Specification and Construction Plans For: South Bethany Landscaping Improvement Plan Contract Number T

Similar documents
Shelbyville, KY Stormwater Best Management Practices. Section 2 EROSION PREVENTION AND SEDIMENT CONTROL PLAN

SUPPORTING DOCUMENT POST-CONSTRUCTION SOIL QUALITY AND DEPTH WORKSHEET

Request for an Exception to the Napa County Road and Street Standards

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

City of Stoughton Erosion Control Permit Application (effective 2/6/2018)

Project: Developer/Designer: Reviewer: I. Narrative: 1. Project Description: Describes the nature and purpose of the land disturbing activity.

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

Nuts and Bolts (or Gravel and Asphalt) of the Main Street Project

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS

SECTION TURF AND GRASSES

CARVER COUNTY DIVISION OF PUBLIC WORKS LANDSCAPE POLICY. Adopted by the Carver County Board of Commissioners March 3, 2015

RAIN GARDEN ILLINOIS URBAN MANUAL PRACTICE STANDARD. (feet) CODE 897 DEFINITION

Rice SWCD Rain Garden Cost-Share Program

PROTECTIVE MEASURES FOR TREES DURING CONSTRUCTION

2

The following general requirements will be met for all planter box installations:

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE

Tree Pits Construction Guide

Residential Rain Gardens. Dr. Cathy Neal Extension Specialist Landscape Horticulture

Xeriscape Rebate Program Manual

SOIL EROSION AND SEDIMENT CONTROL

Bexar County Public Works Department Flood Control Program

SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL

EAGLE POINT PARK. Issues of Concern. Eagle Point Park is a cultural, historic, and ecological treasure

Specimen trees are those that are either of a larger grade than normally planted or have been specified as such by the Engineer.

UBC Technical Guidelines Section Edition Planting Preparation Page 1 of 6

ARTICLE IX SPECIAL PERMIT USES

Town of Fuquay-Varina

SECTION AMENDED TOPSOIL

ARTICLE VI: SITE PLAN REVIEW

PAVING PARKING AREAS AND ROADS DESCRIPTION. Alternate Names: Pavement Practices, Impervious Paving

Site Development Plan (SDP) Checklist

Preliminary Sediment & Stormwater Management Plan Review Checklist DATE RECEIVED: PROJECT NUMBER: PROJECT NAME:

CHAPTER 26 LANDSCAPING (Chapter added in its entirety 05-08)

ROANOKE STREET IMPROVEMENTS CHRISTIANSBURG, VIRGINIA VDOT PROJECT # U R24 UPC #:

Low Impact Development Practices

ORDINANCE NO LC

Rain Garden Site Selection and Installation

Soil Erosion and Sediment Control

Landscape Rebate: Rainwater Harvesting Rain Garden Installer Guidelines

Weston s Wetlands, Stormwater, & Open Space

Kittson Parkway / Watershed Park Parking Lot

STORM WATER MANAGEMENT PLAN APPLICATION Manheim Borough

A. INTRODUCTION AND SUMMARY OF FINDINGS B. EXISTING CONDITIONS. Table 10-1 Adjacent Storm Drains

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT

STORWATER AWARNESS TRAINING

A/E REVIEW CHECKLIST SITE & LANDSCAPE

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion

a. Site Topography and Relationship to Surrounding Topography

Public Information Centre. Welcome

EROSION & SEDIMENT CONTROL

Non-Metallic Mining Reclamation Checklist

TOWNSHIP OF LOGAN SOIL & FILL IMPORTATION AND PLACEMENT APPLICATION SUBMITTAL CHECKLIST

Soil Health Practices in the Landscape

WATER QUALITY IMPACT ASSESSMENT (WQIA) FORM

SITE PLAN REVIEW APPLICATION AND CHECKLIST

SECTION 1 CLEARING /GRADING PERMIT APPLICATION:

Case Study Bioretention Installation and Maintenance

2-B-18-UR. Revised: 3/27/2018

Erosion Control for Home Builders in the. City of Jacksonville

ROME CANALWAY TRAIL ERIE BOULEVARD WEST AND SOUTH CHARLES STREET ROME, NEW YORK DELTA PROJECT NO SEPTEMBER 2017 ISSUED FOR BID

DESIGN SCENE SUBJECT INDEX

TOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,

WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES

GENERAL INFORMATIONaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa

Certain areas of your yard or property may not represent a good location for your rain garden. Don t plant your rain garden:

Vegetation. Fe=0.90 (When fully established; lower while vegetation is first growing)

