CRAFTSMAN EXAMINATION, NOVEMBER 2009 GASFITTING QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

Similar documents
REGISTRATION EXAMINATION, JUNE 2012 LICENSED GASFITTER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, NOVEMBER 2016 LICENSED GASFITTER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

CRAFTSMAN EXAMINATION, NOVEMBER 2009 PLUMBING QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, NOVEMBER 2017 TRADESMAN PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, NOVEMBER 2014 LICENSED PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

CRAFTSMAN EXAMINATION, JUNE 2007 PLUMBING QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, JUNE 2015 LICENSED PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

Level 1 Economics, 2016

CERTIFYING GASFITTER

REGISTRATION EXAMINATION, JUNE 2013 CERTIFYING PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, NOVEMBER 2011 CERTIFYING PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, JUNE 2015 LICENSED GASFITTER ANSWER SCHEDULE

Level 1 Physics, 2016

Domestic Gas Safety Assessments (DGA) Competency Assessment Certification Scheme for Registered Gas Installers

Standards of Training in Safe Gas Work Domestic Natural Gas Training Specification

Fundamentals of a gas fire New Zealand. August 2017

Gas Flare & Rail Burners Gas Flare & Rail Burners Installation Instructions

Domestic Gas Cookers & Ranges

Level 1 Physics, 2014

Level 1 Physics, 2013

Level 1 Agricultural and Horticultural Science, 2011

Eastside Installation Guidelines and Operating Instructions January 2018

ACS.CCLP1 PD SAFETY ASSESSMENT CRITERIA INITIAL & RE-ASSESSMENT DOMESTIC LPG PERMANENT DWELLINGS

A word from the Chair

RHEEM CONTINUOUS FLOW GAS WATER HEATERS

QUALIFICATIONS AND CREDIT FRAMEWORK (QCF) LOGIC CERTIFICATION LIMITED (LCL) QUALIFICATION SPECIFICATION

Dovre 250 Cast Iron Gas Stove

BASIC BOILERS NAME :- DATE :-

REGULATED QUALIFICATIONS FRAMEWORK (RQF) LOGIC CERTIFICATION LIMITED (LCL) QUALIFICATION SPECIFICATION

Gasfitter A Level 3 Rev. June 2011

CRAFTSMAN EXAMINATION, JUNE 2007 PLUMBING ANSWER SCHEDULE

SG Burner Only

REGISTRATION EXAMINATION, NOVEMBER 2014 LICENSED PLUMBER ANSWER SCHEDULE

Gas (Safety and Measurement) Amendment Regulations 2014

CHAPTER 5 - STRUCTURAL FIRE PRECAUTIONS

our range Page 2 USE TOOLBAR TO NAVIGATE

SIME FORMAT WALL HUNG BOILERS MODEL 34i AND MODEL 34e. cod A

ecotec pro Operating instructions Operating instructions For the operator GB, IE Gas-fired wall-hung high-efficiency boiler

A6VS VENTILATION STANDARDS

ELECTRICAL APPLIANCE SERVICEPERSON EXAMINATION 19 November 2016 QUESTION AND ANSWER BOOKLET

INSTALLATION & OPERATING INSTRUCTIONS GAS HOBS MODELS

Eligibility criteria

(Text with EEA relevance) Reference and title of the harmonised standard (and reference document) EN 26:1997/A1:2000 Note 3 Date expired (18.7.

Domestic Gas Safety Assessments (DGA) Competency Assessment Certification Scheme for Registered Gas Installers

Operation & Installation Manual

REGISTRATION EXAMINATION, NOVEMBER 2011 CERTIFYING PLUMBER ANSWER SCHEDULE

ecotec plus boiler user guide

ALL THE BENEFITS OF THE ALL COPPER HEAT EXCHANGER

Unit 2 Fire Safety (Zone 1)

Operating instructions

Understand and apply domestic central heating system installation and maintenance techniques

DOMESTIC PREMISES GAS INSTALLATION

Different energy sources can be used to generate electricity.

REGISTRATION EXAMINATION, NOVEMBER 2017 TRADESMAN PLUMBER ANSWER SCHEDULE

Gas Instantaneous Water Heater

Non-domestic gas installations (Edition 2)

Document code: 1 (10) Issuing date: Status:

BUILDING OR RENOVATING? Jonathan Smith. The Plumbers, Gasfitters and Drainlayers Board (PGDB) says: ASK TO SEE THEIR CARD

Owner s Guide and Installation Instructions

COMMERCIAL GAS AND ELECTRIC STACKED WASHER/ DRYER INSTALLATION INSTRUCTIONS

Installation & Maintenance Manual

Operating instructions

Unvented Hot Water Criteria

U tube models PTU 09, 12, 15, 25, 30, 35, 40, 45. single linear tube models PTS 09, 12, 15, 25, 30, 35, 40, 45

USER GUIDE. IMAX XTRA EL kW. For Installation Guide see reverse of book

LANDSCAPE BALANCED FLUE SPACE HEATER

Q1. The diagram shows an experiment to find out what happens to infrared waves when they strike different surfaces.

