Sydenham Pearl Brownfield Remediation Project
|
|
- Gordon May
- 5 years ago
- Views:
Transcription
1 Sydenham Pearl Brownfield Remediation Project 2017 Conference - Brownfields: The Next Generation June. 15, 2017 Ed Taves Project Manager CH2M HILL Joshua Schram, BA Policy Planner City of Brantford
2 Presentation Overview Site Context Historical Background Pre-remediation Environmental Assessments Remediation Phases 2 &3 Key Project Challenges Next Steps
3 City of Brantford Population: 100,000 Single-tier municipality 2 Major Brownfield Projects Underway Brownfield projects managed by: *Planning Department Technical support from other departments
4 Site Context Site is comprised of 2 properties owned by the City of Brantford The site area is approximately 2.4 ha (6 acres) Mostly surrounded by a residential neighbourhood. 22 Sydenham Street directly abuts the CN rail line on the north side.
5
6
7 Smaller companies went bankrupt vacant & underutilized infrastructure Prone to vandalism, fire, pests, squatters
8
9 Project History Major industry vacated the Site and portions of onsite infrastructures were demolished After a subsequent fires, the City acting as the agent on behalf of the Medical Officer of Health, demolished all remaining structures on site. The City proceeded with environmental investigations of the site, the demolition of above ground structures, and removal of underground storage tanks The City entertained options for purchase and sale of the property. City decided to undertake remediation and redevelopment of the site To achieve parkland/residential standards
10 Project Funding 2012 Council approved $4.6 million to complete the remediation of the Sydenham Pearl Site to the highest environmental standards to support residential/parkland uses.
11 Remediation Program 2012 Phase One (Technical Background) Phase Two Environmental Site Remediation Risk Assessment 2016 Risk Assessment-Soil Cap Requirement Site Risk Assessment Approval 2017 Record of Site Condition Finalized regulatory procedures Consideration for Redevelopment
12 Project Mobilization 2012 RFP: Phase One and Two Environmental Site Assessments CH2M HILL Retained to oversee remediation and provide contract administration Milestone Environmental Contracting was hired by the City to complete the remediation of the site, and remediation was overseen by CH2M HILL.
13 Phase Two Environmental Site Assessment (17 Sydenham)
14 Phase 2 - Remediation Program The remediation took 8 weeks to complete and included: The removal of underground storage tanks Excavation and offsite disposal of petroleum hydrocarbons in soil Insitu-soil mixing to break down volatile organic compounds in soil and groundwater
15 Phase 2 - Remediation Program
16 Lang Tool
17
18 Phase 3: Soil Cap Design and Construction Phase 3 took roughly 8-10 weeks to complete and included: Asphalt stripping, transport and disposal excavation, Crushing and reuse of concrete onsite; Berm construction (CN requirement); Installation of non-woven geotextile and soil capping over the entire site and; Hydro-seeding, tree planting, and sodding.
19 Phase 3 Photos Preparation for Concrete Crushing Stockpiling of Crushed Concrete
20 Phase 3 Photos Infiltration Gallery 22 Sydenham Street Infiltration Gallery 17 Sydenham Street
21 Phase 3 Photos Non-woven geotextile installed on 17 Sydenham Installation of geogrid on 17 Sydenham
22 Phase 3 Photos 22 Sydenham (March 2016) 22 Sydenham (Nov 2016) (City of Brantford Planning Department, 2016)
23 22 Sydenham (Sep 2016) (City of Brantford Planning Department, 2016) 22 Sydenham (Nov 2016)
24
25 Key Project Challenges Adjacent Residential Encroachments Public Communication
26 Next Steps: Public Consultation Future Uses The Public Options Consultants City of Brantford
27 Project Timelines Task Schedule Record of Site Condition Fall 2017 Staff Report to Council Fall 2017 Public Communication & Information Fall/Winter 2017
