City of Jersey City. Department of Administration Division of Engineering Traffic and Transportation

Similar documents
HUDSON COUNTY URBAN ENTERPRISE ZONE PROGRAMS

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

TOWNSHIP OF HOWELL TOWNSHIP OF HOWELL ENGINEERING PROJECTS STATUS REPORT OCTOBER 19, Resurfacing of Aldrich Road West Contract # 11-06

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

Construction Engineering & Inspection

Spring 2018 Construction Update

Public Works Project Delivery Report

FY 2005 TRANSPORTATION CAPITAL PROGRAM

Chris Gent Landscape Studio

FY Capital Improvement Program Arroyo Projects - Central Arroyo Summary

City of Kearney Capital Improvement Update October 1, TH STREET AND 17TH AVENUE IMPROVEMENTS

2040 Long Range Transportation Plan

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

PROJECTS UNDER CONSTRUCTION

Capital Projects impacting Odenton Town Center

THREE-YEAR CAPITAL IMPROVEMENT PLAN FY

Municipality of Anchorage. Community Council Survey Capital Projects Needs Ranking Survey (ALPHABETICAL) Airport Heights

Interstate Traffic Interruptions Weekend of Oct 9, 2015-Oct 12, 2015

Phone: (856) Providing you with the Fax #: (856) tools you need to grow. your business!

Knoxville Area Transit (KAT) Transit Development Plan Corridor Analysis

STREET IMPROVEMENT AND MAINTENANCE PROGRAMS

Transportation Projects Quarterly Report. Morrisville Planning Department May 22, 2018

Roads Plan

VILLAGE OF DOWNERS GROVE REPORT FOR THE VILLAGE COUNCIL MEETING SEPTEMBER 10, 2013 AGENDA

FDOT D4 Complete Streets

AGENDA ACTION ITEMS INFORMATION ITEMS

Capital Projects in and near Odenton Town Center

North Loop Paving. December 18th, Street Reconstruction Project. Forrest Hardy, Transportation Planner Minneapolis Public Works

RFP DRAINAGE OUTFALL DESIGN AND PERMITTING. Mandatory Meeting for Proposers August 15, 2015

Engineering Department

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

Catalyst For Economic Development Washington Park Chicago IL

Transportation Improvements

MAIN STREET RECONSTRUCTION PROJECT PRE-CONSTRUCTION PUBLIC INFORMATION SESSION AGENDA

Creative Engineering Group Inc, (Creative) Construction Engineering and Inspection (CEI) Professionals

TRANSPORTATION ELEMENT GOALS, OBJECTIVES, AND POLICIES

Maplewood Avenue Downtown Complete Street Project

Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL

Burlington Enhancement Plan

TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 No Projects US-19E Under Development in Carter County

Fall 2017 Construction Update

Marion Street Green Infrastructure Project. Whittier Neighborhood Community Meeting April 18, 2018

CITY COUNCIL STAFF REPORT

Corridor Investment Projects (FY FY2012)

Complete Streets Master Plan for Downtown New Britain CRCOG Transportation Committee Meeting Monday, December 9, 2013

PUBLIC HEARING. DRAFT Environmental Impact Statement. Matthews Memorial Baptist Church Washington, DC October 18, National Capital Region

John F. Kennedy STEM High School Green Infrastructure Information Sheet

BENJAMIN BANNEKER PARK FRAMEWORK PLAN (PLAN ADOPTION)

March 1, PWG Meeting #4

#8) T-1409 CENTENNIAL & LAMB TENTATIVE MAP

Transportation Alternatives Program (TAP) Experience

Revised Long Range Transportation Plan

Long Branch-Wayne Local Park Renovation Project

TOWNSHIP OF HOWELL TOWNSHIP OF HOWELL ENGINEERING PROJECTS STATUS REPORT OCTOBER 30, 2015 A. MUNICIPAL CAPITAL PROJECTS

Pine Avenue Improvement Project

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

Sacramento County - Department of Transportation

Community-Based Green Infrastructure Initiative for New Jersey

ARROYO PROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET

TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 US-19E No Projects Under Development in Carter County

Expo Line Transit Project. Project Status Update Meeting West End Corridor Segment C

Table of Contents. Elm Avenue Improvement Plan City of Waco, Texas. Introduction 1. Existing Context 1 Figure 1 2.

