DC Clean Rivers Project - Green Infrastructure Program. ACEC What s New at DC Water?

Similar documents
DC Clean Rivers Project Green Infrastructure Program

DC Clean Rivers Project Green Infrastructure Program Potomac River Project A

Can Urban Redevelopment Restore Aquatic Resources

MSD Project Clear s Rainscaping Program - Neighborhood Scale Rain Gardens

NYC Green Infrastructure Program

4. CONCEPT PLAN DEVELOPMENT

Framework for Post-Construction SMP Program Management

Reducing New York City s CSOs Using Green Infrastructure

FLEET AVENUE GREEN STREET USES VACANT LOT FOR CSO REDUCTION. Thomas M. Evans, AECOM Cleveland, Ohio

Green Infrastructure in the Greater Lansing Area

6.1 Bioretention Areas

SITING CONSIDERATIONS

Sustainable Storm Water Management

Third Ave CSO Integrated Green Infrastructure

North Street Reconstruction & Integrated Stormwater Management System

Melissa Bernardo Hess, PE, CFM February 18, 2016

West Little Pimmit Storm Sewer & John Marshall Green Street Projects. July 7, 2015 Nottingham Elementary School

Moving from Pilots to a Program: Seattle s Green Infrastructure Program: September 20, 2012

6.2 Flow-Through Planter

SITING CONSIDERATIONS

Old Mill Community Association Bioretention Facility

LID/GI and BMP Case Studies

Ken Kortkamp, PE San Francisco Public Utilities Commission San Francisco, CA

Green Stormwater Infrastructure Handbook. Kristin Kerr, P.E. EOA / SCVURPPP November 29, 2018

Rebecca Dohn October 13, 2017

NEORSD Green Infrastructure Grant (GIG) Program Opening Remarks

Citywide Integrated Stormwater Management Plan (ISMP) DRAFT ACTION PLAN REVIEW Public Consultation November 16 th, 2016

Retrofitting Low Impact Development (LID) for Stormwater at Sacramento State. City of Sacramento Sacramento State Facilities Management

GREATER NEW HAVEN WPCA. GREEN REDEVELOPMENT REDUCES CSOs IN NEW HAVEN. Tom Sgroi, P.E. Director of Engineering, GNHWPCA

HEALTH SCIENCES BUILDING REDEVELOPMENT PROJECT

Building Green: An Update on Atlanta's Green Infrastructure Approach

Stormwater Control Plan: Small (Tier 1) Land Development Project

Ames City Hall Campus: Stormwater Improvements

2016 WORKSHOP LVR Field Trip

GREEN STREETS. Lessons Learned from Philadelphia and New York City. Maine Stormwater Conference. November 16, 2015

The Benefits and Challenges Associated with Green Infrastructure Practices

Design and Construction of Bioretention Areas

Blueprint Columbus GI Implementation & Design Guidelines One Water 2014 Technical Conference & Expo

Appendix D - Technical Design Criteria for BMPs

GREEN INFRASTRUCTURE DESIGNS RAIN GARDEN

Two Sides of the Green Infrastructure Coin. Jaren Hiller, PE, LEED AP Nathan Guequierre

STORMWATER FACILITIES OPERATION AND MAINTENANCE PLAN. Example Commercial Project. February 21, 2018

- 33 Years. - HQ in Richmond VA. - New England Merrimack NH Compost Silt fence. - Product Distributors, Manufacturers and Innovators

Project phasing plan (if applicable) 12 copies of site plan

New Development Stormwater Guidelines

Conceptual Green Infrastructure Design in the Point Breeze Neighborhood, City of Pittsburgh

Agenda. NPDES Phase II Program (US EPA, 2003 Pending 2009) Costs of Stormwater Management and How to Structure a Stormwater Utility

Green Infrastructure and Low-Impact Development Technologies

Appendix G. Detailed Design

Concept Plan Report: Lafayette Neighborhood RiverSmart Low Impact Development and Green Infrastructure Development Project.

