Guiding Landowners in Stream Restoration. The Science, Practice & Art of Restoring Native Ecosystems 2015

Size: px
Start display at page:

Download "Guiding Landowners in Stream Restoration. The Science, Practice & Art of Restoring Native Ecosystems 2015"

Transcription

1 Guiding Landowners in Stream Restoration The Science, Practice & Art of Restoring Native Ecosystems 2015 January 24, 2015

2 Guiding Landowners in Stream Restoration January 24, 2015

3 Agenda 1Watershed Planning 2Assessment 3Project Planning 4Applications

4 Stream Restoration Master Plans

5 Stream Restoration Master Planning Geomorphic assessment (departure analysis) Stream potential (valley type, geology, soils, land use, materials, constraints) Planform Diverse bedform topography Floodplain connectivity wet landscape

6

7 Assessing Stream Functions Parameter Simple Measure Intensive Measure Floodplain connectivity Bank Height Ratio Entrenchment Ratio Stage vs. discharge Bedform diversity % Riffles and pools Max. pool depth Variable depth, velocity, Froude number Lateral stability Streambank erosion Replicate cross-sections Riparian vegetation Buffer density, width Vegetation plots Adapted from Harman, et al. 2012

8 River Instability Processes Over-widening Accelerated downstream meander migration Chute cutoffs Aggradation (excessive deposition) Degradation (downcutting or incision)

9 Signs of Aggradation Pool filling Most of bed exposed during low flow Slope reversals Coarse over-bank deposition Transverse bars; mid-channel bars; side bars

10 Interpreting Depositional Features B1, B2 Stable B4, B8 Mod. Unstable B3 Unstable B5, B6, B7 Highly Unstable

11 Signs of Degradation Exposed till bed Nickpoints caused by headcutting Stream tributary rejuvenation Steep bars Leaning trees, vertical banks

12 Geomorphic Thresholds Bank height exceeds1.3 x bankfull depth Width-to-Depth Ratio exceeds 1.4 x reference W:d Shift in stream type >25% of banks or vegetation impacted >20% change in bankfull discharge >30% riffle embeddedness >20% pool filling with fine sediment

13 Detrimental riparian actions Pesticides, herbicides, salt Rock dams Yard waste disposal on top of banks Altered riparian vegetation especially mowed turf Broken concrete, riprap Wood removal Water gardening

14 When do you need assistance? Bank heights exceed 3-6 ft 6 ft banks = geotechnical concerns Replacing culverts or other structures Erosion threatens infrastructure Permitting assistance Channel instability Needs more than a change in management practices

15 Riparian Landowner DIY Vegetation Management Reducing the Width-to-Depth Ratio (with appropriate permits) Soil Bioengineering

16 Phasing by Focus Area Infiltration, tile control structures Water on the landscape Longitudinal connectivity: culvert replacement, weirs Sediment regime: gravel augmentation, excessive fines Cattle or human access points Floodplain excavation Tree planting Instream habitat: wood

17 Cost Reduction Avoid importing rock Use on-site materials: wood, gravel, topsoil Design and install appropriate erosion control products Design/Build? Construction bid as time and materials? Finish with volunteers (plants, blankets)

18 Actions Requiring Heavy Equipment Floodplain or riparian wetland restoration Toe wood construction Native vegetation transplants: shrub or sod Infiltration practices

19 Project Implementation Time scale Consequences of Do Nothing Fiscal or physical site constraints

20 Level of action required 1. Protection and conservation 2. Riparian management 3. Induced meandering or other adaptive management approach 4. Active restoration (or combined approach)

21 Self-Forming Channel Dam removal Master Plan Cost savings Grant eligible

22 Multi-phased restoration plan Cost savings Leverage infrastructure expenses Maintenance to a restoration approach Various restoration approaches - stream types vary by site constraints

23

24 Induced Meandering

25

26 Oxbow Re-Connection

27 Paint Creek Toe Wood Structure Log Vanes

28 Paint Creek Gravel Inner Berm Toe Wood Fabric-encapsulated Lift

29

30 Paint Creek Children s Park Concept Plan

31 Paint Creek Meeks Park Concept Plan

32 Paint Creek Master Plan White topping asphalt to reduce thermal impacts Bioretention and detention basin retrofits Catchbasin and outfall retrofits Sidewalk removal/raised boardwalk and floodplain connectivity Replace bridge to allow floodplain connectivity Manage and restore riparian vegetation to maintain views, angler access, shade, stability Channel re-meandering to maintain pools, toe wood, gravel augmentation, riffle/glide/pool construction

33

34 Typical Channelized Stream

35 Floodplain Connectivity Restored

36

37 Multi-Stage Channel Design Technical guidelines for open drain design in Macomb County Funded by MI Sea Grant Partnering with WSU Website:

38 Riparian Vegetation Management 0% Canopy 100% Canopy No canopy Cattails/phragmites Siltation, flooding Fully shaded Invasive shrubs Bare banks underneath The Goal 50-75% Canopy

39 Riparian Improvement Cut Clearing and thinning Cut and treat invasives Reuse materials (mulch, LWM) Establish plantings with vertical diversity o Seed bare areas (native grasses) o Soil bioengineering (native shrubs) oshade trees above top of bank Perennial crop vegetated buffers?

