Oconomowoc Area School District Facility Construction Update August 25, 2017

Similar documents
Binghamton University Construction SUMMER 2012 HIGHLIGHTS

REPORT CARD TO THE COMMUNITY MAY 15, 2018

Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED

Forest Hills Facilities Plan

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

Briar Crest Elementary

New High School Concept

2014 Bond Project Guide

NEW ELEMENTARY SCHOOL AT THOMAS JEFFERSON MIDDLE SCHOOL

Master Project List Report

NASSAU COMMUNITY COLLEGE. Garden City, New York Capital Committee Meeting January 12, :00 PM

Meadow Point Elementary School East Grand Avenue Aurora, Colorado 80015

Doing Business with Bartlett Cocke General Contractors

NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS

7/14/2016 CITY HALL ADA ENHANCEMENT/REMODEL ACTION PLAN 1978 Construction

Grand River Ravines Georgetown Township

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX

Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS

SCO # 1 & 2 PUNCLH LIST Project Name: VANCLEAVE UPPER ELEMENTARY CLA#: 13003

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

Proposed Bond Construction Projects

TIFT COUNTY SCHOOLS E-SPLOST HISTORY

Oxford Hills School District Capital Renewal Plan Updated March 2017

Alessandro Volta Elementary School

Master Facility Planning Update School Board Meeting May 26, 2016

Sagebrush Elementary School East Temple Place Aurora, Colorado 80015

Springpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp.

RE: Clark East Tower Renovations DATE: November 16, 2015 Ypsilanti, Michigan

ROSLINDALE BRANCH, BPL COMMUNITY PRESENTATION #2 MARTIN J. WALSH, MAYOR CITY OF BOSTON PUBLIC FACILITIES DEPARTMENT 02/07/2018

Town of Yucca Valley Capital Improvement Projects Report July 24, 2014

Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15)

Richard Henry Lee Elementary School

startup. Construction of contractor entrance off University City Blvd connecting to Lot 8 has started.

Old Jail HVAC Replacement Feasibility Report

MASTER PLAN DIAGRAMS DISTRICT CAMPUS OVERVIEW

Fall 2017 Construction Update

Appendix B. Facilities Assessment Report

SCHEMATIC DESIGN PRESENTATION

WESTERN ILLINOIS UNIVERSITY

Garfield Elementary School Feasibility Study for New Library Building Project Number A C

Encumbered Balance (E-D) Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765, $635, $635, $130, $0.

Francis M McKay Elementary School

The Van Ness Campus. Weekly Construction Bulletin #259

Warren County Schools Plant and Operations

Electrical Inspection Special Electrical

Rt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000

campus master plan VIRGINIA STATE UNIVERSITY

Draft. Security Study. Germantown School District Germantown, WI. PRA Project # February 2014

DeWitt Clinton Elementary School

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate

Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111

PLATTEVILLE MIDDLE SCHOOL

Downtown Redevelopment Project Update

Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018

Arena Elementary School 314 Willow St. Arena, WI 53503

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District

UAA School of Engineering Parking Garage Master Plan Amendment. 1. Purpose

HISTORIC RESOURCES INVENTORY - BUILDING AND STRUCTURES. Please send completed form to: National Register and State Register Coordinator,

Princeton Joint Unified School District Invitation for Bid Installation of District-Wide Lighting Occupancy Sensors

Allisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767

Calmeca Academy of Fine Arts and Dual Language

PALO ALTO HIGH SCHOOL Palo Alto Unified School District MEETING NOTES. DATE: 21 September Palo Alto HS Update

WLAC Facilities Committee Meeting. September 18, 2017

SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- ELECTRICAL

WESTERN ILLINOIS UNIVERSITY

Electrical Inspection Special Electrical

John Palmer Elementary School

LAMPETER-STRASBURG SCHOOL DISTRICT Lampeter, Pennsylvania 17537

CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14

Riverview West Side Elementary 160 Isabel Avenue East

Intelligence Community Campus- Bethesda (ICC-B)

2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect

University of Wisconsin-Stevens Point REQUEST FOR ARCHITECTURAL & ENGINEERING DESIGN SERVICES NEALE RESIDENCE HALL RENOVATION PROJECT.

