OVERBURDEN MANAGEMENT PLAN APPENDIX ENVIRONMENTAL IMPACT STATEMENT

Similar documents
MERIDAN PLAINS SAND RESOURCE AREA

14 Visual Amenity 14-1

PANSHANGER QUARRY, Hertfordshire

LYNWOOD QUARRY. Earth Bund Options Environmental Impact Analysis FINAL

I539. Smales 2 Precinct

64 Mineral Extraction Area Rules

E&JW Glendinning Ltd.

SECTION AMENDED TOPSOIL

VISUAL IMPACT ASSESSMENT APPENDIX ENVIRONMENTAL IMPACT STATEMENT

APPENDIX K. Visual Impact Assessment

ARROW BOWEN PIPELINE ENVIRONMENTAL MANAGEMENT PLAN OUTLINE SOIL MANAGEMENT PLAN

REPORT AND SPECIFICATION FOR RESTORATION WORKS ON NELLIES GLEN ROAD and THE 6 - FOOT TRACK NELLIES GLEN

Local Area Key Issues Paper No. 11: Extractive industry - Yandina Creek and Browns Creek Road

Appendix E Preliminary Design

Appendix N. Preliminary Design

FINAL AND TEMPORARY REHABILITATION PRINCIPLES. BLOOMFIELD GROUP REPORT 2013 Rix s Creek

4.6. Low Impact and Retentive Grading

Landscaping Management Plan. Woodlawn Mechanical Biological Treatment Facility. Veolia Environmental Services Australia Pty Ltd

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

Rempstone Extension - East Leake 2014

CONSTRUCTION SPECIFICATION FOR RIP RAP, ROCK PROTECTION AND GRAVEL SHEETING

YENNADON QUARRY, DOUSLAND, YELVERTON, DEVON, PL20 6NA EXTRACTIVE MATERIALS MANAGEMENT STATEMENT. For YENNADON STONE LTD

Northgate Minerals Corporation Kemess South Mine. Reclamation & Closure Preparation. Minerals North Conference 2009, Fort St. James, B.C.

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

Shelbyville, KY Stormwater Best Management Practices. Section 2 EROSION PREVENTION AND SEDIMENT CONTROL PLAN

OSSGA Student Design Competition

BREEDON NORTHERN LIMITED

MARBLE RIVER WIND POWER PROJECT Agricultural Protection Measures

Soil Reclamation and Site Reinstatement

POLICY SRT/D4 STORMWATER MANAGEMENT

NON-TECHNICAL SUMMARY

ENVIRONMENTAL ENGINEERING LAND SURVEYING

McKay Road Interchange and Salem / Lockhart Crossing

Guidance on Preparation of Construction and Maintenance Costs

DEVELOPMENT APPLICATION DECISION NOTICE Sustainable Planning Act 2009 (SPA)

ARTICLE VI: SITE PLAN REVIEW

INDIAN BUREAU OF MINES MINERALS DEVELOPMEMT AND REGULATION DIVISION MCDR INSPECTION REPORT. Chennai regional office

2.5.1 Mineral aggregate resources shall be protected for long-term use

Request for a Scoping Opinion by Provectus. Proposed Surface Mining of Coal on Land west off the A61, Hill Top Farm, Clay Cross, Derbyshire

Low Gradient Velocity Control Short Term Steep Gradient [1] Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent

Table of Contents. Attachments Attachment A Photos Attachment B Site Map. Pages 3 of 9

Assessment of Landscape, Visual and Natural Character Effects

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion

6.9 Check Dams Description/Purpose Catchment Area Construction

SOIL EROSION AND SEDIMENT CONTROL

Grantham Southern Quadrant Link Road Environmental Statement

Huntington Stormwater Utility

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT

Red Hill Quarry. West Quarry Extension Area A. Screening and Rehabilitation Plan. Ministerial Statement 912