TOWNSHIP OF HOWELL DEPARTMENT OF COMMUNITY DEVELOPMENT & LAND USE

HUDSON RIVER WATERFRONT. Hudson River Waterfront Walkway

Borderland Expressway Coalition Status Report Camino Real RMA Board Meeting. El Paso, TX April 11, 2018

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

Phone: (856) Providing you with the Fax #: (856) tools you need to grow your business!

City of Jersey City. New Jersey s Long-Range Transportation Plan. For Public Discussion URBAN SUPPLEMENT REPORT. September 2008

Community-based Green Infrastructure Initiative in New Jersey

2018 Capital Improvements Report

The Community and Transportation Linkage Planning Program

Blue Line LRT Extension

HARBOR BRIDGE. Randall C. Grones, PE - SPD. US 181 Harbor Bridge October

Special Revenue Funds

Somers Point Master Plan

Highway 417 Expansion East

II PREVIOUS REPORTS PERTINENT TO THIS MATTER II

Construction Projects Report

2017 Capital Improvements Report

San Francisco DPW Construction Contract Awards (FY 09-10)

Subareas 9 & 10 Master Plan Updates

Abbott Loop. Community Council Survey Capital Projects Needs Ranking Survey. Comm Council Priority Rank. Rank # ABBOTT LOOP COMMUNITY PARK

MPRD s Keith Mione (Community) Park Midlothian Road Entrance Traffic Signals

Construction Engineering & Inspection Services Transit Bus Stop Infrastructure for the Broward County Transit Division (BCT)

METRO Gold Line BRT CBAC Meeting. August 23, 2018

EXHIBIT A 2019 FINANCING: PROJECT AUTHORIZATIONS

I-70/71 Innerbelt Project

Construction Projects Report

Construction Projects Report

Johnson Street Bridge Public Realm Update

Building Great Neighbourhoods LAURIER HEIGHTS

SR 916/NW/NE 135 Street Public Hearing

CITY OF MANHATTAN BEACH STAFF REPORT. THROUGH: Marisa Lundstedt, Director of Community Development

Retailer Address City

Community-Based Green Infrastructure Initiative for New Jersey

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FOR IMMEDIATE RELEASE DATE: FRIDAY, AUGUST 31, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?

Weekly Activity Log. About Cutting Edge Landscaping Ltd. and their services:

Construction Contract A47CN01: Wollaston Station Improvements and Quincy Center Garage Demolition. June 2017

Transit Implementation Strategy Westside Study Group Meeting

Transcription:

Division of Engineering Traffic and Transportation : Duncan Avenue Road Program Bergen Avenue Road Program PSE&G Gas System Modernization Program NJDOT Municipal Aid FY2015 Road Program Ogden Dog Park Dr. Martin Luther King Jr. Drive Road Program Capital Improvement Resurfacing Miscellaneous Line Restriping

Duncan Avenue Road Program Start: April 2018 Projected End: October 2018 Duncan Avenue from Route 1&9 to Hackensack River. Jersey City, Jersey City Municipal Utilities Authority (JCMUA), Hudson County; $1.7M Scope of Work: The Duncan Avenue Road Program aims to resurface Duncan Avenue from Route 1&9 west to the Hackensack River. It is funded by Jersey City, JCMUA, and Hudson County.

Bergen Avenue Road Program Start: May 2018 Projected End: November 2018 Bergen Avenue from John F. Kennedy Boulevard to Communipaw Avenue Community Development Block Grant (CDBG); $1.5M Scope of Work: The Bergen Avenue Road Program aims to resurface Bergen Avenue from John F. Kennedy Boulevard to Communipaw Avenue. This project also includes curb ramp reconstruction at all corners, replacement and resetting of castings, drainage improvements, signage upgrades, etc.

PSE&G Gas System Modernization Program Start: May 2018 Projected End: October 2018 Various locations (see maps) PSE&G; $10M Scope of Work: As part of its Gas System Modernization Program (GSMP), PSE&G has been repairing and replacing gas utilities throughout the City and repaving streets curb to centerline or curb to curb. This project also includes curb ramp reconstruction at all corners, replacement and resetting of castings, drainage improvements, signage upgrades, etc. By completion of the project, PSE&G will have updated six miles of gas infrastructure, completed 80,000 square yards of paving, and invested approximately $10 million toward upgrades. The City is overseeing this work and coordinating construction and traffic aspects, per City ordinance.

