CLAY BRICK PERVIOUS PAVEMENT CASE STUDY CITY OF NEW ALBANY

Similar documents
North Street Reconstruction & Integrated Stormwater Management System

Green Infrastructure Stormwater Management Options in an Ultra-Urban Redevelopment. Sandy Doyle-Ahern

Permeable Pavement Systems

Permeable Interlocking Pavers

Portland, Oregon, (population 551,000) endeavors to maintain

Technical Assistance Permeable Interlocking Concrete Pavement PICP

BorAL. PAvErS Build something great. commercial pavers BUILD A TRADITION IN YOUR COMMUNITY WITH BORAL PAVERS.

HEALTH SCIENCES BUILDING REDEVELOPMENT PROJECT

Permeable Pavement [STRATEGY] Page 1

P A V E R S Are they really the same? The 3-P s and how they relate to storm water management

Types and Basic Design of Post-Construction BMPs

Appendix G. Detailed Design

8 th Ave NW LID Retrofit

Installation Manual May 9/14 No revision

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS

Stormwater Control Plan: Small (Tier 1) Land Development Project

GSI Handbook Details Pervious Pavement

Green Infrastructure & Low Impact Development

Ames City Hall Campus: Stormwater Improvements

Post-Construction BMPs

Preparing a Stormwater Control Plan for a Small Land Development Project

The Benefits and Challenges Associated with Green Infrastructure Practices

Permeable Paver Streets Are Not Parking Lots Successes and Challenges With Permeable Paver Streets in the Midwest

Butchers Hill. Greening Feasibility FINAL REPORT MAY 2009 N PORT ST N WOLFE ST S MADEIRA ST. Submitted To: Submitted By:

Using Green Infrastructure To Protect Water Quality

Permeable Interlocking Concrete Pavement A Low Impact Development Tool Training for Developers

Green Infrastructure Overview

815 NE 172 nd Avenue Vancouver, WA Installation Manual

The Concept. Features. Benefits

Subsurface Infiltration Bed

Stormwater Management Techniques WMPF LAND USE TRAINING INSTITUTE MARCH 14, 2018

n1. Design 5.4.6a Urban Bioretention 5.4.6a Urban Bioretention Variations: Planter box, Extended tree pits, Stormwater curb extensions.

Appendix D - Technical Design Criteria for BMPs

Pavements Built for the Future

12/31/2014 County of Mendocino s Low Impact Design Standards Manual v1.0 A P P E N D I X 8. Site Design Measures. 32 P a g e

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

GREEN COLLECTION E C O - F R I E N D LY P E R M E A B L E P A V E R S T R E M R O N. C O M

Green Infrastructure and Low-Impact Development Technologies

Page 19 L.L.C. (Previously the United Salad Co. Garage) 939 SE Alder St.

Bioretention Designs to Meet Different Goals. Jay Dorsey & John Mathews ODNR-DSWR June 18, 2014

4.5 City of Indianapolis Stormwater Green Infrastructure Guidance: Bioretention (rain gardens) Bioretention Fact Sheet Bioretention Technical Design

ADVANTAGES OF USING PERMEABLE PAVERS ABOVE SILVA CELLS. Prepared by:

DRIVABLE GRASS GUIDELINE FOR PLANTED INFILL INSTALLATION

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion

Ken Kortkamp, PE San Francisco Public Utilities Commission San Francisco, CA

Green Infrastructure Recommendations For Parks and Public Spaces

A New Generation of Permeable Pavers

SECTION A-1: DESCRIPTION

9 Steps to a Lasting Paver Installation

Melissa Bernardo Hess, PE, CFM February 18, 2016

Appendix B DETAILED DESIGN

Stormwater & South Carolina. A Case for Low Impact Development

NEORSD Green Infrastructure Grant (GIG) Program Opening Remarks

Rain Gardens Water Quality the Way Mother Nature Intended

Design Standards. Green Development. Shadow Studies. Standards. July 2010 Updated October 2014

HUDSON VALLEY REGIONAL COUNCIL 3 Washington Center, Newburgh NY

Post-Construction Infiltration Practices Table 4b

LOW DENSITY RESIDENTIAL

Third Ave CSO Integrated Green Infrastructure

Construction of Interlocking Concrete Pavements

The following general requirements will be met for all planter box installations:

Metropolitan Area Planning Council 60 Temple Place, Boston, Massachusetts fax

ENVIRONMENTAL PAVING SOLUTIONS

Going Green with the NYS Stormwater Design Standards

Green Infrastructure Modeling in Cincinnati Ohio. Small Scale Green Infrastructure Design Using Computer Modeling

