Cable Selection and Detailed Circuit Analysis on Plant under Construction

Similar documents
METHODOLOGY. Circuit Analysis Basics. Joint RES/EPRI Fire PRA Training Workshop San Diego, CA, August 2011 and Jacksonville, FL, November 2011

Fire Risks of Loviisa NPP During Shutdown States

INSIGHTS GAINED FROM A REVIEW OF FIRE PRA RISK CONTRIBUTION BY IGNITION FREQUENCY BINS

The Impact from Fire PSA Hazard Factor for the PWR Plant

FIRE PROBABILISTIC SAFETY ASSESSMENT FOR KUDANKULAM NPP IN INDIA. G.Tokmachev. Atomenergoproekt, Bakuninskaya 7, Moscow, Russia

METHODOLOGY. Module I-1: Fire Risk Requantification. J.S. Hyslop NRC/RES R.P. Kassawara EPRI

Electrical failure during NPP cable fires

Design Characteristics and Classification Issue of the I&C Systems for the JRTR

AP1000 Advanced Control Room

Uncertainty Analysis For Input Parameters Of Electrical Cabinet Fire Simulation By Coupling Latin Hypercube Sampling And CFAST

Data collection in Fire PSA. Institut de Radioprotection et de sûreté Nucléaire (IRSN), BP 68, 91192, Gif-sur-Yvette, France,

Event Tree Methodology as Analytical Tool for Fire Events

IAEA SAFETY STANDARDS

Guidance for Post-fire Safe Shutdown Analysis

PERFORMANCE-BASED FIRE PROTECTION OF NUCLEAR PLANTS

Fire Protection Design Services

Requirements for Electrical Installations

Metzger, Brian. From: Sent: To: Cc: Subject:

Developing a New Fire PRA Framework by Integrating Probabilistic Risk Assessment with a Fire Simulation Module

SIL DETERMINATION AND PROBLEMS WITH THE APPLICATION OF LOPA

Fiber Optic Cable Qualification Update

NFPA Changes

Computer-based Alarm Processing and Presentation Methods in Nuclear Power Plants

REGULATORY GUIDE OFFICE OF NUCLEAR REGULATORY RESEARCH. REGULATORY GUIDE (Draft was issued as DG-1170, dated November 2006)

Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Resolution Plan for GI-AP1000-IH-01 Internal Fire Safety Case Substantiation.

INTERNATIONAL PEER REVIEW SERVICE For Probabilistic Fire Safety Assessment of Mühleberg Nuclear Power Plant

Fire Protection Regulatory Approach for Nuclear Power Plants in Canada

Part 1 General Part 2 Indenter modulus Part 4 Oxidation Induction methods Accepted by IEC and IEEE for publication Published in September 2011

Y. ORMIERES. Fire risk analysis method for nuclear installations

Protection against Internal Hazards in the Design of Nuclear Power Plants

Failure Modes, Effects and Diagnostic Analysis

Fire Test Evaluation using the Kerosene and Aviation Fuel

TABLE OF CONTENTS. Section Title Page 1.0 SUMMARY TEST SPECIMEN Materials and Construction TEST PROGRAM 4

Microgrid Fault Protection Based on Symmetrical and Differential Current Components

VACUUM BREAKER MEDIUM VOLTAGE AUTOMATIC TRANSFER SWITCHES

METHODOLOGY. Definitions. A Collaboration of U.S. NRC Office of Nuclear Regulatory Research (RES) & Electric Power Research Institute (EPRI)

Protection against Internal Hazards in the Design of Nuclear Power Plants

DRAFT NFPA 805 TRANSITION PILOT PLANT OBSERVATION GUIDANCE

INSTALLATION AND OPERATING INSTRUCTIONS R-3F2-LXX

Effective Alarm Management for Dynamic and Vessel Control Systems

New Developments in the IEC61511 Edition 2

Reliability and Safety Assessment in Offshore and Process Industries

IEC61511 Standard Overview

INPO Fire Protection Activities and Results

Licensing of FPGA-based Safety Platform RadICS: Case Study

EKL3 short circuit and earth fault indicator

NATIONAL TRAINING BOARD (ELECTRICIAN) REGULATIONS 2008 BR 54/2008 NATIONAL OCCUPATIONAL CERTIFICATION ACT :38

Technical This Review document of Risk-Informed,

English version. Railway applications Systematic allocation of safety integrity requirements

