Lindsay Frederick. Lighting + Electrical. Ron Dodson Faculty Advisor. Native American Cultural Center Arizona. Technical Report 2

Similar documents
Chang Liu Lighting + Electrical M.A.E./B.A.E. Integrated Degree. Technical Assignment 2 October 12, 2012 Faculty Consultants: Ron Dodson

Technical Report 2: Electrical Systems Criteria and Existing Conditions

PART 1. Executive Summary. The Frederick College of Cardiology

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

ELECTRICAL SYSTEMS ASSESSMENT Hanover High School

Executive Summary. CNBC Global Headquarters Christine Cajilig

Technical Report Two

Building Electrical System Overview

Renovate MCRC Facilities Great Lakes, IL

GARCIA GALUSKA DESOUSA Consulting Engineers

Currently, all electrical upgrades would be voluntary, but there are situations in which upgrades would be required.

Corbin Building. Technical Assignment 2. Matthew Trethaway Lighting/ Electrical AE 481W 10/26/2011 Advisor: Ted Dannerth

Introduction Consultant shall incorporate the material in the DSS into the project specifications.

SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- ELECTRICAL

Chandler City Hall Chandler, Arizona

SECTION LIGHTING CONTROLS

FIRE ALARM: BY OTHERS, IF REQUIRED.

ELECTRICAL Seminar. B A L A Consulting Engineers, Inc. Edward J. Lynch, PE Vice President, Electrical Department Manager.

Construction Management at Risk Services. New North East Branch Library Project. August 3, 2018

FIRE ALARM: BY OTHERS, IF REQUIRED.

Element D Services Electrical

TABLE OF CONTENTS CHAPTER 1 GENERAL RULES CHAPTER 2 WIRING AND PROTECTION... 51

LIGHT LEVEL REQUIREMENTS MINIMUM ACCEPTABLE FOOT CANDLES

Technical II Report Electrical Systems

NEC Requirements for Standby Power Systems. New England Building Officials Education Association Annual Conference October 5, 2015

Lord Stirling Community School Electrical Systems Existing Conditions & Building Load Summary Technical Assingment#2 Due October 26, 2004

PANELBOARDS & BUILDING DISTRIBUTION

TONY ESPOSITO LIGHTING/ELECTRICAL TECHNICAL REPORT II SEPTEMBER 15, 2011 HUNTER S POINT SOUTH INTERMEDIATE SCHOOL AND HIGH SCHOOL QUEENS, NY

UNIVERSITY OF PENNSYLVANIA NEURAL AND BEHAVIORAL SCIENCES BUILDING 415 University Ave, Philadelphia, PA 19104

Division 26 ELECTRICAL TABLE OF CONTENTS

M001. Revenue Services ISSUED FOR CONSTRUCTION SEPTEMBER. 2, East State Parkway Schaumburg, Illinois Do Not Scale Drawings

ELECTRIC SERVICE EVALUATIONS ELECTRICAL / BOILER REPLACEMENTS. Clarkstown Central School District. June Arch Proj. #

ELECTRICAL EXISTING CONDITIONS AND DESIGN ANALYSIS

Chapter 1 General... 5

Electrical System (N) PANELBOARD "L1" VOLTAGE: 208/120 A, 3P :MAIN C/B PHASE: 3 A :BUSSING WIRE: 4 :MOUNTING

Electrical Design Guidelines Table of Contents

PLATTEVILLE MIDDLE SCHOOL

NATIONAL ELECTRICAL CODE (NEC) & NFPA 70E ARC FLASH ELECTRICAL SAFETY

SECTION PANELBOARDS Painting Wire and Cable Overcurrent Protective Devices.