28 THANK YOU - QUESTIONS? Joshua Schram, BA Policy Planner City of Brantford JSchram@brantford.ca Ed Taves Project Manager CH2M HILL etaves@ch2m.com
Community Involvement Plan
Palm Beach County Community Involvement Plan 2401 Broadway (Northwood Anchor Site) West Palm Beach Palm Beach County Department of Economic Sustainability 2015 Table of Contents Sections 1. Overview of
More informationFLEET AVENUE GREEN STREET USES VACANT LOT FOR CSO REDUCTION. Thomas M. Evans, AECOM Cleveland, Ohio
FLEET AVENUE GREEN STREET USES VACANT LOT FOR CSO REDUCTION Thomas M. Evans, AECOM Cleveland, Ohio INTRODUCTION As part of the Northeast Ohio Regional Sewer District s (Sewer District) Green Infrastructure
More informationVaughan Metropolitan Centre (VMC) Black Creek Renewal CLASS ENVIRONMENTAL ASSESSMENT
PUBLIC INFORMATION CENTRE Vaughan Metropolitan Centre (VMC) Black Creek Renewal Wednesday, May 10, 2017 6:00 p.m. to 8:00 p.m. Add photo Project Management, Environmental Assessment, Stormwater Management
More informationPier 70 Master Plan. Port of San Francisco
Project Overview Develop a Preferred Master Plan for a 65-acre Brownfield site Adaptive reuse of historic structures and new development that reconciles numerous regulatory, economic, maritime, historic
More informationProposed Brampton Fire & Emergency Services Training Campus
F 1-1 Proposed Brampton Fire & Emergency Services Training Campus Williams Parkway / Chrysler Drive June 10, 2015 F 1-2 Outline Current Situation: Statement of Need Existing Facilities Current Land Use
More informationAPPENDIX J PERFORMANCE STANDARDS FOR GRAVEL MINE, PIT MINE, OR QUARRY
APPENDIX J PERFORMANCE STANDARDS FOR GRAVEL MINE, PIT MINE, OR QUARRY A. Purpose: 1. Regulatory Requirement and Use Mitigation: The purpose of this appendix is to provide a regulatory context (standards)
More informationPublic Storage Self-storage Facility (Warehouse)
Public Storage Self-storage Facility (Warehouse) 3545 St. Joseph Boulevard Planning Rationale PREPARED FOR: Maple Reinders Constructors Ltd. 2660 Argentia Road Mississauga, Ontario L5N 5V4 PREPARED BY:
More informationSTAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Residential Demolition Application 595 Vaughan Road Date: December 15, 2011 To: From: Wards: Reference Numbers: North York Community Council Director and Deputy Chief Building
More informationDATE: June 17, 2013 REPORT NO. PW TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ x ]
PUBLIC WORKS COMMISSION DATE: June 17, 2013 REPORT NO. PW2013-044 TO: FROM: Chair and Members Committee of the Whole Operations and Administration Geoff Rae, MBA, P.Eng. General Manager, Public Works Commission
More informationRedevelopment Plan for the Former South Gifford Road Landfill
Redevelopment Plan for the Former South Gifford Road Landfill Summary Report July 2018 Treasure Coast Regional Planing Council Former South Gifford Road Landfill Site Redevelopment Plan July 2018 prepared
More informationFrom and
GREEN INFRASTRUCTURE IN PROVIDENCE, RI The Box Office From http://web.uri.edu/riss/the-box-office/ and http://www.morrisbeacon.com/media/portfolioprojects/implementation/box-office/box%20office.pdf: At
More information1296 Kennedy Road - Zoning Amendment Application - Preliminary Report
STAFF REPORT ACTION REQUIRED 1296 Kennedy Road - Zoning Amendment Application - Preliminary Report Date: January 15, 2016 To: From: Wards: Reference Number: Scarborough Community Council Acting Director,
More informationEXHIBIT A. Tax Increment Reinvestment Zone No. 1 (Town Center) First Amended Project Plan 1
EXHIBIT A Tax Increment Reinvestment Zone No. 1 (Town Center) First Amended Project Plan 1 1 As amended by Resolution No. 2008-02-001(TR1R) of the Tax Increment Reinvestment Zone No.1, and approved to
More informationThe London 2012 Olympic Park and Green Network Legacy
2012 Central Scotland Green Network Forum How Green Networks make our Towns and Cities Livable The London 2012 Olympic Park and Green Network Legacy Neil Mattinson Senior Partner LDA Design The Story Begins.