SECTION AUTOMATIC TRANSFER SWITCHES

AVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY

FIRE PROTECTION REGULATION AND EXPERIENCE FIRE PROTECTION IN INDONESIA. Agus Waluyo Indonesian Nuclear Energy Regulatory Agency

December 5, 2016 V.C. SUMMER NUCLEAR STATION, UNIT 1 NRC TRIENNIAL FIRE PROTECTION INSPECTION REPORT /

FUNCTIONAL SAFETY: A PRACTICAL APPROACH FOR END-USERS AND SYSTEM INTEGRATORS

NATIONAL ELECTRICAL CODE (NEC) & NFPA 70E ARC FLASH ELECTRICAL SAFETY

CIRCUIT BREAKER FAIL PROTECTION

Feasibility Study of Condensation Heat Exchanger with Helical Tubes for a Passive Auxiliary Feedwater System

Failure Modes, Effects and Diagnostic Analysis. PR electronics A/S Rønde Denmark

INSTALLATION, OPERATION AND MAINTENANCE MANUAL

PRIMATECH WHITE PAPER CHANGES IN THE SECOND EDITION OF IEC 61511: A PROCESS SAFETY PERSPECTIVE

Safety Instrumented Systems Overview and Awareness. Workbook and Study Guide

Converting Existing Copper Wire Firing System to a Fiber-Optically Controlled Firing System for Electromagnetic Pulsed Power Experiments

AVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY

a high level of operational reliability), and the designer (in performing probabilistic-based

PGR-8800 TECHNICAL FAQ

Regulatory Perspective for Fire Protection and Emergency Management at Nuclear Facilities in Canada

Integrated Knowledge Base Tool for Acquisition and. Verification of NPP Alarm Systems

IDENTIFYING TRAY CABLES FOR YOUR NEXT INSTALLATION A WHITE PAPER

NFPA 70E Edition Update

SEL Arc-Flash Solutions

-SQA- SCOTTISH QUALIFICATIONS AUTHORITY. Hanover House 24 Douglas Street GLASGOW G2 7NQ NATIONAL CERTIFICATE MODULE DESCRIPTOR

A Review of Current Calculation

NECA S System Approach to Electrical Safety for NFPA 70E

FIRE HAZARD ASSESSMENT IN SUPPORTING FIRE PROTECTION SYSTEM DESIGN OF A CHEMICAL PROCESS FACILITY ABSTRACT

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

SECTION 2 NEC REFERENCES SECTION 1 LOW-VOLTAGE AND POWER- LIMITED SYSTEMS...1. CHAPTER 1 GENERAL Introduction...35

ADIPEC 2013 Technical Conference Manuscript

Technical Paper. Functional Safety Update IEC Edition 2 Standards Update

TABLE OF CONTENTS CHAPTER 2 WIRING AND PROTECTION CHAPTER 1 GENERAL RULES... 19

LOPA. DR. AA Process Control and Safety Group

Lifting of evacuation orders and subsequent efforts in Japan

NZQA unit standard version 1 Page 1 of 6. Install, maintain and repair of telecommunications optical fibre network infrastructure

EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HEALTH AND FOOD SAFETY

Is your current safety system compliant to today's safety standard?

Safety Instrumented Systems

The SIL Concept in the process industry International standards IEC 61508/ 61511

NFPA 2001: Standard for Clean Agent Fire Extinguishing Systems NFPA 70: National Electrical Code (NEC) NFPA 72: National Fire Alarm Code

Failure Modes, Effects and Diagnostic Analysis

White Paper. Integrated Safety for a Single BMS Evaluation Based on Siemens Simatic PCS7 System

Serie 3 Interaction Design Basics, HCI in the Software Process & Design Rules

Brazil. Current status in NPP I&C and Discussion Topics. 24th Meeting of the IAEA TWG-NPPIC

rev3 INSTALLATION & OPERATION MANUAL OIL CIRCULATING HEATING SYSTEM MODEL OSM

FACILITY STANDARDS (FS) 2 TABLE OF CONTENTS

ELECTRICAL CURRICULA OUTLINE CORE CURRICULUM 2015

Standard PRC Transmission Relay Loadability

Continuous, real-time detection, alarming and analysis of partial discharge events