S AGE E NGINEERING A SSOCIATES, LLP

CHAPTER 20 SERVICE EQUIPMENT

PLAN REVIEW SUBMITTAL GUIDE

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Electrical Inspection Service & Distribution

CHAPTER 8 ELECTRICAL

SECTION LIGHTING CONTROL DEVICES

INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION

Integrated Solutions. Simple and flexible designs for space and time savings

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District

CHAPTER 8 ELECTRICAL

TABLE LIGHTING POWER DENSITIES FOR BUILDING EXTERIORS ASHRAE Uncovered Parking Areas. Building Grounds. Walkways 10 feet wide or greater

The following narrative outlines a conceptual electrical Scope of Work for converting the Phase 2 TRW Building to an Exhibition Hall.

ELECTRICAL DESIGN BRIEF

A. This Section includes the following lighting control devices:

A. Product Data: For each electrical identification product indicated. B. Comply with 29 CFR and 29 CFR

UltraLITE. Centralized Emergency Lighting Inverters MODEL ELU

Building Division 201 SE 3 rd STREET (Second Floor) OCALA, FL Phone: (352) BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS

ELECTRICAL SYMBOLS AND ABBREVIATIONS NOT ALL SYMBOLS, DEVICES OR ABBREVIATIONS MAY BE USED

UltraLITE MODEL ELU. Centralized Emergency Lighting Inverters

Appendix B. Facilities Assessment Report

COMMON WORK RESULTS FOR ELECTRICAL: Basic Electrical Materials Methods

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

TABLE OF CONTENTS GENERAL... 2 A. DEFINITIONS DIGITAL, ADDRESSABLE FIRE ALARM SYSTEM... 2

CITY OF LOS ANGELES LARUCP ELECTRICAL PLAN CHECK LIST

Chapter 1 General...9 Article 100 Definitions...11 Article 100 Questions Article 110 Requirements for Electrical Installations...

ELECTRICAL POWER SYSTEMS

IMPORTANT NOTICE BUILDERS AND CONTRACTORS WORKING IN NORTH RICHLAND HILLS, TEXAS. June 17th, 2016

TABLE OF CONTENTS CHAPTER 2 WIRING AND PROTECTION CHAPTER 1 GENERAL RULES... 19


Technical Report #2. Newseum and Freedom Forum Headquarters. Washington, D.C. Ryan Wise Lighting/Electrical Prof. Dannerth November 2, 2007

A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards.

White Paper SPDs for Essential Power Systems in Health Care Facilities

PART GENERAL 1.01 SECTION INCLUDES

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

TOM BURNS, PLANNING DIRECTOR

SECTION ISOLATED POWER SYSTEMS

DIVISION 28 ELECTRONIC SAFETY AND SECURITY

SECTION ELECTRICAL IDENTIFICATION

Student Services & Classroom Addition. A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards.

Air Flow Diagram. Orange County Sanitation District SP-194 Section 05 Conceptual Design

5.17 Electrical Systems

SECTION 2 NEC REFERENCES SECTION 1 LOW-VOLTAGE AND POWER- LIMITED SYSTEMS...1. CHAPTER 1 GENERAL Introduction...35

NYC Department of Education

A. This Section includes the following lighting control devices:

FOR LEASE ROCKWOOD OFFICE PARK

Town of Cicero Local Code Amendments

SECTION EMERGENCY POWER SYSTEMS

F. GENERAL REQUIREMENTS Electrical Design Criteria 2006 Edition 4/3/06 School District Palm Beach County Page-1 of 15

F. GENERAL REQUIREMENTS Electrical Design Criteria 2009 Edition 11/23/2009 School District Palm Beach County Page-1 of 17

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

DEMOLITION GENERAL NOTES As-built conditions have been determined from Record Drawings (if they exist), field investigations (accessible areas and

SECTION AUTOMATIC TRANSFER SWITCHES

OPERATIONS AND STORAGE BUILDING

A. Shop Drawing submittals shall include, but not be limited to, the following:

State College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT

NYC Department of Education

Technical Report #3 Mechanical Systems Existing Conditions Evaluation

Existing Building Electrical Systems Description

SECTION GENERATOR PARALLELING CONTROLS

Transcription:

Lindsay Frederick Lighting + Electrical Ron Dodson Faculty Advisor Native American Cultural Center Arizona Technical Report 2

