The Gore Road Queen Street East to Castlemore Road

Similar documents
Mavis Road Class Environmental Assessment

St. Clair Avenue West Area Transportation Master Plan

Highway 427 Industrial Secondary Plan Area 47 Schedule C Class Environmental Assessment For Arterial Roadways

Commissioners Road West Realignment Environmental Assessment

Bostwick Road. Municipal Class Environmental Assessment. Public Information Centre #2 June 14, City of London

Commissioners Road West Realignment Environmental Assessment

Portage Parkway Environmental Assessment Public Information Centre No. 1

Bostwick Road. Municipal Class Environmental Assessment. October 13, City of London. Bostwick Road Municipal Class Environmental Assessment

Municipal Class EA Study Public Information Centre No. 1 December 13, :00 pm 7:00 pm. Please sign in so we can keep you updated on this study

Improvements Municipal Class Environmental Assessment. Public Information Centre #1 June 11, 2015

Heritage Road Improvements from Steeles Avenue to Rivermont Road

WELCOME TO OPEN HOUSE TWO November 28, 2018

Baby Point Wastewater Pumping Station Forcemain Class Environmental Assessment Study

Recreational Pathway Crossing of Richmond Street Municipal Class Environmental Assessment. Public Information Centre #2 April 22, 2015

City of Toronto. Emery Village Transportation Master Plan

WELCOME TO OPEN HOUSE # 3

City of Cornwall Municipal Class Environmental Assessment. Proposed Improvement and Extension of Lemay Street

FANSHAWE PARK ROAD/RICHMOND STREET INTERSECTION IMPROVEMENTS. PUBLIC INFORMATION CENTRE 2 June 16, 2016

Lower Don River West Remedial Flood Protection Project TABLE OF CONTENTS. Page. Executive Summary

Welcome. Community Consultation Meeting November 28, Review and discuss the Bathurst Quay Neighbourhood Plan Framework

Western Road/Wharncliffe Road North Widening from Platts Lane to Oxford Street. Municipal Class Environmental Assessment Public Information Centre #1

The purpose of tonight s PIC is to:

Second Line West Pedestrian/Cyclist Crossing of Highway 401 Class EA. Second Line West Pedestrian/Cyclist Crossing of Highway 401 Class EA

Better Cycling. The City will update the cycling master plan (London ON Bikes) based on the approved BRT network.

Rapid Transit Implementation Working Group

Public Information Centre No. 1 King-Vaughan Road Bridge Replacement Municipal Class Environmental Assessment City of Vaughan

Blackfriars Bridge Municipal Class Environmental Assessment. Public Information Centre #1 November 19 th, 2014

The West Vaughan Employment Area Secondary Plan Policies

North York Centre South Service Road

Toronto Complete Streets Guidelines

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

Scope of Services. River Oaks Boulevard (SH 183) Corridor Master Plan

GLEN ROAD PEDESTRIAN BRIDGE ENVIRONMENTAL ASSESSMENT STUDY PUBLIC INFORMATION CENTRE #2 OCTOBER 24, 2017

Welcome to the Public Information Update for

The Lincoln Neighborhood Corridor Plan. The LiNC

Vaughan Metropolitan Centre (VMC) Black Creek Renewal CLASS ENVIRONMENTAL ASSESSMENT

Public Information Centre. Welcome

URBAN DESIGN BRIEF. 2136&2148 Trafalgar Road. Town of Oakville

Public Hearing. Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, open house at 4 p.m., formal presentation at 5 p.m.

Rapid Transit Implementation Working Group September 14, 2017

WILLIAM STREET STORM SEWER OUTFALL. PUBLIC INFORMATION CENTRE March 23, 2017

Public Information Centre

GEOMETRIC IMPROVEMENTS AND WATERMAIN LOOPING MUNICIPAL CLASS ENVIRONMENTAL ASSESSMENT

ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville. Environmental Screening Report

Don Mills Crossing Study and Celestica Lands Development Application Community Meeting, Open House, and Breakout Discussions

Meeting Agenda. City of Guelph. River Systems Advisory Committee. Agenda Items. Item 1, 2 and 3. Item 4 Ward to Downtown Pedestrian Bridge