More informationREPORT TO: Council FOR: Regular Meeting. PRESENTED: April 1, 2008 FILE: , Byl 1932 & 1936
DISTRICT OF SQUAMISH REPORT TO: Council FOR: Regular Meeting PRESENTED: April 1, 2008 FILE: 2006-08, Byl 1932 & 1936 DEPARTMENT: Planning Department SUBJECT: First and Second Readings for Bylaws 1932 (rezoning)
More informationRe: Application Type: Proposed Highlands Redevelopment Area Designation
CHRIS CHRISTIE Governor KIM GUADAGNO Lt. Governor State of New Jersey Highlands Water Protection and Planning Council 100 North Road (Route 513) Chester, New Jersey 07930-2322 (908) 879-6737 (908) 879-4205
More informationGREEN INFRASTRUCTURE DESIGNS RAIN GARDEN
GREEN INFRASTRUCTURE DESIGNS RAIN GARDEN JULY 2015 RAIN GARDEN SCALABLE TOOL AND DESIGN TEMPLATE This tool and associated design files are one section of a larger toolkit: Green Infrastructure Designs:
More informationItem No Halifax Regional Council February 7, 2017
P.O. Box 1749 Halifax, Nova Scotia B3J 3A5 Canada Item No. 14.1.3 Halifax Regional Council February 7, 2017 TO: Mayor Savage and Members of Halifax Regional Council SUBMITTED BY: Jacques Dubé, Chief Administrative
More informationPUBLIC OPEN HOUSE SEPTEMBER 8 TH, 2010 CITY OF LETHBRIDGE DEVELOPMENT SERVICES
PUBLIC OPEN HOUSE SEPTEMBER 8 TH, 2010 CITY OF LETHBRIDGE DEVELOPMENT SERVICES INTRODUCTION Why is the City creating the West Lethbridge Employment Centre Area Structure Plan? West Lethbridge Urbanization
More informationPlanning Commission March 14, Presented by: City of Bellingham Port of Bellingham
Planning Commission March 14, 2013 Presented by: City of Bellingham Port of Bellingham 1 Agenda Waterfront District Background Waterfront District Proposal Overview Sub-area Plan Development Regulations
More information30 and 44 Zorra Street - Zoning By-law Amendment Application - Preliminary Report
STAFF REPORT ACTION REQUIRED 30 and 44 Zorra Street - Zoning By-law Amendment Application - Preliminary Report Date: March 14, 2016 To: From: Wards: Reference Number: Etobicoke York Community Council Director,
More informationPennsylvania Stormwater Best Management Practices Manual. Chapter 1. Introduction and Purpose
Pennsylvania Stormwater Best Management Practices Manual Chapter 1 Introduction and Purpose Chapter 1 Introduction and Purpose 1.1 Purpose of this Manual 1 1.2 How to Use this Manual...1 1.3 Overview
More informationCITY OF VAUGHAN D R A F T YONGE STREET STUDY. June 2008 YOUNG + WRIGHT /IBI GROUP ARCHITECTS DILLON CONSULTING LTD.
CITY OF VAUGHAN June 2008 YOUNG + WRIGHT /IBI GROUP ARCHITECTS GHK SUSTAINABILITY INTERNATIONAL + LIVABILITY (CANADA) LTD. = COMMUNITY VALUE DILLON CONSULTING LTD. Public Open House Tonight s Meeting WELCOME
More informationAncient Greek and Roman planners recognized the importance of centralized gathering spaces within urban
TEAMS Competition 2014 Urban Green Space Design Introduction Ancient Greek and Roman planners recognized the importance of centralized gathering spaces within urban areas. Early Greek agora and Roman forums
More informationLANGAN QUALIFICATIONS FOR THE MORGAN COMPANIES
LANGAN QUALIFICATIONS FOR THE MORGAN COMPANIES CONTACT Arlington Virginia 1300 Wilson Boulevard Suite 450 Arlington VA 22209-2323 571.366.6800 571.366.6801 CONTACT Louise Pretzman 571.366.6826 lpretzman@langan.com
More informationLand Use Amendment in Southwood (Ward 11) at and Elbow Drive SW, LOC
2018 November 15 Page 1 of 10 EXECUTIVE SUMMARY This land use amendment application was submitted by Rick Balbi Architect on 2017 August 31 on behalf of Sable Developments Ltd, and with authorization from
More information5 TOWN OF MARKHAM OFFICIAL PLAN AMENDMENT NO. 144 MILLIKEN MAIN STREET SECONDARY PLAN
5 TOWN OF MARKHAM OFFICIAL PLAN AMENDMENT NO. 144 MILLIKEN MAIN STREET SECONDARY PLAN The Planning and Economic Development Committee recommends the following: 1. The communication from Brendan O Callaghan,
More informationTransforming Ebbw Vale from steelworks to green space
Case Study: Brownfield Transforming Ebbw Vale from steelworks to green space The Ebbw Vale regeneration scheme in Gwent, South Wales, is one of the largest and most complex of its type in the UK Transforming
