is reduced due to the stormwater being stored in the aggregate subbase and slowly released to the downstream piping systems. Traditionally, at a minimum, the depth of the aggregate subbase is designed to meet the storage needs for the Water Quality Volume (WQv), which is 1.25 inches of rainfall in Iowa. Permeable pavements can dramatically reduce the surface runoff from most rainfall events by disconnecting and distributing runoff through filtration and detention. The use of permeable pavements can result in stormwater runoff conditions that approximate the predevelopment site conditions for the immediate area covered by the pavers. The design of permeable interlocking pavements (PIP) involves both structural and hydrological analyses. Figure 5K-1.01 illustrates a typical cross-section of a PIP. These two design elements are typically not interconnected and in reality are often in conflict. This is particularly the case with the subgrade treatment and volume of aggregate subbase. Structural design requires a compacted subgrade and the hydrologic design desires an uncompacted subgrade to allow as much infiltration as possible. In most instances, the hydrologic requirements for filter and storage aggregate exceed the structural needs for the unbound aggregate subbase. Figure 5K-1.01: Permeable Interlocking Paver Cross-section 1 Revised: 2018 Edition

2 PIP are used for low speed/low volume streets, alleys, parking lots, and driveways. The design and operating speed of the facility should be below 35 mph. Permeable paver projects should only be developed in areas dominated by impermeable surfaces or surfaces that are fully vegetated so that sediment runoff is minimized and life of the pavement is maximized. PIP are capable of handling truck traffic. The following elements should be reviewed prior to undertaking a detailed design process: Underlying geology and soils NRCS hydrologic soils groups History of fill, disturbance, or compaction of underlying soils Current drainage patterns and volume of runoff Local and downstream drainage facilities Distances to potable water supply wells Elevation of the static water table Traffic volumes, including percent trucks Because water is stored in the subbase rock, it may be necessary to protect structures that are adjacent to the permeable paver project by sealing the foundation walls. The PIP must be a minimum of 100 feet from a municipal water supply well. There are two types of permeable interlocking pavers. One type is concrete pavers that are 3 1/8 inches thick; the other type is clay brick pavers that are at least 2 5/8 inches thick. The concrete pavers must comply with ASTM C 936. There are two ASTM standards for brick pavers, depending on the traffic loading. ASTM C 902 is for pedestrian and light vehicular traffic locations. ASTM C 1272 is for heavier vehicular traffic and will be the type listed in the SUDAS Specifications. The clay pavers should be 2 3/4 inches thick, Type F brick for PX applications according to ASTM C B. Structural Design The design procedure for permeable interlocking pavers is the same as for flexible pavements. Research has shown that the load distribution and failure modes of PIP are similar to other flexible pavements. Because the designs are the same as for flexible pavements, the AASHTO Guide for Design of Pavement Structures (AASHTO, 1993) can be used. The paver used in design for concrete pavers is a 3 1/8 inch thick paver with a minimum 1 inch bedding layer. The structural coefficient is 0.44 per inch. This provides a structural number of The clay brick paver is 2 3/4 inches thick, which has a corresponding structural number of The remaining structural support comes from the aggregate layers and the soil subgrade. The American Society of Civil Engineers has developed a design standard called Structural Design of Interlocking Concrete Pavement for Municipal Streets and Roadways (ASCE/T&DI/ICPI 58-10). The structural design for clay brick pavers is the same as for concrete pavers. The engineer will need to determine or select the following: Design traffic loading (ESALS) Design life (40 years minimum) Design reliability (usually 75% to 80%) Overall standard deviation (0.45) Required structural number to meet traffic loading Initial serviceability (flexible pavements = 4.2) Terminal serviceability (local streets = 2.0) Subgrade resilient modulus based on saturated soil characteristics, including seasonal variability Drainage conditions 2 Revised: 2018 Edition

3 Once these elements are determined, the design thickness of the unbound aggregate subbase can be determined. The ASCE design standard has tables showing thickness of the layers that were developed using the AASHTO 1993 Guide. Thickness is selected based on the ESALS, the soil category, and the drainage. Three types of interlock are critical to achieve: vertical, rotational, and horizontal. Vertical interlock is achieved by the shear transfer of loads to surrounding pavers through the material in the joints. Rotational interlock is maintained by the pavers being of sufficient thickness and aspect ratio (3:1 minimum), being placed close together, and restrained by a curb from lateral forces of vehicle tires. Rotational interlock can be further enhanced if there is a slight crown to the pavement cross-section. Horizontal interlock is primarily achieved through the use of laying patterns that disperse forces from braking, turning, and accelerating vehicles. Herringbone patterns, either 45 or 90, are the most effective patterns for maintaining interlock. A string or soldier course should be used at the interface between the pavers and the edge restraint. A PCC edge restraint is typically used for street and alley projects. The edge restraint may be a standard curb and gutter section, a vertical curb section, or a narrow concrete slab, and should be placed on the subbase aggregates. After placement, the pavers are compacted with a high frequency plate compactor, which forces the joint material into the joints and begins compaction of the paver into the bedding layer. The pavement is transformed from a loose collection of pavers into an interlocked system capable of spreading vertical loads horizontally through the shear forces in the joints. One of the direct conflicts with the hydrologic design of PIP is the compaction of the subgrade soils. The structural design calls for subgrades compacted to 95% Modified Proctor Density according to AASHTO T 180. The effective compaction depth should be 12 inches minimum. This compaction requirement will prevent efficient infiltration of water through the subgrade and thus will likely necessitate a piping design to handle the stormwater that accumulates in the storage aggregate (unbound subbase). The engineer should provide a geotextile between the subgrade and the storage aggregate (subbase) as a means of preventing mixing of the materials. The geotextile should comply with Iowa DOT Section 4196 for subsurface drainage. C. Hydrologic Design The design process follows traditional storm sewer procedures for pavements. The initial step in the hydrologic design is the determination of the design storm event. Some agencies may establish the storm return period and the rainfall intensity. Information on intensity-duration-frequency for various return periods can be found in Chapter 2. In addition, the contributing area must be determined. The runoff volume should be determined according to the methods described in Chapter 2 using a design rainfall depth of 1.25 inches as a minimum, unless the jurisdiction has a different policy. The next step involves establishing the drainage area. The storm event is then applied to the drainage area and the volume of runoff is determined. The permeability of the subgrade soil is a critical design element. If the subgrade soil permeability is less than 1/2 inch per hour, a subdrain piping network will be needed. Soil compaction to support vehicular traffic will decrease permeability. Good design practice for vehicular traffic loads is to provide a minimum CBR of 5. Thus as the soil permeability is determined it should be assessed at the density required to realize a CBR of 5 under soaked conditions. 3 Revised: 2018 Edition