THE FOLGER SHAKESPEARE LIBRARY ANC 6B Meeting

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

If the address on this form is different than the address of the building, submit a written explanation.

2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16

Michigan State University Barrier-Free/Accessibility Project Status Summary March 2017

Sidney Sawyer Elementary School

Bringing the Community Together. TOWN SQUARE UPDATE November 1, 2017

Priorities. Public Communication & Transparency Website, CM Public Updates, Magic City Newsletter

Agustin Lara Elementary Academy

Genevieve Melody Elementary School

Main Street Conversion Site

Attachment F. Campus Capital Needs Sales Surtax Funded Detail Report

CHESAPEAKE CHILD DEVELOPMENT CENTER

Notice Basic Information Estimated Contract Value (USD) $100, (Not shown to suppliers) Reference Number Issuing Organization

Summer 2016 Summer 2017

DESIGN & CONSTRUCTION GUIDELINES

PROPOSED SCOPE OF WORK

Ashland School District Facility & Capacity Assessment Report 2005

Capital Projects in and near Odenton Town Center

DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students

Expo Line Transit Project. Project Status Update Meeting West End Corridor Segment C

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner

Australian National University

ACADEMY AREA CONCEPT PLAN

CITY OF INVER GROVE HEIGHTS A G E N D A CITY COUNCIL WORK SESSION June 3, :00 PM INVER GROVE HEIGHTS CITY HALL COUNCIL CHAMBERS

Transcription:

Oconomowoc Area School District Facility Construction Update August 25, 2017

IXONIA ELEMENTARY SCHOOL Ixonia Elementary is getting ready for the start of the new school year! Interior cleaning and classroom setup are underway and installation of the temporary main entrance and ramp are complete. The footings and poured walls for the new addition will be completed this week, then structural steel delivery will begin. The new addition will start to take shape as the steel work begins in early September. A time-lapse camera has been installed to view still photos of the construction progress at Ixonia Elementary. You can view images by clicking this link: https://app.oxblue.com/open/nicholasassoc/ixonia. There will be some new routines this school year as a result of the construction work and those details will be available on the Ixonia Elementary School page. BEGAN June 9, 2017 SITE PREPARATION, RETENTION POND EXCAVATION, WELL INSTALLATION, PLAYGROUND EXCAVATION, DEVELOPMENT OF BUS LOOP, AND RELOCATION OF UTILITIES BEGAN June 2017 RETENTION POND CLAY LINER INSTALLED, CONTINUED DEVELOPMENT OF BUS LOOP, UTILITIES RELOCATED, NEW WELL INSTALLED & TIED INTO INTERIOR LINES, REMOVAL OF OLD WELL BEGAN, FIRE PROTECTION SYSTEM WATER STORAGE TANK INSTALLATION BEGAN, REMOVAL OF EXTERIOR CANOPIES & CEILING SECTIONS BEGAN July 2017 INTERIOR CONCRETE WORK COMPLETED, EXTERIOR BRICK WORK FOR THE GYM DOOR & TEMPORARY MAIN OFFICE DOOR COMPLETED, FOOTINGS FOR NEW ADDITION COMPLETED, FIRE PROTECTION SYSTEM STORAGE TANK INSTALLATION COMPLETED, INTERIOR ASBESTOS ABATEMENT COMPLETED July 31-August 25, 2017 OASD CREWS FINISH INTERIOR CLEANING FOR THE START OF THE SCHOOL YEAR, STRUCTURAL STEEL WORK BEGINS, EXTERIOR DRAIN TILE INSTALLATION CONTINUES August 28-Septmber 1, 2017 CONTINUES September 2017- August 2018