Low Impact Development at Naval Facilities: Opportunities and Constraints

2008 SWMM, 2010 Revision City of Tacoma

Presentation Item C Annotated Model Outline for a Framework for a Green Infrastructure Plan

Bioretention cell schematic key

Retrofit of the Gwinnett County DWR Facility Using Low Impact Development Practices SESWA 2012 Annual Conference October 19, 2012

Kittson Parkway / Watershed Park Parking Lot

Village of Forest Park. July 27, Sewer Separation Evaluation

Green Infrastructure on Brownfields

Street Flooding Mitigation Plan KYOVA Interstate Planning Commission. Presented to AMPO National Conference October 18, 2017

Small Town Sustainable Stormwater Solutions

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS

March 30, 2017

My Soil Won t Drain, Can I Still Use LID? Rob Buchert, John Knutson, Erik Pruneda

n1. Design 5.4.6a Urban Bioretention 5.4.6a Urban Bioretention Variations: Planter box, Extended tree pits, Stormwater curb extensions.

Stormwater Runoff and the District of Columbia RiverSmart Homes Defined:

FACT SHEET: Pervious Pavement with Infiltration

Successful Green Infrastructure Planning: A Micro-Scale Modeling and Field Investigation Approach

Green City, Clean Waters

Thorncrest Village Neighbourhood Improvements Public Drop-In Event

Western Pennsylvania Conservancy Clairton & Harrison Community Greening Assessment Projects Request for Proposals July 2018

Preparing a Stormwater Control Plan for a Small Land Development Project

Sustainable Stormwater Retrofit Best Practices

Inspection and Maintenance of Stormwater Best Management Practices

Bioretention. Matt Scharver Northeast Ohio Regional Sewer District. #ProjectCleanLake

City of Richland Stormwater Management Plan

Broadway Avenue Streetscape Project City of Albert Lea. Streetscape Design Committee Meeting October 29, 2012

Williamsburg Boulevard Green Streets Project. April 27, 2011 Williamsburg Middle School

Slow it, Spread it, Sink it using Green Stormwater Infrastructure

2012 Saginaw Bay Watershed Conference

Green Infrastructure Recommendations For Parks and Public Spaces

WQ-07 INFILTRATION TRENCH

David Clark, P.E. RW Armstrong & Associates, Inc. June 20, 2012

Monroe Street Reconstruction. Final Corridor Design Presentation & Open House August 16, 2017

Edenfield Avenue Green Street Demonstration Project Neighborhood Meeting

Example Stormwater Control Plan For a Commercial Project 123 Main Street Anytown, USA

Key Environmental Issues in U.S. EPA Region 2 Panel 4 Water Issues

Physical Approaches to Flood Mitigation

WELCOME NEIGHBORS! April 11, 2019

[TEMPLATE FOR] STORMWATER FACILITIES OPERATION AND MAINTENANCE PLAN. [date] [revision date]

Example Stormwater Control Plan For a Residential Subdivision Project. Whispering Pines Lane Anytown, USA

Example Stormwater Control Plan For a Residential Subdivision Project. Whispering Pines Lane Anytown, USA. February 21, 2018

Detroit Stormwater Rules and Drainage Fee Updates

Stormwater Retrofits Made Practical City of Eugene Oregon. Doug Singer, P.E., CSM Principal Civil Engineer City of Eugene Public Works

green streets San Antonio, Texas February 17-18, 2009 Chris Kloss

Horsley Witten Group Sustainable Environmental Solutions. Rich Claytor, P.E. Janet Bernardo, P.E. horsleywitten.com

Integrating Stormwater Management into Municipal Programs: A Cost Effective Method for Achieving Clean Water Goals

Example Stormwater Control Plan For a Commercial Project 123 Main Street Anytown, USA. February 21, 2018

City of Fort Wayne Six-Month Status Report Consent Decree Case # 2:07 cv 00445

County of Prince Edward. Stormwater Management Plan. Agreement in lieu of a Stormwater Management Plan

