TENNESSEE GAS PIPELINE COMPANY, L.L.C.

Size: px
Start display at page:

Download "TENNESSEE GAS PIPELINE COMPANY, L.L.C."

Transcription

1 TENNESSEE GAS PIPELINE COMPANY, L.L.C. HYDROLOGIC AND HYDRAULIC CALCULATIONS FOR ACCESS ROADS ALONG THE CONNECTICUT PIPELINE EXPANSION PROJECT CONNECTICUT LOOP Submitted by: Tennessee Gas Pipeline Company, L.L.C. Louisiana St, Suite Houston, TX 77 APRIL

2 The attached hydrologic and hydraulic calculations were performed for all field surveyed waterbodies crossed by the Connecticut Pipeline Extension (Project) Hartford County Connecticut. The Project would consist of installing approximately. miles of pipeline looping:. Miles of 6-inch Pipeline Loop in Albany County, New York ( NY Loop ).8 Miles of 6-inch Pipeline Loop in Berkshire County, Massachusetts ( MA Loop ). 8. Miles of -inch Pipeline Loop in Hampden County, Massachusetts and Hartford County, Connecticut ( CT Loop). The primary objective of the attached calculations was to evaluate the amount of runoff due to the construction of permanent access roadways to the pipeline, and to size flume pipes at each waterbody crossing to convey, at a minimum, normal flow safely under the access roads. A typical flume installation will consist of sand bag cofferdams placed at the upstream and downstream limits of the construction workspace and the installation of the pipe specified in the design.

3 DESIGN CRITERIA AND METHODOLOGY The following design criteria and methodology was used to perform the calculations:. Hydrologic Methodology Hydrologic calculations were performed using a combination of the Rational Method, the NRCS (SCS) Peak Flow Method, USGS StreamStats, and USGS StreamStats with HydroCAD v... The specific method used to calculate the design flows for each waterbody varied based on parameters such as the watershed size, waterbody slope, basin elevation, and ground cover type (e.g. pasture, forest, urban). a. Rational Method: Q=CIA Q = flow (cubic feet per second - cfs) C = runoff coefficient A = drainage area (acres ac) I = rainfall intensity (inches per hour in/hr) This method was used for drainage areas up to acres in size NOAA Technical Memorandum NWS Hydro- was used to determine I in Connecticut County of Hartford. The following Runoff Coefficients were used: Cover Type Slope Range (%) Hydrologic Soil Group* Runoff Coefficient Pasture % - 6% D. Forest % % D. Forest > % D.8 Gravel %-% N/A.8 *Hydrologic Soil Group D was used for a conservative approach. Time of Concentrations were calculated using the following: o Sheet Flow: Manning s Kinematic Solution Maximum (max) sheet flow length of ft

4 o Shallow Concentrated Flow The travel time for shallow concentrated flow was calculated by dividing the travel path length by a calculated velocity. The velocity for specific cover types were calculated using Manning s equation. o Channel Flow As upstream channel morphology is not constant, the travel time for Channel flow was calculated by assuming a channel velocity of. ft/s and applying it to the shallow concentrated flow formula. b. NRCS (SCS) Peak Flow Method: The computer program HydroCAD, Version., was used to determine the peak flow discharges for the watershed. HydroCAD is a program which employs TR- methodology which uses the unit-hydrograph runoff procedure. As with TR-, the HydroCAD peak flow discharges are dependent upon parameters such as watershed size, the curve number for a given watershed, time of concentration, available flood storage, rainfall storm type, rainfall intensity and storm duration. The following curve numbers were used: Cover Type Hydrologic Soil Group* Curve Number (CN) Woods D 8 Pasture D 89 Urban D 98 *Hydrologic Soil Group D was used for poor soil conditions, and a conservative approach. Depths were used in conjunction with a -hour storm duration. The Time of Concentration was calculated using the same methodology used for the Rational Method. c. USGS StreamStats for Connecticut StreamStats is a Web-based tool developed by the USGS and Environmental Systems Research Institute, Inc. (ESRI). This map-based Web application was designed to make it easy for users to obtain stream flow statistics, drainage-basin characteristics, and other information for userselected sites. StreamStats utilizes previously published information from gaging stations and previously gathered basin characteristics to develop stream flow statistics utilizing the

5 appropriate regression equations to compute the stream flows. The StreamStats flows will only be utilized where the drainage area falls within the acceptable ranges for Mean/Base-Flow or for Peak Flow. Drainage areas outside the acceptable ranges generate flows that are based on extrapolations with unknown errors. d. Design Frequency: The design frequency utilized in the design varied based on the U.S. Weather Bureau Technical Paper. A -year design, a -year, and a -year maximum design storm were utilized for all watershed classifications. Average daily flow calculations were also performed for larger watersheds where the - and -year storms resulted in flows that cannot be completely passed within the designed pipes and it is unlikely that a -year or -year storm event will occur during the crossing.. Hydraulic Calculations The temporary flume pipes were sized using the Federal Highway Administration (FHWA) HY-8 computer program. HY-8 is a culvert analysis program that automates the design methods described in HDS No., Hydraulic Design of Highway Culverts.. Summary and Results The post construction hydrology of the access road areas are not significantly altered by the construction of the access roadways. The flows, summarized in the table below, are not significantly higher due to the construction of the access roadways and will not negatively impact the surrounding areas. See attached table on the next page, for flume pipe and stream crossing details. Pre-Development Flow CT PAR- Post-Development Flow Difference Difference (cfs) (cfs) (cfs) ( % ) -Year Year Year

6 X PP X X X X X X X X X X X X X X X X X AREA: CT PAR- // // // AREA: CT PAR-A // // // // // // // // //

7 S S S S CT PAR-a PRE CT PAR- PRE CT PAR- Post CT PAR-a POST R 6R PRE POST Subcat Reach Pond Link Routing Diagram for C-ENG-C78CT-PAR, Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC

8 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Time span=.-. hrs, dt=. hrs, points Runoff by Rational method, Rise/Fall=./. xtc Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method Subcatchment S: CT PAR- PRE Subcatchment S: CT PAR- Post Subcatchment S: CT PAR-a PRE Subcatchment S: CT PAR-a POST Reach R: PRE Reach 6R: POST Runoff Area=9.8 ac.8% Impervious Runoff Depth=." Flow Length=,7' Tc=9.6 min C=. Runoff=.67 cfs.6 af Runoff Area=9.8 ac.8% Impervious Runoff Depth=." Flow Length=,7' Tc=9.6 min C=. Runoff=.96 cfs.8 af Runoff Area=. ac.% Impervious Runoff Depth=." Flow Length=9' Tc=. min C=. Runoff=.7 cfs. af Runoff Area=. ac.% Impervious Runoff Depth=." Flow Length=9' Tc=. min C=.8 Runoff=.8 cfs.7 af Inflow=.9 cfs. af Outflow=.9 cfs. af Inflow=.79 cfs.7 af Outflow=.79 cfs.7 af Total Runoff Area =.788 ac Runoff Volume =.6 af Average Runoff Depth =." 99.6% Pervious =.66 ac.7% Impervious =.6 ac

9 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Subcatchment S: CT PAR- PRE.67 cfs Runoff CT- -yr Duration= min, Inten=. in/hr Runoff Area=9.8 ac Runoff Volume=.6 af Runoff Depth=." Flow Length=,7' Tc=9.6 min C=.

