D2 Subway Project Development. Stakeholder Committee October 24, 2018

Similar documents
D2 Subway Project Development. Public Meeting September 12, 2018

Dallas CBD Second Light Rail Alignment (D2)

D2 Subway Project Development. Interagency Meeting July 27, 2018

Dallas CBD Second Light Rail Alignment (D2)

Scope of Services. River Oaks Boulevard (SH 183) Corridor Master Plan

112th Avenue Light Rail Options Concept Design Report JUNE 2010 PREPARED FOR PREPARED BY TBG PGH

Lake Oswego to Portland Transit Project. Lessons Learned. John Cullerton Senior Project Manager, URS 2012 APTA/TRB Light Rail Conference

Congestion Management Safety Plan. Michael Corbett State Program Administrator September 2017

Chapter 1.0 Introduction

PROJECT BACKGROUND. Preliminary Design Scope and Tasks

Honorable Members of the Mobility Solutions, Infrastructure and Sustainability Committee

Atlanta BeltLine Corridor Environmental Study. Scoping Meeting August 2008

Kick-off Meeting,: September 11, 2014

Union Station Master Plan Task 2 Briefing

Presentation Overview

Parking Garage Site Selection Committee Final Report October 15, 2012

Relief Line Project Assessment

I-84 Hartford Project Open Planning Studio #12. April 25, 2017

Strachan Ave. Overpass Community Design Update. October 26, 2010 Stephen Lipkus Executive Director Georgetown South Project GO Transit

Dallas CBD Second Light Rail Alignment (D2) Ernie Martinez, Project Manager Planning Committee March 22, 2016

RESOLUTION NO. R Refining the route, profile and stations for the Downtown Redmond Link Extension

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA

Tysons Circulator Study: Process and Preliminary Results Summary. March 2012

Welcome. Green Line LRT. Beltline Alignment Options. Stay engaged! Follow the Green Line story at calgary.ca/greenline

Alaskan Way, Promenade, and Overlook Walk Final EIS Appendix D - Supplemental Draft EIS Comments and Responses October 2016.

Expo Light Rail Line. Expo Line Community Meeting Phase 2 Design Update November 2011

Rapid Transit Implementation Working Group

Northwest LRT Downtown to. Northwest Edmonton Study. Public Workshops

Evaluation Criteria. Detailed Evaluation Criteria

SAN RAFAEL GENERAL PLAN 2040 INTRODUCTION AND OVERVIEW

master plan of highways bus rapid transit amendment

Denver Moves: Transit Task Force

Relief Line Project Assessment

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016

REVIEW AND EVALUATION OF REGIONAL LAND USE

GLEN ROAD PEDESTRIAN BRIDGE ENVIRONMENTAL ASSESSMENT STUDY PUBLIC INFORMATION CENTRE #1 SEPTEMBER 28, 2016

Northwest Corridor LRT Line to Irving/DFW Public Meeting No. 1 Project Overview

CITY S GOALS DRIVE MODE CHOICE IN WINSTON-SALEM, NC

Crofton Manor 2803 West 41st Avenue WHAT WE HEARD. Public Consultation: Phase 1

SOUTHWEST CORRIDOR EXTENSION. Environmental Evaluation and Basic Engineering Results PUBLIC MEETING/OPEN HOUSE November 18, 2009

SHERIDAN PARKING STRUCTURE PUBLIC INFORMATION MEETING November 11, :00 pm - 8:00 pm

Kenilworth Landscape Design Community Workshop. June 13, 2015

South Davis County COMMUNITY SPOTLIGHT

preliminary master plan Cover Slide executive summary public presentation

Attachment D Eastside Transit Corridor Phase 2 Technical Study Route Options Screening Analysis and Community Outreach Executive Summary April 2017

The Community and Transportation Linkage Planning Program

Q:%4~ Memorandum CITY OF DALLAS

Project Overview. Get Involved. Public Information Meeting. Contact Information

East Central Area Plan

Shift Rapid Transit Public Participation Meeting May 3, 2017

Port Credit Local Advisory Panel October 20 th Meeting

I. DESCRIPTION OF PROPOSED ACTION... 1 A. General Description... 1 B. Historical Resume and Project Status... 2 C. Cost Estimates...