Installation Manual EF5000 AUS & NZ

ELECTRICAL INSTALLER THEORY EXAMINATION. 14 November 2015 QUESTION AND ANSWER BOOKLET

LANDSCAPE BALANCED FLUE SPACE HEATER

Osprey 2 CFL

Trumatic E. Trumatic E 2400 (Australia) Operating instructions Page 4 Installation instructions Page 7. To be kept in the vehicle!

Hunter Hawk Gas Stove User Instructions

GREENFIRE GAS FIREPLACES

INSTALLATION GUIDE NZ AU D

Operating instructions

Heat 45 & 55. User Instructions FAN POWERED HIGH EFFICIENCY MODULATING DOMESTIC CONDENSING GAS COMBINATION BOILER

GB24 & GB30. User Manual

Owner s Guide and Installation Instructions

Baxi Megaflo System HE IE Range. User s Operating Instructions & Important Warranty Information. Gas Fired Wall Mounted Condensing Boiler

USER GUIDE VOGUE MAX SYSTEM

ELECTRICAL APPLIANCE SERVICEPERSON (QUALIFIED) EXAMINATION 18 November 2017 QUESTION AND ANSWER BOOKLET

Operating instructions

PROF. RANGE COOKER MODEL: EPRC-9850FE/SS EPRC-9860E/SS. Owner s Manual Please read this manual carefully before operating your set.

ATMOSPHERIC GAS BOILER INSTALLATION, OPERATING AND MAINTENANCE MANUAL

Debonaire VIRAGE LH

The iqe Boiler Range. Combination and System T Boilers.

Installation & Maintenance Manual

IE059: Boiler Control and Instrumentation for Engineers & Technicians

Combi C30 & C35. User Guide FAN POWERED HIGH EFFICIENCY MODULATING DOMESTIC CONDENSING GAS COMBINATION BOILER

Installation instructions PYROMAT ECO. for contractors PYROMAT ECO GB 8/2012 Dispose after installation.

Wok Cookers Instruction Manual

5 YEAR GUARANTEE. Inovia. High efficiency condensing combi and system boilers

User Manual for model

USER GUIDE LOGIC HEAT H

INSTALLATION INSTRUCTIONS

REGISTRATION EXAMINATION, JUNE 2015 LICENSED PLUMBER ANSWER SCHEDULE

Q1. The diagram shows the inside of a mains plug. Label the earth, live and neutral pins.

Debonaire DUPLO

DOM-5. Domestic Hot Water Heaters & Boilers

Transcription:

Affix label with Candidate Code Number here. If no label, enter candidate Number if known No. 996 CRAFTSMAN EXAMINATION, NOVEMBER 009 GASFITTING INSTRUCTIONS QUESTION AND ANSWER BOOKLET Time allowed THREE hours Check that the Candidate Code Number on your admission slip is the same as the number on the label at the top of this page. Do not start writing until you are told to do so by the Supervisor. Total marks for this examination: 00. The pass mark for this examination is 60 marks. Write your answers and draw your sketches in this booklet. If you need more paper, use pages 6 7 at the back of this booklet. Clearly write the question number(s) if any of these pages are used. All working in calculations must be shown. Candidates are permitted to use the following in this examination: Drawing instruments, approved calculators The following are NOT permitted in the examination room: Any publications, Acts, Regulations, Codes of Practice, or Standards Check that this booklet has all of 7 pages in the correct order and that none of these pages is blank. YOU MUST HAND THIS BOOKLET TO THE SUPERVISOR AT THE END OF THE EXAMINATION Plumbers, Gasfitters and Drainlayers Board, 009. All rights reserved. No part of this publication may be reproduced by any means without the prior permission of the Plumbers, Gasfitters and Drainlayers Board.

Question (a) State THREE types of gasfitting work that, under the Gas Regulations, require certification. ( marks) (b) When a craftsman gasfitter completes a Gasfitting Certification Certificate, he or she completes a description of the gasfitting and certifies three statements on the certificate about that gasfitting. Outline the content of each of the three statements. (6 marks) Total 9 marks Craftsman Gasfitting 996, November 009

QUESTION (a) State FIVE factors that may affect the overall efficiency of a gas-fired storage hot water system. 5 (5 marks) (b) A flueless instantaneous water heater is to be installed over the kitchen sink in an apartment with a separate kitchen. Give the specific conditions that apply to this installation. ( marks) Total 9 marks Craftsman Gasfitting 996, November 009

QUESTION A five-storey high rise apartment building has internal gas riser pipes supplying gas to individual apartments. Specific requirements for this type of installation must be met before the gas installations can be certified as compliant with NZS 56. Give FIVE of these requirements. 5 Total 5 marks Craftsman Gasfitting 996, November 009

QUESTION The diagram opposite shows the proposed layout of an LPG installation. The piping material is to be copper. Table below shows the input rating for each appliance in the installation. Table below provides pipe lengths for the installation. The available pressure is.kpa. kwh =.6MJ Table Appliance Input Rating A Space heater 7.8kW B Central heating unit 75.6MJ/hr E Cooker 88.MJ/hr G Continuous flow water heater 56kW Using the graph opposite, complete Table below. Show your working. Table Pipe Run Length (m) Gas Rate (MJ/hr) Pipe Size (mm) A-C B-C.5 C-D E-D.75 D-F 5 G-F.5 F-H.75 Total 8 marks Craftsman Gasfitting 996, November 009