4 To maximize the effectiveness of the PIP, the pavement grade should be as flat as possible, although steeper grades can be used. The general guideline is that the longitudinal grade should be greater than 1% and less than 12%. Three design alternatives exist for the PIP. They are: Full infiltration: All of the stormwater runoff from the design storm is infiltrated into the subgrade soils. See Figure 5K-1.02.A. Partial exfiltration: Some of the design storm runoff is infiltrated and the remainder is collected in the subdrain system and slowly discharged into the downstream systems. This is accomplished by setting the subdrain pipe above the top of the subgrade. See Figure 5K B. Full Exfiltration: Soil permeability is limited and thus all of the runoff volume is carried away through the subdrain piping. See Figure 5K-1.02.C. Designers must also evaluate and provide for larger storm events. One way to provide for the larger storms but still provide for infiltration of the water quality storms is to raise the elevation of the intakes above the pavers so the small storms are infiltrated and the large storms are handled by the intakes and pipe network. Once the volume of runoff and the soil permeability are known, the thickness of the storage aggregate layer (Iowa DOT Gradation No. 13/ASTM Gradation No. 2) can be determined. The void space (volume of voids/volume of aggregate) for Iowa DOT Gradation No. 13 is 40%. A 40% void space provides 0.4 cubic feet of stormwater storage for each cubic foot of aggregate. Thus, the volume of the storage aggregate will need to be 2.5 times the volume of water to be stored. Due to the need to compact the subgrade soil to handle vehicles, it is very likely that subdrains will be needed to discharge at least a portion of the runoff. The elevation and sizing of the subdrains should be set to provide for full discharge of the design storm within 72 hours either through infiltration into the subgrade soil or through subdrain pipe discharge. In order to prevent absorption of the bedding stone into the storage aggregate layer, a layer of filter aggregate (Iowa DOT Gradation No. 3/ ASTM Gradation No. 57) is needed. This layer is typically 4 inches thick. The bedding aggregate (Iowa DOT Gradation No. 29/ASTM Gradation No. 8) is then placed 2 inches thick, compacted, and leveled. Fine graded sand should not be used as the bedding and for filling of voids due to the increased clogging potential. The pavers are placed, additional bedding stone is added to fill the voids in between the pavers, the area is swept, and finally the pavers are compacted. Sweeping prior to compaction is important to prevent stones on the surface from marring or cracking the pavers. That process may need to be repeated to entirely fill the voids. The final step is to sweep and remove any excess void filler stone. 4 Revised: 2018 Edition

5 Figure 5K-1.02: Permeable Interlocking Paver Design Alternatives 5 Revised: 2018 Edition

6 D. Construction Elements Monitoring and controlling the construction activities of a permeable interlocking paver project are critical to the long-term performance of the permeable pavement. Preventing and diverting sediment from entering the aggregates and pavement during construction must be of the highest priority. Aggregate stockpiles must be isolated to prevent contamination by sediment. Erosion and sediment control devices must be placed and maintained throughout the project until vegetation is fully established. All unnecessary vehicle and pedestrian traffic should be restricted once the aggregate placement has initiated. It may be necessary to wash vehicle and equipment tires to prevent tracking dirt and mud onto the aggregate layers. A test section (approximately 5 feet by 5 feet) should be constructed to provide a basis for construction monitoring. The test section should be placed on the prepared subgrade to illustrate the processes used to place the pavers and illustrate the paver pattern and the edge details. Restrict all equipment and workers from the paver placement area once the bedding stone has been placed, leveled, and compacted. Pavers may be placed by hand or mechanically. Placement should proceed from one end or side and continue work from the completed placement areas. An important consideration with mechanically placed pavers for large projects is to ensure the wear on the paver molds does not change the size of the pavers and thus impact the ability to correctly place the pavers. E. Maintenance As with any pavement, particularly permeable pavements, specific maintenance activities are necessary to achieve the design life of the pavement. PIP can become clogged with sediment that affects its infiltration rate. The rate of sedimentation can depend on the number and type of vehicles using the pavement, as well as the control of erosive soils adjacent to the pavement. The most important element of maintenance is keeping the sediment out of the pavement by vacuum sweeping. Regular vacuum street sweeping will maintain a high infiltration rate and keep out vegetation. Calibration of the vacuum force may be necessary to remove the sediment but minimize removal of the filler material from the joints. Over time, it may be necessary to add additional joint filler material to prevent intrusion by sediment. Winter maintenance involves plowing snow and applications of de-icing chemicals. Although not required, snowplows can be equipped with rubber edged blades to minimize chipping of the pavers. Use of de-icing chemicals is often not necessary because the PIP remains warmer throughout the winter. Sand should not be used as an abrasive for traction. The sand will clog the filler material in the pavement joints. 6 Revised: 2018 Edition