THE IMPORTANCE OF SOILS FOR SUCCESSFUL DEVELOPMENT HELEN SIMPSON

APPENDIX J PERFORMANCE STANDARDS FOR GRAVEL MINE, PIT MINE, OR QUARRY

2016 Annual Inspection Report

Vegetation Management

The Concept. Features. Benefits

Draft Eastern District Plan

Milpitas College Extension Milpitas Dry Landscape

2018 Annual Landfill Inspection Report

Subsurface Infiltration Bed

South Whitehaven, Cumbria EIA

PENRHYN QUARRY BETHESDA GWYNEDD. Proposed Inert Recycling Facility DESIGN AND ACCESS STATEMENT

SEQ Strategic Stabling Investigation Working paper: Northern corridor site selection - Town planning assessment

6 Growth Management Challenges and Opportunities

Authority. any changes required as a result of the approved CHMP.

Small Heath Rail Sidings, Anderton Road, Small Heath, Birmingham, B11 1TG

Garden Bridge Planning Application

Chapter 4. Route Window C12: Mile End Park and Eleanor Street Shafts

BUSINESS PLAN CEN/TC 231 MECHANICAL VIBRATION AND SHOCK EXECUTIVE SUMMARY

Appendix F Construction phase management

HARDROCK PROJECT CONCEPTUAL SOIL MANAGEMENT PLAN

INDIAN BUREAU OF MINES MINERALS DEVELOPMEMT AND REGULATION DIVISION MCDR inspection REPORT Hyderabad regional office

DIVISION 40 PUMP STATION SITE WORK AND LANDSCAPING

Infiltration basin under normal conditions, with generous grassed area for water soakage (Source: WSUD in the Sydney Region)

Northern Territory Compact Urban Growth Policy

Inspection report of Donimalai iron ore Mine of M/s Nadeem Minerals (ML No. 2526)

Draft Rhode Island Stormwater Design and Installation Standards Manual

LAND AT WEST YELLAND. Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP

Soil Erosion & Sediment Control Plan Requirements for Submittal to the Cape Atlantic Conservation District

York Potash Project Mine, MTS and MHF Environmental Statement, Part 2 Chapter: 16 Land Use and Soils Appendix 16.5 Outline Soil Management Plan

Santa Barbara County Planning Commission May 11 th, Cuyama Valley Conservancy vs. Troesh Diamond Rock Mine

Concrete Plants ASTEC. Roller Compacted Concrete and Cement Treated Base

INDIAN BUREAU OF MINES MINERALS DEVELOPMEMT AND REGULATION DIVISION MCDR inspection REPORT Chennai regional office

STORM WATER MANAGEMENT PLAN APPLICATION Manheim Borough

SECTION 02230BP AGGREGATE BASE

Alberta policy and regulations for grassland reclamation criteria, evolution of the criteria from the 1995 version to today

APPENDIX A SIMPLIFIED APPROACH TO STORMWATER MANAGEMENT FOR SMALL PROJECTS. In West Sadsbury Township, Chester County, Pennsylvania

a. Site Topography and Relationship to Surrounding Topography

Visual Impact Assessment - December Figure 5.2: Viewshed analysis of the haul route.

Non-Metallic Mining Reclamation Checklist

RSMX VSI Rotor Centrifugal Crusher. The cubicator for crushing and shaping

ELLIOTT HEADS STRUCTURE PLAN

INDIAN BUREAU OF MINES MINERALS DEVELOPMEMT AND REGULATION DIVISION MCDR INSPECTION REPORT Bhubaneshwar regional office

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF INTERLOCKING CONCRETE PAVERS

Sandy Creek Road and 1720 Bacchus Marsh Road, Little River

2.1.4 Roof Downspout Rain Gardens

A. Contractor shall provide product data for each type of product indicated.

VALLEY COUNTY MINIMUM STANDARDS FOR PRIVATE ROAD DESIGN AND CONSTRUCTION

Objectives. NFPA Dust Specific Documents. Combustible Dust Process Hazard Safety Overview of NFPA Standards for Combustible Dusts