40 Questions?

Stream Restoration: Working with Nature?

Stream Restoration: Working with Nature? Stream Restoration: Working with Nature? Greg Jennings, PhD, PE jenningsenv@gmail.com Ecosystem Restoration activities that initiate or accelerate the recovery of ecosystem health, integrity, and sustainability

More information

Stream Restoration: Working with Nature? Greg Jennings, PhD, PE

Stream Restoration: Working with Nature? Greg Jennings, PhD, PE Stream Restoration: Working with Nature? Greg Jennings, PhD, PE jenningsenv@gmail.com Ecosystem Restoration activities that initiate or accelerate the recovery of ecosystem health, integrity, and sustainability

More information

Department of Agriculture. Conservation Service. United States. Natural Resources REVISED 8/26/16

Department of Agriculture. Conservation Service. United States. Natural Resources REVISED 8/26/16 GENERAL NOTES: SYMBOL LEGEND 1. All work shall comply with the constriction specifications, drawings, project-specific quality assurance plan and other contract requirements. 2. All notes on the drawings

More information

Presentation to Parks and Open Space Advisory. Committee September 22, 2016

Presentation to Parks and Open Space Advisory. Committee September 22, 2016 Flood Planning & Preliminary Design Services for South St. Vrain Creek Restoration at Hall Ranch Presentation to Parks and Open Space Advisory Prepared for: Boulder County, Colorado Committee September

More information

STREAM BANK STABILIZATION THORPS MORTIMER RECREATION AREA Grandfather Ranger District SITE LOCATION & DRAINAGE AREA

STREAM BANK STABILIZATION THORPS MORTIMER RECREATION AREA Grandfather Ranger District SITE LOCATION & DRAINAGE AREA STREAM BANK STABILIZATION THORPS CREEK @ MORTIMER RECREATION AREA SITE LOCATION & DRAINAGE AREA SITE LOCATION Drainage Area = 1.14 sq. miles STREAM BANK STABILIZATION THORPS CREEK @ MORTIMER RECREATION

More information

North Branch of Cypress Creek Ecological Restoration: A Comprehensive Approach to Stream Restoration

North Branch of Cypress Creek Ecological Restoration: A Comprehensive Approach to Stream Restoration North Branch of Cypress Creek Ecological Restoration: A Comprehensive Approach to Stream Restoration Rocky Powell Clear Creeks Consulting, LLC Keith D. Tate, P.E. BayLand Consultants & Designers, Inc.

More information

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT NOT WELL 800 - Urban Stormwater Wetlands A constructed system of shallow pools that create growing conditions for wetland plants to lessen the impacts of stormwater quality and quantity in urban areas.

More information

The use of low head weirs to. perennial streams with their floodplains:

The use of low head weirs to. perennial streams with their floodplains: The use of low head weirs to reconnect severely entrenched perennial streams with their floodplains: An Anne Arundel County TMDL Watershed Implementation Plan Strategy presented by Hala Flores, P.E Mid

More information

Guidelines for Streambank Protection

Guidelines for Streambank Protection PDHonline Course C187 (3 PDH) Guidelines for Streambank Protection Instructor: John Poullain, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org

More information

URBANIZED STREAM CORRIDOR: COMMUNITY APPROACH TO ADDRESS EROSION

URBANIZED STREAM CORRIDOR: COMMUNITY APPROACH TO ADDRESS EROSION URBANIZED STREAM CORRIDOR: COMMUNITY APPROACH TO ADDRESS EROSION Stephen Crawford, P.E., CFM Romin Khavari, P.E., CFM NCTCOG Public Works Roundup MAY 23, 2018 Today s Agenda Urbanized Stream Erosion Solving

More information

PERMANENT SEEDING. Overview of Sedimentation and Erosion Control Practices. Practice no. 6.11

PERMANENT SEEDING. Overview of Sedimentation and Erosion Control Practices. Practice no. 6.11 Overview of Sedimentation and Erosion Control Practices Practice no. 6.11 PERMANENT SEEDING Permanent vegetation controls erosion by physically protecting a bare soil surface from raindrop impact, flowing

More information

Banking on Natural Fibers Products made from coir and jute play a key role in stabilizing a restored stream for a commercial stream mitigation bank.

Banking on Natural Fibers Products made from coir and jute play a key role in stabilizing a restored stream for a commercial stream mitigation bank. Banking on Natural Fibers Products made from coir and jute play a key role in stabilizing a restored stream for a commercial stream mitigation bank. By Greg Northcutt When White Creek Mitigation, LLC,

More information

5.0 Storm Water Landscape Guidance Introduction

5.0 Storm Water Landscape Guidance Introduction 5.0 Storm Water Landscape Guidance Introduction Landscaping is a critical element to improve both the function and appearance of storm water management practices. Integrated storm water landscapes can

More information

SECTION 5: REACH RECOMMENDATIONS/MAPS

SECTION 5: REACH RECOMMENDATIONS/MAPS SECTION 5: REACH RECOMMENDATIONS/MAPS This section describes areas of concern and provides specific recommendations for each project reach. Locations of stormwater drains were from GIS coverage supplied