More informationFrom: Director, Community Planning, Scarborough District. Ward 40 Scarborough-Agincourt
STAFF REPORT ACTION REQUIRED 2967 Sheppard Ave E - Zoning Amendment Application - Preliminary Report Date: July 18, 2014 To: Scarborough Community Council From: Director, Community Planning, Scarborough
More informationInternational Blvd. TOD Plan Public Workshop #1
International Blvd. TOD Plan Public Workshop #1 Add photos or project images September 21 and 22, 2010 Workshop Purpose Introduce the public to the Project Review and discuss the existing conditions analysis
More informationGeneral Information. Site Conditions. 9b 9b. 9a 1b. Best Management Practices Illustration
Model Construction SWPPP Planning & Development Services 1800 Continental Place Mount Vernon WA 98273 voice 360-416-1320 inspections 360-416-1330 www.skagitcounty.net/stormwaterpermitting Permit #: General
More informationCenter for Towns Program. Strategic Planning Retreat December 2014
Center for Towns Program Strategic Planning Retreat December 2014 Background Center for Towns ESLC Vision in 2050 is an Eastern Shore where: towns are vibrant and well defined 2010 2015 Strategic Plan
More informationRequest for Decision. Recommendation. Presented: Monday, Jul 07, Report Date Friday, Jun 20, Type: Public Hearings
Presented To: Planning Committee Request for Decision Application for rezoning in order to permit a place of worship on a vacant lot zoned for C1, Local Commercial uses, Cam Street, Sudbury Sitiri Investments
More informationMW-401B Area Soil Remediation Report
MW-401B Area Soil Remediation Report Maine Yankee Decommissioning Project Corrective Measures Study December 2004 Prepared for: Maine Yankee 321 Old Ferry Road, Bailey Point Wiscasset, ME 04578 Prepared
More informationResidential Stormwater Credit Application
Residential Stormwater Credit Application This residential Stormwater Credit Application package includes: Background information about the Stormwater Credit Program Information to help residential property
More information10 Principles for a Sustainable Development of Urban Waterfront Areas
10 Principles for a Sustainable Development of Urban Waterfront Areas In the context of the initiatives for the Global Conference on the Urban Future (URBAN 21) held in Berlin in July 2000 and in the course
More information280 Manse Road - Official Plan Amendment, Zoning Amendment, Draft Plan of Subdivision Applications - Preliminary Report
STAFF REPORT ACTION REQUIRED 280 Manse Road - Official Plan Amendment, Zoning Amendment, Draft Plan of Subdivision Applications - Preliminary Report Date: March 11, 2014 To: From: Wards: Reference Number:
More informationStructural Stormwater Best Management Practices
Structural Stormwater Best Management Practices for Small Commercial and Residential Applications Timothy Bruno Watershed Manager PA Department of Environmental Protection What are STRUCTURAL BMPs? Physical
More informationPosted by Calgary Public Library on November 1, 2012
Call to Artists for Signal Hill Library Public Art Project Posted by Calgary Public Library on November 1, 2012 Eligibility This project is open to local and regional artists. Emerging and established
More informationOUR JOBS Innisfil Heights Strategic Settlement Employment Area Planning Policy Update. Council Workshop April 22, 2015
Innisfil Heights Strategic Settlement Employment Area Planning Policy Update Council Workshop April 22, 2015 Study Objectives Support the Economy pillar of Inspiring Innisfil 2020 Strategically position
More informationChair and Members of the Planning, Public Works and Transportation Committee. Tara Buonpensiero, Senior Planner Policy, MCIP, RPP
REPORT TO: REPORT FROM: Chair and Members of the Planning, Public Works and Transportation Committee Tara Buonpensiero, Senior Planner Policy, MCIP, RPP DATE: April 9, 2018 REPORT NO.: RE: PLS-2018-0027
More information141 GEORGE STREET PLANNING RATIONALE