SPECIAL COMMITTEE OF THE WHOLE DECEMBER 9, 2002 BLOCK 57/58 WEST BLOCK PLAN BLOCK PLAN FILE BL.57/58W.99 HUNTINGTON BUSINESS PARK LAND OWNERS

Adelaide Street / Canadian Pacific Railway (CPR) Grade Separation. Public Information Centre #1

Welcome. Walk Around. Talk to Us. Write Down Your Comments

Burloak Drive Grade Separation

Master Environmental Servicing Plan & Secondary Plan

38 Queen s University Campus Master Plan Part 1

Adelaide Street / Canadian Pacific Railway (CPR) Grade Separation Class Environmental Assessment. Public Information Centre 3

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A

Seneca Meadows. Block 4 Locate office, technology, and medical development adjacent to I Screen views of garage structures from I-270.

This page left intentionally blank.

elcome Public Information Centre No. 3 May 12, 2009 Burnhamthorpe Road East From Arista Way to Dixie Road Class Environmental Assessment (EA) Study

Public Information Centre #1

7.0 SOCIAL, ECONOMIC, AND ENVIRONMENTAL ISSUES

Welcome. Date: Thursday March 2, 2017 Time: 6:30 p.m. 9:00 p.m. Location: Woodview School Gym, 69 Flatt Road, Burlington Presentation Time: 7:00 p.m.

Report to: Development Services Committee Report Date: April 24, 2017

London s Bus Rapid Transit System

URBAN DESIGN BRIEF Gordon Street City of Guelph. Prepared on behalf of Ontario Inc. March 25, Project No. 1507

Appendix B-13: Community Stakeholders Group Meeting Materials and Minutes

Lambeth Main Street Streetscape Improvements

Elfrida Growth Area Study

East River Waterfront Esplanade and Piers New York, New York Draft Environmental Impact Statement

PUBLIC HEARING. Thursday, December 14, 2017 FDOT Urban Office 2198 Edison Avenue Jacksonville, FL 32204

Maplewood Avenue Downtown Complete Street Project

Shift Rapid Transit Public Participation Meeting May 3, 2017

PLANNING, DESIGN & DEVELOPMENT OPEN HOUSE

Public Information Centre # 2 Coronation Park Drainage Improvements Town of Oakville Municipal Class Environmental Assessment

Laird in Focus Community Information Session

Environmental Study Report

SECTION II SECTION II STATEMENT OF GOALS, OBJECTIVES, PRINCIPLES, ASSUMPTIONS, POLICIES AND STANDARDS

Derry Green Corporate Business Park

Integration of Trees into Roads Policy - the road to success -

GUIDELINES WESTON LOCATION: URBAN DESIGN GUIDELINES

Master Plan Class Environmental Assessment for Downtown Mississauga Road Improvements

Lakeview and Port Credit District Policies Review Public Engagement Process

Ashbridges Bay TTC Maintenance and Storage Facility

TORONTO TRANSIT COMMISSION AND THE REGIONAL MUNICIPALITY OF YORK

Master Environmental Servicing Plan & Secondary Plan

Alternative Routes. St. Vital to La Verendrye Station - Southern Loop Transmission Corridor. 20 different segments 4 segments common to all routes

Scarborough Waterfront Project

Chairman and Members of the Planning and Development Committee. Thomas S. Mokrzycki, Commissioner of Planning and Building

A larger version of this map is located on the last page of this PDF.

EXECUTIVE SUMMARY. Introduction

Inform you of the purpose and scope of the study for PTH 100 and a proposed future St. Norbert Bypass;

Emery Village Road 2A Municipal Class Environmental Assessment Study

Figure 3-1: Public Realm Plan

Update. What is the Osborne Bridge Rehabilitation project all about and how is it being planned? Neighbourhood Advisory Committee (NAC)

Building Great Neighbourhoods. Strathcona

SECTION 4(f) DE MINIMIS DOCUMENTATION

TABLE OF CONTENTS Page

SCTPO Project Summary September 2014

Table of Contents. Executive Summary...S-1

PROPOSED REDEVELOPMENT OF THE GLEN ABBEY GOLF CLUB. STREETSCAPE DESIGN STUDY (excerpt from the Urban Design Brief) TOWN OF OAKVILLE.