More information

4.6. Low Impact and Retentive Grading

4.6. Low Impact and Retentive Grading 4.6. Low Impact and Retentive Grading Low Impact Grading techniques focus on utilizing existing topography during Site layout to minimize cost. Proposing structures, roads, and other impervious surfaces

More information

SECTION 6. Routine Maintenance Activity Details

SECTION 6. Routine Maintenance Activity Details SECTION 6 Routine Maintenance Activity Details 80. DEBRIS REMOVAL When Deadfall, and other objects, such as shopping carts, tires, appliances, and mattresses have accumulated in the drain. Why To prevent

More information

Use of Best Management Practices

Use of Best Management Practices Use of Best Management Practices Presented at the ANJEC Flood Hazard Workshop Bordentown, NJ March 13, 2008 Stormwater BMPs "a technique, measure or structural control that is used for a given set of conditions

More information

Jill Stachura STORMWATER BMP AND STREAM RESTORATION IN A CITY PARK. October 2013 Southeast Stormwater Association Annual Conference, Charlotte, NC

Jill Stachura STORMWATER BMP AND STREAM RESTORATION IN A CITY PARK. October 2013 Southeast Stormwater Association Annual Conference, Charlotte, NC Jill Stachura STORMWATER BMP AND STREAM RESTORATION IN A CITY PARK October 2013 Southeast Stormwater Association Annual Conference, Charlotte, NC Project Location Gwinnett County, GA: Population: 825,000

More information

Town of Essex Small Site Erosion Control Guide

Town of Essex Small Site Erosion Control Guide Town of Essex Small Site Erosion Control Guide Why do we need to protect against erosion? Water Quality: Erosion and the transport of sediment and pollutants impacts the water quality of nearby streams

More information

Lilburn, GA STORMWATER BMP AND STREAM RESTORATION IN A CITY PARK. July 2013 Jill Stachura

Lilburn, GA STORMWATER BMP AND STREAM RESTORATION IN A CITY PARK. July 2013 Jill Stachura Lilburn, GA STORMWATER BMP AND STREAM RESTORATION IN A CITY PARK July 2013 Jill Stachura Project Location Gwinnett County, GA: Population: 825,000 Area: 437 sq. miles 1,300 miles storm drainage system

More information

STREAM ALTERATION PRACTICES

STREAM ALTERATION PRACTICES STREAM ALTERATION PRACTICES Stream Diversion Channel SDC DEFINITION A temporary channel constructed to convey stream flow around in-stream construction. PURPOSE Stream diversion channels are used to allow

More information

Lake and Stream Restoration Project

Lake and Stream Restoration Project Pre-project Fact Sheet May 2012 Toledo Botanical Garden (TBG) is a 60 acre public garden visited by more than 120,000 people annually. It is located in Toledo, Ohio in the Ottawa River watershed within

More information

How to Update a Storm Water Management Program (SWMP) to Incorporate Total Maximum Daily Load (TMDL) BMPs

How to Update a Storm Water Management Program (SWMP) to Incorporate Total Maximum Daily Load (TMDL) BMPs How to Update a Storm Water Management Program (SWMP) to Incorporate Total Maximum Daily Load (TMDL) BMPs Janine Rybka Cuyahoga Soil & Water Conservation District About Habitat Habitats are the places

More information

Construction Progress Report

Construction Progress Report Report Date: 4/8/2017 Subject: Construction Week 2 70% Complete Project: Sunset Pond EWP Stream Reclamation, Fourmile Creek, Boulder County, CO Report By: TJ Burr, Civil Engineer/Stream Restoration Specialist,

More information

Is a Riparian Restoration Still Viable After 100-year Storm Events Alter the Original Design?

Is a Riparian Restoration Still Viable After 100-year Storm Events Alter the Original Design? Is a Riparian Restoration Still Viable After 100-year Storm Events Alter the Original Design? Sarah Spear Cooke, Ph.D. Seattle, Washington Presentation Outline Introduction The site pre-restoration Restoration

More information

Tentatively Selected Plan within Harlem River, East River and Western Long Island Sound Planning Region. First Level Costs. Federal Non-Federal Total

Tentatively Selected Plan within Harlem River, East River and Western Long Island Sound Planning Region. First Level Costs. Federal Non-Federal Total HARLEM RIVER, EAST RIVER AND WESTERN LONG ISLAND SOUND PLANNING REGION Flushing Bay and Creek Ecosystem Restoration Source Feasibility Study Background Study Resolution (1994), Reconnaissance Report (1996),

More information

Working Group Meeting

Working Group Meeting April 4,, 2017 Parks Operations Bldg Working Group Meeting Arts Districts Overview Stormwater/RPA/Stream Considerations First Principles Agenda 7:00pm 7:05pm 7:10pm 7:40pm 8:30pm 9:40pm 9:45pm Welcome

More information

RECONNECTING A COMMUNITY TO THE CREEK

RECONNECTING A COMMUNITY TO THE CREEK RECONNECTING A COMMUNITY TO THE CREEK 0 The J.J. Seabrook Stream Restoration, Rain Garden, and Urban Trail Project Kristin K. Pipkin, P.E. Michelle Adlong, EI.T. TXSER/TRA Joint Conference November 2,

More information

Rain Gardens. A Welcome Addition to Your Landscape

Rain Gardens. A Welcome Addition to Your Landscape Rain Gardens A Welcome Addition to Your Landscape Where Does The Rainwater Go? Naturally, forests provide a way for rainwater to percolate into the soil, filtering pollutants while trees are allowed to