141 GEORGE STREET PLANNING RATIONALE MINOR ZONING BY-LAW AMENDMENT NOVEMBER 2, 2016 PLANNING RATIONALE 223 McLeod Street Ottawa, ON K2P 0Z8 613.730.5709 fotenn.com INTRODUCTION FOTENN Consultants is acting
More informationProject Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM
Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM I. PROJECT DATA Project Name Bay Meadows Development Phase II Project Address 2600
More informationWEST OAKLAND SPECIFIC PLAN & DRAFT ENVIRONMENTAL IMPACT REPORT
WEST OAKLAND SPECIFIC PLAN & DRAFT ENVIRONMENTAL IMPACT REPORT Landmarks Preservation Advisory Board Public Hearing February 10, 2014 1 Specific Plan Overview Plan Area is generally bounded by I-580 to
More informationONTARIO MUNICIPAL BOARD
PL 120483 ONTARIO MUNICIPAL BOARD Applicant/Appellant: 2124123 Ontario Limited Subject: OPA, Rezoning and Draft Plan of Subdivision Municipal Address: 3940 Highway 7 East Municipality: City of Markham
More informationCity of Toronto. Emery Village Transportation Master Plan
City of Toronto Emery Village Transportation Master Plan May 2009 Emery Village Transportation Master Plan Toronto, ON May 2009 Consulting Inc. 100 York Blvd., Suite 300 Richmond Hill, ON L4B 1J8 Tel:
More informationQUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project
QUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project PROJECT OVERVIEW Windsor Woods, Princess Anne Plaza and The Lakes are neighborhoods located in what was once
More informationSplendor Test Tour TEST TOUR SPLENDOR - 08/02/17
TEST TOUR SPLENDOR - 08/02/17 Dear client We are pleased to write this description for you. We are testing line breaks in this paragraph. These lines should all be breaking by themselves with no need to
More information1. Introduction
Table of Contents 1. Introduction... 1-1 1.1 Project Background... 1-1 1.2 Project Goals and Objectives... 1-3 1.3 Proponent... 1-5 1.4 The Ontario EA Act... 1-6 1.4.1 Co-ordinated EA Process... 1-9 1.4.2
More informationJ. Paul Guyer, P.E., R.A.
J. Paul Guyer, P.E., R.A. Paul Guyer is a registered civil engineer, mechanical engineer, fire protection engineer, and architect with over 35 years experience in the design of buildings and related infrastructure.
More informationBCRC-SEA s PROJECT: DEVELOPMENT OF REGIONAL TECHNICAL GUIDELINES FOR E-WASTE INVENTORY AND ESM 5R OF E-WASTE
BCRC-SEA s PROJECT: DEVELOPMENT OF REGIONAL TECHNICAL GUIDELINES FOR E-WASTE INVENTORY AND ESM 5R OF E-WASTE Aboejoewono Aboeprajitno Director of BCRC-SEA BASEL CONVENTION REGIONAL CENTRE for South-East
More informationCumberland Region Tomorrow is a private, non-profit, citizen based regional organization working with Greater Nashville Regional Council
Cumberland Region Tomorrow is a private, non-profit, citizen based regional organization working with Greater Nashville Regional Council and others in the public and private sectors, dedicated to planning
More informationPasco County Watershed Meeting for Flood Impacted Areas Port Richey Watershed
Pasco County Watershed Meeting for Flood Impacted Areas March 15, 2017 Regency Park Library, 9701 Little Road, New Port Richey, Pasco County The following is a summary of the meeting held on March 15,
More informationCity of Richland Stormwater Management Plan
City of Richland Stormwater Management Plan City of Richland Public Works Department 840 Northgate Drive Richland, WA 99352 2015 Nancy Aldrich Special Projects Coordinator City of Richland Public Works
More informationCOMMERCIAL CORRIDOR PLANNING SW 9 TH STREET CORRIDOR NE CORRIDOR MARKET DISTRICT KEO WAY CORRIDOR
COMMERCIAL CORRIDOR PLANNING SW 9 TH STREET CORRIDOR NE CORRIDOR MARKET DISTRICT KEO WAY CORRIDOR Council Workshop July 29, 2013 SW 9 th Street Corridor Plan What is this initiative? A PUBLIC-PRIVATE pilot-partnership
More informationRetrofit of the Gwinnett County DWR Facility Using Low Impact Development Practices SESWA 2012 Annual Conference October 19, 2012
Retrofit of the Gwinnett County DWR Facility Using Low Impact Development Practices SESWA 2012 Annual Conference October 19, 2012 Jeff Herr, P.E., D.WRE National Stormwater Leader jherr@brwncald.com Acknowledgements
More information4. UTILITIES ELEMENT.
