Route Alignment Options Summary Report

Similar documents
Rannoch 132 / 33 kv Substation Extension

Barvills Solar Farm Environmental Statement Non-Technical Summary

9 Archaeology & Cultural Heritage

E16: MAINTENANCE OF LANDSCAPED AREAS

The Place Solar Farm

GUIDELINES FOR THE ROUTEING OF NEW HIGH VOLTAGE OVERHEAD TRANSMISSION LINES

7. The Landscape. 7.1 Introduction. Environmental Impact Statement (EIS) Scoping Report

Grantham Southern Quadrant Link Road Environmental Statement

University Park, Worcester Non Technical Summary December 2011

Replacement Golf Course Facilities and Residential Development, Churston. Environmental Statement Non-Technical Summary

Longhorsley Neighbourhood Plan

LAND AT WEST YELLAND. Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP

Public Consultation. Land at Monks Farm, North Grove. Welcome

PANSHANGER QUARRY, Hertfordshire

Genex Kidston Connection Project: Draf t Environmental Assessment Report Powerlink Queensland

Dorenell Wind Farm 132 kv Grid Connection

3. Highway Landscaping Assessment

TIDAPA Structure Plan

Our approach to the design and routeing of new electricity transmission lines

APPENDIX 1: SCOPED ENVIRONMENTAL IMPACT STATEMENT (EIS) FORM

Reserved Matters application for a site that straddles the boundary between CBC and BBC

List of Policies. SESPlan. None applicable. Consolidated Scottish Borders Local Plan 2011: POLICY G1 - QUALITY STANDARDS FOR NEW DEVELOPMENT

Highway Alignment and Route Location Survey

Wind energy development in the South Pennines landscape

Plumpton Neighbourhood Development Plan Revised Pre Submission Document - Regulation 14 Consultation

Thornton Road, Pickering Environmental Statement Non-Technical Summary. January 2016

BREEDON NORTHERN LIMITED

- - - Key Characteristics

Environmental Impact Assessment

TRCA Field Staking Protocol December 2016

Request for a Scoping Opinion by Provectus. Proposed Surface Mining of Coal on Land west off the A61, Hill Top Farm, Clay Cross, Derbyshire

PROPOSED RESIDENTIAL DEVELOPMENT LAND AT GREEN LANE, YARM

Lower Sensitivity. VS Classification Level 2: Exposed Upland/Plateau

AMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON

Statement of Community Involvement LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE

Babergh and Mid Suffolk Joint Draft Local Plan Consultation, August 2017, Public Consultation

Assessing the impact of smallscale wind energy proposals on the natural heritage

TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997

Lower Sensitivity. VS Classification Level 2: Exposed Upland/Plateau

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Planning and New Communities Director

3.1 This evidence is based on the landscape and visual impact assessment included in Chapter 10 and Appendix I of the EIS.

Cape Environmental Assessment Practitioners(Pty)

MANAGING CHANGE IN THE HISTORIC ENVIRONMENT. Historic Battlefields August 2016

Neighbourhood Planning Site Assessment Pro-forma and Guide Version 2

Environmental Impact Assessment for Waterway Restoration Projects. Chris John, Technical Director Ecus Ltd.

INTRODUCTION. Land south of Bishopswood Lane, Tadley

Summary Note on Landscape and Visual Impact and Mitigation

LAND AT HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. March 2017 Our Ref: Q70433

INTRODUCTION. Welcome to the third round of information events on the emerging Yorkshire Energy Park proposals. THE CONSULTANT TEAM WHERE IS THE SITE?

volume 11 environmental assessment section 2 environmental impact assessment Part 4 ha 204/08 scoping of environmental impact assessments

CA//16/00504/FUL. Canterbury City Council Military Road Canterbury Kent CT1 1YW. Crown copyright and database rights 2016 Ordnance Survey

Site Assessment Technical Document Appendix A: Glossary

Lower Sensitivity. VS Classification Level 2: Exposed Upland/Plateau

West of Chichester Proposals for land to the west of Centurion Way 1 Welcome Introduction

volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08

SAN RAFAEL GENERAL PLAN 2040 INTRODUCTION AND OVERVIEW

ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville. Environmental Screening Report

A payment of 1080 is due in this instance, for a meeting and follow up written response, and will be made by card over the phone.