Permeable Pavement Systems

Permeable Pavement Systems Permeable Pavement Systems EGRA Stone ECO Stone CONSERVATION DESIGN FORUM Permeable Pavement Presentation Outline Case Studies Benefits Hydrologic Design Engineering Design Construction Considerations

More information

Installation Manual May 9/14 No revision

Installation Manual May 9/14 No revision 815 NE 172 nd Avenue Vancouver, WA 98684 877-694-0141 Installation Manual May 9/14 No revision Installation steps include job planning, layout, excavating and preparing the soil subgrade, applying geotextiles

More information

815 NE 172 nd Avenue Vancouver, WA Installation Manual

815 NE 172 nd Avenue Vancouver, WA Installation Manual 815 NE 172 nd Avenue Vancouver, WA 98684 800-377-3877 www.xeripave.com info@xeripave.com Installation Manual Installation steps include job planning, layout, excavating and preparing the soil sub grade,

More information

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance. The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language

More information

Subsurface Infiltration Bed

Subsurface Infiltration Bed Subsurface Infiltration Bed The Subsurface Infiltration Bed BMP consists of a storage bed underlying either a vegetated or hardscaped surface for the purpose of temporary storage and infiltration of stormwater

More information

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS 5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS Low Impact Development (LID) requires a shift in stormwater management away from conveying runoff to a small number of downstream points through hydraulically

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF INTERLOCKING CONCRETE PAVERS

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF INTERLOCKING CONCRETE PAVERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 355 NOVEMBER 2014 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF INTERLOCKING CONCRETE PAVERS TABLE OF CONTENTS 355.01 SCOPE 355.02 REFERENCES

More information

Permeable Interlocking Concrete Pavement A Low Impact Development Tool Training for Developers

Permeable Interlocking Concrete Pavement A Low Impact Development Tool Training for Developers Permeable Interlocking Concrete Pavement A Low Impact Development Tool Training for Developers Presented by: Interlocking Concrete Pavement Institute The Low Impact Development Center, Inc. North Carolina

More information

Permeable Pavement [STRATEGY] Page 1

Permeable Pavement [STRATEGY] Page 1 [STRATEGY] Brief Description Permeable pavement systems, also referred to as pervious or porous paving, allow stormwater runoff to filter through the pavement section and infiltrate into the soil below.

More information

Technical Assistance Permeable Interlocking Concrete Pavement PICP

Technical Assistance Permeable Interlocking Concrete Pavement PICP Permeable Interlocking Concrete Pavement PICP Rick Crooks, Director of Business Development Mutual Materials Co. Bellevue, WA 1-800-477-3008 rcrooks@mutualmaterials.com Information and tools available

More information

Appendix G. Detailed Design

Appendix G. Detailed Design Appendix G Detailed Design G1: Construction details Construction detail drawings usually include important details and specifications for required project design elements. This section provides information

More information

The Concept. Features. Benefits

The Concept. Features. Benefits The Concept 02 The concept of Ecopave permeable paving is already well established in many countries where development threatens already over-stretched drainage and river systems. As more land is developed

More information

GREEN COLLECTION E C O - F R I E N D LY P E R M E A B L E P A V E R S T R E M R O N. C O M

GREEN COLLECTION E C O - F R I E N D LY P E R M E A B L E P A V E R S T R E M R O N. C O M GREEN COLLECTION E C O - F R I E N D LY P E R M E A B L E P A V E R S T R E M R O N. C O M MANAGE STORMWATER RUNOFF 4 x8 : 96 specially designed pavers will reduce or eliminate storm water run-off and

More information

Construction of Interlocking Concrete Pavements

Construction of Interlocking Concrete Pavements Tech Spec 2 Construction of Interlocking Concrete Pavements Purpose This technical bulletin gives construction guidelines to design professionals and contractors of interlocking concrete pavements. The

More information

Bioretention cell schematic key

Bioretention cell schematic key Bioretention Cells Bioretention cell schematic key 1 3 Hardwood mulch 2 Curb cut 3 18-30 Modified soil 4 Stone aggregate choker layer 5 Stone aggregate base layer 6 Subdrain 7 Undisturbed soil 8 Overflow/Cleanout

More information

Appendices: Glossary. General Terms. Specific Terms. Low Impact Development Approaches Handbook

Appendices: Glossary. General Terms. Specific Terms. Low Impact Development Approaches Handbook 67 67 General Terms Specific Terms 66 Low Impact Development Approaches Handbook The vocabulary of low impact development is evolving, and many terms are used interchangeably and to describe the same or

More information

INFILTRATION TRENCH - LEAKY PIPE

INFILTRATION TRENCH - LEAKY PIPE INFILTRATION TRENCH - LEAKY PIPE FLOW PERFORATED CMP OR RCP WITH PULLED JOINTS OVERSIZED PIPE (INLINE DETENTION) PERFORATED CMP OR RCP WITH PULLED JOINTS EXFILTRATE TRENCH VOLUME EXFILTRATE SEDIMENT SUMP

More information

DRIVABLE GRASS GUIDELINE FOR PLANTED INFILL INSTALLATION

DRIVABLE GRASS GUIDELINE FOR PLANTED INFILL INSTALLATION DRIVABLE GRASS GUIDELINE FOR PLANTED INFILL INSTALLATION Please read through this instruction completely before beginning your installation. Be sure the proper equipment, and safety precautions are in

More information

Green Street BMP Matrix

Green Street BMP Matrix Bioswale Can be planted with either grass or native vegetation, bioswales are best served in residential, industrial, and commercial www.duluthstreams.ogr landuse with smaller tributary drainage areas.