ESSENTIAL ENGINEERING FOR PLANNERS

BUSHFIRE CONSTRAINTS ASSESSMENT FOR THE SHONE AVENUE WEST DAPTO ROAD NEIGHBOURHOOD PLAN HORSLEY

Post - Construction Hydromodification Development Requirements

Transcription:

OVERBURDEN MANAGEMENT PLAN APPENDIX V ENVIRONMENTAL IMPACT STATEMENT

Overburden Management Plan BORAL Gold Coast Quarry, Reedy Creek B12119MR004 April 2013

TABLE OF CONTENTS GLOSSARY OF TERMS III EXECUTIVE SUMMARY IV 1.0 INTRODUCTION 1 1.1 TERMS OF REFERENCE (TOR) 1 2.0 PROJECT DESCRIPTION 2 2.1 STAGES OF DEVELOPMENT 6 3.0 SITE SOIL AND ROCK CHARACTERISTICS 10 3.1 PLANT AREA 10 3.2 PIT AREA 10 4.0 MATERIAL TYPES PRODUCED 11 4.1 TOPSOIL 11 4.2 OVERBURDEN (ON SITE) 11 4.3 OVERBURDEN (OFF SITE) 11 4.4 ROCK (PRODUCT) 11 5.0 MATERIAL VOLUMES 12 6.0 MATERIAL PLANNED USE 13 6.1 TOPSOIL 13 6.2 OVERBURDEN (ON SITE) 13 6.3 OVERBURDEN (OFF SITE) 13 6.4 ROCK (PRODUCT) 14 TABLES TABLE 1 QUARRY DEVELOPMENT STAGES 7 TABLE 2 MATERIAL VOLUMES DURING ESTABLISHMENT AND DEVELOPMENT 12 Ref: B12119MR004RevC-OMP - i - OMP- BORAL Gold Coast Quarry

Document Control Page Revision Date Description Author Signature Verifier Signature Approver Signature C 15/04/13 Final MM RR AR Ref: B12119MR004RevC-OMP - ii - OMP- BORAL Gold Coast Quarry

GLOSSARY OF TERMS AHD Australian Height Datum Boral Boral Resources (QLD) Pty Limited GCQ Gold Coast Quarry m Metres m3 Cubic metres Overburden Low value quarry material, including soil/overburden and weathered rock Plant Boral crushing plant Product High value quarry material QLD Queensland RL Reduced Level ROM Run of Mine Site Lot 105 t Tonne Topsoil Soils within 50mm of the existing surface. To be stockpiled for future reuse. ToR Terms of Reference WBQ West Burleigh Quarry Ref: B12119MR004RevC-OMP - iii - OMP- BORAL Gold Coast Quarry

EXECUTIVE SUMMARY This Overburden Management Plan supports the Environmental Impact Assessment (EIS) for a new extractive industry operation (quarry), proposed by Boral Resources (Qld) Pty Limited, on a greenfield site at Old Coach Road, Reedy Creek, Gold Coast. The contents of this report have been prepared in response to the Term of Reference for the EIS related to Topography, geology and soils issued by the Queensland Government for the quarry project. This report details the planned overburden management activities and associated components that will be required for the pre-operation stages of the project. The report determines the appropriate overburden management strategy based on: The volume of each type of overburden produced at each phase of each stage of the project; The characteristics of each type of overburden produced by the site activities, including density, strength, degree of weathering; The end use of each type of overburden both on and off site that includes; Stockpiling topsoil on site for future use; Rock overburden will be used as controlled fill onsite; and Excess rock overburden will be transported offsite for use elsewhere. During the establishment and development phases it is expected that approximately 3Mt of overburden, which includes topsoil will be produced. Topsoil will be stockpiled on site for future re-use in rehabilitation. The general strategy for overburden to go offsite may be sale to market, as market conditions allow, transport to another large fill project or to the West Burleigh quarry for controlled filling. Overburden that remains on site will be utilised for platforms, embankments, and dams as required. Ref: B12119MR004RevC-OMP - iv - OMP- BORAL Gold Coast Quarry