Presentation Overview

The Cambie Corridor 2015 Fall workshop series. What we heard WORKSHOP OUTLINE

Transcription:

Municipal Class Environmental Assessment The Gore Road Queen Street East to Castlemore Road Public Open House # 1 Date: Thursday May 29, 2014 Time: 5:30pm to 8:30pm Location: Gore Meadows Community Centre

1 Welcome to Public Open House # 1 We invite you to learn about the Municipal Class Environmental Assessment for The Gore Road (from Castlemore Road to Queen Street East) Questions? Ask any member of the team here tonight. If we don t have an answer, we ll get it for you This evening we will introduce you to the project, specifically: What this study is about Why this planning study is being done What has happened so far What the planning process is moving forward How you can help plan the improvements to The Gore Road We are looking for your feedback. Please take a sheet from the registration table and record your comments on: The work we have done to date. What areas of study are important to you? The environment? The cultural features? The flow of transportation? The proposed criteria for evaluating the improvements Please submit your comment sheet here or send your feedback to Neal Smith, Project Manager, Region of Peel neal.smith@peelregion.ca

2 Why This Study? Why Now? We are one of the fastest growing Regions in Canada. As our population grows, so does our demand for safe and efficient roadways that accommodate cars, transit, pedestrians and cyclists The recent widening of The Gore Road stems from planning work that was completed over a decade ago to accommodate the growth that we see today and expect by 2020 Since good planning takes time, we re starting now to investigate options and complete the necessary studies for The Gore Road to be ready for future growth beyond 2020 McVean Drive Corridor under Study The Gore Road Clarkwway Drive

3 Making The Gore Road Better Complete Streets. The intent is for The Gore Road to be as functional and comfortable as possible for all who use it. This includes children, seniors, cyclists, motorists, transit users and pedestrians, including those with disabilities. Ensuring that there is a place for trees and the natural environment are other key characteristics of a complete street Recent improvements to The Gore Road have included the addition of 2 lanes, sidewalks, intersection redesign and turning lanes Other work included bridge widening, utility relocation, drainage improvements and safety measures such as school crossings Design concepts for this study will consider: - Better transit facilities (e.g., bus bays, shelters) - Continuous sidewalks and safer pedestrian crossings - Space for cyclists - Traffic signal coordination - New or modified bridges - Additional through lanes or turning lanes - Multi-use path to The Gore Road Meadows Community Centre Source: Complete Streets by Design, Toronto Centre for Active Transportation

4 Design Ideas to Consider Many cities have found ways to improve the safety and attractiveness of walking and cycling. Here are some ideas that may be considered for The Gore Road: Eglinton Avenue West Etobicoke, Toronto Bike path and sidewalk set back to create car waiting area at stop sign for minor cross street and reduce blockage of sidewalks and paths Separate bicycle and pedestrian crossings where multiuse pathways cross an intersection Bicycle detection through in-pavement detectors and/or push buttons Rochussenstraat Rotterdam, The Netherlands Separate areas for pedestrians, cyclists, and bus loading at bus stops Dedicated traffic signals for left turns, right turns, bicycles, and pedestrians to reduce conflicts between turning vehicles and crossing cyclists / pedestrians Eendrachtsplein Rotterdam, The Netherlands Protected waiting area behind the curb for waiting through and turning cyclists Setback crosswalk reduces pedestrian crossing distance High-visibility crosswalk and bicycle markings at conflict areas Two-stage turn queue boxes for bicycle left turns Sherbourne Street Toronto Finch Hydro Corridor Trail North York, Toronto Bedumerweg Groningen, The Netherlands Source of all photos: AECOM

5 Study Schedule and Planning Process 2000-2002 November 2002 - The Gore Road EA Completed 2005-2013 Design and Construction (2 Phases) 2011-2012 Peel Long Range Transportation Plan (LRTP) Update We Are Here Winter/Spring 2014 Phase 3a Summer/Fall 2014 to Winter 2015 Phase 3b Spring/Summer 2015 Phase 4 Recommendations included: The Gore Road widening from Queen Street East to Castlemore Road (2 to 4 lanes in certain sections) Realigning the centreline south of Fitzpatrick Drive to mitigate impacts to cemeteries and watercourses This phase involved: Detailed design and approvals Acquiring 45m of right-of-way Construction in phases This phase involved: Identifying The Gore Road improvements (e.g., future widening, transit enhancements and active transportation) High level evaluation of alternative solutions Addressed Phases 1 and 2 of the Class Environmental Assessment Process This phase involves: Confirm Phases 1 and 2 of the LRTP Problem and opportunity statement Document existing and future conditions (e.g., traffic, natural, socioeconomic and cultural environments) Field investigations (e.g., natural environment) Preliminary design concepts This phase involves: Review and consider input received during and following Public Open House # 1 Evaluation of alternative design concepts Preliminary recommended design concept Project description Mitigation measures Next steps This phase involves: Review and consider input received during and following Public Open House # 2 File Environmental Study Report Public opportunity to request additional studies and review by the Minister of the Environment

