Problem Understanding

POLE BRIDGE ROAD NEAR FIVE LOT FARM

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

GENERAL INFORMATION What is Stormwater? What is a stormwater utility? What is an impervious surface?

Presentation Item C Annotated Model Outline for a Framework for a Green Infrastructure Plan

Butte Creek Canyon. The New Road Built in April of 2015 by Signalized Intersection West, LLC. Presentation slides from December 2015 through June 2016

AGENDA 2015 Community Stormwater Event

Inventory and Assessment of Stormwater Infrastructure

Inventory and Assessment of Stormwater Infrastructure

City of Petersburg, VA Stormwater Utility Frequently Asked Questions

Climate Smart Communities Green Infrastructure Case Studies

Case Study: Parsippany-Troy Hills

Erosion Control for Home Builders in the. City of Jacksonville

Funding Assistance to Stormwater Utility Fee Payers for Stormwater Solutions and Incentives. Danny Bowden City of Raleigh Stormwater Utility

ions nts July 1, 2019 The utility answers to some increase: Q: A: rainwater Q: A: areas any the total by

Appendix I. Checklists

4. Contractor (and subcontractors if applicable) certification statement(s)

Green Infrastructure Basics

Storm Water Improvements

2016 WORKSHOP LVR Field Trip

STORMWATER UTILITY PRESENTATION November 18, 2014

Highlands Region Stormwater Management Program Guidance

NEW YORK STATE WATER RESOURCES INSTITUTE Department of Biological and Environmental Engineering

DEPARTMENT OF PUBLIC WORKS & UTILITIES

water that enters our streams during storms. Any water the rain garden can t accept will continue into the storm sewer system.

MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS

Rapid Transit Implementation Working Group September 14, 2017

Checklists. Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Applicant: Contact Name: Phone Number:

Pasco County Watershed Meeting for Flood Impacted Areas Port Richey Watershed

STORMWATER UTILITY FREQUENTLY ASKED QUESTIONS

City of Kitchener Integrated Stormwater Management Master Plan (ISWM-MP) Public Open House No. 2 April 28, 2016

Scaling Up Stormwater Green Infrastructure in the Hudson Valley

OVERMOUNTAIN VICTORY TRAIL BURKE CALDELL CORRIDOR FEASIBLITY STUDY REQUEST FOR QUALIFICATIONS CALDWELL COUNTY PATHWAYS

CITY OF VALPARAISO STORMWATER MASTER PLAN

Request for Qualifications. Knowledge Park Pedestrian/Cyclist Connectivity Planning and Design

Stormwater Retrofitting: The Art of Opportunity. Presented by the Center for Watershed Protection

NEW YORK STATE WATER RESOURCES INSTITUTE Department of Biological and Environmental Engineering

Huntington Stormwater Utility

Just The Basics: Illicit Discharge. What does it mean to me?

Homeowners Guide to Stormwater BMP Maintenance

Stormwater Master Plan Update. City Council Briefing January 8, 2019

Maintaining Your Neighborhood Stormwater Facilities

4. CONCEPT PLAN DEVELOPMENT

Erosion & Sediment Control Plan Application Form & Checklist

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) (360) (FAX)

SITE PLAN REVIEW APPLICATION AND CHECKLIST

City of Petersburg, Virginia Stormwater Utility Program Residential Fee Credit Manual (Revised March 2014)

2

Maintaining Your Neighborhood Stormwater Facilities How to identify stormwater facilities and keep them working

30% Design Technical Report

A Review of Green Infrastructure Projects Implemented in the Grand Traverse Region

Bay County RESTORE Act Direct Component Proposals The project will encompass all of Unincorporated Bay County as a whole.

