Preliminary Operations and Maintenance Plan Baron Winds Project

Similar documents
Site Security Plan - Operations Baron Winds Project

Preliminary Site Security Plan Operations Cassadaga Wind Farm

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

Conditions for the provision of services Valid from 1 November only for the Jablotron Alarms series of alarms

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

Michigan State University Construction Standards COMMISSIONING OF FIRE ALARM SYSTEMS PAGE

QUALITY ASSURANCE SURVEILLANCE PLAN (QASP) INTRODUCTION

CONDITIONS OF SERVICE - NBN SERVICES 1. ABOUT

Pebble Beach Community Services District

Specialists at your service

KELTRON LS 7000 ALARM MANAGEMENT SYSTEM Keltron Alarm Monitoring, Dispatch, and Reporting Software

DTW Master Specification Section EMCS: Start Up, Verification and Commissioning

SolarPower Europe O&M Task Force

PART 3-O REQUIREMENTS FOR SPRINKLER SYSTEMS MAINTENANCE AND SUPERVISION. 3-O Introduction O.1 Scope of Maintenance and Supervision...

Majis Industrial Services SAOC TENDER NO. MISCP/09/2014

Tom Miesner Principal Pipeline Knowledge & Development

Contact Phone Number: (609) Fax: (609)

PART 1 GENERAL Quality Assurance A. Fire Alarm Contractor Qualifications:

SIOUX FALLS FIRE RESCUE STRATEGIC PLAN

Branch Fire Rescue Services

I. Scope: II. Environmental Health and Safety Fire Alarm System Impairment Program - Guideline Revision Date: April, 2018

Park Board Strategic Framework. (Mission, Vision, Directions, Goals and Objectives) June 27, 2012

PART 1 GENERAL Quality Assurance A. Fire Alarm Contractor Qualifications:

Presentation Title. Subtitle (optional) Wastewater Treatment Operations. O&M Contract Procurement. Vancouver City Council Workshop/Public Hearing

FACILITY CONNECTION STANDARD

Gambling with your fire security?

Chapter 1 Introduction

"This is only the scope of work for the project. For more information, interested parties should contact Procurement at

Assetguard GDM. Gas density Monitoring for Gas Insulated Switchgears

Initial Version Revision No. 0 Next Review Date: Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6

Public Notice of Amendment to New Shoreham General Ordinances Chapter 5 Fire Prevention and Protection New Article IV Fire Alarm Ordinance

CARD ACCESS CONTROL SYSTEM

S T A T E O F F L O R I D A D E P A R T M E N T O F J U V E N I L E J U S T I C E BUREAU OF MONITORING AND QUALITY IMPROVEMENT PROGRAM REPORT FOR

A. Introduction 1. Title: Transmission and Generation Protection System Maintenance and Testing

A safe journey with Dräger CRUISE CATALOGUE

TABLE OF CONTENTS. Tender Forms Letter of Tender A20 Appendix to Tender A20 A20 Contract Agreement A20

SECTION SECURITY TESTING AND COMMISSIONING

i-con Switchgear Condition Monitoring HV Switchgear Integrated Substation Condition Monitoring ISCM Answers for Infrastructure & Cities.

APPENDIX 4J SECURITY AND SURVEILLANCE SERVICES

GUIDELINES TO SHOP COMPLIANCE

S T A T E O F F L O R I D A D E P A R T M E N T O F J U V E N I L E J U S T I C E BUREAU OF MONITORING AND QUALITY IMPROVEMENT PROGRAM REPORT FOR

PART 8 - Miscellaneous Services 3rd Revised Sheet 1 SECTION 8 - Other Miscellaneous Services Replacing 2nd Revised Sheet 1

"This is only the scope of work for the project. For more information, interested parties should contact Procurement at

Arc Flash Mitigation Solutions: A Proactive Approach To Arc Flash Risk

INTRODUCTION TAQQAT Global Co. Abdulla Fouad Group

Dennis Mullen System Operations Manager

1.1 DESCRIPTION A. The purpose of this section is to specify Division 23 responsibilities in the commissioning (Cx) process.

