DESIGN AND CONSTRUCTION STANDARDS GENERAL DESIGN GUIDELINES

DUKE UNIVERSITY CONSTRUCTION STANDARDS

DESIGN STANDARDS SECTION PLUMBING FIXTURES AND EQUIPMENT. 1.3 Wall hung toilet room fixtures. Urinals for handicapped may be stall type.

DESIGN STANDARDS SECTION Toilet rooms and utility rooms to have floor drains at lowest point.

C. ASSE 1013: Performance Requirements for Reduced Pressure Principle Backflow Preventers.

GARCIA GALUSKA DESOUSA Consulting Engineers

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Mechanical Inspection Plumbing

B. Shop Drawings: Include diagrams for power, signal, and control wiring.

GENERAL PLUMBING REQUIREMENTS

DESIGN STANDARDS SECTION Toilet rooms and utility rooms to have floor drains at lowest point.

Division 11 - Equipment

2. All necessary storm and sanitary pumps shall be tied into emergency power, and sump levels shall be monitored electronically through the B.A.S.

A. Section Joint Sealants: Seal fixtures to walls and floors.

BRADLEY HALO EMERGENCY PLUMBING FIXTURES (Short Form Version)

HWC NOTES: CONTRACTOR SHALL REFER TO ARCHITECTURAL DRAWINGS FOR MOUNT HEIGHTS AND SPECIAL MOUNTING INSTRUCTION AND LIMITATIONS.

SECTION PLUMBING

GENERAL PLUMBING REQUIREMENTS

PERFORMANCE TECHNICAL SPECIFICATION *************************************************************************** SECTION D20 PLUMBING 02/18

SECTION PLUMBING FIXTURES

BRADLEY HALO EMERGENCY PLUMBING FIXTURES

LAV FCO WCO NOTES: CONTRACTOR SHALL REFER TO ARCHITECTURAL DRAWINGS FOR MOUNT HEIGHTS AND SPECIAL MOUNTING INSTRUCTION AND LIMITATIONS.

Sanitary Drainage Systems

1. Division 22 Section "Emergency Plumbing Fixtures." 2. Division 22 Section "Drinking Fountains and Water Coolers."

A. This Section includes the following emergency plumbing fixtures:

A. This Section includes the following domestic water piping specialties:

A. All fixtures shall meet the requirements of ANSI A117.1, ANSI Z124.2 and the State of Texas Accessibility Standards (TAS).

CHAPTER 10 TRAPS AND INTERCEPTORS

DESIGN GUIDELINES AND TECHNICAL STANDARDS

Level I Chapter 1 Worksheet

SECTION PLUMBING FIXTURES AND TRIM. A. Types of plumbing fixtures required for the project include the following:

TRUMAN STATE UNIVERSITY PRESIDENT S RESIDENCE RENOVATION

ICP Plumbing Exam. Name: Carefully read each question and then circle the letter of the best answer.

PERFORMANCE TECHNICAL SPECIFICATION *************************************************************************** SECTION D20 PLUMBING 02/18

PERFORMANCE TECHNICAL SPECIFICATION *************************************************************************** SECTION D20 PLUMBING 02/18

PLUMBING REQUIREMENTS

Yale University Design Standards

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Plumbing Standards

Read Only Document Not For Distribution

DESIGN AND CONSTRUCTION STANDARDS SPECIFICATION GUIDELINES

SECTION DOMESTIC WATER PIPING SPECIALTIES

University of New Hampshire Scholars' Repository

C. EWFs shall deliver the quality and quantity of water that is satisfactory for emergency washing purposes.

DeCA DESIGN CRITERIA HANDBOOK PLUMBING SYSTEMS

SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- PLUMBING

GENERAL PLUMBING REQUIREMENTS

Tighe&Bond. Groton Heights School Mechanical Evaluation. 1 Existing Conditions. 1.1 Water Service Entrance

Work Order Number PERFORMANCE TECHNICAL SPECIFICATION *************************************************************************** SECTION D20

Plumbing and Drainage

PLUMBING DESIGN GUIDELINES SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS

TABLE OF CONTENTS DIVISION 22 - MECHANICAL

Gulfport, Mississippi 21 May 2007

Facility Condition Assessment Summary Report. British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building

2). Crane Co. 4). Kohler Co. 5). Universal-Rundle Corp. Revised September 29, 2017 Commercial Plumbing Fixtures

B. Shop Drawings: Include diagrams for power, signal, and control wiring.

MATERIALS Traps TRAPS. No. IPC IRC Description

PLUMBING INSTALLATIONS

DESIGN CRITERIA See Part II for additional information regarding Energy and Water Efficiency, etc.