Green Infrastructure on Brownfields

SMALL PAVER PROJECT. Home Gardeners School March 19, Presented by Robert W. Bellek Owner

Time Value of Money and Optimization Process

BuildingProductsCorp.com

Please make the following changes in your copy of the bid proposal for the captioned project:

FLEET AVENUE GREEN STREET USES VACANT LOT FOR CSO REDUCTION. Thomas M. Evans, AECOM Cleveland, Ohio

Fayetteville s Incorporation of Stormwater Management into the Person Street Streetscape Project

green streets San Antonio, Texas February 17-18, 2009 Chris Kloss

University Park Subdivision Street Assessment Report

DC Clean Rivers Project - Green Infrastructure Program. ACEC What s New at DC Water?

Low Impact Development Practices

Planning, Design, and Construction of Green Infrastructure.

CHAPTER 8. Mrs. Zimman s Class - Central Elementary

Retrofit of the Gwinnett County DWR Facility Using Low Impact Development Practices SESWA 2012 Annual Conference October 19, 2012

INFILTRATION TRENCH - LEAKY PIPE

SMSHE Southeastern Michigan Society for Healthcare Engineering

PERMEABLE PAVEMENTS. Have been around for a long time, but are poised for a resurgence

COMPLETE GREEN STREET CHECKLIST

C-10. Disconnected Impervious Surface

HORSE STABLE USING AZEK PAVERS.

Green Stormwater Infrastructure Handbook. Kristin Kerr, P.E. EOA / SCVURPPP November 29, 2018

BARD COLLEGE REGIONAL GREEN INFRASTRUCTURE DEMONSTRATION PROJECT A Case Study Addressing Stormwater Management for a Small Watershed

Severn River Sub-Watershed: BMP 09-Retrofit

APPENDIX G: TOWN ORDINANCE REVIEW

Design and Construction of Bioretention Areas

World s Strongest Permeable Pavers

Blueprint Columbus GI Implementation & Design Guidelines One Water 2014 Technical Conference & Expo

Stormwater Retrofits Made Practical City of Eugene Oregon. Doug Singer, P.E., CSM Principal Civil Engineer City of Eugene Public Works

Post Construction BMP Inspection. Scott Taylor, P.E. Stormwater

Main Street Reconstruction From Ninth Line to Stouffer Street. Town of Whitchurch-Stouffville. Public Information Centre

ATTACHMENT A STORMWATER MANAGEMENT TECHNIQUES Cahill Associates Environmental Consultants

Evaluating Low Impact Development Practices for Stormwater Management on an Industrial Site in Mississippi

The Engineer/Developer s Perspective on Storm Water Management

George Bialecki, Jr. takes green building seriously. Autumn Trails Pioneers

understanding Green Infrastructure In Zoning

Transcription:

OWEA COLLECTIONS CONFERENCE 2012 CLAY BRICK PERVIOUS PAVEMENT CASE STUDY CITY OF NEW ALBANY May 10, 2012 Travis Eifert, PE, LEED AP Doug Turney, PE, CFM, LEED AP EMH&T

STORMWATER MASTER PLAN

VILLAGE CENTER STREETSCAPE CONCEPTS Development of Historic Center and Village Core Pedestrian experience and accessibility Design of streets and public places Amenities

PILOT PROJECT OPPORTUNITIES

CITY EVALUATION CRITERIA Aesthetics consistent with Historic Village Center Third Street must be reconstructed Options explored Overlay (Not Possible) Spot repair (Not Possible) Full depth reconstruction (Standard Section) Reconstruction with considerations for future developments Stormwater requirements Incentives for redevelopment

THIRD STREET: EXISTING CONDITIONS

THIRD STREET: CONCEPT PLAN

THIRD STREET: GREEN INFRASTRUCTURE OPTIONS EVALUATED Recommended Solution Pervious Pavers Most cost effective Functional Aesthetically pleasing Water quality credits per draft OEPA standards Low maintenance 8

PAVEMENT SELECTION CONCRETE OR CLAY?