Native American Cultural Center Technical Report 2 p. 2 Executive Summary The Native American Cultural Center in Arizona is a 48,000 sf facility created for tribe members and visitors to learn about the culture and heritage of the Arizona tribe. The electrical design is based on cost-savings and efficiency. The following report determines the criteria for the electrical system, examines the existing design, and explores alternative solutions. The nature of its function as a cultural center determined the criteria. The Cultural Center has short and specific operating hours of occupancy. It contains no important data or data storage and no important special equipment that relates to life-safety. The engineers at SmithGroupJJR created a practical design that meets code and is sensitive to both initial costs and long term costs. The analysis determined that, even with the other options available, the design from SmithGroupJJR is the best alternative for the Tribe.

Native American Cultural Center Technical Report 2 p. 3 Table of Contents Executive Summary... 2 Electrical Systems Criteria... 5 Electrical Load Estimate... 5 Arizona Public Service Rate Schedule... 5 Building Utilization Voltages... 6 Emergency Power Requirements... 6 IBC... 6 NEC... 6 Special Occupancy Requirements... 6 Special Equipment... 7 Priority List for Electrical System Design... 7 Loads with Optional Back-up Power... 7 Special/Communications Building Systems... 7 Special/Communications Service to Building... 7 Major Equipment needed... 7 Existing Electrical System Analysis... 7 Existing Electrical Rate Schedule and Service Voltage... 8 Existing Building Utilization Voltage... 8 Existing Emergency Power... 8 Special Occupancy Requirements... 9 Special Equipment... 9 Existing Electrical Equipment... 9 Existing Loads on Optional Back-up Power... 11 Special/Communications Systems... 11 Telephone/data... 11 Fire alarm... 11 CATV... 11 Security Intrusion Detection, Video Surveillance... 11 Other... 11 Square footage of Electrical and Communications Spaces... 12

Native American Cultural Center Technical Report 2 p. 4 Energy Cost Savings/Energy Reduction Techniques... 12 Electrical One Line Diagram... 13 Existing Electrical System Evaluation and Potential Changes... 14 Comparison of Estimated vs. Actual Connected Building Loads... 14 Power Company Rate Schedule... 14 Building Utilization Voltage... 14 Emergency Power System... 15 Electrical Equipment Analysis... 15 Optional Back-up Power... 16 Integration Possibilities... 16 Energy Reduction Techniques... 16

Native American Cultural Center Technical Report 2 p. 5 Electrical Systems Criteria Electrical Load Estimate Assume the following load approximations: Lighting: 3 W/sf Receptacles: 1 W/sf HVAC: 5 W/sf The resulting energy use would be Lighting: 145800 VA Receptacles: 48600 VA HVAC: 243000 VA. There is no special equipment to take into consideration. Demand Factors are as follows: Lighting: 125% Receptacles: First 10kVA 100%, Remainder 50% Mechanical/Other: 100% Arizona Public Service Rate Schedule 1 The Cultural Center should have a secondary service from the power company. For a facility this small, it would make the most sense for the power company to own the transformer. Additionally, the service should be provided at 277/480V to support the larger mechanical equipment and allow for smaller currents corresponding with the lighting. General Service (metered kw demand) Basic Service Charge: Bundled Package Demand Charge: $1.068 per day $21.149 per kw for the first 100 kw, plus $14.267 per kw for all additional kw 1 Arizona Public Service <http://www.aps.com/main/services/business/rates/>