GREENLAND ELEMENTARY SCHOOL Greenland Elementary is getting ready for the start of the new school year! Classroom cleaning and setup is complete while final cleaning is underway in the corridors. The new cooling system will be complete next week and ready for the last few weeks of summer weather. Work on the new boiler will continue in the month of September, for the system to be operational before the weather turns cold. BEGAN June 9, 2017 SITE DEMOLITION, INSTALLATION OF SERVICE & FEEDER CONDUIT, INSTALLATION OF PIPING, ROOF REMOVAL & REPLACEMENT, DUCT WORK, FIRE ALARM SYSTEM & EMERGENCY LIGHTING INSTALLATION, FURNACE/BOILER REMOVAL AND CORRIDOR LIGHTING REMOVAL & REPLACEMENT ALL BEGAN June 10-July 31, 2017 CORRIDOR & EGRESS LIGHTING INSTALLATION COMPLETED, PLANNED ELECTRICAL SHUTDOWNS FOR INSPECTION, PLANNED FIRE ALARM SYSTEM TESTS, PIPING INSULATION COMPLETED, CEILING GRID INSTALLATION COMPLETED, ROOF REPLACEMENT COMPLETED, HEATING AND COLLING SYSTEM INSTALLATION COMPLETED August 1-25, 2017 REMOVAL OF REMAINING TOOLS/MATERIALS, FINAL CORRIDOR CLEANING, PAINT TOUCH UP August 28-September 1, 2017 WELCOME BACK TO SCHOOL September 5, 2017 September 15, 2017

PARK LAWN ELEMENTARY SCHOOL Park Lawn is ready to welcome back students! Classrooms are clean and set for the start of the new school year and final corridor cleaning is nearly complete. Boiler work will continue in the month of September for the heating system to be operational before Fall.. BEGAN June 9, 2017 SITE DEMOLITION, CONDUIT RACK INSTALLATION, INSTALLATION OF PIPING, ROUGH-IN & INSTALLATION OF NEW UNIT VENTILATORS, FIRE ALARM SYSTEM INSTALLATION, DUCT WORK INSTALLATION, AND BOILER ROOM ELECTRICAL PANEL INSTALLATION ALL BEGAN June 10-July 31, 2017 UNIT VENTILATOR INSTALLATION COMPLETED, ROOF REMOVAL & REPLACEMENT COMPLETED, CLASSROOM & CORRIDOR CLEANING COMPLETED, FIRE ALARM SYSTEM INSTALLATION COMPLETED, PIPING INSULATION COMPLETED, ELECTRICAL UPGRADES COMPLETED August 1-25, 2017 September 29, 2017 WELCOME BACK TO SCHOOL September 5, 2017 REMOVAL OF REMAINING TOOLS/MATERIALS, FINAL CORRIDOR CLEANING, PAINT TOUCH UP August 28-September 1, 2017

MEADOW VIEW ELEMENTARY The OASD School Board approved initial schematic designs for the new Meadow View Elementary School at their June 20, 2017, meeting, then reviewed this initial exterior schematic design at their July 18, 2017 meeting. The design development and construction document phases of the project will continue through the spring of 2018 before public bidding and construction begin. SCHEMATIC DESIGNS PRESENTED TO OASD SCHOOL BOARD June 20, 2017 & July 18, 2017 DESIGN DEVELOPMENT & DOCUMENTS July 2017-March 2018 BIDDING OPEN March 2018 BEGINS April 2018 GROUND BREAKING CEREMONY May 2018 COMPLETE August 2019 August 2019 In early July, the archeologist s report from the Commonwealth Heritage Group was submitted to, and accepted by, the Wisconsin Historical Society. The Commonwealth Heritage Group also forwarded the approval to the DNR, and the NE Corridor project received its Notice of Intent permit from the DNR. The City of Oconomowoc began work at the site this week and initial paving is set to be completed in early November, 2017.

OHS: MAIN & EAST CAMPUS The OASD School Board approved initial schematic designs for the OHS Main and East Campus projects at their July 18, 2017, meeting. The presentation included designs like these, for the café/gathering space at OHS East Campus. The design development and construction document phases will continue through the fall before public bidding and construction begin in December 2017/January 2018. OHS MAIN CAMPUS & OHS EAST CAMPUS INSTRUCTIONAL SPACE PROJECT VISIONING BEGAN April 2017 DESIGN PHASE May-November 2017 PUBLIC BIDDING PHASE December 2017 BEGINS December 2017/ January 2018 COMPLETE August 2018 September 2018