More information

Single most pervasive problem: Polluted runoff from watershed development

Single most pervasive problem: Polluted runoff from watershed development What are Some Potential Threats to Maine s Lakes Acid rain Mercury contamination Aquatic Invaders: The Milfoil threat Loss of critical habitat Global climate change Single most pervasive problem: Polluted

More information

Homeowners Guide to Stormwater BMP Maintenance

Homeowners Guide to Stormwater BMP Maintenance Homeowners Guide to Stormwater BMP Maintenance What You Need to Know to Take Care of Your Property Rain Barrel Dry Well Rain Garden Pervious Asphalt Porous Pavers City of El Monte Stormwater BMP Management

More information

The Napa River Flood Protection Project

The Napa River Flood Protection Project The Napa River Flood Protection Project Creating Flood Protection and Restoring Geomorphic and Biological Processes Jeremy Sarrow, Napa County Flood Control & Water Conservation District June 2, 2014.

More information

Big Thompson River Restoration Master Plan. Stakeholder Kick off Meeting and Workshop April 12, 2014

Big Thompson River Restoration Master Plan. Stakeholder Kick off Meeting and Workshop April 12, 2014 Big Thompson River Restoration Master Plan Stakeholder Kick off Meeting and Workshop April 12, 2014 AGENDA 1:30 to 2:10 Information 2:10 to 2:35 Questions 245t 2:45 to 4:00 400 Worksession in Cafeteria

More information

Stormwater BMP and Stream Restoration in a City Park. Jeff Herr P.E., D.WRE Jill Stachura

Stormwater BMP and Stream Restoration in a City Park. Jeff Herr P.E., D.WRE Jill Stachura Stormwater BMP and Stream Restoration in a City Park Jeff Herr P.E., D.WRE Jill Stachura 770.673.3673 JHerr@BrwnCald.com Project Location Camp Creek in Metro Atlanta 7 sq. mile drainage area at project

More information

BIORETENTION FACILITY

BIORETENTION FACILITY ILLINOIS URBAN MANUAL PRACTICE STANDARD BIORETENTION FACILITY (feet) CODE 800 Source: Jessica Cocroft, Winnebago Soil and Water Conservation District DEFINITION Facility that utilizes a soil media, mulch,

More information

Appendix N. Preliminary Design

Appendix N. Preliminary Design Appendix N Preliminary Design Belfountain Dam and Headpond Class EA Preferred Alternative D4H5: Lower the spillway & backfill headpond & construct channel Preliminary Cost Estimate ITEM ITEM UNIT EST.

More information

Appendix E Preliminary Design

Appendix E Preliminary Design Appendix E Preliminary Design 1 1 0+080 0+100 0+200 0+240 LEGEND PROPOSED POOL PROPOSED RIFFLE PROPOSED COIR CLOTH BANK TREATMENT PROPOSED VEGETATED STONE BANK TREATMENT PROPOSED VEGETATED BLOCK BANK TREATMENT

More information

A Review of Green Infrastructure Projects Implemented in the Grand Traverse Region

A Review of Green Infrastructure Projects Implemented in the Grand Traverse Region A Review of Green Infrastructure Projects Implemented in the Grand Traverse Region Sarah U Ren Program Director The Watershed Center of Grand Traverse Bay 231-935-1514, suren@gtbay.org Our Mission: The

More information

Chapter 3 Site Planning and Low Impact Development

Chapter 3 Site Planning and Low Impact Development CHAPTER 3 Site Planning and Low Impact Development Chapter 3 Site Planning and Low Impact Development 3.0 Introduction The City of Charleston requires that major residential, large commercial (>1 acre),

More information

Tips for Maintaining and Enhancing Stormwater Management Areas

Tips for Maintaining and Enhancing Stormwater Management Areas 4 4 N. Second Street, Denton, Md. 21629 (410) 479-3625 (410) 479-3534 fax www.dentonmaryland.com Tips for Maintaining and Enhancing Stormwater Management Areas Information provided by the Town of Denton

More information

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS 5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS Low Impact Development (LID) requires a shift in stormwater management away from conveying runoff to a small number of downstream points through hydraulically

More information

Restoration of Riparian Buffer at the Former Smelt Hill Dam Site, Falmouth, Maine

Restoration of Riparian Buffer at the Former Smelt Hill Dam Site, Falmouth, Maine Restoration of Riparian Buffer at the Former Smelt Hill Dam Site, Falmouth, Maine Final Report June 30, 2006 Page 1 of 16 I. Project Title Restoration of Riparian Buffer at the Former Smelt Hill Dam Site,

More information

East Montpelier SWMP Preliminary BMP Summary Sheet BMP ID #: 1 Site name: U-32 High School. Current site type

East Montpelier SWMP Preliminary BMP Summary Sheet BMP ID #: 1 Site name: U-32 High School. Current site type East Montpelier SWMP Preliminary BMP Summary Sheet BMP ID #: 1 Site name: U-32 High School 930 Gallison Hill Rd, East Montpelier, VT Filter Berm, Sand Filter, Cistern / Rain Barrel, Gravel Wetland, Check