Native American Cultural Center Technical Report 2 p. 6 Building Utilization Voltages Service Entrance: 277/480V Lighting 277V Receptacle 120V Mechanical 208V or 480V Special Equipment Elevator: 480V Emergency Power Requirements IBC Smoke Control Systems: Smoke Control Systems must have two sources of power: the normal building power and the second approved standby by ICC Electrical Code. Emergency Lighting: Aisles and egress require automatic illumination in the event of a power outage that lasts greater than or equal to 90 minutes and provides at least 1fc with a uniformity ratio of 40 to 1. Elevators: Where only one elevator is installed, the elevator shall automatically transfer to standby power within 60 seconds after failure of normal power 2. NEC Emergency power is required for systems that are essential for life safety. The capacity must be adequate for all loads to be operated simultaneously. Wiring for emergency circuits must be kept independently of other wiring, i.e. in different conduit. Emergency power source must take occupancy and type of service into consideration. These sources include batteries, generators, uninterruptable power supplies, separate service, fuel cell system, and unit equipment. I would recommend the use of a battery source system because it is a low initial cost and because fire alarms and emergency lighting are the only necessary items for life safety in this facility. Emergency Lighting accounts for approximately 18000 VA. The elevator adds 13815 VA. Assuming another 20000 VA for Security and Fire Alarm systems, back-up power would need to support 60kVA at a voltage of 277/480V. Special Occupancy Requirements There are no special occupancy requirements for the Native American Cultural Center. 2 IBC 2006 3003.1.2

Native American Cultural Center Technical Report 2 p. 7 Special Equipment There should be an elevator in the cultural center to move individuals to and from the ground floor to the lower level. Priority List for Electrical System Design Reliability - Medium Power Quality - Low Redundancy - Low Initial Cost - High Long term ownership cost - Medium Flexibility - High Loads with Optional Back-up Power Access Control Card readers Security System Special/Communications Building Systems Telephone/data Fire Alarm IBC requirements listed on page 6 CATV Access Control Card swipes Security Intrusion and Video Surveillance Special/Communications Service to Building Telephone Data CATV Major Equipment needed Space will be needed for the switchboard. There is no need for a generator, meaning no need for extra space. The rest of the equipment is small enough that it doesn t require a significant amount of extra space. Existing Electrical System Analysis Electrical Loads Mechanical Systems 422011 VA Panelboards 757209 VA

Native American Cultural Center Technical Report 2 p. 8 Panelboard Connected Load (VA) Estimated Demand Load (VA) BHA 245293 235940 1HA 68247 58194 1HB 215562 191717 1LK 37800 37800 1LK2 12600 12600 1LB1 95624 67053 1LB2 45116 34551 1LB3 15498 14153 BLA1 54180 43236 BLA2 7680 7680 BLA3 3177 3177 1LA1 44990 31585 1LA2 20560 16835 1LA3 2230 2688 Connected Building Loads Lighting: 65249 VA Receptacle: 351704 VA Mechanical: 299254 VA Special Equipment: n/a Total: 678681 VA Existing Electrical Rate Schedule and Service Voltage General Service (metered kw demand) Basic Service Charge: Bundled Package Demand Charge: Existing Building Utilization Voltage $1.068 per day $21.149 per kw for the first 100 kw, plus $14.267 per kw for all additional kw The existing design utilizes 277/480V for the lighting system and the majority of the mechanical system. Receptacles and select mechanical equipment uses 120/208V. By operating the lighting on the higher voltage, the lighting will draw less current and reducing the operating cost. Existing Emergency Power There is no emergency power generation for the Cultural Center. The lighting is powered by batteries in case of an emergency.

Native American Cultural Center Technical Report 2 p. 9 Special Occupancy Requirements There are no special occupancy requirements. Special Equipment There is an Elevator from the ground to lower level of the cultural center. Existing Electrical Equipment The main service is a single ended system with a1200a, 277/480V, 3 phase 4 wire switchboard. The switchboard is a steel, NEMA 250, Type 1 enclosure and contains a IEEE C62.41-compliant surge protection device. It is located in the lower level SES room.

Native American Cultural Center Technical Report 2 p. 10 The main transformer is outdoor, liquid-type, and utility-owned by the Arizona Public Service. There are 5 step down transformers, 3 75kVA and 2 112.5kVA, that connect to the panelboards with receptacle loads. They are NEMA 250, Type 2 with copper coils. The transformers are a NEMA TP-1 efficiency. The panelboards are MLO, NEMA 250, Type 1, copper. They utilize molded-case circuit breakers with mechanical type lugs. There are three distribution panels fed from the switchboard. The feeder for each is 2 sets of 4#3/0 + 1#3 ground in two 2 EMT conduit. Conductors are copper and comply with NEMA WC 70. Conductor insulation complies with NEMA WC 70 for types THHN=THWN and XHHW.