More information

PERMEABLE PAVEMENTS. Have been around for a long time, but are poised for a resurgence

PERMEABLE PAVEMENTS. Have been around for a long time, but are poised for a resurgence PERMEABLE PAVEMENTS Have been around for a long time, but are poised for a resurgence Three Broad Types of Pavers PC: Porous Concrete PA: Porous Asphalt IP: Interlocking Concrete Pavers The depth of the

More information

Green Infrastructure and Low-Impact Development Technologies

Green Infrastructure and Low-Impact Development Technologies Green Infrastructure and Low-Impact Development Technologies The guiding principles of these technologies is to manage stormwater at their sources using natural means, and establish conditions so that

More information

Portland, Oregon, (population 551,000) endeavors to maintain

Portland, Oregon, (population 551,000) endeavors to maintain Portland Tries Permeable Interlocking Concrete Street Pavements Known for its leadership in environment stewardship, The City of Portland, Oregon, placed over 19,000 sf (1,765 m 2 ) of permeable interlocking

More information

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion Topics Erosion, TESC and Construction sequencing Procedures and timing Remedies for failing sites Curtis Hinman WSU Extension and Bio Systems Eng. Faculty Low Impact Development Specialist chinman@wsu.edu

More information

PAVER BLOCK FIXING INSTRUCTIONS VYARA ROTATIONAL INTERLOCK

PAVER BLOCK FIXING INSTRUCTIONS VYARA ROTATIONAL INTERLOCK INTRODUCTION AND ACKNOWLEDGMENTS This manual is designed as a basic guide to be used by paver laying contractors. The format of the manual and much of the information contained herein are taken from the

More information

Paving Systems Using Clay Pavers on a Sand Setting Bed

Paving Systems Using Clay Pavers on a Sand Setting Bed TECHNICAL NOTES on Brick Construction 12007 Sunrise Valley Drive, Suite 430, Reston, Virginia 20191 www.gobrick.com 703-620-0010 14A May 2017 Paving Systems Using on a Abstract: This Technical Note describes

More information

PAVING PARKING AREAS AND ROADS DESCRIPTION. Alternate Names: Pavement Practices, Impervious Paving

PAVING PARKING AREAS AND ROADS DESCRIPTION. Alternate Names: Pavement Practices, Impervious Paving 4.2-i PAVING PARKING AREAS AND ROADS Alternate Names: Pavement Practices, Impervious Paving DESCRIPTION All roads, driveways, and parking lots proposed for year-round use shall be paved with a hard plowable

More information

FACT SHEET: Pervious Pavement with Infiltration

FACT SHEET: Pervious Pavement with Infiltration FACT SHEET: Pervious Pavement with Infiltration DESCRIPTION Pervious pavement is a Green Infrastructure (GI) technique that combines stormwater infiltration, storage, and structural pavement consisting

More information

Stormwater Control Plan: Small (Tier 1) Land Development Project

Stormwater Control Plan: Small (Tier 1) Land Development Project Stormwater Control Plan: Small (Tier 1) Land Development Project Project ID for Tracking (for City Staff only): The California Regional Water Quality Control Board for the Central Coast Region (Water Board)

More information

Pavements Built for the Future

Pavements Built for the Future Pavements Built for the Future Main Street Warrenville, IL Permeable Interlocking Concrete Pavement Durable, Sustainable, Attractive Segmental paving dates back to the Roman Empire. Today s version is

More information

Homeowners Guide to Stormwater BMP Maintenance

Homeowners Guide to Stormwater BMP Maintenance Homeowners Guide to Stormwater BMP Maintenance What You Need to Know to Take Care of Your Property Rain Barrel Dry Well Rain Garden Pervious Asphalt Porous Pavers City of El Monte Stormwater BMP Management

More information

CLAY BRICK PERVIOUS PAVEMENT CASE STUDY CITY OF NEW ALBANY

CLAY BRICK PERVIOUS PAVEMENT CASE STUDY CITY OF NEW ALBANY OWEA COLLECTIONS CONFERENCE 2012 CLAY BRICK PERVIOUS PAVEMENT CASE STUDY CITY OF NEW ALBANY May 10, 2012 Travis Eifert, PE, LEED AP Doug Turney, PE, CFM, LEED AP EMH&T STORMWATER MASTER PLAN VILLAGE CENTER

More information

C-10. Disconnected Impervious Surface

C-10. Disconnected Impervious Surface C-10. Disconnected Impervious Surface Design Objective Disconnected Impervious Surface (DIS) is the practice of directing stormwater runoff from built-upon areas to properly sized, sloped and vegetated

More information

Concrete pavers with sand filled joints. Bedding sand 1-1/2 in. (25-40 mm) thick

Concrete pavers with sand filled joints. Bedding sand 1-1/2 in. (25-40 mm) thick TECH SPEC N U M B E R 10 Application Guide for Interlocking Concrete Pavements This technical bulletin provides an overview of interlocking concrete pavements for a range of applicatons. The Interlocking

More information

County of Prince Edward. Stormwater Management Plan. Agreement in lieu of a Stormwater Management Plan

County of Prince Edward. Stormwater Management Plan. Agreement in lieu of a Stormwater Management Plan County of Prince Edward Stormwater Management Program Date: E-Permitting Number: This stormwater management plan (Agreement) is hereby submitted by the Owner to specify the methods that will be implemented

More information

Planning, Design, and Construction of Green Infrastructure.