2035 General Plan Update and Belmont Village Specific Plan. Joint Study Session with the City Council and Planning Commission April 12, 2016

Economic Development & Housing Council Committee Comprehensive Plan Update September 20, 2005

Coordinated Transit Planning in Toronto SmartTrack GO RER Scarborough Relief Line Waterfront Transit

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

ITS Concept Development Activity Descriptions

SCARBOROUGH RAPID TRANSIT ENVIRONMENTAL PROJECT REPORT CHAPTER 2 PROJECT DESCRIPTION. Table 2-4: North Segment Alignment Analysis 2-21

UPDATE ON THE INDEPENDENCE BOULEVARD AREA PLAN. Citizen Advisory Group Meeting March 3, 2011

SUBJECT: Waterfront Hotel Planning Study Update TO: Planning and Development Committee FROM: Department of City Building. Recommendation: Purpose:

City of Tacoma Planning and Development Services

SCARBOROUGH SUBWAY EXTENSION. Scarborough Subway Extension. Final Terms of Reference

Lesson 6. Corridor Planning

METRO Gold Line BRT CBAC Meeting. August 23, 2018

THE GARDEN CITY PLAN. City of St. Catharines Official Plan. City of St. Catharines

STATUS REPORT ENVIRONMENTAL REVIEW FOR IMPROVED ACCESS. at the NORTH WHITE PLAINS STATION

HIGHWAY INFLUENCES ON REGIONAL DEVELOPMENT. Tony Hartzel, TxDOT Northeast Texas Public Information Mgr.

Draft Cary Community Plan Review Part 3: Shop, Engage, Serve, Special Area Plans, Other Updates. October 27, 2015 Police Department Training Room

INDEPENDENCE BOULEVARD AREA PLAN. June 24, 2008

North York Centre South Service Road

Eastside Transit Corridor Phase 2 Technical Study Update Community Outreach Meeting February 2017

Blueprint Denver Task Force Meeting #

Dyersville Downtown Plan. Open House October 24, 2017

Southern Gateway Project and Public Green

SECTION 4(f) DE MINIMIS DOCUMENTATION

7.0 DRAFT SECTION 4(f) EVALUATION

GLEN ROAD PEDESTRIAN BRIDGE ENVIRONMENTAL ASSESSMENT STUDY PUBLIC INFORMATION CENTRE #2 OCTOBER 24, 2017

A community driven catalyst for an equitable, healthy, (economically viable and environmentally) sustainable corridor

State Highway 121 Southwest Parkway. Fort Worth s Transportation Success Story in Design and Cooperation

City of Los Angeles Department of Public Works

Railyard Alternatives and I-280 Boulevard Feasibility Study. MTA Board Meeting May 6, 2014

Workshop 3. City of Burlington Waterfront Hotel Planning Study. September 14, The Planning Partnership

WELCOME TO OPEN HOUSE TWO November 28, 2018

St. Clair Avenue West Area Transportation Master Plan

DOWNTOWN PARKS & PUBLIC REALM PLAN

Northern Branch Corridor SDEIS March Table of Contents

Inglewood Transit Connector Environmental Impact Report Scoping Meeting July 26, 2018

Bus Rapid Transit Environmental Assessment and Section 4(f) Evaluation Summary

King-Spadina Secondary Plan Community Consultation Meeting. Michelle Knieriem, City Planner October 11, 2017

PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY

Rapid Transit Implementation Working Group September 14, 2017

Route 110 Alternatives Analysis

2. AGENCY COORDINATION AND PUBLIC INVOLVMENT

WARM SPRINGS PARK MASTER PLAN

The Emerald Bracelet Dallas, Texas. October 2005

Downtown Streetscape Manual & Built Form Standards

~!VAUGHAN NOV Z November 21, Mr. Denis Kelly, Regional Clerk The Regional Municipality of York Yonge Street Newmarket, ON L3Y 6Z1

Markham Centre: The centre of a new City. Unionville Ratepayers October 7, 2013

Future Proposed Development

Transcription:

D2 Subway Project Development Stakeholder Committee October 24, 2018 1

Agenda Welcome and Introductions D2 Subway Overview Status of Project Development (PD) Efforts Focus Area Workshop Results Potential Alignment/Station Refinement in CBD East Area Next Steps 2

Purpose of Today s Meeting To update stakeholders on key observations related to Focus Area workshops and progress To get feedback on: Overall urban design vision Potential subway station portal locations Potential CBD East alignment refinement Potential issues related to engineering, environmental 3

