HAYLE NEIGHBOURHOOD PLAN FUTURE HOUSING EXPANSION VISION DOCUMENT. Prepared for Hayle Neighbourhood Plan Steering Group by AECOM

Similar documents
Kibworth Harcourt. Introduction. Introduction

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of

ROCHFORD LOCAL DEVELOPMENT FRAMEWORK: Sustainability Appraisal/ Strategic Environmental Assessment. Rochford Core Strategy Preferred Options Document

Welcome to our exhibition

Oxford Green Belt Study. Summary of Final Report Prepared by LUC October 2015

Newcourt Masterplan. November Exeter Local Development Framework

Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS. A New Garden Neighbourhood Matford Barton 17

Carterton Construction Ltd is bringing forward plans for up to 85 new family homes and extra care facilities on land east of Burford.

WELCOME. Land North of STEVENAGE. We would like to thank you for attending our public exhibition today.

PHASE III: Reserved Matters Submission

WELCOME. Welcome and thank you for visiting today.

Perth and Kinross Council Development Management Committee 8 June Pre-Application Report by Development Quality Manager

SOUTH EAST LINCOLNSHIRE LOCAL PLAN: HOUSING PAPER DONINGTON (JUNE 2016)

WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014

3. Neighbourhood Plans and Strategic Environmental Assessment

Great Easton Neighbourhood Plan Statement of Basic Conditions

Suffolk Coastal Local Plan Review Issues and Options, August 2017, Public Consultation

Draft Hailey Neighbourhood Plan

Briefing Document of CNP. June 2017

Land at Fiddington Hill Nursery, Market Lavington

Public Consultation. Land at Monks Farm, North Grove. Welcome

Neighbourhood Planning Local Green Spaces

HS2 Hybrid Bill Petitioning. Summary of SMBC Asks 23/09/13. Background

University Park, Worcester Non Technical Summary December 2011

Welford-on-Avon Neighbourhood Plan Consultation Event Sunday, 6 April Your name Your address

Site Assessment Technical Document Appendix A: Glossary

PROPOSED RESIDENTIAL DEVELOPMENT LAND AT GREEN LANE, YARM

HARDWICK GREEN, King s Lynn. Welcome to our Exhibition. What are your views? Introduction to the site and proposals. About us

Public Consultation 23 January Peel Hall, Warrington Board 1. A message from Satnam... Site history...

ABOUT CALA HOMES CALA HOMES

WINCHESTER TOWN 3.1 LOCATION, CHARACTERISTICS & SETTING

Welcome to our public exhibition

LAND EAST OF HORNDEAN. 1. Welcome. Morrisons supermarket. Keydell Nurseries A3(M)

DUNSFOLD NEIGHBOURHOOD PLAN Site Selection Policies

Blandford Forum Town Council, Blandford St Mary Parish Council and Bryanston Parish Council

Wallingford Neighbourhood Plan

Land at Rampton Road. Cottenham

Welford-on-Avon. Neighbourhood Development Plan Welford-on-Avon Parish Council

Plumpton Neighbourhood Development Plan Revised Pre Submission Document - Regulation 14 Consultation

INTRODUCTION NORTH HEYBRIDGE GARDEN SUBURB

Development of land adjacent to Braggs Farm Lane and Rumbush Lane, Dickens Heath. Welcome. Today s exhibition. The proposal site

Place Brief. National Collections Facility (NCF site)

Neighbourhood Plan Representation

Longbridge Town Centre Phase 2 Planning Application

1. Nantwich - Planning for a Sustainable Future

The Gwennap Parish Vision Statement

Ebbsfleet Development Corporation

New Homes at Winton East

Colchester Northern Gateway Master Plan Vision Review Draft. July 2016

BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY

A Growing Community Rural Settlement Areas

Ipswich Issues and Options for the Ipswich Local Plan Review, August 2017, Public Consultation

Joint Core Strategy Rushden Sustainable Urban Extension

Strategic Environmental Assessment Screening Report. Dublin Port Masterplan Review 2017

OKEFORD FITZPAINE NEIGHBOURHOOD PLAN

INTRODUCTION. Welcome to the third round of information events on the emerging Yorkshire Energy Park proposals. THE CONSULTANT TEAM WHERE IS THE SITE?