Complete solutions for commercial security. Verex delivers leading intrusion, access and video products to protect today s companies

Request for Proposals Design Services for Kitchen Remodel and Second Floor Layout

Local Rules: Fire Safety

A. Introduction 1. Title: Transmission and Generation Protection System Maintenance and Testing

DISTRIBUTION OPERATIONS AND MAINTENANCE

EC 5.10 FIRE PREVENTION MANAGEMENT

This chapter shall be known as the "City of Bayfield Alarm Systems Ordinance."

Appendix J Framework Fire Prevention and Suppression Plan. Prepared by Idaho Power Company 1221 W Idaho Street Boise, ID 83702

MODEL 5100 BROADBAND ALARM COMMUNICATOR INSTALLATION & USER S GUIDE PRODUCT ID #

New requirements for IEC best practice compliance

Classifying Forced Outages Transmission Maintenance Procedure No. 5

Distribution Control Center Operator Training

MINOOKA FIRE PROTECTION DISTRICT Fire Prevention Bureau Fire Inspector Rodney Bradberry Plan Review

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION

Installation Operation Maintenance

BURN NOTICE: KEEP THE HEAT AWAY!

PRC (I) August 9, Authored by

CAN/ULC-S561. To comply, or not to comply. actually it s not even a question! Underwriters Laboratories of Canada. By Alan Cavers & Brian McBain

Continuous, real-time detection, alarming and analysis of partial discharge events

Standard PRC Transmission Relay Loadability

Electrical Safety Policy and Management System

Subject: Fire Protection Impairment Program Reference: NFPA (see bottom of page 5) Effective Date: August 2014 Distribution All YC Employees

Pre-seen case study for Strategic level examinations Papers E3, P3 and F3. For examinations in May 2014 and September 2014

Spectron LSN (Life Safety Network) Suggested Specifications

BCGEU JOB DESCRIPTION MINISTRY OF FORESTS

FIRE DEPARTMENT FIRE CHIEF. Deputy Fire Chief Operations Section. Assistant Fire Chief Planning & Budget Section

Emergency Action Fire Prevention Plan

What Utility Analytics means to Exelon

Nova Scotia Fire Dispatch Minimum Standards (2017)

Relay Performance Index for a Sustainable Relay Replacement Program

CENTRAL STATE HOSPITAL PLAN PLANT OPERATIONS UTILITIES MANAGEMENT PLAN

The smart alternative

1.3 REFERENCE STANDARDS

Remote Pump Monitoring

Enhancing Current Maintenance Practices 04. Managing the Risk 06. Constant Monitoring of Electrical Enclosures 08

COILED TUBING SERVICES & SOLUTIONS

Z-GROUP 3 Business Units Until end 2011

New York s Electric Reliability Monitoring Utility Performance

THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF LEE LAJOIE AND BRIAN DICKIE

COOPER POWER SERIES. S.T.A.R. TM Fiber optic cable installation instructions. Fault Indicators MN320004EN. Fiber optic fitting (To led display)

Stationary Engineer 11 Month (Non-Exempt) HVAC - Maintenance Assistant Manager or Designee

1. Floor above/floor below notification. 2. Private alarm notification. 3. Not Used 4. Voice alarm notification. 5. Not Used.

Fire Prevention and Emergency Preparedness Plan for Black Oak Wind Farm

Users Manual. LAURUS Systems, Inc. - Ph: Fax:

Sustain.Ability. Alarm Management: Be Pro-active, not Re-active Honeywell Users Group Europe, Middle East and Africa. Tyron Vardy, Honeywell

IoT use cases for smart building. IoT is changing the way facility management, security and construction companies are operating.