Read Only Document Not For Distribution

C. All components of the systems described shall meet the requirements as stated herein and shall be approved by the Architect and Consultant.

Summary of BBS Proposed Ohio Plumbing Code Rule Changes October 2016

PLAN REVIEW SUBMITTAL GUIDE

CHAPTER 10 TRAPS AND INTERCEPTORS TABLE 10-1 HORIZONTAL LENGTHS OF TRAP ARMS (EXCEPT FOR WATER CLOSETS AND SIMILAR FIXTURES) 1, 2

A. General: comply with appropriate standards. 1. International Association of Plumbing and Mechanical Officials: IAPMO. 2. California State AB 1953.

2016 Plumbing Supplemental Plan Review List

Moen Commercial Products Eco-Performance Product Guide

PLUMBING FIXTURES CHAPTER 27

FIRE PROTECTION. 1. Vertical fire pumps shall not be used at the University.

Plumbing Technology/Plumber CIP Task Grid

2009 IPC ,IMC Q &A ANDIFGC

DESIGN AND CONSTRUCTION STANDARDS July 2011

CHAPTER 10 TRAPS AND INTERCEPTORS The vent pipe opening from a soil or waste No more than one (1) approved slip joint

SECTION LABORATORY and DE-IONIZED WATER SYSTEMS STANDARD CONSTRUCTION STANDARD

PLUMBING CURRICULA OUTLINE

DIVISION 22: PLUMBING DESIGN STANDARDS TABLE OF CONTENTS

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 22 PLUMBING. A. This Section includes the following sanitary drainage piping specialties:

CHaPTeR 10. TRaPS and INTeRCePTORS. Table 10-1 Horizontal lengths of Trap arms (except for water closets and similar fixtures)*

Building Utilities 1 Plumbing and Sanitary Systems

Perkins Statewide Articulation Agreement. Documentation item: Secondary Competency Task List Coversheet

IPC Plumbing Exam. Name: Carefully read each question and then circle the letter of the best answer.

Read Only Copy Not For Distribution. Chapter 10. Water Supply and Distribution 10.1 QUALITY OF WATER SUPPLY 10.2 RESERVED 10.

Contents. Eye/Face Washes... 3 Eyewashes... 3 Swing-Away Eyewashes... 4 Eyewash/Drench Hose Units... 4 Emergency Showers... 4 Safety Stations...

STACKS AND STACK VENTS

1.1 Refer to Section for General Mechanical Requirements. 1.3 Refer to Section for Pipe and Equipment Identification Requirements.

Plumbing. Definitions. Background Factors. Air Chambers. Air Gap (Drainage System) Air Gap (Water Distribution System) Air Lock.

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

SAFETY PLUMBING PACKAGES. Quality Products & Value Packages SUSTAINABILITY. Residential Solutions ANTI-SCALE SYSTEMS FIRE PROTECTION

SECTION PLUMBING SPECIALTIES

WARRANTY POLICY & RECOMMENDED MAINTENANCE

SUBCOURSE EDITION EN US ARMY ENGINEER SCHOOL PLUMBING FIXTURES (PLUMBING IV)

University of Rochester October 17, 2008 Brooks Landing Business Center

Mechanical System Description

BSD Technical Standard. Division 22: Plumbing

This Product MasterSpec Section is licensed by AVITRU, LLC to Haws Corporation ("Licensee").

Plumbing Fixtures CEU 216. Continuing Education from the American Society of Plumbing Engineers. October ASPE.

SCHEDULE OF FEES. Penalty Fees. Building Fee Schedule FEE

AIRPORT PLUMBING DESIGN STANDARDS REV. 3 3/18/2016

SECTION DOMESTIC WATER PIPING SYSTEMS. 0. Pipe and pipe fittings are specified in the following sections:

SECTION PLUMBING EQUIPMENT Piping (Plumbing). 2. Division 16 - Electrical Wiring and Connections.