10 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Subcatchment S: CT PAR- Post.96 cfs CT- -yr Duration= min, Inten=. in/hr Runoff Area=9.8 ac Runoff Volume=.8 af Runoff Depth=." Flow Length=,7' Tc=9.6 min C=. Runoff

11 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Subcatchment S: CT PAR-a PRE cfs Runoff CT- -yr Duration= min, Inten=. in/hr Runoff Area=. ac Runoff Volume=. af Runoff Depth=." Flow Length=9' Tc=. min C=..

12 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page 6 Subcatchment S: CT PAR-a POST cfs CT- -yr Duration= min, Inten=. in/hr Runoff Area=. ac Runoff Volume=.7 af Runoff Depth=." Flow Length=9' Tc=. min C=.8 Runoff..

13 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page 7 Reach R: PRE 6.9 cfs Inflow Area=.89 ac Inflow Outflow

14 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page 8 Reach 6R: POST 6.79 cfs Inflow Area=.89 ac Inflow Outflow

15 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page 9 Time span=.-. hrs, dt=. hrs, points Runoff by Rational method, Rise/Fall=./. xtc Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method Subcatchment S: CT PAR- PRE Subcatchment S: CT PAR- Post Subcatchment S: CT PAR-a PRE Subcatchment S: CT PAR-a POST Reach R: PRE Reach 6R: POST Runoff Area=9.8 ac.8% Impervious Runoff Depth=.9" Flow Length=,7' Tc=9.6 min C=. Runoff=6.8 cfs.86 af Runoff Area=9.8 ac.8% Impervious Runoff Depth=." Flow Length=,7' Tc=9.6 min C=. Runoff=7.7 cfs. af Runoff Area=. ac.% Impervious Runoff Depth=." Flow Length=9' Tc=. min C=. Runoff=. cfs.9 af Runoff Area=. ac.% Impervious Runoff Depth=.8" Flow Length=9' Tc=. min C=.8 Runoff=. cfs.68 af Inflow=7.89 cfs.6 af Outflow=7.89 cfs.6 af Inflow=8.8 cfs.79 af Outflow=8.8 cfs.79 af Total Runoff Area =.788 ac Runoff Volume =.9 af Average Runoff Depth =." 99.6% Pervious =.66 ac.7% Impervious =.6 ac

16 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Subcatchment S: CT PAR- PRE cfs CT- -yr Duration= min, Inten=. in/hr Runoff Area=9.8 ac Runoff Volume=.86 af Runoff Depth=.9" Flow Length=,7' Tc=9.6 min C=. Runoff

17 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Subcatchment S: CT PAR- Post cfs Runoff 7 6 CT- -yr Duration= min, Inten=. in/hr Runoff Area=9.8 ac Runoff Volume=. af Runoff Depth=." Flow Length=,7' Tc=9.6 min C=.

18 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Subcatchment S: CT PAR-a PRE. cfs Runoff CT- -yr Duration= min, Inten=. in/hr Runoff Area=. ac Runoff Volume=.9 af Runoff Depth=." Flow Length=9' Tc=. min C=.

19 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Subcatchment S: CT PAR-a POST. cfs Runoff CT- -yr Duration= min, Inten=. in/hr Runoff Area=. ac Runoff Volume=.68 af Runoff Depth=.8" Flow Length=9' Tc=. min C=.8

20 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Reach R: PRE cfs Inflow Area=.89 ac Inflow Outflow 6

21 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=. in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Reach 6R: POST cfs Inflow Area=.89 ac Inflow Outflow 7 6

22 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=.9 in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page 6 Time span=.-. hrs, dt=. hrs, points Runoff by Rational method, Rise/Fall=./. xtc Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method Subcatchment S: CT PAR- PRE Subcatchment S: CT PAR- Post Subcatchment S: CT PAR-a PRE Subcatchment S: CT PAR-a POST Reach R: PRE Reach 6R: POST Runoff Area=9.8 ac.8% Impervious Runoff Depth=.8" Flow Length=,7' Tc=9.6 min C=. Runoff=.9 cfs.67 af Runoff Area=9.8 ac.8% Impervious Runoff Depth=.9" Flow Length=,7' Tc=9.6 min C=. Runoff=.67 cfs.76 af Runoff Area=. ac.% Impervious Runoff Depth=.88" Flow Length=9' Tc=. min C=. Runoff=.8 cfs. af Runoff Area=. ac.% Impervious Runoff Depth=." Flow Length=9' Tc=. min C=.8 Runoff=. cfs.9 af Inflow=.76 cfs.777 af Outflow=.76 cfs.777 af Inflow=.78 cfs.8 af Outflow=.78 cfs.8 af Total Runoff Area =.788 ac Runoff Volume =.6 af Average Runoff Depth =.89" 99.6% Pervious =.66 ac.7% Impervious =.6 ac

23 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=.9 in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page 7 Subcatchment S: CT PAR- PRE cfs CT- -yr Duration= min, Inten=.9 in/hr Runoff Area=9.8 ac Runoff Volume=.67 af Runoff Depth=.8" Flow Length=,7' Tc=9.6 min C=. Runoff

24 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=.9 in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page 8 Subcatchment S: CT PAR- Post cfs CT- -yr Duration= min, Inten=.9 in/hr Runoff Area=9.8 ac Runoff Volume=.76 af Runoff Depth=.9" Flow Length=,7' Tc=9.6 min C=. Runoff

25 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=.9 in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page 9 Subcatchment S: CT PAR-a PRE.8 cfs Runoff CT- -yr Duration= min, Inten=.9 in/hr Runoff Area=. ac Runoff Volume=. af Runoff Depth=.88" Flow Length=9' Tc=. min C=.

