SYNCHROTRON RADIATION ABSORPTION AND VACUUM ISSUES IN THE IR*

Similar documents
Vacuum Quality Assurance in Practice

VACUUM PERFORMANCE IN THE MOST RECENT THIRD GENERATION SYNCHROTRON LIGHT SOURCES

A CONCEPT FOR CANCELLING THE LEAKAGE FIELD INSIDE THE STORED BEAM CHAMBER OF A SEPTUM MAGNET*

Status Report about the TPC Detector and Module at CEPC

Radiation Safety issues for the PF-AR in KEK

Radiation Safety issues for the PF-AR in KEK

Injection with front ends open at the ESRF

Machine-Detector Interface

OPERATIONAL EXPERIENCE ON CRYOGENIC SYSTEMS FOR LARGE-SCALE ACCELERATORS AT CERN

Minimizing radiation and beam losses at the ESRF

Abstract. 1 NSRRC, 101 Hsin-Ann Road, Hsinchu 300, Taiwan 2 Dept. of Biomedical Engineering & Environmental Sciences, NTHU, Hsinchu 300, Taiwan

XFEL Collimation and Beam Switchyard Vacuum Issues

Mechanical Concept of the TESLA Detector

The use of NEG pumps and coatings in large vacuum systems: experience and limitations

Technological Challenges for the LHC Vacuum System. Ray VENESS CERN Technology Department Vacuum, Surfaces and Coatings Group

arxiv: v1 [physics.ins-det] 27 Jan 2012

MD456: Monitoring of abort gap population with diamond particle detectors at the BGI in IP 4

Table of Contents. Check the LCLS Project website to verify 2 of 12 that this is the correct version prior to use.

Beam Loss Position Monitoring with Optical Fibres at DELTA

PoS(ICHEP2012)516. The status of the CMS pixel upgrade detector

RAMSES: THE LHC RADIATION MONITORING SYSTEM FOR THE ENVIRONMENT AND SAFETY

Experimental Particle Physics PHYS6011 Joel Goldstein, RAL

Measuring Couch Motion Accuracy with X-ray Beam Fluence

THEORY OR OPERATION 2 SENSOR UNIT - MECHANICAL 6 SENSOR UNIT - ELECTRICAL 8 CONTROL UNIT - MECHANICAL 9 CONTROL UNIT - ELECTRICAL 9 OPTIONS 11

Instrumental technique (MCP detectors) - Kamalesh ( )

2008 JINST 3 S The CMS experiment at the CERN LHC THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS.

ATLAS Beam Abort System Using CVD Diamond Sensors

Goals Understand Responsibilities, Awareness, Communication. Beamline phases Design, Implementation, Commissioning, Operation

Today s Outline - September 12, C. Segre (IIT) PHYS Fall 2016 September 12, / 21

IntegraTorr Sputtered Non-Evaporable Getter. We support your innovation

Status of the PRad Experiment (E )

Vacuum requirements and Beamline interface at the VUV-FEL User Facility

NON-DESTRUCTIVE 2-D BEAM PROFILE MONITOR USING GAS SHEET IN J-PARC LINAC -overview & hardware construction-

The LHCb Outer Tracker: Production & Ageing studies

ESTB Proposal from the Stony Brook University: Test of a RICH-Prototype Based on CsI-GEMs

arxiv: v1 [physics.ins-det] 20 Mar 2017

Particle Accelerators - Their Hazards and the Perception of Safety

Fire Detection System: An Overview

Bunch Length Interferometer System

The Compact Muon Solenoid Experiment. Conference Report. Mailing address: CMS CERN, CH-1211 GENEVA 23, Switzerland

Pocket Dilution Cooler

Seyedeh Sepideh Ghaffari 1 & Seyed Ali Jazayeri 2

Ultraviolet radiation detector to obtain the rate of particles at different heights

Development of the CMS Phase-1 Pixel Online Monitoring System and the Evolution of Pixel Leakage Current