Project Overview 4

Locally Preferred Alternative Commerce via Victory/Swiss 5

Project Purpose Add Core Capacity to and through downtown Some trains will be at capacity within a few years Provide Operational Flexibility for the system Continuity of service during incidents System expansion/added service Enhance Mobility and Access for existing and future riders Get our riders where they need to go Enhance Economic Development Add value through context sensitive design 6

Status of Project Development Efforts 7

Project Development Engineering Activities Reached level of 5% conceptual design Completed 34 geotechnical borings since 2016 with 25 borings focused along alignment Utility and building foundation research Engineering Surveys Current focus is on evaluating above data to develop preferred tunnel construction approach Station space planning and design 8

Preliminary Engineering Subway Station Space Planning Station Sizing Considerations: Functions to be accommodated and space needed such as vertical circulation, restrooms, service rooms (mechanical, electrical), police office, etc. Maximum train capacity x 2.5 Design level of service (LOS) for passengers Where fare enforcement begins (street level vs. mezzanine) Physical constraints: o o o o Building foundations Geology (rock depth, thickness) Right-of-way Utilities 9

Preliminary Engineering Subway Station Space Planning 10

Preliminary Engineering Subway Station Space Planning Planning for LOS C for maximum crowd conditions 11

Project Development Environmental Activities Existing conditions documentation is in progress to support Supplemental Draft Environmental Impact Statement (SDEIS) Key topics: Traffic and transportation (auto, bike/pedestrian, parking, transit) Noise/vibration Displacement/acquisition Historic resources and Parklands Visual/aesthetics Hazardous materials Safety and security Construction impacts 12

Cultural and Historic Resources Area of Potential Effects (APE) of 300 feet from either side of alignment 600-foot radius around the three subway stations Resource age of 45 years from the anticipated revenue service date of 2024 (1979 or prior) Field survey work is complete 13

Noise & Vibration 14

Focus Area Workshop Results 15

Focus Areas Small Group Workshops 16

Victory-Perot Museum Focus Area 4 Example 17

Victory-Perot Station Area Plan 18

Station Portal Feedback 19

Metro Center Station Focus Area 3 Examples 4 20

Commerce Station Focus Area 2 Examples 5 6 21

CBD East Station Focus Area 1 Examples 2 3 22

Deep Ellum Focus Area 2 Example 23

Potential CBD East Alignment Refinement 24

Current LPA Alignment Key Issues 3 4 1 2 1. Potential impacts to Elm Street Garage 2. Subway station design constraints 3. Carpenter Park impacts 4. Potential impacts to Cesar Chavez 25

CBD East Station Constructability 26

CBD East Station Constructability Garage Expansion 27

Potential Alignment Refinement 28

Potential Alignment Refinement 29

Potential Alignment Refinement Property Needs/Potential Displacements 2107 Main Southwest Blueprint 108 N Pearl The Lounge (potentially historic) 30

CBD East/Deep Ellum Area Plan 31

Summary of Trade-Offs LPA FACTORS Refinement 0.45 mile Length 0.50 mile $382M Cost Estimate $334M Surface parking lots needed for cut-andcover construction (easement or acquisition TBD) Elm Garage may be out of service during construction or displaced pending engineering analysis Temporary surface lot disruptions Easement beneath Main Street Garden and Carpenter Park; construction impacts to south end of Carpenter Park Portal may require modification to Cesar Chavez; avoids IH 345 columns but requires TxDOT coordination Property Needs Parking Parks Roadway Surface parking lots needed for cut-and-cover construction (easement or acquisition TBD) Two building displacements (Lounge @ 108 N Pearl; Small business @2107 Main) Temporary surface lot disruptions Avoids Main Street Garden and Carpenter Park Minimal changes to Cesar Chavez Requires TxDOT coordination for innovative design around columns 32

Potential Alignment Refinement Stakeholder Feedback 33

Next Steps 34

Next Steps Complete SDEIS Existing Conditions to begin impact assessments concurrent with 10% design Complete subway station concept plans (size, functions, fare enforcement areas) Refine Area Plans for Victory/Perot and Deep Ellum Subway station portal feasibility evaluation and concepts Finalize alignment through CBD East and Deep Ellum area in cooperation with TxDOT and area stakeholders Continue to evaluate tunnel construction methods Next Stakeholder Committee meeting in early 2019 35

Schedule 36

How to Stay Involved Visit www.dart.org/d2 Sign up for project alerts at www.dart.org/d2 Email D2@DART.org Request a briefing or meeting with your organization Attend meetings regularly Mail the Project Manager 37