Substation Monitoring System

American Nuclear Society (ANS)

2015 Functional Safety Training & Workshops

Criteria I&C and Inherent Characteristics

Transcription:

Cable Selection and Detailed Circuit Analysis on Plant under Construction Sang Hyun Kim 1, Dong Kyu Kim 2, Myung Ro Kim 3 1 KEPCO E&C, Integrated Safety Assessment Department, Korea, ksh8934@kepco-enc.com 2 KEPCO E&C, Integrated Safety Assessment Department, Korea, kimdk@kepco-enc.com 3 KEPCO E&C, Integrated Safety Assessment Department, Korea, mrkim@kepco-enc.com Electrical analysis and circuit failure mode likelihood analysis has performed for APR1400 NPP under construction. It was first time to perform electrical analysis using NUREG/CR-6850 methodology for APR1400. Cable Raceway Database system had been developed for fire probabilistic risk assessment. Cut-off date applied to design drawings and data to maintain consistency, because of continuous design change during under construction. Cable Selection, detailed analysis, and circuit failure mode likelihood analysis had been performed. There was no risk significant electrical cable routing design. Also fire probabilistic risk assessment result shows the APR1400 design regarding the fire protection is safe enough to meet the safety goal. I. INTRODUCTION The objectives of the fire Probabilistic Risk Assessment (PRA) are to estimate the contribution of internal fires to the overall plant Core Damage Frequency (CDF) and Large Release Frequency (LRF) to identify any plant specific vulnerability to fire-induced accidents, and to provide insights for plant design and construction. Risk due to internal fire has been one of the major concerns for design and operation of nuclear power plants. Korea has performed fire PRA for all plants (nuclear power plants in operation and under construction) by fire PRA implementation guide (FPRA IG, Ref. 1). In the meantime, NUREG/CR-6850 (Ref. 2) was issued and applied to operating plants in U.S. One of the differences between FPRAIG and NUREG/CR-6850 is the electrical analysis (cable selection and detailed circuit analysis) and circuit failure mode likelihood analysis. These are important tasks in NUREG/CR-6850 (Ref. 3) fire PRA methodology, because it takes lots of manpower and effects to interfacing and following tasks. NUREG/CR-6850 fire PRA methodology is applied to Korean Advanced Pressurized Reactor (APR) 1400 nuclear plant under construction for the first time. Electrical analysis and circuit failure mode likelihood analysis are performed with current design data at the time of analysis. This paper will focus on the difference approach, result and insight between under construction plant and operating plant, rather than general approach and procedures, which are same with NUREG/CR-6850. II. Cable Selection The purpose of this task is to identify the circuits and cables associated with the fire PRA equipment and the cable routing/location of the identified circuit and cables. These relationships can then be used to determine the fire PRA equipment potentially affected by postulated fires at different plant locations. NUREG/CR-6850 provides the approach for selecting the cables as six steps as below. Compile and Evaluate Prerequisite Information and Data Select fire PRA Circuits/Cables Identify and Select fire PRA Power Supplies Perform Associated Circuit Review Determine Cable Routing and Plant Locations Fire PRA Cable List and Target Location Reports 1