Post-Construction Stormwater Management Checklist* (5,000 SF or Greater)

Transcription:

District of Columbia Water and Sewer Authority George S. Hawkins, General Manager Briefing on: DC Clean Rivers Project - Green Infrastructure Program Briefing for: ACEC What s New at DC Water? April 7, 2016

Agenda Welcome DC Clean Rivers Project Overview Rock Creek and Potomac River Projects Schedules and Next Steps Questions Green Roof at Fort Reno Reservoir Bioretention in Right-of-Way Bioretention in Right-of-Way 2

DC Clean Rivers Project Overview: Sewer Systems in DC Sunny Day Rainy Day* Combined Sewer System 1 pipe Combined Sewer Overflow = CSO Outfall pipe Outfall pipe Separate Sewer System 2 pipes Outfall pipe Outfall pipe *Discharge occurs when pipe s capacity is exceeded 3

DC Clean Rivers Project Overview: Where is the Combined Sewer System Located? CSO Outfalls Blue Plains Combined Sewer Drainage Area Municipal Separate Storm Sewer System (MS4) Area Combined Sewer System covers 1/3 of the District (12,478 acres) 47 Active CSO outfalls 13 to Anacostia 10 to Potomac 24 to Rock Creek Three receiving waters Anacostia River Potomac River Rock Creek 4

DC Clean Rivers Project Overview: Magnitude of the Problem, DC Water s Solution 3500 1996 2013 2016 LTCP Completed (DC Water Formed) Program Completion 96% Reduction 3254 CSO Overflow (mg/avg year) 3000 2500 2000 1500 1000 500 0 2142 1963 1282 1063 638 54 79 49 43 138 5 Total System Anacostia River Potomac River Rock Creek Total System 5

DC Clean Rivers Project Overview: Consent Decree Timeline January 14, 2016 Consent Decree Modification Entered in Federal Court Public Participation Public Participation 6

DC Clean Rivers Project Overview: Modified Long Term Control Plan CSO s 027, 028, 029: Manage volume equal to 1.2 of rain falling on 133 impervious acres CSO 049: Manage volume equal to 1.2 of rain falling on 365 impervious acres CSO s 025, 026: Separate sewers CSO s 020-024: Control using Potomac River Tunnel 7

DC Clean Rivers Project Overview: GI Implementation - Consent Decree Schedule Potomac River GI Potomac River Projects - A1 and A2 Rock Creek GI Rock Creek Project - A 8

DC Clean Rivers Project Overview: GI Program Drivers Volume Management (Gallons/Cubic Feet) Control Combined Sewer Overflows Cost Effectiveness Responsibility to Rate Payers Maintenance/Asset Management Safety Aesthetics Performance Outreach Build Public Awareness and Stewardship Triple Bottom Line Benefits Deliver Multiple Benefits to the Community 9

Rock Creek Project A: Boundary, Performance, and Schedule Requirements Contract Volume Requirement: Manage 1.2 of runoff from 25-30 impervious acres RFP Development: 2015 - mid 2016 Procurement: mid 2016 early 2017 Design-Build: early 2017 2019 Place in Operation: 3/30/19* Monitoring: 2019-2020 Throughout: Public Outreach & Engagement Coordination with District Agencies Rock Creek GI Area Rock Creek Project A *Consent Decree Deadline Rock Creek Project A 10

Potomac River Project A1: Boundary, Performance, and Schedule Requirements Contract Volume Requirement: Manage 1.2 of runoff from 30-35 impervious acres Potomac River GI Area RFP Development: 2015 - late 2016 Procurement: late 2016 mid 2017 Design-Build: mid 2017 2019 Place in Operation: 6/23/19* Monitoring: 2019-2020 Throughout: Public Outreach & Engagement Coordination with District Agencies Potomac River Project A1 Potomac River Project A1 *Consent Decree Deadline 11