26 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=.9 in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Subcatchment S: CT PAR-a POST. cfs Runoff CT- -yr Duration= min, Inten=.9 in/hr Runoff Area=. ac Runoff Volume=.9 af Runoff Depth=." Flow Length=9' Tc=. min C=.8

27 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=.9 in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Reach R: PRE.76 cfs Inflow Area=.89 ac Inflow Outflow

28 C-ENG-C78CT-PAR CT- -yr Duration= min, Inten=.9 in/hr Printed 7// HydroCAD. s/n HydroCAD Software Solutions LLC Page Reach 6R: POST 6.78 cfs Inflow Area=.89 ac Inflow Outflow

BRISBANE BAYLANDS INFRASTRUCTURE PLAN FEBRUARY 2011 APPENDIX O DRAFT

BRISBANE BAYLANDS INFRASTRUCTURE PLAN FEBRUARY 2011 APPENDIX O DRAFT BRISBANE BAYLANDS INFRASTRUCTURE PLAN FEBRUARY 2011 APPENDIX O DRAFT PRELIMINARY STORM DRAIN CALCULATIONS ASSOCIATED WITH BRISBANE BAYLANDS REDEVELOPMENT BRISBANE, CALIFORNIA Prepared by BKF Engineers

More information

PSLS Surveyors' Conference Workshop Information Form Workshop Number: (leave blank if unknown) Hours: Workshop Title: Workshop Description: Suggested Speaker(s), affiliation/contact information 1. 2. 3.

More information

PRELIMINARY ENGINEERING REPORT

PRELIMINARY ENGINEERING REPORT PRELIMINARY ENGINEERING REPORT GRAND AVENUE STREET & SIDEWALK EXTENSION WORTHINGTON, MINNESOTA 6-3-15 Project No. 14-16841 Table of Contents Page # Introduction... 1 Project Need... 1 Design... 1 Costs

More information

STAFFORD TRACT NORTH OF US90A 1.0 INTRODUCTION 1.1 OBJECTIVE

STAFFORD TRACT NORTH OF US90A 1.0 INTRODUCTION 1.1 OBJECTIVE 1.0 INTRODUCTION 1.1 OBJECTIVE This report, prepared for submittal to TxDOT, analyzes existing and proposed detention facilities draining into the TxDOT US90A storm sewer system. The results of the detailed

More information

Pollutant Removal Benefits

Pollutant Removal Benefits Bioswales Bioswales Similar to biocells, but have a slight, but positive grade toward an outlet Designed to convey the WQv event at very low velocities Promote filtration through native vegetation, infiltration

More information

PRELIMINARY ENGINEERING REPORT

PRELIMINARY ENGINEERING REPORT PRELIMINARY ENGINEERING REPORT GRAND AVENUE STREET & SIDEWALK EXTENSION WORTHINGTON, MINNESOTA 7-25-14 Project No. 14-16841 Signature Sheet I HEREBY CERTIFY THAT THIS REPORT WAS PREPARED BY ME OR UNDER

More information

DRAINAGE CALCULATIONS

DRAINAGE CALCULATIONS DRAINAGE CALCULATIONS For the Carroll Single Family Residence At Santa Clara County Saratoga, California APN: 517-26-010 December 18, 2015 Prepared For: John and Peggy Carroll Prepared By: RI Engineering,

More information

STORMWATER REPORT FOR WALMART SUPERCENTER STORE # SIOUX FALLS, LINCOLN COUNTY, SOUTH DAKOTA BFA PROJECT NO

STORMWATER REPORT FOR WALMART SUPERCENTER STORE # SIOUX FALLS, LINCOLN COUNTY, SOUTH DAKOTA BFA PROJECT NO STORMWATER REPORT FOR WALMART SUPERCENTER STORE # 2443-00 SIOUX FALLS, LINCOLN COUNTY, SOUTH DAKOTA BFA PROJECT NO. 3286 March 1, 2012 I hereby certify that this engineering document was prepared by me

More information

ARIZONA WATER COMPANY

ARIZONA WATER COMPANY ARIZONA WATER COMPANY East Sedona Water Storage Facility February 21, 2018 Community Meeting STORMWATER RUNOFF Issue: Runoff sometimes flows out of the wash at bottlenecks in front of several homes on

More information

CHECKLIST FOR PHASE II DRAINAGE REPORT

CHECKLIST FOR PHASE II DRAINAGE REPORT I. COVER SHEET CHECKLIST FOR PHASE II DRAINAGE REPORT A. Name of Project B. Address C. Owner D. Developer E. Engineer F. Submittal date and revision dates as applicable II. GENERAL LOCATION AND DESCRIPTION

More information

PCE PRELIMINARY DRAINAGE ANALYSIS REPORT FOR WESTWOOD MIXED USE NEIGHBORHOOD PROJECT 772 NORTH FOREST ROAD TOWN OF AMHERST, ERIE COUNTY, NEW YORK

PCE PRELIMINARY DRAINAGE ANALYSIS REPORT FOR WESTWOOD MIXED USE NEIGHBORHOOD PROJECT 772 NORTH FOREST ROAD TOWN OF AMHERST, ERIE COUNTY, NEW YORK PCE PRELIMINARY DRAINAGE ANALYSIS REPORT FOR WESTWOOD MIXED USE NEIGHBORHOOD PROJECT 772 NORTH FOREST ROAD TOWN OF AMHERST, ERIE COUNTY, NEW YORK MAY 19, 2014 Prepared By: Timothy M. Lavocat, P.E., CFM

More information

Bioretention cell schematic key

Bioretention cell schematic key Bioretention Cells Bioretention cell schematic key 1 3 Hardwood mulch 2 Curb cut 3 18-30 Modified soil 4 Stone aggregate choker layer 5 Stone aggregate base layer 6 Subdrain 7 Undisturbed soil 8 Overflow/Cleanout

More information

26 Attachment 2. Township of New Britain APPENDIX B STORMWATER MANAGEMENT DESIGN CRITERIA

26 Attachment 2. Township of New Britain APPENDIX B STORMWATER MANAGEMENT DESIGN CRITERIA (26, APPENDIX B) 26 Attachment 2 Township of New Britain APPENDIX B STORMWATER MANAGEMENT DESIGN CRITERIA TABLE B-1 DESIGN STORM RAINFALL AMOUNT Source: Field Manual of Pennsylvania Department of Transportation

More information

APPENDIX B. Hydrologic and Hydraulic Analysis

APPENDIX B. Hydrologic and Hydraulic Analysis APPENDIX B Hydrologic and Hydraulic Analysis HYDROLOGIC AND HYDRAULIC ANALYSIS PETERSBURG ROAD IMPROVEMENTS DOT&PF Project No. 67879 Prepared for: State of Alaska Department of Transportation and Public