PERMEABLE INTERLOCKING CONCRETE PAVEMENT Solid Concrete ( 3-1/8 ) 8,000 psi (avg) Can Be Machine Installed Can Be Used on Low Volume Streets Traffic Calming Aesthetic Value Life Cycle Cost Savings

CLAY PERVIOUS PAVERS 2-3/4 Paver 14,000 psi (avg) Better Durability Less Likely to Fade Installed by Hand Aesthetic Value Traffic Calming Can Be Used on Low Volume Streets Life Cycle Cost Savings

SELECTED PAVER: PINE HALL BRICK NORTH CAROLINA COLOR: IRON SPOT Ohio Permeable Clay Paver Manufacturers: Whitacre Greer Alliance Belden Brick - Canton

PRELIMINARY COST ESTIMATE Traditional Street Full Depth Replacement Excavation, Street, Pavement $191,364 Storm Sewer/Water Quality Unit$107,990 10 year Maintenance (mill & pave) $ 18,597 Street & Storm Total: $317,951 Project Total: $426,052 Clay Pervious Paver Full Depth Replacement Excavation, Street, Pavement $268,822 Storm Sewer/Water Quality Unit$ 42,152 Totals: $310,974 Project Total: $415,851 Winning Bid $424,389

CLAY PAVER COSTS Clay Paver Section Costs (11,916 sq.ft.) Clay Paver Installation Cost $4.90 sq.ft. Clay Paver Material Cost* $5.85 sq.ft. No. 2/No. 57 Aggregate Cost $3.54 sq.ft Total $14.29 sq. ft. *Includes extra 10% for future repairs

PAVEMENT DESIGN How thick does pavement have to be?

STRUCTURAL DESIGN: AASHTO FLEXIBLE PAVEMENT Two Geotechnical Borings CBR of 4.6 and 8.0 CBR value of 4.6 used Traffic Count of 780 ADT 2% Truck Traffic Assumed Structural Number Required 2.28

STRUCTURAL DESIGN: AASHTO FLEXIBLE PAVEMENT Compacted Base ODOT 204 Stone sub-base and pavement layer coefficient of 0.14 used Required Structural Thickness: 2.28/0.14 = 16.3 Interlocking Pavement Industry uses 0.44 for pavement course Required Structural Thickness: 2.75 x0.44 = 1.21 (2.28 1.21)/0.14 = 7.6 + 2.75 = 10.4

FROST DEPTH Recommended Thickness of Pavement System Pavement + Stone Layer = 0.65 * Frost Depth (based on UNH Stormwater Center, 2009) Pavement + Stone Layer = 0.50 * Frost Depth (based on National Ready Mix Concrete Association) Located North of Latitude Max. Frost Depth (in) Min. Recommended Thickness (0.65 x Frost Depth) (in) 38.3 Ironton 24 16 38.7 26 17 39.0 Cincinnati 28 18 39.3 30 20 39.7 32 21 40.0 Columbus 34 22 40.3 36 24 40.7 38 25 41.0 40 26 Source: Floyd (1978) 41.3 Cleveland 42 27 41.7 Ashtabula 44 29 * Tentative 12/10

WATER QUALITY VOLUME (WQV) Full Infiltration of WQv within 48 hours pre- approval from Ohio EPA not required No Infiltration of WQv (lined system or compacted subgrade) drain within 24 hours case-by-case, prior approval required by EPA and MS4 Partial Infiltration of WQv within 48 hours case-by-case, prior approval required by EPA and MS4 Redevelopment Projects

WQv WATER QUALITY DESIGN

DRAINAGE FROM ADJACENT AREAS Impervious Pervious A impervious < 2*A pervious

CONSTRUCTION & OVERSIGHT: LESSONS LEARNED 3 RD STREET NEW ALBANY Use perforated 6 PVC pipe Protect against collapse during compaction Video inspect after compaction to verify integrity

CONSTRUCTION & OVERSIGHT: LESSONS LEARNED 3 RD STREET NEW ALBANY Compaction of Aggregate Layer Use 10-15 ton vibratory roller Try to eliminate settlement of stone layer

CONSTRUCTION & OVERSIGHT: LESSONS LEARNED 3 RD STREET NEW ALBANY Compaction of Aggregate Layer ODNR Recommends Lightly Compacted Village of New Albany wanted Full Compaction

NO. 9 AGGREGATE

NO. 9 AGGREGATE SCREED

INSTALLATION

PINE HALL BRICK IRON SPOT

WHITE BRICK STOP BAR

SIDEWALK SETTLEMENT

ROAD SALT

INSTALLATION

POST SWEEPING OF NO. 9 INTO VOIDS

MID-APRIL 2011

BEFORE

AFTER (JULY 2011)

QUESTIONS? Doug Turney EMH&T (614) 775-4213 dturney@emht.com