Continuous Commissioning: A Valuable Partner to Retrofit Projects

Similar documents
Submitted to. Texas A&M University at Galveston The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

Submitted to. Texas A&M University-Corpus Christi The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

Auburn University Basketball Arena:

Computing Services Center

Impacts of Optimized Cold & Hot Deck Reset Schedules on Dual Duct VAV Systems - Theory and Model Simulation

Retrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems

Paul McCown, PE, CEM, LEED AP, CxA Sr. Mechanical Engineer SSRCx, LLC Nashville, TN USA

AIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS

Civil Engineering Building

Mechanical System Redesign. Dedicated Outdoor Air System. Design Criteria

The Temperature and Relative Humidity Control in Cushing Library

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner

Song Deng, P.E. Assistant Director Energy Systems Laboratory Texas A&M University College Station, TX

HVAC Controls Upgrades: Requirement Details ( )

HVAC Controls Upgrades: Requirement Details ( )

Physical Plant Complex

Matt Cooper, PE, BEMP, HBDP, Group 14 Engineering Ken Urbanek, PE, HBDP MKK Consulting Engineers, Inc.

On Balance: Heat Rejection Control a Packaged Solution

Improving Performance with a Building Tune-Up. Janice Peterson, P.E. LEED AP Market Manager, Building Operations BetterBricks

An HVAC Audit of the Canberra Institute of Technology

November 11, City of Sparks 215 S. 21 st St. Sparks, NV

Engineers and Contractors - Innovative Technologies to Achieve Highest GeoExchange System Efficiencies for Commercial Projects

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT

Selected Laboratory Energy Efficiency Measures

Continuous Commissioning Report

INTRODUCTION TO: ASHRAE STANDARD 90.1, HVAC System Requirements for Reducing Energy Consumption in Commercial Buildings

Andrea Borowski The Pennsylvania State University University Park, PA November 11, 2002 Consultant: Dr. Bahnfleth Technical Assignment M-3

OSU Alumni Center Phase I Implementation Review. Oregon State University 130 Oak Creek Bldg. Corvallis, Oregon

Improving Control of Dual-Duct Single-Fan Variable Air Volume Systems

How to Cut Chiller Energy Costs by 30%

The Ed Roberts Campus Berkeley, CA

Hot Water a Hot Commodity Better Buildings by Design, February 2012 Burlington, VT

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 11/11/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

MECHANICAL, ELECTRICAL, PLUMBING, AND FIRE PROTECTION CONDITIONS FACILITIES MASTER PLAN MAY

Appendix 13. Categories of Cooling and Heating systems

Free cooling on RTAF Chiller. Integrated option

DACC Health Sciences Building Air Handler Assessment/Study

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

Dehumidification: Energy Efficiency Comparisons

WLAC Facilities Committee Meeting. September 18, 2017

10+ HVAC Troubleshooting Tips for Healthcare Facilities Jerry Hirsch JCI Facility O&M Performance Development Manager.

ASHRAE Guideline 36 Advanced HVAC Control Sequences

MSP WRAP-AROUND MULTIPLE SMALL PLATE DEHUMIDIFICATION TECHNOLOGY VS. CONVENTIONAL DEHUMIDIFICATION IN DEDICATED OUTDOOR AIR SYSTEMS (DOAS)

Technical Report #3 Mechanical Systems Existing Conditions Evaluation

Cork County Energy Agency

Senior Thesis Centre Community Hospital East Wing Addition - Proposal Keith Beidel Mechanical Option 12/05/02 1

HVAC Mandatory Provisions Part II, Page 1

Madeira City Schools Madeira, Ohio. HVAC Assessment. December 2011 (Revised February 2012)

UNIFIED FACILITIES GUIDE SPECIFICATIONS

VARIABLE HEAT RECOVERY IN DOUBLE BUNDLE ELECTRIC CHILLERS. Richard J Liesen 1, Rahul J Chillar 2 1 University of Illinois at Urbana Champaign

Harrington Tower Building

Demand-Controlled Ventilation For Commercial Kitchens

A New Approach to Museum HVAC Design ASHRAE TECHNOLOGY AWARD CASE STUDIES

IES Whole-Building Energy Model Baseline Energy Model Input/ Output Report. East Liberty Presbyterian Church East Liberty Presbyterian Church

BES-TECH TECHNOLOGY & SYSTEM INTEGRATION

The M & V Guided Recommissioning Process. Energy & Water Conservation Program. September 2015 MOO

