Closing the Crazy Horse Landfill

Similar documents
Selecting the Right Closure Cap Option for Your Surface Impoundment or CCR Landfill

Exposed Geomembrane Cover Systems for Coal Ash Facilities

Alternative Cover Systems

New turf system stops erosion for starters. Award-winning slope survives typhoon New wall repairs erosion, widens road

Super Gripnet INTEGRATED DRAINAGE SYSTEM (IDS) GEOMEMBRANE

Drop-In Specifications INTEGRATED DRAINAGE SYSTEM GEOMEMBRANE

LiteEarth Advanced Synthetic Grass Geomembrane Liner INDEPENDENT THIRD PARTY PERFORMANCE TESTING REPORT. U.S. Patent No.

A Collection and Removal System for Water in the Final Cover Drainage Layer

ENVIRONMENTAL ENGINEERING LAND SURVEYING

Geosynthetics for the Management, Containment and Closure of Coal Combustion Residual Disposal Facilities

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

We Don t Have No Stinkin Dirt! Coal Ash Pond Closures (Traditional and an Alternative Method)

FINAL COVER VENEER STABILITY ANALYSES FOR SCA DESIGN

Acronyms. TRI TRI Environmental, Inc. Table of Contents. iii

Geomembranes and Geosynthetic Clay Liners (GCLs)

Structural Storm Water Best Management Practices (BMPs)

The use of geosynthetics in the installation of ballast layers

SWANA/A&WMA s. Third Annual Landfill Operator s Training Geosynthetics in Landfills. February 13, 2013

EROSION & SEDIMENT CONTROL

Cost Estimating for Landfill Design

Charudatta R. Prayag Deputy Director Ahmedabad Textile Industry s Research Association Ahmedabad

Exposed geomembrane covers: Part 1 - geomembrane stresses

Consulting Engineers and Scientists. Closure Plan. Submitted by: GEI Consultants, Inc Voyager Drive Green Bay, Wisconsin

NOTICE OF INTENT. Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo Bluff, VA 23022

HEAP LEACH PAD DESIGN AND CONSTRUCTION PRACTICES IN THE 21 ST CENTURY

BRISBANE BAYLANDS INFRASTRUCTURE PLAN FEBRUARY 2011 APPENDIX O DRAFT

Lessons Learned From the Failure of a GCL/Geomembrane Barrier on a Side Slope Landfill Cover

Section Specification for Geotextile Used in Permanent Erosion Control Application

Geosynthetics. Work platforms built with geotextile tubes at the Lach Huyen Bridge. GMA TECHLINE Exposed GM? Deformations?

2018 Annual Landfill Inspection Report

APPLICATIONS IN FILTRATION AND DRAINAGE & EROSION CONTROL

Liner Construction & Testing Guidance Overview

Chesapeake Energy Center. Submitted To: Chesapeake Energy Center 2701 Vepco Street Chesapeake, VA 23323

to hard armor

D.P.E. Enviroliner. geotextile protection layer. covering new ground 2016

Permeable Interlocking Pavers

!!!!!!!!!!!!!!!! INSTALLATION!GUIDELINES!MANUAL! January!2018,!Revision!3.0! Advanced!Revetment!Technology!

Technical Specification Guidelines

REHABILITATION OF SAIDA DUMPSITE

Selecting Appropriate Stormwater Control Measures for Your Development Project

A Revolutionary Green Alternative to Hard Armor

G E O T E X T I L E s o l u t i o n s

Slope Stability in Harris County

GEOWEB slope & shoreline protection OVERVIEW

RESOLUTIO REGARDI G A THREE YEAR MOWI G SERVICES AGREEME T FOR THE HARTFORD LA DFILL

SPECIAL SPECIFICATION 3687 Impermeable Liner

Capping waste rock at a Superfund site An innovative design tackles pollution at a mining operation s waste repository.

DESIGNING AND SPECIFYING LANDFILL COVERS

GEOMEMBRANE FIELD INSTALLATION

2016 Annual Inspection Report

Horsehead Holding Corporation Relies on XR-5

SECTION 02230BP AGGREGATE BASE

Severn River Sub-Watershed: BMP 09-Retrofit

CAPPING OF A GOLD MINE IN ROSIA MONTANA, ROMANIA

CHAPTER 8 SLOPE STABILITY ANALYSIS

Introduction To Geosynthetics In Transportation

Table 4.7.1: Swales Potential Application and Storm Water Regulation

INTRODUCTION TO GREEN INFRASTRUCTURE HOW WE CAN PROTECT OUR COMMUNITIES AND OUR WATERS Maywood Public Library Bergen County, New Jersey