6 Future Land Use City of Brampton, Secondary Plan Area 47 1 Corridor under Study 3 2 1 2 3 Project Study Area

7 Problem/Opportunity Statement The problem/opportunity statement forms the basis for the entire study. For The Gore Road, the statement is: Approved and planned growth within and outside the study area will require improvement to avoid traffic congestion and deterioration of road conditions over the next 10 to 25 years These factors affect the level of service and adequacy of the road resulting in the need for improvements Alternative design concepts to address these problems will consider opportunities to increase road capacity, enhance streetscape conditions and encourage the use of non-auto modes of transportation by providing supporting infrastructure based on Complete Streets (e.g., transit stops, better accommodations of cyclists and pedestrians including people with disabilities)

8 Transportation Existing and Future Conditions

9 Transportation Operations and Safety Traffic Volumes/Growth The Gore Road has experienced dramatic growth in usage since the 1990s but demand has leveled off since 2006. Planned development to the north of Castlemore Road and beyond is expected to trigger a surge in future demand. The Gore Road will be congested when that development is complete (after 2020) Intersection Operations/Congestion With the recent widening, all intersections on The Gore Road currently operate well, with the exception of Queen Street, where several movements are delayed during peak periods. Delays are also known to occur during concentrations of school, religious, or banquet traffic Vehicular Safety We are continuing to investigate the safety record of The Gore Road, but nothing unusual or problematic has emerged yet Transit In peak periods, there is a bus on The Gore Road every 12 minutes south of Cottrelle, and every 20 minutes to the north. Brampton Transit plans to increase service in accordance with demand. Brampton has designated The Gore Road as a Primary Transit Corridor Pedestrian Movement and Personal Safety A multi-use trail is planned for the west side of The Gore Road Improvements can be made in maintenance practices that will help the pedestrian environment Cycling Activity and Safety Only Castle Oaks Crossing has bike lanes today Bicycle Lane on Castle Oaks Crossing Need to maintain clear paths for pedestrians 12,000 10,000 8,000 6,000 4,000 2,000 0 Average Daily Traffic on The Gore Road Brampton Transit in The Gore Road Area NB SB

10 Existing Environmental Conditions: West Humber Tributary Fluvial geomorphology is used to understand the historical and possible future movement of the stream channel allows for the proper planning of road structures such as bridges and culverts So far, we have reviewed historical aerial photography as well as surficial geology, land use and topography Future activities include a field assessment along the stream to collect additional important data

11 Existing Environmental Conditions: Aquatic (water) Field investigations on various aquatic features of the adjacent stream will identify how road improvements could affect fish communities and habitat Preliminary research has confirmed that this is currently classified as a degraded warm water stream with no sensitive species Future investigations will study fish habitat features such as: - Bank stability - Barriers to fish movement McVean Drive Watercourse crossings to be investigated Clarkwway Drive - Aquatic vegetation The Gore Road West Humber River Tributary at North Wylies Bridge-West Side of Road West Humber River Tributary at South Wylies Bridge-East Side of Road

12 Existing Environmental Conditions: Terrestrial (on ground) The following 6 vegetation types are found within the study area: Types 1,2,3 and 5 1. Mineral Cultural Meadow Ecosite 2. Dry-Moist Old Field Meadow Type 3. Fresh-Moist Ash Lowland Deciduous Forest Type 4. Fresh-Moist Willow Lowland Deciduous Forest Type 5. Cattail Mineral Shallow Marsh Type McVean Drive Types 2 and 5 Types 2 and 4 Types 1, 5 and 6 Clarkwway Drive 6. Reed-canary Grass Mineral Meadow Marsh Type None of the above communities are considered to be rare within the Region of Peel or Provincially Significant A tree inventory survey will be completed along the entire corridor Project study area will also be screened for potential Species at Risk (e.g., Butternut Tree, Barn Swallows) Type 2 The Gore Road Type 1 Type 2 Cattail Mineral Shallow Marsh Type Fresh Moist Ash Lowland Deciduous Forest Type