HVAC DISTRIBUTION and DELIVERY SYSTEMS

FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) 2016 Q1

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

Best Practices for Applied Rooftop ` Systems - Application and. Jerry Cohen President Jacco & Assoc. Installation

DIGI-VAV APPLICATIONS

Digital Precise Air Control - DPAC

Best Practices for Applied Rooftop ` Systems, Applications and. Jerry Cohen President Jacco & Assoc. Installation

Time-Based Scheduling of Residential Ventilation

Sustainability Best Practices for HVAC Retrofits. Cal Poly State University, San Luis Obispo. Presented to the UC/CSU/CCC Sustainability Conference

2009 IECC Commercial Mechanical Requirements

Remodeling Market. Kermit Baker. Remodeling Futures Conference November 9, Harvard University JOINT CENTER FOR HOUSING STUDIES

Agenda and Objectives

RE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana

Copyright 2003 IBACOS, Inc. All rights reserved.

Laboratory Evaluation of Hybrid and Advanced Water Heaters: Performance Overview in Hot Humid Climate

High Efficiency Dehumidification System (HEDS)

INTRODUCTION HVAC BASICS AND HVAC SYSTEM EFFICIENCY IMPROVEMENT SECTION O 4/19/2012

MCH Series Drives. HVAC Application Guide. ag-mch-e2

4. OVERVIEW OF MECHANICAL SYSTEM

Available online at ScienceDirect. Energy Procedia 52 (2014 ) Vishal Vadabhat, Rangan Banerjee

SECTION SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL

RECOMMENDATIONS FOR 15% ABOVE-CODE ENERGY EFFICIENCY MEASURES FOR RESIDENTIAL BUILDINGS

WLAC Facilities Committee Meeting. May 15, 2017

ASHRAE WILL GIVE YOU THE WORLD. This ASHRAE Distinguished Lecturer is brought to you by the Society Chapter Technology Transfer Committee

A. Base Bid: 1. Heating Contractor provide: a. Control sequences for HVAC systems, subsystems, and equipment.

Continuous Commissioning Report

Terminal. Las Vegas, NV. Technical

Mechanical Redesign, Proposal Elizabeth C. Krauss Mechanical Option September 18, 2013

Job Name Control Systems Description Date

Farm Energy Audit Workshop

COMcheck Software Version Review Mechanical Compliance Certificate

HONORABLE MENTION: COMMERCIAL BUILDINGS, EXISTING

Special Topics on Residential HVAC

High-Performance VAV Systems

HVAC Water chiller selection and optimisation of operation

HVAC System Consideration$ 05/14/2012 SAVING MONEY IN HVAC SYSTEMS

ASHRAE Standard 62 Ventilation Report Technical Assignment #1. Calvert Memorial Hospital Prince Frederick, MD

Memorial Student Center Complex (Bldg. 454)

Raised Access Floor - (AE Breadth Area)

AHU Air Handling Unit Fundamentals. j.ilangumaran

FAST AND ROBUST BUILDING SIMULATION SOFTWARE. Chilled Beam Performance: 1 Shelly Street, Sydney

Technical Assignment 3 11/15/04. Executive Summary

Performance of Solar Water Heating Systems in the United States

Transcription:

Continuous Commissioning: A Valuable Partner to Retrofit Projects Yeqiao Zhu Aamer Athar Kenneth Banks Ph.D. PE, CEM PE, CEM Energy Systems Laboratory Sempra Energy Solutions Sempra Energy Solutions Charles Culp Dan Turner Bahman Yazdani Ph.D. PE Ph.D. PE PE, CEM Energy Systems Laboratory, Texas A&M University ABSTRACT Continuous Commissioning (CC) or HVAC system optimization is not only a valuable stand-alone energy saving measure for commercial buildings, but it is also an important escort solution to retrofit projects. Energy retrofit projects typically achieve projected savings. But in cases where savings goals are not being met, optimizing HVAC system performance can be the difference in an underachieving versus a successful project. This paper presents a real-world study of pairing a CC project with an energy retrofit in a 107,000 square foot hospital building. Applying the CC strategy to an underperforming retrofit, projected energy savings were achieved and even increased. Additionally, by increasing supply air capacity, patients, staff and visitors now enjoy improved comfort conditions. This paper also explores the working relationship between an ESCO and a university research laboratory, whose combined efforts led to this remarkable turn around. INTRODUCTION For commercial buildings, modifications in the existing HVAC system is one of the highest recommended energy measure. The scope of the HVAC system retrofit mainly includes VAV conversion of the fans and pumps, using variable frequency drives on constant speed motors and installing/modifying the DDC control system to control and optimize operation and to improve the system efficiency. In most cases, the retrofit projects realize their projected energy savings and payback on time. However, in some cases, the retrofit projects may not achieve the projected goals. Application of post-retrofit system commissioning into the overall energy conservation project can achieve the savings goal and considerably speeds up the payback. In most cases, system optimization can also improve the building comfort conditions. Post-retrofit commissioning of the HVAC system can be a stand alone energy solution for existing buildings and can also act as an escort solution and valuable partner to the retrofit project. This hospital located in central Texas was retrofitted with energy efficient measures including VFD conversion of fans and pumps, chiller and boiler replacement and lighting and EMCS upgrade. However, after the retrofit, almost all of the AHU fans were running at full speed. The energy consumption was higher than the pre-retrofit measured data. By applying the CC strategy to this underperforming retrofit, projected energy savings were not only achieved but also increased considerably. Increasing the supply air capacity has allowed patients, staff and visitors to enjoy a much improved comfortable building environment. The commissioning audit, energy analysis and energy solution measures build into CC were applied to five major variable air volume (VAV) air handling units (AHUs), chiller and boiler plant and the water loops at this hospital at Fort Worth, Texas. The overall operation of the HVAC systems was investigated in detail. Improved measures were also implemented in the plant. Since the implementation of the suggested measures, the air capacity has increased significantly for all the five AHUs. The capacity and lack of air flow for AHU-2 has been totally solved. Optimized operational schedules were also developed for the chiller, boiler, chilled water loop, hot water supply temperature and terminal boxes. Finally, recommendations for improving the maintenance of the terminal boxes and AHUs were also provided. BUILDING AND HVAC SYSTEM INFORMATION The hospital is located in central Texas, and was built in 1986. It is a two-story, 106,841 square foot building. There is a separate 3,969 square foot central plant building. The plant provides chilled water, hot water and steam to the building. Two water-cooled chillers, hot water and steam boilers are located at the central plant. The pumps at the central plant are used to pump chilled water and hot water through all the cooling and heating coils in the building. Eight (8) single duct AHUs provide conditioned air to the hospital. As a part of the retrofit project, VFDs were installed on the pumps, AHUs and cooling towers. Chiller replacement and lighting system upgrades were also completed in the Spring of 1999. Table 1 shows a list of installed VFDs.

Table1: List of Equipment with Installed VFDs Air-side VFD Supply fans Return fans AHU # HP VFD HP VFD AHU-2 60 Yes 15 Yes AHU-3 25 Yes 5 Yes AHU-5 5 Yes None AHU-6 15 Yes 5 Yes AHU-7 15 Yes 8 Yes AHU-8 25 Yes 5 Yes Water-side VFD P-1 (Condenser Water Pump) 15 Yes P-2 (Condenser Water Pump) 15 Yes P-3 (Chilled Water Pump) 40 Yes P-4 (Chilled Water Pump) 40 Yes P-5 (Hot Water Pump) 15 Yes P-6 (Hot Water Pump) 15 Yes CTF-1 (Cooling Tower Fan) 15 Yes CTF-2 (Cooling Tower Fan) 15 Yes COMMISSIONING ACTIVITIES Pre-Continuous Commissioning (CC) Operational Conditions The data collected from the energy management and control system (EMCS) indicated that the majority of the VFDs (especially AHU fans) were running at a constant speed and were not modulating with the load. Most of the VFD fans were running continuously between the speed 90 to 100%, though the outside air temperature was below 45 o F. Figure 1 shows the graphics for AHU-2. Note the fan speed for the supply air (SA) and return air (RA) fans in the lower left-hand corner. Prior to commissioning, any changes in the duct static pressure or discharge air temperature setpoints did not affect the VFD speed. The operation of five AHUs was analyzed using the data collected through the EMCS. Table 2 presents summarized information for each AHU. Operational data for 20 terminal boxes was also collected by checking the position and the response of the dampers and the steam valve by changing the space temperature from 55 o F to 85 o F. It was also noticed that the natural gas consumption has significantly increased. No apparent reason was given by the facility personnel for this increase.