1.0 INTRODUCTION This report serves to provide details about the management of the overburden during the preoperational stages of the proposed Gold Coast Quarry. 1.1 TERMS OF REFERENCE (TOR) This report has been prepared in accordance with the requirements of section 4.2.3 Topography, geology and soils of the Terms of Reference. Discuss overburden management including end use of such products and expected volumes. Ref: B12119MR004RevC-OMP - 1 - OMP- BORAL Gold Coast Quarry

2.0 PROJECT DESCRIPTION Boral is proposing to establish a new extractive industry operation on a greenfield site, Lot 105 on SP144215 at Old Coach Road, Reedy Creek as shown in Figure 1, below. Figure 1 - Location Map Ref: B12119MR004RevC-OMP - 2 - OMP- BORAL Gold Coast Quarry

The project is necessary to compensate for the scheduled winding down of Boral s existing West Burleigh Quarry (the location of this quarry is detailed in Figure 1), which has sufficient reserves for only a further 6.5 to 9 years of production (depending on market conditions). Given the lead times that are involved (in gaining development and environmental approvals; establishing the operation and completing preliminary site works in order to enable full scale production), it has been necessary for Boral to commence the relevant approval processes to ensure that an adequate, uninterrupted and efficient supply of construction materials remains available for critical infrastructure and construction projects in the Gold Coast region. The Gold Coast Quarry will represent an investment of $140-$160million (2012 [1] dollars) by Boral into the economy of the Gold Coast region and is projected to provide continuity of employment for approximately 100 staff across Boral s integrated quarrying, asphalt, concrete and transport operations. An estimated total of 246 full-time equivalent (FTE) person-years will be directly required for the development and on-site construction of the project. The flow-on benefits of this employment would generate further employment opportunities for the wider Gold Coast region and Queensland, resulting in a total of approximately 480 and 490 full-time equivalent personyears, respectively. Once operational, the proposed Gold Coast Quarry would directly generate 24 FTE positions. The flow-on benefits of this employment would support about 65 FTE positions in Queensland, with 62 positions generated in the Gold Coast. The proposed Gold Coast Quarry would provide a net increase in employment opportunities and help continue quarrying industry jobs within the area once the West Burleigh Quarry resources are exhausted. The site of the proposed Gold Coast Quarry contains the last and largest known deposit of metagreywacke quarry rock resources on the southern Gold Coast. Meta-greywacke is of extremely high strength and forms the excavated and processed quarry product. The meta-greywacke resource is located within a deposit that is favourably surrounded by ridgelines (reducing amenity impacts) and has the benefit of having substantial vegetated buffers on land owned by Boral. In developing this proposal, Boral has attempted to balance the need to secure this hard rock resource with the social and environmental factors associated with extractive industry development. After taking into account a range of environmental constraints and providing appropriate separation buffers during the detailed design process for the proposed quarry footprint, it has been estimated that a total of 79 million tonnes of measured, indicated and inferred quarry resources have been delineated on the site (within the optimised pit shell and including the area to be developed for the plant and associated infrastructure). Boral has voluntarily sterilised a significant proportion of the resource which is known to occur on the site in order to achieve an appropriate balance between environmental, economic and community interests. [1] Based on the value of the Australian dollar during 2012 Ref: B12119MR004RevC-OMP - 3 - OMP- BORAL Gold Coast Quarry