NORTH CIRCULAR ROAD - REGENERATION IN ACTION

1.0 INTRODUCTION. Brantham Industrial Area Regeneration - Factory Lane - Brantham

Linby Neighbourhood Plan Masterplan Safeguarded Land Top Wighay Farm March Linby Neighbourhood Development Plan Masterplan 1

Memorial Business Park Site. Proposed Future Development. Design guidelines. August

Former North Works, Lickey Road, Longbridge, Birmingham

Statement of Community Involvement LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE

Proposed Amendment to the

Reserved Matters application for a site that straddles the boundary between CBC and BBC

Site ref: AS06 Site Name or Address: Murreys Court, Agates Lane

DEVELOPMENT MANAGEMENT REPORT

DEVELOPMENT MANAGEMENT REPORT

CLEVE PARK, THORNBURY

6 Growth Management Challenges and Opportunities

Appendix 1 Structure plan guidelines

Brighton Marina Neighbourhood Forum AGM. City Plan Part Two - Draft Plan

The Corporation of the TOWN OF MILTON

13 THORNHILL YONGE STREET STUDY IMPLEMENTATION CITY OF VAUGHAN OPA 669 AND TOWN OF MARKHAM OPA 154

Effingham Neighbourhood Plan 1. Basic Conditions Statement

Babergh and Mid Suffolk Joint Draft Local Plan Consultation, August 2017, Public Consultation

GREENFORD HALL & ADJOINING LAND

Application Guide. Should you have any questions on the Outline Application please contact:

Rochford District Council Allocations Development Plan Document: Discussion and Consultation Document Sustainability Appraisal

WELCOME TO THE NEW WILTON PARK

12 TH ANNUAL CHILTERNS AONB PLANNING CONFERENCE ENGLISH HERITAGE: HISTORIC ENVIRONMENT GOOD PRACTICE ADVICE

INTRODUCTION. Land south of Bishopswood Lane, Tadley

Crofton Manor 2803 West 41st Avenue WHAT WE HEARD. Public Consultation: Phase 1

A VISION FOR BLAIRGOWRIE

Reporter: Section 3 Place, Drymen, pp reference: Body or person(s) submitting a representation raising the issue (including reference number):

LAND EAST OF SUDBURY ROAD, HALSTEAD PUBLIC CONSULTATION. Proposed Residential Development

Story Homes. Land at Thirsk Road, Kirklevington. An Introduction to Story Homes. Our Foundations. Commitment to Consultation.

Town And Country Planning Act 1990 (As Amended) Town And Country Planning (General Development Procedure) Order 1995

01 Welcome. Why are we here?

Droitwich Spa 6. Reasoned Justification

THAT the attached Terms of Reference for the Thornhill Centre Street Study be approved.

LETTER OF OBJECTION LAND TO THE SOUTH WEST OF FORGE GARAGE, HIGH STREET, PENSHURST, KENT, TN11 8BU

Settlement Boundaries Methodology North Northumberland Coast Neighbourhood Plan (August 2016)

8.0 Design and Form of Development 43/

SUBJECT: GO Station Mobility Hubs Preferred Concepts: Aldershot GO, Burlington GO and Appleby GO. Planning and Development Committee - Public Meeting

WELCOME. North East Haverhill. The Planning Process

9 Pershore. Introduction. Pershore Abbey

Cotswolds AONB Landscape Strategy and Guidelines. June 2016

Copyright Nigel Deeley and licensed for reuse under this Creative Commons Licence

STATEMENT OF OBJECTION TO THE PROPOSED DEVELOPMENT OF LAND AT CHURCH CLIFF DRIVE FILEY

Examination of South Cambridgeshire Local Plan

Transcription:

HAYLE NEIGHBOURHOOD PLAN FUTURE HOUSING EXPANSION VISION DOCUMENT Prepared for Hayle Neighbourhood Plan Steering Group by AECOM December 2015