Planning, Design, and Construction of Green Infrastructure. Planning, Design, and Construction of Green Infrastructure www.water.rutgers.edu What is Green Infrastructure? an approach to stormwater management that is costeffective, sustainable, and environmentally

More information

Appendix B DETAILED DESIGN

Appendix B DETAILED DESIGN Appendix B DETAILED DESIGN Design details for bioretention/bioswale Figures 1 and 2 provide cross-sectional details of standard bioswales and bioretention installations used in design drawings. Table 1

More information

Pollutant Removal Benefits

Pollutant Removal Benefits Bioswales Bioswales Similar to biocells, but have a slight, but positive grade toward an outlet Designed to convey the WQv event at very low velocities Promote filtration through native vegetation, infiltration

More information

WQ-07 INFILTRATION TRENCH

WQ-07 INFILTRATION TRENCH Greenville County Technical Specification for: WQ-07 INFILTRATION TRENCH 1.0 Infiltration Trench 1.1 Description Infiltration Trenches are excavations filled with stone to create an underground reservoir

More information

AASHTO M Subsurface Drainage

AASHTO M Subsurface Drainage Subsurface Drainage Description: This specification is applicable to placing a geotextile against the soil to allow long-term passage of water into a subsurface drain system retaining the in -situ soil.

More information

Low Impact Development (LID) Techniques. Associate BD Presentation, October 7, 2014

Low Impact Development (LID) Techniques. Associate BD Presentation, October 7, 2014 Low Impact Development (LID) Techniques Associate BD Presentation, October 7, 2014 Low Impact Development (LID) Techniques What are LIDs? Why are they used? Where are they used? How are they designed or

More information

ABBREVIATIONS. Dwg LID of 1. Abbreviations

ABBREVIATIONS. Dwg LID of 1. Abbreviations ABBREVIATIONS DIA DIAMETER EL ELEVATION FT2 SQUARE FOOT GAL/MIN GALLONS PER MINUTE H HORIZONTAL HDPE HIGH DENSITY POLYETHYLENE HMAC HOT MIX ASPHALT CONCRETE IE INVERT ELEVATION MAX MAXIMUM NO. NUMBER ODEQ

More information

2.1.4 Roof Downspout Rain Gardens

2.1.4 Roof Downspout Rain Gardens 2008 SWMM, 2010 Revision City of Tacoma 2.1.4 Roof Downspout Rain Gardens Purpose and Definition Bioretention areas are shallow stormwater retention facilities designed to mimic forested systems by controlling

More information

Attachment 2: Permeable Pavement Design Guidelines

Attachment 2: Permeable Pavement Design Guidelines Attachment 2: Permeable Pavement Design Guidelines Design of permeable pavement systems is critical if they are to function properly and efficiently. The area and shape are dependent on the site design,

More information

ENVIRONMENTAL PAVING SOLUTIONS

ENVIRONMENTAL PAVING SOLUTIONS ENVIRONMENTAL PAVING SOLUTIONS Control Stormwater Runoff Reduce Stormwater Pollutants Enhance Land-Use Planning Reduce Drainage Retention Needs 2 Contents LEED Contributions... 2 Paver Construction...

More information

The following general requirements will be met for all planter box installations:

The following general requirements will be met for all planter box installations: Greenville County Technical Specification for: WQ-25 PLANTER BOX 1.0 Planter Box 1.1 Description Planter boxes are designed to capture and temporarily store stormwater runoff. Planter Boxes are intended

More information

Preparing a Stormwater Control Plan for a Small Land Development Project

Preparing a Stormwater Control Plan for a Small Land Development Project Preparing a Stormwater Control Plan for a Small Land Development Project Addendum to the Stormwater C.3 Guidebook December 1, 2012 Introduction As of December 1, 2012, development projects that create

More information

Technical Bullet Series on Clay Brick Pavers

Technical Bullet Series on Clay Brick Pavers 2701 Shorefair Drive, Winston-Salem, NC 27105 pinehallbrick.com 1-800-334-8689 Technical Bullet Series on Clay Brick Pavers #4 Designing For Heavy Vehicular Traffic Abstract This Tech Bullet focuses on

More information

Te c h S p e c 3. Edge Restraints for Interlocking Concrete Pavements

Te c h S p e c 3. Edge Restraints for Interlocking Concrete Pavements Te c h S p e c 3 Edge Restraints for Interlocking Concrete Pavements Introduction Edge restraints are an essential component of interlocking concrete pavements. Restraints hold the pavers tightly together,

More information

P A V E R S Are they really the same? The 3-P s and how they relate to storm water management

P A V E R S Are they really the same? The 3-P s and how they relate to storm water management PERVIOUS PERMEABLE POROUS P A V E R S Are they really the same? The 3-P s and how they relate to storm water management By: Mark Walker Director, Business Development Office: (574) 232-9911 Mobile: (574)

More information

GSI Handbook Details Pervious Pavement

GSI Handbook Details Pervious Pavement GSI Handbook Details Workshop April 10, 2018 GSI Handbook Details Pervious Pavement Peter Schultze-Allen, EOA / SCVURPPP Outline of Presentation Pervious pavement basics Types of pervious pavement and

More information

The Engineer/Developer s Perspective on Storm Water Management

The Engineer/Developer s Perspective on Storm Water Management The Engineer/Developer s Perspective on Storm Water Management CASE STUDY: An Innovative Approach to Storm Water Management for Small Parcel Site Development Presented by: James B. Leedom, P.E. The Sigma

More information

2008 SWMM, 2010 Revision City of Tacoma

2008 SWMM, 2010 Revision City of Tacoma 2008 SWMM, 2010 Revision City of Tacoma 2.2.3.1 BMP L630 Rain Gardens Purpose and Definition Bioretention areas are shallow stormwater retention facilities designed to mimic forested systems by controlling

More information

Low Density Projects. Design Objective

Low Density Projects. Design Objective E-1. Low Density Projects Design Objective Low density projects are not required to be equipped with Stormwater Control Measures (SCMs) in exchange for limiting their built-upon area, maximizing dispersed

More information

City of Bonita Springs Driveway Permit Information Packet

City of Bonita Springs Driveway Permit Information Packet City of Bonita Springs Driveway Permit Information Packet General: As stated in American Association of State Highway and Transportation Officials (AASHTO) Geometric Design of Highways and Streets A driveway

More information

HEALTH SCIENCES BUILDING REDEVELOPMENT PROJECT

HEALTH SCIENCES BUILDING REDEVELOPMENT PROJECT INTRODUCTION In recent years, the University of Cincinnati (University) has demonstrated a commitment to identifying and implementing sustainable goals and objectives throughout University s Uptown Campuses.