Building Self-Inspection Program

Tysons Circulator Study: Process and Preliminary Results Summary. March 2012

FIRE PREVENTION PLAN EMERGENCY ACTION

Fire Smoke Damper Actuator Replacements SECTION COMMISSIONING OF HVAC

FIRE SAFETY MANAGEMENT PLAN

GPS-based Dig-In Prevention System. Gas Technology Institute and PG&E August 8 th 2017

Transcription:

Preliminary Operations and Maintenance Plan Baron Winds Project August 2017

Table of Contents 1. Introduction... 3 2. O&M Philosophy and Process... 3 3. Typical O&M Responsibilities and Maintenance Schedules... 4 3.1. Turbines... 4 3.2. Balance of Plant Components... 4 4. Training and Notifications... 5 Appendix A... 7

1. Introduction An Operations and Maintenance Plan is a project-specific plan that is typically created based on the specific turbine selected, the turbine manufacturer, and other project-specific considerations. This preliminary Operations and Maintenance Plan ( O&M Plan ) is intended to be the foundation of the final O&M Plan that will be implemented at the Baron Winds Project (the Project ) once it becomes operational and reflects typical O&M maintenance requirements based on EverPower s experience. EverPower s employees at the Project ( Project Operators ) will be responsible for the Plan s implementation. The objective of the Plan is to optimize the Facility s operational capacity and availability through best in class maintenance guidelines and inspections that are designed to pro-actively detect any significant safety or maintenance issues. 2. O&M Philosophy and Process EverPower has an operational philosophy and process that forms the overarching goals and objectives of its operations. This philosophy and process includes: Best in Class o Safety, First and Foremost o Continuous safety and technical training o Community and environment stewardship o High fleet availability that translates into strong production o Proactive management minimizing Mean Time Between Failure (MTBF) o Technical library that is comprehensive and up to-date o Wind Turbine Generators (WTGs) are maintained to the highest industry standards Taking Ownership o Holistic approach to project operations that entails working closely with stakeholders including turbine maintenance providers, Balance of Plant (BOP) providers, utilities, state agencies and local communities o Technical oversight of turbine manufacturers teams on a day-to-day basis o Contract compliance o Ensure critical BOP infrastructure is well maintained o Technical and Safety Audits Asset Optimization o Real-time performance monitoring via control center o Internal supervisory control and data acquisition (SCADA) system that converts turbine manfacturers SCADAs to a common platform o What we want to improve, we need to measure Maximize revenues and enhance performance Standardization of performance metrics for the entire fleet Validation of actual production levels regardless of under- or overproduction Validation of wind energy models to real asset performance Site manager bonus incentives tied to specific performance indicators o Lightning detecting program to reduce major damage o Anomaly Detection Algorithm thousands of data points monitored

o Feedback loop to site managers 3. Typical O&M Responsibilities and Maintenance Schedules Wind energy projects typically consist of multiple wind-to-energy generators that are electrically connected together to produce the desired project output. Each of these stand-alone generators requires periodic preventive maintenance as well as corrective maintenance in the event of a malfunction within the individual generator. In addition, the collection system that ties the generators together, as well as the substation that steps up voltage for delivery to the bulk electric system, require periodic maintenance. 3.1. Turbines Each individual WTG typically requires preventive maintenance semi-annually. One of these maintenance outages is typically designated as minor scheduled maintenance and is completed in one working day per unit. The other is major scheduled maintenance and usually takes one to two working days to complete. For a typical wind energy facility, each semi-annual maintenance cycle is scheduled to be performed outside of high-wind season (usually spring or fall) and a crew or crews will work on individual units until the entire project maintenance cycle is completed. Depending on the size of the project, each maintenance cycle typically lasts for about two months for the entire project. On any given day during the maintenance cycle, one or more WTGs is taken out of service for scheduled maintenance, typically no more than five percent of the project s generating capacity. EverPower is an experienced manager of turbine services and has five different turbine suppliers under long-term service agreements. Turbine EverPower O&M responsibilities and contracting typically include: a. Ensure Turbine O&M service providers are fulfilling contractual obligations including but not limited to: availability guarantees, maintenance schedule, manpower requirements, turbine repairs, safety, etc. Typical contract services provided by the O&M service provider consist of an all-inclusive service (scheduled and unscheduled repairs, all parts, labor, and ancillary equipment or tooling necessary to perform the work). a. Turbine O&M service contract term is 5 years minimum b. Turbine O&M service provider staffing typically consists: a. Site Supervisor b. Administrator c. One Technician per 10 turbines c. Contract typically includes a warranty period for serial defects d. Turbine O&M service provider typically performs two scheduled services each year at 6-month intervals. This consists of replacement of consumables, torque checks, equipment testing, and housekeeping. e. Turbine O&M service provider also monitors security and safety lighting to ensure appropriate function 3.2. Balance of Plant Components