Figure 1. Pre-CC Operation of AHU-2 Table 2. Operation Status of VAV AHUs on 10/23/00 AHU # S-fan speed % R-fan speed % P-setpoint ( H2O) SF P-setpoint ( H2O) RF 2 100 95 4.0 0.3 3 100 95 2.0 0.97 5 95 N/A N/A N/A 6 100 93 1.0 0.94 7 97 97 1.0 1.0 8 100 100 1.5 1.12 Problems Identification The HVAC operation was reviewed in detail by collecting the trend data from the EMCS. During the initial visit, the commissioning engineers took detailed field measurements, performed air-restriction analysis and made sure that all the sensors were reading the correct values 1. It was found that AHU-2 had insufficient airflow both in the summers and in the winters. According to the facility personnel, there were a high number of hot call complaints during the summer period. The supply air fan was running at 100% speed and was not modulating with the load. The actual static pressure was less than 0.3 H 2 O even though the setpoint was set at 4.0 H 2 O. Similar type of investigation was conducted on all the AHUs. The detailed measured results are presented 1 Some static pressure sensors were found to be out of calibration. The sensors were either replaced or were calibrated. in Table 3. The three major problems identified from the field measurements were a) the air resistance from the filters and the coils, b) errors in the static pressure sensor and c) high static pressure set-points. It was also found that for some of the VAV boxes, the damper actuator that controls the amount of the cold air to the boxes was leaking and unable to hold the pressure. As a result of these leaks, dampers in the VAV boxes remained open allowing high volume of cold air to the boxes even in the heating mode, resulting in simultaneous cooling and heating. It was also noticed that some of the reheat valves and controls were not working properly. In some cases, the reheat was on continuously and in other instances, the reheat came on before the dampers started to close. Air balance problems were also noticed. Difference in the supply air temperature for terminal boxes served by the same AHU, high air velocity and noise were indications of air balance problems.

Table 3. Detailed measured results of air-side resistance (inch H 2 O) for AHUs AHU 3 AHU 7 AHU 8 AHU 2 AHU 6 Pre-filter P 1.3 0.5 0.5 0.4 0.46 Cooling coil P 0.8 0.9 0.9 0.6 1.02 Final filter P 1.0 0.34 0.32 7.6 0.3 Duct condition Good Good Good Good Good Static pressure -0.39-0.27-0.36-0.3-0.39 sensor offset Current setpoint 2.0 1.0 1.5 4.0 0.8 Actual setpoint 0.7 to 0.8 0.7 to 0.8 0.7 to 0.8 0.6 to 0.7 0.8 needed for operating condition Operating 70 F to 75 F 70 F to 75 F 70 F to 75 F 40 F to 55 F 45 F to 55 F condition Special Problems The high static pressure caused a rupture on the fan discharge flexible duct Recommended Measures 1. Clean & Replace Air Filters for all AHUs Recommended measures for each of the AHUs are summarized in Table 4. Pressure sensors were also recommended for all the filters. This arrangement would allow the hospital staff to receive a signal from the EMCS to change the filters. Table 4. Recommended measures for AHUs to solve the air resistance problems AHU 3 AHU 7 AHU 8 AHU 2 AHU 6 Pre-filter Replace Replace Replace Cooling coil Clean Clean Clean Clean Final filter Replace Replace Static pressure Calibrate Calibrate Calibrate Calibrate Calibrate sensor offset New static pressure 0.84 0.9 1.0 0.7 0.8 setpoint at operating conditions Special issue Fix the flexible duct Note: This static pressure setpoint is for the existing weather condition. The reset schedule will be presented later. 2. Optimized Control Scheme-Reset Schedules on Air-side The optimal static pressure and discharge air temperature reset schedules were also developed. These suggested schedules were approved by the hospital and were recently incorporated in the control strategy of the EMCS. Electrical and thermal savings from these measures are not available at this time. Data collection is in progress and will be analyzed soon to calculate the savings.

