Prince William Street Project (Grant Avenue to Wellington Road) 1
Goals Improve pedestrian and bike traffic safety Improve street drainage with curb & gutter Upsize water mains Enhance overall street appearance Enhance sanitary sewer reliability Improve electric and utility reliability Install new street lighting 2
A Little History Introduced into City s Capital Improvement Plan 2000 Estimated Total Cost of $9.2 million Included in the Old Town Sector Plan (Adopted June 2008) 3
A Little History Prince William Street Citizens Committee Created by Council in September 2012 Comprised of local business owners and residents Mrs. Myra Brent Mr. Julian Rozzell Mr. Tony Sfreddo Mr. Paul Odems Mr. Paul May Mr. Tony Willingham Mr. Lawrence Buck Buchanan 4
A Little History Prince William Street Citizens Committee Reviewed design considerations including: Right-of-way, road width, and sidewalks Walking/bike trail connection to Old Town from Dean Park Existing family cemetery Storm sewer, street lighting and utility improvements 5
A Little History Prince William Street Citizens Committee Recommendations to City Council in September 2014: Right-of-way of 48 feet or less Jefferson Street to Wellington Road and adjust to avoid cemetery All utilities located in right-of-way to extent possible Storm sewer to address issues at the American Legion; Gregory Building; intersection of Old Wellington Road and School Street; and include storm behind 9519 School Street 6
A Little History Prince William Street Citizens Committee Recommendations: Evenly distributed street lights Bike lanes on both sides in right-of-way; 5ft wide maximum width No on street parking north side from Grant Avenue to Jefferson Street; possible exception at Gregory Building No parking on either side from Jefferson Street to Wellington Road 7
What s Been Happening Electric, Comcast and Verizon utilities have been relocated underground Columbia Gas continuing work to upgrade main and connect service lines Demolition at 9524 Prince William Street Finalization of engineering plans 8
Proposed Design Grant Avenue to Jefferson Street 9
Proposed Design Jefferson Street to Wellington Road 10
Proposed Design Additional design details: No parking on north side except Gregory Building Four parking spaces on south side at The Courts at Historic Manassas Cemetery will remain undisturbed New cobra head street lights on aluminum poles New pedestrian signals at Wellington Road School Street drainage project not included 11
Proposed Design Cobra Head Street Lights on Aluminum Poles 12
Proposed Design Bike lanes and sidewalk 13
Proposed Design Additional design details: Driveway slopes 9410 Prince William Street 9512 Prince William Street 9414 Prince William Street 9513 Prince William Street 9418 Prince William Street 9514 Prince William Street 9500 Prince William Street 9518 Prince William Street 9502 Prince William Street 9519 Prince William Street 9503 Prince William Street 9520 Prince William Street 9504 Prince William Street 9521 Prince William Street 9505 Prince William Street 9525 Prince William Street 9510 Prince William Street 9526 Prince William Street 9511 Prince William Street (2) 9528 Prince William Street 14
Expected Construction Phasing 4 3 2 1A 1A 1B 1A 4 15
Construction Phase 1A West of Grant to Courts of Manassas 24 Water line construction from west of Grant to Courts of Manassas 16
Construction Phase 1A Westfield Road 8 Water line construction on Westfield Road and Runaldue Street. 17
Construction Phase 1A Douglas Street 8 Water line construction on Douglas Street and Runaldue Street. 18
Construction Phase 1B Courts of Manassas to 9270 Prince William Street 24 Water line construction Curb, gutter and sidewalk work in front of 9216 Prince William Street and also in front of 9270 Prince William Street (Old Town Auto Building) 19
Construction Phase 2 9270 Prince William Street to 9402A Prince William Street 24 Water line construction Sanitary Sewer replacement work Roadway improvement work 20
Construction Phase 3 9402 Prince William Street to Jefferson Street 24 Water line construction Roadway improvement work Storm and Sanitary Sewer work 21
Construction Phase 4 Jefferson Street to Wellington Road 12 Water line construction Roadway improvement work Storm and sanitary sewer work 22
Construction Phase 4 Prince William to Winters Branch via Lincoln Avenue and School Street. Storm outfall work from 9517 Prince William Street (American Legion Post 114) to existing box culvert located in Winters Branch Sanitary sewer work at Lincoln Avenue 23
Construction Phase 5 Wellington Road to Grant Avenue Final pavement layers Pavement markings Removal of detour 24
Construction Detour 25
What to Expect Construction hours are 8:00 AM - 5:00 PM M-F 12-18 month project duration Through traffic will be limited during construction hours Street closures will occur periodically Continual access to your property Trash service will continue Announced brief water and sanitary sewer service disruptions will occur During construction, on-street parking will be limited 26
Schedule Underground Electric, Comcast and Verizon - 100% complete Gas Line Upgrade 95% complete Bid Plans and Specifications - 95% complete Invitation to Bid Receive Bids Award Project Begin Construction Project Complete June 2017 August 2017 September 2017 October 2017 Late 2018- Early 2019 27
Questions? Project Website: www.manassascity.org/pwstreet Design Project Manager: Vijay Dindigal Office Phone: 703-257-8475 Email: vdingigal@ci.manassas.va.us Construction Project Manager: Corinna Sigsbury Office Phone: 703-257-8397 Email: csigsbury@ci.manassas.va.us 28