West Chester Borough Stream Protection Fee (SPF) Overview

MS4 PROGRAM COST SAVINGS THROUGH COMMUNITY PARTNERSHIPS

Welcome to Proper Maintenance of

Keep the Rain, not the runoff! Residential Best Management Practice (BMP) Incentive Program Criteria

Chapter 4 - Preparation of Stormwater Site Plans

Kittson Parkway / Watershed Park Parking Lot

Rain Gardens. A Welcome Addition to Your Landscape

Title 11 Streets and Sidewalks

Stormwater Management Plan (SWMP) Revision Date: 11/05

4. UTILITIES ELEMENT.

March 30, 2017

Horsley Witten Group Sustainable Environmental Solutions. Rich Claytor, P.E. Janet Bernardo, P.E. horsleywitten.com

Annual Report East Pennsboro Township s Stormwater Management Program

NYC Green Infrastructure Program

Agenda. NPDES Phase II Program (US EPA, 2003 Pending 2009) Costs of Stormwater Management and How to Structure a Stormwater Utility

City of Miami MIAMI RIVER BASIN WATER QUALITY IMPROVEMENT REPORT FOR FIRST AND SECOND QUARTER 2010

The Town Board of the Town of Vienna, County of Dane, State of Wisconsin, does ordain and adopt as follows.

Project: Mooney Lake Preserve Received: Location: 300 Sixth Ave. N., Orono Complete: Noticed:

Draft Rhode Island Stormwater Design and Installation Standards Manual

City of Stoughton Erosion Control Permit Application (effective 2/6/2018)

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2009 ANNUAL REPORT

Low Impact Development for your homes, businesses & streets

continues in the watershed, additional flood control and water quality / natural system improvements may be required in the future.

Portland International Airport Storm Water Master Plan June 5, Susan Aha Water Quality Manager

ARTICLE VI: SITE PLAN REVIEW

Rain Garden Site Selection and Installation

Reducing Runoff with Green Infrastructure. Lake George, NY May 5, 2011

SMALL PROJECTS SIMPLIFIED APPROACH

Outflow to Saw Mill Run

CITY OF URBANA STORMWATER UTILITY FEE FREQUENTLY ASKED QUESTIONS

6.1 Bioretention Areas

What is stormwater runoff? Why is it a problem? Available Financial Incentives for Stormwater BMP s Downspout Disconnection - up to $20

Appendix D - Technical Design Criteria for BMPs

THE CITY OF DELAWARE, OHIO ILLICIT DISCHARGE DETECTION AND ELIMINATION PLAN

Swatara Township Stormwater Program. 1. There are no storm sewers on or near my property. Why should I pay a fee?

3/26/2011. David Dods URS Corp., Overland Park, KS. Year 5. Photos: David Dods

Operation & Maintenance of Stormwater Management Facilities

Town of Bolton Stormwater Retrofit Opportunities

COMMUNITY DEVELOPMENT DEPARTMENT POLICY DRAINAGE FOR RESIDENTIAL PROJECTS WITH ONE OR TWO UNITS REVISED JANUARY 4, 2018

STORM WATER MANAGEMENT SYSTEMS

Action Plan for Retrofitting Structural BMPs

2

STORM WATER UTILITY FREQUENTLY ASKED QUESTIONS

Page 19 L.L.C. (Previously the United Salad Co. Garage) 939 SE Alder St.

Transcription:

TOWN OF ESOPUS REQUEST FOR PROPOSAL Stormwater Infrastructure Assessment and Drainage Capital Improvement Plan The Town of Esopus, 284 Broadway, Ulster Park, New York is soliciting proposals from qualified firms to perform consulting work for assessment of the stormwater drainage system within the Town of Esopus. Qualified Engineering Consultants ( Consultant ) should email their proposal to Supervisor@esopus.com by December 10, 2018. Questions can be directed to Shannon Harris, at (845) 331-0676. The anticipated project start date is December 2018 with the submission of a Draft Capital Improvement Plan ( CIP ) April 2019, with submission of a Final CIP by May 2019. Services to be provided by the Consultant to the Town are as follows: 1. Inventory all municipally owned drainage structures including culverts, natural flows and outfalls, swales specifically identified as drainage easements, catch basins and drainage piping. 2. Site visits and recommended remediation of known flooding areas 3. Mapping of inventoried structures using ArcGIS system. 4. Evaluate the condition of the structures. 5. Assess and evaluate the capacity of identified structures. 6. Prepare a capital improvement plan complete with visuals and recommendations for priority of drainage system improvements. Technical Proposals shall be limited to a maximum of ten (10) single-sided pages, including resumes and project descriptions. Any pages submitted beyond the maximum will be discarded and not count toward the proposal evaluation. The total cost to the Town for performing the proposed services shall be indicated, broken down by component and work elements. The Fee Proposal shall be in a separate, sealed envelope, appropriately identified on its face. Task 1 Drainage System Inventory (4 weeks) Consultant shall meet with Town and liaise with Ulster County Department of Environment (MS4 filings) to initiate project and collect mapping and other data on known Town-owned drainage structures. Consultant shall complete field work to identify Town-owned drainage systems and structures. Consultant shall utilize county parcel mapping and Town records to identify drainage easements. Inventory development will include development of structure numbering where it does not exist. Task 2 Site visits and recommended remediation of known flooding areas (2 weeks) Consultant shall work with Supervisor develop specific solutions for known flooding spots throughout the town. The following chart identifies the trouble spots which have been reported by residents where extreme flooding was experienced on or in the days following September 12, 2018. 1

Site Approx. address of reported issue Description of issue Visit? Hwy Intersection of Waterside Ave at 9W at Lake Shore Villas Regular flooding. Consider alternate placement of nearby catch basin on 9W Intersection of Doris Street, Eugene Catch basin consistently overflows at this location. and Lee, Port Ewen, NY 12466 No West Stout and Park Lane, Port Ewen, Flooded area. NY 12466 203-213 Clay Road, Ulster Park, NY Significant water flowing (off road drainageunderground pipe/coming up in front yard). No 17 Hardenburg Rd, Ulster Park, NY Significant long-standing flooding at this address since new construction went in. 5 River Road, Port Ewen, NY 12466 Backyard is often saturated weeks after heavy rainfall. Many issues with culvert and drainage pipe. 57 Main Street, Esopus, NY 12466 Serious drainage problems, dealing with this for thirty years. Had to replace section of house due to water. Now portion of backyard has collapsed. Hwy 186 Hasbrouck Ave, Port Ewen, NY 12466 Deterioration of pipeline, spewing large quantities of water, several holes, & cave-ins have appeared. Land level lower (from erosion and accumulation. 169 Sunset Drive, Port Ewen, NY 12466 Standing water, a small sinkhole area that we have never had before. side of driveway washed away. 166 First Ave., Connelly, NY 12417 Assess catch basins in flooding vicinity. 240 Tilden Street, Port Ewen, NY 12466 Flooding during heavy rain. Runoff bypasses drainage. 71 Main St, Esopus, NY 12429 Hill slopes on Main St crossing Parker Ave, all properties on west side are affected. Flooding; significant drainage issues. Back yard is now a lake; neighbor installed barrier-diverting water 173 and 179 Horton Ln, Port Ewen, NY 12466 Water shooting up out of the storm drain, crawl space took on quite a bit of water. The problem is in that pipe (drainage on the other side of the driveway was working properly). Rondout Hills, Port Ewen, NY 12466 RHHA & The Hills-the town wide flooding and impacts that occurred, discuss and review maps of drainage systems Hwy 142 Sackett St, Port Ewen, NY 12466 Water is running down 9W, every year he hires someone to dig out the back yard 736 Floyd Ackert Rd, New Paltz, NY, 12561 Culvert pipe & stream/affected areas, with the building of the house above; causes the dampness. Water pollution flowing into his property through the town culvert; tested by Kingston Water Dept. Coliforms, are present/tntc, E.Coli; water percolating (well water tested safe). No 211 Tilden Street, Port Ewen, NY 12466 Mud slide, flow of underground water that saturated an area on property. Hwy 95 Hudson Lane, Ulster Park, NY 10/9/18 Has been in communication with the Highway Dept for several years and they agree that there are drainage issues Brookview Lane intersection and Hudson. floods driveway and road frontage by 2