SUSTAINABLE MANAGEMENT

Contents. Annexes. Annex 1 Process Diagram for the discharge of the DCO Requirements. Annex 2 Design Sheet Power Generation Plant

UTT/16/1466/DFO GREAT DUNMOW MAJOR

Comments on the proposed scope are requested from WCC/NBBC officers to be provided to SLC Rail by 25 th March 2016 and sent to

Circular L8/08 2 September Water Services Investment and Rural Water Programmes Protection of Natural Heritage and National Monuments

Cranbrook EXPANSION ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY PRODUCED BY DAVID LOCK ASSOCIATES

Chapter 8: Cultural Heritage Assessment

Background Summary Report

Kier Infrastructure and Overseas Limited Greenburn Surface Mine, Dalgig Farm Site

Examination of South Cambridgeshire Local Plan

Welcome to the Public Consultation Exhibition

The Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion

Land at BROOK STREET PROPERTIES TENCREEK FARM, LISKEARD. Environmental Statement: Non-Technical Summary

Introduction. Grounds of Objection

Chapter 3 Site Planning and Low Impact Development

Site ref: AS06 Site Name or Address: Murreys Court, Agates Lane

Former RAF Sealand Site EIA

RURAL ZONE - POLICY. Rural Zone Policy. Issue: Rural Environment. Ruapehu District Plan Page 1 of 8

Application for Certificate of Environmental Compatibility and Public Need

LAND EAST OF SUDBURY ROAD, HALSTEAD PUBLIC CONSULTATION. Proposed Residential Development

Form to Submit Land for Residential Evidence Gathering Shepway Strategic Housing Land Availability Assessment (SHLAA) Partial Review

SEABANK 3. Interim Landscape and Design Statement

Lead Local Flood Authority SuDS Policy Statement

8.0 Design and Form of Development 43/

Woodland Conservation and the Master Plan

Derry City and Strabane District Council Planning Committee Report. Amended layout from approval A/2004/0462/F with reduction from 166 units

Copyright Nigel Deeley and licensed for reuse under this Creative Commons Licence

North York Moors National Park Authority Planning Committee

Strategic Environmental Assessment Screening Report. Dublin Port Masterplan Review 2017

TOWN AND COUNTRY PLANNING ACT 1990 (AS AMENDED).

Derry City and Strabane District Council Planning Committee Report

BRE Strategic Ecological Framework LI Technical Information Note 03/2016

SPG 1. * the northern and western sections which are open fields used for pasture and grazing;

North Wales Wind Farm Connections. Route Corridor Report

Master Environmental Servicing Plan & Secondary Plan

Appendix G Response to Comments

Response by the Wiltshire Archaeological and Natural History Society

Section 6A 6A Purpose of the Natural Features and Landscapes Provisions

ROCHFORD LOCAL DEVELOPMENT FRAMEWORK: Sustainability Appraisal/ Strategic Environmental Assessment. Rochford Core Strategy Preferred Options Document

Powys (Mid Wales) Conjoined Windfarm Inquiry Llanbrynmair Windfarm Supplementary Environmental Information February 2014

64 Mineral Extraction Area Rules

DEFGH. Crystal Place Park. Environmental Impact Assessment (EIA) Elin Thomas and Emily Low Waterman Environmental

Transcription:

Brechfa Forest Connection Project February 2014

Summary report 1. RSK Environment Ltd (RSK) was commissioned by Western Power Distribution (WPD) to provide environmental consultancy support services for the connection of three proposed wind farms in Carmarthenshire to the electricity distribution network. RSK are advising WPD on the selection of a route for the proposed 132,000 kilovolt (132kV) overhead line (OHL) to connect three proposed wind farms at Brechfa Forest West 1, Bryn Llywelyn 2 and Brechfa Forest East 3, to a common grid connection point near Llandyfaelog, south of Carmarthen (the scheme). 2. This document is a summary of the Route Alignment Options Report (January 2014), which records the process undertaken to develop possible route alignment options, each 300m wide, within the preferred route corridors. Background and work completed in previous stages 3. The work undertaken to date has been carried out in a structured manner involving the following main stages (see Figure 1). Stage 1a: Primary environmental constraints review, which defined the project and the study area (area of search) and identified important environmental constraints to the installation of an OHL. Stage 1b: Primary technical constraints review, which identified potential physical or practical engineering constraints to the scheme, such as existing or planned infrastructure. Stage 2a: Route corridor options identification and appraisal, which involved desk-based review and site evaluation to identify broad route corridors that could accommodate the necessary OHL connections between the three proposed wind farms and the likely grid connection 1 Consented project 2 Planning appeal pending determination 3 Consented project Page 1 of 12