More information

October 7, City of Thornton 9500 Civic Center Drive Thornton, CO (303) RE: Maverik Thornton, CO - Drainage Report

October 7, City of Thornton 9500 Civic Center Drive Thornton, CO (303) RE: Maverik Thornton, CO - Drainage Report October 7, 2016 City of Thornton 9500 Civic Center Drive Thornton, CO 80229 (303) 538-7295 RE: Maverik Thornton, CO - Drainage Report As per your request, we are submitting to you the drainage report and

More information

Evaluating Low Impact Development Practices for Stormwater Management on an Industrial Site in Mississippi

Evaluating Low Impact Development Practices for Stormwater Management on an Industrial Site in Mississippi Evaluating Low Impact Development Practices for Stormwater Management on an Industrial Site in Mississippi Dennis S. Painter, Tennessee Valley Authority, Nashville, Tennessee Donald Becker, Tennessee Valley

More information

July 19, City of Watertown Attn: Justin Wood, City Engineer Room 305, City Hall 245 Washington Street Watertown, NY 13601

July 19, City of Watertown Attn: Justin Wood, City Engineer Room 305, City Hall 245 Washington Street Watertown, NY 13601 July 19, 2016 City of Watertown Attn: Justin Wood, City Engineer Room 305, City Hall 245 Washington Street Watertown, NY 13601 Re: Site Plan Review Application Access Drive and Infirmary Addition and Renovation

More information

Draft Rhode Island Stormwater Design and Installation Standards Manual

Draft Rhode Island Stormwater Design and Installation Standards Manual Draft Rhode Island Stormwater Design and Installation Standards Manual Summary The May 2009 Public Review Draft version of the RI Stormwater Design and Installation Standards Manual consists of approximately

More information

STORM WATER MANAGEMENT STUDY. Johnson County Park and Recreation District Verhaeghe Park

STORM WATER MANAGEMENT STUDY. Johnson County Park and Recreation District Verhaeghe Park STORM WATER MANAGEMENT STUDY Johnson County Park and Recreation District Verhaeghe Park Prepared By: The Clark Enersen Partners 1251 NW Briarcliff Parkway, Suite 400 Kansas City, MO 64116 October, 2017

More information

Table of Contents G.1.a Water Resources - Surface Water - Drainage

Table of Contents G.1.a Water Resources - Surface Water - Drainage Table of Contents G.1.a Water Resources - Surface Water - Drainage 1. INTRODUCTION... 1335 2. ENVIRONMENTAL SETTING... 1335 a. Regional Hydrology... 1335 b. Local Hydrology... 1337 c. On-site Hydrology...

More information

Three Rivers Park District Administration Center Rain Garden

Three Rivers Park District Administration Center Rain Garden Three Rivers Park District Administration Center Rain Garden Introduction There are significant changes to the hydrologic regime and nutrient loading following urban and industrial development. The post-development

More information

MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS

MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS May 2007 SECTION 1 Responsibility of Applicant TABLE OF CONTENTS A. Stormwater Management Plan Required Information

More information

City of Richmond. Engineering Design Specifications

City of Richmond. Engineering Design Specifications City of Richmond Design Specifications June 2008 CITY OF RICHMOND ENGINEERING DESIGN SPECIFICATIONS JUNE 2008 THIS DOCUMENT DETAILS THE MINIMUM STANDARDS TO BE USED FOR THE DESIGN OF ENGINEERING PROJECTS

More information

Outfall Flow Analysis for the Oswego Canal and Blue Heron Canal

Outfall Flow Analysis for the Oswego Canal and Blue Heron Canal DRAFT REPORT Outfall Flow Analysis for the Oswego Canal and Blue Heron Canal Prepared for: City of Lake Oswego, Oregon Prepared by: Pacific Water Resources, Inc. January 31, 2008 We Think the World of

More information

Appendix K. Stormwater Management Plan

Appendix K. Stormwater Management Plan Regional Municipality of Halton - Steeles Avenue (Regional Road 8) Class EA - Industrial Drive to Regional Road 25/Martin Street Appendix K Stormwater Management Plan PR226401.001 Rev. 2 PR.DOT, 00/01

More information

Modeling Cumulative LID Features for Floodplain Impacts in an Urban Watershed in Houston, TX

Modeling Cumulative LID Features for Floodplain Impacts in an Urban Watershed in Houston, TX Modeling Cumulative LID Features for Floodplain Impacts in an Urban Watershed in Houston, TX Christina Hughes, Phil Bedient cmhughes@rice.edu May 2, 2014 1 Modeling Cumulative LID Features for Floodplain

More information

Land Development Characteristics (Module 6)

Land Development Characteristics (Module 6) Land Development Characteristics (Module 6) Robert Pitt and Celina Bochis Department of Civil, Construction and Environmental Engineering The University of Alabama Tuscaloosa, AL 35487 Example of 1 m monochromatic

More information

City of Waco Stormwater Management Regulations

City of Waco Stormwater Management Regulations 1.0 Applicability: City of Waco Stormwater Management Regulations These regulations apply to all development within the limits of the City of Waco as well as to any subdivisions within the extra territorial

More information

NAPA COUNTY PUBLIC WORKS Standards & Specifications

NAPA COUNTY PUBLIC WORKS Standards & Specifications Roadway Design & Construction Manual (Table of Contents) 1. Chapter 1: General Provisions 1.1 Short Title 1.2 Jurisdiction 1.3 Purpose and Effect 1.4 Enactment Authority 1.5 Amendment and Revisions 1.6

More information

Going Green with the NYS Stormwater Design Standards

Going Green with the NYS Stormwater Design Standards Going Green with the NYS Stormwater Design Standards Shohreh Karimipour, P.E. NYSDEC History of Stormwater Management Ancient Greek Cisterns Water Cistern Systems in Greece from Minoan to Hellenistic Period,

More information

Session 1E Non-Structural BMPs. Chesapeake Bay Stormwater Training Partnership 1

Session 1E Non-Structural BMPs. Chesapeake Bay Stormwater Training Partnership 1 Session 1E Non-Structural BMPs Chesapeake Bay Stormwater Training Partnership 1 Agenda Site Design (self-crediting) Soil Amendments Simple l Disconnection Sheet Flow Grass Channels Site Plan courtesy of

More information

Washington County, Maryland Division of Public Works Policy Manual

Washington County, Maryland Division of Public Works Policy Manual Washington County, Maryland Division of Public Works Policy Manual Subject: Downstream Drainage Easement Category: Land Development Engineering Number: 7-4.1 Date: June 1, 2009 (effective) PURPOSE: The