More information

Public Meeting for the Redevelopment of. July 17,2018 7pm to 9pm Rolling Knolls Elementary School

Public Meeting for the Redevelopment of. July 17,2018 7pm to 9pm Rolling Knolls Elementary School Public Meeting for the Redevelopment of July 17,2018 7pm to 9pm Rolling Knolls Elementary School Meeting Agenda Welcome/ Community Meeting Key Project Information History - Damian Cosby, DRP- Chief of

More information

Rule D Wetland and Creek Buffers

Rule D Wetland and Creek Buffers Rule D Wetland and Creek Buffers 1 Policy It is the policy of the Board of Managers to ensure the preservation of the natural resources, recreational, habitat, water treatment and water storage functions

More information

RIVER TRAINING STRUCTURES

RIVER TRAINING STRUCTURES RIVER TRAINING STRUCTURES SPUR DIKES Spur dikes, deflectors or groins are transverse structures that extend into the stream from the bank and reduce erosion by deflecting flows away from the bank. Transverse

More information

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM Project ID Number: 25-5 Problem: Stormwater collected from the neighborhood upstream is released at 9 Muirfield Lane and flows west toward

More information

2.1.4 Roof Downspout Rain Gardens

2.1.4 Roof Downspout Rain Gardens 2008 SWMM, 2010 Revision City of Tacoma 2.1.4 Roof Downspout Rain Gardens Purpose and Definition Bioretention areas are shallow stormwater retention facilities designed to mimic forested systems by controlling

More information

Working with nature to manage your stream

Working with nature to manage your stream Working with nature to manage your stream Issued by Auckland Council March 2013 If you have any questions about this information sheet please contact Auckland Council on 09 301 0101 A stream in a property

More information

Lake Nokomis Shoreline Enhancement Project

Lake Nokomis Shoreline Enhancement Project Lake Nokomis Shoreline Enhancement Project Community Meeting 2 February 13, 2018 Agenda Current Problems Project Goals Project Status Existing Conditions Community Input Draft Schematic Design Long-term

More information

CHAPTER 4. SPECIAL CONDITION EROSION CONTROL MEASURES

CHAPTER 4. SPECIAL CONDITION EROSION CONTROL MEASURES CHAPTER 4. SPECIAL CONDITION EROSION CONTROL MEASURES 4.1 INFILTRATION BASIN AND TRENCH Figure 4.1. Infiltration basin and trench (Source: Department of Civil, Construction, and Environmental Engineering,

More information

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion Topics Erosion, TESC and Construction sequencing Procedures and timing Remedies for failing sites Curtis Hinman WSU Extension and Bio Systems Eng. Faculty Low Impact Development Specialist chinman@wsu.edu

More information

Design Considerations for Open Channel and Detention Pond Design. Howard Redfearn, City of Mansfield

Design Considerations for Open Channel and Detention Pond Design. Howard Redfearn, City of Mansfield Design Considerations for Open Channel and Detention Pond Design Howard Redfearn, City of Mansfield Previous Experience/Criteria/Maintenance Issues New Criteria Discussion Overview Where is Mansfield?

More information

Low Gradient Velocity Control Short Term Steep Gradient [1] Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent

Low Gradient Velocity Control Short Term Steep Gradient [1] Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Grass Linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient [1] Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] May be used on short, steep

More information

WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES

WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES Greenville County Technical Specification for: WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES 1.0 Mountainous and Steep Slope Sites 1.1 Description The geographic locations of portions of Greenville County are

More information

Client #: Dawson /91. NRCS Tract #(s): Location: Fleming Memorial Park Field #(s): Program(s): Urban Project Name: Date:

Client #: Dawson /91. NRCS Tract #(s): Location: Fleming Memorial Park Field #(s): Program(s): Urban Project Name: Date: Natural Resource Stewardship Plan Jackson Soil and Water Conservation District 89 Alder Street Central Point, Oregon 97502 Ph. (541) 664-1070 www.jswcd.org Client Name: Elisa Dawson, City of Rogue River

More information

Vegetating Disturbed Road & Stream Banks. By Mike Fournier NRCS Resource Conservationist

Vegetating Disturbed Road & Stream Banks. By Mike Fournier NRCS Resource Conservationist Vegetating Disturbed Road & Stream Banks By Mike Fournier NRCS Resource Conservationist Clearly Identify The Problem Project Objectives Clearly Define Objectives Before Work Starts Determine Whether Project

More information

PICTURE CANYON Planning Riparian-Wetland Refugia in an Urban Setting

PICTURE CANYON Planning Riparian-Wetland Refugia in an Urban Setting PICTURE CANYON Planning Riparian-Wetland Refugia in an Urban Setting Rio De Flag Existing Conditions. Ephemeral stream; Limited riparian plants, habitats.. & Opportunities Water (effluent) available Restore

More information

MINNEHAHA GLEN FEASIBILITY STUDY

MINNEHAHA GLEN FEASIBILITY STUDY THE KESTREL DESIGN GROUP, INC. 2007 Prepared for: Prepared by: Minnehaha Creek Watershed District Minneapolis Park and Recreation Board The Kestrel Design Group, Inc. Wenck Associates ISSUES AND STRATEGIES:

More information

Colorado Watershed Protection Fund - Project Grant Application Fountain Creek Restoration Shryver Park Reach Including Shryver Pond

Colorado Watershed Protection Fund - Project Grant Application Fountain Creek Restoration Shryver Park Reach Including Shryver Pond Fountain Creek - Manitou Springs, CO Shryver Park Reach and Pond Restoration Project Submitted by: The Fountain Creek Restoration Committee & The Pikes Peak Community Foundation April 28, 2008 FCRC Page

More information

EAGLE POINT PARK. Issues of Concern. Eagle Point Park is a cultural, historic, and ecological treasure

EAGLE POINT PARK. Issues of Concern. Eagle Point Park is a cultural, historic, and ecological treasure Issues of Concern Eagle Point Park is a cultural, historic, and ecological treasure However it s dramatic topography and long term environmental pressures have led to a number of issues of concern in the

More information

NATURAL LAKE & STREAMBANK PROTECTION & NATURAL BUFFERS. By Sam Martin, Water Management Specialist, Pine SWCD

NATURAL LAKE & STREAMBANK PROTECTION & NATURAL BUFFERS. By Sam Martin, Water Management Specialist, Pine SWCD NATURAL LAKE & STREAMBANK PROTECTION & NATURAL BUFFERS By Sam Martin, Water Management Specialist, Pine SWCD Natural Lake & Streambank Protection & Natural Buffers Lakeshore & Streambank Erosion Projects

More information

APPENDIX A SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS. In West Sadsbury Township, Chester County, Pennsylvania

APPENDIX A SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS. In West Sadsbury Township, Chester County, Pennsylvania APPENDIX A SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS In West Sadsbury Township, Chester County, Pennsylvania TABLE OF CONTENTS I. Introduction 3 II. Importance of Stormwater Management

More information

Case Study: Dallas Green Infrastructure for Stormwater

Case Study: Dallas Green Infrastructure for Stormwater Case Study: Dallas Green Infrastructure for Stormwater Extension and Research Sandhya Mohan Fouad H. Jaber, PhD Biological and Agricultural Engineering Texas Agrilife, Texas A&M University System Urban

More information

Beyond Rain Gardens Advancing the Use of Compost for Green Infrastructure, Low Impact Development, & Stormwater Management

Beyond Rain Gardens Advancing the Use of Compost for Green Infrastructure, Low Impact Development, & Stormwater Management Beyond Rain Gardens Advancing the Use of Compost for Green Infrastructure, Low Impact Development, & Stormwater Management VORS 2018 Stormwater Management Session 2 Stormwater Management, Green Infrastructure,

More information

Stormwater Standards. Clackamas County Service District No. 1. Planting Guide for Buffers

Stormwater Standards. Clackamas County Service District No. 1. Planting Guide for Buffers Stormwater Standards Clackamas County Service District No. 1 APPENDIX B Planting Guide for Buffers Table of Contents Appendix B - Planting Guide for Buffers... Page B.1 General... 1 B.1.1 Introduction...

More information

Understanding Drainage Options What s Feasible and Legal. February 2019

Understanding Drainage Options What s Feasible and Legal. February 2019 Understanding Drainage Options What s Feasible and Legal February 2019 Outline for the Presentation Do you need a permit? Does common law apply? Does local government approve it? Will my neighbor allow

More information

Property Owner s Guide to Creek and Shoreline Maintenance

Property Owner s Guide to Creek and Shoreline Maintenance 2014 Property Owner s Guide to Creek and Shoreline Maintenance City of O Fallon This guide for homeowners of creekside property is intended to serve as a reference for helping homeowners understand what

More information

Section 3 Non-Structural BMPs

Section 3 Non-Structural BMPs 3.1 Stream Buffers A stream buffer or stream setback is a designated area around a stream, lake, or wetland left in a natural, densely vegetated state so as to protect the receiving water quality and provide

More information

WETLAND SOD u Bare Root Wetland Plants u Deep Rooted Willows u Coir Logs u Native Trees & Shrubs u Habitat Islands u Custom Growing

WETLAND SOD u Bare Root Wetland Plants u Deep Rooted Willows u Coir Logs u Native Trees & Shrubs u Habitat Islands u Custom Growing WETLAND SOD u Bare Root Wetland Plants u Deep Rooted Willows u Coir Logs u Native Trees & Shrubs u Habitat Islands u Custom Growing 2009 PROJECT HIGHLIGHTS The following 10 projects highlight the interesting

More information

Chapter 14. Stormwater Quality Introduction

Chapter 14. Stormwater Quality Introduction 14.0 Introduction This chapter addresses requirements and design criteria related to post-construction stormwater best management practices (requirements for construction erosion and sediment control are

More information

Improving Communities Through the Arroyo Seco Sustainability Campaign and Watershed Assessment

Improving Communities Through the Arroyo Seco Sustainability Campaign and Watershed Assessment Improving Communities Through the Arroyo Seco Sustainability Campaign and Watershed Assessment Arroyo Seco Headwaters in the San Gabriel Mountains Major tributary to the Los Angeles River 44 square mile

More information

POST-FIRE RESTORATION Dos and Don ts

POST-FIRE RESTORATION Dos and Don ts POST-FIRE RESTORATION Dos and Don ts USDA Natural Resources Conservation Service The NRCS/RCD office is located at: 744 LA GUARDIA ST BLDG A SALINAS, CA 93905-3354 (831) 424-1036 (NRCS) (831) 424-1036