CUSTOMIZED TEACHER ASSESSMENT BLUEPRINT PLUMBING. Test Code: 5924 Version: 01

Transcription:

DIVISION 22 PLUMBING 22 11 16 DOMESTIC WATER PIPING 22 11 19 DOMESTIC WATER PIPING SPECIALTIES 1. To facilitate landscape and other maintenance operations, exterior hose bibs shall be provided at 150 foot intervals along building perimeters, including near principal building entrances and exits. Each building face shall have at least one hose bib. 1. All hose bibs shall be of the non-freeze, recessed lockable wall box type, and shall be mounted flush to the wall. 22 11 23 DOMESTIC WATER PUMPS 22 11 23.13 DOMESTIC WATER PACKAGED BOOSTER PUMPS 22 12 00 FACILITY POTABLE WATER STORAGE TANKS PART III DIVISION 22 PAGE 1 RUTGERS DESIGN STANDARDS MANUAL JUNE 2018

22 13 16 SANITARY WASTE AND VENT PIPING 1. All new building sanitary lines shall go to a manhole. 2. For design purposes, all floor drains in spaces other than mechanical equipment rooms shall be considered infrequent use in accordance with the National Standard Plumbing Code. 3. All floor drains in mechanical rooms and other locations shall be connected to the sanitary sewer system. 1. Hubless cast iron pipe is preferred above grade and should be used above grade where piping related noise may be an issue. Hubless cast iron pipe is prohibited underground or under floor slabs. 2. Cast iron hub & spigot piping is preferred to PVC under floor slabs. PVC piping is prohibited under floor slabs in facilities containing high temperature hot water equipment. 22 13 19 SANITARY WASTE PIPING SPECIALTIES 22 13 29 SANITARY SEWERAGE PUMPS 22 14 13 FACILITY STORM DRAINAGE PIPING PART III DIVISION 22 PAGE 2 RUTGERS DESIGN STANDARDS MANUAL JUNE 2018

1. Provide at least 2 roof drains per section of roof. See Uniform Construction Code for additional requirements. 22 14 29 SUMP PUMPS 22 15 13 GENERAL SERVICE COMPRESSED AIR PIPING 22 15 16 GENERAL SERVICE COMPRESSED AIR VALVES 22 15 19 GENERAL SERVICE PACKAGED AIR COMPRESSORS AND RECEIVERS 22 31 00 DOMESTIC WATER SOFTENERS 22 32 00 DOMESTIC WATER FILTRATION EQUIPMENT 22 33 00 ELECTRIC DOMESTIC WATER HEATERS 1. Electric water heaters are permitted as an alternative to direct or indirect-fired hot water heaters to serve local low flow hot water requirements. PART III DIVISION 22 PAGE 3 RUTGERS DESIGN STANDARDS MANUAL JUNE 2018

1. Electric hot water heaters shall be as manufactured by A.O. Smith or approved equal. 22 34 00 FUEL-FIRED DOMESTIC WATER HEATERS 1. Oil fired water heaters may be required where significant hot water requirements must be met and gas service or indirect water heating is not available. Oil fired water heaters shall be used only with Rutger's approval. 1. Fuel burning equipment must be registered with REHS by the A/E (care of the project team leader) during design. Fuel burning equipment with a maximum rated fuel input of 1,000,000 BTU/hr or greater will require an air permit, prior to installation. REHS will submit all air permit applications. The A/E shall be responsible for preparation and follow-up correspondence with REHS and\or the DEP for all permitting required for fuel burning equipment. The A/E is responsible to supply equipment information to REHS with adequate lead-time to obtain permit (180 days prior to intended installation date.) This information includes, but is not limited to: a description of the fuel burning equipment, manufacturer name, model number and fuel type used. All documentation demonstrating conformance with Factory Mutual requirements must be submitted to FM for review\approval as required. 1. Oil fired water heater manufacturers shall be as approved by Rutgers. 22 35 00 DOMESTIC WATER HEAT EXCHANGERS 1. Domestic water generally should be heated with high temperature hot water (HTHW) when central heating system is available. 2. HTHW system operating parameters vary depending upon the system under consideration. PART III DIVISION 22 PAGE 4 RUTGERS DESIGN STANDARDS MANUAL JUNE 2018

3. For the Busch and Livingston campuses, HTHW is provided from the Busch Central Heating Plant. HTHW leaves the plant at approximately 365 degrees F. and a pressure between 180 psi and 200 psi. Depending on where the building is located on the distribution system, the temperature will vary between 335 degrees F. and 360 degrees F. The pressure will vary between 160 psi and 200 psi. Heat exchangers shall be designed for a 100 degree temperature differential. More specific design parameters can be provided by Rutgers Utilities Department based upon actual building location. 4. For the College Avenue campuses, HTHW is provided from the College Avenue Central Heating Plant for a portion of the campus. HTHW leaves the plant at approximately 315 degrees F. and a pressure of approximately 110 psi. Heat exchangers shall be designed for a 75 degree F. temperature differential. Depending on where the building is located on the distribution system, temperatures and pressure will vary. More specific design parameters can be provided by Rutgers Utilities Department based upon actual building location. 1. Refer to Section 23 05 23 General-Duty Valves for HVAC and Section 23 21 13 Hydronic Piping for related information. 2. All heat exchangers shall comply with ASME Boiler and Pressure Vessel Code and shall be stamped with appropriate code symbols. 3. Bolted flange connections shall be provided on both the primary side and secondary side of all heat exchangers. 4. HTHW heat exchangers shall be shell and tube type with HTHW in tubes and shall be rated for 400 psi. Tubes shall be 90-10 copper-nickel. Heads shall be forged steel. Domestic water heat exchangers must conform to requirements of the National Standard Plumbing Code (i.e. double wall construction, etc). 5. HTHW control valves shall be located on the supply side of the heat exchanger. PART III DIVISION 22 PAGE 5 RUTGERS DESIGN STANDARDS MANUAL JUNE 2018