More information

2I-5 Bioswales (Numbering pending)

2I-5 Bioswales (Numbering pending) Iowa Stormwater Management Manual 2I-3 2I-5 Bioswales (Numbering pending) Source: Steve Anderson, 2011 BENEFITS Low =

More information

Chapter 1 GENERAL SOUTH DAKOTA DRAINAGE MANUAL

Chapter 1 GENERAL SOUTH DAKOTA DRAINAGE MANUAL Chapter 1 GENERAL SOUTH DAKOTA DRAINAGE MANUAL October 2011 Table of Contents Section Page 1.1 INTRODUCTION...1-1 1.2 BASIC APPROACH...1-2 1.3 FUNCTIONAL RESPONSIBILITIES...1-3 1.3.1 Office of Road Design...1-3

More information

User s Guide for the BMP Sizing Tool. Revised December 2017

User s Guide for the BMP Sizing Tool. Revised December 2017 User s Guide for the BMP Sizing Tool Revised December 2017 Table of Contents Section 1.0 Introduction... 1 Section 2.0 Intended Audience... 2 Section 3.0 Installing and Starting the Application... 2 Section

More information

Managing Stormwater within the Road Right-of-Way: An Urban NAI Approach

Managing Stormwater within the Road Right-of-Way: An Urban NAI Approach Turgay Dabak, Joni Calmbacher, Sara DeGroot, Andrea Ryon Managing Stormwater within the Road Right-of-Way: An Urban NAI Approach Presentation Outline Project Background Project Overview BMPs Evaluated

More information

PRELIMINARY DRAINAGE REPORT LATHAM 200 MMSCFD GAS PROCESSING PLANT

PRELIMINARY DRAINAGE REPORT LATHAM 200 MMSCFD GAS PROCESSING PLANT PRELIMINARY DRAINAGE REPORT LATHAM 200 MMSCFD GAS PROCESSING PLANT LOTS B, RECORDED EXEMPTION 1211-2-1, RECX13-0096 LOCATED IN THE NORTH 1/2 OF SECTION 2, TOWNSHIP 3 NORTH, RANGE 66 WEST, 6 TH PRINCIPAL

More information

West Virginia Stormwater Management Manual: Methods.

West Virginia Stormwater Management Manual: Methods. West Virginia Stormwater Management Manual: Methods Created to deliver targeted training on new tools and practices to improve the quality of stormwater runoff. www.cbstp.org www.chesapeakestormwater.net

More information

Old Mill Community Association Bioretention Facility

Old Mill Community Association Bioretention Facility Project Overview This project will install a bioretention facility in a community recreation area owned by the Old Mill Community Association, Inc. Drainage from the area is currently unmanaged and has

More information

Lincoln 270. City of Lincoln. Stormwater Management Plan. April 2, 2013

Lincoln 270. City of Lincoln. Stormwater Management Plan. April 2, 2013 Lincoln 270 City of Lincoln Stormwater Management Plan April 2, 2013 # 2005.48 Prepared By: Civil Engineering Solutions, Inc. 590 E Street Lincoln, Ca 95648 (916) 645 5700 1.0 Background: The project site

More information

ENVISIONING THE POSSIBILITIES OF A DIGITAL CITY: A CASE STUDY OF RAIN GARDENS AS FLOOD CONTROL IN AUSTIN, TEXAS CE 394K FALL 2011 PROF.

ENVISIONING THE POSSIBILITIES OF A DIGITAL CITY: A CASE STUDY OF RAIN GARDENS AS FLOOD CONTROL IN AUSTIN, TEXAS CE 394K FALL 2011 PROF. ENVISIONING THE POSSIBILITIES OF A DIGITAL CITY: A CASE STUDY OF RAIN GARDENS AS FLOOD CONTROL IN AUSTIN, TEXAS BY KIERSTEN TYSSELAND DUBE CE 394K FALL 2011 PROF. MAIDMENT INTRODUCTION With the advent

More information

Project Name: Project Address or Location: Principal Designer Name and Company: Principal Designer Phone Number:

Project Name: Project Address or Location: Principal Designer Name and Company: Principal Designer Phone Number: SECTION 1: GENERAL INFORMATION Plan Submission Date: Total Disturbed Acreage: _ Project Name: Project Address or Location: Principal Designer Name and Company: Principal Designer Phone Number: email: SECTION

More information

Stormwater Retrofitting: The Art of Opportunity. Presented by the Center for Watershed Protection

Stormwater Retrofitting: The Art of Opportunity. Presented by the Center for Watershed Protection Stormwater Retrofitting: The Art of Opportunity Presented by the Center for Watershed Protection What Are Stormwater Retrofits? Retrofits are stormwater management measures inserted in an urban or ultra-urban

More information

Figure 1 Cypress Street Study Area Location Map

Figure 1 Cypress Street Study Area Location Map July 20, 2016 TO: FROM: Jim Massarelli Director of Engineering Jeff Julkowski, PE Michael Burke, PE SUBJECT: Cypress Street Study Area Stormwater Analysis (CBBEL Project No. 16-0058) At the request of

More information

Appendix I. Checklists

Appendix I. Checklists Appendix I Checklists Town of Greenwich Drainage Manual Department of Public Works - Engineering Division Town Hall - 101 Field Point Road, Greenwich, CT 06836-2540 Phone 203-622-7767 - Fax 203-622-7747

More information

DFH JOINT VENTURE. Stormwater Management Report for Proposed Residential Subdivision at Graham Block, Pokeno

DFH JOINT VENTURE. Stormwater Management Report for Proposed Residential Subdivision at Graham Block, Pokeno DFH JOINT VENTURE Stormwater Management Report for Proposed Residential Subdivision at Graham Block, Pokeno DOCUMENT CONTROL RECORD Document: DFH Joint Venture Graham Block Stormwater Management Report

More information

City of Elmhurst. City of Elmhurst. Storm Sewer System Workshop November 22, 2010

City of Elmhurst. City of Elmhurst. Storm Sewer System Workshop November 22, 2010 City of Elmhurst City of Elmhurst Storm Sewer System Workshop November 22, 2010 1 City of Elmhurst Watershed divide (green dashed line) through Elmhurst Area east of divide drains to Addison Creek Area

More information

PHASE III DRAINAGE REPORT

PHASE III DRAINAGE REPORT PHASE III DRAINAGE REPORT FOR Eastlake Assisted Living & Memory Care April 20, 2016 June 3, 2016 August 5, 2016 Prepared for: 3301 E 120 th Ave, LLC. 8200 E. Maplewood Ave., Suite 150 Greenwood Village

More information

ANSWER KEY MGSFlood v WWHM2012 (released 5/15/2015)

ANSWER KEY MGSFlood v WWHM2012 (released 5/15/2015) ANSWER KEY MGSFlood v. 4.35 --- WWHM2012 (released 5/15/2015) Name: Date: Module 6.0: Advanced Topics in LID Design: Hydrologic Modeling General instructions: You may model facility dimensions to the nearest

More information

North Branch of Cypress Creek Ecological Restoration: A Comprehensive Approach to Stream Restoration

North Branch of Cypress Creek Ecological Restoration: A Comprehensive Approach to Stream Restoration North Branch of Cypress Creek Ecological Restoration: A Comprehensive Approach to Stream Restoration Rocky Powell Clear Creeks Consulting, LLC Keith D. Tate, P.E. BayLand Consultants & Designers, Inc.