Table 5. Optimized reset schedules for AHUs AHU Reset Schedule for Static Pressure Reset Schedule for Supply Temperature No. 3 0.7 H 2 O if OAT 50 F and ramped to 1.1 H2O if 61 F if OAT 50 F and ramped to 55 F if 7 0.8 H 2 O if OAT 60 F and ramped to 1.2 H2O if 61 F if OAT 50 F and ramped to 55 F if 8 0.8 H 2 O if OAT 60 F and ramped to 1.3 H2O if 61 F if OAT 50 F and ramped to 55 F if 2 0.7 H 2 O if OAT 50 F and ramped to 1.2 H2O if 61 F if OAT 50 F and ramped to 55 F if 6 0.8 H 2 O if OAT 50 F and ramped to 1.3 H2O if 56 F if OAT 40 F and ramped to 55 F if 3. Improved Operation of Chiller Plant and Chilled Water Loop The CC team recommended that the manual balance valves to be opened, and also made recommendations to isolate the chiller loop to run one chiller. With this measure, the chilled water pump power consumption will be further reduced. 4. Optimized Reset Schedules for Chilled Water Loop P Setpoint The chilled water loop P setpoint was set at 26 psi. After the detailed measurements, optimized schedule was generated as follow: 7 PSI if OAT 60 F and ramped to 14 PSI if 5. Improved Operation of Boiler and Hot Water Loop The recommendation to run one boiler when the outside air temperature is higher than 45 F was provided to the hospital. This measure cannot be programmed in to the EMCS, but it can be accomplished by plant operators due to the existing 24 hour shift operation. 6. Optimized Reset Schedules for Hot Water Supply Temperature Setpoint Optimized reset schedule for hot water supply temperature setpoint was also provided to the facility. 155 F if OAT 20 F and ramped to 110 F if OAT 80 F 7. Improved Operation for Terminal Boxes As mentioned in the previous section, it was discovered that there was simultaneous cooling & heating consumption at the majority of the terminal boxes. Almost all the boxes had a 1 F deadband for cooling and heating setpoints. The CC team recommended increasing this deadband to 4 F to 5 F. This will reduce simultaneous cooling and heating. Accomplishing this task was very time consuming, as the only way to change the deadband was to adjust the AUX port in each individual terminal control board at the terminal box location in the ceiling. The CC team successfully adjusted the deadband for 39 terminal boxes. The adjustments on the remaining 205 terminal boxes are in progress and will be achieved by the facility personnel. Commissioning Results The commissioning team and the hospital were able to fix most of the problems by implementing the suggested measures. The new setpoints were implemented immediately at the site. The performance of the AHUs improved significantly. Table 5 presents some of the immediate results. Table 5. Results for VAV AHUs AHU 3 AHU 7 AHU 8 AHU 2 AHU 6 Fan speed 65% to 75% 70% to 85% 65% to 75% 55% to 65% 55% to 65% OAT ( F) 65 to 80 65 to 80 65 to 80 35 to 55 35 to 55

Figure 2 presents a graphic layout for AHU-2 after the implemented measures. Notice the reduced fan speed for the supply air fan (SA Fan) and the return air fan (RA Fan). The reduced static setpoint and the alarms on the filters are also noticeable. Figure 2. Post-CC operation of AHU-2 Continuous Commissioning was also successful on the remaining AHUs. Now all of them modulate with the load changes. The air-side capacity for AHUs has also been increased significantly. Figure 3 and 4 shows the decrease in the electrical demand for all AHUs. The first drop in the electricity demand is in October (1 st trip) and then a much larger decrease can be noticed in November (2 nd trip). Figure 4 shows the electricity demand versus average outside air temperature. Figure 5 shown the decrease in the whole building electricity energy consumption and demand. A significant drop is noticeable after October 2000.

140 120 Total AHU Electricity Consumption April 2000 to March 2001 Baseline kw 100 VFD kw 80 60 Pre-CC kw ` 40 20 0 Post-CC kw Apr-00 May-00 Jun-00 Jul-00 Aug-00 Sep-00 Oct-00 Nov-00 Dec-00 Jan-01 Feb-01 Mar-01 Date Total AHU Vs OA Temp April 2000 to March 2001 140.00 Pre-CC kw 120.00 100.00 VFD kw 80.00 60.00 40.00 Post-CC kw 20.00 0.00 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 OAT

Monthly kwh Consumption (kwh/month) WHOLE BUILDING ELECTRICITY CONSUMPTION & DEMAND (JAN. 2000 - MAR. 2001) 400,000 350,000 300,000 250,000 200,000 150,000 100,000 Pre-CC Post-CC 800 700 600 500 400 300 200 50,000 100 0 0 Jan-00 Feb-00 Mar-00 Apr-00 May-00 Jun-00 Jul-00 Aug-00 Sep-00 Oct-00 Nov-00 Dec-00 Jan-01 Feb-01 Mar-01 Monthly kw Demand (kw) Months CONCLUSION The successful combination of Continuous Commissioning and retrofit project has been presented here. The combination transforms this under-performing project to an energy efficient project. The building environment and the productivity have also been improved significantly. The total measured savings for the period of December 2000 to April 2001 are approximately $20,000. The estimated annual savings will be more than $50,000. ACHNOWLEDEGMENT The authors would like to express thanks to Mr. Jack French, Mr. Brian Barton, and Mr. John Riddle from All Saints Health Care System. The audits and commissioning went very smoothly and everything was well organized during our visits. REFERENCE ESL, Continuous Commissioning SM Audit Report for All Saints Health Care System/Cityview Hospital, ESL-TR-00/12-02