More information

Tech Spec 10. Application Guide for Interlocking Concrete Pavements. Concrete pavers with sand filled joints. Edge restraint/curb

Tech Spec 10. Application Guide for Interlocking Concrete Pavements. Concrete pavers with sand filled joints. Edge restraint/curb Tech Spec 10 Application Guide for Interlocking Concrete Pavements This technical bulletin provides an overview of interlocking concrete pavements for a range of applicatons. The Interlocking Concrete

More information

HORSE STABLE USING AZEK PAVERS.

HORSE STABLE USING AZEK PAVERS. HORSE STABLE USING AZEK PAVERS When choosing a new floor for their horse stable these horse owners understood that the most common horse stable surfaces such as concrete, dirt, clay or aggregate (loose

More information

George Bialecki, Jr. takes green building seriously. Autumn Trails Pioneers

George Bialecki, Jr. takes green building seriously. Autumn Trails Pioneers Autumn Trails Pioneers PICP in Streets Autumn Trails in Moline, Illinois demonstrates the cost-savings of permeable interlocking concrete pavement to developers, cities and homeowners. George Bialecki,

More information

BIORETENTION CELLS. Green Infrastructure For Stormwater Management WHAT ARE BIORETENTION CELLS? WHERE ARE BIOCELLS INSTALLED?

BIORETENTION CELLS. Green Infrastructure For Stormwater Management WHAT ARE BIORETENTION CELLS? WHERE ARE BIOCELLS INSTALLED? BIORETENTION CELLS Green Infrastructure For Stormwater Management WHAT ARE BIORETENTION CELLS? Bioretention cells (or biocells) are one of the most widely used green infrastructure practices for managing

More information

DEALING WITH STORM WATER MANAGEMENT

DEALING WITH STORM WATER MANAGEMENT December 2012 DEALING WITH STORM WATER MANAGEMENT This fact sheet provides information on the guiding principles of storm water management practices, explains the difference between structural and non-structural

More information

Porous Pavements for Stormwater Restoration in Urban Environments

Porous Pavements for Stormwater Restoration in Urban Environments Porous Pavements for Stormwater Restoration in Urban Environments Cliff Aichinger Ramsey-Washington Metro Watershed District 1 Porous Pavements Why am I talking about this topic: I am not an engineer.

More information

Green Infrastructure Overview

Green Infrastructure Overview Green Infrastructure Overview Christopher C. Obropta, Ph.D., P.E. obropta@envsci.rutgers.edu Jeremiah Bergstrom, LLA, ASLA jbergstrom@envsci.rutgers.edu February 26, 2016 Water Resources Program NJDEP

More information

Table 4.7.1: Swales Potential Application and Storm Water Regulation

Table 4.7.1: Swales Potential Application and Storm Water Regulation 4.7. Swales A swale is a vegetated open channel, planted with a combination of grasses and other herbaceous plants, shrubs, or trees. A traditional swale reduces peak flow at the discharge point by increasing

More information

Stormwater Management Techniques WMPF LAND USE TRAINING INSTITUTE MARCH 14, 2018

Stormwater Management Techniques WMPF LAND USE TRAINING INSTITUTE MARCH 14, 2018 Stormwater Management Techniques WMPF LAND USE TRAINING INSTITUTE MARCH 14, 2018 Potential Impacts of New Development Urban development can significantly increase stormwater runoff Water quality considerations

More information

Selecting Appropriate Stormwater Control Measures for Your Development Project

Selecting Appropriate Stormwater Control Measures for Your Development Project Phase II Post-Construction Stormwater Requirements Workshop - February 10, 2014 Selecting Appropriate Stormwater Control Measures for Your Development Project Jill Bicknell, P.E., EOA, Inc. Outline of

More information

SMALL PAVER PROJECT. Home Gardeners School March 19, Presented by Robert W. Bellek Owner

SMALL PAVER PROJECT. Home Gardeners School March 19, Presented by Robert W. Bellek Owner SMALL PAVER PROJECT Home Gardeners School March 19, 2016 Presented by Robert W. Bellek Owner LET S GET STARTED You re going to need some important tools in order to accomplish your patio with less headaches

More information

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance. The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language

More information

APPENDIX G: TOWN ORDINANCE REVIEW

APPENDIX G: TOWN ORDINANCE REVIEW APPENDIX G: TOWN ORDINANCE REVIEW TYLin (225740) Woodard & Curran SWMP January 2013 Stormwater LID strategies, ranked for Zoning Bylaw and Site Plan Review Standards Dimensional Requirements Permit the

More information

Maintenance and Restoration of Porous Pavement Surfaces. Elgin Sweeper Company Mark D. Kinter, Technical Consultant

Maintenance and Restoration of Porous Pavement Surfaces. Elgin Sweeper Company Mark D. Kinter, Technical Consultant Maintenance and Restoration of Porous Pavement Surfaces Elgin Sweeper Company Mark D. Kinter, Technical Consultant Porous surfaces have been growing at a double digit rate the last several years as a BMP

More information

Paving Systems Using Clay Pavers

Paving Systems Using Clay Pavers TECHNICAL NOTES on Brick Construction 14 12007 Sunrise Valley Drive, Suite 430, Reston, Virginia 20191 www.gobrick.com 703-620-0010 May 2017 Paving Systems Using Clay Pavers Abstract: This Technical Note

More information

Site design measures. Chapter. This Chapter explains how site design measures can reduce the size of your project s stormwater treatment measures.