More information

WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES

WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES Greenville County Technical Specification for: WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES 1.0 Mountainous and Steep Slope Sites 1.1 Description The geographic locations of portions of Greenville County are

More information

PLAN SUBMITTER'S CHECKLIST

PLAN SUBMITTER'S CHECKLIST Page 1 of 8 PLAN SUBMITTER'S CHECKLIST FOR EROSION AND SEDIMENT CONTROL PLANS Please fill in all blanks and reference the plan sheets/pages where the information may be found, where appropriate, or write

More information

Stormwater Pollution Prevention Plan Oneonta Heights Oneonta, NY TABLE OF CONTENTS PAGE

Stormwater Pollution Prevention Plan Oneonta Heights Oneonta, NY TABLE OF CONTENTS PAGE Oneonta Heights Oneonta, NY TABLE OF CONTENTS PAGE I. INTRODUCTION... 2 II. EXISTING CONDITIONS... 3 A. Topography/ Drainage... 3 B. Soils... 3 C. Wetlands... 3 D. Floodplain... 3 E. NYSDEC Environmental

More information

Chapter 4 - Preparation of Stormwater Site Plans

Chapter 4 - Preparation of Stormwater Site Plans Chapter 4 - Preparation of Stormwater Site Plans The Stormwater Site Plan is the comprehensive report containing all of the technical information and analysis necessary for the City to evaluate a proposed

More information

ARTICLE III COMBINED SEWERS

ARTICLE III COMBINED SEWERS I ' j I' ARTICLE III COMBINED SEWERS COM'RS MIN.. VOL.281 JAN 2 2001 IMAGE Section 301 Construction; Extension of Sewers The construction of and/or extension to combined sewers are hereby prohibited, unless

More information

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS 5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS Low Impact Development (LID) requires a shift in stormwater management away from conveying runoff to a small number of downstream points through hydraulically

More information

Attachment 2: Permeable Pavement Design Guidelines

Attachment 2: Permeable Pavement Design Guidelines Attachment 2: Permeable Pavement Design Guidelines Design of permeable pavement systems is critical if they are to function properly and efficiently. The area and shape are dependent on the site design,

More information

MEMORANDUM. September 10, 2018

MEMORANDUM. September 10, 2018 September 10, 2018 MEMORANDUM TO: Chad Bird, City of Decorah FROM: Larry Weber and Dan Gilles, Iowa Flood Center, IIHR Hydroscience & Engineering COPY TO: Dana Werner, St. Paul District Corps of Engineers,

More information

When planning stormwater management facilities, the following principles shall be applied where possible.

When planning stormwater management facilities, the following principles shall be applied where possible. 2.0 Principles When planning stormwater management facilities, the following principles shall be applied where possible. 2.0.1 Drainage is a regional phenomenon that does not respect the boundaries between

More information

Town of Windsor. Stormwater Manual

Town of Windsor. Stormwater Manual Town of Windsor Stormwater Manual February 4, 2009 Last Revised August 17, 2009 275 Broad Street, Windsor, Connecticut 06095-2994 www.townofwindsorct.com List of Revisions Effective Sections(s) Remarks

More information

CHAPTER 9 STORM DRAINAGE. Minimum Requirements for New Development and Redevelopment

CHAPTER 9 STORM DRAINAGE. Minimum Requirements for New Development and Redevelopment CHAPTER 9 STORM DRAINAGE 9.01 General The standards established by this chapter are intended to represent the minimum standards for the design and construction of storm drainage facilities. 9.02 Design

More information

Predicting Design Storm Runoff for the Six Mile Creek Watershed: Effects of the Potential Sprawl-Is-Us, Inc. Development

Predicting Design Storm Runoff for the Six Mile Creek Watershed: Effects of the Potential Sprawl-Is-Us, Inc. Development Predicting Design Storm Runoff for the Six Mile Creek Watershed: Effects of the Potential Sprawl-Is-Us, Inc. Development Ross Guida Faulkner Consulting Engineers, Inc. December 19, 2008 1 Table of Contents

More information

Assessing Directly Connected Impervious Areas in Residential Subdivisions in Western Sydney, NSW

Assessing Directly Connected Impervious Areas in Residential Subdivisions in Western Sydney, NSW Assessing Directly Connected Impervious Areas in Residential Subdivisions in Western Sydney, NSW 1, 1 Cardno (APAC South), 203 Pacific Highway St Leonards, 2065. Email: Stephen.Gribble@cardno.com.au Key

More information

4. CONCEPT PLAN DEVELOPMENT

4. CONCEPT PLAN DEVELOPMENT 4. CONCEPT PLAN DEVELOPMENT Concept Plan Step 1: Identify Site Constraints and Opportunities Review the existing site to identify constraints and opportunities for GI Practices to meet the RRv. Constraints

More information

Village of New Maryland. Storm Water Management Master Plan

Village of New Maryland. Storm Water Management Master Plan Village of New Maryland Storm Water Management Master Plan Village of New Maryland Storm Water Management Master Plan Fredericton Office 80 Bishop Drive Fredericton NB E3C 1B2 Canada Telephone: +1 506

More information

Portland and Progressive Stormwater Design

Portland and Progressive Stormwater Design Cory Gallo, ASLA, LEED AP Emily Overbey, Graduate Student Brian Wethington, Portland BES Portland and Progressive Stormwater Design Regarded as a leader in progressive and innovative stormwater management

More information

TABLE OF CONTENTS 1 INTRODUCTION...

TABLE OF CONTENTS 1 INTRODUCTION... Drainage Report & Impact Analysis TABLE OF CONTENTS 1 INTRODUCTION.... 1 1.1 PROJECT DESCRIPTION AND LOCATION... 1 1.2 REPORT OBJECTIVES... 2 1.3 DRAINAGE DESIGN CRITERIA... 3 1.4 DRAINAGE DESIGN ASSUMPTIONS...