6. HTHW heat exchangers shall have operating and high limit temperature sensing elements located in the shell near the outlet nozzle or immediately adjacent to the outlet nozzle. 7. HTHW heat exchangers shall be as manufactured by Cemline, Yula, Bell & Gossett or Armstrong. 22 40 00 PLUMBING FIXTURES 1. The A/E shall obtain the Standard Plumbing Fixture List from University Housing for the respective Housing project. Provide hose bibb in dormitory common toilet rooms where required by Housing. 2. Automatic hands free (automatic flushing and turn on/off) fixtures are preferred for toilet areas and are required for all ADA water closets, urinals, sinks and hand dryers. All hands free fixtures shall be equipped with manual override. Hard-wired automatic fixtures are preferred to battery operated. Bathroom and kitchen fixtures for projects not under the jurisdiction of University Housing, Dining Services or Athletics shall be as follows unless otherwise necessary to suit project specific requirements: a. Toilets: Wall-hung, vitreous china, single flush, piston or heavy duty diaphragm type, maximum 1.28 GPF as manufactured by Toto, Kohler or American Standard. b. Urinals: Wall-hung, vitreous china, piston or heavy duty diaphragm type, maximum.125 GPF as manufactured by Toto, Kohler or American Standard. c. Lavatories: Wall-hung or under-mount, vitreous china, maximum 0.5 GPM as manufactured by Toto, Kohler or American Standard. Automatic faucets shall be equipped with above deck mixing valve where required to ensure access to serviceable faucet components. Premolded Corian type lav/countertops for multiple lavatory applications shall be permitted subject to Rutgers approval. d. Kitchen Sinks (Office Kitchen Areas): Drop-in, self-rimming, single compartment, stainless steel as manufactured by American Standard, Just or Kohler. Faucets for Kitchen sinks to be manual, single lever type PART III DIVISION 22 PAGE 6 RUTGERS DESIGN STANDARDS MANUAL JUNE 2018

with ceramic disc valving as manufactured by Moen, Kohler or American Standard. e. Shower control valves shall be pressure balance type, solid brass construction. f. For design purposes, all floor drains in spaces other than mechanical equipment rooms shall be considered infrequent use in accordance with the National Standard Plumbing Code. Where practical, gravity type tailpiece trap primers for floor drains are preferred to trap primers hard-piped to the domestic water system. Deep seal traps are acceptable for floor drains in heavy use areas such as Mechanical Rooms. All floor drains serving mechanical rooms and similar areas shall be equipped with sediment bucket. Floor drains must be provided for emergency showers. 3. Plumbing fixtures for janitor s closets shall be as follows (subject to the review/approval of Rutgers Department of Buildings and Grounds on a project by project basis): a. Mop Sinks: Terrazzo, stainless steel or enameled cast iron with low front lip as manufactured by American Standard, Fiat or Florestone. Faucets for mop sinks shall be as manufactured by T & S Brass and Bronze Works, Inc. or equal. b. Service Sinks: Wall-hung, enameled cast iron as manufactured by American Standard or Kohler. 4. All plumbing fixtures must be tight fitting to walls and be neatly sealed at joint with silicone sealant. 5. All piping penetrating walls shall be covered with escutcheon plates. 6. Plumbing fixtures and fittings for laboratory furniture shall be provided by the laboratory furniture manufacturer. 7. Provide freeze-less wall hydrants every 150 on exteriors of new buildings. A minimum of one centrally located wall hydrant shall be provided for each building exposure. Model B65 series as made by Woodford Manufacturing, Inc. or approved equal. 8. Provide vacuum breakers for all plumbing fixtures as required by Code and as required to prevent back-siphonage to domestic water supply. 9. All fixtures shall be provided with ¼ turn stop valves (ball valves). PART III DIVISION 22 PAGE 7 RUTGERS DESIGN STANDARDS MANUAL JUNE 2018