Potomac River Project A2: Boundary, Performance, and Schedule Requirements Contract Volume Requirement: Manage 1.2 of runoff from 15-20 impervious acres Potomac River GI Area RFP Development: 2015 - late 2016 Procurement: late 2016 mid 2017 Design-Build: mid 2017 2019 Place in Operation: 6/23/19* Monitoring: 2019-2020 Throughout: Public Outreach & Engagement Coordination with District Agencies Potomac River Project A2 Potomac River Project A2 *Consent Decree Deadline 12

Rock Creek and Potomac River Projects: Expected GI Technologies Typical Bioretention Physical Components Inlet with Energy Dissipation (Downstream Outlet Not Shown) Safety Fence Bioretention Soil Media Impermeable Liner Choker Layer to Prevent BSM Migration Aggregate Layer for Storage Perforated Underdrain Connects to Solid Pipe to Sewer Separate Sewer System Typical Sizing Approximate width: Width of planter strip and or parking lane (for curb extension bioretention) Approximate Depth: 4-6 Approximate Length: 20-40 Note: Utilities not shown (adjacent and within facility) 13

Rock Creek and Potomac River Projects: Expected GI Technologies Typical Bioretention Two Applications: Planter Bioretention Curb Extension Bioretention Variations for Additional Storage: Option for combined Planter Bioretention & Curb Extension Bioretention Option for subsurface adjacent aggregate storage under sidewalk Separate Sewer System Planter Bioretention Curb Extension Bioretention in Parking/No Parking Lane 14

Rock Creek and Potomac River Projects: Expected GI Technologies Typical Permeable Pavement Physical Components Permeable Pavement (Type to be Selected Based on Site-Specific Conditions) Choker Layer to Prevent Sediment Migration Impermeable Liner Storage Layer Perforated Underdrain connects to Solid Pipe to Sewer Separate Sewer System Typical Sizing Approximate width: Width of parking lane/alley Approximate Length: Up to entire length of parking lane/alley Approximate Depth: 3-4 Note: Utilities not shown (adjacent and within facility) Permeable Pavement 15

Rock Creek and Potomac River Projects: Expected GI Technologies Typical Permeable Pavement Two Applications: Parking Lane Permeable Pavement Alley Permeable Pavement Separate Sewer System Parking Lane Permeable Pavement Alley Permeable Pavement 16

Rock Creek and Potomac River Projects: Expected GI Technologies Typical Parking Lane Storage Physical Components New Pavement (Type to be Selected Based on Site-Specific Conditions) Inlet Storage Layer Impermeable Liner Perforated Underdrain Connects to Solid Pipe to Sewer Parking Lane Subsurface Storage Typical Sizing Approximate width: Up to full width of parking lane/street Approximate length: Up to entire length of the block Approximate Depth: 3-4 Note: Utilities not shown (adjacent and within facility) 17

Rock Creek and Potomac River Projects: Expected GI Technologies Typical Crosswalk Subsurface Storage Physical Components New Pavement (Type to be Selected Based on Site-Specific Conditions) Inlet (Type to be Selected based on Site-Specific Conditions) Storage Layer Perforated Underdrain Connects to Solid Pipe to Sewer Typical Sizing Width: Entire width of crosswalk Length: Entire length of crosswalk Approximate depth: 3-4 Crosswalk Subsurface Storage Note: Utilities not shown (adjacent and within facility) 18

Rock Creek and Potomac River Projects: Expected GI Technologies Typical Sewer Separation Typical Sizing Approximate width: Varies based on site specific conditions Physical Components New Pavement Approximate length: Up to entire length of the block Approximate depth: Varies New Stormwater Pipe Existing Combined Sewer Pipe Piped Wastewater from Homes Sewer Separation Note: Utilities not shown (adjacent and within facility) 19

Rock Creek and Potomac River Projects: Current Estimated # of Facilities* GI Application RC-A PR-A1 PR-A2 Planter Bioretention 45% 10% Curb Extension Bioretention 15% 25% Parking Lane Permeable Pavement 15% 40% Alley Permeable Pavement 25% 25% 20% Subsurface Storage 75% Sewer Separation 5% *To be refined for 100% request for proposals; limited amounts of non-right-of-way bioretention and permeable pavement may be included. 20