Native American Cultural Center Technical Report 2 p. 11 The conduit is rigid steel where it is exposed and EMT where it is concealed. Receptacles are either straight blade 5-20R or GFCI straight blade, class A with indicator light. Switch and receptacle faceplates are smooth, high-impact thermoplastic with metal plate-securing screws that color-match the faceplate. The motor starters are individual starters for multispeed motors. There is no existing UPS for this system. Existing Loads on Optional Back-up Power There is no emergency back-up power for optional systems. The only back-up power for the whole building is with the emergency lighting which utilizes battery power. Special/Communications Systems Telephone/data There is a Main Distribution Frame on the lower level of the Cultural Center for the telecommunications system. Four electrical conduits run under the building out to a 4 x4 x4 Telecommunications vault to the east of the building. The vault is provided service via six 4 electrical conduit stemming from the service telecom vault to the north. Additionally, six 4 electrical conduit lead out of the vault to an existing casino telecom vault to the south.the rack is then connected to the appropriate panelboard. Fire alarm Each space in the cultural center has at least one fire alarm horn and strobe. Smoke detectors are in the transition spaces. CATV There is CATV cable running from the telecommunications rack throughout the building. Security Intrusion Detection, Video Surveillance There is one fixed security camera for each section of parking lot (2). Three security cameras capable of rotating 180 degrees protect the main entry area. The conduits for the exterior cameras route back to MDF B106 on the lower level. Other There is power fed to the door operators for ADA access. The drawings do not indicate that any of these systems are integrated, nor are there demand management systems in place.

Native American Cultural Center Technical Report 2 p. 12 Square footage of Electrical and Communications Spaces Five rooms totaling in 653sf of 48,600sf total building. This means that the electrical and communications rooms make up 1.34% of the total building square footage. Energy Cost Savings/Energy Reduction Techniques The building is not LEED certified, but due to the location in Arizona and the state s dark sky ordinances, the Native American Cultural Center employs curfews to turn off the exterior lighting.

Native American Cultural Center Technical Report 2 p. 13 Electrical One Line Diagram Not to scale. Provided by SmithGroupJJR.

UTILITY METER M SERVICE ENTRANCE SECTION - SES 1200A, 277/480V, 3PH-4W 42,000 AIC TO ARIZONA PUBLIC SERVICE UTILITY TRANSFORMER COORDINATE EXACT LOCATION AND REQUIREMENTS WITH APS. 1,000A GFI LSIG M CUSTOMER METER (A, V, kwhr, PF, VAR) SPD 80A 400A LSI 400A LSI 400A LSI 225A LSI 300A LSI 300 BOND TO GROUNDING ELECTRODE SYSTEM, WATER PIPING, AND BUILDING STEEL PER NEC REQUIREMENTS. BHA F2 400 1HA F9 400 1HB F13 400 AHU-1 F15 T75 T75 125-3 T30 T75 T75 T112 T112 T-1LK T-BLA1 T-1LAIG T-1LA1 T-1LA3 T BUSSMAN E501 UNIT #2 #2 #8 100-5 #2 #2 #2 ELEVATOR F8 F5 AFC=<10K F12 AFC=<10K AFC=<10K #1/0 T 400 400 KITCHEN PROVIDE 42CKT FOR FUTURE KITCHEN EQUIPMENT 1LK 1LK2 100 AFC=<10K FEED THRU LUGS BLA1 BLA2 100 AFC=<10K BLA3 AFC=<10K 225 1LAIG 1LA1 1LA2 225 AFC=<10K 1LA3 1LB1 1LB2 400 1LB3 100 DIMMER RACK DR F18 FUTURE. NOTE-ALL S TO BE PROVIDED WITH 20A1P BREAKERS TO FILL ALL 42 SPACES UNLESS NOTED OTHERWISE. KITCHEN PROVIDE 42CKT FOR FUTURE KITCHEN EQUIPMENT 1 ELECTRICAL ONE LINE/RISER DIAGRAM SCALE: 12" = 1'-0"