Site design measures. Chapter. This Chapter explains how site design measures can reduce the size of your project s stormwater treatment measures. Chapter 4 Site Design Measures This Chapter explains how site design measures can reduce the size of your project s stormwater treatment measures. Site design measures for water quality protection are

More information

Low Impact Development Site Design

Low Impact Development Site Design Chapter 4 Low Impact Development Site Design In this Chapter: How site design measures can reduce stormwater treatment measure size Tree preservation and planting Self-treating and self-retaining areas

More information

Post Construction BMPs

Post Construction BMPs Post Construction BMPs Why are Post Construction BMPs important? With increased development brings the increase of impervious cover Parking lots, rooftops, driveways Storm water runoff volume increases

More information

SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS

SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS Introduction As required by federal and state law, the Borough of Swarthmore has adopted regulations that affect stormwater runoff and surface

More information

2I-5 Bioswales (Numbering pending)

2I-5 Bioswales (Numbering pending) Iowa Stormwater Management Manual 2I-3 2I-5 Bioswales (Numbering pending) Source: Steve Anderson, 2011 BENEFITS Low =

More information

n1. Design 5.4.6a Urban Bioretention 5.4.6a Urban Bioretention Variations: Planter box, Extended tree pits, Stormwater curb extensions.

n1. Design 5.4.6a Urban Bioretention 5.4.6a Urban Bioretention Variations: Planter box, Extended tree pits, Stormwater curb extensions. 5.4.6a Urban Bioretention Variations: Planter box, Extended tree pits, Stormwater curb extensions. Description: Urban bioretention SCM are similar in function to regular bioretention practices except they

More information

Appendix D - Technical Design Criteria for BMPs

Appendix D - Technical Design Criteria for BMPs Appendix D - Technical Design Criteria for BMPs City of Wayzata Page 3 On-site infiltration features Definitions and Scope: Infiltration facilities are constructed basins or depressions located in permeable

More information

ARCHITECTURAL PAVING STONE PRODUCT CATALOG

ARCHITECTURAL PAVING STONE PRODUCT CATALOG ARCHITECTURAL PAVING STONE PRODUCT CATALOG ARCHITECTURAL PAVING STONES - 360, H STREET, WASHINGTON, D.C. ARCHITECTURAL PAVING STONE Nitterhouse s high strength Architectural Pavers combine durability with

More information

DIVISION E ENGINEERING STANDARDS

DIVISION E ENGINEERING STANDARDS CITY OF ALBANY DEPARTMENT OF PUBLIC WORKS DIVISION E STORMWATER MANAGEMENT ENGINEERING STANDARDS Prepared By PUBLIC WORKS DEPARTMENT ALBANY, OREGON 97321 Telephone: (541) 917-7676 TABLE OF CONTENTS E 1.00

More information

Ames City Hall Campus: Stormwater Improvements

Ames City Hall Campus: Stormwater Improvements Ames City Hall Campus: Stormwater Improvements Tracy Warner, Municipal Engineer for the City of Ames, IA Jake Moore, Stormwater Specialist for the City of Ames, IA Ryan Benjegerdes, Water Resources Engineer

More information

24. Disconnected Impervious Surface (DIS)

24. Disconnected Impervious Surface (DIS) 24. Disconnected Impervious Surface (DIS) Description Disconnected Impervious Surface (DIS) is the practice of directing stormwater runoff from built-upon areas to properly sized, sloped and vegetated

More information

Can Urban Redevelopment Restore Aquatic Resources

Can Urban Redevelopment Restore Aquatic Resources Can Urban Redevelopment Restore Aquatic Resources with Standards for Stormwater Retention and Landscape Performance? Rebecca C. Stack District of Columbia Department of the Environment Industry, Agriculture,

More information

6.1 Bioretention Areas

6.1 Bioretention Areas SAN MATEO COUNTYWIDE WATER POLLUTION PREVENTION PROGRAM 6.1 Bioretention Areas Figure 6-1. Bioretention Area. Source: City of Brisbane Bioretention areas 1, or rain gardens, are concave landscaped areas

More information

8 th Ave NW LID Retrofit

8 th Ave NW LID Retrofit Design and Construction of Porous Asphalt Pavements Presenter: Mark A. Palmer, P.E., LEED AP WSU LID Certified City Engineer City of Puyallup Foothills Trail, South Prairie Albany Remodel, Tumwater WSU

More information

THE FOLLOWING IS AN EXCERPT FROM THE 2011 CITY OF SEATTLE STANDARD SPECIFICATIONS WITH MINOR CORRECTIONS MADE TO SECTION 9-03.SEATTLE.

THE FOLLOWING IS AN EXCERPT FROM THE 2011 CITY OF SEATTLE STANDARD SPECIFICATIONS WITH MINOR CORRECTIONS MADE TO SECTION 9-03.SEATTLE. THE FOLLOWING IS AN EXCERPT FROM THE 2011 CITY OF SEATTLE STANDARD SPECIFICATIONS WITH MINOR CORRECTIONS MADE TO SECTION 9-03.2 THE COMPLETE 2011 EDITION MAY BE FOUND AT: HTTP://WWW.SEATTLE.GOV/UTIL/ENGINEERING/STANDARD_PLANS_&_SPECS/INDEX.ASP

More information

Inspection and Maintenance of Stormwater Best Management Practices

Inspection and Maintenance of Stormwater Best Management Practices FAC T S H E E T Inspection and Maintenance of Stormwater Best Management Practices is a general term that refers to vegetated stormwater best management practices (BMPs) that temporarily store rainwater

More information

Indirect Design Comparison of the structural strength of the pipe (Three- Edge-Bearing Test) to the field supporting strength of a buried pipe.