Rock Creek and Potomac River Projects: Contract Organization DC Water and Sewer Authority (Director, DC Clean Rivers Project) Assistant Director DC Clean Rivers Project Program Consultants Organization (PCO) Project Review Board (Advises DC Water) Greeley and Hansen-and-Jacobs Associates (Assists in Administration of DC Clean Rivers Project) Design-Build Design-Bid-Build Design Builder Construction Manager A/E Construction Manager Contractor Designer Contractor (Contracts with DC Water) 21

Rock Creek and Potomac River Projects: Design Builder Roles and Responsibilities 50% - 60% Design of Projects (RC-A, PR-A1, and PR-A2). DC Water to provide the following: GI Facility Elements Locations of facilities specified Minimum volume specified Design details specified (lengths, widths, depths, materials) Underdrain requirements and proposed underdrain layouts and tie-ins Planting plans/palettes Design of temporary facilities not provided i.e., MOT, Support of Excavation, E&S, etc. Existing Conditions ROW Field Survey Field inventory for drainage from private property Level C utility survey (entire ROW) Level A utility survey (GI-specific locations) Geotechnical and Environmental Data Reports (GDR/EDR) Utilities (and existing conditions) information from survey Underdrain GI Facility Footprint GI Facility Drainage Area Unique GI Facility ID (linked to specific design parameters in RFQ) 22

Rock Creek and Potomac River Projects: Design Builder Roles and Responsibilities Design-Build Team Contractual Responsibilities Design Temporary Facilities and Obtain Permits Not Obtained by DC Water Construction of All Facilities Outreach (in Coordination with DCCR Outreach) Maintenance/Asset Management of all Facilities for Initial Maintenance Period (1 Year) Project Closeout Including Service Manuals (non-dccr standard elements) 23

Rock Creek and Potomac River Projects: CM Services Roles and Responsibilities Preparation of project CM plan Tracking construction permits Construction administration and CM services CM safety plan Independent QA/QC verification Project controls DC Water and third-party security programs Environmental compliance monitoring 24

Rock Creek and Potomac River Projects: Green Jobs Program in the District Green Jobs Memorandum of Agreement (MOA) created with District of Columbia and DC Water. Goal: 51% of new jobs created by contracts or procurements entered into by DC Water with third parties to implement GI required by modified decree are filled by District residents National Certification Program led by the Water Environment Federation Construction Inspection Maintenance First groups of District residents will be certified in: January 2017 (training to be held Fall 2016) August 2017 Installation of Green Roof at East Side Pumping Station National Certification Contract Details Available at: dcwater.com/green ( Resources Section) Pilot Green Roof Maintenance Training Course Graduates 25

Schedules and Next Steps: GI Design - Build Schedules Item RC-A PR-A1 PR-A2 Release RFQ February 18, 2016 February 18, 2016 February 18, 2016 SOQ/Technical Proposals due April 14, 2016 April 14, 2016 April 14, 2016 Notice to Proceed January, 2017 March, 2017 October, 2017 GI Construction Management Schedule Item Date Release RFQ March 31, 2016 SOQ/Technical Proposals due May 17, 2016 Notice to Proceed January, 2017 Contact Person to Request a Copy of the RFQs: Ms. Kimberly Isom / Kimberly.Isom@dcwater.com District of Columbia Water and Sewer Authority DC Clean Rivers Project. 5000 Overlook Ave, SW., CMF 2nd Floor, Washington, DC 20032-5397 26

Questions? FOR MORE INFORMATION PLEASE CONTACT: Bethany Bezak, PE, LEED AP DC Clean Rivers Project Green Infrastructure Manager Bethany.Bezak@dcwater.com (202) 787-4466 OR VISIT THE WEBSITE: http://www.dcwater.com/green 27