BESSY ventilation concept

A THIN GOLD COATED HYDROGEN HEAT PIPE -CRYOGENIC TARGET FOR EXTERNAL EXPERIMENTS AT COSY

Jurnal UMP Social Sciences and Technology Management Vol. 3, Issue. 3,2015

ICSV14. Cairns Australia 9-12 July, Noise reduction of handheld vacuum cleaners according to geometric optimization of air passages

CONSTRUCTION AND OPERATION. 1. Air Conditioning Operation BE-95 BODY ELECTRICAL AIR CONDITIONING

Diamond Windows & MCP Detectors for Synchrotron Applications

DESIGN, MANUFACTURE AND TEST RESULTS OF THE VTCS CO 2 EVAPORATOR FOR THE LHCB EXPERIMENT AT CERN.

CO 2 COOLING FOR THE LHCB-VELO EXPERIMENT AT CERN.

FEE Diagnostics and Commissioning. June 17, 2008

XEUS mirror calibration:

Metal hydride storage system for MICE experiment at Rutherford Appleton Laboratory. Technical specification.

El63 Laser Acceleration at the NLCTA

First results and developments of the multi-cell SDD for Elettra and SESAME XAFS beam lines

STATUS OF THE LHC EXPERIMENTS.

Use Metal Bellows To Replace Springs Benefits of Precision Metal Bellows as Spring Replacements in Mechanical and Electrical Applications

SPECIFICATIONS MODEL E859C MINI DEHYDRATOR

Commissioning of the ASTA Photoinjector Laser System

LCLS Instruments. Jerry Hastings June 20, 2008 LCLS

ATLAS Diamond Beam Conditions Monitor

HiRadMat facility at the CERN SPS

A Small Refrigerator System for Cooling Thermal Shield of a Large Superconducting Magnet

PHYSICS FORM 5 TRANSFER OF THERMAL ENERGY

EU Diagnostics: Recent progress & near-term opportunities. Frederic Le Guern on behalf of Glenn F. Counsell Programme Manager. 18 th September 2018

Status of the Advanced Virgo detector

When Precision is not good enough

Compact Muon Solenoid Detector (CMS) & The Token Bit Manager (TBM) Alex Armstrong & Wyatt Behn Mentor: Dr. Andrew Ivanov

Figure 1-1 Furnace Front Elevation

7XG3130 ReyArc30 Optical Arc Fault Sensor Energy Management

Radiation Safety for AREAL Phase 1

Doc. No. SP R0. CXI Reference Laser. Prepared by: Jean-Charles Castagna Signature Date Design Engineer

Micromegas detectors for the upgrade of the ATLAS Muon Spectrometer

Expected needs in Electronics for the CERN Experiments. 5 October 2015

Outline Specification: EDSUKMT1 MAN TRAP CYLI NDER GATE

CCD and CID solid-state detectors

Identify the following features and specifications for the ESP1

GEM detectors activity at the Laboratori Nazionali di Frascati of INFN

The ATLAS detector: status of the construction and installation a year before the first p-p collisions at the LHC Collider

THE THERMOSIPHON COOLING SYSTEM OF THE ATLAS EXPERIMENT AT THE CERN LARGE HADRON COLLIDER

Status Report on LHC Beam Instrumentation

R&D of GEM detector high rate for CBM Experiment at FAIR Muon Chamber R&D in India

AVAILABILITY AND RELIABILITY OF CERN CRYOPLANTS

FRIB Cryogenic Distribution System and Status

Geothermal ORC Systems Using Large Screw Expanders

Competency: Critically evaluate the function of the ionisation chamber in the Linear Accelerator and its importance for correct treatment delivery

EXPANSION JOINT PRODUCTS

Special Aspects in Designing High - Frequency Betatron

SOLAR WATER HEATING SYSTEM VERSOSUN THERMAL SOLUTIONS

ISO AIR FILTERS FOR GENERAL VENTILATION: DETERMINING FRACTIONAL EFFICIENCY

Accelerator Operations Safety Audit of NLCTA / ESB Carsten Hast (CEF)

Laser Safety and Classification Full Version (CA-1110) Advanced Version (CA-1111) Basic Version (CA-1112)

February 12, PHY357 Lecture 11. Experimental Methods. Accelerators. Particle Interactions. Particle Detectors. Full experiment (eg.