point. Stage 2b: Identification of the preferred route corridors, which appraised the various corridor options brought forward from Stage 2a and determined a preferred broad corridors for the connections (see Figure 2). 4. The process to select the preferred route corridors in Stage 2b was reported in the Route Corridor Selection Report (December 2013). 5. The work described in this summary report is that undertaken in Stage 3a: Identification of route alignment options, which involved development of feasible route alignments (each 300m wide to allow flexibility in choosing a final alignment) within the preferred route corridors. 6. Following consultation on the identified options, the work will progress to Stage 3b: Selection of the preferred route alignment, which will review the options shortlisted at Stage 3a to determine a preferred alignment, which will then be subject to formal EIA procedures. Stage 3a: Identification of route alignment options 7. During Stage 3a, the design development work has been progressed to identify route alignment options within the preferred route corridors that will meet the overall project objective of providing an efficient, coordinated and economic grid connection which, on balance and where possible, results in the least disturbance to the receiving natural and built environment and those who live and work within it. 8. The approach taken in Stage 3a was a combination of desk-based work, using tools such as GIS and Google Earth, based on information gathered during earlier stages of the study, including information gathered during Stage 1 Consultation, and field work to check that information and allow refinement of the options. Design workshops involving engineering and environmental specialists were held to discuss and refine various options based on potential lines of least resistance (i.e. route options that optimise Page 2 of 12

social and environmental outcomes as well as technical and economic considerations). 9. The main assumptions in our approach to the identification of route alignment options were as follows: The preferred route corridors from Stage 2b would be taken as the starting point; The basic principles that were applied to the identification of route corridors, such as the Holford Rules, would also apply to the identification of route alignments within the preferred corridors; Modifications or additions to the preferred route corridors 4 would be permissible if substantiated with sound reasons for instance, flexibility would be allowed for an alignment option to deviate outside a previously identified corridor if that would offer a better overall solution than an alignment wholly within a previously identified corridor; and Route alignments were identified that were based on feasible options for an OHL. However, potential mitigation options such as undergrounding of a section of OHL would be considered in order to develop an acceptable final alignment. Consideration of the need to mitigate, and the details of any specific mitigation measures, will be confirmed after Stage 2 Consultation, when the final route alignment is chosen. 10. During the Stage 3a work, various alignment options were identified, initially considering engineering issues related to ease and practicality of construction and informed by the avoidance of known environmental constraints. Preliminary route alignment options were then reviewed by the project team specialists applying professional judgement. The initial options were amended and new options were put forward for consideration. 4 Two minor modifications to the corridor boundary were made in E1 and E2 as it was recognised they may provide a better overall solution. Page 3 of 12

11. The evaluation of the preliminary alignment options involved a range of factors including: Physical factors (e.g. geology, landform/ land use type); Landscape and visual aspects; Ecological aspects including habitat information and protected species records; Cultural heritage aspects such as impact on the setting of key resources; Flood risk and hydrology; Areas of peat deposits and historic and active landfills; and Development Plan allocations and recent planning applications. 12. All preliminary route alignment options had to be feasible such that an engineered OHL alignment could be installed within the 300m wide route alignment, taking into account various engineering factors such as: Alignments that would achieve, where practicable, the most direct route (i.e. the shortest route length); Reducing the design and construction complexity, for instance: minimising the need for different pole types; minimising the height of the poles (and associated materials) needed; minimising route deviations (especially where angle structures/stays, etc. may be required); meeting accepted engineering tolerance such as achievable span lengths. Consideration of topography (e.g. slope steepness, change in gradients); Minimising the number of crossings (e.g. rivers, transport links, pipelines, other electrical infrastructure); Page 4 of 12

Retaining suitable set-back or buffer distances from built-up areas and avoiding conflicts with other infrastructure (e.g. other OHLs, wind turbines, landfills, airports/ flight paths, etc.); and Consideration of construction phase issues such as ease of access to the route, amount of site preparation required (e.g. minimal tree felling 5 ), anticipated ground conditions/ foundation requirements; and associated costs or possibility of time delay. 13. Where practicable, the environmental and engineering teams visited critical parts of each preliminary route alignment to confirm the existence or absence of potential constraints and to ensure that the resulting OHL alignment options would all be possible to construct. 14. With regard to a preliminary route alignment through preferred corridor E1, initial engineering work indicates that construction would be very challenging. Should an alignment option be taken forward within this corridor then its construction will entail substantial tree felling and the possible need for bespoke metal gantry designs or strengthened wood pole structures needed for the 400-450m span lengths required to cross steep sided valleys. Removal of tree stumps for construction would be required and is difficult due to the presence of steep slopes with poor access. The maintenance of a line would be very difficult through this corridor and will also require significant resilience tree cutting throughout its lifetime. 15. A preliminary route alignment through the River Cothi Special Landscape Area requires careful routing and consideration of span lengths and steep valley slopes. The detail surrounding this is being investigated further and this and the information that comes out from Stage 2 consultation will assist in determining the appropriateness of a final route alignment in this area. 16. The preliminary alignment options were reviewed in the context of existing physical and environmental constraint information, mapping and aerial photography (including resources such as Google Earth) as well as visits to 5 Where an OHL traverses an area of woodland, the cutting width required will be about 60m wide. Page 5 of 12