1. Introduction Context Hayle is a linear town situated in the St. Ives Bay estuary in West Cornwall. Its unique natural landscape features makes it a popular tourist destination and ongoing waterfront development aims to enhance its local economy. The town is valued for its industrial heritage and its World Heritage Site which covers most of Hayle s urban area stretching along its waterfront. Hayle benefits from rail, road and harbour connections, with one major road cutting through the town and the A30 by-pass running to the southern edge. To set expectations for applicants on the standards of development to be expected; To understand the infrastructure requirements and possibilities relating to different levels of growth; and To provide some images that can be used to engage with the community. Process Through the Department of Communities and Local Government neighbourhood planning programme, AECOM has been commissioned to help Hayle Town Council to explore some of the masterplanning issues relating to the growth of the town. The following steps were undertaken to produce this report: A two-day series of site visits and briefing meetings with members of the Town Council s Neighbourhood Plan Steering Group, culminating with an agreement of the consultant team s scope A review of the policy and evidence base pertinent to the project Urban design analysis of the potential growth sites Preparation of high level, draft vision plans, including input from planning, urban design, landscape design, transport and infrastructure specialists Comments made by the steering group and Cornwall Council A follow-up meeting with the steering group and Cornwall Council to discuss the plans Updating of plans, to take account of comments received and also an emerging updated housing requirement, and production of this report. Current housing shortage is putting pressure on the town to expand and especially to provide affordable housing. Whilst brownfield development opportunities are being exploited and are already subject to development proposals, the relatively limited supply of brownfield sites makes the agricultural land between the town boundary and the A30 by-pass being the preferred option for future development. Aims This report considers, at a very strategic level, the form that development of this land to the south of the current built-up area might take. Its aims are: To provide further evidence base to the Hayle Neighbourhood Plan, specifically content on sustainable development; To illustrate the form that any new development on the edge of Hayle may take; To contribute to ensuring that new development is considered in a co-ordinated and strategic way; N Aerial view 1

2

2. Context - how many homes and where? How many homes should Hayle plan for? The number of homes that Hayle needs to plan for in the period up to 2030 is defined by the Cornwall Local Plan. The Plan was submitted for examination in February 2015 (but suspended on 6th July 2015) and will act as the key planning policy document within Cornwall once adopted, setting the overall vision and policies for development in the unitary authority. Proposed changes are currently being considered for the Local Plan, which will undergo consultation in early 2016. The suspended Cornwall Local Plan does carry significant weight as an emerging document that has been subject to significant consultation. Proposed changes for consultation in 2016 include changes made to Policy 2a Key targets, due to Inspector comments to provide additional certainty regarding delivery in each Community Network Area (CNA), to deliver 52,500 homes over the plan period at an average rate of about 2,625 per year to 2030. This provision of new housing of appropriate types to meet future requirements, and in particular to meet affordable housing needs, includes a Housing Allocation of 1,600 new homes for Hayle. This is an increase in of 200 from the previously submitted plan. How many homes should Hayle plan for outside the existing built-up area? As noted above, 1600 new homes for Hayle are proposed in emerging Local Plan. Almost 1000 of these homes are already in the planning pipeline on urban sites, most notably at the Hayle Harbour development. After these are taken account of, the need for 650 dwellings remains. An allowance can also be made for windfall sites coming forward. These are sites in the town that will become available but are not currently in the Local Plan. After this windfall allowance is considered, space for 350-400 homes needs to found outside the existing built-up area. Where should the new homes be planned for? Considerable thought has been given to the question of where new housing might be built outside the existing built up area, once all urban opportunities are taken up. As well as the studies around the Local Plan, this has most recently insert included the Hayle plan Town Framework, here again led by Cornwall Council but including a level of community input and including an Urban Extension Assessment that considered landscape assessment, urban design, heritage and access. The wider evidence base is usefully collated and summarised in a series of reports prepared to input into the neighbourhood planning process, such as Hayle Neighbourhood Plan Evidence Report 1 (Paul Weston, May 2014) and Considering Development Potential and Options for Allocating Development Sites in Hayle (Stuart Todd, May 2014). The analysis to date, including work undertaken the Town Council, is clear that an urban extension into land between the southern edge of the builtup area and the A30 is the most suitable location for an urban extension. We would concur that environmental, heritage, landscape sensitivities and the desire to avoid coalescence of settlements makes this the only reasonable option for growth. This land is the study area for this report. Housing along Hayle Terrace Holiday homes in Phillack Housing in the Mill Pond area 3

