TOP R4 Unknown Operating State

Similar documents
Standard PRC Transmission Relay Loadability

IRO Reliability Coordinator Real-time Reliability Monitoring and Analysis Capabilities

Standard Development Timeline

Innovative Real-Time Contingency Analysis Enhancements for Transmission Operations

A. Introduction 1. Title: Transmission and Generation Protection System Maintenance and Testing

A. Introduction 1. Title: Transmission and Generation Protection System Maintenance and Testing

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

A. Introduction 1. Title: Transmission and Generation Protection System Maintenance and Testing

Standard PRC-005-X Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance

Standard PRC-005-4(X) Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

Standard Development Roadmap

4. Applicability: 4.1. Functional Entities: 4.2. Facilities: 5. Effective Date: See Implementation Plan

POWER SYSTEM INCIDENT REPORT: TRIP OF DOUBLE CIRCUIT MACKAY- COLLINSVILLE TEE - PROSERPINE 132 KV LINES AND STRATHMORE SVC ON 29 DECEMBER 2010

Standard PRC Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance

Standard PRC Protection System and Automatic Reclosing Maintenance. Standard Development Roadmap

Standard PRC-005-3(i) Protection System and Automatic Reclosing Maintenance

4. Applicability: 4.1. Functional Entities: 4.2. Facilities:

4. Applicability: 4.1. Functional Entities: 4.2. Facilities: 5. Effective Date: See Implementation Plan

Standard PRC 004 5(i) Protection System Misoperation Identification and Correction

Standard PRC-005-3(X) Protection System and Automatic Reclosing Maintenance

Standard PRC Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance

National Grid / DG Installation Process Guide per NY SIR / July 2011 ver. 1.0

5. How and Why the Blackout Began in Ohio

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

NERC s Compliance Enforcement Initiative Find, Fix, Track and Report Implementation

Distributed Generation (greater than 10kW) Connecting to Vector s electricity network

June 4, 2014 VIA ELECTRONIC FILING. Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C.

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

Arc Flash Mitigation Solutions: A Proactive Approach To Arc Flash Risk

Standard PRC Protection System Misoperation Identification and Correction

PRC (I) August 9, Authored by

INSTALLATION, OPERATION AND MAINTENANCE MANUAL

Transmission Line Protection End to End Testing

Standard PRC Protection System Misoperation Identification and Correction

SPP-MISO M2M First Year Review. March 8, 2016

Can You Hear Me Now?

Can You Hear Me Now?

Standard PRC Disturbance Monitoring Equipment Installation and Data Reporting

Retrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems

NY LCC Data Specification

Relay Performance Index for a Sustainable Relay Replacement Program

Is your current safety system compliant to today's safety standard?

100 & 120 Series Pressure and Temperature Switches Safety Manual

FACILITY CONNECTION STANDARD

Compatibility between Smoke Alarms and Arc-Fault Circuit Interrupters

The North American Electric Reliability Corporation ( NERC ) hereby submits

GPS 140 NEC Requirements for Generators. Professional Development Seminar Series NEC Requirements for Generators

USER APPROVAL OF SAFETY INSTRUMENTED SYSTEM DEVICES

Community Development and Recreation Committee

Protection System Maintenance

Firm Flow Entitlement

Conditions for the provision of services Valid from 1 November only for the Jablotron Alarms series of alarms

INSTALLATION INSTRUCTIONS MASTER CONTROLLERS MC91AE MC92AE MC93AE MC94AE MC94AEH MC96AEH

User s Manual. YTA110, YTA310, YTA320, and YTA710 Temperature Transmitters. Manual Change No

Supplementary Reference and FAQ - Draft

API RP 1175 Pipeline Leak Detection Leak Detection Program, Culture, & Strategy

ADVANCED MONITORING AND DIAGNOSTIC SYSTEMS FOR INDUSTRIAL GAS TURBINES

! WARNING. McDonnell & Miller Installation & Maintenance Instructions MM-214(C) Series 61 Low Water Cut-Off OPERATION

CHAPTER 20 SERVICE EQUIPMENT

Market to Market Update. MISO-SPP JOA Stakeholder Meeting August 13, 2015 MISO Office Carmel, IN

National Grid / Supplement to Specifications for Electrical Installations / ESB ver Doc. File: ESB _ver3_

Electric Power Group Presents. Welcome!

Model 1104 Troubleshooting Guide

CAN/ULC-S561. To comply, or not to comply. actually it s not even a question! Underwriters Laboratories of Canada. By Alan Cavers & Brian McBain

New requirements for IEC best practice compliance

ASHRAE JOURNAL ON REHEAT

2017 Annual Report. King County Fire District No. 27 Fall City, WA

Supplementary Reference & FAQ. Draft

TSP-6: Solar Water Heater

United Electric Controls One Series Safety Transmitter Safety Manual

Revision: None DCN No. First Issue Date: November 30, 1998 Product: Standard DCT, 120-volts