Native American Cultural Center Technical Report 2 p. 14 Existing Electrical System Evaluation and Potential Changes Comparison of Estimated vs. Actual Connected Building Loads The estimates were based on averages for commercial buildings. In this case, the cultural center incorporates LED technology which reduces the watts consumed. The receptacle loads were greatly under-estimated, which could be due to the fact that there are many receptacles in each room, i.e. more than a normal office building. The mechanical estimate is relatively similar to the actual connected load. Power Company Rate Schedule Arizona Public Service is the only electric provider in the area. The voltage provided by APS is 277/480V which is necessary to provide power to the HVAC units; therefore, I wouldn t suggest a change there. The rate schedule is based on the building system s capacity and therefore the rate cannot vary from the existing rates. Note that there are advantages to a 120/208V system, in that there would be no need for step-down transformers that end up taking up space in the electrical rooms. It also means that the owner is reducing the initial cost of buying more transformers. With that in mind, by running the lighting on 277/480V the owner will see another cost savings. The existing lighting is specified at 277/480, but most of the light fixtures have a 120V counterpart. A 227/480V service also provides a better quality in that it reduces the harmonics. I think it is still necessary, considering the equipment in the building to use a 277/480V service. Building Utilization Voltage Lighting: The existing is 277/480, but it could be operated at 120/208V. For longer runs however, wire size will increase a size or two just by using 120/208V over 277/480V; this also means a higher voltage drop across the length of the wire. For initial cost concerns, this could be a savings on the cost of copper. Receptacle: Receptacles are operated on 120V.

Native American Cultural Center Technical Report 2 p. 15 Mechanical: Mechanical systems should be operated at 277/480V. For the size of the loads and the corresponding equipment, it would be very costly to attempt to run the mechanical system at 120/208V. All in all, 277/480V allows for flexibility throughout the building systems and reduces some initial cost with regards to the wiring. Emergency Power System The as-designed emergency power system is in accordance to code. All of the emergency power for life-safety systems comes from batteries. Using batteries over another source such as a UPS or a generator could mean more maintenance and testing of the systems and their batteries. Due to the priority being placed on initial costs over reliability, batteries appear to be the better option. With that in mind, it is not that reliability is not important. A generator would provide further reliability and would not require any component to be exchanged regularly as would batteries. It would also mean that there would need to be more wiring and more space occupied in the electrical rooms. Any added equipment could provide an added load on the mechanical systems (cooling) and structural systems (dead load). Electrical Equipment Analysis The existing Main Service Equipment is a switchboard. A switchboard is the cheaper solution for a flexible electrical system. In the case of the cultural center, the operations of the building are not as important to require that the system must be operating at all times; therefore, it is not detrimental to the center to shut down the whole system to make repairs or changes. For the previous reasons, I do not think it is necessary to upgrade to something like a switchgear. The system is, as well as should be, single-ended as redundancy is not important here. The main service transformer is owned by the electric company and cannot be changed unless the voltage. The step-down transformers as existing are the highest efficiency transformers. Though this would provide an overall savings with a short pay-back period, there is also the option of installing lower efficiency transformers to reduce the initial cost. The asdesigned system is the most cost-effective choice for the Tribe.

Native American Cultural Center Technical Report 2 p. 16 Optional Back-up Power If a generator were added into the design, it may be beneficial to connect the card readers (access control) and security systems. This would provide a more reliable source of power with less maintenance. If a generator is not part of the design, I believe that battery power would make the most sense in terms of initial cost. Integration Possibilities While full building system coordination for the building is not necessary, it could be beneficial for the lighting and the shades to be controlled together in order to make the most of the daylight coming in as well as reduce the mechanical loads by dropping the shades on sunny days. Energy Reduction Techniques The Tribe could save further costs by using the technique of demand shifting in order to reduce the overall cost of electricity by turning off unnecessary electrical loads during peak hours.