Project BOP EverPower provides O&M services for BOP components. Collection system and substation preventive maintenance activities are typically performed once a year, outside of high-wind season. Annual collection and substation maintenance usually requires the entire project to be shut down. Minor annual maintenance typically takes one to two days, while more extensive maintenance (usually performed at five-year intervals) typically takes three to four days. Project BOP EverPower s O&M responsibilities typically include: a. Oversee operations, repair and maintain BOP including, but not limited to, substation, collector system, interconnect transmission lines, roads, grounds, foundations, transformers, etc.); b. Furnish all labor (or cause to be furnished) and perform (or cause to be performed) all maintenance and repair activities, sufficient to maintain the BOP in good working condition, consistent with prudent business practices and any applicable operation and maintenance manual; c. Maintain all materials, including spare parts inventory, required to maintain the BOP in the normal course of business; d. Prepare purchase orders to procure parts, materials and supplies necessary for the operation, maintenance and repair of the projects; e. Schedule power outages and maintenance shutdowns in coordination with the turbine schedule provider(s), power purchaser(s) and transmission provider(s) to minimize revenue loss and interference with facility operations; f. Supervise, monitor and report on the operation and maintenance of interconnection facilities, in accordance with the Interconnection Agreement; g. Respond to trips as reported by the auto-dial monitoring system and provide trip reports of all faults, defects and breakdowns occurring in respect of such electrical system; h. Calibrate Power Purchaser( s) revenue meters; i. Produce monthly operating reports including turbine performance, BOP performance, safety and environmental matters, etc.; j. Coordinate and pursue all warranty and other claims against suppliers of materials and equipment to the BOP or turbines, including any claims against any insurance carrier for payment of claims, liabilities, or losses in connection with the BOP and turbines or its operation covered by such insurance, and including any litigation associated with any such claims; k. Oversee North American Electric Reliability Corporation (NERC) compliance l. Operate and maintain the projects in compliance with all governmental requirements, loan and material project documents; m. Produce and provide facility data and information requested by governmental authorities; and n. Provide SCADA overlay service, which includes tracking, trending, and internet access to Dashboard as well as record of the facility data. 4. Training and Notifications New site personnel will be oriented to the O&M Plan via a copy and review of this document in combination with their orientation to other Baron Wind policies and plans such as the Emergency Action Plan and Health and Safety Plan.

Beyond new hire orientation, the Project Operators, or the employee s direct supervisor, shall provide training in accordance with this Plan as needed to support their job function. A copy of the O&M Plan is provided to each person on site and is to be available at all times for all site personnel to review at the O&M building. If work is necessary within a public right-of-way in order to conduct maintenance in accordance with the O&M Plan, notification and any necessary work permit(s) will be discussed and obtained with the appropriate agencies prior to starting the work. During any substation maintenance visits, security lighting will be checked to ensure it is functioning appropriately.

Appendix A O&M Plan Acknowledgement Form

I have read the O&M Plan for this site and fully understand its contents. Date Name Company