RAIN GARDENS. Task: PART 1 (60 minutes) Student Directions: Steps you will be following: Directions for beginning: Source Information:

National Wildlife University Reston, Virginia Habitat Restoration George Mason University Grounds Shop Fairfax, Virginia 22030

Route 347. New York State Department of Transportation Region 10, Long Island. THE GREENING of ROUTE 347

Landfill Closure, Intermediate Cover & Post-Closure Care. Municipal League Meeting

6.1 Bioretention Areas

Grand River Ravines Georgetown Township

Kelly Elementary School 9030 SE Cooper Street, Portland, Oregon

14 HIGHWAY PLANTING AND IRRIGATION

Example Stormwater Control Plan For a Commercial Project 123 Main Street Anytown, USA

Wisconsin Contractors Institute Continuing Education

Downtown Redevelopment Project Update

Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM

LANDSCAPING. Design. Development of the site shall not unreasonably impair the ability of adjoining properties to utilize solar energy.

DECLARATION OF COVENANT FOR IMPERVIOUS SURFACE LIMIT


STORM TACOMA 02. Potential permitting requirements STANDARD DETAILS FOR RAIN GARDEN CONSTRUCTION. How to use this document

GRAND ARBOR RESERVE GRAND ARBOR RESERVE, LLC ULIAN KISSIOV D'ONOFRIO KOTTKE & ASSOC., INC.

C-10. Disconnected Impervious Surface

Analyzing the Bioretention Construction Sequence

Decision Notice. Proposed Action

Gloucester County PLAN SUBMITTER'S CHECKLIST

STORMWATER FACILITIES OPERATION AND MAINTENANCE PLAN. Example Commercial Project. February 21, 2018

Plan Review Checklist

Stormwater Control Plan: Small (Tier 1) Land Development Project

Proposed Staging Plan For:

Town of Essex Small Site Erosion Control Guide

Grass Buffer T-1. Description. Site Selection. Designing for Maintenance

Rain Gardens. A Welcome Addition to Your Landscape

Urban Water Management (ESRM 311 & SEFS 507) Cougar Mtn Regional Wildland Park & Lakemont Blvd, Bellevue WA

Pavement Removal Fact Sheet

5.0 Storm Water Landscape Guidance Introduction

Key Topics. Bioretention Crime Scene Investigation The Bioretention Construction and Maintenance Sequence

These tools may be useful when constructing the rain garden. Power tools can make the work easier, but are not essential. n Stakes or marking flags

Transcription:

Specification and Construction Plans For: South Bethany Landscaping Improvement Plan Contract Number T201220010 1

INDEX OF SHEETS Sheet Number Description 1 Title Sheet 2 Index of Sheets 3 Overview 4 General Notes 5 Maintenance of Traffic 6 Notes for Rain Gardens in Landscape rea 1 7, 10, 13, 16, 19, 22 Rain Garden Locations from Reference Document 8, 11, 14, 17, 20, 23 Description of Existing Beds and New Rain Gardens 9, 12, 15, 18, 21, 24 Section Views Showing Excavation Required to Create Rain Gardens 25, 26, 27, 28 Planting Specifications for Rain Gardens 29, 30 Photos Showing Current State of Rain Garden reas 31 Notes for York Beach Mall Landscape rea 2 32, 34 York Beach Mall Locations from Reference Document 33, 35 Planting Specifications for York Beach Mall 36 Notes for Circle Beds in Landscape rea 3 37, 38, 39, 40 Circle Bed Locations 41 Planting Specifications for Circle Beds 2

Overview This document describes the landscaping that will be installed by the Town of South Bethany under the Delaware Department of Transportation s Transportation Enhancement Program (TEP), Contract Number T201220010, South Bethany Landscaping Improvement Plan, within the Delaware State Route 1 Right of Way. The project will encompass three landscape areas: 1. Rain Gardens at the storm drains along the east side of the pedestrian walkway on the west side of Route 1; 2. Landscape areas between the York Beach Mall parking area and the Route 1 pedestrian walkway; and 3. Circle beds that currently exist in the Route 1 median at road cross over points. This document contains marked up copies of pages from The State of Delaware Department of Transportation Specification and Construction Plans for: South Bethany Beach Pedestrian Walkway, Contract Number 96-200-03, Federal id Project Number ETE-S050(3), 1998. The marked up pages show the locations of the landscape areas within the Route 1 Right of Way. The above 1998 document is the reference document for the locations for all three landscape areas. 3