Brookview. flooded leach field creating unsanitary environment. Hwy 99 East Main St, Port Ewen, NY 12466 10/9/18 backyard is flooding (ankles in water) houses from below the hill in back of Stewarts drainage added by the state 10/9/18 Water flooding backyard of her home (up to her ankles), she is below the hill in the back of Stewarts (where the State installed drainage pipes; has been getting worse each year). 169 Sunset neighbor (Sentar Lane), Port Ewen, NY 12466 10/9/18 Sentar Lane. Neighbors at 169 Sunset having flooding and standing water issues. Yard floods anytime it rains. 512 Main St, St Remy, NY 12401 8/24/18 need a capital improvement which would be allocated to the project with minimal impact on Highway s budget. 253 Tilden St, Port Ewen, NY 12466 Flooding damage occurred when water went over the guard rail and caused a sinkhole. (Per Highway Superintendent; cleaned it up filled in some of the washouts but need to go back when the flow of water stops). 183 Schryver Street, Port Ewen, NY Hwy 150 Doris St, Port Ewen, NY 12466 10/9/18 Flooding in yard year after year; the drain at the corner of Doris and Green St. floods with heavy rainsthat drain is clogged and the water comes up within feet of our house. on 9/12. House is built on a slab; risk of flooding; people drive by fast and make actual waves that come toward our house (landscaping gets ruined, bus stop-students trudge through about a foot deep of water to get onto the bus). Assess size of pipe. Rondout Harbor Homeowners Association, Port Ewen, NY 12466 RHHA storm drainage issue. No Town easements. Town put sand bags to help divert water. Culvert pipe in the Hills cloggs up. Follow up meeting took place on 9/17 between the Hills and RHHA apts. 7 Valley Rd, Ulster Park, NY Ongoing issues (12-14 yrs) rain water runs over the pipes, ground floods and then front yard and house. In winter water in road freezes and assess whether swales should be installed on even numbered side of street 251 Agnes St, Port Ewen, NY 12466 Neighbor of 249 Agnes St, Port Ewen. Same issue as above (flood from all the blockages in Millbrook). (Per Highway Superintendent; Berg field/millbrook is behind house and it overflows when flooding occurs; all swamp. Trees need to be cleaned up. Hwy Intersection of Pine Street and 1458 State Route 213 Rifton/Ulster Park, NY Neighbor who owns two houses on Pine Street and experienced flooding which damaged cellars, heaters, electrical panels/systems, cars and furnaces-went into the garages. (Per Highway Superintendent; 4 foot pipe with a 12-14 foot stream going into it; above occurrence is from the last flood IRENE, he wants to prevent future flooding) 105 Canal St, Port Ewen, 12466 Runoff water coming down yard, owner put a French drain to catch any water coming down, large amt coming down through the dirt, the water overflows to 3

the top of the yard and starts running down deck and into first floor kitchen, bathroom and living room. Hwy 225 Lindorf Street, Ulster Park, NY 10/9/18 Flooding situation; for year-infiltration of water heavy rain into basement of home. Town easement west side of home. Three drainage basins set deep into the ground. On 9/15/18 heavy rains again flooded the drain (drainage basin closest to Lindorf Street was shooting water almost one-foot high, spewing road dirt into the yard). Resident met with B-Dry system company to discuss challenges to filtration. 249 Agnes St, Port Ewen, NY 12466 Drain water is usually out of the yard in a reasonable time, this time it s still in the yard. Resident believes area behind houses is flooded from all the dead trees in the Millbrook. (Per Highway Superintendent; he can t go through that property -swamp behind the house). Hwy 205 Rogers St, Port Ewen, NY 12466 Backyard has water that sits and does not drain (dealing with this for years now). Believes there is an old pipe or catch basin there. Hwy 204 Lindorf St, Ulster Park, NY Now needs to excavate property to drench in order to remove water flowing to her home. There are no catch basins and swale was filled in leaving standing water in backyard 4