ScienceDirect. Development progress of critical equipment in the CSNS cryogenic hydrogen system

High Throughput Large Area Silicon Drift Detectors

Diode-Pumped Solid-State Blue Lasers

LCTPC Setup at the DESY Testbeam. AWLC 14, Fermilab , R. Diener, DESY

FABRICATION AND COMPARISON OF SOLAR WATER HEATER WITH AND WITHOUT SEMI CIRCULAR TROUGH

Transcription:

SYNCHROTRON RADIATION ABSORPTION AND VACUUM ISSUES IN THE IR* J. T. Seeman, SLAC, Menlo Park, CA 94025 USA Abstract The PEP-II B-Factory (3.1 GeV e+ x 9.0 GeV e-) at SLAC operated from 1999 to 2008, delivering luminosity to the BaBar experiment. PEP-II surpassed by four times its design luminosity reaching 1.21x10 36 cm -2 s -1. It also set stored beam current records of 2.1 A e- and 3.2 A e+ in 1732 bunches. Continuous injection was implemented with BaBar taking data. PEP-II was constructed by SLAC, LBNL, and LLNL with help from BINP, IHEP, the BaBar collaboration, and the US DOE OHEP [1, 2]. The interaction region at PEP-II had to bring the multiampere beams into collisions at one point, produce small vertical beta functions (~1 cm), provide beam separation for parasitic beam crossings, provide low backgrounds to the detector, and remove heat generated by synchrotron radiation and higher order modes. All of these constraints made the IR design very complicated. The synchrotron radiation generated by the many dipole and quadrupole magnets had to be absorbed without generating a lot of emitted gas which would cause beam-gas interaction, lost particles, and detector backgrounds. A complication was the permanent magnet dipoles and quadrupoles near the collision point inside the Babar detector used to focus the beam and to provide the beam separation [3, 4]. The IR region extended away from the collision point by about 65 m on each side to accomplish all the needed requirements. Table 1: PEP-II Collision Parameters Parameter Units Design *Supported by US DOE contract DE-AC02-76SF00515. seeman@slac.stanford.edu April 2008 Best Gain Factor over Design I+ ma 2140 3210 x 1.50 I- ma 750 2070 x 2.76 Number bunches 1658 1732 x 1.04 y* mm 15-25 9-10 x 2.0 Bunch length mm 15 11-12 x 1.4 y 0.03 0.05 to 0.06 x 2.0 Luminosity 10 34 /cm 2 /s 0.3 1.2 x 4.0 Int lumin per day pb -1 130 911 x 7.0 174 PEP-II PARAMETERS In PEP-II the Low Energy Ring (LER) was mounted 0.89 m above the High Energy Ring (HER) in the 2.2 km tunnel as shown in Figure 1. The interaction region is shown in Figure 2 where the beams were collided head on. Figure 3 shows the Be vacuum chamber inside the detector with the permanent magnet dipoles on either side. The interface cone angle at the IR between BaBar and PEP-II was at 300 mrad. To bring the beams into collision, LER was brought down 0.89 m to the HER level and then with a horizontal deviation for both rings were made to collide. Since both rings have the same circumference, each bunch in one ring only collides with one bunch in the other ring making the beam-beam interaction much easier. Parameters are shown in Table 1. Figure 1:PEP-II tunnel with LER above the HER. The high beam currents were supported large RF systems consisting of 1.2 MW klystrons at 476 MHz and high power copper cavities with HOM absorbing loads. An RF cavity had three HOM loads with the capability of 10 kw each. At the peak currents the HER cavities each received 285 kw and the LER cavities 372 kw. The average klystron power was 1.01 MW. An overhead of about 20% in power was needed to allow the RF feedback systems to be stable. The power from synchrotron radiation was ultimately deposited in the walls of the vacuum system and had to be removed by water cooling. The vacuum systems were extruded copper in the HER arcs and extruded aluminium with antechambers and photon-stops in the LER arcs. Both rings had stainless steel double walled chambers in the non-ir straight