ACTIVITY: Geotextiles ES 12

Permeable Pavement Systems

City of Larkspur. Notice of Mitigated Negative Declaration for the 285

Advance Engineering & Surveying PLLC

Erosion Control for Home Builders in the. City of Jacksonville

Patrick E. Lindemann INGHAM COUNTY DRAIN COMMISSIONER. Towar Rain Garden Drains A Low-Impact Urban Retrofit

CalTrans tackles The Merge

1993 Specifications CSJ SPECIAL SPECIFICATION ITEM Impermeable Liner

Moisture Content Effect on Sliding Shear Test Parameters in Woven Geotextile Reinforced Pilani Soil

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

CI/SfB (16)(17) Common Arrangement D11 Uniclass L1411/ L132/ L6634. Woven Polypropylene Geotextiles.

EARTH STABILIZATION GEOSYNTHETIC SOLUTIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Your Landfill Cap is an Asset, Profit from It!

PRELIMINARY DRAINAGE REPORT LATHAM 200 MMSCFD GAS PROCESSING PLANT

AASHTO M Subsurface Drainage

3. Are there any projects exempt from the definition of Regulated Projects?

Green Roofs. Environment friendly e-library

LANDFILL FINAL COVER AND MANAGEMENT OF LEACHATE SEEPS BELOW FINAL COVER

Civil engineering Fibertex Geotextiles

GEOSYNTHETIC-STABILIZED VEGETATED EARTH SURFACES FOR ENVIRONMENTAL SUSTAINABILITY IN CIVIL ENGINEERING JIE HAN PH.D.

Workshop On Capping Design In South Africa. Product Showcase By. Tyrone Naidoo

A PVC geomembrane integrated in the landscape

Sustainable geomembrane recycling and downcycling

Evaluating Tubular Drainage Geocomposites for use in Lined Landfill Leachate Collection Systems

Technical Supplement 14D. Geosynthetics in Stream Restoration. (210 VI NEH, August 2007)

V. EROSION CONTROL. -Drainage swales separation -Under rip-rap protected -Under rip-rap unprotected

Elements of Design of Multi-linear Drainage Geocomposites for Landfills

AASHTO NTPEP Rolled Erosion Control Product (RECP) Test Report

Nonwoven geotextile. Edilfloor Professionalism and knowledge at 360

Holmberg & Howe, Land Surveyors and Civil Engineers Zoning District: R-35

COIR GEOTEXTILES. Er. Sheela Mary Cherian, M.Tech, Assistant Executive Engineer. Woven coir netting / Mesh matting used as geotextiles

PERFORMANCE OF GEOSYNTHETICS IN THE FILTRATION OF HIGH WATER CONTENT WASTE MATERIAL

Stormwater Retrofitting: The Art of Opportunity. Presented by the Center for Watershed Protection

SECTION 2.5. Construction Quality Assurance Plan

Performance of Geosynthetics in the Filtration of High Water Content Waste Material

TITAN TIMES 2015 HIGHLIGHTS. More Inside! Completion of an Impressive Geodesic Dome Project

FOR PROJECTS INITIATED AFTER FEBRUARY 1, 2010 REVISION 1 ITEM 709 TRIANGULAR FILTER FABRIC FENCE

Introduction. Functions of Non woven Geotextile (TechGeo) Separation. Filtration. Drainage. Containment. Tech Geo. . Geotextile Overview

B511 - RIP-RAP, ROCK PROTECTION AND GRANULAR SHEETING - OPSS 511

Experiences with Placement of Alternative Final Covers Presented by

STREAM BANK STABILIZATION THORPS MORTIMER RECREATION AREA Grandfather Ranger District SITE LOCATION & DRAINAGE AREA

Transcription:

Closing the Crazy Horse Landfill First large-scale landfill closure in California to use artificial turf closure system By Christopher M. Richgels PROJECT HIGHLIGHTS CRAZY HORSE LANDFILL CLOSURE SALINAS, CALIF. OWNER Salinas Valley Solid Waste Authority PROJECT SIZE 66 acres DESIGN ENGINEER Golder Associates GEOSYNTHETIC MATERIALS ClosureTurf, DuraTurf, HydroTurf Watershed Geosynthetics LLC 50-mil LL Super Gripnet geomembrane Agru America Inc. Christopher M. Richgels, P.E., is the western regional engineer for Agru America Inc. He has been a California registered civil engineer since 1991. Photos and figures courtesy of Agru America 1.0 Introduction The Crazy Horse Landfill (CHLF) is located on a 160-acre parcel west of, and adjacent to, Crazy Horse Canyon Road about nine miles north of the city of Salinas in northern Monterey County, Calif. The landfill, owned and maintained by the Salinas Valley Solid Waste Authority (SVSWA), had been in service for 75 years, with final in-place waste volume estimated at 4.3 million cubic yards. Final cover design for the closure of the CHLF went through three iterations before the SVSWA settled on an artificial turf final cover system. The project marks the first large-scale implementation of this type of cover system in California. 2.0 Project background 2.1 Site history The CHLF began operation in 1934 as a burn dump in an area referred to as Module 1 and continued in that operation method until 1966. In 1966, Module 1 disposal operations were converted to a sanitary landfill operation, which continued until about 1972. The landfill was closed in 1988 when an 80-mil, high-density polyethylene (HDPE) geomembrane final cover and overlying vegetative soil layer was put in place. This membrane and soil layer served as a corrective action measure. The U.S. Environmental Protection Agency (EPA) placed Module 1 of the landfill on the National Priorities List (NPL), and the landfill became a Superfund site in 1990. The primary landfill continued to receive non-hazardous residential, commercial, and industrial solid waste until December 2009, when the SVSWA ceased all fill operations. The primary landfill is a canyon fill of approximately 66 acres. Three phases (15 acres total) of the main landfill on the western side were lined in accordance with Subtitle D solid ( household ) waste regulations after Oct. 9, 1993. The lined modules were constructed with a composite liner system. The landfill base consisted of six unlined acres beneath Module 1, 51 unlined acres beneath the primary landfill, and 15 acres of lined module. 2.2 Site conditions pertaining to design and construction The SVSWA s final cover system would have to meet five criteria: 1. The system had to withstand the environmental conditions present, including wind erosion and uplift, rainfall erosion, concentrated flow erosion, ultraviolet light degradation, and traffic. 38 Geosynthetics February March 2014

2. The system had to provide a static factor of safety (FS) of at least 1.5 and resist seismic deformation due to the San Andreas Fault zone located about five miles northeast of the site. 3. The final cover system had to provide excellent groundwater protection to halt continued impact to the local groundwater supply. 4. Due to an old cross-traffic style highway interchange, risk to motorists had to be avoided during construction. 5. The new system could not create additional nuisance conditions for nearby residents, many of whom had been concerned about the landfill site operations and impacts for years. In addition, surface water that could be affected by the landfill would provide groundwater recharge, contact (i.e., swimming) recreation, and wildlife habitat. Access to the site is approximately 1.5 miles from U.S. Highway 101. The interchange consisted of a left-turn lane from the southbound lanes of 101 (crossing northbound traffic) at a blind corner to oncoming northbound traffic. This stretch of U.S. 101 and the interchange had been the site of many catastrophic, sometimes fatal, accidents. Adjacent land uses near the site include cattle grazing and residences located 560ft from the landfill on the northwest and approximately 360ft on the southwest. Homeowners often registered complaints with the SVSWA regarding dust generation, windblown litter, odors, and general site appearance. 3.0 Final cover systems considered and rejected 3.1 Evapotranspirative (ET) cover system The ET cover system is an aesthetically pleasing approach to capping landfills. However, ET covers may require substantial amounts of soil and unless a soil supply is on-site imported soil can become cosly. The CHLF had no available on-site soil supply. In addition, hydrological investigations at the site revealed it was too wet for an ET cover. The initial site design FIGURE 1 Completed Crazy Horse Landfill closure (Salinas Valley, Calif., summer 2013). www.geosyntheticsmagazine.com 39