Indirect Design Comparison of the structural strength of the pipe (Three- Edge-Bearing Test) to the field supporting strength of a buried pipe. 2 Indirect Design Comparison of the structural strength of the pipe (Three- Edge-Bearing Test) to the field supporting strength of a buried pipe. Direct Design The design of pipe in the installed condition.

More information

World s Strongest Permeable Pavers

World s Strongest Permeable Pavers True to your project. True to the environment. PRESS KIT 2018 World s Strongest Permeable Pavers US Patent #8,734,049 US and Foreign Patents Pending www.truegridpaver.com 855-355-GRID TRUEGRID PAVER PRESS

More information

Stormwater Prevention and Control

Stormwater Prevention and Control Stormwater Prevention and Control Principles of Stormwater Management Stormwater Fact Sheet No. 4 This fact sheet is No. 4 of a eight-part series focused on stormwater runoff problems and control strategies.

More information

Standard Specifications for Lot-Scale Measures for Small Projects

Standard Specifications for Lot-Scale Measures for Small Projects Appendix K Standard Specifications for Lot-Scale Measures for Small Projects Table of Contents Section K.1 Permit Requirements for Small Projects... K-2 Section K.2 Regional Guidance for Site Design Measures...

More information

SEATTLE PUBLIC UTILITIES Drainage Design Options for street right of ways.

SEATTLE PUBLIC UTILITIES Drainage Design Options for street right of ways. SEATTLE PUBLIC UTILITIES Drainage Design Options for street right of ways. Numerous ecosystem-based functional stormwater quantity and quality design alternatives are possible within the street ROW. Several

More information

My Soil Won t Drain, Can I Still Use LID? Rob Buchert, John Knutson, Erik Pruneda

My Soil Won t Drain, Can I Still Use LID? Rob Buchert, John Knutson, Erik Pruneda My Soil Won t Drain, Can I Still Use LID? Rob Buchert, John Knutson, Erik Pruneda Presentation Topics Background information Designing LID for cold and snow prone conditions Applying LID in Pullman s low

More information

RUBBERSIDEWALKS Installation Manual

RUBBERSIDEWALKS Installation Manual RUBBERSIDEWALKS Installation Manual Overview 2 1 2 3 4 5 6 7 8 9 10 11 12 1) Break out existing concrete (use jackhammers near trees) and clean out loose soil 2) Conduct tree root inspection (if applicable)

More information

AWR Engineering, LLC

AWR Engineering, LLC AWR Engineering, LLC Alaska Water Resources Memorandum To: Kirsti Bischofberger, Watershed Manager, Municipality of Anchorage From: Janie Dusel, PE Date: February 3, 2017 Re: 2016 Low Impact Development/Green

More information

Vegetated Filter Strips and Buffers

Vegetated Filter Strips and Buffers 3.15 Sediment Control Description: Buffer strips (existing vegetation) and filter strips (planted vegetation) are sections of vegetated land adjacent to disturbed areas. They are designed with low slopes

More information

I N D U S T R I A L Y A R D S

I N D U S T R I A L Y A R D S I N D U S T R I A L Y A R D S GEOTEXTILES INDUSTRIAL YARDS 1.0 Features of INDUSTRIAL PG 2 YARDS 2.0 How Typar geotextiles PG 2 work 4.0 Installation guide PG 7 5.0 Overlap and joining PG 8 6.0 Setting

More information

Title 11 Streets and Sidewalks

Title 11 Streets and Sidewalks Chapter 11.01 - Definitions Title 11 Streets and Sidewalks Low Impact Development (LID) - A stormwater and land use management strategy that strives to mimic predisturbance hydrologic processes of infiltration,

More information

INTRODUCTION TO GREEN INFRASTRUCTURE HOW WE CAN PROTECT OUR COMMUNITIES AND OUR WATERS Maywood Public Library Bergen County, New Jersey

INTRODUCTION TO GREEN INFRASTRUCTURE HOW WE CAN PROTECT OUR COMMUNITIES AND OUR WATERS Maywood Public Library Bergen County, New Jersey INTRODUCTION TO GREEN INFRASTRUCTURE HOW WE CAN PROTECT OUR COMMUNITIES AND OUR WATERS Maywood Public Library Bergen County, New Jersey Jeremiah D. Bergstrom, LLA, ASLA Rutgers Cooperative Extension Water

More information

SMALL PROJECTS SIMPLIFIED APPROACH

SMALL PROJECTS SIMPLIFIED APPROACH SMALL PROJECT APPLICATION AND STORMWATER MANAGEMENT DESIGN ASSISTANCE MANUAL FOR SMALL PROJECTS IN FULTON TOWNSHIP LANCASTER COUNTY, PENNSYLVANIA SMALL PROJECTS SIMPLIFIED APPROACH Prepared By: Light-Heigel

More information

Placement of the soil should be in lifts of mm and loosely compacted (tamped lightly with a backhoe bucket).

Placement of the soil should be in lifts of mm and loosely compacted (tamped lightly with a backhoe bucket). 6 Rain Gardens Rain Gardens 6.1 Introduction A rain garden is used to attenuate peak flows and to provide stormwater treatment. Rain gardens use the concept of bioretention, a water quality practice in

More information