How much land is needed and what form should new development take? The plans in this report make high level recommendations on which land should be considered for development and how it should be designed. We consider this in two phases: Phase 1 makes broad recommendations on how 400 homes might be accommodated on the edge of Hayle. The vision plan includes advice on which land might be used for housing and green infrastructure (open space, play space, pitches, allotments), density, access and structure. It is similar to Cornwall Council s work. For access, heritage, environmental and landscape reasons, it focuses development towards the eastern end of the study area. demonstrating the form and extent that growth may take if the decision in taken at some point over the coming decades that it is desirable, and a recognition that any growth of the town at this point must be strategically planned, not ad-hoc. A note on current planning applications There are a number of planning applications in the study area. This report does not pre-judge those and, as such, is not influenced by those that have not been granted or refused at the time of writing. However, the report illustrates how those applications that fit the Town Council s vision can be accommodated. The vision in phase 2 is blue-sky thinking about what might happen beyond 2030. It is an early attempt to demonstrate a suitable way for the town to grow in the longer term, but importantly shows how development in the current plan period fits into a wider strategic framework. Again, it promotes the view that development in the eastern section of the study area is most appropriate (for the same reasons as above); it is hoped that proposals that do not adhere to this vision will be resisted. Phase 2 shows how up to a total of 850 homes might be accommodated. Development on this scale would impact on the character and functioning of the town in both positive and negative ways. The positives include increasing the viability of new community infrastructure, such as a school, and a new junction from the A30 to help to address existing traffic issues within Hayle, and providing custom for local business. It is important, however, not to read this exercise as endorsement of growth on this scale it is simply Views from the study area 4

3. Site analysis This section gives a brief overview of the analysis undertaken, with particular attention to issues surrounding the proposed area for the urban extension. The two distinct town centres - Copperhouse and the Foundry - are both located close to the site with only the Foundry being earmarked for future employment and commercial growth. Hayle also benefits from social facilities including a number of primary schools, a secondary school and a hospital. Heritage assets were also taken into consideration due to the site s proximity to the World Heritage Site area and a number of listed buildings, which call for a sensitive approach to future expansion. The northern part of the study area is bounded by the rail viaduct while the A30 bypass bounds the southern edge. Although there is a natural green buffer along this side of the site, traffic noise can still be heard at certain locations. The elevated nature of the site provides attractive views from strategic points towards the sea and the adjacent countryside, as well as neighbouring towns such as St. Ives. The study area boundary also includes recently developed residential units along Trevassack Hill and football pitches situated along Viaduct Hill. 1 Public right of way from rail station to the town centre 3 2 Hayle town centre - Foundry 4 There is also pressure on the existing road infrastructure especially since heavy vehicles have to drive through Hayle Terrace for deliveries and servicing because the town s gateway junctions are at either ends of the town and there is no intermediate connection to the A30 by-pass. This calls for a major junction improvement at the point where Mellanear Road overpasses the A30 - known as the Tolroy junction. With regards to pedestrian and cycling accessibility, it was noticed from our site visit that although the hilly terrain of the area, Hayle is a very compact town with public footpaths connecting the train station to the Foundry town centre and to the rest of the town. A30 from Strawberry Lane 5 Public footpath and cycle network signs 6 The valley leading to the estuary, known as Mill Pond area, provides a mixture of historical and ecological features, protected due to their added scientific value. This ecological trail is also a functional flood plain and a green asset to the town. The study area comprises of agricultural land with public rights of way linking to the existing local roads. Harvey s Foundry View from the study area 5