13 Existing Environmental Conditions: Drainage and Stormwater Management Stormwater Management Pond Outlet to West Humber Tributary Castlemore Bridge Wylie North Bridge Stormwater Management Pond South of Castle Oaks Crossing Wylie South Bridge Recessed Catchbasin at Castlemore Bridge Culvert and Drainage Ditch South of Castlemore Road Catchbasin South of Castle Oaks Crossing

14 Existing Environmental Conditions: Archaeology and Built Heritage Archaeology The existing road does not have any archaeological interest, however, there are 12 areas in the surrounding area that may be of archaeological interest Built Heritage The following cultural heritage resources are located near The Gore Road Ebenezer Schoolhouse 4494 Ebenezer Road *Designated* Ebenezer Primitive Methodist Chapel and Cemetery 8999 The Gore Road *Designated* Mature Spruce Tree Line St. John Cemetery Ebenezer Schoolhouse (today Ebenezer Community Hall) recently went through a full restoration

15 Existing Land Uses North Area Primarily open space and institutional recreational Predominately low to medium residential with several schools, religious/spiritual institutions that serve the surrounding community

16 Existing Land Uses South Area Retail commercial uses, provide a variety of goods and services including food, medical, clothing, financial and personal care that cater the ethnically diverse community

17 Preliminary Evaluation Criteria Before we can decide on the best alternatives for The Gore Road, we need to identify the criteria that will be used to evaluate the alternatives Please use the comment sheet to tell us which criteria are important to you Technical Transportation Effect on transit, cycling and pedestrian facilities Effect on local street connectivity Effect on safety Effect on overall network delay and future road capacity beyond 2020 Constructability Effect on ease of construction including phasing Stormwater Management Effect on stormwater management including drainage patterns Utility Conflicts Effect on existing utilities located within and outside of the Region s right of way Natural Environment Terrestrial Features Effects on terrestrial habitats or functions (e.g., trees, shrubs, vegetation) Effect on terrestrial species including Species at Risk Aquatic Features Effects on aquatic habitat or functions Effect on aquatic species including Species at Risk Groundwater and Surface Water Effect on groundwater Effect on surface water Socio-Economic Environment Property Requirements Effect on public property Effect on private property Overall Community Effect on existing established communities and businesses, noise/dust/vibration Effect on planned future land use along corridor Street Character and Vibrancy Effect on visual character of road corridor Effect on urban design Cultural Environment Archaeological Resources Effect on known or potential significant archaeological resources Built Heritage and Cultural Landscape Effect on built heritage resources and cultural landscape features Costs Effect on value/cost-benefit and affordability

18 Alternatives Under Consideration Many alternatives are being considered to address problems and opportunities: Long List of Alternative Ideas Screening Result Alternative Groups for Further Study 1. Increase Intersection Capacity a. More green time for North-South traffic b. Longer traffic signal cycle length c. Double left turn lanes d. High-capacity intersection designs to reduce turning traffic conflicts Carry Forward (Group 1) (for testing and refinement) Carry Forward (Group 1) Carry Forward (Group 2) Carry Forward (Group 2) (at grade options) e. Pedestrian bridges or tunnels across The Gore Road Set Aside, not appropriate in this context Alternative Group 1: Operational Improvements (No Infrastructure) 1a) More green time for N-S traffic 1b) Increase cycle length 1c) Coordinate signal timing 1d) Signage review/ improvement f. Wide median for two-stage pedestrian crossings Set Aside, excessive penalties to pedestrians 2. Increase Roadway Capacity a. Adding one through lane in each direction throughout the corridor b. Use reversible lanes to increase peak direction capacity without widening in both directions 3. Manage Gore Road Operations a. Reduce the number of intersections and driveways Carry Forward (Group 3) Carry Forward (Group 3) (five-lane option with tidal flow operation) Carry Forward (Group 3) Alternative Group 2: Localized Site Specific Infrastructure Changes 2a) Double left turn lanes 2b) High-Capacity intersection designs 2c) Reduce driveway left turns 2d) Implement bus bays b. Implement bus bays c. Restrict left turns (in peak periods, or all day) Carry Forward (Group 2) Carry Forward (Group 2) d. Restrict truck traffic No Further Action, trucks already restricted from using The Gore Road e. Coordinate signal timing f. Increase the speed limit Set Aside, not desirable g. Ensure road signs are clear and properly located h. Restrict advertising and other motorist distractions No Further Action, By-Laws in place i. Providing trip planning and real-time traffic information to influence motorists decisions to use The Gore Road (time, mode, route of travel) Carry Forward (Group 1) Carry Forward (Group 1) No Further Action, GTA-wide activity, not specific to The Gore Road Alternative Group 3: Whole of Corridor Infrastructure Changes 3a) Adding one lane in each direction in part or all of the corridor 3b) Five-lane configuration with Tidal Flow operation (reversible median lane) 3c) Eliminate midblock left turns