4. UTILITIES ELEMENT. The purpose of this element is to provide for necessary public facilities and services correlated to future land use projections and population demand. Utilities Sub-Elements (A)
More informationWelcome! Agenda. South Downtown
Welcome! Agenda 4:00 Open House 5:00 Presentation Welcome Subarea Plan Overview Existing Studies Next steps: Scoping 6:00 Questions and Answers 6:30 Open House continues Project background and purpose
More informationThe Benefits and Challenges Associated with Green Infrastructure Practices
The Benefits and Challenges Associated with Green Infrastructure Practices Thomas M. Evans ASLA, LEED AP Regional Green Infrastructure Design Services Director OWEA Technical Conference, June 20, 2013
More information599 Kennedy Road - Official Plan Amendment and Zoning Amendment Application - Preliminary Report
STAFF REPORT ACTION REQUIRED 599 Kennedy Road - Official Plan Amendment and Zoning Amendment Application - Preliminary Report Date: March 7, 2017 To: From: Wards: Reference Number: Scarborough Community
More informationPROJECT SPOTLIGHT TOUR: LANGAN LEADER JUNE 2017
PROJECT SPOTLIGHT TOUR: LANGAN LEADER JUNE 2017 Learn more about Langan's involvement in our featured projects: Via Lofts - Hoboken NJ Eastline (2100 Telegraph) Mixed-Use - Oakland CA Hyde Beach Residence
More informationhere today Public exhibition
Public exhibition here today Find out more about Central England Co-operative and Hawkstone Vale Developments Ltd s redevelopment proposal to bring new retail and community facilities to Wilnecote. The
More informationDAVENPORT VILLAGE SECONDARY PLAN
27 DAVENPORT VILLAGE SECONDARY PLAN 27. DAVENPORT VILLAGE SECONDARY PLAN 1. VISION FOR THE DAVENPORT VILLAGE SECONDARY PLAN Davenport Village, municipally known as 830, 940, 980 and 1100 Lansdowne Avenue,
More information1071 King Street West Zoning Amendment Application - Preliminary Report
STAFF REPORT ACTION REQUIRED 1071 King Street West Zoning Amendment Application - Preliminary Report Date: August 9, 2012 To: From: Wards: Reference Number: Toronto and East York Community Council Director,
More informationSECTION ONE: INTRODUCTION. introduction
introduction 1 INTRODUCTION Since it was first established in 1843 as a trading post for the Hudson s Bay Company, Victoria has evolved into a Provincial capital city that is recognized across Canada and
More informationInspection and Maintenance of Stormwater Best Management Practices
FAC T S H E E T Inspection and Maintenance of Stormwater Best Management Practices is a general term that refers to vegetated stormwater best management practices (BMPs) that temporarily store rainwater
More informationCase Studies of Master Planning for Sustainable Urban Underground Space Utilization
Case Studies of Master Planning for Sustainable Urban Underground Space Utilization Zhu Wenjun 1, Wang Hui 1, Li Chuanbin 2, Wei Lijun 3 1 Department of Civil Engineering, Tsinghua University, Beijing,
More informationChristopher J. Webb, PE. Chris Webb & Associates, Inc., PS, Bellingham, WA
Christopher J. Webb, PE Chris Webb & Associates, Inc., PS, Bellingham, WA www.chriswebbpe.com THE CHARETTE April 22, 2008 (Earth Day) THE CHARETTE Goals Consider innovative approaches and evaluate application
More informationGreen Infrastructure on Brownfields
Green Infrastructure on Brownfields Tysen O. Miller, PE, LEED AP, CPESC KU Resources, Inc. tmiller@kuresources.com Jim Pillsbury, MS, PE Westmoreland Conservation District jim@wcdpa.org October 3, 2018
More informationRequest for Proposal
Request for Proposal 10 th Street Corridor Master Plan Department of Planning and Zoning 500 Quartermaster Court Suite 200 Jeffersonville, IN 47130 April 18, 2017 For further information contact: Chad
More informationTaking Action on Fire and Life Safety
AU13.11 Taking Action on Fire and Life Safety Facilities Management July 13, 2018 Taking Action on Fire & Life Safety We accept the Auditor General's recommendations and are acting quickly to address issues
More informationGAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT
GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT FIRE FOR LIBRARY HOTEL OCTOBER 2014 Report for Department of Infrastructure Development Fire Services Preliminary Report: Library
More informationJohn M. Fleming Managing Director, Planning and City Planner. Old East Village Dundas Street Corridor Secondary Plan Draft Terms of Reference
Report to Planning and Environment Committee To: From: Subject: Chair and Members Planning & Environment Committee John M. Fleming Managing Director, Planning and City Planner Old East Village Dundas Street
More informationTown of Yucca Valley Capital Improvement Projects Report July 24, 2014
Town of Yucca Valley Capital Improvement Projects Report July 24, 2014 SR 62 Traffic and Pedestrian Improvements from Apache Trail to Palm Avenue (PLHD) The project includes construction of curbs, gutters,
More informationCOMMUNITY OPEN HOUSE. March 28, 2012
COMMUNITY OPEN HOUSE March 28, 2012 THE CASE FOR URBAN INVESTMENT One of the best things that cities can do to create jobs especially in the private sector is to improve the quality of life of their inhabitants.