More information

12/7/2007. Christopher B. Burke Engineering West, Ltd Aux Sable Creek Watershed Plan Update 1

12/7/2007. Christopher B. Burke Engineering West, Ltd Aux Sable Creek Watershed Plan Update 1 The ABC s of BMP s Aux Sable Watershed Plan St. Charles, IL Why are BMP s Important Best Management Practices (BMPs) developed as a set of practices which help to achieve goals of the Clean Water Act and

More information

VA DCR STORMWATER DESIGN SPECIFICATION NO. 11 WET SWALE. VERSION 2.0 January 1, 2013 SECTION 1: DESCRIPTION

VA DCR STORMWATER DESIGN SPECIFICATION NO. 11 WET SWALE. VERSION 2.0 January 1, 2013 SECTION 1: DESCRIPTION VIRGINIA DCR STORMWATER DESIGN SPECIFICATION No. 11 VERSION 2.0 January 1, 2013 SECTION 1: DESCRIPTION Wet swales can provide runoff filtering and treatment within a conveyance system and are a cross between

More information

Rangeland Health (Rangeland only)

Rangeland Health (Rangeland only) Chapter 20 Rangeland Health (Rangeland only) 20.1 Overview This chapter covers data elements relating to Rangeland Health. Rills Infiltration and Runoff Waterflow patterns Compaction Layer Pedestals and/or

More information

Natural Shorelines. for Inland Lakes. A Landowner s Guide to using. to STABLIZE SHORELINES, Michigan s inland lakeshore.

Natural Shorelines. for Inland Lakes. A Landowner s Guide to using. to STABLIZE SHORELINES, Michigan s inland lakeshore. Natural Shorelines for Inland Lakes A Landowner s Guide to using NATURAL MATERIALS to STABLIZE SHORELINES, IMPROVE WATER QUALITY and ENHANCE WILDLIFE HABITAT along Michigan s inland lakeshore. Natural

More information

Key elements : Filter Strips must be designed within parameters required by the Fort Wayne s Development Standards/Criteria Manual.

Key elements : Filter Strips must be designed within parameters required by the Fort Wayne s Development Standards/Criteria Manual. 4.4. Filter Strips Filter Strips are densely vegetated lands that treat sheet flow storm water from adjacent pervious and impervious areas. They function by slowing runoff, trapping sediment and pollutants,

More information

13. Implementation Showcase: Walnut Brook Streambank Stabilization and Riparian Restoration Project

13. Implementation Showcase: Walnut Brook Streambank Stabilization and Riparian Restoration Project 13. Implementation Showcase: Walnut Brook Streambank Stabilization and Riparian Restoration Project The Walnut Brook watershed is located on the eastern side of the Route 12 and C.R. 523 circle and north

More information

Stormwater Management Techniques WMPF LAND USE TRAINING INSTITUTE MARCH 14, 2018

Stormwater Management Techniques WMPF LAND USE TRAINING INSTITUTE MARCH 14, 2018 Stormwater Management Techniques WMPF LAND USE TRAINING INSTITUTE MARCH 14, 2018 Potential Impacts of New Development Urban development can significantly increase stormwater runoff Water quality considerations

More information

319 Grant: Baker Creek & Centenary Creek Restoration Initiative

319 Grant: Baker Creek & Centenary Creek Restoration Initiative 319 Grant: Baker Creek & Centenary Creek Restoration Initiative Objectives: Overview of Watershed Characteristics: Discussion of Project Tasks: Discussion of Watershed Management Plan: Presented by: Erich

More information

The Toe Wood Structure

The Toe Wood Structure The Toe Wood Structure by Dave Rosgen Objectives: Enhance fish habitat/food chains Stabilize streambanks Maintain a low width/depth ratio Provide a more natural appearance & improve visual values Be compatible

More information

City of Shady Cove Riparian Ordinance Ordinance XXX

City of Shady Cove Riparian Ordinance Ordinance XXX 1 Updated October 8, 2015 City of Shady Cove Riparian Ordinance Ordinance XXX This language is to be located in Chapter 155 of the Shady Cove Code of Ordinances. This will affect property inside city limits,

More information

Coir Fibers Help Strengthen Environmentally-Friendly Golf Course Stream Restoration Project

Coir Fibers Help Strengthen Environmentally-Friendly Golf Course Stream Restoration Project Coir Fibers Help Strengthen Environmentally-Friendly Golf Course Stream Restoration Project RoLanka International, Inc. 2004 Stabilizing nearly two miles of streambanks and slopes wasn t the only challenge

More information

Illinois Urban Manual

Illinois Urban Manual Illinois Urban Manual Jim Nelson: Association of Illinois Soil and Water Conservation Districts (AISWCD) Funding for this project provided, in part, by the Grand Victoria Foundation of Elgin IL, the Governor

More information

Glencoe Elementary School Parking Lot Retrofit 825 SE 51 st Street

Glencoe Elementary School Parking Lot Retrofit 825 SE 51 st Street Glencoe Elementary School Parking Lot Retrofit 825 SE 51 st Street Project Summary Project Type: Technologies: Institutional parking lot retrofit demonstration project Vegetated infiltration swale with