4 1 2 3 6 5 0 100 500m 1km Hayle: Site analysis plan 6

4. Vision plan Phase 1 The plan illustrates the first phase of the proposed strategic development on the edge of Hayle. The following opportunities for consideration in the Neighbourhood Plan promote the town expansion in a sustainable manner, with improved access and enhanced green infrastructure to create a high-quality environment for current and future residents. Residential development to house 400 dwellings at a density of 30 dwellings per hectare. This density was chosen to integrate future development with that found in the adjacent residential areas while preserving the openness of the site. This density also caters for onplot car parking which reduces the need for communal off-street parking. Detailed housing design should be in accordance with the Cornwall Design Guide to ensure best architectural and urban design. Access to the site at this stage is provided by and from the existing roads, with new routes cutting through the proposed residential parcels. These should also provide space for green verges, bicycle lanes and adequate carriage width to allow for a maximum of 20mph vehicular speed. The provision of open space as recommended by the Open Space Strategy for Larger Towns in Cornwall (adopted July 2014), will include a variety of parks, amenity space and natural areas, with facilities catering for all age groups and. Allotments areas will enhance the health and well-being of the site and make the are more liveable. The existing sports fields along Viaduct Hill were retained and extended to the south side of the road, in accordance with the increased residential units. 7

Phase 2 The proposed Phase 1 framework could sit within a longer term strategy shown in the Phase 2 plan. As drawn here, this comprises of: The provision of up to 850 housing units, calculated on the basis of the open space requirements to provide the maximum residential density on the given area. New residential development which respects the existing urban grain and distances where it backs with existing housing. The introduction of a new primary school (2.75ha) which is justified by the increased population. The location of the school was chosen to have direct access onto Strawberry Lane to minimise the risk of adding vehicular traffic loads onto residential roads. New road junction at Tolroy intersection to take account of the wider traffic objectives. Added public open space areas to enhance the existing openness of the site and provide a functional green network which improves biodiversity as well as a more pleasant environment. Internal routes which connects to the one already developed in Phase 1 and to the existing road infrastructure. A new access from High Lanes will also provides a new gateway to the new development. 8

Project Role Name Position Actions Summary Signature Date Researcher(s) Jessica Sammut Urban Designer Research and drawings Jessica Sammut 24.08.2015 Project Manager / Technical Specialist Niltay Tosun Senior Urban Designer Designer Revisions Niltay Tosun 08.10.2015 Director/QA Ben Castell Technical Director Approval of document Ben Castell 6.11.2015 Qualifying Body Technical Specialist Mill Hill Neighbourhood Forum Niltay Tosun Senior Urban Designer Jessica Sammut Urban Designer Submitted the comments 08.10.2015 Final report insert plan Niltay Tosun here 04.12.2015 Jessica Sammut Project Coordinator Rob Kyle Neighbourhood Planning Coordinator Rob Kyle 04.12.2015 Limitations AECOM Infrastructure & Environment UK Limited ( AECOM ) has prepared this Report for the sole use of Hayle Neighbourhood Plan Steering Group (NPSG) in accordance with the Agreement under which our services were performed. No other warranty, expressed or implied, is made as to the professional advice included in this Report or any other services provided by AECOM. Where the conclusions and recommendations contained in this Report are based upon information provided by others it is upon the assumption that all relevant information has been provided by those parties from whom it has been requested and that such information is accurate. Information obtained by AECOM has not been independently verified by AECOM, unless otherwise stated in the Report. The methodology adopted and the sources of information used by AECOM in providing its services are outlined in this Report. The work described in this Report was undertaken in the period August 2015 to December 2015 and is based on the conditions encountered and the information available during the said period of time. The scope of this Report and the services are accordingly factually limited by these circumstances. Where assessments of works or costs identified in this Report are made, such assessments are based upon the information available at the time and where appropriate are subject to further investigations or information which may become available. AECOM disclaim any undertaking or obligation to advise any person of any change in any matter affecting the Report, which may come or be brought to AECOM s attention after the date of the Report. Certain statements made in the Report that are not historical facts may constitute estimates, projections or other forward-looking statements and even though they are based on reasonable assumptions as of the date of the Report, such forward-looking statements by their nature involve risks and uncertainties that could cause actual results to differ materially from the results predicted. AECOM specifically does not guarantee or warrant any estimate or projections contained in this Report. Where field investigations are carried out, these have been restricted to a level of detail required to meet the stated objectives of the services. The results of any measurements taken may vary spatially or with time and further confirmatory measurements should be made after any significant delay in issuing this Report. Copyright This Report is the copyright of AECOM Infrastructure & Environment UK Limited. Any unauthorised reproduction or usage by any person other than the addressee is strictly prohibited. 9

insert plan here