Task 3 GIS System Mapping (4 weeks) The consultant shall develop a storm drainage system in an Esri standard database. Existing source documentation showing the drainage system shall be used to digitize relevant drainage features: including pipes, catch basins, manholes, outfalls, culverts and stormwater structures. Relevant attribute data such as size, material, year install, and source documentation shall be captured and associated with each feature. Consultant shall configure an Esri Collector application for field investigations of missing features and attributes. Catch basin and drain manhole depth shall be captured in the field and a photograph of each structure investigated shall be taken and associated with each structure in the GIS. The consultant shall host the data and provide access through Esri s ArcGIS Online system for a one-year period. Consultant will provide training for staff in the use of the ArcGIS Online system and the Collector application. Consultant shall provide Town with a mobile collection tablet (ipad or approved equivalent) with rugged field case. Task 4 Evaluation Condition and Capacity of Structures (4 weeks, simultaneous with GIS) Consultant shall provide a visual condition assessment of all identified Town-owned culverts, drainage manholes and catch basins. Condition should identify specific flaws or deterioration. Consultant shall work with the Town to identify up to 6 specific culverts, drainage structures or drainage swale segments for capacity analysis. The selection of these six drainage system elements will be based upon the Town s 5

flooding observations. The purpose of the analysis will be to prioritize these infrastructure segments for future capital improvements plan, and the analysis shall be conceptual in nature. Capacity analysis will include calculation of estimated stormwater runoff through the stormwater feature for storm return periods of 2, 5, 10, 25 and 50 years, and, proposed resizing of inadequate segments of the selected features, and their estimated construction cost required to carry calculated flows. Task 5 Drainage System Capital Improvements Plan (4 weeks) Consultant shall prepare a 10-year period capital improvements plan that prioritizes needed drainage system improvements, provides a schedule for improvements and an opinion of probable cost. Opinions of probable cost shall consider all construction as well as temporary access, engineering and legal fees. Final plan shall be organized in a way that will allow the Town to use document to provide documentation of need in pursing grant funding opportunities and for a public meeting. Task 6 Meetings and Deliverables (exact dates TBC in consultation with the Town) Project meetings shall include: 1. Project Initiation with members of Esopus Stormwater Drainage Committee 2. Presentation of Inventory and GIS Mapping with members of Esopus Stormwater Drainage Committee 3. GIS Collector Application Training for Highway Department Employees 4. Presentation of Draft Drainage Capital Improvements Plan with Esopus Stormwater Drainage Committee and Esopus Town Board at Public Meeting 5. Powerpoint presentation complete with visual renderings of Final Drainage Capital Improvements Plan at Public Meeting Task 7 Grant Procurement Assistance (ongoing) Consultant shall assist the Town with grant procurement including applicable opportunities from NYSDEC and Hudson River Estuary Program, among other possible sources of funding. Proposals shall include: 1. Identification and Resumes of Key Personnel; 2. Statement of Experience with similar kinds of projects specifically including: 3. Utility mapping utilizing ArcGIS for municipalities in the Hudson Valley; 4. Drainage system and stormwater modeling for municipalities in the Hudson Valley; 5. Grant procurement assistance for municipalities in the Hudson Valley; 6. Statement of Familiarity with Project Requirements; 7. Statement of a Project Approach 8. Statement of Organizational and Financial responsibility; 9. Statement of Logistical and Familiarity with the Project Area including distance of office providing services to the Town and previous work experience in Town; and 6

10. Re-Statement or verification of anticipated schedule. Evaluation of Proposals: The Selection Committee, shall make the selection of the Consultant based upon an evaluation of proposals. Proposals will be evaluated on the following criteria: 1. Prior experience of the firm on projects of this type and scope (20%); 2. Prior experience and expertise of the personnel to be assigned to this Project (20%); 3. Proposer s understanding of the work to be done and familiarity with the Town (20%); 4. Proposer s project approach (20%) 5. Cost factors (20%). The Selection Committee shall rank the Technical Proposals prior to opening the Fee Proposal. 7