More information1.0 Purpose of a Secondary Plan for the Masonville Transit Village
Report to Planning and Environment Committee To: Chair and Members Planning & Environment Committee From: John M. Fleming Managing Director, Planning and City Planner Subject: Masonville Transit Village
More informationMOUNTAIN VIEW ELEMENTARY SCHOOL SITE REDEVELOPMENT OPEN HOUSE. MacPherson Room, 10 am 5 pm
MOUNTAIN VIEW ELEMENTARY SCHOOL SITE REDEVELOPMENT OPEN HOUSE MacPherson Room, 10 am 5 pm MOUNTAIN VIEW SCHOOL SITE REDEVELOPMENT 1 WELCOME TO THE OPEN HOUSE FOR THE MOUNTAIN VIEW SCHOOL SITE WHY WE ARE
More informationNOTICE OF PREPARATION OF A DRAFT ENVIRONMENTAL IMPACT REPORT
NOTICE OF PREPARATION OF A DRAFT ENVIRONMENTAL IMPACT REPORT TO: SUBJECT: Interested Parties Notice of Preparation of a Draft Environmental Impact Report for the Marywood Residential Development project.
More informationJuan C. Feliciano Marvel Marchand Architects. Gowanus Green Master Plan: Reclaiming a Brownfield Site for NYC May 10 th, 2017
Juan C. Feliciano Marvel Marchand Architects Gowanus Green Master Plan: Reclaiming a Brownfield Site for NYC May 10 th, 2017 Aerial view. Source: Google Maps Historical Facts The Gowanus Canal is a 100-foot-wide,
More informationResidential Stormwater Credit Application
Residential Stormwater Credit Application Who can apply? Residential and non-residential property owners can apply for stormwater credits. Residential: Use the residential application if you own the following
More informationPavement Removal Fact Sheet
Rushern L. Baker, III County Executive Pavement Removal Fact Sheet What is pavement removal? Pavement removal is the replacement of impervious surfaces, such as asphalt and concrete, with grass or native
More informationThe Hartford Line Transit-Oriented Development (TOD) Action Plan. Maxwell L. Sokol, AICP WSP USA, Lead Planner New York, NY
The Hartford Line Transit-Oriented Development (TOD) Action Plan Maxwell L. Sokol, AICP WSP USA, Lead Planner New York, NY Key Presentation Take-Aways Deliberately build upon prior efforts at the local,
More informationLocal Growth Planning in North Central Green Line Communities
2018 April 30 Page 1 of 6 EXECUTIVE SUMMARY This report outlines a high-level scope for local growth planning for north central Green Line communities. The catalyst for this review is the significant investments
More informationAire Valley Leeds Area Action Plan - Marsh Lane Allocation (AV18)
City Development Policy and Plans Group The Leonardo Building 2 Rossington Street LDS LS2 HD 3 th January 207 Our ref: TP/LN/207-006 Network Rail Floor 3A/55 George Stephenson House Toft Green York YO
More informationLEED-ND 101: Practical Strategies for Achieving Sustainability Goals. Travis Parker Lakewood Planning Director
LEED-ND 101: Practical Strategies for Achieving Sustainability Goals Travis Parker Lakewood Planning Director Metro Vision Idea Exchange Oct 11, 2012 West Corridor Stations West Corridor Overview West
More informationAWR Engineering, LLC
AWR Engineering, LLC Alaska Water Resources Memorandum To: Kirsti Bischofberger, Watershed Manager, Municipality of Anchorage From: Janie Dusel, PE Date: February 3, 2017 Re: 2016 Low Impact Development/Green
More informationStrategic Environmental Assessment Screening Report. Dublin Port Masterplan Review 2017
Strategic Environmental Assessment Screening Report Dublin Port Masterplan Review 2017 Table of Contents 1 Introduction... 1 2 Purpose of the Masterplan... 2 3 Task 1.1 Pre-Screening Check... 5 4 Task
More informationStreets for People, Place-Making and Prosperity. #TOcompletestreets