critical parts of the routes. Refinements were proposed, which in summary were related to the following: Geology and ground conditions 17. There are four areas where peat deposits may be encountered. Given the small footprint of the proposed infrastructure and the ability to vary span lengths and micro-site pole locations, it is considered that direct effects upon some of these peat areas could be avoided. Should this not be possible, construction best practice will ensure that any effects upon the areas of peat are minimised. The presence of peaty ground is therefore considered not to be an absolute constraint requiring the realignment of the preliminary route option. 18. The precise footprint of three landfills will be checked to ensure that the final alignment would not conflict with the facilities or result in an additional risk of pollution. A fourth landfill lies within the boundary of one route alignment option, however, should this be taken forward it may be possible to adjust the route of the overhead line to avoid this feature. Landscape and visual 19. Further review identified locations where the preliminary alignment options might be improved to: Minimise the elevation of the routes to ensure that any visually prominent local hilltops are avoided and that ridgelines are crossed at appropriate saddle locations; Further avoid areas of sloping ground where these are identified to be particularly visible from surrounding areas; Identify less prominent ways in which visible slopes could be climbed; Confirmation of the presence and principal aspects of residential properties to, wherever possible, avoid principal views from main frontages; and Page 6 of 12

Further detailed consideration of the landscape sensitivity of key locations particularly within special landscape areas including identification of any locations where the construction of an OHL is likely to be considered unacceptable. 20. The following locations were subject to particular scrutiny: The preliminary alignment of the OHL within the Towy Valley to the east of Carmarthen this was checked from a number of surrounding and sometimes elevated vantage points in the surrounding area to ensure that the alignment option would minimise any impact on the integrity of the valley landscape and special landscape area; The preliminary alignment option to the west of Pontarsais was revised to minimise visibility at sloping ground to the north; The final link to the Bryn Llywelyn Substation was amended to avoid impacts on the open moorland to the east or valley landscape to the west; Amendments were made to alignments in the vicinity of Brechfa village that would minimise visual effects on the settlement; and Careful consideration was given to any preliminary alignment options along or crossing the route of the River Cothi. Ecology 21. The preliminary alignment options were reviewed to understand their possible ecological effect. Given that the nature of the project will, in places, require clearance of trees under the OHL, the effects on woodland and its associated species are likely to be greater than the effects where the route passes through grasslands (where only the footprint of the wooden poles could cause a direct long-term effect on habitats). One of the key priorities in selecting the preliminary route alignment options was therefore to avoid woodland wherever possible, in particular avoiding ancient semi-natural Page 7 of 12

woodland (ASNW). The preliminary route alignment options were reviewed to achieve alignment options that would where possible avoid: Ancient semi-natural woodland; Peatland habitats; Semi-improved grasslands; and Linear habitats. Cultural Heritage 22. The main issues taken into account in refinement of the preliminary route alignment options were to avoid any physical effects on designated receptors, or any effects resulting from changes within their settings. The designated receptors considered include Scheduled Monuments, Listed Buildings, Conservation Areas, Registered Parks and Gardens, and Registered Landscapes of Historic Interest. To remove or reduce potential adverse effects, consideration was given to: Avoiding crossing or oversailing receptors; Maximising the setback distance from receptors Taking advantage of screening by terrain and filtering from existing vegetation; Avoidance of prominent/ dominant positioning in the landscape (e.g. breaking the skyline, on high ground, etc.); and Respecting the existing boundaries between historic landscape zones. 23. The preliminary alignment options have been developed with consideration for the above constraints and in particular the following potential cultural heritage issues were considered in the review of preliminary route alignment options: East of Gwernogle, the preliminary route alignment option passes two Page 8 of 12