sections. The chambers were water cooled continuously over their 2.2 km lengths due to beam heating from synchrotron radiation, HOM heating, and resistive wall heating. From beam-off to beam-on the vacuum chambers expanded and high power expansion bellows were needed (Figure 4). shaped components such as stainless steel flanges, discrete masks, and collimator jaws. Figure 2:PEP-II Interaction Region (IR) with head-on collisions. There are four permanent magnets within the BaBar 1.5 T solenoidal field covering +/- 2.5 m. B1 is a dipole. A is a fixed quadrupole. The two magnets B were rotatable quadrupoles with two longitudinal slices each so that a skew quadrupole term could be introduced or an adjustable quadrupole (S. Ecklund, M. Sullivan). Figure 4:Ultimate design of the PEP-II high power expansion bellows module with sliding fingers, compression (hold down) fingers, beam RF seals at the ends, and water cooled HOM absorbers tiles. This bellow could handle over 3 amperes with 1700 bunches with a bunch length (sigma) of 1 cm (N. Kurita). IR VACUUM SYSTEM The beams in a circular e+e- collider emit synchrotron radiation photons in the dipoles and quadrupoles in the interaction region and deposit them in the nearby vacuum chambers [5]. These photons must be absorbed in the vacuum chambers with the deposited power taken away and the emitted gasses pumped away not to cause beamgas backgrounds. A discussion of how this was done in the PEP-II IR will be presented and implications for a Higgs Factory will be shown. The beam-stay-clears in the two rings as a function of distance from the IP are shown in Figures 5 and 6. Figure 3:IR double-walled Be collision chamber with nearby water cooling and permanent magnet dipoles. The vacuum chambers were cooled with water using various techniques. The first was double walled chambers with several mm layer of water between the walls which was used in the straight sections and some in the IR region. The second was cooling channels extruded into the vacuum chamber seen mostly in the LER arcs and some of the IR chambers (Q4 and Q5). The third was copper cooling lines e-beam welded or brazed onto the outside of the copper chambers. The fourth was stainless tubing welded or brazed on the outside of smaller odd Figure 5:HER horizontal and vertical beam stay clears as a function of distance from the interaction point. This information is used to design the vacuum chamber dimensions (M. Sullivan). 175

Figure 6:LER horizontal and vertical beam stay clears as a function of distance from the interaction point. This information is used to design the vacuum chamber dimensions (M. Sullivan). The two energy beams produced x-ray fans inside the detector depending on the location and strength of the quadrupole and dipole magnets. The radiation fans for the incoming HER beam is shown in Figure 7 and for the incoming LER in Figure 8. The masking was designed so that no single scattered x-ray off a mask tip could hit the Be chamber at the IP in the detector. The Be chamber was a double walled chamber with about 1 mm of water in radius that flowed along its length. The cooling could remove about 1 kw of power safely. The cooling lines were arranged so that the water flowed in one side, travelled down the length and then return back on the other side. The cooling water system had a sub-atmospheric pressure so that if a leak developed, no water would enter the BaBar detector. The Be chamber and the permanent magnets were support in a support tube that was stainless steel on both ends and a Be cylinder on the center. The diameter was about 60 cm. Figure 8:Radiation fans on the incoming LER beam showing the masking for backgrounds and the exiting high power photon beam (M. Sullivan). A vacuum chamber schematic near the entrance and exit of BaBar is shown in Figure 9. Here, the chamber divides from one to two for the two accelerators as the beam separate. The various styles of vacuum pumps can be seen in the drawing using any space available. An enlargement of the vacuum chambers in the B1 dipole and the Q2 quadrupole are shown in Figures 10 and 11 showing their three dimensional shapes. Figure 9:Schematic layout of the vacuum chambers just outside of BaBar showing the pumping arrangement. Figure 7:Radiation fans on the incoming HER beam showing the masking for backgrounds and the exiting high power photon beam (M. Sullivan). 176 Figure 10:B1 chamber showing taper and masking.