BUILDING MANAGEMENT SYSTEMS. Introduction to Building Management Systems

INSTALLATION INSTRUCTIONS MASTER CONTROLLERS MC91AE MC92AE MC93AE MC94AE MC94AEH MC96AEH MC97AE-1

APC BC300 Series 40kW 208/450/480V User Guide

GENERATOR SELF-TEST VERIFIER (GSV300) INSTALLATION INSTRUCTIONS

Tom Miesner Principal Pipeline Knowledge & Development

G INSPECTION, TESTING, AND MAINTENANCE OF COMPANY-OWNED AUTOMATIC TEMPERATURE CONTROL EQUIPMENT

LATTNER BOILER COMPANY 9.5 HP Low-NOx Installation and Start-Up Checklist for Dry Cleaners

FreezeAlarm. General Description FA-D /FA-D-AAB. Applications. Features. Specifications. Dimensions

CONTENTS. B. System Design and Performance Requirements

Nova Scotia Fire Dispatch Minimum Standards (2017)

National Grid Requirements for Interconnection of Parallel Generation

PRC-005. Tips and Updates. February 25th, Jonathan Hayes

PGR-8800 TECHNICAL FAQ

Electrical Protection and Transportation Installations for Non-domestic Buildings

ABOUT THIS DOCUMENT AND THE DOCUMENT STRUCTURE WE USE

Property risk solutions

CONTROL PANEL INTERFACE ACTIVATE THE GENERATOR DISPLAY INTERFACE MENUS. Control Panel USING THE AUTO/OFF/MANUAL SWITCH

Guide To Troubleshooting INEFFICIENT COOLING FANS

PART 8 - Miscellaneous Services 3rd Revised Sheet 1 SECTION 8 - Other Miscellaneous Services Replacing 2nd Revised Sheet 1

Life Cycle Considerations for Microprocessor Relays

FAIR LABOR ASSOCIATION INDEPENDENT EXTERNAL MONITORING REPORT

OUT TO WALLJACK. Input

CONTENTS AUTOMATIC TRANSFER SWITCHES

Lecture 4 Power System Protection. Course map

CO Guardian LLC Document: E. AIRPORT DRIVE Date: 11/15/05 OWNERS MANUAL

User Manual. Dryer Controller M720

WOOSTER SAFETY CENTER

A guide to the changes between BS 8418:2010 and BS 8418:2015

Transcription:

TOP-004-2 R4 Unknown Operating State September 30, 2014 Greg Sorenson, PE Senior Compliance Engineer gsorenson.re@spp.org 501.688.1713

Outline Requirement Language Study Outcomes and Limitations Self-Check Questions Case Studies Internal s Audit Questions we might ask 2

TOP-004-2 R4 If a Transmission Operator enters an unknown operating state (i.e. any state for which valid operating limits have not been determined), it will be considered to be in an emergency and shall restore operations to respect proven reliable power system limits within 30 minutes. 3

NERC Definition - System Operating Limits The value (such as MW, MVar, Amperes, Frequency or Volts) that satisfies the most limiting (emphasis added) of the prescribed operating criteria for a specified system configuration to ensure operation within acceptable reliability criteria. System Operating Limits are based upon certain operating criteria. These include, but are not limited to: Facility Ratings (Applicable pre- and post-contingency equipment or facility ratings) Transient Stability Ratings (Applicable pre- and post- Contingency Stability Limits) Voltage Stability Ratings (Applicable pre- and post- Contingency Voltage Stability) System Voltage Limits (Applicable pre- and post- Contingency Voltage Limits) 4

Studies Routinely Performed Transmission Planning Studies (TPL-001, 002, 003, 004) Tariff Studies (MOD-001, MOD-030) Interconnection Studies (FAC-002) Next Day Studies (TOP-002 R11) Outage Coordination Studies (TOP-004 R6, TOP-002) Real Time Contingency Analysis (TOP-002 R11) 5

Facility Ratings Final facility ratings are the basis for all studies Inaccurate facility ratings lead to invalid system studies Ask Yourself. Are operations and planning working off the same set of ratings? Are the same ratings reported to the Planning Coordinator and the Reliability Coordinator and Transmission Service Provider? Are interconnection ratings verified with neighbors? Do flowgate limits correspond to your ratings? 6

Planning Studies N-1 in planning horizon N-2 studies, many entities run all N-2 contingencies Stability studies consider single phase and 3 phase faults, establish clearing times Form the baseline seasonal study Ask Yourself Do operators have access to the results of these studies? 7

State Estimator Uses meter inputs to calculate a best guess of what is happening Can compensate for a broken RTU Forms the basis for the Real Time Contingency Analysis tool and flowgate monitoring tools Ask Yourself What actions should be taken if an RTU fails? What actions should be taken if the State Estimator alarms? 8

Next Day Studies Typically study the outages planned to ensure that no problems are anticipated at peak hour Risks: Switching may not occur at peak hour, generators online may be significantly different, Flows may be higher at non-peak due to wind generation output Forced outage(s) between next-day and current day 9

Real Time Contingency Analysis (RTCA) Takes all N-1 contingencies periodically from the current state Should be referenced after forced outages (30 minutes) Assumes protection systems clear only one element Ask Yourself Do you have a procedure that covers what needs to be done if the RTCA fails? What if a contingency case does not converge? Is this routinely checked? Is this checked after switching/forced outages? 10