Listed Buildings (one a church) on the road at Nant-y-Waun. Consideration should be given to maximising the distance of the final alignment from these buildings; The preliminary route alignment option in corridor E2 passes a Listed Building on the B4310 west of Abergorlech but topography and vegetation in this area should be sufficient to screen an OHL alignment; The preliminary route alignment option has been adjusted southwards where it passes a Listed Building at Forest. Keeping the final alignment to the south would reduce the potential for adverse effects on that receptor; A preliminary route alignment option south of Brechfa was dropped in favour of a more southerly option avoiding a pair of Listed Buildings on the B4310 (Brechfa House and its stables); The final alignment will be adjusted to avoid crossing directly over a scheduled cairn north of Caeglas and Cwrt Farm; The preliminary western preliminary route alignment option around Alltwalis was adjusted to allow greater setback from the western fringes of the historic settlement; Close to Rhydargaeau, the preliminary route alignment option was adjusted to the west to provide sufficient width to enable a better final alignment at this point; In the section approaching the north of Carmarthen (Peniel to the River Towy), the preliminary route alignment option was shifted slightly further from the Listed Building at NGR 242821 222784; Sufficient setback has been allowed for the final route alignment option near the A485 Dolgwili roundabout to reduce potential adverse effects on a Listed Building at this location; East of Carmarthen the preliminary route alignment passes by a Listed Page 9 of 12

Building near Llangunnor but topography and vegetation in this area should be sufficient to screen an OHL alignment; and The preliminary route alignment option to the southern connection point has allowed for sufficient setback from the church at Llandyfaelog. Flood risk and hydrology 24. Avoidance of flood plains and watercourses (main rivers as well as minor watercourses and drainage ditches) is preferable, however it is acknowledged that in many cases they are not possible to avoid. The preliminary route option has considered the location of the flood zones and subsequent stages in the planning of the alignment will aim to ensure there is no impact on the existing hydrology and function of the floodplains. 25. It is preferable that pole positions are located outside of the 8m easement zone associated with main rivers. Any associated constructions compounds, works and excavated material should be stored out of the flood zone, where possible. This is again a more detailed matter for consideration in the planning of the final alignment. 26. The flood storage cells along the River Towy are located to the east of the A485 and are avoided by the preliminary alignment route however construction work should ensure that the effectiveness of this zone is not compromised. Planning 27. A desk-based review of relevant development plans and other sources was undertaken to identify existing and proposed land use allocations, and existing planning applications and permissions that have potential to influence the location of the preliminary route alignment options. The focus of the exercise was on areas of proposed development, although land uses such as recreation areas and conservation areas were also noted. Alignment options were refined to take these identified areas into account. Page 10 of 12

Final refinements to alignment route options 28. The review and refinement process resulted in many possible and feasible OHL alignment options, each lying within each of the identified 300m wide route alignment options. This improved the confidence that the outcome of Stage 3a has resulted in feasible 300m wide route alignment options for later evaluation. 29. The Stage 3a process has resulted in the identification, refinement and verification of route alignment options. The preliminary route alignment options (shown shaded in grey) are compared with the final refined alignment options (shown outlined in green) in Figures 3 and 4. These plans are referenced with numbers to indicate the main areas where the alignment options have been adjusted, as explained in the table below. Reference Location Proposed adjustment 1 Bancycapel An alignment south east of Bancycapel that would have followed a lower lying route in a valley to avoid the more elevated plateau areas to the north west of this settlement was rejected due to likely effects on woodland and ecological interests in the valley. 2 A48 Alignment discounted in favour of a route to the east, considered to have less impact on residential properties. 3 Towy Crossing Alignment adjusted to the west 4 Peniel On site checks suggested that a route slightly further west of Peniel would have less impact on the valley landscape in this area. 5 Pontarsais Alignment option to the west of Pontarsais was rejected due to potential visibility of sloping ground and prominent hill landform to the north. 6 Bryn Llywelyn link The final link to the Bryn Llywelyn Substation was realigned to avoid impacts on the open moorland to the east or valley landscape to the west. 7&8 Brechfa Identification of other OHL alignments in the vicinity of Brechfa village that would minimise visual effects on the settlement and follow a less elevated route. 9 Cothi Valley Route across the Cothi Valley was rejected due to impact on sensitive, narrow v shaped section of the valley in the SLA and due to potential visibility on elevated sloping ground to the south east in sensitive scenic views from just east of Brechfa village. The new route provides two options that would allow Page 11 of 12

a route avoiding ancient semi-natural woodland.. Future stages 30. Route alignment options within the preferred route corridors have been identified and the reasoning behind the selection has been described in the Route Alignment Options Report. The options will be subject to consultation in early 2014 with statutory consultees, elected representatives, local community groups and the public. 31. Following consultation, WPD will decide on their preferred route alignment and this will be subject to formal Environmental Impact Assessment in order to develop a final design that avoids, as far as possible, adverse effects on people and the environment. The scope and coverage of this assessment work will be agreed in advance with the Planning Inspectorate. 32. Formal consultation on the final design and the Environmental Statement will take place in autumn 2014 and WPD expects to submit their application to the Planning Inspectorate at the end of 2014. Page 12 of 12