Figure 11:Q2 chamber showing taper, masking and heavy duty water cooling with tapered sided to reduce local synchrotron radiation heat loading and stresses (S. Ecklund, N. Kurita). The vacuum pressure in a heavily heating chamber from synchrotron radiation will outgas. But with time as a function of dose the outgassing rate will reduce. In Figure 12 is shown the reduced outgassing rate with an integrated dose of over 10 25 photons/m. The reduction with dose does not saturate but keeps reducing. Figure 13:Schematic of the IP showing where higher order modes could be trapped between x-ray masks. Figure 14:Various frequency HOM modes from the bunched beam as displayed in the IR vacuum chamber. Figure 12:Outgassing rates as a function of synchrotron radiation dose (N. Kurita). The reduced transverse dimensions of the vacuum chambers in the IR plus the addition of x-ray masks allow for the capture of HOM fields and associated power deposition from a high power beam. A calculation of HOM fields and frequencies for the PEP-II IR geometry is shown in Figure 13 and the associated modes are shown in Figure 14. The HOM modes added several kilowatts of integrated local power that had to be cooled. The fields were excited by both beams. Because of geometry with two oppositely traveling beams, the two sets of fields could either coherently add or subtract. PEP- II had some modes that added and some that subtracted fields with two beams. A lot of the generated fields were not trapped in the IR chamber but flowed out along the beam line and were dissipated in the vacuum chambers away from the IR, sometime many 10s of meters away. IR PERFORMANCE IMPROVEMENTS Over the years several improvements to the vacuum system in the IR were done. A) The small (10 cm diameter) expansion bellows on each end of the IP Be chambers had to have extra air and water cooling installed to survive the higher combined beam currents. B) The synchrotron and lost particle masking near detector was improved as the currents were raised. C) The high power vacuum expansion bellows went through several designs being able to handle ever increasing HOM powers. See Figure 6 for the best design. D) The HOM screens for the NEG pumps in the IR had to be replaced as some beam HOM power was leaking through the screens and heating the NEG strips to several hundred degrees causing vacuum issues. 177

CONCLUSIONS In the design of an interaction region for an e+e- Higgs factory the designer must minimize the SR power lost in various components and their vacuum chambers. It is important to find creative possibilities to provide vacuum pumping near the IR. Pumping inside of the detector is important if possible. Finally, it is important to shield carefully the detector from x-rays and lost particles for detector data integrity. ACKNOWLEDGMENTS The author and the PEP-II team wish to thank the operations staff, the maintenance crews, the safety teams, and all other supporting staff at SLAC for their hard work and support. The author thanks N. Kurita, S. Ecklund and M. Sullivan for discussions about IR vacuum systems. REFERENCES [1] PEP-II an Asymmetric B Factory, Conceptual Design Report, CALT-68-1869, LBL-PUB-5379, SLAC-418, UCRL-ID-114055, UC-IIRPA-93-01, June 1993. [2] J. Seeman, et. al., PEP-II at 1.2x10 34 /cm 2 /s Luminosity, PAC 2007, pg. 37. [3] M. Sullivan, et. al., Results from a Prototype Permanent Magnet Dipole-Quadrupole Hybrid for the PEP-II B-Factory, PAC 1997, pg. 3330. [4] M. Sullivan, et. al., Further Progress on a Design for a Super-B Interaction Region, PAC 2009, pg. 51. [5] U. Wienands, Vacuum Performance and Beam Lifetime in the PEP-II Storage Rings, PAC 2001, pg. 597. 178