Closing the Crazy Horse Landfill FIGURE 2 Cross section of the artificial turf with infill sand ballast and underlying layers installed for closure of the Crazy Horse Landfill in northern Monterey County, Calif. FIGURE 3 HDPE grass retained tensile strength vs. exposure time had used rainfall data from the nearby Salinas Municipal Airport. The CHLF, situated on the windward face of the north Gabilan Range, receives significantly more rainfall than Salinas because the landfill location is the first elevation change encountered by Pacific storms as they make landfall from Monterey Bay. The ET cover needed to be thicker than initially envisioned to provide storage capacity for the anticipated percolation. Based on the site s climatological conditions and soil import cost, an ET cover design for the CHLF project was ultimately rejected. 3.2 Subtitle D final cover system The preliminary closure plan was also evaluated using a textured geomembrane as the barrier layer in the final cover design. However, with the CHLF located approximately five miles from the San Andreas Fault, the final cover design had to provide veneer stability. The CHLF would be subject to a Peak Ground Acceleration (PGA) between 0.5 and 0.6 gravity according to the California Geological Survey. Initial seismic stability analysis of the final cover veneer indicated a residual interface friction angle on the order of 31 degrees was required to prevent seismic induced deformations greater than 1ft. Linear low-density polyethylene (LLDPE) textured geomembrane cannot provide such high residual interface shear strength. Two existing sideslopes, 2H:1V and 2.3H:1V, added to the challenge. The average residual interface friction angle for textured LLDPE geomembranes is approximately 18 degrees, with the geotextile component of a geocomposite drainage layer. The slope coefficient for a 2H:1V slope is 0.5, which creates a static factor of safety (FS) less than 1.0: FS=tan(18 )/0.5=0.65. The required minimum static FS is 1.5. This situation rendered the project unbuildable using typical textured geomembranes. 40 Geosynthetics February March 2014

FIGURE 4 Hartford Landfill, Connecticut Resources Recovery Authority. 3.3 Structured geomembrane system A structured geomembrane that provides a high shear strength was then examined by the SVSWA. This geomembrane considered for the CHLF project consisted of a 50-mil LLDPE sheet with 130-mil studs on the drainage side of the sheet and 170- mil spikes on the underside of the sheet. An interface shear strength testing program was initiated with the geomembrane and the soils specific to the CHLF. The shear interface of the geomembrane vs. the various soil types proposed for use all delivered acceptable static FS. The CHLF final closure plan was approved, incorporating this structured geomembrane. However, getting vegetative cover soil to the site proved financially prohibitive. The estimated minimum total miles for soil import was 660,000. Adding that level of heavy truck traffic to U.S. 101 and the local roads was not desirable due to the difficult highway access. The average cost to haul in soil was $13/cy for a total cost of approximately $2.6 million. The design, while buildable, was too expensive. 4.0 Final closure design and system approved 4.1 Artificial turf closure system In 2010, the SVSWA examined an alternative final cover system consisting of five layers (see Figure 2) from bottom to top: 1. A minimum 1ft-thick (2ft-thick in traveled areas) soil foundation layer beneath a structured geomembrane. 2. A structured geomembrane lowpermeability layer. 3. A woven polypropylene geotextile layer over the geomembrane. www.geosyntheticsmagazine.com 41

Closing the Crazy Horse Landfill FIGURE 5 Solar panels at Hartford Landfill, Connecticut Resources Recovery Authority. FIGURE 6 Closed Crazy Horse Landfill in background. 4. A geosynthetic erosion protection layer of engineered synthetic turf with tufted grass blades. 5. A sand ballast layer placed in the artificial grass blades to provide anchoring against wind and water erosion. Initially, the design engineer and the primary regulating agency were skeptical of the product s ability to serve as an adequate alternative to the Subtitle D prescriptive standard final cover. The SVSWA decided to revise the project description after reviewing initial data and material costs regarding the artificial turf system. The estimated materials cost of $1.75/ sf could be paid with available closure funds. With regard to engineer and agency skepticism, a testing program was already started to prove the system s ability to withstand extreme environmental conditions: wind erosion and uplift, rainfall erosion, concentrated flow erosion, ultraviolet radiation degradation, and traffic. 4.2 Wind erosion and uplift An exposed geomembrane can be susceptible to wind damage from uplift forces, particularly at leeward slope hinges. Exposed geomembranes can also require ballasting with sandbags to resist these uplift forces. Wind tunnel testing revealed unexpected results for the material with regard to wind uplift. At a wind speed of approximately 60ft/sec (40 mph), the uplift force peaked and then began a decline at 80ft/sec (55mph). The uplift force reduced to zero at an approximate wind speed of 100ft/sec (70mph) and became a downward force at higher wind speeds tested (up to 120mph or Category 3 hurricane wind speeds). The design wind speed for the California Pacific Coast was 85mph in 2010. For the CHLF final cover system, the minimum 8psf of sand ballast specified for the perimeter and sideslope access roads (along the critical slope hinge) was more than sufficient to resist wind uplift. 42 Geosynthetics February March 2014