19 Analysis and Evaluation Process Review and comment on: - Draft Evaluation Criteria - Alternative Design Focus Areas: - Increasing intersection capacity - Increasing midblock capacity - Managing corridor operations Grouping of Short Listed Design Alternatives Consider Feedback from Public and Agencies/ Stakeholders Confirm Evaluation Methodology Weighting/scoring vs Paired Comparison vs Multi- Factor Evaluation Approaches Qualitative + Quantitative Develop Evaluation Criteria Public Open House #1 May 29, 2014 *We Are Here* Respond to Agency and Public Comments Alternative Design Concepts including Supporting Plans Showing Limits of Construction Evaluation of Alternative Design Concepts and Select the Recommended Concept Project Team/ Region Meeting Agency/Stakeholder Meetings Refine/Finalize Alternative Design Concept Evaluation for Presentation to the Public Public Open House #2 Early 2015 Consider Feedback from Public and Agencies/ Stakeholders Alternative Group 1: Operational Improvements (No Infrastructure) Alternative Group 2: Localized or Site Specific Infrastructure Changes Alternative Group 3: Whole Corridor Infrastructure Changes Overview of POH #1 Review of engineering assessments Identification and Evaluation of Alternative Design Concepts Recommended Alternative Design Concept including Project Description and Property Requirements Mitigation Measures Next Steps Respond to Agency and Public Comments

20 What s Next for the Study? Study s Next Steps Confirm existing conditions through site specific investigations Spring/Summer 2014 Describe and evaluate alternative design concepts Fall/Winter 2014 Identify preliminary recommended design concept Early 2015 Consult with key stakeholders and review agencies prior to Open House # 2 Notification and hosting of Open House # 2 Early 2015 Please note, timing and cost of improvements are determined at the end of the study following confirmation of the recommended design alternative(s).

21 How You Can Participate Planning Your Way The best plan for The Gore Road will be created with input of the community Thank you for your participation and feedback today Please submit your comment sheet here or send your feedback by email, fax or letter to Neal Smith or Stephen Schijns (see below) To stay connected, please visit the study website at www.peelregion.ca/thegoreroad If you have signed in, you will be added to the study mailing list Neal Smith, C.E.T Project Manager Region of Peel 10 Peel Centre Drive, Suite B, 4 th Floor Brampton, Ontario L6T 4B9 Tel: 905-791-7800 ext. 7866 Toll Free: 1-888-919-7800, Fax: 905-791-1442 Email: neal.smith@peelregion.ca Stephen Schijns, P.Eng Project Manager AECOM 5080 Commerce Boulevard Mississauga, Ontario L4W 4P2 Tel: 905-238-0007 Direct: 905-206-8136 Email: stephen.schijns@aecom.com

The Gore Road s Role in the Community We want to know what The Gore Road means to you and how it can best suit your needs in the future Using the sticky dots, highlight areas on the large map that are of concern and use post-it notes provided here to tell us what you feel should be important considerations when it comes to planning for your road and the community. Use this list to get you thinking: Safety Economic Vitality Utilities Traffic Congestion Place post-it notes on blank space below Noise Right of Way Constraints Water Crossings Cultural Heritage Resources School Crossings Aging Society Cycling Crossing Areas between Traffic Lights Vibration Walking Path Connectivity Stormwater Management Bridges Access to Businesses Nature Unsignalized Interesctions