Analysis was performed for APR1400 under construction plant. The differences between operating plant and characteristic of APR1400 will be described in the following sections. II.A. Prerequisite Information Proper cable and raceway database system (CRS) was not available to identify cable routing and location. There was a cable database for electrical design, but raceway location is not identified by fire compartment. CRS was developed to perform fire PRA. To develop CRS, cut-off date was applied to cable route data and raceway design. Raceway drawings (cable tray plan and cable conduit plan) are reviewed and marked-up to identify raceway locations per room for further application and fire compartment change. Suffix (e.g. -01, -02) had been added to raceway number to distinguish raceway which passes through the multi room. Cable route data had been connected to above raceway location in CRS to identify cable routing and location per room. The example of CRS is shown in Figure 1 and Table I. Fig. 1. Example of Marked-up Cable Tray Plan. TABLE I. Example of Cable Routing Data in CRS Cable Number Sequence Raceway Number Room Number Note 431-C-01-X-X-X-A 1 313-K-01-X04A-01 100-C02B 431-C-01-X-X-X-A 2 313-B-01-X01A-01 100-C02B 431-C-01-X-X-X-A 3 313-K-01-X03A-01 100-C02B Embedded 431-C-01-X-X-X-A 4 313-K-01-X03A-02 130-C01 Embedded 431-C-01-X-X-X-A 5 313-K-01-X03A-03 106-C01 Embedded 431-C-01-X-X-X-A 6 313-K-01-X03A-04 128-C01 Embedded 431-C-01-X-X-X-A 7 313-K-01-X03A-05 115-C02 Embedded II.B. Selection of Fire PRA Cables and Circuits Cables are selected per fire PRA equipment and its failure mode. Drawings associated with fire PRA equipment (cable block diagram, control logic diagram, piping and instrumentation diagram, schematic diagram, single line drawings, and so on) are reviewed to find out associated circuit and cable effect to equipment response. Additional control cabinets, local control panel and power supplies were found during cable selection, and it feeds back to fire PRA equipment selection task. 2

APR 1400 plant has digitalized instrument and control system. There are redundant and diverse manual control methods in the Main Room (MCR), such as soft control, dedicated control, and diverse manual control. Cables associated with redundant and diverse manual control are identified and selected per fire PRA equipment s failure mode. Most of control cables, which are connected between MCR and local control cabinet, are screened out for spurious operation, because those cables are mainly fiber optic cables. Additional circuitry information such as power supply configuration (grounded AC, ungrounded AC with or without control power transformer, ungrounded DC), and target cable configuration (thermoset-insulated conductor cable, thermoplastic-insulated conductor cable, metal foil shield wrap cable, armored cable, fiber optic) are corrected for following detailed circuit analysis and circuit failure mode likelihood analysis. 6444 cables are selected for 1784 fire PRA equipment. Table II shows the example of cable selection result. Fire PRA Failure Mode Cable Number TABLE II. Cable Selection Result Cable Selection Screen-out Basis Description From To 433-C-01-A-J-A-A Cable Y 433-W-501A 433-C-01-A-J-B-A Cable Y 433-W-501A 839-E-EA07A-K1 433-C-01-A-J-C-A Cable Y 839-E-EA07A-K1 433-W-001A 433-C-01-A-J-D-A Cable Y 839-E-EA07A-K1 745-J-LX12A 433-C-01-A-J-E-A Cable Y 433-J-JZ-0410A 433-W-001A 433-C-01-A-J-F-A Cable Y 433-W-001A 745-J-LX12A 745-C-01-C-S-M-A Cable N 745-C-01-D-S-M-A Cable N Fiber Optic Cable. This cable cannot cause spurious operation. Fiber Optic Cable. This cable cannot cause spurious operation. 745-J-LX12A 745-J-LX12A 752-J-PA03A 752-J-PA03A Note Safety Soft/Dedicate Safety Soft/Dedicate III. Detailed Circuit Analysis After quantitative analysis, mainly switchgear breakers, Motor Operated Valve (MOV), and Solenoid Operated Valve (SOV) are selected to detailed circuit analysis. type, equipment status (normal position, fail position, and required position), failure modes, associated circuit configuration, and reference drawings are reviewed and confirmed. Schematic drawing, elementary wiring diagram, and associated drawings are used to find out equipment/circuit response by cable hot short or short to ground. Analysis had been performed by cable wire scope; it means equipment/circuit responses are identified as each cable s wire level. The example of detailed circuit analysis is shown in Table III. TABLE III. Example of Detailed Circuit Analysis FPRA Cable Number Fault Consequence Comment 451-V-000X 451-C-10-X-X-X-A Solenoid Cable Inter-cable hot short on wire #N1 will energize the solenoid to remain in open position (Inter-cable hot short must come from the same power source, because this circuit is a ungrounded DC circuit) IV. Circuit Failure Mode Likelihood Analysis The purpose of this task is to develop probabilities for fire-induced circuit failures leading to spurious component operation. The probabilities of hot short developed are based on method and data contained in NUREG/CR-7150 (Ref. 6). If 3