The proposed development will operate as a quarry for the extraction and processing of hard rock primarily for use in concrete, asphalt, drainage materials, road base, bricks/blocks, pavers, pipes and landscape supplies. Investigations indicate that the quality and consistency of the resource at the site is of equal or better quality than the meta-greywacke deposit situated at Boral s existing West Burleigh Quarry, providing an opportunity to completely replace the current quarry operations at Boral s existing West Burleigh Quarry due to the diminishing supply of consented resources at that site. The proposed Gold Coast Quarry has the potential to supply the Gold Coast region with high grade construction materials for at least 40 years whilst maintaining continuity of employment across Boral s integrated quarrying, asphalt, concrete and transport operations. The greenfield site will be fully developed and operated in accordance with recognised industry best practice. Initial development requires the removal of significant overburden over the first few years of site development, including the introduction of mobile crushing plants to develop the site and value the excavated material. Boral estimates that approximately 5 million tonnes of materials (all types) will be removed from the site to allow the site infrastructure and fixed plant to be built. Overall, the proposed Gold Coast Quarry s processing plants and supporting heavy mobile equipment (HME) will comprise: Mobile Crushing Plants Fixed Plant Mobile Fleet Proprietary modular trains from recognised (best practice) manufacturers such as Sandvik or Metso. The 3-stage road base train consists of a Primary Jaw, Secondary and Tertiary Cone Crushers complete with screens, conveyors and stockpiling conveyors. The second train (for aggregates production) will be the same or similar to the first and may include a vertical shaft impactor (VSI) to improve aggregate quality for use in higher specification applications. Each train will be targeting to achieve a minimum of 300 tonnes per hour of aggregate or base course materials. The estimated capital cost of each train is $6 million (2012 dollars). The plant will be designed as a modern, fit for purpose crushing plant which will target the production of aggregates. It is estimated that the production rate will be between 750-900 tonnes per hour to achieve an annual production of 2 million tonnes. The estimated cost of the plant is $75 million with a construction timeframe of 18-24 months. There will be two distinct fleets, firstly a development fleet which will service the site development and stripping works, through to load and haul service for the mobile crushing trains. The second fleet will be sized to service the 750-900 tonne per hour fixed plant. Over the course of the establishment and operation of the project (refer to Table 1), Ref: B12119MR004RevC-OMP - 4 - OMP- BORAL Gold Coast Quarry

there will be a range of equipment on the site for various periods of time. This equipment includes, amongst others, the following: Excavators; Graders; Front-end Loaders; Bulldozers; Compactors; Articulated Dump Trucks; Water Trucks; Haulage Trucks; and Cranes. The quarrying process commences with a survey of the rock face and bench to be developed (by drilling and blasting). Laser survey equipment defines the rock mass, and an optimised blast hole pattern is designed and drilled. As production requirements demand, the drilled shot is then charged with bulk explosives (from Boral s key supply partner, Orica), and fired, in accordance with the site blasting model and procedures. Once the rock has been blasted, fragmented rock will be loaded from the pit floor onto haul trucks, whereas any larger rock fragments ( oversize ) will typically be broken by a rock breaker before loading. The load and haul fleet will generally be operated continuously during the operating hours of the quarry, in order to maintain continuity of supply for processing. The primary stage of processing involves the use of a jaw crusher and vibratory screens, with crushed product being held in an interim stockpile called a surge pile. From this stage, material will be conveyed to several downstream stages of crushing and screening equipment. After processing, the material will be conveyed to individual product stockpiles. The processing plant, including primary and secondary crushers (and screening to separate dust and aggregates) will be located within the plant and infrastructure area, near the individual product stockpiles. The quarry materials are then either loaded directly by a front end loader ( sales loader ) from the stockpiles, or via overhead storage bins at the plant (under typical conditions), to road haulage trucks. The road haulage trucks then proceed across the weighbridge and through the wheel wash before exiting the site to deliver quarry materials to the market. Section 2.0 of the EIS document provides a more detailed description of the various components of the project. Ref: B12119MR004RevC-OMP - 5 - OMP- BORAL Gold Coast Quarry