NJDOT Municipal Aid FY2015 Road Program Start: June 2018 Projected End: November 2018 Academy Street from Van Reypan Street to Mill Road Mill Road from Academy Street to Montgomery Street Wayne Street from Gray Street to Cornelison Avenue Cornelison Avenue from Wayne Street to Summit Avenue NJ Department of Transportation (NJDOT) Municipal Aid; $1.6M Scope of Work: The NJ Department of Transportation (NJDOT) Municipal Aid FY2015 Road Program aims to resurface the above streets surrounding McGinley Square. This project also includes curb ramp reconstruction at all corners, replacement and resetting of castings, drainage improvements, signage upgrades, etc.

Ogden Dog Park Start: July 2018 Near 105 Odgen Avenue, next to Janet Moore Park Projected End: Ribbon cutting ceremony to be held on August 23, 2018 Jersey City Scope of Work: Ogden Dog Park is the newest dog park in Jersey City. It is entirely fenced in and features a canine turf surface, which is dog friendly, antimicrobial, and antifungal. Layers of stone under the turf allow for efficient drainage and easy cleaning with minimal maintenance required. Plumbing was added to give the adjacent garden access to water and facilitate the addition of a two-tiered drinking fountain for both dogs and humans. Additional amenities include benches and a dog post with waste bags and a receptacle.

Dr. Martin Luther King Jr. Drive Road Program Start: August 2018 Projected End: July 2019 Dr. Martin Luther King Jr. Drive from McAdoo Avenue to Communipaw Avenue NJ Department of Transportation (NJDOT) Municipal Air, Federal Highway Administration (FHWA); $1.9M Scope of Work: The Dr. Martin Luther King Jr. Drive Road Program aims to resurface Dr. Martin Luther King Jr. Drive from McAdoo Avenue to Communipaw Avenue. This project also includes curb ramp reconstruction at all corners, replacement and resetting of castings, drainage improvements, signage upgrades, etc.

Capital Improvement Resurfacing Ward Street From To A B C D E F Cator Avenue Old Bergen Road JFK Blvd. Cator Avenue Princeton Avenue Ocean Ave. Glenn Lane West Side Avenue Stevens Avenue Service Road West Side Avenue Stevens Avenue Stegman Street JFK Blvd. Bergen Ave MacAdoo West Side Avenue Spring St Custer Ave. JFK Blvd. North End Emerson Avenue Logan Avenue Sip Avenue Jewett Ave Westside Ave. JFK Blvd Duncan Avenue Rt. 440 Westside Ave. Bryant Avenue Sip Avenue Dead End Britton Street Montgomery St Fairmount Ave Wales Avenue Broadway Fayette Place Westview Ct Broadman Pkwy Culver Ave Abbett St. Booraem Ave Ferry St Booraem Ave Palisade Ave. Abbett St. Sherman Ave Ferry St Franklin St Waverly St Palisade Ave. Central Ave Hopkins Avenue Baldwin Ave. Palisade Ave. Garrison Ave. Sip Avenue Tonnelle Ave Elm St. Dead End JFK Blvd. Hutton St. Sherman Ave Palisade Ave. Summit Ave. Grace St. Secaucus Road Sherman Ave Franklin St. Congress St Mountain Rd. Griffith St. South End Reserve Ave. Western Ave. End Newport Parkway Washington Blvd River Drive 1st Street Marin Blvd. Provost St. 1st Street Brunswick St Merseles Street 9th Street Erie Street Marin Blvd. Merseles Street 3rd St 2nd St 18th St. Grove St. Marin Blvd. Jersey Ave 6th St. 8th St 8th St Erie Street Coles Pavonia Avenue Erie Street Manila Ave Summit Ave Clifton Place Montgomery St Rose Avenue Grant Avenue Orient Avenue Union St. Ocean Ave. Clerk St. Union St. MLK Blvd Ocean Ave. Caven Point Ave Garfield Ave Pacific Ave Claremont Ave. Randolph Ave. Garfield Ave. Forrest St Pacific Ave. Halladay St Bright Street Florence St Merseles St Garfield Avenue Bayview Avenue Wilkinson Avenue Various locations (see map) Start: September 2018 Projected End: September 2019 Jersey City; $4M Scope of Work: The Capital Improvement Resurfacing program aims to resurface the locations shown in the above map. Milling and paving limits were determined by grading of all roads. This project also includes curb ramp reconstruction at all corners, replacement and resetting of castings, drainage improvements, signage upgrades, etc.

Miscellaneous Line Restriping Various locations Start: May 2018 Projected End: On-going until funds are fully utilized Jersey City; $1.1M Scope of Work: This open contract is used on an as-needed basis when the City identifies locations where various issues require restriping, including crosswalks, no parking zones, parking stalls, driving lanes, etc.