QUESTION (cont d) B E A C G D F F H H Pressure drop, kpa/m Craftsman Gasfitting 996, November 009 5

QUESTION 5 The gas pressure within an industrial complex is to be reduced from 00kPa to 5kPa. Two regulators are to be installed in a series for over-pressure protection. The maximum allowable operating pressure of the pipework system downstream of the second regulator is 5kPa. Using the correct symbols, draw a line diagram showing the regulators and their impulse lines. Show the pressure in each section of pipework and indicate the direction of gas flow. Total 5 marks Craftsman Gasfitting 996, November 009 6

QUESTION 6 (a) A new LPG domestic gas installation comprising three appliances has been installed. State EIGHT actions that must be carried out when conducting the final installation test. 5 6 7 8 ( marks) (b) A manual shut off valve is to be fitted on the inlet to a domestic gas appliance. State SIX features of the valve that should be considered when selecting the valve. 5 6 ( marks) Total 7 marks Craftsman Gasfitting 996, November 009 7

Question 7 A new domestic gas installation consisting of an open-flued natural gas space heater has just been completed. The appliance does not have a fan. The work was done by a registered gasfitter working under a craftsman gasfitter s supervision. (a) After the installation pressure test has been completed, several aspects of the operation of the heater should be checked by the craftsman prior to certifying the installation. Give SIX of these aspects. 5 6 ( marks) (b) Give SIX matters that must be brought to the attention of the consumer at the completion of commissioning. 5 6 ( marks) Total 6 marks Craftsman Gasfitting 996, November 009 8

Question 8 A kitchen is being renovated and a gas hob is to be fitted in the kitchen bench. The wall behind the kitchen bench has timber framing and will be lined with Gibraltar board. (a) (i) State the minimum clearance distance there must be between the hob and the wall if the wall is lined with Gibraltar board only. ( mark) (ii) Specify the point on the hob where the minimum clearance in (i) must be measured from. ( mark) (b) Give TWO methods of protecting the wall if it is possible to have only 00mm clearance. ( marks) (c) State the minimum height for the wall protection if the clearance is 00mm. ( mark) Total 7 marks Craftsman Gasfitting 996, November 009 9

QUESTION 9 (a) A gas fired automatic commercial laundry dryer has an input rating of 0MJ/h, and is fitted with an exhaust fan. State THREE requirements the flue for the dryer must meet. ( marks) (b) An industrial boiler has a maximum heat output rating of 5000MJ/h. The heating value of the gas is MJ/m and the boiler efficiency is 60%. Calculate the gas input flow rate for the boiler. ( marks) Total 5 marks Craftsman Gasfitting 996, November 009 0

QUESTION 0 A bank of x 5kg LPG cylinders is to supply an installation. List EIGHT factors to be considered when selecting the location for the cylinders. 5 6 7 8 Total marks Craftsman Gasfitting 996, November 009

Question (a) An air curtain is to be mounted above an external door of a warehouse. Give THREE specific conditions that must be met relating to clearances and positioning of the air curtain. ( marks) (b) An overhead radiant tube heater is to be positioned in a warehouse. Give TWO distinct requirements regarding clearances that must be met to avoid damage to the heater. ( marks) Total 5 marks Craftsman Gasfitting 996, November 009

Question (a) An industrial automatic gas burner may develop the faults listed below. Give THREE likely causes for each fault. (i) No ignition ( marks) (ii) No pilot flame ( marks) (b) A boiler situated in the basement of a multi-storey office block is to be fitted with a power flue. Give TWO advantages of the power flue compared with a conventional flue. ( marks) Total 8 marks Craftsman Gasfitting 996, November 009

QUESTION A forced draught package burner fitted with a double block valve assembly is to be installed. Explain what occurs during each of the following periods in the start sequence of the burner. (a) Pre-purge period: (b) Start gas flame ignition period: (c) Start gas flame proving period: (d) Main flame ignition period: (e) Main burner run period: Total 0 marks Craftsman Gasfitting 996, November 009

Question (a) A flue is being designed for a natural draught appliance. Give SIX factors that should be taken into account when determining the size of the flue. 5 6 ( marks) (b) A flue is to be concealed in a wall. State FOUR specific installation requirements that the flue must meet so that it complies with NZS 56. ( marks) (c) An LPG continuous flow fan-assisted water heater is to be positioned on an outside wall. The appliance has an input rating of 0MJ/hr. Give FIVE requirements that must be met to ensure adequate ventilation and disposal of products of combustion. Include minimum distances if any clearances are given. 5 (5 marks) Total marks Craftsman Gasfitting 996, November 009 5

This page is available for additional working or answers Question number Craftsman Gasfitting 996, November 009 6

This page is available for additional working or answers Question number Craftsman Gasfitting 996, November 009 7

For Examiner s use only Question number Marks Marks 5 6 7 8 9 0 Total