2.1 STAGES OF DEVELOPMENT The site will be developed in a sequence of discrete stages, each of which will involve a series of phases: Site establishment (E), development (D), and construction (C) stages (all featuring a number of intermediate phases); Quarry operation stage (Q) (featuring a number of phases) associated with the development of the quarry pit itself; and Rehabilitation and decommissioning of the site once the operations have concluded. The timing and rate of progression through the stages associated with the pit development will be defined by market conditions and demand. It is not appropriate to specify timeframes for the development of each respective phase of the project at this early point, but the quarry will have an operational life of at least 40 years. During the establishment, development and construction stages, the proposed Gold Coast Quarry will operate with mobile plant(s), and be replaced with a permanent fixed plant as soon as practicable after the plant site infrastructure area and initial pit have been established (estimated to occur between 5 to 6 years of the development approval). The staging plans for the project, as prepared by Lambert & Rehbein, detail how the development of the quarry is intended to progress. Table 1 below provides a general overview of the works undertaken as part of each phase of the development stage. Ref: B12119MR004RevC-OMP - 6 - OMP- BORAL Gold Coast Quarry

Table 1 Quarry Development Stages SITE ESTABLISHMENT STAGE PHASE WORKS UNDERTAKEN E1 The external access road and associated intersection (from Old Coach Road) will be constructed. E2 A portion of the access road, as it enters the site from the intersection constructed as part of Phase E1, will be constructed and sealed (with bitumen). Earthworks (cut) associated with the development of the internal road network are undertaken, specifically for the construction of: o o the internal road that will ultimately link to the plant facility and ROM pads; and the access and maintenance road extending to the dam. Temporary weighbridge and wheel wash area will be developed. The water storage dam embankment wall (requiring 89,300 tonnes of fill) and associated spillway will be constructed. Overall, a total of approximately 230,000 tonnes of overburden will be removed from the site as a result of the development of this phase. E3 The extent of the internal access road created in Phase E2 will be sealed with bitumen. The temporary weighbridges and wheel wash areas will be removed and replaced by the permanent facilities. The construction of the facilities pad will be commenced, while the sedimentation pond will also be developed. The temporary buildings associated with the (construction) facilities pad will also be constructed. Filling works will be completed in an existing gully so as to facilitate the future pad area for the plant equipment. Overall, a total of approximately 260,000 tonnes of overburden will be removed from the site as a result of the development of this phase. The extent of filling completed as part of this phase equates to 115,900 tonnes. Ref: B12119MR004RevC-OMP - 7 - OMP- BORAL Gold Coast Quarry

DEVELOPMENT STAGE PHASE WORKS UNDERTAKEN D1 Earthworks associated with the construction of the plant pad will be continuing. These earthworks will be performed in a receding rim fashion in order to minimise impacts on nearby sensitive receptors. By this time the quarry dam and sedimentation pond will be operational. Overall, a total of approximately 770,000 tonnes of overburden will be removed from the site as a result of the development of this phase. Furthermore, approximately 280,000 tonnes of quarry product extracted from the site will be utilised and sold as marketable material. D2 Earthworks associated with the construction of the plant pad will be continuing. Overall, a total of approximately 750,000 tonnes of overburden will be removed from the site as a result of the development of this phase. Furthermore, approximately 560,000 tonnes of quarry product extracted from the site will be utilised and sold as marketable material. D3 Earthworks associated with the construction of the plant pad will be continuing. The ROM pad and ROM ramp will be created, and a small amount of fill will be required to develop this area (24,890 tonne). Overall, a total of approximately 745,000 of overburden will be removed from the site as a result of the development of this phase. Furthermore, approximately 560,000 tonnes of quarry product extracted from the site will be utilised and sold as marketable material. D4 Earthworks associated with the construction of the plant pad will be completed. The final floor level for the plant area equates to RL 34.0m AHD. The final floor level for the ROM pad equates to RL 50m AHD. The stockpile area for the storing of materials will be cleared of its overburden. The stockpile area rock (suitable for product) will be left in place for processing at a more economic rate once the permanent plant has been established. Overall, a total of approximately 215,000 tonnes of overburden will be removed from the site as a result of the development of this phase. Furthermore, approximately 540,000 tonnes of quarry product that can be utilised and sold is extracted. Ref: B12119MR004RevC-OMP - 8 - OMP- BORAL Gold Coast Quarry