General Notes 1. ll work shall be performed in a manner that will ensure the least practicable obstruction to traffic consistent with safety. No lane closures should occur. Only shoulder closures are allowed. 2. The contractor shall maintain access to all driveways and side streets for the duration of the project. 3. The contractor shall give a minimum ten (10) calendar day notice to DelDOT of all anticipated shoulder closures for the project prior to any work. 4. There are no anticipated roadway or street closures required to complete the project. 5. ll vehicles in the work areas shall display flashing lights. 6. The only utilities expected to be in the landscape areas are storm drains. Excavation must have no impact on the storm drains or storm drain piping. Even though no other utilities have been identified in the landscape areas, the contractor is required to have all utilities in the work area located prior to commencement of any work. If any utility is identified, the contractor shall work with the Town of South Bethany to modify any excavation to protect the utility. 7. It is intended that mud tracking be eliminated on all state maintained roadways adjoining the project. ll paved surfaces adjoining the project limits shall be left in a broom clean condition at the end of each work day. 8. The contractor shall work in such a manner as to minimize the time of bare soil exposure. ll disturbed areas, rough graded areas, final graded areas and stockpile materials shall be stabilized at the end of each workday. 4

Typical Placement of Warning Signs and Traffic Cones for Maintenance of Traffic Traffic Cones, as required Work Zone Shoulder Taper Zone Warning Signs Maintenance of Traffic Plan Notes 1. t the beginning of each work day the following warning signs shall be placed on both sides of the south bound lane: Road Work head Placed 1,500 feet before the taper begins; Shoulder Work 1000 Placed 1,000 feet before the taper begins; and Shoulder Work head Placed 500 feet before the taper begins. 2. t the beginning of each work day traffic cones shall be placed at 25 spacing, center to center, to create the shoulder taper one block before the work zone begins as shown above. 3. t the beginning of each work day traffic cones shall be placed at 25 spacing, center to center, to define the work area for that day as shown above. Only the shoulder will be closed. 4. t the end of each workday all traffic cones and warning signs shall be removed. 5

Storm Drain Notes for Rain Gardens in Landscape rea 1 amended soil depth ~ 12 Figure from CIB Publication, Rain Gardens Local Solution To Stormwater Pollution, - Consistent with the DNREC Rain Garden Training, March 23, 2011 at Blackbird State Forest. 1. Excavate so that the top of the storm drain is 6 above the amended soil. 2. Excavate no closer than 2 to the Route 1 paved shoulder surface. 3. Slopes to bottom vary depending on location of Route 1 and location of the walkway (see the following pages) In no case are the slopes greater than 1:4. 4. Remove old beds and grade towards the rain gardens. 5. mend the soil to a depth of about 12 inches. The amended soil is nominally two parts sand, one part top soil (no clay) and one part compost. 6. Plant the rain gardens per the following pages. 7. Seed disturbed areas outside of the rain gardens. 8. Edge each rain garden bed. 9. Finish with a 3 inch layer of double shredded mulch. 10. Place 6 to 8 river rock around the perimeter of each drain, 12 wide. 6

Landscape rea 1 Rain Garden 8S & 8N Location From Page 6 of the Reference Document Rain Garden 8S Rain Garden 8N 7

Landscape rea 1 Rain Garden 8S & 8N Existing Beds & New Rain Gardens Rain Garden 8S Rain Garden 8N 10 15 Legend: Existing Bed 18 29 Drain New Rain Garden 8

Inlet 8N Section - 11 South Bound Route 1 6 4 6 Below top of Drain Walk Way New Slope = 1:6 New Slope = 1:8 Inlet 8S Section - Legend: pproximate Existing Contour Rain Garden Excavation 8 South Bound Route 1 6 Below top of Drain 6 1 Walk Way New Slope = 1:5 New Slope = 1:4 9

Landscape rea 1 Rain Garden 10 & 9 Location From Page 6 of the Reference Document Rain Garden 10 Rain Garden 9 10

Landscape rea 1 Rain Garden 10 & 9 Existing Bed & New Rain Garden Legend: Existing Bed Drain New Rain Garden Rain Garden 10 12 Rain Garden 9 12 18 18 11

Inlet 9 Section - 8 South Bound Route 1 6 Below top of Drain 6 3 Walk Way New Slope = 1:6 New Slope = 1:6 Inlet 10 Section - Legend: pproximate Existing Contour Rain Garden Excavation South Bound Route 1 6 Below top of Drain 9 6 3 Walk Way New Slope = 1:6 New Slope = 1:6 12

Landscape rea 1 Rain Garden 12 & 11 Location From Page 6 of the Reference Document Rain Garden 12 Rain Garden 11 13