COMPLETE STREETS FOR TORONTO Streets for People, Place-Making and Prosperity COMPLETE STREETS: A NEW APPROACH A Complete Streets design approach considers the needs of all users people who walk, bicycle,
More informationWelcome to the. Open House
Welcome to the 5th Street to Kinsman Road Open House November 14 5:30 7:00 p.m. Please sign in Project Overview In December 2016, City Council adopted SW 5th Street as the preferred alignment to connect
More informationRain Gardens Water Quality the Way Mother Nature Intended
Rain Gardens Water Quality the Way Mother Nature Intended Maintenance Discussion Design Discussion Susan Morgan, Ph.D, PE Southern Illinois University Edwardsville smorgan@siue.edu (618) 650 5014 Michael
More informationSewing the Seeds for a
Sewing the Seeds for a Green Development Strategy Quote from -Thomas Mueller; President of the Canadian Green Building Council Buildings account for as much as 48% of energy consumption & greenhouse gas
More informationAtlanta BeltLine, Inc. Pathways to Urban Sustainability
Atlanta BeltLine, Inc. Pathways to Urban Sustainability September 30, 2010 WHAT IS THE ATLANTA BELTLINE? Transit 22-mile loop Parks 1300 + new acres Trails 33 miles Jobs & Economic Development 20 areas,
More informationAppendix F. Wisconsin. Department of Natural Resources. Contaminated Site Listings. Village. Park Ridge
Appendix F Wisconsin Department of Natural Resources Contaminated Site Listings Village of Park Ridge WI DNR Activities at Discharge Sites BRRTS data comes from many sources inside and outside of DNR.
More informationORDINANCE NO. WHEREAS, the Comprehensive Plan directs that master plans be developed for each proposed urban village (FLU-18), and
ATTACHEMENT 1 ORDINANCE NO. AN ORDINANCE RELATED TO LAND USE PLANNING AND ZONING ESTABLISHING THE FOUNTAIN DISTRICT URBAN VILLAGE SUBAREA PLAN, AMENDING PORTIONS OF LAND USE AREAS 3 AND 8, AND ALL OF AREAS
More information5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS
5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS Low Impact Development (LID) requires a shift in stormwater management away from conveying runoff to a small number of downstream points through hydraulically
More informationPlanning & Zoning Commission Planning & Development Department February 17, 2014
Request Applicant Owner Zoning Location Attachments Subdivision of 2.79 acres of currently vacant property to create 27 town home lots and 6 restricted reserves for the use of HOA Parks. John English;
More informationChapter 10 The Urban World
Chapter 10 The Urban World Overview of Chapter 10 Population and Urbanization Characteristics of Urban Population Urbanization Trends City as an Ecosystem Environmental Problems in Urban Areas Environmental
More informationSwatara Township Stormwater Program. 1. There are no storm sewers on or near my property. Why should I pay a fee?
1. There are no storm sewers on or near my property. Why should I pay a fee? All properties produce stormwater runoff that must be managed by the Township. Even if your property has never flooded and there
More informationNorth Fair Oaks Community Plan Summary and Information
North Fair Oaks Community Plan Summary and Information WHAT IS THE NORTH FAIR OAKS COMMUNITY PLAN? The North Fair Oaks Community Plan is part of the San Mateo County General Plan, and establishes policies
More information2
1 2 3 4 5 6 7 The goal of modern stormwater management techniques is to increase infiltration, or the amount of water that soaks into the ground. In natural areas like you see on the left, about half of
More information