CONSTRUCTION PHASE PHASE WORKS UNDERTAKEN C1 The construction / erection of the crushing plant will be commenced. All permanent buildings (e.g. site office, employee facilities, workshop etc.) are constructed. Earthworks associated with the removal of overburden are commenced with respect to extending into the area that will ultimately become the quarry pit. C2 The construction / erection of the crushing plant will be completed. Earthworks associated with the removal of overburden will be continuing with respect to extending into the area that will ultimately become the quarry pit. QUARRY OPERATION PHASE PHASE WORKS UNDERTAKEN Q1 Earthworks associated with Pit Stage 1 will be undertaken. The base levels for Pit Stage 1 will range between RL 78.0m AHD (western end of the pit area) and RL 66.0m AHD (eastern end of the pit area, adjacent to the ROM pad). Q2 Earthworks associated with Pit Stage 2 will be undertaken. The base levels for Pit Stage 2 will be RL 54.0m AHD (eastern end of the pit area, adjacent to the ROM pad). Rehabilitation of the benches associated with the pit will commence as necessary. Q3 Earthworks associated with Pit Stage 3 will be undertaken. The base levels for Pit Stage 3 will be RL 30.0m AHD (western end of the pit area). Rehabilitation of the benches associated with the pit will commence as necessary. Q4 Earthworks associated with Pit Stage 4 will be undertaken. The base levels for Pit Stage 4 will be RL 6.0m AHD (centrally located within the pit area). Rehabilitation of the benches associated with the pit will commence as necessary. Q5 Earthworks associated with Pit Stage 5 will be undertaken. The base levels for Pit Stage 5 will be RL -66.0m AHD centrally located within the pit area). Rehabilitation of the benches associated with the pit will commence as necessary. Ref: B12119MR004RevC-OMP - 9 - OMP- BORAL Gold Coast Quarry

3.0 SITE SOIL AND ROCK CHARACTERISTICS The following interpreted ground conditions represent the average parameters adopted from discussions between L&R, Groundworks Plus and Boral Resource Planning & Development. 3.1 PLANT AREA Material Degree of Weathering Depth (m) Average Strength Interpreted Density (T/m3) Topsoil Residual soil 0-0.05-1.80 Soil/overburden Residual soil 0.05-6 Low Strength 2.00 Greywacke/Argillite Greywacke and/or Argillite Greywacke and/or Argillite Distinctly weathered Slightly weathered 6-10 Moderate Strength 10-16 High strength Fresh 16+ High strength to V High strength 2.40 2.65 2.70 3.2 PIT AREA Material Degree of Weathering Depth (m) Average Strength Interpreted Density (T/m3) Topsoil Residual soil 0-0.05-1.80 Soil/overburden Residual soil 0.05-2 Low Strength 2.00 Greywacke/Argillite Greywacke and/or Argillite Greywacke and/or Argillite Distinctly weathered Slightly weathered 2-6 Moderate Strength 6-11 High strength Fresh 11+ High strength to V High strength 2.40 2.65 2.70 Ref: B12119MR004RevC-OMP - 10 - OMP- BORAL Gold Coast Quarry