Landscape rea 1 Rain Garden 12 & 11 Existing Bed & New Rain Garden Legend: Existing Bed Drain New Rain Garden Rain Garden 12 Rain Garden 11 12 10 18 18 14

Inlet 11 Section - South Bound Route 1 6 Below top of Drain 7 5 2 Walk Way New Slope = 1:5 New Slope = 1:4 Inlet 12 Section - South Bound Route 1 8 Legend: pproximate Existing Contour Rain Garden Excavation 6 3 6 Below top of Drain Walk Way New Slope = 1:5 New Slope = 1:6 15

Landscape rea 1 Rain Garden 14 & 13 Location From Page 6 of the Reference Document Rain Garden 14 Rain Garden 13 16

Landscape rea 1 Rain Garden 14 & 13 Existing Bed & New Rain Garden Legend: Existing Bed Rain Garden 14 Rain Garden 13 Drain New Rain Garden 10 12 18 18 17

Inlet 13 Section - 8 South Bound Route 1 6 3 6 Below top of Drain Walk Way New Slope = 1:5 New Slope = 1:6 Inlet 14 Section - South Bound Route 1 6 Below top of Drain 8 6 Legend: pproximate Existing Contour Rain Garden Excavation Walk Way New Slope = 1:5 New Slope = 1:4 1 18

Landscape rea 1 Rain Garden 16 & 15 Location From Page 5 of the Reference Document Rain Garden 16 Rain Garden 15 19

Landscape rea 1 Rain Garden 16 & 15 Existing Bed & New Rain Garden Legend: Existing Bed Drain New Rain Garden Rain Garden 16 Rain Garden 15 13 11 18 18 20

Inlet 15 Section - South Bound Route 1 6 Below top of Drain 10 6 4 Walk Way New Slope = 1:6 New Slope = 1:8 Inlet 16 Section - Legend: pproximate Existing Contour Rain Garden Excavation South Bound Route 1 6 Below top of Drain 8 6 2 Walk Way New Slope = 1:5 New Slope = 1:4 21

Landscape rea 1 Rain Garden 17 Location From Page 5 of the Reference Document Rain Garden 17 22

Landscape rea 1 Rain Garden 17 Existing Bed & New Rain Garden Legend: No Existing Bed Drain New Rain Garden Rain Garden 17 13 18 23

Inlet 17 Section - 9 South Bound Route 1 6 Below top of Drain 6 4 Walk Way New Slope = 1:6 New Slope = 1:8 Legend: pproximate Existing Contour Rain Garden Excavation 24

25

26

27

28

Photographs Showing Current State of Rain Garden reas ll Views Looking North 8N 8S 9 10 11 12 13 14 29

Photographs Showing Current State of Rain Garden reas ll Views Looking North 15 16 17 30

Notes for Landscape rea 2 between the York Beach Mall parking area and the pedestrian walkway 1. No excavation is required for landscape area 2. 2. Relocate the existing gravel as shown in the following pages. 3. Relocate existing holly tree as shown on page 35. 4. Relocate existing benches to the gravel areas. 5. Plant the two beds per the following pages. 6. Finish with a 3 inch layer of double shredded mulch place locally around plants. 31

Landscape rea 2 York Beach Mall Landscape Bed #1 Location From Page 5 of the Reference Document 32

Landscape rea 2 York Beach Mall Landscape Bed #1 Planting Specifications Indian hawthorne 33

Landscape rea 2 York Beach Mall Landscape Bed #2 Location From Page 5 of the Reference Document 34

Landscape rea 2 York Beach Mall Landscape Bed #2 Planting Specifications Indian hawthorne 35

Notes for Circle beds that currently exist in the Route 1 median at road cross over points Landscape rea 3 1. No excavation is required for any of the circle beds. 2. 1 Circle bed at south end of median stays as a raised bed as it is on top of a control box. 3. Plant the circle beds per the following page. 4. Finish with a 3 inch layer of double shredded mulch. 5. Edge each circle bed. 36

Landscape rea 3 Circle Bed Layton Dr. N and Layton Dr. S Circle Bed Layton - N Circle Bed Layton - S 37

Landscape rea 3 Circle Bed South 7 th St. N and South 7 th St. S Circle Bed South 7 th St. - N Circle Bed South 7 th St. - S 38

Landscape rea 3 Circle Bed Bayshore Dr. N and Bayshore Dr. S Circle Bed Bayshore Dr. N Circle Bed Bayshore - S 39

Landscape rea 3 Circle Bed York Dr. Circle Bed York Dr. Not a Rain Garden 40

Landscape rea 3 Planting Specifications broom sedge 41