4.3 Rainfall erosion Subtitle D landfill covers are allowed erosive soil loss up to 2 tons/acre, a restriction that also applies to the artificial turf sand ballast. The greatest danger for sand erosion would occur along the toe of the landfill sideslopes. Slope erosion testing using ASTM test method D6459 confirmed that no sand loss occurred at 2.63in. and 4.65in. of rainfall per hour. At 6.6in./hr (above design rainfall intensity), 184.45 grams of the finer grained component in the sand were collected at the 8ft 40ft test plot outlet. This was equivalent to an erosive soil loss of 0.03 tons/acre. 4.4 Concentrated flow erosion Based on concentrated flow erosion testing (ASTM test method D6460), the decision was made to replace typical final closure drainage infrastructure concrete lined ditches and channels, overside corrugated metal pipe drains, and riprap energy dispersion aprons with a system that uses a sand-cement ballast infill, rather than just sand, to increase hydraulic shear resistance up to a measured 15psf (equivalent to a 12-in. D50 riprap). During the first winter after installation, an intense series of storms occurred. Inspections during and after the storms revealed no observable damage to the surfaces. 4.5 Ultraviolet radiation degradation The SVSWA wanted to know how long the exposed artificial grass tips would last under UV radiation exposure. >> For more, search landfill at www.geosyntheticsmagazine.com www.geosyntheticsmagazine.com 43

FIGURE 7 Confluence of drainage channels at the Crazy Horse Landfill outlet. Tensile tests were conducted on artificial grass samples from a field test location near Phoenix, Ariz., at five- and seven-year exposure conditions. The retained strength in the HDPE grass was measured at 89.7% and 83.8%, respectively, from an original tensile strength of 20.2lbs/in. Projecting out to 30 years of field exposure from these two data points, the turf-retained tensile strength was estimated at approximately 60%. This longevity property was reassessed in 2012. As shown in Figure 3 (p. 38), the 30-year exposure tensile strength projection increased to 70% based on four data points shown. Projecting out another log cycle from the 10-year data set, the service life estimate of the system could be more than 100 years using a 15% retained strength parameter (grass blade strength required to retain the sand ballast). 4.6 Traffic Because periodic final cover inspection and maintenance is required post-closure, the cover system had to withstand traffic from pickups and other heavier vehicles. A traffic analysis was conducted that considered burst resistance, tensile strength, puncture resistance, and vehicle slide while braking. After extensive testing, the final cover system proved acceptable in all aspects. 4.7 Integration of solar power array station The final cover system is supportive of a solar power array installation with zero impact to the system s synthetic materials. One of the highest solar panel conversion efficiency loss factors is dirt and dust accumulation on the panel surface. The lack of soil beneath the solar arrays means a significant reduction in the amount of maintenance needed to keep the arrays clean. And since completion of the Crazy Horse project, that vision has become a reality on a recent installation at the Hartford Landfill owned by the Connecticut Resources Recovery Authority. Figure 4 (an aerial shot of the Hartford Landfill, p. 37) and 5 (p. 38) show solar panels deployed in a five-acre area. 5.0 Conclusions 5.1 Project costs The initial project budget was $10.4 million for materials, installation, construction management, and quality assurance costs. 44 Geosynthetics February March 2014

Closing the Crazy Horse Landfill The completed project, from finish grading to geomembrane installation, including construction management and quality assurance cost, was approximately $10.5 million. The annual postclosure maintenance cost is estimated at $46,600 per year. The CHLF closure design eliminated the soil component, all vegetation maintenance costs, and reduced drainage maintenance costs by approximately 70%. The total savings over a nominal 30-year postclosure cost for the reduced final cover maintenance is projected at $1.4 million. To date, the site owner has had to perform no significant final cover maintenance activities. 5.2 Reduced carbon footprint The final cover system eliminated about 11,000 truck trips to import soil to the site. The project s carbon footprint was reduced by 70% due to the combined project size reductions of soil import elimination and reduced heavy equipment needs. FIGURE 8 Finished topdeck at Crazy Horse Landfill. 5.3 Benefits to local community Typical landfill closures require specialized equipment and labor due to their complicated combinations of earthworks and specialty geosynthetic materials. With a CHLF artificial turf system that is relatively easy to construct, the SVSWA could hire local labor to perform the work since Monterey County was experiencing high unemployment rates at the time. The closed landfill, with its artificial green grass top layer mottled with gray sand infill, is barely discernible from the natural hillside behind it. Aesthetic and odor complaints from neighbors abutting the landfill have diminished, with many of the residents contacting the SVSWA to compliment the appearance of the site. Intrusive and noisy postclosure care efforts, including slope reconstruction, revegetation, fertilization, and mowing, are now reduced to essentially zero. G www.geosyntheticsmagazine.com 45