cable type information (thermoset-insulated conductor cable, thermoplastic-insulated conductor cable, metal foil shield wrap cable, armored cable, and fiber optic) is not available, it assumed as the worst case. Ground fault equivalent hot short had been included as failure mode for determining the probability of a hot short for ungrounded DC or ungrounded distributed AC circuits. Dedicated conduit condition is not considered, because electrical design is not completed. External hot short is always assumed for conservative analysis. Table IV shows the example of fire-induced circuit failure probabilities. Hot short duration was considered for SOV and Air Operated Valve (AOV). NUREG/CR-7150 provides data for duration of hot shorts. That is, circuit testing performed by the NRC indicated that the majority of hot short connects will burn themselves out in a matter of minutes. When the hot short dissolves, the component will revert back to its fail safe position, provided the component has these features. AOV s and SOV s will have a fail-safe position which indicates how the valve will fail upon loss of motive power or control power. Hot short duration was considered for 125 VDC powered SOV s and AOV s. Hot short duration was credited by multiplying the probability for spurious operation by the spurious hot short duration conditional probability from table 6-3 in NUREG/CR-7150, resulting in a single value for the active hot short. Table V shows the fire-induced circuit failure probability after consider hot short duration. ID Type TABLE IV. Fire-Induced Circuit Failure AC or DC Single or Grounded Double Break Circuit Circuit Circuit Cable No Power Transformer NUREG/CR 7150 Table Reference 521-V-0109 SOV 521-C-08-A-J-A-A 125 VDC Single Break No No 5.60E-01 Table 4-1 521-V-0109 SOV 521-C-08-A-J-D-A 125 VDC Single Break No No 5.60E-01 Table 4-1 521-V-0109 SOV 521-C-08-A-J-A-A 125 VDC Single Break No No 5.60E-01 Table 4-1 521-V-0109 SOV 521-C-08-A-J-D-A 125 VDC Single Break No No 5.60E-01 Table 4-1 ID TABLE V. Fire-Induced Circuit Failure after Considering Hot Short Duration Type Cable No 521-V-0109 SOV 521-C-08-A-J-A-A 521-V-0109 SOV 521-C-08-A-J-D-A Function Fail (De-energized) Fail (De-energized) Allowed Time for Hot Short Duration Aggregate for Hot short Operation Duration Conditional Total 7 Min. 5.60E-01 2.20E-02 1.23E-02 7 Min. 6.30E-01 2.20E-02 1.39E-02 V. CONCLUSIONS It was the first time to perform Electrical Analysis using NUREG/CR-6850 Methodology for APR1400. It was found that there was no risk significant electrical cable routing design through the detailed circuit analysis and circuit failure likelihood analysis. Also the Fire PRA result shows the APR1400 design regarding the fire protection is safe enough to meet the safety goal. REFERENCES 1. EPRI 105928, Fire PRA Implementation Guide, EPRI, December 1995 2. NUREG/CR-6850, EPRI/NRC-RES Fire PRA Methodology for Nuclear Power Facilities Volume 1: Summary & Overview, USNRC, Washington, DC, August 2015 3. NUREG/CR-6850, EPRI/NRC-RES Fire PRA Methodology for Nuclear Power Facilities Volume 2: Detailed Methodology, USNRC, Washington, DC, August 20015 4. NEI 00-01, Guidance for Post Fire Safe Shutdown Circuit Analysis, NEI, October 2011 5. NUREG/CR-7150, Joint Assessment of Cable Damage and Quantification of Effects form Fire Volume 1: Phenomena Identification and Ranking Table (PIRT) Exercise for Nuclear Power Plant Fire-Induced Electrical Circuit Failure, USNRC, Washington, DC, October 2012 4

6. NUREG/CR-7150, Joint Assessment of Cable Damage and Quantification of Effects form Fire Volume 2: Expert Elicitation Exercise for Nuclear Power Plant Fire-Induced Electrical Circuit Failure, USNRC, Washington, DC, May 2014 5