4.0 MATERIAL TYPES PRODUCED 4.1 TOPSOIL Topsoil has been designated as, on average, the top 50mm of organic soil across the disturbance footprint. Topsoil will not be removed from the site, instead stockpiled for future reuse in rehabilitation. 4.2 OVERBURDEN (ON SITE) Overburden material is designated as the following two layers: Soil/overburden (Residual soil) Greywacke/Argillite (Distinctly weathered) This material will be primary crushed on site and utilised within the proposed GCQ site for earthworks filling requirements. 4.3 OVERBURDEN (OFF SITE) Overburden material is designated as the following two layers: Soil/overburden (Residual soil) Greywacke/Argillite (Distinctly weathered) This material will be primary crushed on site and exported off site via Truck & Dog as fill material. This material represents the surplus of the overburden required for the onsite earthworks. 4.4 ROCK (PRODUCT) Rock suitable to produce quarry product for sale is designated as the following two layers: Greywacke and/or Argillite (Slightly weathered) Greywacke and/or Argillite (Fresh) This material will be tertiary crushed on site and exported off site via Truck & Dog as both roadbase material and/or gravels. Ref: B12119MR004RevC-OMP - 11 - OMP- BORAL Gold Coast Quarry

Constr.n Development Establishment 5.0 MATERIAL VOLUMES During the phases of the establishment and development stages the following volumes of topsoil and overburden will be generated. Table 2 Material Volumes during Establishment and Development Phase Topsoil (t) Overburden (Onsite) (t) Overburden (Off Site) (t) Rock (Product) (t) Phase E1 1,035-57,800 - Phase E2 5,220 95,760 233,440 - Phase E3 2,880 115,900 263,200 - Phase D1 8,640-768,099 279,005 Phase D2 - - 751,027 559,086 Phase D3 6,300 24,890 745,557 559,086 Phase D4 - - 213,828 540,434 Phase C1 1,292-307,472 0 Phase C2 3,955-941,183 0 TOTAL 29,322 236,550 4,281,606 1,937,611 Both Overburden (off Site) and Product will be exported from the proposed GCQ site, representing a total of 6,219,217t of exported material prior to the Quarry entering its operational stage. Ref: B12119MR004RevC-OMP - 12 - OMP- BORAL Gold Coast Quarry

6.0 MATERIAL PLANNED USE 6.1 TOPSOIL Topsoil will be stockpiled on site for future reuse. A general protocol for topsoil handling is detailed below: The surface of the completed stockpiles will be left in a rough condition to help promote water infiltration and minimise erosion prior to vegetation establishment. Topsoil stockpiles will have a maximum height of 3m in order to limit the potential for anaerobic conditions to develop within the soil pile. Topsoil stockpiles to have an embankment grade of approximately 1V:4H (to limit the potential for erosion of the outer pile face). Topsoil stockpiles will be seeded and fertilised. Soil rejuvenation practices will be undertaken if required prior to respreading as part of rehabilitation works. 6.2 OVERBURDEN (ON SITE) Overburden (onsite) will be used as controlled fill for the pads, embankments and dams required for the proposed GCQ. This material will be processed and placed in accordance with the relevant Australian Standards for Earthworks. General guidelines for fill placement are detailed below: Fill material should be placed in near-horizontal layers of uniform thickness, deposited systematically across the fill area. The thickness of each layer should be appropriate to the compaction equipment to be used and test procedures to be adopted. The maximum particle size of any rocks or other lumps within the layer, after compaction, generally should not exceed two-thirds of the compacted layer thickness. 6.3 OVERBURDEN (OFF SITE) The general strategy for Overburden (offsite) may be: Sale to market, dependent on market conditions. Transport of material to another large fill project. Transport of material to the West Burleigh Quarry for controlled filling activities. Ref: B12119MR004RevC-OMP - 13 - OMP- BORAL Gold Coast Quarry

6.4 ROCK (PRODUCT) Rock material is produced during the Development stage. During this stage a significant quantity of rock is excavated to produce a flat crushing plant and support facilities platform. In total approximately 1,940,000t of rock is expected to be processed (via mobile crushing plants) into roadbases and aggregates suitable for engineering uses. This material will supplement or replace product traditionally supplied from the West Burleigh Quarry into the commercial market. Ref: B12119MR004RevC-OMP - 14 - OMP- BORAL Gold Coast Quarry