Planning vs. Operational Studies Lines in Service - All vs. 10-40 out for maintenance Generation available All vs. Actual Dispatch - Chosen vs. Market/Variable Protection Systems - Operational vs. Broken Time - Peak hour vs. Minimum or switching hour In-service Date - Estimated vs. Actual Ratings - Fixed vs. Dynamic 11

Stability Concerns Clearing times are assumed by studies (25 cycles) Certain areas may be determined to have more stringent requirements (4 cycles) If these clearing times cannot be met, the circuit needs to be switched out or the effect of the cascade studied Plants should not be operated above the output in the stability study 12

Protection System Failures Do operators know what relays are redundant? What actions need to be taken in the case of a relay alarm? (POTT vs. DCB) What if the relay cannot be fixed in the field? Ask Yourself What carriers are out of service? Have they been studied? What actions will be taken for relay alarms? 13

Example #1 - Post Event Investigation Entity had numerous facility ratings that were incorrect which led to invalid studies Entity was relying on a third-party to conduct operational studies, but did not provide accurate ratings Entity did not study the effect of numerous carrier failures Entity had protection systems that were failed long enough that a transmission planning study should have been used $350,000 penalty and $2,000,000 of compliance improvements 136 FERC 61,132, FERC Order Approving Stipulation and Consent Agreement, penalty assessed for several violations, not just TOP-004 R4 14

Example #2 - Post Event Investigation Uninterruptible Power Supply at power plant for boiler controls were out of service (one for a week, one for 5 months) This condition was not reported to system operations Plant could not ride through nearby fault No study of this condition was done Dynamic and Stability Studies assume all equipment is in proper working order $3,925,000 penalty plus additional Reliability Measures 137 FERC 61,176 15

Example #3 Post Event Investigation While troubleshooting, primary and secondary (breaker failure) relay protection was disabled Effect of disabling protection was not studied, even though the live work was approved 37 minutes later, subsequent switching was conducted, fault occurred, cleared after 1.7 seconds 22 transmission lines, 4,300 MW of generation, 3650MW load lost $25,000,000 penalty plus additional reliability enhancements 129 FERC 61,016 16

Event #4 Post Event Investigation Next day plan (based on outdated powerflow) indicated: If both transformer A1 and A2 tripped, transformer B would trip Another line would be at 109% of normal, which would activate a Special Protection System RTCA indicated for 44 minutes that loss of A1 would overload A2 above its trip point (operator did not monitor RTCA except once per shift) 2.7 million customers lost $3,000,000 penalty plus $9,000,000 in improvements 148 FERC 61,108 17

TOP-004-2 Internal Examples (1 of 3) Procedure/ Process Activity Type Facility Ratings Construction Review Facility ratings are reviewed after construction is complete to ensure as built is correct and rating correct Detective Model development Configuration Management All rating changes to systems are reviewed, approved, and double checked after implementation to ensure accuracy of all study models Preventative SOL Correction Plan Pre-planned actions Plan to reduce flow was developed ahead of time. Operator takes action when SOL exceeded. Corrective Outage Approval Protection System review Review to see effect of Zone 2 tripping near area of proposed outage. Review to see if an unusual situation is created that would cause Zone 1 to fail. Preventative 18

TOP-004-2 Internal Examples (2 of 3) Procedure/ Process Activity Type Monitoring SOLs EMS Alarm Systems are configured to alarm when SOLs are approached. Detective RTCA monitoring Alarm RTCA alarms when it identifies a new contingency, does not solve, or cannot solve a case Detective Outage Switching RTCA check RTCA checked by operator after any forced or planned outage to verify system is safe for next contingency. Preventative Outage Approval Protection System review Review to see effect of Zone 2 tripping near area of proposed outage. Review to see if an unusual situation is created that would cause Zone 1 to fail. Corrective 19

TOP-004-2 Internal Examples (3 of 3) Procedure/ Process Activity Type Failed Equipment Reporting Effective Reporting TOP reviews expectations with GOPs and field personnel to ensure that failed equipment is reported so it can be studied. Preventative Failed Equipment Repair Management Review Management should review failed equipment reports to ensure that prompt repair action is being taken Corrective Alarm responses Training Drills Operators conduct training on various RTCA alarms, relay alarms, and SE failure alarms. Preventative Real-time SOL monitoring RTCA System TOP Operator reviews RTCA results at a specified interval and takes action when needed. Preventative 20

Auditing the Overall Study Process (including TOP-004) Evidence should answer Are Facility Ratings correctly determined? Are planning models and operational models correct? Are stability and voltage limits correctly determined and still valid? Are effects of protection systems studied? Is improperly functioning equipment assessed? How are protection systems reviewed during the outage approval and work approval processes? Do the operators review RTCA results often enough? 21

QUESTIONS????? Greg Sorenson Sr. Compliance Engineer 501-688-1713 gsorenson.re@spp.org 22

Summary TOP-004-2 R4 requires operating in a known state 30 minutes to study or take action Planning and operational studies can be used to demonstrate a safe state Large events often have this as a contributing factor Internal s help ensure proper operation Audit questions you may be asked 23