More information

Feet. Overland. Drainage Area Boundary. To Swale. Swale. To Catch Basin. Culvert Pipe. To Drain Outfall. NRCS Soil Area Boundary

Feet. Overland. Drainage Area Boundary. To Swale. Swale. To Catch Basin. Culvert Pipe. To Drain Outfall. NRCS Soil Area Boundary 0 25 50 00 Feet Parcel Boundary, Approximate 202 LIDAR 2 FT CONTOURS, VCGI BING AERIAL NRCS SOIL MAPPING MMI FIELD DATA Culvert Pipe Swale 0 Scale: "=40' SOURCE(S): NRCS Soil Area Boundary Overland st

More information

Part IV(a): BMPs for Erosion, Sediment, Velocity Control

Part IV(a): BMPs for Erosion, Sediment, Velocity Control Part IV(a): BMPs for Erosion, Sediment, Velocity Control Find Design Standards and Specifications for Iowa Erosion and Sediment Control Practices at: www.iowasudas.org Erosion Control Keeping the soil

More information

2011 ASLA Design Awards. Coyote Gulch Honor Award and Land Stewardship Designation Valerian LLC. Environmental Restoration and Reclamation

2011 ASLA Design Awards. Coyote Gulch Honor Award and Land Stewardship Designation Valerian LLC. Environmental Restoration and Reclamation 2011 ASLA Design Awards Honor Award and Land Stewardship Designation Valerian LLC Environmental Restoration and Reclamation Project Name: Category : Project Location: 5 2011 Environmental Restoration and

More information

Table 4.7.1: Swales Potential Application and Storm Water Regulation

Table 4.7.1: Swales Potential Application and Storm Water Regulation 4.7. Swales A swale is a vegetated open channel, planted with a combination of grasses and other herbaceous plants, shrubs, or trees. A traditional swale reduces peak flow at the discharge point by increasing

More information

6.5 Lakewood Gulch. Basin Snapshot

6.5 Lakewood Gulch. Basin Snapshot 6.5 Lakewood Gulch The Lakewood Gulch Map Unit is comprised of both Lakewood Gulch and Dry Gulch (4800-01 and 4801-01) from the Denver Storm Drainage Master Plan (SDMP) and has a total drainage area of

More information

Worksheet #14 Water Runoff Management

Worksheet #14 Water Runoff Management Water Runoff Management Use this worksheet to assess how well your property minimizes the potential for water runoff and property damage.. Why should you be concerned? What can you do? Rural runoff, also

More information

Learning from Nature: Reducing Urban Stormwater Impacts

Learning from Nature: Reducing Urban Stormwater Impacts This article was published in the Spring, 2005 Issue of LakeLine magazine It is posted on the Urban Drainage and Flood Control District s web site with the authors and the publishers permission to the

More information

Best Management Practices

Best Management Practices Best Management Practices Urban Areas Aquatic Areas Natural Areas Best Management Practices Urban Areas Green Industry Best Management Practices Fertilizer Label Nitrogen Applications Phosphorous Applications

More information

Applied Ecological Services, Inc. Sustainable Solutions for Over 30 Years.

Applied Ecological Services, Inc. Sustainable Solutions for Over 30 Years. Applied Ecological Services, Inc. Sustainable Solutions for Over 30 Years. Landfills Can Mitigate and Restore Riparian Impacts on Their Property Jason Dremsa, Construction Manager Applied Ecological Services,

More information

Zoning Ordinance Article 3

Zoning Ordinance Article 3 Article 3 Natural Resources Protection Section 301 Natural Resources Protection 301.1. Purpose - The following natural resources protection standards are established to protect the public health, safety

More information

Town of Vershire Road Erosion Inventory Report

Town of Vershire Road Erosion Inventory Report Town of Vershire Road Erosion Inventory Report Taylor Valley Road. Photo taken by TRORC staff. Prepared by: 128 King Farm Road Woodstock, VT 05091 Inventory and report funded by the Vermont Agency of Transportation

More information

Case Study 6. Fitzpatrick Creek Cable Concrete Block Mat Ford

Case Study 6. Fitzpatrick Creek Cable Concrete Block Mat Ford Case Study. Fitzpatrick Creek Cable Concrete Block Mat Ford Location Southwest Oregon. Bureau of Land Management Coos Bay District. Fitzpatrick Creek. BLM road 23-8-11.0. This ford was constructed in 2000

More information

Study Area Map. Wasatch Hollow Open Space Restoration, Use, & Management Plan. Legend. Harrison Ave East. Roosevelt East.

Study Area Map. Wasatch Hollow Open Space Restoration, Use, & Management Plan. Legend. Harrison Ave East. Roosevelt East. Harrison Ave Roosevelt Emerson «4 «5 Rosecrest 1900 East «3 1800 East Wasatch Hollow Open Space Restoration, Use, & Management Plan Study Area Map Legend «2 «1 Potential Access Location Emigration Creek

More information

Southeast Michigan Council of Governments

Southeast Michigan Council of Governments Southeast Michigan Council of Governments SEMCOG Green Infrastructure Activities Regional Green Infrastructure Vision GLRI Green Streets EPA Technical Assistance MDOT Grants Green Infrastructure Vision

More information