More information

Erosion & Sediment Control Plan Application Form & Checklist

Erosion & Sediment Control Plan Application Form & Checklist Erosion & Sediment Control Plan Application Form & Checklist GENERAL INFORMATION Application Date: Project Address: Tax Map / Parcel Number(s): PROPERTY OWNER / DEVELOPER Firm Name: Contact Person: Title:

More information

General Technical Guidance for Treatment Measures

General Technical Guidance for Treatment Measures Chapter 5 General Technical Guidance for Treatment Measures The technical guidance in this Chapter will help you with proper sizing and design concepts for various types of stormwater treatment measures.

More information

Development and Design of Cost-Effective, Real-Time Implementable Sediment and Contaminant Release Controls

Development and Design of Cost-Effective, Real-Time Implementable Sediment and Contaminant Release Controls Development and Design of Cost-Effective, Real-Time Implementable Sediment and Contaminant Release Controls Richard Warner, Ph.D. Biosystems and Agricultural Engineering Department University of Kentucky

More information

APPENDIX APPENDIX 6 STORMWATER MANAGEMENT REPORT

APPENDIX APPENDIX 6 STORMWATER MANAGEMENT REPORT APPENDIX APPENDIX 6 STORMWATER MANAGEMENT REPORT ECHO BAY NEW ROCHELLE, NEW YORK STORMWATER MANAGEMENT REPORT Prepared for: Forest City Residential Group 1 Metro Tech Center North Brooklyn, NY 11201 Prepared

More information

GREATER NEW HAVEN WPCA. GREEN REDEVELOPMENT REDUCES CSOs IN NEW HAVEN. Tom Sgroi, P.E. Director of Engineering, GNHWPCA

GREATER NEW HAVEN WPCA. GREEN REDEVELOPMENT REDUCES CSOs IN NEW HAVEN. Tom Sgroi, P.E. Director of Engineering, GNHWPCA 1 GREATER NEW HAVEN WPCA GREEN REDEVELOPMENT REDUCES CSOs IN NEW HAVEN Tom Sgroi, P.E. Director of Engineering, GNHWPCA Bruce Kirkland, P.E. Senior Engineer, GNHWPCA 2 1975 GREEN INFRASTRUCTURE BACKGROUND

More information

Evaluating Urban Stormwater Retrofits in the SE US Coastal Plain

Evaluating Urban Stormwater Retrofits in the SE US Coastal Plain Evaluating Urban Stormwater Retrofits in the SE US Coastal Plain 2017 Florida Stormwater Association June 14-17, 2017 Eban Z. Bean, PhD, PE Assistant Professor & Extension Specialist Agricultural and Biological

More information

Article 20 Stormwater Management

Article 20 Stormwater Management Article 20 Section 20.01 Intent Article 20 The purpose of this Article is to protect the health, safety, and general welfare of the citizens by requiring compliance with accepted standards and practices

More information

GIS Training of Undergraduates: Campus Stormwater Mapping. Joanne Logan, University of Tennessee. Gordie Bennett, University of Tennessee

GIS Training of Undergraduates: Campus Stormwater Mapping. Joanne Logan, University of Tennessee. Gordie Bennett, University of Tennessee GIS Training of Undergraduates: Campus Stormwater Mapping Joanne Logan, University of Tennessee Gordie Bennett, University of Tennessee Seth Benge, University of Tennessee Tim Prather, University of Tennessee

More information

MASTER DEVELOPMENT DRAINAGE PLAN FOR MONUMENT HEIGHTS

MASTER DEVELOPMENT DRAINAGE PLAN FOR MONUMENT HEIGHTS MASTER DEVELOPMENT DRAINAGE PLAN FOR MONUMENT HEIGHTS DRAINAGE REPORT STATEMENT ENGINEER'S STATEMENT: The attached drainage plan and report were prepared under my direction and supervision and are correct

More information

Hydrologic Assessment of using Low Impact Development to Mitigate the Impacts of Climate Change. Chris Jensen, AScT Master of Science Thesis

Hydrologic Assessment of using Low Impact Development to Mitigate the Impacts of Climate Change. Chris Jensen, AScT Master of Science Thesis Hydrologic Assessment of using Low Impact Development to Mitigate the Impacts of Climate Change Chris Jensen, AScT Master of Science Thesis Bowker Creek Initiative April 12, 2012 Outline 1. Future Impacts

More information

GIS-Enabled Rain Garden Design: A Case Study in Austin, Texas. GIS in Water Resources (C E 394K-3) Clint Smith, E.I.T.

GIS-Enabled Rain Garden Design: A Case Study in Austin, Texas. GIS in Water Resources (C E 394K-3) Clint Smith, E.I.T. GIS-Enabled Rain Garden Design: A Case Study in Austin, Texas GIS in Water Resources (C E 394K-3), E.I.T., MSCE 12/07/2018 Table of Contents: 1. Abstract 3 2. Introduction 4 2.1 Background 4 2.2 Project

More information

Blake C. Kronkosky, PE, Ph.D.

Blake C. Kronkosky, PE, Ph.D. Blake C. Kronkosky, PE, Ph.D. Blake.Kronkosky@statetecheng.com, CELL (512) 663-1954 Education Ph.D., Civil Engineering, Texas Tech University, May 2018: An Engineer's Guide for Estimating 1-Day, 100-Year

More information

City of Columbia BMP Manual. Volume Calculation Tool and Examples

City of Columbia BMP Manual. Volume Calculation Tool and Examples City of Columbia BMP Manual Volume Calculation Tool and Examples July 24, 2013 Today s Agenda 1. Welcome 2. Review City s Design Aid Tools Example Project 3. Revisit City s BMP Maintenance Agreement Procedure

More information

Stormwater Management Plan Narrative Quality Fleet Services, Inc. SITE RE-DEVELOPMENT 548 New Ludlow Road South Hadley, MA The project proposed by Quality Fleet Services, Inc. consists of the site improvements

More information

4. Contractor (and subcontractors if applicable) certification statement(s)

4. Contractor (and subcontractors if applicable) certification statement(s) CHEMUNG COUNTY STORMWATER COALITION STORMWATER POLLUTION PREVENTION PLAN (SWPPP) SUBMITTAL CHECKLIST GENERAL INFORMATION: 1. Owner/Operator name, legal address, phone number 2. Copy of signed Notice of

More information

General Technical Guidance for Treatment Measures

General Technical Guidance for Treatment Measures Chapter 5 General Technical Guidance for Treatment Measures This Chapter contains guidance on: Hydraulic sizing criteria, Applicability of non-landscape based treatment measures, Using Manufactured Treatment