22 45 00 EMERGENCY PLUMBING FIXTURES 1. Eyewash units shall be installed at or near sinks within the hazardous operations space. Such spaces include biological laboratories, wet laboratories, areas where dust is generated, darkrooms, mechanical rooms and other areas where liquid chemicals are used or handled. Handheld hose type units providing a soft spray of 3-7 gpm tempered water at a pressure of 30 pounds per square inch are recommended. These may be bench mounted or on the side of the bench or wall, and should be readily accessible and located in a high visibility area near the main door. Wall-mounted units, pedestal-mounted units, eye\face wash units, combination safety shower\eyewash units must be provided with a soft spray of 3-7 gpm at 30 pounds per square inch of pressure. 2. All eyewash units must flush both eyes simultaneously, the flow must remain on without the use of the operator s hands, the unit must remain activated until intentionally cut off and the nozzles must be protected from airborne contaminants. 3. A sign must be posted to identify the location of the eyewash unit and the area behind or around the eyewash unit must be painted with a bright color. Eyewash units for non-ada compliant units should be installed between 2-9 and 3-9 from the floor. For ADA compliant stations, for dimensions ICC ANSI A117.1 standards for drinking fountains shall be followed. However, the appliances shall be eyewash units. 4. Safety showers are to be installed in a conspicuous location, such as a well-traveled aisle, doorway or corridor. They must be within the room or space they serve or within 25 feet of the main room door. Safety showers in corridors can serve several laboratories or rooms. Safety showers must be installed in locations that are accessible at all times. Safety showers must have floor drain. 5. Safety showers are to be installed so that the center of the shower head is at least 25 from the nearest wall, bench or furnishing and at a safe distance away from electrical equipment or outlets. The base of the shower must be between PART III DIVISION 22 PAGE 8 RUTGERS DESIGN STANDARDS MANUAL JUNE 2018

6-10 and 8 above the floor. The shower head should be a deluge-type head, and should be made of plated brass or plastic. The safety shower unit should be capable of providing a flow of 30-50 gallons of water per minute at 30 pounds per square inch of pressure. 6. Safety shower activating valves are to be operated by pulling either a chain, a cord attached to die valve lever, an 8 diameter ring or a triangle connected by a chain or a cord to the lever. The lowest portion of the ring, triangle or cord should be located no more than 48 from the floor for frontal approach and no more than 54 from the floor for a side approach, and should be run within 1-2 of a wall or bench. Safety shower activating valves are to be quick- opening, self-closing globe valves. A shut-off valve accessible from a 6 foot ladder is to be installed for each shower head. 7. A sign must be posted to identify the location of the safety shower, and the area behind or around the safety shower must be painted with a bright color. Exterior safety shower and water supply lines must be protected from freezing. 8. Installation and operation of safety shower and eyewash units must comply with the most recent edition of ANSI Z358.1-standard. 9. The contractor must test each emergency eyewash and safety shower unit prior to building occupancy to confirm compliance with these paragraphs. The test results shall be posted on tags affixed to each unit that includes: the test date, the flow rate, the initials of the person conducting the testing, and whether or not the unit meets these design criteria (pass or fail). In addition, the contractor shall provide the building owner with a list that identifies the type and location of all emergency plumbing fixtures installed in the building. 22 47 00 DRINKING FOUNTAINS AND WATER COOLERS 1. Provide lead free materials certification from drinking fountain manufacturer prior to installation. PART III DIVISION 22 PAGE 9 RUTGERS DESIGN STANDARDS MANUAL JUNE 2018

1. Drinking fountains and water coolers shall be as manufactured by Elkay or approved equal. Unless otherwise approved by Rutgers project manager, all water coolers must be equipped with a bottle cooler. 22 61 13 COMPRESSED AIR PIPING FOR LABORATORY AND HEALTH CARE FACILITIES 22 61 19 COMPRESSED AIR EQUIPMENT FOR LABORATORY AND HEALTHCARE FACILITIES 22 62 13 VACUUM PIPING FOR LABORATORY AND HEALTH CARE FACILITIES 22 63 13 GAS PIPING FOR LABORATORY AND HEALTH CARE FACILITIES 22 66 00 CHEMICAL WASTE SYSTEMS FOR LABORATORY AND HEALTHCARE FACILITIES 22 66 83 CHEMICAL WASTE TANKS 22 67 13 PROCESSED WATER PIPING FOR LABORATORY AND HEALTHCARE FACILITIES PART III DIVISION 22 PAGE 10 RUTGERS DESIGN STANDARDS MANUAL JUNE 2018