More information

Keele Campus Storm Drainage. Presented by Mark Hagesteijn September 24, 2013

Keele Campus Storm Drainage. Presented by Mark Hagesteijn September 24, 2013 Keele Campus Storm Drainage Presented by Mark Hagesteijn September 24, 2013 1 Presentation Overview Urbanization Impact on the Hydrologic Cycle Why Do We Manage Stormwater? Typical Stormwater Management

More information

Drainage Analysis-Newgate/Phelps & Hatchett Hill Road Areas Rev. 0 Erosion & Sediment Control Measures

Drainage Analysis-Newgate/Phelps & Hatchett Hill Road Areas Rev. 0 Erosion & Sediment Control Measures Drainage Analysis-Newgate/Phelps & Hatchett Hill Road Areas Rev. 0 Erosion & Sediment Control Measures 4.0 EROSION & SEDIMENT CONTROL MEASURES After performing the analysis summarized above, Burns & McDonnell

More information

City of Elmhurst. Comprehensive Flood Plan. City of Elmhurst. City Council Meeting September 15, 2014

City of Elmhurst. Comprehensive Flood Plan. City of Elmhurst. City Council Meeting September 15, 2014 City of Elmhurst City of Elmhurst Comprehensive Flood Plan City Council Meeting September 15, 2014 City of Elmhurst Presentation Overview Study Background Study Methodology Analysis of Three Additional

More information

Albert R. Jarrett. Annual and Individual-Storm Green Roof Stormwater Response Models

Albert R. Jarrett. Annual and Individual-Storm Green Roof Stormwater Response Models Annual and Individual-Storm Green Roof Stormwater Response Models Albert R. Jarrett Professor of Agricultural Engineering Penn State University arj@psu.edu www.abe.psu.edu/fac/jarrett.html D. J. Beattie,

More information

CITY OF FORT LUPTON STORM DRAINAGE DESIGN AND TECHNICAL CRITERIA SECTION 10 STREETS

CITY OF FORT LUPTON STORM DRAINAGE DESIGN AND TECHNICAL CRITERIA SECTION 10 STREETS SECTION 10 STREETS CITY OF FORT LUPTON STORM DRAINAGE DESIGN AND TECHNICAL CRITERIA SECTION 10 STREETS 10.1 INTRODUCTION The criteria presented in this section shall be used in the evaluation of the allowable

More information

South Bismarck Watershed Model Update and Stormwater Improvement Project

South Bismarck Watershed Model Update and Stormwater Improvement Project Preliminary Engineering Report Bismarck Tribune South Bismarck Watershed Model Update and Stormwater Improvement Project City of Bismarck, ND January 2017 14.105.0046 1.0 Executive Summary The focus of

More information

County Council Of Howard County, Maryland

County Council Of Howard County, Maryland County Council Of Howard County, Maryland 2010 Legislative Session Legislative Day No. 4 Resolution No. 38-2010 Introduced by: The Chairperson at the request of the County Executive A RESOLUTION revising

More information

City of Troutdale South Troutdale Road Storm Drainage Plan

City of Troutdale South Troutdale Road Storm Drainage Plan City of Troutdale South Troutdale Road Storm Plan January 29 City of Troutdale SOUTH TROUTDALE ROAD STORM DRAINAGE PLAN January 29 Prepared for: City of Troutdale 342 SW 4th Street Troutdale, OR 976 Prepared

More information

Gloucester County PLAN SUBMITTER'S CHECKLIST

Gloucester County PLAN SUBMITTER'S CHECKLIST Page 1 of 9 Gloucester County PLAN SUBMITTER'S CHECKLIST FOR EROSION AND SEDIMENT CONTROL PLANS Please fill in all blanks and please reference the plan sheets/pages where the information may be found,

More information

C. WATER. 1. Surface Water Runoff. See Section C.3, Flood Hazard/Mudflow Hazard, page Ground Water

C. WATER. 1. Surface Water Runoff. See Section C.3, Flood Hazard/Mudflow Hazard, page Ground Water C. WATER 1. Surface Water Runoff See Section C.3, Flood Hazard/Mudflow Hazard, page 67. 2. Ground Water Determined not significant by the October 1984 and January 1999 Initial Studies conducted by the

More information

Post Construction BMPs

Post Construction BMPs Post Construction BMPs Why are Post Construction BMPs important? With increased development brings the increase of impervious cover Parking lots, rooftops, driveways Storm water runoff volume increases

More information

URWH at various scales

URWH at various scales URWH at various scales Training programme on Mainstreaming Sustainable Urban Water Management March 23-26, 2015 Structure of Presentation Surface runoff/ flood management practices to ensure runoff quantity

More information

1. Project Description

1. Project Description To: By: Checked By: Jimmy Vilce, E.I. (FOT istrict 1 Project Manager) Jennifer Nunn, P.E. (The Balmoral Group) Lori Stanfill, P.E. (The Balmoral Group) Memorandum ate: July 10, 2018 Subject: In May of

More information

Green Infrastructure Modeling in Cincinnati Ohio. Small Scale Green Infrastructure Design Using Computer Modeling

Green Infrastructure Modeling in Cincinnati Ohio. Small Scale Green Infrastructure Design Using Computer Modeling Green Infrastructure Modeling in Cincinnati Ohio Small Scale Green Infrastructure Design Using Computer Modeling Presenters Jason Abbott is a Design Engineer with over 17 years of experience. Jason is

More information

A. Regional Detention Requirements

A. Regional Detention Requirements I. GENERAL DESIGN GUIDELINES A. Full-spectrum detention is provided for all new development, redevelopment or expansion of a site to provide for water quality and flood control detention. B. Detention

More information

Village of Forest Park. July 27, Sewer Separation Evaluation

Village of Forest Park. July 27, Sewer Separation Evaluation Village of Forest Park July 27, 2015 Sewer Separation Evaluation Presentation Overview Study Background Historic Nature of Forest Park Drainage Scale of Flooding Problem Forest Park Sewer System Background

More information

Preliminary Sediment & Stormwater Management Plan Review Checklist DATE RECEIVED: PROJECT NUMBER: PROJECT NAME:

Preliminary Sediment & Stormwater Management Plan Review Checklist DATE RECEIVED: PROJECT NUMBER: PROJECT NAME: Preliminary Sediment & Stormwater Management Plan Review Checklist DATE RECEIVED: PROJECT NUMBER: PROJECT NAME: General Information: 1. Completed application signed by the owner, review fee, one set of

More information